Town Council Quarterly Workshop — Agenda Packet
Town of Bluffton · Beaufort County · Town Council · meeting of Oct 27, 2026 · Agenda packets
Open the original document More from Town of Bluffton
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Town Council Quarterly Workshop
Tuesday, October 27, 2026 at 5:00 PM
Theodore D. Washington Municipal Building, Henry “Emmett” McCracken Jr. Council Chambers,
20 Bridge Street, Bluffton, SC
AGENDA
This meeting can be viewed live on BCTV, on Sparklight Channel 9 and 417 or on Spectrum Channel
1304.
I. CALL TO ORDER
II. PUBLIC COMMENTS - Pertaining only to agenda items
III. WORKSHOP AGENDA ITEMS
1. Discussion of Short-term Resilience Recommendations - Beth Lewis, Watershed Resilience
Manager and Andrea Moreno, Watershed Division Manager
2. Parks and Rec Survey and Event and Venue Survey - Chris Forster, Assistant Town Manager
3. Preliminary Site Analysis of Town Owned Land – Chris Forster, Assistant Town Manager
IV. ADJOURNMENT
“FOIA Compliance – Public notification of this meeting has been published and posted in compliance
with the Freedom of Information Act and the Town of Bluffton policies.”
In accordance with the requirements of Title II of the Americans with Disabilities Act of 1990 ("ADA"), the
Town of Bluffton will not discriminate against qualified individuals with disabilities on the basis of
disability in its services, programs, or activities. The Town of Bluffton Council Chambers are ADA
compatible. Auditory accommodations are available. Any person requiring further accommodation
should contact the Town of Bluffton ADA Coordinator at 843.706.4500 or
adacoordinator@townofbluffton.com as soon as possible but no later than 48 hours before the
scheduled event.
Executive Session – The public body may vote to go into executive session for any item identified for
action on the agenda.
*Please note that each member of the public may speak at one public comment session and a form must
be filled out and given to the Town Clerk. To submit a public comment online, please click here:
https://www.townofbluffton.sc.gov/FormCenter/Town-15/Public-Comment-60
Public comment is limited to 3 minutes per speaker.
Page 1
Town of Bluffton, SC Town Council Quarterly Workshop Agenda October 27, 2026
Page 2
TOWN COUNCIL
STAFF REPORT
Projects and Watershed Resilience Department
MEETING DATE: October 27, 2026
PROJECT: Discussion of a Short-term Resilience Recommendations
PROJECT MANAGER: Beth Lewis, Watershed Resilience Manager
Andrea Moreno, Watershed Division Manager
REQUEST: Staff requests Town Council’s guidance on several proposed resilience opportunities.
These recommendations resulted from work related to:
1. Developing a Resilience Ordinance for the Town’s consideration; and
2. A completed SC Sea Grant Consortium Resilience Planning Analysis (“Resilience Analysis”).
BACKGROUND: In January of 2025, Town Council approved a Master Service Agreement (MSA) task
authorization with McCormick Taylor, Inc. and Center for Watershed Protection (“Consultants”). The
Consultants were tasked with developing a Town Wetland Ordinance and a Resilience Ordinance to
protect health, safety, and welfare of our citizens and natural resources.
Table 1. McCormick Taylor & Center for Watershed Protection Tasks.
CONSULTANTS’ TASKS – WETLAND PROTECTION AND RESILIENCE ORDINANCES STATUS
1 Review current Town policies. Completed
2 Identify and inventory wetlands within the Town’s jurisdiction. Completed
3 Develop a map of wetlands to be protected. Completed
4 Develop a Wetland Ordinance for the Town. Completed – 2nd
Reading 8/2026
5 Apply comprehensive drainage study results to identify and map resiliency
zones.
Completed
6 Identify primary stormwater drainage channel systems. Completed
7 Develop a Resilience Ordinance for the Town. In progress –
following
Council’s
direction
Page 3
Section 3. Item # 1.
October 27, 2026 Page 2
Resilience Recommendations for Discussion Town Council – Workshop
In 2024, the Town engaged SC Sea Grant Consortium to conduct a Resilience Planning Analysis
(“Resilience Analysis”) independent of the Consultants’ work. SC Sea Grant’s Resilience Analysis Final
Report (completed June 2025) included the key findings below.
Table 2. SC Sea Grant Consortium Resilience Analysis Recommendations.
SC SEA GRANT CONSORTIUM RESILIENCE ANALYSIS OF THREATS & POSSIBLE OPPORTUNITIES TO
CONSIDER
1 Flood Vulnerability is Increasing: Areas currently experiencing minor flooding are projected to
face more severe events in the future. Parcels presently outside of flood-prone zones may also
become vulnerable.
2 Future Development: New construction and land use changes increase the risk of flooding.
3 Protecting Wetlands: Preserving wetlands and requiring buffers significantly reduces flood risk.
4 Land Elevation-Based Zoning: Areas at lower elevations face higher flood risks, while those at
higher elevations are less susceptible.
5 Significance of Community Engagement: Community input was instrumental in shaping the
Resilience Analysis and emphasized the necessity for stronger flood mitigation policies.
RESILIENCE RECOMMENDATIONS FOR DISCUSSION : The following is a list of resilience
recommendations that resulted from the Consultants’ scope of work and the Resilience Analysis.
Detailed recommendations from the Consultants and the Resilience Analysis can be found in
Attachment #1 and Attachment #2, respectively. Staff is requesting Council’s guidance to prioritize
which, if any, r esilience r ecommendations Staff should explore further. Future W orkshops with
Council will occur as needed as these recommendations are further developed in a phased approach.
Phase 1 (proposed completion FY27):
1. Strengthen Wetlands Protection (Completed):
o Implement comprehensive wetland protections to steer new development away from
ecologically sensitive wetlands and ensure long-term preservation.
2. Expand Land Acquisition and Partnerships:
o Collaborate with land trusts and conservation organizations to acquire and protect
critical wetlands and floodplain areas. Conservation priority areas have been
identified.
o Update the Town’s Land Acquisition Manual to expand the acquisition criteria to
include identified conservation priority areas.
Page 4
Section 3. Item # 1.
October 27, 2026 Page 3
Resilience Recommendations for Discussion Town Council – Workshop
3. Update Flood Management Policies and Strategies:
o Strengthen the Town’s Flood Damage Prevention Ordinance to include compensatory
storage requirements and expand on requirements that help prevent downstream
flooding.
o Join the Community Rating System (CRS) to allow residents to receive discounted flood
insurance premiums.
o Expand the Federal Emergency Management Agency (FEMA) Flood Hazard Area to
include the 500-year floodplain to help protect life and property in areas facing
increased flood risk due to future projections.
4. Implement Cove Buffer Ordinance:
o Adopt a buffer ordinance applicable to the coves of the May River to protect water
quality, stabilize cove banks, and enhance flood control.
o Apply different buffer widths based physical characteristics of coves.
Phase 2 (anticipated, FY28):
1. Implement Resilience Zone Overlay District:
o Restrict development in flood -prone, low -lying areas by integrating land elevation
criteria into local zoning regulations.
o Apply the Town’s Flood Damage Prevention Ordinance and an enhanced resilience -
focused stormwater plan review to development in this overlay district.
2. Offer Financial Incentives for Resilient Development:
o Enhance programs like Transfer of Development Rights (TDR) and considering
additional financial incentives to encourage resilient construction and land use.
CONSIDERATIONS & NEXT STEPS : Below is a list of recommended items for Town Council ’s
consideration, should you choose to proceed.
1. Update the Town’s Land Acquisition Manual
2. Update Floodplain Management Regulations
3. Implement Cove Buffer Ordinance
If Council agrees, staff will move forward with these resilience recommendations per the tentative
timelines, below.
Resilience Recommendation Next Steps Tentative Date
Update the Town’s Land Acquisition Manual Resolution December 2026
Update Flood Management Regulations Workshop December 2026
Implement Cove Buffer Ordinance Workshop April 2026
Page 5
Section 3. Item # 1.
October 27, 2026 Page 4
Resilience Recommendations for Discussion Town Council – Workshop
ATTACHMENTS:
1. McCormick Taylor Memos
2. SC Sea Grant Resilience Analysis
Page 6
Section 3. Item # 1.
MEMORANDUM
To: Town of Bluffton Project Team
From: McCormick Taylor
Date: 6/3/2026
Subject: Task 3.1 – Resiliency Ordinance
Project: Town of Bluffton – Wetlands and Resiliency Ordinance
1 PURPOSE
Given the state's vulnerability to hurricanes, sea-level rise, and flooding, resilience has become a major
focus for many communities, and jurisdictions along the coast have been actively implementing resiliency
plans and related policy updates. For example, in 2023, the South Carolina Office of Resilience completed
the first ever Statewide Resilience and Risk Reduction Plan for South Carolina and at the local level, in 2025,
the Town of Sullivan’s Island developed its first Sea Level Adaptation and Resilience Plan. To address
resilience, most local plans call for comprehensive updates to their municipal code. Recommendations
typically focus on strengthening stormwater management and requiring low-impact development and green
infrastructure, updating development standards and floodplain management requirements, and redesigning
zoning regulations with overlay districts to limit development in vulnerable areas.
The Town of Bluffton recently adopted a wetland ordinance to protect wetlands and their associated buffers
from development, preserving the essential natural functions these areas provide. This action follows the
2023 Sackett v. EPA decision, which removed protection from millions of acres of wetlands across the
United States that no longer qualify as federally jurisdictional. Other coastal communities, such as the Town
of Mount Pleasant and Georgetown County, are also considering or actively drafting similar wetland
protection ordinances. To further strengthen resilience to flooding, higher intensity storm events, and
projected sea level rise, the Town of Bluffton has begun exploring methods to map “resiliency zones” and
develop a resilience zone ordinance. These resiliency zones are locally defined as undeveloped areas that
provide critical environmental services, such as stormwater and floodwater storage, natural buffering from
storm surge, and groundwater recharge, all of which help mitigate the impacts of a changing climate. The
methodology used to identify and map these resilience zones is described in Memo 3.4. This memo provides
recommendations to incorporate into a resilience zone ordinance aimed at protecting and preserving the
mapped areas.
2 OTHER COASTAL JURISDICTIONS- RESILIENCE ORDINANCE REVIEW
As part of this effort, McCormick Taylor (MT) reviewed the municipal codes and regulations of nearby
jurisdictions to identify whether any resiliency zone ordinances had been adopted and if so, what elements
they contained that could help inform the Town’s approach. Focusing on coastal South Carolina
municipalities, MT reviewed the municipal codes from Charleston County, the City of Charleston, the Town
of Hilton Head, the City of Beaufort, Beaufort County, the Town of Kiawah Island, the Town of Mount
Pleasant, and the City of Myrtle Beach. While no jurisdiction has formally adopted a resiliency zone
ordinance in name, many municipalities have addressed resiliency through strengthened stormwater
Attachment 1
McCormick Taylor Memos
Page 7
Section 3. Item # 1.
regulations, flood management ordinances, and updated development standards and zoning districts. The
following section provides a high-level overview of resilience elements from each jurisdiction.
2.1 CHARLESTON COUNTY, SC
Charleston County does not have a specific resilience ordinance, however, in 2020, the County appointed
its first Chief Resilience Officer and created a Resilience Committee to help fulfill the resilience element of
the Comprehensive Plan. Members of the committee discussed proposed changes to the zoning and land-
use regulations, building and flood codes, and stormwater manual to increase resilience, and in 2022, three
recommended ordinances were adopted: Ordinance #2217 which amended the zoning and land
development regulations (ZLDR) regarding building height measurements, Ordinance #2218 which
amended the ZLDR to encourage parking under buildings, thereby promoting building designs that
encourage flow beneath structures, and Ordinance #2232 which updated impervious surface limits. Other
long-range recommendations that have been proposed for inclusion, but require further study, include
updating parking limits, strengthening tree protection ordinances, encouraging elevation-based
development, and updating design standards to reduce building footprints and incentivize green
infrastructure.
In 2022, the County passed Ordinance #2225 which formally established a permanent Resilience and
Sustainability Advisory Committee and in 2024, the County updated their Flood Damage Prevention and
Protection Ordinance ( Ordinance #2306 ), updating design flood elevation (DFE) to base flood elevation
(BFE) plus two (2) feet. Charleston County also maintains minimum buffers and setbacks from all saltwater
wetlands, waterways, and OCRM critical lines. Depending on the zoning district, the buffers range from 15
to 35 feet, and the setbacks are an additional 35 to 50 feet.
Chief Resilience Officer: Karen Burney-Green
Email: kgreen@charlestoncounty.org
Charleston County municipal code: Code of Ordinances | Charleston County, SC | Municode Library
2.2 CITY OF CHARLESTON, SC
Despite not having a formal resilience ordinance, the City of Charleston has implemented regulations that
address flood protection, sea level rise, and overall community resilience. In 2015, the City updated its
zoning and land-use ordinances to encourage growth in low-risk areas such as the Upper Peninsula. The
Upper Peninsula Zoning District is an incentive-based zoning district that provides opportunities to earn
height and density bonuses provided that developers implement community identified benefits such as
open space protection or green infrastructure. In 2018, the City of Charleston established the Mayor’s
Office of Resilience and Sustainability to spearhead resiliency initiatives. More recently, in 2023, the City
passed an ordinance banning “slab-on grade” foundations within the 100-year floodplain for single family
homes and multi-family dwellings.
The City of Charleston is currently undergoing a project to update and modernize its zoning code to make it
more user friendly, address the goals of the recently adopted comprehensive plan ( Charleston City Plan),
and address rising water levels. Based on the Charleston City Plan and a recent code assessment, one of
the recommendations was for the City to adopt “elevation-based” development regulations. These
regulations would address development and redevelopment in the context of the rising water environment,
Attachment 1
McCormick Taylor Memos
Page 8
Section 3. Item # 1.
which will cause an increased risk of flooding for low elevation areas. The Charleston City Plan included a
Land and Water Analysis (LWA) that used elevation, in consideration with watershed and environmental
sensitivity, to develop four broad planning strategies: grow, defend, adapt, and reserve. From this analysis,
four elevation risk zones were developed to guide the elevation-based zoning: Tidal Flood Risk Zone,
Compound Flood Risk Zone, Adapt Zone, and High Ground Elevation Risk Zone. The Tidal Flood Risk Zone
encompasses the lowest land in Charleston, nearly 100% of which is in the 100-year floodplain. This
includes elevations of approximately 7 feet and below, which is the point where tidal flooding of land can
occur and where marsh migration is likely to occur with 3 feet of sea level rise. This zone informed the
creation of boundaries for the Low/Impact/Conservation land use category as part of the City Plan’s Future
Land Use Map. The High Ground Elevation Risk Zone encompasses the highest elevations in the City,
generally 15 feet and above. These areas were used to map out areas of the town for higher intensity growth,
residential density, and a wide range of uses. The Adapt Zone consists of land outside of the FEMA 100-year
floodplain that is still within the NOAA maximum storm surge of a category 3 hurricane. Lastly, the
Compound Flood Risk Zone encompasses areas within the floodplain but above the tidal risk zone where
flood risk comes from a mixture of rainfall, runoff, and tidal conditions. The elevation-based zoning is
expected to be implemented over the next one to two years.
Director of Planning, Preservation, & Sustainability: Robert Summerfield
Email: newCHSstandards@charleston-sc.gov, summerfieldr@charleston-sc.gov
City of Charleston Municipal Code:
https://library.municode.com/sc/charleston/codes/code_of_ordinances?nodeId=10245
2.3 TOWN OF HILTON HEAD, SC
While the Town does not have a formal resilience ordinance, Hilton Head encourages resilience through
natural resource protection. Under the land management regulations, the Town maintains a wetland
protection ordinance to regulate development and activities in and around wetlands and wetland buffers.
Wetland buffer width requirements are 20 feet for single-family homes and vary for multi-family and non-
residential development. Additionally, under this ordinance, no work may be undertaken within a wetland
buffer without first receiving approval from the Town through a natural resources permit. The Town also
requires mitigation for any activity where the alteration of a wetland cannot be avoided. The loss of the
wetland must be mitigated for through any approved combination of wetland revegetation, wetland
restoration, wetland creation, wetland preservation, wetland mitigation banking, or the payment of fees in
lieu of mitigation.
The Town maintains strong flood hazard reduction standards, requiring all new construction and substantial
improvements to be elevated three (3) feet above BFE or to an elevation of 13 feet in special flood hazard
areas. The Town is currently working with a consultant team to develop a resilience plan addressing sea
level rise and climate adaptation and is in the process of updating the current land management ordinance.
Both efforts are expected to include resilience-based policy recommendations.
Chief Environmental Officer: TJ Lett
Email: TJJ@hiltonheadislandsc.gov
Town of Hilton Head municipal code: Code of Ordinances | Hilton Head Island, SC | Municode Library
Attachment 1
McCormick Taylor Memos
Page 9
Section 3. Item # 1.
2.4 CITY OF BEAUFORT, SC
While the City of Beaufort does not have a specific resilience zone ordinance, the local planning commission
has discussed implementing a wetland ordinance, though nothing has formally been adopted. The City
currently maintains critical area buffer requirements to preserve and restore native landscape along the
marsh edge. For transect-based zoning districts, the buffer is 30 feet and for conventional districts the buffer
is 50 feet. The City has also adopted the Southern Lowcountry Stormwater Design Manual (SoLoCo) which
emphasizes the use of green infrastructure and low impact development for post-construction stormwater
management.
While the City’s current flood damage prevention ordinance only requires all new construction and
substantial improvements to be elevated one (1) foot above BFE or to an elevation of 13 feet in special flood
hazard areas, the City has limited the amount of fill allowed on a parcel to three (3) feet to meet these
requirements.
City Planner III: Christopher Klement
Email: cklement@cityofbeafort.org
City of Beaufort municipal code: Code of Ordinances | Beaufort, SC | Municode Library
2.5 BEAUFORT COUNTY, SC
Beaufort County maintains natural resource protection standards that help preserve and protect wildlife
habitat, species diversity, and water quality. The current ordinance addresses tidal wetlands, non-tidal
wetlands, beach dune systems, endangered species and bird nesting habitat, flood hazard area, and
forests. Development in non-tidal wetlands is prohibited except for approved activities, and on-site or off-
site mitigation is required under certain conditions. The County requires a setback along the edges of all
freshwater wetlands in the form of a vegetative strip. For single family residential the setback is 20 feet and
for multifamily residential, commercial/industrial, and impervious parking areas/roads/driveways the
setback is 50 feet. A vegetated river buffer must also be established landward of the OCRM (BCM) critical
line. River buffer widths vary based on zoning district and range from 20 to 50 feet.
Beaufort County maintains a fill ordinance in special flood hazard areas. Similar to the City of Beaufort, fill
may not increase the existing natural grade more than three (3) feet and can only be placed underneath the
elevated structure. The County has also adopted the SoLoCo manual for post construction stormwater
management.
In 2024, Beaufort County updated its 2015 Sea Level Rise Action Plan to develop the Beaufort County Long-
Term Resilience Strategy , which focuses on sea level rise and includes recommendations for mitigating
localized flooding. The report includes recommendations categorized into four resilience strategy groups:
Awareness, Study, Action, and Reassess. Awareness and Study recommendations focus on research and
data gathering to support future decision making. Action recommendations focus on resilience policies and
planning strategies along with timelines for implementation. Reassess recommendations address ways to
ensure the policies and strategies are reaching the intended outcomes. A few of the relevant “Action”
recommendations from the report regarding resiliency include: 1) designing and constructing future capital
improvements and infrastructure to account for project sea level rise, 2) periodically evaluating policies
related to Base Flood Elevation (BFE), 3) adopting a coastal resilience overlay district that corresponds with
Attachment 1
McCormick Taylor Memos
Page 10
Section 3. Item # 1.
areas in the 100-year and/or 500-year floodplain and developing a set of policies to require new
infrastructure to be located outside of the district unless deemed necessary, and 4) identifying low lying
properties that serve important drainage and stormwater functions based on elevation and soils and
considering acquiring them or transferring development rights.
Planning and Zoning Department Director: Robert Merchant
Email: robm@bcgov.net
Beaufort County municipal code:
https://library.municode.com/sc/beaufort_county/codes/code_of_ordinances
2.6 TOWN OF KIAWAH ISLAND, SC
The Town of Kiawah is addressing resilience through planning initiatives and code updates. In 2023, the
Town adopted its Comprehensive Marsh Management Plan to guide future development while protecting
the Island’s vulnerable salt marshes. The Town established a Resiliency Committee to advise Town Council
on resilience and sustainability issues while helping to implement the recommended strategies from the
Marsh Management Plan and 2018 Flood Mitigation and Sea Level Rise Report. The Town recently approved
the 2025 Comprehensive Plan, KiawahNext. This plan, along with the Marsh Management Plan, details
recommended policy actions to meet the Town’s resiliency goals, such as creating a Chief Resiliency
Officer position, developing a consolidated Resiliency Plan, and forming an education program to increase
community awareness of resilience issues. In July 2025, the Town adopted an ordinance requiring all
development to submit a stormwater management plan for review and approval to help reduce flooding,
protect water quality, control erosion, and manage runoff. Previously, only construction projects larger than
one acre that required coverage under a NPDES construction general permit were regulated for stormwater
management.
The Town of Kiawah held its second reading for an ordinance to establish a Beachfront Overlay Zoning
District (BOD). The purpose of the BOD is to establish and protect a transition zone between the built
environment and the ocean, beach and dune system and promote coastal resilience and aesthetic
compatibility through zoning and vegetation standards. As of April 2026, Town Council has chosen to defer
action on the proposed BOD. While the Town does not have a wetland or wetland buffer ordinance, it
maintains critical line buffer and setback requirements. For residential development, the critical line
setback is 30 feet, and the critical line buffer is 10 feet. For non-residential development, the critical line
setback is 50 feet, and the critical line buffer is 35 feet.
Planning and Zoning Department Director: John Taylor
Phone Number: 843-768-9979
Town of Kiawah Island municipal code: Code of Ordinances | Kiawah Island, SC | Municode Library
2.7 TOWN OF MOUNT PLEASANT, SC
The Town of Mount Pleasant has several resilience-based standards already in place and created a
Committee on Flood Resilience and a GREEN (Green Space, Environment, Ecology, and Natural Resources)
Commission tasked with continuing to build town-wide resilience. In 2021, the Town updated the design
flood elevation from one (1) foot to two (2) feet plus BFE. The Town developed an “Environmental Guidelines
for Land Development ” program for commercial and non-residential development that encourages low
Attachment 1
McCormick Taylor Memos
Page 11
Section 3. Item # 1.
impact design, green infrastructure, nature-based solutions and sustainable building practices to make the
Town more resilient to flooding, habitat loss, and pollution. The program is based off a point system, and
any eligible project must be designed to meet a minimum of 100 points across four categories: 1) Protect,
Restore, and Conserve Natural Water Resources, 2) Protect and Improve Ecosystem Biodiversity, 3)
Improve Community Livability (Mobility, Aesthetics, Well-Being), and 4) Promote Energy Efficiency and
Sustainable Material Resources. They are currently considering implementing a similar program for
residential development. The Town also maintains a Single-Family Residential Stormwater Management
and Tree Preservation Program. The ordinance regulates construction on single family lots and ensures
neighboring properties are protected from stormwater and construction site sediment.
The Town of Mount Pleasant is currently (as of April 2026) moving to adopt a local ordinance to protect
isolated non-jurisdictional wetlands. The proposed ordinance would also require a buffer around all isolated
wetlands or vernal pools with an average width of 10 feet (no more than 20 feet and no less than five feet).
The Town has an existing wetland buffer ordinance, establishing a 35-foot buffer around all freshwater
wetlands and a critical area buffer ordinance with an average buffer width of 35 feet and a minimum of 20
feet.
Director of Planning, Land Use, & Neighborhoods: Michele Reed
Email: planning@tompsc.com
Town of Mount Pleasant municipal code:MOUNT PLEASANT, SOUTH CAROLINA CODE OF ORDINANCES
2.8 CITY OF MYRTLE BEACH, SC
The City of Myrtle Beach does not have a specific resilience zone ordinance; however, resilience is partially
addressed through their zoning and development standards. The City maintains a Coastal Protection
Overlay Zone for properties seaward of the projected 50-year erosion control line to control erosion,
preserve and maintain the beach, safeguard property, and promote public safety. Under the City’s zoning
code, there are four different “development options” one of which, the Sustainability and Conservation
Development Option, helps to promotes resilience and the protection of natural resources. This
development option is allowed in any new subdivision in any district that allows residential use, with the
intent of preserving and protecting natural resources such as groundwater, floodplains, wetlands, streams,
and woodlands for natural flood control, filtration, habitat for wildlife, and aesthetics. This option provides
the developer with various incentives for implementing certain measures. For example, if the land developer
maintains at least a 50’ vegetated buffer around all existing wetland and riparian areas, they are allowed to
construct one additional multifamily dwelling unit per 3,000 square feet of provided buffer area. Similarly, if
native plants are used for landscaping, one additional multifamily dwelling unit per 0.5 acre of natively
landscape area, including the utilization of rain harvesting and/or water recycling for irrigation, is allowed.
Incentives are additionally granted for trails and open space connectivity, additional provision of open
space, low-impact development, affordable housing, and energy and water efficiency/sustainable
construction certification.
The City also maintains strong flood management requirements and requires all development in the 100-
year flood zones and coastal high hazard zones to be elevated three (3) feet above BFE.
Director of Planning & Zoning: Kenneth May
Phone Number: 843-918-1167
Attachment 1
McCormick Taylor Memos
Page 12
Section 3. Item # 1.
City of Myrtle Beach municipal code: CODE OF ORDINANCES CITY OF MYRTLE BEACH, SOUTH
CAROLINA | Code of Ordinances | Myrtle Beach, SC | Municode Library
3 JURISDICTIONS OUTSIDE SC- RESILIENCE ORDINANCE REVIEW
MT reviewed regulations from four other coastal jurisdictions along the East Coast that have established
resilience or wetland ordinances. This section summarizes the ordinances from Norfolk, Virginia, Beaufort,
North Carolina, Savannah, Georgia, and Boston, Massachusetts.
3.1 CITY OF NORFOLK, VA
The City of Norfolk underwent a comprehensive zoning ordinance update and in 2018 adopted new
regulations that established resilience overlay districts and a resilience quotient system. The resilience
overlay districts, which were identified in Norfolk’s Vision 2100 plan, consists of a Coastal Resilience
Overlay (CRO) district and an Upland Resilience Overlay (URO) district. The CRO district is defined as all
land within the 100-year floodplain with the intent of reducing flood risk to individual properties and the
surrounding community. The CRO district has specific regulations for ground floor height, landscaping, open
space set-asides, and parking. For example, landscaping must consist of exclusively salt tolerant and native
species and paved parking is limited to reduce stormwater runoff. The URO district applies to all land
outside of the CRO district and is intended to encourage development in upland areas, away from flood risk.
Concurrently, the City established a resilience quotient system within its development standards. All new
and redevelopment must comply with the resilient quotient and undergo site plan review to ensure resilient
development is addressed by reducing risk from flooding, managing stormwater, promoting energy
resilience, conserving water resources and protecting water quality, supporting multiple mode of mobility,
developing in a manner that promotes health and safe environments and lifestyles, and providing
inclusionary dwelling units with mixed-income residential or mixed-use developments. In lieu of the site
plan review process, depending on the development type (multi-family residential or non-residential) and
number dwelling units or total square footage, applicants may elect to achieve a minimum number of points
from the resilient quotient across three categories: flood risk reduction, stormwater management, and
energy resilience. Single-family development may also choose to comply with the resilience quotient for
single family development in lieu of the City’s site plan review process. Instead of achieving a minimum
number of points, under this option, flood risk reduction must be addressed by elevating the lowest
habitable floor and all significant electrical and mechanical equipment at least 16 inches above the highest
existing adjacent grade. Stormwater requirements must be met by either capturing and detaining roof runoff
on site with at least 200 gallons of storage or by planting one healthy medium or large tree (or two healthy
small trees) for every 25 feet of lot frontage. Lastly, energy resilience must be addressed by designing the
electrical system with pre-installed wiring and connections to safely support a generator and/or connection
to solar, wind, or other locally generated electricity sources.
The CRO and URO overlay districts also have specific requirements under the resilience quotient. If located
within the CRO district, developers for multiple dwelling unit residential development and non-residential
and mixed-use development must reach a higher minimum point requirement or provide 25% greater
flooding risk reduction and stormwater management efforts if utilizing the site plan review procedure. If
Attachment 1
McCormick Taylor Memos
Page 13
Section 3. Item # 1.
developing in the URO, four points may be counted towards the resilient quotient if a developer extinguishes
development rights in the CRO, either through direct purchase or easement.
Zoning Administrator: Jeremy Sharp
Email: Jeremy.sharp@norfolk.gov
City of Norfolk zoning ordinance: Norfolk_Zoning_Ordinance
3.2 TOWN OF BEAUFORT, NC
The Town of Beaufort is currently drafting a new Unified Development Ordinance (UDO) that will
consolidate its zoning, subdivision, flood protection, and minimum housing ordinances into a single
document. As part of the new UDO and as recommended by the Town’s Comprehensive and CAMA Land
Use Plan, the new UDO will include a Coastal Resilience Overlay District (CR-O). As of October 2025, the
Town has completed a proposed draft CR-O which will establish two subdistricts: the CR-NIZ, non-
intensification zone subdistrict and the CR-M, moderate hazard subdistrict. The CR-NIZ corresponds to the
100-year floodplain (Zones AE and VE) and the CR-M corresponds to the 500-year floodplain (Shaded Zone
X). The overlay will include specific regulations for residential density, impervious surface coverage,
shoreline management, and low-impact development. For example, within the CR-NIZ, new critical
facilities and new residential uses other than detached single family homes are prohibited. Additional
regulations include:
1. New developments within the CR-NIZ subdistrict are limited to a maximum density of five
dwelling units per acre;
2. All lots in the CR-O subdistrict that have frontage along a natural waterbody must maintain or
establish a shoreline buffer with native vegetation; and
3. All new developments in the CR-O that are subject to Chapter 54, Stormwater must use at least
two LID techniques to manage at least 50% of the developments peak flow.
The proposed regulations will also incorporate incentives for developers. If an existing development is
proposed to be renovated, repaired, altered, or otherwise improved by more than 50% of its replacement
value, developers can receive incentives for stormwater retrofits. For example, adding vegetation to existing
retention/detention areas or installing a bioswale or raingarden may count toward the on-site landscaping
requirements. Replacing impervious surfaces with pervious materials may also allow a reduction in the
required shoreline buffer area, equivalent to the amount of impervious surface removed, up to 750 square
feet. Additional incentives are provided if the development incorporates increased construction standards.
For instance, if the principal structure is elevated above the regulatory flood protection elevation (RPFE),
the maximum building height may increase by 1 foot for each additional foot the structure is elevated above
RPFE. If at least 75% of the structure’s windows and doors are impact resistant, the maximum impervious
surface coverage may increase by up to 2%. The complete list of incentives can be found in the draft
ordinance.
Planner: Michelle Eitner
Phone number: 252-728-2141
Town of Beaufort draft coastal resilience overlay district: Draft Coastal Resilience Overlay District 09-05-
25 | Town of Beaufort, NC
Attachment 1
McCormick Taylor Memos
Page 14
Section 3. Item # 1.
3.3 CITY OF SAVANNAH, GA
While not a formal resilience ordinance, the City of Savannah, Georgia has several natural resource
ordinances in place to protect riparian systems, groundwater recharge areas, and wetlands. The city has a
Protected River Corridor Buffer limiting certain land-disturbing activities and uses within a designated 100-
foot buffer for perennial streams or watercourses with an average annual flow of at least 400 cubic feet per
second. The city maintains a Groundwater Recharge Area ordinance in which land uses that generate, use,
or store pollutants within groundwater recharge areas are restricted. The boundaries of this area are defined
by the George Department of Natural Resources Pollutant Susceptibility Map in the Hydrologic Atlas. For
wetlands, the City has a Wetlands Assessment regulation in which any applicant seeking land disturbance,
building, or demolition permits must consult the U.S. Environmental Protection Agency West Chatham
County Advance Identification Map of Wetlands and Uplands (ADID map) or the U.S. Fish and Wildlife
Service NWI map. If the proposed activity is located within a wetland inventory area or within 100 feet of
one, a USACE jurisdictional determination is required. If jurisdictional features are found and a USACE
permit is required, the city will only issue a land disturbance, building, or demolition permit after receiving
the USACE permit. The City also maintains a wetland and marsh buffer ordinance, with a wetland buffer
width of 35 feet along jurisdictional wetlands and a marsh buffer width of 35 feet along all marsh. Activities
such as soil disturbance, clearing of vegetation, and filling are prohibited within the wetland and marsh
buffers, and an approved modified wetland or marsh buffer permit is required from the city before any
approved land-disturbing activities can be conducted within the buffer area.
Director of Planning and Urban Design: Bridget Lidy
Email: Blidy@savannahGA.gov
City of Savannah municipal code: City of Savannah Code of Ordinances
3.4 CITY OF BOSTON, MA
Boston, MA has integrated resilience in numerous ways. All projects subject to or electing to comply with
Article 80 Large Project Review, Planned Development Area Review, Institutional Master Plan Review, or
Small Project Review must comply with Zoning Article 37 and the City’s Climate Change Review Policy, and
be designed, constructed, and managed to minimize and mitigate adverse environmental impacts, promote
sustainable development, and minimize and mitigate the impacts of greenhouse gas emissions. In 2017,
the Climate Change Review Policy was updated, requiring all Large Project, Planned Development Area,
and Institutional Master Plan review to complete a climate resiliency checklist as part of their development
review procedure. As of July 2025, small project review applications must also include a climate resiliency
checklist. Utilizing the checklist, applicants must consider and analyze the impacts of near and future
climate conditions and incorporate measures to avoid, eliminate, or mitigate greenhouse gas emissions and
impacts related to climate change in project planning, design, and construction. The review process
requires applicants to consider a range of climate stressors including sea level rise, higher annual
temperatures, more frequent and longer extreme heat events, increased precipitation, more severe rain
events, and increased greenhouse gas concentrations.
Boston also developed and adopted a Coastal Flood Resilience Overlay District (CFROD) in 2021 to
address long-term flood risks. The overlay district corresponds to the area anticipated to be flooded with a
1% chance storm event in 2070 with 40 inches of sea level rise. Within the CRFOD, all projects must be
designed to meet the minimum sea level rise design flood elevation (SLR-DFE). Per Article 25A of the zoning
Attachment 1
McCormick Taylor Memos
Page 15
Section 3. Item # 1.
code, a Resilience Reviewer will ensure project compliance with the City’s resilience policies and
requirements. For projects not subject to Article 80 Large Project review, the Boston’s Planning and
Development Agency (BPDA) will conduct resilience review through the resilience component of the Small
Project review process. In addition to the elevation requirements, projects within the CFROD must be
consistent with the coastal flood resilience design guidelines . These guidelines include incorporating
resilient practices to reduce flood risk, enhancing the character of the public realm, integrating district-scale
resilience solutions, and including sustainability co-benefits.
Deputy Director for Climate Change and Environmental Planning: Rich McGuinness
Email: Richard.McGuinness@boston.gov
City of Boston municipal code: ARTICLE 25A - COASTAL FLOOD RESILIENCE OVERLAY DISTRICT |
Redevelopment Authority | Boston, MA | Municode Library
4 TOWN OF BLUFFTON’S EXISTING MUNICIPAL CODE
MT reviewed the Town of Bluffton’s municipal code to identify existing resilience-based elements to help
guide the creation of the recommended resilience zone ordinance.
4.1 FLOODPLAIN MANAGEMENT
As summarized in the Memo 3.2, the Town of Bluffton regulates all development within FEMA-designated
Special Flood Hazard Areas (SFHAs) through a permitting process that requires scaled site plans, elevation
data, and professional certifications for new or improved structures. Development is prohibited in
floodplains if alternative locations exist, and projects that affect floodways, base flood elevations (BFE), or
watercourses must obtain FEMA Conditional Letters of Map Revision (CLOMRs) before construction and
submit as-built certifications upon completion, which require professional engineer certification. General
floodplain development standards require anchoring, flood-resistant materials, and utility protection to BFE
+3 ft. The first floor of residential, non-residential, and manufactured housing construction must be elevated
at least one foot above the adjacent roadway centerlines or three (3) feet above BFE, whichever is higher,
and enclosures below BFE are limited to non-habitable uses with flood openings provided to relieve
hydrostatic pressure. Critical development (hospitals, fire stations, etc.) elevations must meet or exceed
the 500-year flood elevation or the highest known historical flood.
Additional provisions address a wide range of development scenarios to ensure flood risk is minimized
across the community. Floodways prohibit encroachments is prohibited unless certified as “no-impact,”
and Coastal High Hazard Areas (V-Zones) require pile or column foundations with breakaway walls to
accommodate wave action. Recreational vehicles (RVs) are only permitted if temporary, road-ready, or
compliant with manufactured housing standards, while accessory structures and utility rooms must be
anchored and floodproofed according to FEMA guidance. Subdivisions, streams without mapped BFEs,
shallow flooding zones, and coastal hazard areas all have tailored requirements mandating hydrologic and
hydraulic studies when necessary.
Attachment 1
McCormick Taylor Memos
Page 16
Section 3. Item # 1.
4.2 ZONING AND DEVELOPMENT STANDARDS
The Town’s design standards are intended to promote development that allows for more open space to be
preserved to help promote infiltration, reduce flooding, and lower the amount of pollution entering local
waterbodies. Bluffton maintains open space requirements for all development and redevelopment
activities. A minimum of 20% of the gross acreage must be developed/preserved as open space, and for
residential development a minimum of 10% of the gross residential use acreage must be specifically
identified and developed to use as common open space and accessible to the residents and the general
public. Lands designated as open space includes active recreation areas, central greens, community parks,
natural open land, greenbelts, or stormwater detention areas with greenway trails and footpaths. Current
lot and building standards include maximum lot coverage percentages, but do not indicate specific
impervious surface limits. However, the ordinance does encourage shared parking and block and roadway
layouts that reduce overall impervious surfaces.
The Town maintains a preserve (PR) zoning district. The PR district is intended to preserve and protect
sensitive environmental areas, restrict development that could compromise these areas, and maintain
open spaces that provide an ecological and aesthetic value to the community. The Town’s development
ordinance also incentivizes sustainable neighborhood design and development through the implementation
of Smart Growth Principals in four of the Town’s “Place Types” (Rural Crossroads, Hamlet, Village, or Town
Center). To receive incentives, a project must score a minimum of 15 out of 20 points from six different
criteria: redevelopment site, compact, complete, and connected development, environmental
sustainability, water conservation/efficiency/management, energy efficiency, and operations and
maintenance education. Developments that meet these criteria can receive a 25 % fee reduction and up to
a 50% fee reduction if 20 points are achieved.
4.3 STORMWATER MANAGEMENT
The Town adopted the Southern Lowcountry Stormwater Design Manual, or the SoLoCo Manual in 2021.
The manual, which was amended March of 2025, standardizes how stormwater elements of projects are
designed, submitted, reviewed, approved, and inspected and emphasizes the use of green infrastructure
and low impact development to address post-construction stormwater management. The design criteria in
the manual are applicable to any new development or redevelopment activity that meets one of more of the
following criteria or is a major substantial improvement: 1) development that involves 5,000 square feet or
more of land disturbing activities, 2) redevelopment/infill that will result in an additional 2,000 square feet
or more of impervious surface, or 3) land disturbance, regardless of size, that is part of a larger common
plan of development that meets criteria 1 or 2. The SoLoCo manual has designated three separate
watershed protection areas with unique stormwater management requirements based on the current and
anticipated water quality control measures for their contributing watersheds. The Town falls within the
Bacteria and Shellfish Watershed Protection area, and therefore any applicable new development,
redevelopment, or major substantial improvement must meet the following performance requirements
below.
" To address water quality, the developer must implement Better Site Design (BSD) and retain the
95th percentile storm on site with approved infiltration/filtering BMPs. For the Bacteria and Shellfish
Watershed Protection Areas this is 1.95 inches of rainfall. The developer must also fulfill maximum
Attachment 1
McCormick Taylor Memos
Page 17
Section 3. Item # 1.
extent practical (MEP) requirements or, as a last resort, fulfill off-site credit and/or fee-in-lieu
requirements.
" As a pollutant removal minimum, the developer must intercept and treat stormwater runoff volume
to at least an 80% reduction in total suspended solid loads, 30% reduction of total nitrogen load,
and 60% reduction in bacteria load.
" The developer must control the post-development peak runoff discharge rate for the 2, 10, 25, 50,
100-year, 24-hour design storm events to the pre-development discharge rates.
" The developer must accommodate the 100-year, 24-hour storm event conveyance through the site
and downstream without causing damage/inundation to structures and provide 10% rule analysis.
4.4 NATURAL RESOURCE PROTECTION
The Town recently adopted an wetland and wetland buffer ordinance following the 2023 Sackett v. EPA
decision that removed protection from millions of acres of wetlands that no longer qualify as federally
jurisdictional. The Town also maintains a riparian buffer ordinance requiring a buffer of 100 feet from the
SCDES Critical Line adjacent to any tidal wetlands and waterways (see memo from Task 3.4 for more
information on riparian buffers). The Town maintains a tree conservation ordinance where the preservation
and enhancement of native vegetation is encouraged and any impacts to protected trees (all trees that are
8 inches in diameter at breast height (DBH) or greater and all American holly, dogwood, redbud, southern
magnolia and red buckeye trees that are 4 inches in DBH or greater) and significant trees (24 inches in DBH
or greater, any tree listed on America’s Historic Tree Register, and all trees that are located within regulated
wetland buffers) requires a permit. If protected trees are removed, they are required to be replaced
according to the standards established in the ordinance. Native and regionally appropriate plant species
must be planted, and replacing invasive species with hardwood species is encouraged. For sites less than
one (1) acre, a tree canopy with a minimum 75% coverage must be provided. When land disturbance is
proposed for sites of at least one (1) acre, a minimum of 15 hardwood trees per acre must be provided.
5 RESILIENCE ZONE ORDINANCE RECOMMENDATIONS
A resilience ordinance could be implemented using two general approaches. The first approach would be
to establish a resilience-focused site plan review process which could be implemented alongside the
Town’s current development plan review procedures. This option would apply town-wide and take a more
comprehensive approach to resilience, evaluating not only flood reduction, primarily addressed in the
SoLoCo manual, but also broader resilience objectives such as energy resilience and risk reduction.
Alternatively, the Town could establish a resilience zone overlay district to focus protection on the more
vulnerable flood prone areas. The boundary of the overlay district could correspond to the locally derived
conservation priority areas, the elevation-based analysis, or the 100 year and/or 500-year FEMA floodplain
boundaries, depending on the Town’s goals. Within the overlay district, additional regulations would apply
to increase resilience to flooding, sea level rise, and other climate related impacts and encourage
development and redevelopment in areas outside of the resilience zones. Consideration should be made
regarding redevelopment or remodeling of structures; the threshold constituting a “substantial
improvement” to a structure should be predefined. Following FEMA guidance of 50% of the structure’s
value would be in line with the current flood damage requirements.
Attachment 1
McCormick Taylor Memos
Page 18
Section 3. Item # 1.
An overview of the two approaches is described below, though the selected approach will depend on the
Town’s ability to implement and enforce the suggested policy and procedures.
5.1 RESILIENCE PLAN REVIEW PROCESS
Under the resilience plan process, applicants seeking approval for new or redevelopment would be required
to submit a resilience plan demonstrating how the proposed development addresses the Town’s identified
resilience objectives. The resilience plan could be submitted as a standalone document or incorporated
into the required stormwater management plan (SWMP) submittal to reduce redundancy. The Town could
require that the applicant pay an additional resilience review fee as part of the process. Revenue generated
through this fee could go towards a resilience fund used to support resilience initiatives or purchase
conservation easements.
The proposed approach is adapted from Boston, Massachusetts Climate Resiliency Guidelines, Norfolk,
Virginia’s resilient quotient and site plan review process, and Mount Pleasant’s Environmental Guidelines
for Land Development. Under this framework, a developer must also achieve a minimum number of points
across a range of resilience categories. The required point threshold could be based on factors such as
project size, location, or development type. For example, more points could be required for developing
within the previously identified resilience zones or FEMA regulated flood hazard areas versus areas outside
of these zones. Point requirements could also vary based on development type (single family residential,
multi-family, commercial, institutional, industrial), with single family, single lot development needing fewer
points. Subdivisions of greater than four lots should follow the same requirements as multi-family
development since subdivisions will typically include infrastructure such as roads and community centers.
Whereas single lot residential developments are typically built off of an existing road and includes only the
structure and driveway.
As part of the review process, applicants would submit a resilience plan with a standardized resilience
checklist, providing supporting information and calculations demonstrating how the proposed development
meets the Town’s requirements. This approach allows for flexibility in how the applicant achieves
compliance with these standards and is not intended to discourage development, but instead ensure
developers integrate resilience into all steps of the planning and design process. Resilience categories may
include stormwater and floodplain management, energy resilience, protection of natural resources, hazard
and risk reduction, and the promotion of healthy and safe communities, though the specific categories can
be tailored to the Town’s priorities. To ensure a balanced approach, the Town should require that the
applicant meet a minimum point threshold from all resilience categories. Alternatively, the Town could
require points to be earned from a specific number of categories (e.g., 3 or 4). While incentives could be
offered for projects that exceed the minimum point thresholds, given the suburban nature of the Town,
expedited review times or reduced permitting fees are recommended rather than density bonuses or
relaxed building codes.
The following section outlines recommended resilience elements the Town may choose to incorporate into
their resilience plan process. It’s important to note that many of these techniques require maintenance and
continued financial investment. The Town should require that the applicant provide a maintenance
agreement along with the resilience plan submission.
Attachment 1
McCormick Taylor Memos
Page 19
Section 3. Item # 1.
Stormwater Management
All development:
" Exceed SoLoCo requirements for water quality and quantity management using projected
precipitation rates
" Reduce impervious surface on the site by a predetermined percentage
" Design the drainage system for future climate conditions such as the current 25-year storm or
use projected precipitation rates
" Consider increased tailwater conditions that reflect sea level rise or increase in downstream
water surface elevations due to precipitation changes for storm drain computations
" Provide downspout disconnection
Single family, single lot, residential development:
" Construct new hard landscaping (driveways, walkways, pool surrounds) using pervious
materials
" Intercept and detain roof drainage on site via rain gardens or cisterns
Multiple Lot Single Family Development or Multi-family residential development/commercial
development:
" Use pervious pavement or grass paving systems on at least 50% of a parking lot
" Construct new hard landscaping (driveways, walkways, pool surrounds) using pervious materials
on all parking bays except ADA
" Intercept and detain roof drainage on site via rain gardens or cisterns
" Install pet waste stations
" Utilize open section roadways with grass swales
" Develop gray water reuse systems for irrigation or other non-potable uses
Floodplain Management
All development:
" Minimize floodplain fill (1 foot or less) within any site buildout
" Provide compensatory storage at a ratio of 1.5 to 1
" Increase finished floor elevations above the minimum standards
Energy Resilience
All development:
" Generate a predetermined percentage of electricity from on-site solar, wind, geothermal, or other
renewable energy source
" Install electric vehicle charging stations
Natural Resources
Attachment 1
McCormick Taylor Memos
Page 20
Section 3. Item # 1.
All development:
" Provide a wider wetland buffer or riparian buffer than what is currently required by the Town’s
ordinance
" Provide a minimum 35’ riparian buffer along all streams
" Plant exclusively native and salt-tolerant landscaping
" Install a pollinator garden
" Retain all existing large trees or expand the existing tree canopy
" Reforest previously disturbed areas
" Utilize stormwater marshes and wetlands instead of wet ponds, or incorporate varying grading
schemes within ponds to allow for various planting zones of native species
" Install a naturalized riparian buffer around stormwater ponds
" Install floating wetlands within the stormwater ponds
Hazard and Risk Reduction
All development:
" Install impact (hurricane or wind) resistant windows
" Install storm shutters
" Impact resistant roof
Healthy and Safe Communities
All development:
" Provide public walkways or connect to an existing trail or path system utilizing pervious surfaces
" Provide open space greater than what is currently required
" Provide a community garden space at a ratio of 50 square feet per residential dwelling unit
" Provide bicycle amenities
The process would work as follows: a trigger mandates a required resilience plan review – for example,
projects with a land disturbance greater than 5,000 square feet. Once required, the developers, architects,
consultants, and engineers would complete the resilience checklist consisting of a range of quantitative and
qualitative questions about the site and how the development addresses the proposed resilience elements
and achieves the required points. As part of this process, project planners must evaluate if the location and
site conditions are vulnerable to flooding (FEMA 100 and 500-year floodplain as an example) or fall within
the Town’s resilience zone (see hybrid approach below). This framework encourages projects to be
designed around future risk, and the Town may decide to choose a set year, say 2070, as a project target for
sea level rise, changes in precipitation, and projected development within the area. The process should not
be rigid but instead considered as a resilience framework that can be adapted to broader landscapes or risk
patterns while removing bias. The following section provides an example of what information and questions
the checklist could include:
Attachment 1
McCormick Taylor Memos
Page 21
Section 3. Item # 1.
Project Information
Owner, Developer, Architect, Engineer, etc. contact information and licenses
Parcel and Building Information including:
• Site location
• Property area and building area
• Area of disturbance
• Existing site elevation low and high
• Proposed site elevation low and high
• Proposed first floor elevation
Is any portion of the parcel in a FEMA SFHA, what zone and what elevation?
Is any portion of the parcel in the Town’s selected Resilience Zone?
Is any portion of the parcel within the SC projected sea level rise or marsh migration area?
Applicable green building rating systems:
• LEED Version, Certification, Rating and Point Score
Project Specifications
Building Envelope – R Values:
• Roof, exposed floor, foundation wall, slab edge
• Above-grade assemblies such as windows, doors, and spandrels
Energy Loads and Performance:
• Annual Electric (kWh), Peak Electric (kW)
• Annual Heating (MMbtu/hr), Peak Heating (MMbtu)
• Annual Cooling (Tons/hr), Peak Cooling (Tons)
• Energy Use – Below ASHRAE 90.1-2013 (%)
• Energy Use – Below SC Code (%)
• Energy Use Intensity (kBtu/SF)
Back-up / Emergency Power System:
" Electrical generation output (kW)
" System type (kW)
" Number of power units
" Fuel source
Greenhouse Gas Reduction and New Zero / Net Positive Carbon Building Performance:
" Annual building GHG emissions
" Describe how building energy performance has been integrated into project planning, design and
engineering, provide supporting analysis or modeling.
" Describe passive energy efficiency measures
" Describe specific active energy efficiency measures
" Describe building specific load reduction strategies
" Describe any area or district scale emission reduction strategies
" Describe any energy efficiency assistance or support provided
" Describe utilization of renewable energy resources
" Describe how the building and its systems will evolve to further reduce GHG emissions
Attachment 1
McCormick Taylor Memos
Page 22
Section 3. Item # 1.
Climate:
" Temperature range (low/high)
" Annual heating degree days and cooling degree days
" What extreme heat event characteristics will be / have been used for project planning
" Days above 90 degrees, days above 100 degrees
" Number of and duration of heatwave per year
" Describe building and site measures to reduce heat island effects
" Describe how the building and its systems will be adapted to efficiently manage future higher
average temperatures, additional heatwaves, and longer heatwaves
" Describe all mechanical and non-mechanical strategies that will support building functionality
during extended interruptions of utility services and infrastructure including proposed and future
adaptations
Resilience:
" Describe how the site meets the resilience point requirements
" Describe all building and site measures for reducing storm water runoff
" Describe how site and building systems will be adapted to efficiently accommodate future more
significant rain events
" Describe site design strategies for adapting to sea level rise including building access during flood
events, elevated site areas, hard and soft barriers, wave/velocity breaks, stormwater systems,
utilities, etc.
" Describe how the proposed building design flood elevation will be achieved including dry/wet
flood proofing, critical systems protection, utility service protection, temporary flood barriers,
waste and drain back flow prevention
" Describe how occupants might shelter in place during a flooding event including any emergency
power, water, and wastewater provisions and the expected availability of such measures
" Describe any strategies that would support rapid recovery after a weather event
" Describe future site design and or infrastructure adaption strategies for responding to sea level
rise including future elevating of site areas, access routes, barriers, etc.
5.2 RESILIENCE ZONE OVERLAY DISTRICT
Alternatively, the Town may choose to address resilience through the establishment of a resilience overlay
district. Overlay districts are a flexible planning tool that would allow for additional requirements to be
implemented while keeping the base zoning regulations in place. Implementing an overlay district would
also prevent the need to rewrite the existing zoning code, which is a substantial and time-intensive process,
and is consistent with the approach taken by Norfolk, Virginia, Beaufort, North Carolina, and Boston,
Massachusetts. A variety of mapping methods and approaches were evaluated as the boundary for the
resilience zone (see Task 3.4). If the Town’s primary focus is to reduce flood risk and protect the most
vulnerable areas, MT recommends establishing the overlay district based on the low and medium elevation
areas identified through the Town’s elevation analysis in combination with the 100- and 500-year
floodplains. However, the elevation-based boundary may not protect upland areas with high infiltration
rates from development, potentially increasing flooding impacts downstream. Utilizing the conservation
priority areas identified using the methodology developed by the South Carolina Office of Resilience as the
resilience zone boundary may be more beneficial from a Town-wide resilience standpoint.
Attachment 1
McCormick Taylor Memos
Page 23
Section 3. Item # 1.
The proposed resilience overlay district would complement the SoLoCo manual and further protect water
quality, reduce stormwater runoff, preserve natural habitat and floodplains, encourage resilient
construction, and prepare for and minimize the effects of future sea level rise. MT recommends the
following standards be implemented within the resilience overlay district:
Stormwater Management
• Set impervious surface limits or limits on what percentage of the lot should remain naturally
vegetated/landscaped. Recommended 30% impervious surface limits for residential
development and 50% for non-residential.
• Require driveways and new hard landscaping (walkways, driveways, pool surrounds) to be
constructed using pervious materials.
• Require developments exceed SoLoCo requirements for water quality and quantity management
using projected precipitation rates.
• Require storm drain computations to consider increased tailwater conditions that reflect sea
level rise or increase in downstream water surface elevations due to precipitation changes.
• Do not allow variances or Maximum Extent Practical Waivers.
• Require a comprehensive watershed study that depicts the impact on the downstream
conveyances for storm events up to the 100-year. The study should include the hydrograph
peaks for the main discharge channel / water course and the specific site discharge.
Floodplain Regulations
• Set a limit on the amount of fill for any site buildout. Recommended no fill be allowed within
SFHA, or if fill is allowed, compensatory storage should be required at a ratio of 1.5 to 1.
• Include language to allow easy adjustment of the BFE+3 to account for sea level rise and
increased storm surge.
• Place the same floodplain requirements for the 500-year event that is currently in place for the
100-year event.
Risk Reduction
• Require at least 75% of the windows and doors to be impact resistant.
• Require at least 75% of the windows to include storm shutters.
• Require an impact resistant roof.
Natural Resources/Landscaping
• Require the use of native and salt-tolerant landscaping.
o Consider adding a table of preferred or recommended native vegetation for plantings.
• Require a naturalized riparian buffer around stormwater ponds.
• Require an increased tree canopy or greater replacement requirements.
While other municipalities have explored a transfer of development rights (TDR) program to encourage
development elsewhere, the City of Norfolk has found this approach to not be successful at shifting
development patterns. The overlay district approach could instead include incentives that encourage
development in areas outside of the resilience zone such as expedited permitting or permit fee reductions.
If using the elevation-based boundary, it should be noted that encouraging development in upland areas
may lead to increase runoff further exacerbating flooding within the resilience zones. If incentives of this
Attachment 1
McCormick Taylor Memos
Page 24
Section 3. Item # 1.
nature are explored, careful consideration on enactment of additional stormwater requirements should be
considered.
5.3 HYBRID APPROACH
The resilience site plan review process and resilience zone overlay district could also be implemented
together as a hybrid resilience framework. Under this approach, optional measures identified in the site plan
review process could become mandatory for projects within the resilience zone overlay district. For
properties outside of the resilience zone, the resilience site plan review process/checklist could either be
voluntary with incentives offered to encourage participation, or mandatory through a lower threshold of
points required. MT recommends the latter approach that would hold all development to a level of resilience
planning, while areas within the resilience zone should have additional requirements . With any ordinance,
a waiver or variance mechanism must be in place. Variances should only be granted upon demonstration
that strict compliance would create exceptional hardship, the variance will not increase public danger or
flood risk, and the variance is the minimum necessary relief and complies with all local, state and federal
requirements.
6 CONCLUSION
While many local communities in South Carolina have incorporated resilience elements through floodplain
management standards, stormwater requirements, and other green initiatives, none have adopted a
comprehensive resilience zone ordinance. In review of the above approaches, it is recommended that the
Town of Bluffton adopt a hybrid approach, combining a town-wide resilience site plan review process with
a resilience zone overlay district. Under this approach, all development and applicable redevelopment
would be required to consider resilience throughout the review process, while projects located within the
overlay district would be required to follow more stringent resilient practices. Incentives could be provided
for development in areas outside of the overlay district, including expedited permitting, density bonuses
where appropriate, stormwater fee reduction, reduced parking requirements and public recognition
programs. The launch of the resilience plan process can begin as a recommended checklist for developers.
Then, a scheduled rollout date can be set for mandatory compliance. The success of a resilience ordinance
and enhanced development requirements is reliant on public education. The Town should launch a
“Resilient Bluffton” public information campaign that promotes the values of this program and how it will
ultimately provide for a safer, more resilient community. Care should be taken though that these guidelines
do not burden socially vulnerable populations or workforce housing initiatives.
Attachment 1
McCormick Taylor Memos
Page 25
Section 3. Item # 1.
1
MEMORANDUM
To: Town of Bluffton Project Team, Attn: Beth Lewis & Andrea Moreno
From: McCormick Taylor
Date: 5/5/2026
Project: Town of Bluffton – Wetlands and Resiliency Ordinance
Subject: Task 3 – Resiliency Ordinance, Components and Considerations
Purpose:
This memorandum summarizes the findings from Task 3.2, which involved reviewing the Heyward Cove project
report while considering the framework and methodology, reviewing and summarizing existing Town of Bluffton
flood prevention codes, and recommending flood mitigation ordinances including a minimum first floor elevation for
structures, compensatory storage needed to avoid upstream/downstream impacts, and minimum fill and elevated
“flow through” construction approaches. All thoughts, analysis, concerns, and recommendations provided in the
following memorandum are intended as an objective report and are not intended as legal advice.
1 H EYWARD COVE STUDY REVIEW
In 2023, J. Bragg Consulting completed an engineering analysis of the Heyward Cove drainage basin in Bluffton,
South Carolina. That project included a stormwater asset inventory of drainage infrastructure, hydrologic and
hydraulic analysis, and program and project recommendations. McCormick Taylor (MT) reviewed the J. Bragg
Consulting final report. A summary of their methods and findings is included here. Additionally, the project’s
framework was evaluated to provide recommendations on application of that project’s findings on buffer and
protection areas.
1.1 H EYWARD COVE STUDY SUMMARY
1.1.1 Stormwater Asset Inventory
A comprehensive stormwater asset inventory was developed for the Heyward Cove basin using Beaufort
County LiDAR and DEM data, Bluffton and Beaufort County GIS stormwater inventories, SCDOT as-built
plans, NOAA tidal and rainfall records, FEMA flood maps, USDA soils data, and other regional resilience and
climate references. Assets such as inlets, pipes, culverts, channels, and streams were documented for
type, size, ownership, material, location, elevation, and condition, while smaller pipes, roadside ditches,
and non-stormwater infrastructure were excluded. The assessment categorized assets into structural or
maintenance defects, reflecting collapse, deterioration, sedimentation, or vegetation issues. Bluffton’s
stormwater infrastructure policy framework guided classification by Level of Service (LOS), emphasizing
citizen safety, flood hazard reduction, and natural resource protection at the strategic level, while tactical
LOS directed maintenance, minor rehabilitation, and replacement priorities.
1.1.2 Hydrologic and hydraulic analysis
Hydrologic and hydraulic conditions were evaluated using PCSWMM 2D and QGIS, with calibration
supported by a local rain gauge and the Town’s monitoring station (BV01). Hydrology was simulated with
the NRCS curve number method using conservative soil assumptions and the NOAA B rainfall distribution,
Attachment 1
McCormick Taylor Memos
Page 26
Section 3. Item # 1.
2
and watersheds were delineated from 2020 LiDAR with 10’ resolution in developed areas. Conveyance
piping was modeled without accounting for existing sedimentation or structural deterioration, but iterative
calibration against two major storm events included adjustments to roughness and entrance losses to
reflect assets’ field conditions. Model performance met CIWEM guidance for error tolerances, and
simulations were run for 10- through 100-year storm events under existing, proposed, and proposed with
future sea level rise conditions. Culvert and open channel analyses revealed deficiencies in SCDOT
subgrade freeboard and culvert headwater to depth ratios under existing conditions, identified capacity
improvements from ditch cleaning paired with culvert upgrades, and highlighted the need for downstream
improvements to prevent upstream backwater conditions.
1.1.3 Recommendations
The analysis demonstrated that proposed improvements significantly reduced inundation footprints and
lowered hydraulic grade lines, while future sea level rise scenarios also indicate improved flood conditions
based on modeled road flooding events between existing conditions and proposed retrofits with future sea
level rise conditions. Findings supported the prioritization of capital improvement projects based on
downstream conveyance capacity, choke points, and flood-prone areas, with four projects defined and
cost-estimated at the ditch and pipe level. Maintenance projects were divided into structural (rehabilitation
and replacement) and general O&M (inspections, cleaning, mowing, and minor repairs) categories, aligned
with Bluffton’s LOS framework. Several bullet points are provided in the report as general
recommendations for flood prevention policies for the town to consider.
1.2 G ENERALIZED FRAMEWORK REVIEW
The Heyward Cove study was conducted using a specific framework or order of analysis. The framework
includes the typical steps for drainage or flood studies, in which existing conditions are evaluated,
engineering models are built, and recommendations for improvement are made.
The primary steps in the Heyward Cove analysis include:
1. Background data gathering (desktop analysis)
2. Field data gathering (survey, asset inventory, conditions assessment)
3. Hydrologic analysis/modeling
4. Hydraulic analysis/modeling
5. Conceptual improvement project development and implementation
In many cases, a similar framework should be used to evaluate vulnerability to flood-related hazards. In
others, portions of this framework can be reduced or eliminated. Some specific aspects of the framework
can also be used to inform regulations aimed at reducing flooding or protecting against future stressors.
In the following sections, each aspect of the framework is discussed with a description of the utility of the
findings as related to regulation.
Attachment 1
McCormick Taylor Memos
Page 27
Section 3. Item # 1.
3
1.2.1 Background data gathering
Engineering background data was collected to support modeling and recommendations. These data include
topographic, land cover, soils, rainfall, roadway, County GIS, and other peripheral data. The datasets listed
in the Heyward Cove report appear to be sufficient to support modeling and analysis.
These background data provide the needed insight into field conditions that are difficult or impossible to
obtain directly on-site at the project scale. For example, reliance on USDA for soils data at large scales is
common practice for H&H modeling. Additional background data regarding existing drainage and flooding
issues were also collected. These data are used to define the trajectory of the study and to identify focus
areas. Typically, known drainage issues are targeted for improvement in drainage studies to allow the
analysts to limit the project scope to a manageable and cost-effective scale.
Application to other sites : Most of this background data is typically available on demand through local,
county, state, and federal agency websites. Some datasets, for example SCDOT’s web portal for historic
plans, require login credentials and a subscription fee. Some gauge data, due to the limited number of
gauges deployed by federal agencies (e.g., USGS), are available for purchase from private enterprises or
through partnerships. For example, the SC Office of Resilience (SCOR) has partnered with Clemson
University for a pilot project to deploy 125 water level gauges at bridge crossings and other key locations in
the Upper Savannah and Saluda watersheds. Those gauges are intended to help fill in local data gaps in
flood monitoring. Private industries (such as Hohonu and CoCoRaHS) also offer partnering opportunities for
locally deployed water level and precipitation sensors and monitoring platforms.
For broader adoption, the collection, synthesis, and delivery of these background data should be required
as they will be used for most levels of analysis from conceptual planning to final design. Background data
can take the form of locally obtained or generated datasets (e.g., the Town’s wetlands data generated as a
part of this study), or state and federal agency data (e.g., National Land Cover Dataset, NLCD). When locally
generated or obtained background data is available, that should take precedence over larger-scale agency
data. This means that, for example, local land cover data if available is preferrable to NLCD. This is related
to the different scales at which these data are generated. Federal and state data are often less granular and
may miss prominent landscape or hydrologic features when applied to the local scale. If local data is
unavailable or unobtainable (due to time, funding, or other constraints), agency data should be used with an
understanding of the tradeoff between confidence in model/analysis results and data precision. For the
Heyward Cove study, local rainfall and water level data was obtained for model validation. A similar data
source prioritization is recommended with field monitoring data which is discussed in the next section.
Locations of existing drainage or flooding concerns can be obtained from several sources including internal
Town knowledge, feedback gathered from public meetings, and service or maintenance requests to the
Town and agencies (e.g., local SCDOT maintenance office) from residents. These sources collectively
provide insight into recurring drainage problems, and a catalog of known drainage issues can be developed
at a Town-wide scale prior to conducting detailed H&H studies such as the Heyward Cove study. The
information collected may document a wide range of flooding conditions, from small-scale nuisance issues,
such as ponded water in a front yard or driveway, to large scale events that result in road closures or
widespread property damage. Identifying known flooding areas along with the nature, severity, and
Attachment 1
McCormick Taylor Memos
Page 28
Section 3. Item # 1.
4
frequency of flooding provides a better understanding of the existing system. This allows consultants to
better prepare project scopes, reduce the costs and turnaround times of future drainage studies, and
identify areas for capital improvement projects.
Application to regulatory requirements: Background data collection and synthesis will inform resilience
zones, buffers, and protection areas by establishing baseline conditions and a scientific understanding of
the environmental conditions. Background data gathering is, in part, being completed as part of the current
project through the compilation and creation of GIS layers.
Data on known flooding problems in Bluffton were collected as part of the Town’s Sea Grant Resilience
Planning stakeholder involvement. A flood reporter survey was created using Survey123, an ArcGIS
software, to document past floods experienced by residents. The survey collected data on the location,
timing of flood events, as well as water depth and movement. Paper surveys were also distributed, and
residents were able to identify flood locations in person at Town hosted public meetings. An ArcGIS data
layer was developed with the flood information collected through the various methods. Data on existing
drainage and flooding issues is also being continuously collected by residents using the SeeClickFix
application, which allows users to report issues directly to the Town. These submissions are routed to
OpenGov Enterprise Asset Management (formerly Cartegraph) where they can be evaluated and tracked.
Dedicated reporting tools such as this application are often one of the most effective ways to identify
existing flooding or drainage concerns as residents can report issues in real-time with location specific
information and include photos or videos of the extent of flooding. In addition, the Town may choose to
distribute annual or quarterly flood surveys to residents to ensure broader community participation and
capture feedback from potentially underreported areas. The Town’s catalog of reported drainage and
flooding issues can help identify areas of recurring problems which can be used to prioritize study areas and
focus resources on locations with the greatest need.
1.2.2 Field data gathering
Field data collected includes an inventory of drainage assets and assessments of the condition of those
assets. Stormwater infrastructure assets include inlets, pipes, culverts, channels, and streams, and the
attributes and condition of those assets represent the existing stormwater conveyance network. Existing
conditions assessments are conducted for any drainage study to establish a baseline which is later
compared against proposed improvements to demonstrate and quantify impacts of projects. When
evaluated at the built-infrastructure scale, detailed field inventory is needed. This data is critical to model
the drainage systems to identify areas of concern and opportunities for maintenance and improvement. In
the event an infrastructure asset is inaccessible either due to property access restrictions or being
submerged, typically engineering-based assumptions are justifiable for planning level studies. For final
design, full field data is typically needed. This may require advanced surveying techniques such as divers or
vessels to access submerged areas. Right of entry or eminent domain letters from the Town may be needed
to grant surveyors access to property for data collection. The cost associated with these in-depth measures
is not warranted for planning level assessments, but for final design and construction phases, those costs
are warranted. These decisions are site and project specific. In some cases, novel approaches may be
employed for data collection. For example, if an entire drainage system is flooded, limiting data acquisition,
it is possible to select a downstream limit, insert an inflatable bladder, and dewater the system above the
Attachment 1
McCormick Taylor Memos
Page 29
Section 3. Item # 1.
5
bladder so that visual observations could be made. The cost of such efforts needs to be balanced with the
desired outcomes and the impact of reduced precision.
Application to other sites : An inventory of assets will be needed for projects that involve changes to the
built stormwater management system. Similar field data is needed when investigating natural drainage
systems. The inventory data is used by hydraulic modelers to calculate key design parameters including
water surface elevations, velocities, flow capacity, and others. These data are also required for final design
and construction projects to develop design plans and details. However, for planning projects and studies,
survey grade inventories may not be necessary. Hydraulic modelers and designers can assist with
determining site-specific minimum data needs to support their analyses tailored for the purpose of the
particular study or planning effort. Oftentimes, reasonable assumptions can be made to limit the need for
detailed field inventories depending on the scale and purpose for the study. For example, large-scale
regional planning studies will be minimally affected by residential driveway culvert performance.
Relating to scale, built systems are designed to convey stormwater up to a specified design storm event.
For example, SCDOT roadside drainage is typically designed to convey the 10-year (10% chance) storm.
For larger or higher intensity storms, those systems become ineffective, and larger conveyance pathways
(e.g., entire roadway sections) become more important. This means that for projects that aim to address
flooding from larger storms, greater than the 25-year event, detailed field inventory may not be necessary.
Ultimately, the decision to conduct a detailed asset inventory depends on how the information will be used,
whether it is intended to inform planning studies, support resilience modeling, or, as a secondary use, to
identify maintenance and capital improvement projects based on a system’s current condition and age.
Often the data gathered to build a model can have secondary benefits such as populating an asset
management plan with maintenance needs or with assets nearing their end-of-life cycle. This offers an ideal
time to accomplish two tasks under one project.
Application to regulatory requirements : The asset inventory and conditions assessment at the
neighborhood scale is necessary to build models that will identify hazard vulnerability. Full inventories may
not be necessary when examining large-scale drainage pathways and vulnerability. For example, impacts
of sea level rise can be assessed based on projected ocean levels and topography and details of the local
drainage network will add very little to the understanding of sea level rise impacts on a large scale. If
neighborhood-scale vulnerability is desired, detailed inventory is needed to the extent required by the
hydraulic analysis. Outside of its use in hydraulic modeling, asset inventories and conditions assessments
also provide valuable data for policy development and updates, help to identify partnership and funding
opportunities, and support budget planning and capital improvement programs.
1.2.3 Hydrologic analysis and modeling
The Heyward Cove study used the USDA NRCS methodology (Curve Number method). An SCS Type-III
rainfall distribution was assumed. Area weighted curve number was calculated using USDA soils data and
NLCD for land cover.
Application to other sites : The NRCS method is standard practice for infrastructure scale modeling.
However, more recently NOAA rainfall distributions are favored over SCS distributions and should be used
Attachment 1
McCormick Taylor Memos
Page 30
Section 3. Item # 1.
6
for most analyses. Additionally, runoff-weighting should be considered over area-weighting when
determining a composite curve number.
NLCD land cover data is commonly used for planning level studies. If local land cover, zoning, or other higher
resolution local data is available, that should be used since NLCD data is at a resolution of 30 meters and
may oversimplify local runoff potential for small-scale investigations.
In addition to the hydrologic conditions used by the Heyward Cove study authors, other rainfall distributions
and durations should be evaluated. For example, a short-duration, high-intensity storm in developed
watersheds or ones with unfavorable soils can be more damaging than the standard 24-hour storm.
Additionally, varying levels of build-out scenarios should be modeled against the varying storm intensities
and frequencies. Current land use and ultimate build-out land use should both be considered when
assessing future conditions. A no-action scenario should also be considered which combines existing
control measures with future climate stressors including sea level rise and changing storm characteristics.
These various scenarios can 1) demonstrate the value of implementing improvements, 2) assess impacts
of potential projects, 3) project future performance of existing and proposed mitigation measures, and 4)
project the impact of future land development against an array of stormwater and flood control
management measures. Depending on the time horizons for implementing mitigation measures,
intermediate build-out scenarios should also be considered. Defining the “future year” to be assessed is a
key decision during project planning and will be based on the specific goals and targeted outcomes of
individual studies and projects.
Application to regulatory requirements : The hydrologic analysis can be conducted for other portions of
the Town to assist with identifying resilience zones. Identified drainage areas, flow pathways, groundwater
conditions, etc. can inform the Town of areas that will generate higher runoff as well as areas that may be
leveraged for stormwater management. Additionally, the Town’s larger watersheds can be refined by
evaluating local drainage pathways to create more refined resilience zone boundaries. If hydraulic analysis
is to be conducted, hydrologic analysis will be needed. The hydrologic analysis, similar to the field inventory,
can be limited depending on scale and project needs.
1.2.4 Hydraulic analysis and modeling
The hydraulic analysis included an integrated 1D/2D PCSWMM model of the Heyward Cove drainage
network. The model included the pipe and channel conveyance system as well as the overland flow
generated from subcatchments. The model used a tidal downstream boundary condition. The model was
calibrated for flow and stage at two simulation times. The models were run for three scenarios including the
existing system, proposed system (based on recommended improvements), and the proposed system with
future (2073) rainfall depth predictions and sea level rise (Resiliency Model Condition). Conveyance
features were assessed for key performance metrics such as headwater depth at culvert crossings at key
locations.
Application to other sites: PCSWMM is a powerful modeling tool and can be leveraged to assess a variety
of hydrologic and hydraulic scenarios and small and large scales. The Heyward Cove study report includes
details on the specific modeling approaches, with many being standard practice. Hydraulic modeling
Attachment 1
McCormick Taylor Memos
Page 31
Section 3. Item # 1.
7
involves targeted simplifications, assumptions, method selections based on a combination of project
purpose, experience, and site-specific conditions. The details of the modeling approach appear to be well
justified, but a critique of those would require a full understanding of the conditions at Heyward Cove.
For some situations, 1D/2D modeling is likely the best way to represent the field conditions. The 2D
(overland flow) components of the modeling take many forms in practice and can be developed in several
ways. For example, the overland flow can be exclusively generated from a back-up of the 1D conveyance
system, or overland flow can be directly generated from rainfall at the 2D mesh cale. Rainfall at this scale
is termed “rain-on-grid” and involves resolving the full connectivity of the overland and built infrastructure
system within the model.
The future conditions analysis in the Heyward Cove study included future sea level rise and the updated
NOAA B rainfall distribution. These are important components to evaluate, though additional stressors can
be included. On the scale of Bluffton’s drainage basins, future changes to land use due to build-out of
development agreement sites should be included. Reasonable assumptions as to the density, impervious
cover, etc. of those developments can be made to create a model scenario reflecting future climate and
development conditions. Changes to precipitation intensity should also be considered. Currently, NOAA is
finalizing updates to published rainfall depths for storm recurrence intervals, and throughout the majority of
South Carolina those values are increasing. Future changes to temperature, vegetative uptake,
groundwater, and land subsidence can also be reflected in future-conditions scenarios if deemed
significant for a particular location and planning effort.
Generally, future conditions models should include future climate stressors, future land cover, and future
management practices. Future stressors include sea level rise and changing storm characteristics. These
include higher-intensity, shorter-duration storms as well as long-duration events. Future land cover should
include the ultimate build-out of the expected future developments. Future management practices should
include both the future performance of existing management practices as well as new practices when
exploring improvement alternatives.
Application to regulatory requirements : Pluvial flooding vulnerability can best be assessed through
hydraulic analysis of the drainage system. This can include both built and natural drainage systems using
varying levels of model sophistication. In some cases, simple analyses using spreadsheets or hand
calculations may suffice – particularly for individual drainage assets or roadside drainage. In other cases,
full two-dimensional modeling best represents the interplay of overland and drainage system stormwater
flows. The models in all cases can identify system pinch points, vulnerabilities, and improvement
opportunities. These can help refine resilience zone boundaries at a local level.
1.2.5 Conceptual improvement project development and implementation
Based on the evaluation of the existing model, areas of concern were identified, and improvement projects
were proposed. The level of service improvements were quantified, and reduction in flooding was
determined. Improvement projects were categorized into capital projects and maintenance programs.
Importantly, project dependency was identified. Costs were estimated to implement the project, and a
discussion of the projects was included. Conceptual-level displays were presented in the report.
Attachment 1
McCormick Taylor Memos
Page 32
Section 3. Item # 1.
8
Application to other sites : The strategy of the Heyward Cove report generally follows common practice
and can be applied elsewhere. Although considered when developing project recommendations, a
discussion of implementation hurdles should be included with each project to include permit needs,
easements/ownership, maintenance, and potential for community buy-in. Additionally, benefits can be
quantified using FEMA’s Benefit/Cost Analysis (BCA) methodology based on H&H modeling. While
generally difficult to quantify and costly to develop due to the need for detailed flood data, the inundation
maps produced through the modeling efforts, like those developed for Heyward Cove, can streamline the
analysis. Quantifying the project benefits helps with securing capital by making the project eligible for grant
funds for future project implementation, potentially outweighing the initial investment.
Application to regulatory requirements: Along with new improvement projects, recommendations could
include retrofits or improvements to existing stormwater management facilities or natural storage areas and
conveyances. Identifying where these opportunities exist can help inform resilience zone planning by
identifying parts of Town that may be at full capacity in terms of stormwater management versus areas that
have reserve capacity.
1.3 A PPLICATION OF HEYWARD COVE FINDINGS
The findings of the Heyward Cove study can be applied to recommended first floor elevations for the purpose of
flood protection. The study authors developed inundation maps based on their H&H models which depict flood
depth for various design storms.
As will be discussed in Section 2 of this memo, the Town currently requires flood damage protection in accordance
with the National Flood Insurance Program (NFIP) for development within FEMA special flood hazard areas (SFHA).
However, FEMA stops delineating SFHAs at a certain scale of tributary, even though upstream areas may still face
flood risks. Consequently, this means that the absence of a SFHA for a drainage ditch or stream does not guarantee
that flooding or damaging flooding will not occur. As a result, the Town can choose to develop comparable
requirements for development outside of SFHAs. For these areas, locally generated flood models can be used to
establish flood risk, similar to the procedure of the Heyward Cove study. To ensure that additional burdens are not
placed on developers and property owners, the same level of protection should be required inside and outside of
the SFHA. This means that first floor elevations should be elevated to the local base flood elevation (BFE) plus
freeboard (3 ft currently for Bluffton).
The analysis procedure will be as follows:
I. Determine if the development/redevelopment site is within the FEMA SFHA.
a. If within the SFHA, the Flood Damage Prevention Ordinance applies.
b. If outside of the SFHA, a local comprehensive drainage study is needed.
II. If outside of the SFHA, the applicant should prepare H&H models to generate a 100-year flood map for the
area.
a. Specific modeling requirements will depend on the site and type of development (e.g., single-family
lots, multifamily dwellings, commercial buildings), but the flooding from the nearest flood source
Attachment 1
McCormick Taylor Memos
Page 33
Section 3. Item # 1.
9
as well as any compound flooding effects (e.g., multiple cresting riverine sources or riverine plus
coastal flooding, etc.) is required.
b. Future conditions assessments may be considered as well but will require guidance from the Town
as to the appropriate future conditions scenarios (i.e., sea level rise only, sea level rise plus
buildout, etc.)
III. If the proposed structure is within the locally generated 100-year flood plain, flood damage protection
including elevation of the first floor will be required.
2 E XISTING BLUFFTON CODES SUMMARY
The Town of Bluffton regulates all development within FEMA-designated Special Flood Hazard Areas (SFHAs)
through a permitting process that requires scaled site plans, elevation data, and professional certifications for new
or improved structures. Development is prohibited in floodplains if alternative locations exist, and projects that
affect floodways, base flood elevations (BFE), or watercourses must obtain FEMA Conditional Letters of Map
Revision (CLOMRs) before construction and submit as-built certifications upon completion, which require
professional engineer certification. General floodplain development standards require anchoring, flood-resistant
materials, and utility protection to BFE +3 ft. The first floor of residential, non-residential, and manufactured housing
construction must be elevated at least one foot above the adjacent roadway centerlines or three (3) feet above BFE,
whichever is higher, and enclosures below BFE are limited to non-habitable uses with flood openings provided to
relieve hydrostatic pressure. Critical development (hospitals, fire stations, etc.) elevations must meet or exceed the
500-year flood elevation or the highest known historical flood.
Additional provisions address a wide range of development scenarios to ensure flood risk is minimized across the
community. Floodways prohibit encroachments unless certified as “no-impact” and Coastal High Hazard Areas (V-
Zones) require pile or column foundations with breakaway walls to accommodate wave action. Recreational
vehicles (RVs) are only permitted if temporary, road-ready, or compliant with manufactured housing standards,
while accessory structures and utility rooms must be anchored and floodproofed according to FEMA guidance.
Subdivisions, streams without mapped BFEs, shallow flooding zones, and coastal hazard areas all have tailored
requirements mandating hydrologic and hydraulic studies when necessary.
The Town of Bluffton has also adopted the Southern Lowcountry Stormwater Design Manual (SoLoCo manual) to
address post-construction stormwater management. The SoLoCo manual has designated three separate
watershed protection areas with unique stormwater management requirements based on the current and
anticipated water quality control measures for their contributing watersheds. The Town falls within the Bacteria and
Shellfish Watershed Protection Area, and therefore any applicable new development, redevelopment, or major
substantial improvement must meet the following performance requirements.
• Water Quality: Implement Better Site Design (BSD) and retain the 95th percentile storm on-site with
approved infiltration/filtering BMPs. Fulfill MEP requirements or, as a last resort, fulfill off-site credit
and/or fee-in-lieu requirements.
• As a pollutant removal minimum, intercept and treat stormwater runoff volume to at least an 80%
reduction in total suspended solid loads, 30% reduction of total nitrogen load, and 60% reduction
in bacteria load.
Attachment 1
McCormick Taylor Memos
Page 34
Section 3. Item # 1.
10
• Peak control: Control the post-development peak runoff discharge rate for the 2, 10, 25, 50, 100-
year, 24-hour design storm events to the pre-development discharge rates.
• Accommodate the 100-year, 24-hour storm event conveyance through the site and downstream
without causing damage/inundation to structures. Provide 10% rule analysis.
2.1 B LUFFTON CODES RECOMMENDATIONS
After reviewing the existing Bluffton flood protection codes, MT has developed a series of recommendations
regarding 1) compensatory floodplain storage needed to avoid upstream/downstream impacts, and 2) methods to
demonstrate a no impact designation for construction. The existing code regarding structures’ first-floor elevations,
as well as the existing code for elevated “flow through” construction approaches was determined to be comparable
to other vulnerable communities and therefore no additional changes are recommended at this time
2.1.1 Compensatory floodplain storage
Compensatory floodplain storage is the excavation or creation of equivalent floodplain volume to offset the loss of
storage caused by filling or development, ensuring flood levels are not increased. MT recommends a 1:1 cut to fill
ratio for compensatory storage to ensure that any loss of flood storage capacity from development is offset. This
standard would require that for every unit of fill placed in the floodplain, an equal volume of storage is excavated
within the same flood zone (e.g., compensatory storage in zone AE-9 must be provided for fill within zone AE-9). Fill
volume within a flood zone is defined as the post-development lost storage volume within the flood zone. This can
be measured by the volume of the wedge of fill material that is placed from existing ground elevation up to the
effective BFE. The ideal excavation for floodplain storage is at the same river station as the floodplain fill, on the
opposite side of the stream/floodplain source as the fill. If this is not possible, the next best alternative is upstream
on the same side of the stream as the fill, prioritizing proximity to the fill area. Compensatory storage located
downstream of the fill will not be effective, because under the hydraulic flow conditions typical of this region,
additional downstream storage cannot offset the choke point created by the fill. In parts of the Town where officials
have observed high rates of floodplain development, MT recommends considering a 1.5:1 cut to fill ratio for new
developments/redevelopments to reclaim floodplain storage.
2.1.2 No-Impact Certification
The purpose of a no-impact designation for construction is to ensure development is not contributing to increased
flood risk of adjacent properties and the community. MT recommends different regulations based on the property’s
location with regard to FEMA flood zones. For development within a FEMA flood zone, MT recommends a hydrology
study to show no increase in peak discharges or volumes from a range of storm events from the 2-year to the 100-
year. If the 100-year storm post-development hydrology shows an increase in peak discharges or volumes
compared to pre-development hydrology, a rise of nearby BFEs is likely. In this case, a full engineering study
conducted by a professional engineer is needed to obtain a no-impact certification. The Town of Bluffton requires
that post-development peak runoff discharges do not exceed pre-development conditions for the 2-, 10-, 25-, 50-,
and 100-year, 24-hour storm, however, the current regulations do not require stormwater volume control for the
higher storm events (10-year and greater). Peak rate control maintains the same or lower peak discharge under
proposed conditions when compared to existing. To achieve this standard when proposed conditions generate more
runoff, stormwater management practices are installed, which lower the peak discharge, but elongate the peaking
time. That is, the post-development peak discharge is sustained for a longer period of time. The consequence of
extended peaking times is that the sites that drain to the same watercourse may now have coincidental peaks.
Attachment 1
McCormick Taylor Memos
Page 35
Section 3. Item # 1.
11
Although both sites maintain peak discharges at or below predevelopment values, the extended peaking times could
overlap, resulting in flood conditions. Because of this, modeling of the entire watershed is often critical so that
overlapping or delayed peaks can be identified and addressed. It is not practical to provide volume reduction for
large storm events such as the 100-year event, though it would help manage this potential issue. One effective
method is to incorporate the various Town watersheds into a master watershed model at a coarse scale.
Information from site-specific models can be input into the master model to evaluate broader impacts.
Part of the no impact certification is accounting for downstream impacts that can occur due to cumulative
developments in a watershed. Currently, the Town requires the applicant to demonstrate via the 10% rule described
in the SoLoCo manual that there are no negative impacts to the 10% downstream reach of the property. While this
is a reasonable approach, MT recommends instead that the Town’s floodplain manager, stormwater manager, or
comparable municipal official identifies and approves the location of a downstream impact point. The downstream
impact point should be set at a confluence, bridge, or culvert, since these hydraulic controls strongly influence water
surface elevations and flow conditions and should be selected based on knowledge of the overall watershed,
sensitivity of the watershed, and planned development. If it is found that there is an impact at the downstream
analysis point requiring, for example, upsizing a drainage feature, the downstream analysis should be extended
farther downstream including the proposed upgrades. This should continue downstream until no impact is achieved.
Adverse downstream impacts are often seen in the form of a shortened time of concentration, which is the time it
takes for runoff from the most distant point on a parcel to travel to the parcel’s outlet. If enough parcels
independently decrease their time of concentration, it will result in higher discharges and water surface elevations
downstream not seen with a parcel-by-parcel analysis. If officials are concerned with a development’s downstream
impact based on overall watershed development trends, they should require a development to show no increase in
peak discharges and volumes for a less frequent storm event, regardless of FEMA flood hazard zone boundaries.
2.1.3 Additional recommendations
As an alternative to subdividing areas based on proximity to the FEMA floodplain and flood sources, the Town may
prefer to designate development and environmental regulations based on proximity to streams by stream order. As
part of this project, MT has categorized the drainage pathways in Town by stream order. First and second order
streams are considered headwater streams and collect and convey stormwater from relatively small areas. Higher
order streams must convey runoff from larger areas and the contributing low-order streams. Generally, protection
zones should focus on higher order streams when limited opportunities exist. This will have a broader impact than
protections along headwater streams. Opportunities for protection or regional solutions should be focused on
higher-order streams.
Due to the terrain of Bluffton and existing development agreements, providing compensatory floodplain storage at
a parcel-by-parcel or even at the neighborhood level may be problematic. If space does not exist for compensatory
storage, the developers should first investigate alternative site designs to minimize lost storage volume. Limitations
to the developable area may be needed and the same weight provided to downstream flood prevention as to what
is provided for stormwater management requirements and the required set aside property within a development to
meet those requirements. These limitations further stress the importance of a holistic watershed model that
considers sub-watersheds, existing stormwater management systems, and the impact the proposed development
will have on this system. This is sometimes not possible depending on the existing development agreements. As an
alternative, the Town could identify regional opportunities for flood storage on Town owned properties or through
Attachment 1
McCormick Taylor Memos
Page 36
Section 3. Item # 1.
12
drainage easements. As development takes place, developers could be required to contribute to the enhancement
of the receiving systems, specifically at those regional countermeasures. For example, funds from these imposed
fees could be used to design and construction regional stormwater management projects, and cover the costs
associated with site selection, engineering design, property, easement, or right-of-way acquisition, construction of
the stormwater management facilities, as well as any necessary upgrades, enhancements, or maintenance. While
the Town does not commonly experience repetitive loss, the funds could also be used to buy out flood-prone
properties. An additional option would be to utilize these funds to purchase undeveloped properties or portions of
properties that are adjacent to riverine systems to be placed into perpetual conservation easements, similar to the
SC Office of Resilience Buyout Program.
Attachment 1
McCormick Taylor Memos
Page 37
Section 3. Item # 1.
1
MEMORANDUM
To: Town of Bluffton Project Team, Attn: Beth Lewis & Andrea Moreno
From: McCormick Taylor
Date: 5/3/2026
Project: Town of Bluffton – Wetlands and Resiliency Ordinance
Subject: Task 3.3 – Primary Conveyance Systems
Data Summary
This memorandum summarizes the methodology for classifying the Town of Bluffton’s primary conveyance
systems. The data package included with this submission contains four separate shapefiles. The “Streams”
shapefile contains all the streams with a stream order attribute. The “Nodes” shapefile represents the
junctions between stream segments. The “Outfalls” shapefile represents the outfall locations around the
Town of Bluffton. Lastly, the “Streams by Outfall” folder contains all the streamlines separated by outfall.
Stream Order Classification Background
Streams can be classified using a variety of methods. A common approach is to classify streams by
hydrology, or flow duration, as either ephemeral, intermittent, or perennial, or by morphology using the
Rosgen stream classification system. Stream order is another method which classifies streams based on
their relative size and position within the watershed, where each link within a stream network is assigned a
numeric number. In this system, first order streams are the smallest, fed primarily by overland flow rather
than upstream tributaries. Stream order increases as tributaries merge, with streams becoming larger and
wider as they drain a larger watershed area. The upper reaches of a stream network, referred to as
headwater streams, typically include first- and second-order streams, though it often depends on
watershed size and characteristics, and can sometimes include third-order streams. Typically, fourth
to sixth-order streams are considered medium sized streams, and seventh -order streams and
above constitute larger riverine systems.
Classifying a waterways stream order can provide insight into its role in the drainage network and can
provide an indication of the relative significance of a waterway to the overall conveyance. For example,
conveyance reduction within a higher-order stream will translate to reduced conveyance of all lower-order
streams feeding into it. Stream order can also help identify a stream’s potential vulnerability to
environmental stressors. Headwater streams, for example, are dominated by overland flow, and are
therefore particularly susceptible to non-point source pollution. Since headwater and higher-order streams
are characteristically different, stream order can be used to improve riparian buffer best management
practice (BMP) guidelines and inform future policy updates. For instance, establishing or strengthening
riparian buffer regulations for headwater streams can improve local water quality and reduce the potential
pollutant load throughout the downstream network. Additionally, because higher -order streams typically
carry larger volumes of water, establishing regulations that protect the conveyance capacity of high-order
Attachment 1
McCormick Taylor Memos
Page 38
Section 3. Item # 1.
2
streams will also protect the conveyance capacity of lower -order stream, helping to mitigate potential
flooding.
There are two conventional methods for assigning stream order: the Strahler (1957) method and the Shreve
(1966) method, though other methods exist.
Strahler method
The Strahler method is the most common method for stream ordering. Under this method, all stream links
without any tributaries are assigned an order of one and are referred to as first -order links. Stream order
increases when streams of the same order intersect. For example, the intersection of two first -order links
creates a second-order link. However, the intersection of two links of different orders will not result in an
increase in order. For example, the intersection of a first-order and second-order stream will retain the order
of the highest ordered link and will therefore be classified as a second-order link.
Shreve Method
Similar to the Strahler method, the Shreve method assigns an order of one to all exterior links. However,
unlike the other method, the orders are additive. For example, the intersection of a first -order and second-
order stream link would create a third-order link. Due to the additive nature of this method, instead of stream
orders, they are often considered stream magnitudes.
Methods for Classifying the Town’s Conveyance Systems
McCormick Taylor used the Strahler method to classify the Town’s stream networkas it is the most widely
used stream classification system and establishes a hierarchical structure based on a streams relative size
within the drainage network. The stream network to be classified was obtained from USGS StreamStats .
While there is channel and stream data mapped for two drainage basin s within the Town, Heyward Cove
Figure 1: Visual representation of the two stream order methods.
Source: ArcGIS https://pro.arcgis.com/en/pro-app/3.4/tool-reference/spatial-analyst/how-stream-order-
works.htm
Attachment 1
McCormick Taylor Memos
Page 39
Section 3. Item # 1.
3
and Guerrard/Crooked, the rest of the Town lacks a complete streamline dataset. USGS StreamStats
streamlines are derived from digital elevation models (DEMs) and flow accumulation analysis. While they
may not necessarily represent true streams, the data depicts potential flow paths, creating a continuous
line through features such as lakes, ponds, and culverts. The streamlines from USGS StreamStats were not
modified for this analysis, except for minor corrections to connectivity resulting from the USGS delineation
procedure and DEM resolution. The outer town boundary was used to clip the USGS linework, however the
order of streams flowing from outside of the Town boundary into the Town were included.
Stream Order Results
Figure 2: Town of Bluffton stream order map
Attachment 1
McCormick Taylor Memos
Page 40
Section 3. Item # 1.
4
The streams within the Town ranged in order from one to five (Figure 2). Headwater streams, (first- through
second-order) comprise approximately 69% of the 321 total stream miles. There are two fifth-order streams
within the Town, the New River and May River, which comprise approximately 10% of the total stream miles
(Table 1).
Table 1: Stream length by stream order.
Stream Order Stream Miles Percent of Total
1 141.75 44.09%
2 80.41 25.01%
3 50.3 15.65%
4 17.07 5.31%
5 31.95 9.94%
Total 321.48 100%
The analysis identified 13 outfalls, defined as locations where a stream network conveys flow outside of the
Town boundary. Stream networks vary considerably in size and are listed in Table 2. The largest stream
networks are those draining to outfalls 1 (OF01) and 3 (OF03) along the New River and May River, respectively.
Table 2: Stream length by outfall.
Outfall Stream Miles
OF01 111.44
OF02 31.09
OF03 112.65
OF04 0.28
OF05 8.61
OF06 10.72
OF07 2.32
OF08 1.93
OF09 25.30
OF10 3.05
OF11 1.73
OF12 2.39
OF13 9.96
Total 321.48
Riparian Buffer Recommendations
McCormick Taylor reviewed the Town of Bluffton’s current riparian buffer ordinance and the available literature
to provide recommendations for implementing riparian buffers based on stream order.
Attachment 1
McCormick Taylor Memos
Page 41
Section 3. Item # 1.
5
Current Town Ordinance
Bluffton’s current ordinance concerning riparian buffers is summarized below and can be found in Section 5.5 of
the UDO- Natural Resources: River Buffer.
The ordinance applies to all building, development, redevelopment and site alteration of any land within
100 feet from the South Carolina Office of Ocean and Coastal Resource Management (OCRM) Critical
line adjacent to tidal wetlands and waterways in and around the Town of Bluffton. This area shall not
exceed 40% of the area of the lot provided that no disturbance is closer than 25 feet to the CORM Critical
Line unless expressly permitted in Section 5.5.3.
Under 5.5.3, all vegetation, ground cover, understory trees and shrubs and overstory trees shall be
retained throughout the entire buffer. Removal of the existing vegetation shall only occur to
accommodate the following:
1) To accommodate views, one-third of the total buffer zone area can be selectively trimmed
and landscaped to provide a view between a height of 2 feet and 20 feet measured from the
adjacent grade provided that no more than a maximum contiguous area measuring 75 feet
in horizontal distance parallel to the critical line is selectively trimmed and landscaped at
any one location, separated by a matching undisturbed buffer. Selective landscaping shall
include native understory and groundcover plantings that do not require chemical
treatment for survival or maintenance.
Provided that the minimum land area required to serve the purpose is used, no development is permitted
in the buffer with the exception of the following uses:
1) Pedestrian and/or vehicular access ways leading to docks, fishing piers, boat landings, other
access way, or other approved water/marsh uses, provided that only permeable or semi-
permeable paving materials are used.
2) Docks, fishing piers, boat landings, or other approved water/marsh uses that by design must tie
into the high ground adjacent to the marsh/water.
3) Flood control devices, erosion control devices, and other activities related to soil and water
conservation
4) Utility lines, including irrigation, which must cross the buffer shall be buried and any disturbed
area shall be replanted with vegetation.
5) Roads leading to bridges or causeways that cross the waterway provided the roads are
configured to minimize disturbance into and within the buffer, and provided all shoulders are
vegetated.
Riparian Buffer Literature
Riparian buffers provide numerous benefits. They improve water quality by intercepting pollutants before they
enter waterways, stabilize stream banks, provide shade that lowers in stream temperatures, and provide food
sources and habitat for wildlife. Riparian buffers also serve as effective stormwater controls, providing important
water quantity benefits such as floodwater storage, groundwater recharge, and runoff velocity reduction
(Environmental Protection Agency, n.d.). Buffers help slow the movement of water in the upper reaches of a
watershed, providing water in larger segments downstream more time to move through the system and flush out.
They reduce erosion and trap sediment that would otherwise accumulate in stream channels, decreasing
Attachment 1
McCormick Taylor Memos
Page 42
Section 3. Item # 1.
6
channel capacity and contributing to additional flooding. Riparian buffers also help protect floodplains from
development for non-FEMA mapped streams.
There are multiple types of buffers that can be implemented such as variable width buffers, fixed width buffers,
or zoned riparian buffers. A variable width buffer considers individual site factors in determining buffer width like
slope or erodibility while fixed width buffers are the easiest to enforce and tend to be more conservative. A zoned
riparian buffer system consists of two to three zones with various widths and allowable uses. A three-zone
system is commonly used in the Chesapeake Bay region. Zone 1 or the streamside zone typically extends 15 to
30 feet from the top of bank on either side of the stream and remains forested and undisturbed. Zone 2 or the
middle core extends an additional 30 to 100 feet. Minimal uses are typically allowed in this zone, and the native
vegetation is maintained. Zone 3, or the outer zone, usually extends another 20 to 30 feet. This zone is typically
maintained as grass and designed to act like a vegetated filter strip, with most uses unrestricted (Cunningham,
n.d.; University of South Carolina [USC], 2000).
Numerous studies have provided recommendations on buffer widths for riparian areas, though individual site
characteristics such as slope, soil type, and vegetation will influence their effectiveness. Hawes and Smith
(2005) conducted a literature review on riparian buffer widths, which are summarized by function in Table 3. The
Natural Resource Conservation Service (NRCS) also provides recommended buffer widths based on function.
To reduce overland flow of sediment and organic matter, a minimum buffer width of 35’ is recommended. If
pathogens, chemicals, pesticides or nutrients are a concern, the buffer should be extended to 50’. Depending on
wildlife species habitats, a 50’ buffer is recommended for invertebrates, aquatic species, reptiles, and
amphibians, a 100’ buffer for birds needing interior habitat and small mammals, and a 165’ buffer for large
mammals (Natural Resource Conservation Service, 2020). Within South Carolina, the Department of Natural
Resources Scenic Rivers Program recommends a minimum buffer width of 50 to 100’ for water quality
protection, 100’ for aesthetic/scenic values, and between 100’ and 300’ for conserving and enhancing wildlife
diversity (South Carolina Department of Natural Resources, 2020).
Table 3. Riparian Buffer Widths taken from Hawes and Smith (2005)
Riparian Buffer Function Recommended Buffer
Widths (feet) Sources
Sediment Control
82-328 Wenger 1999
33-148 Army Corps 1991
30-200 Fisher and Fischenich 2000
49-213 Broadmeadow and Nisbet 2004
Nutrient Retention
50-100 Wenger 1999
52-164 Army Corps 1991
16.4-98 Fisher and Fischenich 2000
16.4- 98 Broadmeadow and Nisbet 2004
Aquatic Wildlife
98 Army Corps 1991
>98 Fisher and Fischenich 2000
33-164 Broadmeadow and Nisbet 2004
Stream Temperature
33-98 Wenger 1999
33-66 Army Corps 1991
49-230 Broadmeadow and Nisbet 2004
Bank Stabilization/Erosion
Control
49-98 Army Corps 1991
30-66 Fisher and Fischenich 2000
Attachment 1
McCormick Taylor Memos
Page 43
Section 3. Item # 1.
7
There are limited studies that provide recommended buffer widths specifically for water quantity control , as
hydrologic responses and the effectiveness of the buffers vary widely with topography, stream characteristics,
and other watershed -dependent factors (Figure 3) . One approach is to i mplement buffer widths based on
drainage area or discharge. In Greenville County, South Carolina, a 50’ buffer is required for all Waters of the
State, which increases to 100’ for all waters with a drainage area of 50 acres or more. Similarly, Savannah,
Georgia maintains a Protected River Corridor Buffer ordinance which sets a 100’ buffer for perennial streams or
watercourses with an average annual flow of at least 400 cubic feet per second, exceeding the state’s mandated
25’ buffer. While larger streams convey a greater volume of water, b uffers along smaller streams also play an
important role in downstream flood reduction (Palone and Todd, 1997).
Figure 3: Generalized effect of stream order on variations in buffer function.
Source: Palone and Todd (1997)
While most buffer ordinances are designed to protect larger rivers and tributaries, they dodo not always extend
protection to all streams. For example, in North Carolina, the Department of Environmental Quality only requires
riparian buffers for intermittent or perennial streams that appear on the NRCS Web Soil Survey or USGS Topo
map, which leaves unmapped streams, primarily headwater streams, unprotected. To provide protection for all
streams regardless of stream typeand provide adequate water quality and quantity control, buffer widths can be
implemented based on stream order. Using stream order ensures that vulnerable headwater streams near
development, as well as the rest of the stream network,are protected from point and non-point source pollution.
Simultaneously, using stream order allows for the implementation of wider buffers for higher-order streams to
account for the larger drainage areas.
Riparian Buffer Recommendations
The Town’s current riparian buffer ordinance only requires buffers for rivers/streams within the critical area which
leaves streams outside of the tidal area unprotected. McCormick Taylor recommendsthe following buffer widths
based on stream order . For first- and second-order streams, a two-zone system is recommended. As stream
Attachment 1
McCormick Taylor Memos
Page 44
Section 3. Item # 1.
8
order increases, wider buffers are necessary to protect water quality, stabilize stream banks, and provide flood
control. All buffer widths are measured from the top of bank on either side of the stream (Figure 4).
I. For 1 st and 2 nd order streams, a 50’ buffer is recommended with Zone 1 extending 35’ and Zone 2
extending an additional 15’. Allowable uses within the buffer shall be left up to the Town’s discretion. Is
it recommended that Zone 1 be left as undisturbed natural habitat. Zone 2 may be maintained as lawns
or gardens, however there should be no land-disturbing activities or impervious surfaces located within
this zone. Allowable uses within Zone 2 may include: establishing view corridors, removing invasive
vegetation, allowing pedestrian footpaths for docks, piers, and boat landings, and recreational activities.
If portions of the stream are tidally influenced and within the critical area, the Town’s existing 100’ buffer
ordinance should take precedence.
II. For 3 rd order streams, a 50’ buffer is recommended. The buffer should be left as undisturbed natural
habitat. If portions of the stream are tidally influenced and within the critical area, the Town’s existing
100’ buffer ordinance should take precedence. Allowable uses within the buffer should be limited to the
Town’s existing ordinance.
III. For 4 th order streams, including those tidally and non-tidally influenced, a 100’ buffer is recommended.
Allowable uses within the buffer should be limited to the Town’s existing ordinance.
IV. The 5 th order streams that were mapped within the Town likely fall within the SCDES critical area;
therefore, the Town’s existing riparian buffer ordinance should apply. Allowable uses should remain the
same.
Property owners should use the Town’s stream map to determine what order stream they have on their property
and therefore what buffer width applies. It is important to note on the map or website that the stream network
does not represent surveyed data and must be field verified to determine its precise location. If a stream is not
shown on the map but field verification has determined that is a Water of the State, the buffer widths for a 1st and
2nd order stream should apply.
Although the Town of Bluffton is largely developed, buffer ordinances should be enforced whenever building
plans for site improvements (patio, pool, detached structures) are submitted. In areas where the recommended
35’ buffer may not be feasible, likely near 1st and 2nd order streams, the Town may allow reduced buffers widths.
These exceptions should be established on a case-by-case basis provided that a grass filter strip is installed at
a minimum.
Attachment 1
McCormick Taylor Memos
Page 45
Section 3. Item # 1.
9
References
Environmental Protection Agency. (n.d.). Stormwater Best Management Practice: Riparian/Forested Buffer.
Environmental Protection Agency. Retrieved from:
https://www.epa.gov/system/files/documents/2021-11/bmp-riparian-forested-buffer.pdf
Cunningham, K. (n.d.). Riparian Buffers: Types and Establishment Methods. Report #FSA5-27. University of
Agriculture Research and Extension: University of Arkansas System. Retrieved from:
https://www.uaex.uada.edu/publications/pdf/FSA-5027.pdf
Hawes, E, and M. Smith. (2005). Riparian Buffer Zones: Functions and Recommended Widths. Yale School of
Forestry and Environmental Studies. Retrieved from: https://bolincreek.org/blog/wp-
content/uploads/2011/11/riparian.buffers.attachment3.pdf
Natural Resource Conservation Service. (2020). Conservation Practice Standard: Riparian Forest Buffer.
Retrieved from: https://www.nrcs.usda.gov/sites/default/files/2022-
09/Riparian_Forest_Buffer_391_CPS_10_2020.pdf
Palone, R.S. and A.H. Todd. 1997. Chesapeake Bay riparian handbook: a guide for establishing and maintaining
riparian forest buffers. USDA Forest Service. NA-TPTP-02-97. Radnor, PA. Retrieved from:
https://www.ecrr.org/Portals/27/Publications/watqual_doc7.pdf
South Carolina Department of Natural Resources (SCDNR) Scenic Rivers Program. (2020). Guide to Best
Management Practices for Riparian Lands. Retrieved from:
https://www.dnr.sc.gov/water/river/pdf/guide-riparianlands2020-aug.pdf
Zone 1: 20’Zone 2: 1515’
Figure 4: Example of a two-zone riparian buffer for 1st and 2nd order streams. Figure
adapted from www.deq.nc.gov
Attachment 1
McCormick Taylor Memos
Page 46
Section 3. Item # 1.
10
University of South Carolina. (2000). Final Report of the Statewide Task Force on Riparian Forest Buffers. USC
Center for Environmental Policy, Institute of Public Affairs. Retrieved from:
https://media.clemson.edu/public/restoration/carolina%20clear/toolbox/sctaskforcebuffersreport.p
df
We Conserve PA. (n.d.). The Science Behind the Need for Riparian Buffer Protection. Retrieved from:
https://library.weconservepa.org/guides/131-the-science-behind-the-need-for-riparian-buffer-
protection
Attachment 1
McCormick Taylor Memos
Page 47
Section 3. Item # 1.
To: Town of Bluffton Project Team
From: McCormick Taylor
Date: 3/30/2026
Subject: Task 3.4 – Resiliency Zone Mapping
Project: Town of Bluffton – Wetlands and Resiliency Ordinance
1 P URPOSE
Bluffton faces significant flooding risks due to its location along the May River, low-lying coastal setting, and
rapidly expanding development. Riverine flooding, also referred to as fluvial flooding, occurs when
prolonged or intense rainfall causes nearby creeks and tributaries to exceed their banks, particularly in low-
lying areas with limited floodplain storage. Pluvial flooding occurs during heavy rainfall events that
overwhelm local drainage systems and stormwater infrastructure, resulting in flooding due to lack of
stormwater system capacity. Coastal flooding poses a major concern for the Town because of the direct
connection to tidal waterways. Storm surge from hurricanes or tropical storms flow landward through
streams and drainage systems, inundating roads and homes. High tide flooding, especially during king tide
events, can occur even without rainfall, known as “sunny day flooding”. Coastal flooding issues can then
compound when high tides coincide with heavy rain, preventing runoff from draining effectively. Future
conditions sea level rise is expected to exacerbate coastal, fluvial, and pluvial flooding by elevating baseline
water levels, thereby increasing flood frequency and reducing the effectiveness of existing stormwater
systems and natural flood buffers.
To provide an additional layer of protection from flooding, more frequent and higher intensity storm events,
and projected sea level rise, the Town of Bluffton is interested in mapping and protecting “resiliency zones”.
Resiliency zones consist of undeveloped areas within the Town that can provide valuable services such as
storage for stormwater and flood waters, natural protection from storm surge, and enhanced infiltration, all
which can further help mitigate the effects of a changing climate. While these zones are likely to occur in
low-lying areas near the coast or along rivers and streams, they may also exist in hydrologically
unconnected areas as a result of pluvial flooding or in upland areas with well-drained soils. The following
section summarizes the available data layers that can be used to help inform the development of resilience
zones.
2 E XISTING DATA
Identifying and mapping resilience zones within the Town can be approached using several methods. In the
absence of detailed hydrologic and hydraulic modeling, the process generally relies on overlaying multiple
datasets, such as topography, land use, and soil conditions, to identify where they overlap. Several
organizations, such as NOAA and the South Carolina Office of Resilience (SCOR), have already developed
composite layers which combine multiple datasets to identify flood-prone areas or conservation areas
which can be leveraged in this analysis. The following section summarizes the available base and
composite data layers that can be used to help identify resilience zones within the Town.
Attachment 1
McCormick Taylor Memos
Page 48
Section 3. Item # 1.
2.1 B ASE LAYERS
2.1.1 FEMA Flood Layer
The Federal Emergency Management Agency (FEMA) flood data depicts areas at risk of flooding based on
hydrologic and hydraulic modeling, for a variety of storm events. This information can be accessed through
FEMA’s website and details flood hazard areas for the 1% annual chance flood, the 0.2% annual chance
flood, the future conditions 1% annual chance flood, and floodways where applicable, among other data.
The data can be accessed at the FEMA Map Services Center.
2.1.2 NOAA National Hurricane Center SLOSH Data
The National Oceanic and Atmospheric Administration (NOAA) National Hurricane Center (NHC) Sea Lake
and Overland Surges from Hurricanes (SLOSH) model is used to simulate storm surge from hurricanes and
tropical storms. NOAA hosts SLOSH model results for 29 different basins across the US [e.g., South
Carolina/Charleston Basin]. The data is available for hurricane categories 1 through 5 and depicts areas
expected to flood less than 3 feet above ground, between 3 to 6 feet, between 6 to 9 feet, and greater than
9 feet for a selected hurricane category. The data can be accessed from the National Hurricane Center.
2.1.3 NOAA Sea Level Rise Viewer and Marsh Migration
The NOAA Sea Level Rise Viewer is a web-based application that allows users to visualize areas of
inundation for various sea level rise scenarios. The application features a sliding bar which allows users to
specify a sea level increase, from one to ten feet, relative to the mean higher high water (MHHW) datum and
visualize the resulting inundation extents and depth. Low-lying hydrologically unconnected areas which
may be prone to flooding are also mapped by this tool. This tool also allows viewers to visualize marsh
migration by depicting changes in coastal land use as sea level increases. This data can be accessed at
NOAA’s Digital Coast website.
2.1.4 Watershed Characteristics
Additional GIS data that can aid in a flood vulnerability analysis includes topographic layers (slope,
elevation, DEM), hydrologic layers (distance to drainage network, stream order, Topographic Wetness Index
(TWI)), soil data (hydrologic soil group (HSG)), land cover/land use data (National Land Cover Database
(NLCD), National Wetland Inventory (NWI), impervious surface, Normalized Difference Vegetation Index
(NDVI)), and climatic data (precipitation). These layers can be overlayed to help identify low lying areas
where runoff is likely to accumulate. Most of the data is publicly available online from federal (USGS,
USFWS) and state agencies (SCDNR) or can be acquired from local jurisdictions.
2.2 C OMPOSITE LAYERS
2.2.1 South Carolina Office of Resilience-Conservation Priority Areas
During the development of the Statewide Resilience and Risk Reduction Plan, SCOR identified priority flood
mitigation areas, referred to as Conservation Priority areas . These areas were identified by assessing where
flood hazards are expected, where wetlands exist, and where infiltration rates are high. Protecting these
areas can help to reduce flood risk and allow for natural storage and conveyance functions. The composite
layer was generated using the data and methods described below.
1) Flood hazard areas:
Attachment 1
McCormick Taylor Memos
Page 49
Section 3. Item # 1.
a. FEMA’s 1% and 0.2% annual chance flood hazard areas were used for current conditions.
b. To incorporate future flood risk, the First Street Foundation’s flood model was used to
identify areas that would experience over 3 feet of flooding during a 0.2% annual chance
flood scenario in 2052.
2) Available land for future marsh migration:
a. Marsh migration and sea-level rise data from the NOAA Sea Level Rise Viewer were used
to identify where marsh migration is likely to occur. NOAA predicts a 1.5-foot rise in sea
level by 2050 for South Carolina, with coastal marshes naturally migrating inland.
Conserving available land next to marshes can help preserve future natural storage.
3) Wetlands:
a. Wetland data was incorporated from the U.S. Geological Survey (USGS) 2019 National
Land Cover Dataset.
4) Upland areas with high infiltration rates:
a. To identify upland areas outside of floodplains and wetlands with permeable soils, the
USGS SSURGO Soils mapping was used in conjunction with the USGS 2019 National Land
Cover Dataset (NLCD) and the USDA 30-meter Digital Elevation Model. Runoff curve
numbers were calculated using the USDA NRCS TR-55 method, with high curve numbers
indicating high runoff potential, and low curve numbers indicating low runoff potential. An
analysis was performed to identify the 10th percentile best infiltration areas for each HUC-
8 watershed, identifying the upland areas that should be prioritized for conservation.
Areas that were removed from the analysis include developed areas (low, medium or high developed from
the 2019 NLCD layer), open water areas (from the 2019 NLCD layer), and protected areas (from the USGS
Protected Area Database and the South Carolina Conservation Bank). The Conservation Priority areas were
identified as having one or more of the following characteristics: 1) areas within the 1% or 0.2% flood zone
(FEMA or First Street Data), 2) areas where future marsh migration is expected (NOAA Marsh Migration
Model for 2050 using 1.5’ sea level rise scenario), 3) areas where current wetlands exist, and 4) areas where
the curve number is in the lowest 10% (derived from the Land Cover Dataset). This data can be accessed
at SCORs Resilience Atlas website.
2.2.2 NOAA Coastal Flood Hazard Composite
The NOAA Coastal Flood Hazard Composite layer was developed by overlaying multiple flood hazard
datasets to identify areas exposed to coastal flooding potential. Data layers used in the analysis include
FEMA flood data (V zones, A zones, shaded X zones), NOAA flood frequency zones, NOAA storm surge
inundation for Category 1 through 3 hurricanes, and sea level rise inundation extents for 1, 2, and 3 feet
above current mean higher high water (MHHW). Land is categorized into hazard zones 1 through 11, where
hazard zone 1 represents the least vulnerable areas and zone 11 the most vulnerable. The Coastal Flood
Hazard mapper provides coverage for the U.S. coastal areas along the Gulf of Mexico and Atlantic Coasts,
and the data can be accessed at NOAA’s Digital Coast website.
2.2.3 South Carolina Department of Environmental Services Coastal Hazard Vulnerability
Assessment
The South Carolina Department of Environmental Services (SCDES) developed the Hazard Vulnerability
Assessment (HVA) tool which evaluates coastal hazard vulnerability within the South Carolina critical area
from four hazards: storm surge, shoreline change rate (erosion or accretion), flooding, and social/economic
Attachment 1
McCormick Taylor Memos
Page 50
Section 3. Item # 1.
vulnerability (SoVI®). The HVA tool was developed to improve hazard mitigation planning, post-disaster
redevelopment, and restoration/mitigation project sitting. The analysis produced multiple composite layers
including an inundation vulnerability layer (combining flooding & storm surge), an inundation and SoVI
vulnerability layer (combining flooding, storm surge, and SoVI®) layer, and a shoreline change vulnerability
layer (combining shoreline change rate, temporal variability, and spatial variability). For each layer, values
are assigned an HVA rank from 1 through 5, with 1 being the least vulnerable and 5 being the most
vulnerable. The rankings for each of the individual input data layers can also be viewed in the tool.
The flood data is based on FEMA’s DFIRM data where an HVA rank of 5 includes categories V, VE, and Open
Water while a rank of 1 includes D and 0.2% annual chance flood hazard. Storm surge is taken from NOAA’s
SLOSH model and the HVA rank is based on height exceeding 1 ft for a given hurricane category. A rank of 5
is assigned to areas where a Category 1 hurricane would reach that level of inundation while a rank of 1 is
assigned to areas where it would take Category 5 hurricane to reach that level of inundation. The SoVI® index
is produced by the University of South Carolina’s Hazards and Vulnerability Research Institute and
incorporates 29 socioeconomic variables. For this analysis, SoVI® scores are relative and based on
standard deviations from the mean. A rank of 5 represents scores > +2 standard deviations from the mean
while a rank of 1 represents scores <-2 standard deviations from the mean. The shoreline change data is
taken from the SCDES’s Bureau of Coastal Management (BCM) which was generated using an open-source
geospatial tool called AMBUR (Analyzing Moving Boundaries Using R). The analysis uses three-time steps,
1800’s, 1930’s, and 2000’s, and the tool uses the End Point Rate (EPR) to assign a rank. The HVA tool can
be accessed from SCDES’s website.
2.2.4 First Street Flood Data
The South Carolina Office of Resilience has partnered with First Street Technology, Inc. (First Street) to
obtain hazard data for the entire state. First Street is a non-profit research organization that estimates
climate risk for individual properties, neighborhoods, and communities focusing on five factors: flooding,
fire, wind, air, and heat. The flood model includes risks associated with pluvial, riverine, and coastal flooding
and simulates flood depths for current and future conditions for the 2-, 5-, 20-, 100-, 200-, and 500-year
return periods. Building structure data is also used to calculate annual financial losses from a modeled
storm event. Additional information on the methodology can be found on First Street’s website and data
within the state of South Carolina can be obtained by contacting SCOR.
2.2.5 SeaGrant Resiliency Analysis Vulnerability Layers
SeaGrant and the College of Charleston recently conducted a resilience planning analysis for the Town of
Bluffton to assess the Town’s vulnerability to current and future environmental conditions. To assess
vulnerability, Digital Elevation Models (DEMs) and Digital Surface Models (DSMs) were created and the First
Street flood data was used to determine the mean flood depth per parcel for the 50%, 20%, 5%, 1%, and
0.2% chance flood events for 2023 and 2053. A build-out analysis was then performed. Maximum allowed
density and maximum dwelling units were obtained from the Town’s active planned unit development
(PUD) agreements and the Unified Development Ordinance (UDO), and parcels greater than 5 acres with
zoning categories of PUD, agricultural (AG), and Residential General (RG) were isolated for the analysis.
After removing National Wetland Inventory (NWI) critical area and open water areas, areas that overlapped
with the NOAA’s 2021 Coastal Change Analysis Program (C-CAP) water layer, and areas that intersect with
road network data, the parcels were subdivided based on the allowed maximum density and the average
Attachment 1
McCormick Taylor Memos
Page 51
Section 3. Item # 1.
depth of flooding for each flood scenario was assigned to each parcel. The resulting data layer can be found
in the Resilience Planning Analysis: Town of Bluffton, SC report.
An elevation analysis was also performed to determine the potential vulnerability reduction resulting from
prioritizing development in upland zones within each development area. Using the buildout parcels from the
previous analysis, the average parcel elevation was calculated using the DEM, and the mean and standard
deviation of elevations within each development zone (PUD, AG, or RG) were used to assign categories of
low, moderate, and high elevation. Low elevation parcels were those with an elevation lower than the mean
minus one standard deviation. Moderate elevation parcels are those within one standard deviation from the
mean. High elevation parcels have elevation above the mean plus one standard deviation. The resulting data
layer can be found in the Resilience Planning Analysis: Town of Bluffton, SC report.
3 TOWN OF BLUFFTON RESILIENCE ZONES
3.1 R ESILIENCE ZONE MAPPING
After reviewing the available data, McCormick Taylor (MT) determined that the Conservation Priority areas
identified by SCOR closely align with what the Town would like to prioritize as resilience zones. As
summarized in Section 2.2.1, datasets from FEMA, First Street, NOAA, and the USGS were used to identify
areas for conservation that reduce flood risk, promote infiltration, and preserve natural storage and
conveyance functions. SCOR has conducted its analysis at the statewide scale using publicly available
data. To refine the conservation priority areas at the local level, MT recreated the dataset for the Town using
locally derived data when available. The analysis was completed using the following steps:
1) Data was compiled from FEMA and First Street Foundation for the 1% (100-year) and 0.2% (500-
year) storm events. Areas that would have equal to or greater than 3 feet of flooding in 2055 were
also included from First Street Foundation to incorporate future climate conditions.
2) Data was compiled from NOAA’s Marsh Migration model for the year 2050 based on 1.5 feet of sea
level rise.
3) The wetland potential layer developed by CWP was used as the existing wetlands layer and
included wetlands classified as either medium or high potential.
4) Areas of high infiltration were identified using Bluffton’s existing land cover layer and SSURGO
hydrologic soil group (HSG) data. A curve number (CN) was assigned at the pixel scale using the
lookup table below (Table 1). The 10th percentile highest infiltration areas were identified. Higher
curve numbers indicate higher runoff potential; thus, the highest infiltration areas had the lowest
curve numbers.
5) Ineligible locations were eliminated, including:
a. Developed areas, based on the Town’s existing land cover data layer.
b. Open water based on the NOAA Marsh Migration data layer.
c. Protected areas from the South Carolina Conservation Bank layer and the USGS Protected
Area Database.
6) The data was combined into a single layer, and the ineligible locations above were removed.
Attachment 1
McCormick Taylor Memos
Page 52
Section 3. Item # 1.
Table 1: Curve numbers by land use and HSG
HSG HSG
Existing Land Use Categories A B C D Existing Land Use Categories A B C D
Club House 89 92 94 95 Open Space - Undeveloped 43 65 76 82
Commercial 89 92 94 95 Open Space -Park 49 69 79 84
Commercial - Office-Warehouse 89 92 94 95 Residential - Condo 77 85 90 92
Commercial - Old Town 89 92 94 95 Residential - MF 77 85 90 92
Commercial - Vacant 89 92 94 95 Residential - Mobile Home 61 75 83 87
Education 89 92 94 95 Residential - Single Family 61 75 83 87
Faith 89 92 94 95 Residential - Single Family Attached 61 75 83 87
Golf and Clubhouses 46 65 77 82 Residential - Single Family Vacant 61 75 83 87
Industrial 81 88 91 93 ROW 83 89 92 93
Industrial - Mini Warehouses 81 88 91 93 Service 83 89 92 93
Marsh 98 98 98 98 Service - Utilities 83 89 92 93
Open Space - Conservation 43 65 76 82 Waterway 98 98 98 98
Open Space - Equine 49 69 79 84
Open Space - HOA Park 49 69 79 84
Open Space - Other 49 69 79 84
Open Space - Passive 49 69 79 84
The resulting layer, Figure 1, identifies areas within the Town capable of infiltrating, storing, and conveying
water, for current and future conditions, thereby providing important flood mitigation benefits. The areas
identified through this analysis should be prioritized for conservation, helping to prevent or limit future
development in locations that are essential to the Town’s long-term resilience.
3.2 F LOOD VULNERABILITY MAPPING
McCormick Taylor is also supporting the Town of Bluffton in developing a resilience ordinance. The
resilience ordinance is intended to provide an additional layer of protection from flooding, increased storm
events, and projected sea level rise. While still under development, the ordinance will focus on updating
zoning regulations, building codes, and stormwater management requirements to reduce flood vulnerability
and enhance the Town’s long-term climate resilience. While the resilience zone mapping was originally
intended to support the resilience ordinance, it was determined that performing a vulnerability analysis to
identify flood-prone areas would better inform the regulations. McCormick Taylor followed two different
strategies to identify vulnerable areas within the Town.
Attachment 1
McCormick Taylor Memos
Page 53
Section 3. Item # 1.
Figure 1: Conservation priority areas within the Town
Attachment 1
McCormick Taylor Memos
Page 54
Section 3. Item # 1.
3.2.1 Elevation-based Analysis
McCormick Taylor performed an elevation-based analysis using methods adapted from the SeaGrant
Resiliency Analysis to identify low elevation areas within the Town that may be more vulnerable to flooding.
While the SeaGrant analysis only included land with the PUD, AG, or RG development zones, all land within
the Town was included for this analysis. Additionally, instead of determining the average elevation at the
parcel level, the analysis was done at the resolution of the DEM. The analysis was completed using the
following steps:
1) The NWI Wetlands and Storm Ponds – Town Asset data layers were clipped to the Town of Bluffton
boundary.
a. Estuarine and Marine Deepwater/Wetland, Freshwater Pond, Lake, Riverine categories
from the NWI wetlands layer were queried and isolated to a new working layer.
b. The Town Storm Ponds layer was added to this working layer.
2) After noticing that many of the stormwater ponds in the new subdivisions were not included in the
town’s Storm Ponds layer, using aerial imagery, MT digitized any remaining pond and added them
to the working layer.
3) The NWI Wetlands and Storm Pond areas were clipped from the terrain, so they are excluded from
the elevation analysis.
4) The DEM was clipped to the town boundary and reclassified based on three levels of standard
deviation that are described in the SeaGrant report.
a. The reclassified DEM was then converted into a polygon layer with three classification
codes.
i. Zone 1 = -4.8’ – 9.6’
ii. Zone 2 = 9.6’ – 26.9’
iii. Zone 3 = 26.9’ – 85.9’
5) The NWI Wetlands and Storm Ponds areas were then merged with the reclassified polygon layer
and assigned a unique code in that polygon layer.
a. Zone 4 = Estuarine and Marin Deepwater/Wetland, Freshwater Pond, Lake, Riverine NWI
Wetlands and Town Storm Ponds.
6) All features were then dissolved based on the four different classification zones.
The results from the elevation-based analysis are shown in Figure 2 with Zone 1 (red) as the low elevation
zone, Zone 2 (yellow) as the medium elevation zone, and Zone 3 (green) as the high elevation zone. The low
elevation zone aligns closely with the FEMA 100-year floodplain as shown in Figure 3. The elevation-based
analysis can support the resilience ordinance by encouraging development in high-ground areas that may
be less vulnerable to coastal and riverine flooding. This could be accomplished through overlay zoning
districts, as noted in the SeaGrant report.
Attachment 1
McCormick Taylor Memos
Page 55
Section 3. Item # 1.
Figure 2 : Elevation-based zones within the Town of Bluffton
Attachment 1
McCormick Taylor Memos
Page 56
Section 3. Item # 1.
Figure 3: FEMA flood zones and elevation-based zones
Attachment 1
McCormick Taylor Memos
Page 57
Section 3. Item # 1.
3.2.2 Composite Flood Vulnerability Analysis
To further assess which areas within the Town are least or most vulnerable to flooding, MT conducted a
flood vulnerability analysis. The analysis combined data reflective of riverine, coastal, and pluvial flooding
using a weighted overlay approach. A vulnerability score was first developed for each type of flooding
(riverine, coastal, pluvial) using various input data layers. For each layer, values were assigned a score from
0 to 3 or 1 to 3, with 0 or 1 being the least vulnerable and 3 being the most vulnerable. Data layers were then
weighted based on priority. A final composite layer was developed by overlaying the three individual flood
vulnerability layers. The details and weightings of each individual flood type are outlined below.
3.2.2.1 Riverine Flooding
The riverine vulnerability score was estimated using two layers: FEMA’s National Flood Hazard Layer
(NFHL) and distance to the natural drainage network. The flood zones outlined by FEMA were assigned a
score ranging from 0 to 3, shown in Table 2. Land located with the Floodway, Zone VE, and Open Water
received the highest score and were assigned a 3, while Zone X areas located outside of the 500-year
floodplain (shaded Zone X) were assigned a score of 0.
Table 2: Scoring breakdown for FEMA NFHL input layer
Score FEMA Flood Zones
3 Floodway, Zone VE (High-risk coastal areas), and Open Water
2 Zone Coastal A, AE, or AO (excluding areas noted as Floodway)
1 Shaded Zone X noted as 0.2% annual chance of flooding (the 500-year floodplain)
0 All remaining Zone X areas (areas located outside of the 500-year floodplain)
Distance to the natural drainage network was included since land closer to streams is likely to be more
vulnerable to flooding. The distance to the natural drainage network was calculated using the USGS
StreamStats stream network from the 2024 Release. The stream network was used as an input in the
Distance Accumulation tool within ArcGIS Pro, which calculates accumulated distance for each cell to the
stream network. The results were then clipped to the Town of Bluffton limits and Jenks natural breaks were
used to establish class thresholds. The resulting scoring categories are shown in Table 3.
Table 3 : Scoring breakdown for distance to drainage network input layer
Score Distance to Natural Drainage Network
3 Distance to nearest stream is < 290.2ft
2 Distance to nearest stream is >= 290.2 ft and < 649.0 ft
1 Distance to nearest stream is >= 649.0 ft
0 N/A
The cumulative riverine vulnerability score was calculated based on the weights assigned to each layer in
Table 4. The spatial distribution of these results is shown in Figure 4.
Table 4: Riverine vulnerability scoring input weights
Riverine Data Layers Weight
FEMA Flood Zones 70%
Distance to Drainage Network 30%
Attachment 1
McCormick Taylor Memos
Page 58
Section 3. Item # 1.
3.2.2.2 Coastal Flooding
Coastal flooding was estimated using two layers: NOAA sea-level rise inundation data and NOAA storm
surge (SLOSH) data. To align the sea-level rise data with the Beaufort County Long Term Resilience Strategy,
scoring categories were developed using NOAA 2022 sea level rise projections for Ft. Pulaski based on
estimates for the 2050, 2080, and 2100 timeframes, using the intermediate-high scenario. Scores were
assigned to inundated areas based on the lowest increase in sea-level rise that would cause flooding at a
given location. Therefore, scores are inversely related to sea-level rise and an area inundated from a 1.5 ft
increase in sea-level is considered to be more vulnerable than an area only inundated with a 5 ft increase in
sea-level. The resulting scoring categories are shown in Table 5.
Table 5 : Scoring breakdown for NOAA sea-level rise input layer
Score NOAA Sea-Level Rise
3 Area within the inundation zone associated with 1.5 ft of SLR
2 Area within the inundation zone associated with 3.5 ft of SLR
1 Area within the inundation zone associated with 5.0 ft of SLR
0 Area outside of the inundation zone associated with 5.0 ft of SLR
To evaluate the impacts of storm surge, NOAA’s SLOSH data was used to categorize areas based on the
extent of inundation associated with different hurricane categories. Although the model includes Category
1 through 5 hurricanes, this analysis focused on Categories 1 through 3, which represent hurricanes that
occur more frequently and therefore have lower recurrence intervals. For each category, the mapped
inundation extent assumes landfall at high tide, resulting in maximum potential storm surge. This
assumption represents a risk-averse modeling approach and captures a worst-case inundation scenario for
each hurricane category.
Scores were assigned to inundated areas based on the lowest hurricane category that would cause flooding
at a given location, similar to sea-level rise. As a result, the score is inversely related to hurricane category
and an area inundated during a Category 1 hurricane is considered to be more vulnerable than an area only
inundated during a Category 3 hurricane. This reflects both the greater likelihood of lower-category
hurricanes and the generally greater flood depths experienced at locations inundated during more frequent
storm events. The scoring framework associated with the inundation extents is summarized in Table 6.
Table 6 : Scoring breakdown for storm surge risk map input layer
Score Hurricane Storm Surge Inundation Extent
3 Area within the Category 1 storm inundation extent
2 Area within the Category 2 storm inundation extent
1 Area within the Category 3 storm inundation extent
0 Area outside the Category 3 storm inundation extent
The cumulative coastal vulnerability score was then calculated based on these weights assigned to each
layer in Table 7. The spatial distribution of these results is shown in Figure 5.
Attachment 1
McCormick Taylor Memos
Page 59
Section 3. Item # 1.
Table 7 : Coastal vulnerability scoring input weights
Coastal Data Layers Weight
NOAA Sea-Level Rise 50%
NOAA Storm Surge (SLOSH) 50%
3.2.2.3 Pluvial Flooding
Pluvial flooding occurs when rainfall overwhelms local stormwater infrastructure, resulting in flooding in
urban areas. Identifying where pluvial flooding is likely to occur generally requires detailed hydrologic and
hydraulic modeling that accounts for stormwater infrastructure, rainfall intensity, and fine-scale
topography. In the absence of this detailed flood modeling, vulnerability to pluvial flooding was assessed
using an approach that incorporates key physical and land-use variables known to influence where pluvial
flooding is most likely to occur. The six input layers used in the analysis were:
• US Department of Agriculture (USDA)’s Natural Resources Conservation Service (NRCS)
Hydrologic Soil Group,
• Impervious surface area,
• Land use/land cover,
• Slope,
• Wetness Index based on Landscape Topography (WILT), and
• First Street Flood Model data.
Hydrologic soil group is an indicator of a soil’s runoff potential. Soils are assigned to one of four groups (A,
B, C, and D) or three dual classes (A/D, B/D, and C/D). Group A soils have high infiltration rates and the least
runoff potential, while group D soils consist of soils with a very slow infiltration rate and thus have high runoff
potential. Soils with dual designations indicate the soil responds like a group D soil when wet.
For this analysis, soils with a slow infiltration rate and high runoff potential were scored higher than soil with
a high infiltration rate and low runoff potential. For soils with dual classes (i.e., Group A/D, Group B/D, Group
C/D), scores were assigned based on the second letter. The scoring breakdown for the NRCS HSG layer is
shown in Table 8.
Table 8: Scoring breakdown for NRCS HSG input layer
Score NRCS Hydrologic Soil Groups
3 Group D, Group A/D, Group B/D, and Group C/D soils
2 Group B or C soil
1 Group A soil
0 N/A
Several data layers that depicted various types of impervious surface were provided by the Town of Bluffton
and combined to form one impervious surface data layer. Because impervious surfaces play a large role in
determining where pluvial flooding is more likely to occur, impervious areas were assigned a 3 and all other
areas were assigned a 1. The scoring breakdown for the impervious surface layer is shown in Table 9.
Attachment 1
McCormick Taylor Memos
Page 60
Section 3. Item # 1.
Table 9: Scoring breakdown for impervious surface input layer
Score Impervious Surface Area
3 Impervious surface areas
2 N/A
1 All other surface areas within the Town
0 N/A
Land cover data was derived from a raster layer (Bluffton_Landcover_Classification) which provides a
numeric value representing a specific land cover for each cell (each cell is roughly 4 feet by 4 feet, covering
approximately an 18 sq. ft. area). Similar types of land cover were combined to create three different land
cover groups, which were then assigned a score. Forest and grasslands are non-developed and typically
have high infiltration rates and were therefore assigned the lowest score of 1. Wetlands, open water, and
developed areas were assigned the highest score of 3 as their position in the landscape and high levels of
impervious surfaces make them the most vulnerable to flooding. The scoring breakdown is shown in Table
10.
Table 10: Scoring breakdown for the land cover input layer
Score Land Cover
3 Wetland, Water, and Developed land cover classes
2 Residential and Barren land cover classes
1 Forest and Grassland land cover classes
0 N/A
The slope layer was derived from the Town’s digital elevation model (DEM). Areas with slopes less than or
equal to 2% were assigned a score of 3 while areas with slopes greater than or equal to 5% were assigned
a score of 1. The scoring breakdown for the slope layer is shown in Table 11.
Table 11: Scoring breakdown for the slope input layer
Score Slope
3 Grade is less than or equal to 2%
2 Grade is between 2% and 5%
1 Grade is greater than or equal to 5%
0 N/A
The Wetness Index based on Landscape Topography (WILT) is an index that can be used to infer how wet
or flood-prone a location is relative to the surrounding area. WILT was used for this analysis over
Topographic Wetness Index (TWI) as it is typically a better indicator of relative wetness within a coastal
plain landscape. For this study, the WILT layer was provided by the Center for Watershed Protection, Inc.
(CWP). The WILT accounts for groundwater depth, flow accumulation, and the tangent of slope. To
categorize the WILT data, Jenks natural breaks were used to establish class thresholds. Areas with a higher
WILT were assigned a score of 3 while areas with a low WILT were assigned a score of 1. The scoring
breakdown for the WILT layer is shown in Table 12.
Attachment 1
McCormick Taylor Memos
Page 61
Section 3. Item # 1.
Table 12: Scoring breakdown for wetness index based on landscape topography (WILT) input layer
Score Wetness Index based on Landscape Topography (WILT)
3 WILT greater than or equal to 7.37
2 WILT greater than or equal to 1.65
1 WILT less than 1.65
0 N/A
First Street flood data was provided by SCOR. For this analysis, the future conditions (2053) model was
used to account for projected changes in climate, such as the intensification of storm events and sea-level
rise. The spatial data was categorized based on the lowest recurrence interval storm event that would result
in flooding. Land that is inundated during a lower recurrence interval (more common) flood event was
assigned a score of 3 while areas that would only flood during a higher recurrence interval (less common)
flood event were assigned a lower score. The scoring breakdown for the First Street flood model data is
shown in Table 13.
Table 13: Scoring breakdown for first street flood model (2053) input layer
Score First Street Flood Model (2053)
3 Within the flooding extent of the 5% (20-year) flood event
2 Within the flooding extent of the 1% (100-year) flood event
1 Within the flooding extent of the 0.2% (500-year) flood event
0 Outside the flooding extent of the 0.2% (500-year) flood event
The cumulative pluvial vulnerability score was then calculated based on weights assigned to each layer in
Table 14. The spatial distribution of these results is shown in Figure 6.
Table 14: Pluvial vulnerability scoring input layer weights
Pluvial Data Layers Weight
NRCS Hydrologic Soil Group 15%
Impervious Surface Areas 15%
Land Cover 15%
Slope 30%
First Street Flood Model 2053 data 15%
WILT 10%
3.2.2.4 Composite Vulnerability Score
The impacts of riverine, coastal, and pluvial flooding were combined to generate a composite vulnerability
score. Each of the scoring layers (riverine, coastal, pluvial) were weighted equally and summed to give a
final score ranging between 1.05 to 9, with higher values indicating higher vulnerability. The spatial
distribution of these results is shown in Figure 7. Results from this analysis can also be used to inform the
Town’s resilience ordinance and coincide with SCOR’s Conservation Priority areas to help prioritize the
most vulnerable land to conserve. The vulnerability analysis can also be used in conjunction with the Town’s
wetland mapping analysis to identify wetlands near highly vulnerable areas that should be protected from
future development.
Attachment 1
McCormick Taylor Memos
Page 62
Section 3. Item # 1.
Figure 4: Riverine hazard score
Attachment 1
McCormick Taylor Memos
Page 63
Section 3. Item # 1.
Figure 5: Pluvial hazard score
Attachment 1
McCormick Taylor Memos
Page 64
Section 3. Item # 1.
Figure 6: Pluvial hazard score
Attachment 1
McCormick Taylor Memos
Page 65
Section 3. Item # 1.
Figure 7: Composite hazard vulnerability score
Attachment 1
McCormick Taylor Memos
Page 66
Section 3. Item # 1.
1
Norman Levine 1, Landon Knapp 1,2, Hailey Connell 1, Sophia Truempi 2, Katie
Finegan2,3, and Shu-Mei Huang1,2
Photo: Bluffton, SC
Attachment 2
Resilience Analysis
Page 67
Section 3. Item # 1.
2
1Lowcountry Hazards Center, College of Charleston, Department of Geology and Environmental
Geosciences, Charleston, SC, USA
2South Carolina Sea Grant Consortium, Charleston, SC, USA
3Coastal Carolina University, Conway, SC, USA
Attachment 2
Resilience Analysis
Page 68
Section 3. Item # 1.
3
Table of Contents
ExecutIve Summary ....................................................................................................................................... 4
Background ................................................................................................................................................... 6
Hazards and Land Use Change .................................................................................................................. 7
Resilience Planning Analysis ................................................................................................................... 10
METHODS .................................................................................................................................................... 10
Study Area ............................................................................................................................................... 10
Community Engagement ........................................................................................................................ 13
Flood Reporter Survey ........................................................................................................................ 14
Selection of Vulnerability Metrics ....................................................................................................... 15
Policy ....................................................................................................................................................... 15
Mapping & Modeling .............................................................................................................................. 16
Results ......................................................................................................................................................... 17
Community Engagement ........................................................................................................................ 17
Selection of Vulnerability Metrics ....................................................................................................... 18
Mapping & Modeling .............................................................................................................................. 20
Land Use and Flow Direction .............................................................................................................. 20
Current Development Flood Vulnerability .......................................................................................... 22
Maximum Buildout Flood Vulnerability .............................................................................................. 24
Forested Wetlands Analysis ................................................................................................................ 26
Elevation Analysis................................................................................................................................ 29
Discussion.................................................................................................................................................... 31
References .................................................................................................................................................. 36
Appendices .................................................................................................................................................. 37
Appendix A: Current Development Flood Vulnerability Result .............................................................. 37
Appendix B: Maximum Buildout Flood Vulnerability Results ................................................................. 45
Appendix C: Forested Wetlands Analysis Results ................................................................................... 47
Appendix D: Elevation Analysis Results .................................................................................................. 51
Appendix E: Mapping and Modeling Methods ....................................................................................... 55
Appendix F: Digital Elevation Models (DEMs) and Digital Surface Models (DSMs) ................................ 62
Appendix G: Supplemental Information ................................................................................................. 63
Attachment 2
Resilience Analysis
Page 69
Section 3. Item # 1.
4
The Town of Bluffton (Bluffton), in partnership with the College of Charleston and the South
Carolina Sea Grant Consortium, conducted a Resilience Planning and Engagement Project
(Resilience Analysis) to assess Bluffton’s vulnerability to current and future environmental
conditions, with a focus on flooding risks and the impacts of land development on resilience. The
aim of the project was to identify flood hazards affecting key infrastructure, identify potential
policy options for enhancing resilience, and ensure public input through community engagement
efforts. The analysis involved mapping and modeling current flood risks, evaluating
development scenarios through a build-out analysis, and assessing the role of wetlands in
mitigating flood impacts.
The analysis involved multiple layers of data to assess current and future flood vulnerability,
focusing on both parcel-based flood depth and potential future development. Digital Elevation
Models (DEMs) and Digital Surface Models (DSMs) were used to represent the topography,
while the First Street Foundation flood dataset was used to analyze flood depth across different
flood scenarios. A buildout analysis demonstrated future development to understand the potential
flood impacts, with additional focus on wetlands and elevation-based zoning to determine how
limiting development in certain areas could reduce vulnerability and potential flood damage.
Additionally, community outreach events were held to gather local input, and a flood reporter
survey was used to document residents' experiences with past flooding.
Key Findings:
1. Flood Vulnerability: The analysis revealed significant flood risks for Bluffton’s assets
and infrastructure under both current and future conditions. Increased flood depths were
projected for frequent flood events (1-in-2-year storm), with many parcels that currently
experience minor flooding facing more severe inundation by 2053. The vulnerability was
particularly notable for high-impact flood events (1-in-100-year and 1-in-500-year
storms), which would affect parcels that are currently outside of major flood risk areas.
2. Future Development Risks: A buildout analysis projected that 99,423 additional parcels
could be developed in Bluffton by 2053. However, this increase in development
heightens flood risks, with over 63% of these parcels at risk from the 1-in-500-year flood
event. Protection of wetlands and surrounding areas through buffers as well as
implementation of elevation-based zoning could significantly reduce future flood
vulnerability. After modeling the implementation of each of the policy options analyzed
in this study, more parcels were available for development than are required based on
active Planned Unit Development agreements.
3. Role of Wetlands: Wetlands play a crucial role in absorbing floodwaters, especially
during higher intensity events where over half of the vulnerable developable lands are
within wetland areas. By 2053, more than 20% of the flood risk from low intensity storm
Attachment 2
Resilience Analysis
Page 70
Section 3. Item # 1.
5
events could be associated with areas near wetlands. Protecting these vital ecosystems
through local ordinances could help mitigate the impacts of future flooding events,
potentially reducing overall damage. Protecting wetlands plus a 50-ft buffer reduces more
than 60% of the vulnerability of future development to the 1-in-100-year storm event.
4. Elevation-Based Zoning: Areas with lower elevations showed greater vulnerability to
flooding. Conversely, high ground zones had very little flood risk, with less than 6% of
flooding for the highest intensity storms in this area and no flooding for the lowest
intensity storm. Damage models showed an even greater proportion of property-
damaging floodwaters in low elevation zones. Implementing elevation-based zoning
could drastically reduce the exposure of development to flood risks, ensuring that future
growth occurs in safer, higher-elevation areas.
5. Community Engagement: Public input gathered during community engagement events,
particularly after Tropical Storm Debby in August 2024, provided valuable insights into
flood concerns in low-lying areas. These insights helped shape the flood risk assessment
and reinforced the need for stronger flood management policies.
Conclusions: Bluffton is at increasing risk of flooding due to both current and future climate
impacts. Bluffton’s vulnerability is compounded by projected increases in development and
changes in land use. Protecting wetlands and implementing strategic growth policies, such as
elevation-based zoning, could help reduce these risks and safeguard Bluffton’s infrastructure and
natural resources. Furthermore, community feedback has underscored the importance of
addressing local flood concerns in future resilience strategies.
Recommendations:
1. Strengthen Wetlands Protection:
Consider adopting a wetland overlay zoning district (e.g. marsh migration overlay) or
expansion of the Preserve (PR) District to safeguard flood-prone ecosystems. Use
permitting requirements to guide development away from sensitive areas.
2. Implement Elevation-Based Zoning:
Limit development in low-lying areas by incorporating elevation into zoning criteria,
following models from Charleston, SC, and Norfolk, VA.
3. Update Flood Management Policies:
Enhance Bluffton’s 2021 Flood Damage Prevention Ordinance to ensure that new
developments adhere to stricter flood protection standards.
4. Offer Financial Incentives for Resilient Development:
Strengthen the Transfer of Development Rights (TDR) program and consider tax or fee
incentives for projects in low-risk zones. Explore impact or conservation fees for
developments in sensitive areas.
Attachment 2
Resilience Analysis
Page 71
Section 3. Item # 1.
6
5.5. Expand Land Acquisition and Partnerships:
Work with land trusts to secure key wetlands and floodplains. Use conservation tools and
funding strategies to grow Bluffton’s Land Acquisition Fund and prioritize high-impact
parcels.
By implementing these recommendations, Bluffton can enhance its resilience to future flooding
events and protect valuable ecosystems while balancing developmental goals.
The Town of Bluffton (Bluffton, Figure 1) is one of the fastest growing municipalities in South
Carolina, with a 1,233% growth increase since 2000 (Town of Bluffton, 2022). In 2020, Bluffton
had a population estimate of 34,493 based on the 2020 US Census Bureau projections (US Census
Bureau, 2020). Out of 50,000 acres of land (not including waterways and marshes, ~14,000 acres),
10,344 acres of undeveloped open s pace remain (Town of Bluffton, 2022).
Figure 1: Town of Bluffton with land cover displayed
Within Bluffton’s Comprehensive Plan, sections on natural resources and land use highlight the
importance of locating areas for conservation and stormwater infiltration and preparing joint land
use plans for undeveloped lands to address density and environmental protection (Town of
Attachment 2
Resilience Analysis
Page 72
Section 3. Item # 1.
7
Bluffton, 2022). This is also shown in the May River Watershed Action Plan, though this plan
centers mainly on water quality (fecal coliform, E. coli. , bacteria loading, etc.) and
recommendations for land use alteration to negate the contamination impact of stormwater (Town
of Bluffton, 2020).
Hazards and Land Use Change
The Fort Pulaski National Oceanic and Atmospheric Administration (NOAA) Tide Gauge was
established in 1935 and is located approximately 7 miles south of Bluffton. This gauge is the
closest tidal monitoring station to Bluffton, and because of its long-term, quality-controlled
recording history, it is commonly used to represent trends throughout Beaufort County. The
recorded mean daily tide range at the station is 6.92 feet. Since the station was established, the
relative mean sea level has risen on average 0.14 inches per year, or 1.4 inches per decade (NOAA,
2025) (Figure 2). As sea levels continue to rise, records of high tide flooding also rise on all U.S.
coastlines. These events are defined as a daily rise in water level above the minor flooding
threshold set locally by NOAA’s National Weather Service (Fly et al., 2017).
Figure 2: Rising mean sea levels recorded at NOAA's Fort Pulaski, GA Tide Station (NOAA, 2025)
An analysis of coastal South Carolina by the US Army Corps of Engineers (USACE) (Table 1)
identified Bluffton as a high-risk coastal hazard area (USACE, 2022). The study focused on storm
surge and sea level rise as those hazards were identified as the greatest threat to negatively impact
coastal populations and infrastructure in the region. Of note is the increasing damage rating for
North and East Bluffton when projecting out from Existing Infrastructure Damage to Future
Infrastructure Damage. These results highlight the need for investigating the vulnerability of future
development to coastal hazards, expanding the breadth of traditional vulnerability assessments
which focus only on existing community assets.
Attachment 2
Resilience Analysis
Page 73
Section 3. Item # 1.
8
Table 1: Future flood cost and damage rating for areas of Beaufort County with Bluffton areas shaded (USACE, 2022, Table 4-16)
County
Census
Place or
Location
Name
State
Identified
as
Existing
High-Risk
Location
Identified
as Future
High-Risk
Location
Existing
Infrastructure
Damage ($)
Damage
Rating
Future
Infrastructure
Damage ($)
Damage
Rating
Beaufort
Hilton Head
Island
SC X X $159,517,000 High $313,723,000 High
Beaufort Port Royal SC X X $10,755,000 Med $21,752,000
Med-
High
Beaufort Beaufort SC X X $7,198,000 Med $14,811,000 Med
Beaufort Shell Point SC X X $1,361,000 Low $2,729,000 Low
Beaufort Burton SC X X $1,109,000 Low $3,661,000
Low-
Med
Beaufort Bluffton SC X X $575,000 Low $2,093,000 Low
Beaufort Yemassee SC n/a n/a $91,000 Low $235,000 Low
Beaufort
North
Beaufort
SC n/a n/a $3,072
Low-
Med
$6,253 Med
Beaufort
East
Beaufort
and St.
Helena
SC n/a n/a $24,206
Med-
High
$41,094 High
Beaufort
Dataw
Island
SC n/a n/a $5,532
Low-
Med
$8,267 Med
Beaufort
Fripp
Island
SC n/a n/a $8,401 Med $17,567
Med-
High
Beaufort
North
Bluffton
SC n/a n/a $23,898
Med-
High
$56,558 High
Beaufort
East
Bluffton
SC n/a n/a $9,634 Med $19,611
Med-
High
Figure 3 shows areas of development and general land use change within Bluffton and in the
surrounding watersheds from 2001 to 2024. There is a significant increase in high density areas
resulting in much higher levels of impervious surface across the study area.
Attachment 2
Resilience Analysis
Page 74
Section 3. Item # 1.
9
Figure 3: Change in land use from National Land Cover Dataset (NLCD) 30m data from 2001 (above)-2024 (below)
Attachment 2
Resilience Analysis
Page 75
Section 3. Item # 1.
10
Resilience Planning Analysis
In order to assess Bluffton’s vulnerability to current and future environmental conditions along
with its changing landscape, Bluffton entered into an agreement with the College of Charleston,
with the support of the South Carolina Sea Grant Consortium (S.C. Sea Grant Consortium), to
conduct a Resilience Planning and Engagement Project (“Resilience Analysis”). The goal of the
Resilience Analysis was to determine the flood vulnerability of Bluffton’s assets and infrastructure
within key watersheds. Bluffton’s aim was to leverage the latest methods of coastal scientific
analysis to inform effective policies and resilience plans. Bluffton also wanted to ensure that public
input was considered in this project with ample community engagement opportunities.
A project team was formed with researchers from the College of Charleston and S.C. Sea Grant
Consortium to conduct this interdisciplinary project. The S.C. Sea Grant Consortium led the
community engagement components and provided project management, while the College of
Charleston performed the mapping, modeling, and discussion of results. As a result of the U.S.
Supreme Court’s Sackett vs. Environmental Protection Agency (EPA) decision, Bluffton identified
wetlands as particular features of interest. Bluffton staff requested an additional assessment of
options for local wetlands protection ordinances in South Carolina. The project team partnered
with the National Sea Grant Law Center to conduct this assessment.
While previous studies have identified sea level rise and tidal flooding as top concerns in coastal
areas, Bluffton is fairly unique in that it has relatively high ground areas relative to neighboring
Lowcountry communities. To assess current and future risk from flooding, a range of modeled
storm events from lower intensity to higher intensity events were analyzed across the landscape
(1-in-2-yr, 1-in-20-yr, 1-in-100-yr, and 1-in-500-yr storm events). These events were intersected
with the property parcels within and surrounding Bluffton to investigate development vulnerability
to flood hazards. In addition to current and future flood conditions, current and future development
conditions were analyzed within this study. A buildout analysis was conducted to project areas of
potential development by subdividing developable parcels to the maximum allowable density
within the geographic information systems (GIS) framework. This allowed researchers to overlay
potential development areas with flood hazards and conduct if/then scenarios to analyze changes
in vulnerability with changing development patterns. The scenarios included analyzing the impact
of protecting wetlands from future development and implementing elevation-based zoning. These
analyses are described in the Methods and Results sections, with discussion following. Results are
presented as mapping products as well as tables and charts describing the number of parcels and
estimated damages of each storm event under each policy scenario. A review of land acquisition
processes and policy options as well as local financial incentives to guide development away from
areas vulnerable to flooding is described in the Discussion section as well.
Study Area
For this study, the datasets collected were based on Hydrologic Unit Codes (HUC-12), using the
watershed boundaries that cross or contain Bluffton jurisdictional boundaries (Figure 4). Studying
flooding using the watershed boundaries ensures that all the data collected will account for water
Attachment 2
Resilience Analysis
Page 76
Section 3. Item # 1.
11
movement that crosses political boundaries and offers a more accurate representation of
hydrological processes. The five (5) different watersheds that make up the study area include the
Upper New River-Atlantic Intracoastal Waterway, the Lower New River-Atlantic Intracoastal
Waterway, the Cooper River-Calibogue Sound, the May River, and the Colleton River. The
analysis of current development flood vulnerability was conducted for the full study area, while
the maximum buildout flood vulnerability was performed within the confines of Bluffton’s
boundary, as this was the area with established Development Agreements in place. A Development
Agreement is a legally binding agreement between local government (such as Bluffton) and
property owner(s) for long-term development of large tracts of land. Each of Bluffton’s
Development Agreements provides for maximum build out and includes general uses, density, and
general site layouts.
Attachment 2
Resilience Analysis
Page 77
Section 3. Item # 1.
1212
Figure 4: Project study area represented by HUC-12 boundaries with Bluffton and Beaufort County jurisdictions shown
Attachment 2
Resilience Analysis
Page 78
Section 3. Item # 1.
13
Community Engagement
Bluffton incorporated community engagement as a core component of this assessment to ensure
the knowledge and perspectives of residents were documented. The methodology for this aspect
was established based on discussions during the project meeting held on June 3, 2024. During this
meeting, Bluffton identified key locations to hold three (3) community outreach events that would
ensure broad representation from citizens. Bluffton also agreed on the scope of work and goals of
the outreach events. To inform residents of these events, a website was created for the project with
event details and social media posts. Bluffton created a flyer, press release, and additional
notifications. Outreach events took place at the Bluffton Rotary Community Center on July 18,
2024, from 6 to 7 PM, Pritchardville Elementary School on August 20, 2024, from 6 to 7 PM, and
at the Historic Bluffton Arts & Seafood Festival on October 19, 2024, from 10 AM to 5 PM (Figure
5).
Figure 5: Photos taken from outreach event at the Historic Bluffton Arts & Seafood Festival (Photo credit SC Sea Grant)
Maps of Bluffton were divided according to the broader community boundaries expected to be
represented at each event. However, residents from various areas attended all the outreach events,
so maps of the entire Bluffton area were included to ensure full coverage. Maps of specific
communities were also provided to help participants easily identify areas of concern. These
unofficial boundaries and communities of interest were identified by Bluffton during a project
meeting. Figure 6 shows an example of the maps provided. Attendees were provided with circle
stickers to mark specific parcels, road sections, wetlands, or any other areas they wished to provide
feedback on, along with adhesive note pads to document their comments. This approach enabled
community members to share their personal experiences with flood hazards, providing a sense of
involvement by their local government.
Attachment 2
Resilience Analysis
Page 79
Section 3. Item # 1.
1414
Figure 6: Example of maps created for outreach events
Flood Reporter Survey
A flood reporter survey was created to document past floods experienced by Bluffton residents.
This was built using Survey123, an ArcGIS software that captures on -the-ground data from
residents to track flood information temporally and spatially. The survey included questions about
the timing of the flooding, water depth and movement, and provided space for residents to upload
photos for visual documentation. Because Survey123 can download spatial information directly
from submissions, an ArcGIS layer was created with all information automatically linked to the
submitters identified location. Paper surveys were distributed and gathered from the outreach
events which were manually entered into the layer, separating markers by survey versus outreach
event as well as date of survey event. Additionally, signs were created and printed by the S.C. Sea
Grant Consortium Communications Team, which asked residents to “tell us about flooding in your
community” with a QR code directing them to the f lood reporter survey. These signs were
displayed in strategic locations by Bluffton staff throughout the study area. Additionally, an online
viewer was created to display the community’s input for Bluffton staff.
Attachment 2
Resilience Analysis
Page 80
Section 3. Item # 1.
15
Selection of Vulnerability Metrics
Vulnerability metrics were curated through a review of literature and selected in collaboration with
Bluffton, ensuring the resulting models were scientifically and practically applicable.
Correspondence via emails and meetings with Bluffton Town staff of the Watershed Management
Division led to the creation of a Coastal Vulnerability Form for Bluffton. The primary purpose of
this form was to gather detailed input on which factors Bluffton considered most crucial in
assessing its specific vulnerabilities to coastal hazards and to determine what data, other than
elevation and imagery, should be included in the model.
Through a literature review of common and applicable metrics used for areas such as coastal South
Carolina, the form was divided by different physical, socio-economic, and ecological
characteristics that totaled 21 possible metrics. Each metric was accompanied by a brief
description and an explanation of its importance in the context of coastal vulnerability. This
ensured that participants understood the significance of each factor before assigning it a rank. The
ranking system allowed respondents to score each metric on a scale from 0 (not essential) to 4
(most important), offering a structured way to assess which factors had the most significant local
impact. The Coastal Vulnerability form was created and distributed by Bluffton’s Project Manager
to groups including Town Council members, Bluffton Senior Staff, Emergency Management,
Growth Management, and the Watershed Management Division.
Policy (Adapted from National Sea Grant Law Center Report [NSGLC-24-04-06])
The National Sea Grant Law Center “Options for Local Wetlands Protection Ordinances in South
Carolina Advisory Report” includes a review of federal regulations of wetlands and implications
of the recent Sackett v. EPA U.S. Supreme Court decision. This includes a discussion of the pre-
Sackett legal landscape of wetlands and jurisdictional determinations of wetlands in Bluffton. The
report also examines existing wetlands regulations in South Carolina and examples of local
wetlands protections in the Southeast region and across the United States. The report provides
municipal options to protect wetlands, and key elements that should be considered if a municipality
decides to develop local wetlands protections are explained. An overview of the results of this
report can be found in the Discussion section. See Figure 7 for a diagram of waterway and wetland
protections based on U.S. Supreme Court rulings through 2023.
Attachment 2
Resilience Analysis
Page 81
Section 3. Item # 1.
16
Figure 7: Wetland protection definition through the different U.S. Supreme Court rulings through 2023 (Sulliván & Gardner, 2023)
Mapping & Modeling
See Appendix E for detailed mapping & modeling methods
Flood vulnerability was analyzed using the First Street Foundation flood dataset with five modeled
storm scenarios ranging from higher frequency, lower impact events such as the 1-in-2-yr storm
to moderate (1-in-20-yr storm) to lower frequency, higher impact events such as the 1-in-100-yr
and 1-in-500-yr storm. These storms were modeled for climate conditions in the year 2023 as well
as projected climate conditions in year 2053 to give two time points of vulnerability. The analysis
was separated into a review of the flood vulnerability of the existing development to-date in
Bluffton as well as a prospective analysis of the vulnerability of future development zones. Each
assessment was performed for every property parcel, with future development parcels created via
a buildout analysis, which simulates the subdivision of all developable parcels into their maximum
Attachment 2
Resilience Analysis
Page 82
Section 3. Item # 1.
1717
development density. Future development vulnerability was summarized based on number of
subdivided parcels touched by flood waters as well as the esti mated damages that would occur if
there were a home built on that property. If/then scenarios were run to show the ways different
policy options could reduce the flood vulnerability of future development within Bluffton. These
policy options included wetland protections, wetland buffers, and elevation-based zoning.
Community Engagement
Each community outreach event was attended by members of the community, with a suspected
increase in participation at the second event due to Tropical Storm Debby impacting the area on
August 8, 2024. Both SC Sea Grant Consortium and the College of Charles ton were represented
at all events, as well as the Watershed Management Staff to ensure all parties behind the research
project were available for questions. There was also an increase in the flood report survey
submissions around the time of Tropical Storm Debby.
Figure 8 shows the data layered over the basic digital elevation model (DEM), showing the
clustering of flood concern in the low-lying areas, as well as an example of the type of information
linked to each data point. The example data point shown in Figure 8 includes information such as
the depth of floodwater, duration of the event, extent of water movement, and any infrastructure
affected (e.g., roads, homes). This detailed local knowledge provides real-world insights, enabling
a more accurate a nd community-informed assessment of flood risks. A total of 89 surveys were
completed with a heat map created (Figure 9) to show the density of where locals reported flood
issues. This is another tool that Bluffton can use when visualizing flooding issues.
Figure 8: Community flood submissions with example submission in right dialogue box
Attachment 2
Resilience Analysis
Page 83
Section 3. Item # 1.
1818
Figure 9: Heat map of community flood submissions with high and low elevations displayed showing clustering in low elevations
Selection of Vulnerability Metrics
A total of 22 responses were collected from the various Bluffton departments and Council
members shown in Figure 10. The results of the Vulnerability Metrics Form shown in Figure 11
provide a clear overview of how Bluffton prioritized vulnerability metrics. Several of the following
top concerns were identified as being feasible within the time constraints of this analysis: Wetland
Loss, Flooding/Inundation, Rainfall -runoff, Storm Frequency, and Intensity. Of the top t wo
concerns for Bluffton staff, water quality was outside of the scope of this analysis, while
Evacuation Routes is a component of an analysis that is forthcoming from the South Carolina
Office of Resilience (SCOR). However, addressing flooding issues in B luffton will also provide
significant benefits to water quality by limiting runoff pollution, protecting natural filtration
systems such as wetlands and riparian zones, preventing erosion, and preserving aquatic
ecosystems.
Attachment 2
Resilience Analysis
Page 84
Section 3. Item # 1.
1919
Figure 1010: Distribution of responses from local government groups . WMD = Watershed Management Division, GM = Growth
Management, EM = Emergency Management, SS = Senior Staff, and TC = Town Council
Figure 1111: Final average ranks of all metrics in the Vulnerability Metrics Form
Attachment 2
Resilience Analysis
Page 85
Section 3. Item # 1.
20
Mapping & Modeling
A total of 99,423 parcels were generated by subdividing remaining developable land within
Bluffton’s development areas to the maximum allowable density. Of those developable parcels,
43% were susceptible to flooding by the 1-in-100-yr storm in year 2023 conditions, rising to 60%
of parcels for the 1-in-500-yr storm. When analyzing future conditions, many of the currently
developed areas see a shift in flood inundation from minor or no flooding in 2023 to more severe
depths of flooding in 2053. This trend was similar for future development, with the lowest intensity
event (1-in-2-yr storm) having a 42% increase in parcels covered by the 2053 event versus the
2023.
The number of developable parcels generated by the buildout analysis (99,423) far exceeded the
number of remaining residential dwelling units under development agreements (5,903). This
surplus of available land allowed for scenario planning to determine the flood risk reduction
different policy applications would have in Bluffton based on the location of future development
in relation to flood hazards. Wetlands accounted for just over half of the vulnerable lands within
development areas for all but the smallest storm scenario (1-in-2-yr). The 1-in-100-yr storm in
year 2023 conditions resulted in 23,733 parcels flooded within wetland areas, resulting in an
estimated $1.84 billion in damages if those parcels were developed. Protecting wetlands plus a 50-
ft buffer protects 25,986 potential parcels that would be flooded with an estimated damage value
of $1.99 billion if those parcels were developed and experienced that size storm event. Within the
50-ft buffer zone itself (excluding wetlands), 2,253 potential parcels experienced flooding by the
1-in-100-yr storm with an associated $153.3 million of estimated damages. When analyzing
elevation zones within each development area, the flood risk is almost entirely within the lower
two out of three elevation zones. The high elevation zone contained less than 6% of flooded parcels
and less than 3% of damages for each storm event. If policies were implemented prioritizing high
elevation zones or protecting wetlands plus a 50-ft buffer, there would be more parcels available
for development than are required based on active Planned Unit Development agreements as of
December 2024.
Land Use and Flow Direction
Figure 12 shows the difference between impervious and pervious surface between the years 2001
and 2024 in the watersheds within and surrounding Bluffton, using NLCD (National Land Cover
Database) data. Another aspect to note is the general water flow direction, which the arrows in the
figure represent. Understanding the complexities of water flow at a watershed level helps
understand where potential runoff will lead (Ongaga et al., 2024). This information is important
for the study of both water quantity as well as water quality.
Attachment 2
Resilience Analysis
Page 86
Section 3. Item # 1.
2121
Figure 1212: Impervious surface in 2001 (above) versus 2024 (below) from US NLCD. Red arrows represent the predominant direction
of water movement through each HUC-12 watershed
Attachment 2
Resilience Analysis
Page 87
Section 3. Item # 1.
22
Current Development Flood Vulnerability
Results indicate an escalating severity of flood depths across all scenarios between 2023 and 2053.
For higher-frequency events (1-in-2-yr storm), many parcels experiencing minor flooding in 2023
are projected to face more inundation by 2053. The driver of this increased inundation is the
increased level of precipitation expected for each storm scenario by 2053, which is incorporated
into the flood models used in this study. This progression highlights areas where previously
manageable events may increasingly disrupt properties, infrastructure, ecosystems, and daily life
of Bluffton citizens. In the less frequent, high-impact flood scenarios (1 in-100-yr and 1-in-500-yr
storms), the analysis reveals a stark rise in flood depths, exposing parcels previously outside major
flood risk to considerable future hazard. Figure 13 shows the difference between a 1-in-2-yr flood
scenario (a flood event that has a 50% chance of occurring each year) and a 1-in-100-yr flood
scenario (a flood that has a 1% chance of occurring in any given year) in 2023, showcasing the
expansion of the number of parcels effected between the least and most likely flood occurrences
under current conditions. See Appendix A for parcel maps of vulnerability for each flood scenario
and year conditions for the study area.
Attachment 2
Resilience Analysis
Page 88
Section 3. Item # 1.
2323
Figure 1313: 1-inin-2-2-yr versus 1-inin-100-yr flood scenarios for 2023
Attachment 2
Resilience Analysis
Page 89
Section 3. Item # 1.
24
Maximum Buildout Flood Vulnerability
A total of 99,423 parcels were generated by subdividing remaining developable land within
Bluffton’s development areas to the maximum allowable density (Figure 14). See Appendix B for
results presented for each PUD. For the 1-in-100-yr storm with 2023 conditions, 42,852 parcels
(43%) experienced some level of flooding. The parcels containing flood waters increased with
each increasing storm scenario intensity, with the 2053 storm conditions increasing the
vulnerability compared to the 2023 conditions. The proportion of parcels that experienced an
increase in flooding from 2023 to 2053 storm scenarios declined with each progressively larger
storm event, with a 42% increase in the 1-in-2-yr storm and a 27% increase for the 1-in-20-yr
storm, declining down to 8% and 4% increases for the 1-in-100-yr and 1-in-500-yr storms
respectively (Table 2, Figure 15). This indicates that future conditions will yield a greater increase
in flood impacts from storms that are more likely to occur on a year-to-year basis relative to current
impacts from these events. The 2053 storm conditions covered 5% (4,514) of the total buildout
parcels in the 1-in-2-yr storm while the 1-in-500-yr storm covered 63% (62,454) of the total
buildout parcels. This highlights the need for strategic growth in these areas to reduce vulnerability
to future flood hazards.
Table 2: Vulnerable buildout parcels for each flood scenario and each study year with the percentage increase in parcels when
going from 2023 to 2053 conditions
Year 1-in-2 1-in-20 1-in-100 1-in-500
2023 3,182 22,137 42,852 59,825
2053 4,514 27,052 46,082 62,454
Percent Increase
2023-2053 42% 22% 8% 4%
Attachment 2
Resilience Analysis
Page 90
Section 3. Item # 1.
25
Figure 14: Parcels touched by flood waters of the 1-in-500-yr storm event (red) and those not touched by those flood waters
(green) for year 2023 flood conditions
Attachment 2
Resilience Analysis
Page 91
Section 3. Item # 1.
2626
Figure 1515: Vulnerable buildout parcels (thousands) for each flood scenario with year 2053 flood conditions shown in addition to
year 2023 flood conditions
Forested Wetlands Analysis
When analyzing the buildout parcels that cover the wetlands in Bluffton, these parcels represent
just over half of the vulnerability for all but the lowest intensity event (1 -inin-2-2-yr) (Figure 16). As
climate conditions worsen in the year 2053, a greater number of buildout parcels are impacted by
each storm event, whi le the proportion of parcels that fall within wetland areas for those future
events remain relatively constant. Only 8% of the 1 -inin-2-2-yr storm vulnerability is within wetland
areas for the year 2023; however, that proportion grows to 23% for the year 2053. For parcels
inundated by the 1 -inin-100-yr storm, 55% (23,733) were within wetland areas accounting for an
estimated $1.84 billion in damages if those parcels were developed and impacted in year 2023
condtions. The damage models showed similar trends with r oughly equal proportions of damage
within and outside of wetlands as the parcel analysis revealed. For the highest intensity scenario
(1(1-inin-500-yr storm) in 2023 conditions, roughly $3.11 billion in damages were accounted for by
the parcels within wetlands versus $2.94 billion in damages outside of wetlands. These numbers
rose by roughly $475 million for wetlands and $420 million for non-wetlands when accounting for
year 2053 conditions. These results indicate that, while lower severity events are distributed across
the landscape, wetland areas are critical to absorbing the waters of higher intensity events.
There were ample buildout parcels available in non-wetland areas to fully reach the development
goals of each PUD without future wetland development. Bu ckwalter PUD had the lowest
proportion of available non -wetland parcels compared to remaining dwelling units in the PUD
agreement, yet still had five times more buildout parcels available in non -wetland areas than are
required (Table 3). See Appendix C for results presented for each PUD.
Attachment 2
Resilience Analysis
Page 92
Section 3. Item # 1.
2727
Figure 1616: Vulnerable buildout parcels (thousands) for each flood scenario and each study year with parcels within freshwater
wetlands (orange) shown in addition to those outside of those wetlands (blue)
Table 3: Planned Unit Developments analyzed with non -wetland parcels shown for each, remaining dwelling units from each
Development Agreement, and the percent of those remaining units that would be reached with only non-wetland buildout parcels
Planned Unit
Development
Non-Wetland
Available
Remaining
Dwelling Units
Proportion
Non-Wetland
Buckwalter 10,960 2,176 504%
Jones Estate 4,597 413 1,113%
New Riverside 10,408 724 1,438%
Palmetto Bluff 28,335 2,515 1,127%
Shultz Tract 604 6666 915%
Village at Verdier 200 9 2,222%
Because Bluffton lies slightly inland, the wetlands that now fall under unprotected land have
increased, based off National Wetlands Inventory data showing emergent wetlands within
Bluffton’s boundary (Figure17). Several of these wetland areas are already slated as potential
medium density residential and commercial land use zones. The current definition of WOTUS
allows the development of these areas shown in Figure 17 from a federal perspective, despite the
potential hazards that may occur.
Attachment 2
Resilience Analysis
Page 93
Section 3. Item # 1.
2828
Figure 1717: Overlay of unprotected emergent wetland over hybrid imagery (top) and future land use plans (bottom)
Attachment 2
Resilience Analysis
Page 94
Section 3. Item # 1.
29
Wetland Buffers
An analysis of buffer zones surrounding wetlands was conducted for a 25-ft buffer, 50-ft buffer,
and 100-ft buffer using the 1-in-100-yr storm scenario with 2023 conditions. Over 1/3 of all
available buildout parcels were vulnerable to floodwaters within each buffer distance.
Protecting wetlands plus a 50-ft buffer protects 25,986 potential parcels that would be flooded
with an estimated damage value of $1.99 billion if those parcels were developed and
experienced this size storm event. Within the 50-ft buffer zone itself, 2,253 potential parcels
experienced flooding with an associated $153.3 million of estimated damages. Going from a 25-
ft to a 50-ft buffer increases modeled protections by an additional 1,098 parcels and $75.5
million of potential damages. Increasing the buffer size to 100-ft adds additional protection to
1,784 potential parcels with $129.2 million in estimated damages compared to the 50-ft buffer;
however, the proportion of total parcels protected is slightly less in this zone (33% compared to
36%). There were substantial buildout parcels available in areas outside of wetlands and a 50-ft
buffer to fully reach the development goals of each PUD (Table 4).
Table 4: Planned Unit Developments analyzed with remaining dwelling units from each Development Agreement, parcels available
outside of a 50-ft wetland buffer shown for each, and the percent of those remaining units that would be reached with only non-
buffer buildout parcels
Planned Unit Development
Remaining
Dwelling Units
Available Outside
50-ft Buffer
Proportion Available
Outside 50-ft Buffer
Buckwalter 2,176 9,004 414%
Jones Estate 413 4,185 1013%
New Riverside 724 8,833 1220%
Palmetto Bluff 2,515 26,208 1042%
Shultz Tract 66 539 817%
Village at Verdier 9 187 2078%
Elevation Analysis
Subdividing each development zone into elevation groups of low (Marginal Land), moderate
(Moderate Risk), and high elevation (Low Risk) reveals distinct patterns in the vulnerability of
developable land within Bluffton’s boundaries (Figure 18). For all but the highest intensity event,
the majority of vulnerable buildout parcels fall within the Marginal Lands of Bluffton, with 92%
of the vulnerable parcels within this category for the lowest intensity event (1-in-2-yr storm). The
Moderate Risk category holds an increasing proportion of vulnerability as the storm intensity
increases. This could be due to the number of Marginal Lands being close to fully occupied with
flood waters during higher intensity events and therefore water reaching higher elevations during
those events. For the year 2053, 85% of buildout parcels in Marginal Lands were covered by flood
conditions for the 1-in-100-yr storm, with 94% covered by the 1-in-500-yr storm. The Low-Risk
group showed very little vulnerability for each of the flood scenarios, with 0 parcels affected by
the 1-in-2-yr storm and only 6% for the highest 1-in-500-yr storm, with numbers rising by 1-3
percentage points with each rising level of storm severity. The damage models showed an even
greater proportion of damage accounted for by Marginal Lands, with 74% of damages occurring
within this category for the 1-in-20-yr storm and an average of 58.5% of damages for the 1-in-
Attachment 2
Resilience Analysis
Page 95
Section 3. Item # 1.
3030
500-yr storm, with those damages coming from 41.5% of parcels flooded by that event. The Low-
Risk areas accounted for an even smaller proportion of damage than the parcels analysis showed,
with only 3% of the damage in this elevation group for the 1-inin-500-yr storm. This indicates that,
while any flood waters on a property are impactful, the lower elevation groups are experiencing
greater flood depths and therefore greater flood damage in these models.
Enough available land exists within the Low Risk zone to meet all PUD agreements, while a
combination of Low and Moderate Risk parcels contains at least six times more parcels than ar e
required in each area (Table 5). See Appendix D for results presented for each PUD.
Figure 1818: Vulnerable buildout parcels (thousands) for each flood scenario and each study year with parcels from each elevation
group that are touched by that flood condition shown
Table 5: Planned Unit Developments analyzed with Low and Moderate Risk parcels shown for each, remaining dwelling units from
each Development Agreement, and the percent of that maximum that would be reached with Low Risk as well as Low and
Moderate Risk buildout parcels
Planned Unit
Development
Remaining
Dwelling
Units
Low Risk
Available
Proportion
Low Risk
Moderate Risk
Available
Proportion Low
+ Moderate Risk
Buckwalter 2,176 2,923 134% 18,669 992%
Jones Estate 412 1,045 254% 1,779 685%
New Riverside 724 2,880 398% 10,857 1,897%
Palmetto Bluff 2,515 8,976 357% 22,444 1,249%
Shultz Tract 6666 176 267% 721 1,359%
Village at
Verdier 9 4040 444% 241 3,122%
0
1010
2020
3030
4040
5050
6060
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Elevation Groups - Buildout Parcel Vulnerability
Marginal Land
Moderate Risk
Low Risk
Attachment 2
Resilience Analysis
Page 96
Section 3. Item # 1.
31
This section contains recommendations by College of Charleston faculty and partners
Overall, Bluffton has several options to enact protections for non-jurisdictional wetlands and other
vulnerable areas. These include but are not limited to: providing protections by amending existing
zoning codes, establishing overlay districts and elevation-based zoning, adopting wetland-specific
ordinances, strengthening floodplain management policies, establishing public-private and non-
profit partnerships, strengthening/implementing financial incentives, implementing land
acquisition policy options, and applying for land acquisition grant programs with the help of
organizations, like The Nature Conservancy and The Open Land Trust. The exact framework for
resilience initiatives in Bluffton will depend on how restrictive Bluffton wants to be regarding
development, how much power their zoning/development authority has, and the municipality’s
staff and financial capacity to implement and enforce programs and policies.
Zoning and Overlay Recommendations
The evaluation of forested wetlands and elevation zones within Bluffton’s boundaries highlights
the resilience benefit of additional policy protections, while maintaining the ability to reach
development goals established through PUD agreements. Locally protecting freshwater wetlands,
which recently lost federal protection, could cut the vulnerability of Bluffton’s future development
in half. Additionally, elevation-based zoning has the potential to dramatically reduce the
vulnerability of future development. The clustering of community flood submissions in low lying
areas further supports the argument for elevation-based zoning by Bluffton, as it highlights current
flood vulnerabilities that could potentially be avoided in future development areas with strategic
growth planning. The City of Charleston, SC is an example of a municipality in South Carolina
that is recommending elevation-based zoning for future consideration (City of Charleston, 2021).
The City of Norfolk, VA underwent an ordinance rewrite to protect sensitive areas as well as
incentivize development in higher elevations of the municipality through coastal resilience and
upland resilience overlays (Pew, 2019).
For local governments where state wetland regulations are either in flux after Sackett or are being
drastically rolled back, adopting comprehensive zoning ordinances may not be feasible. In the final
report by the National Sea Grant Law Center, overlay zoning districts, which layer additional
environmental protections on top of existing zoning, seem to be one of the more feasible solutions
for Bluffton. Dekalb County, GA, uses this method to protect environmentally sensitive areas, and
the local board defines what qualifies as "environmentally sensitive" based on local needs (DeKalb
County, Georgia, n.d.). This flexibility could be key for Bluffton, where specific environmental
issues, such as flooding and wetland preservation, need a targeted approach (Drescher et al., 2014).
Overlay districts allow municipalities to address these concerns without navigating hurdles that
may arise in zoning changes. Overlays or other forms of permitting requirements do not restrict or
prohibit all forms of development but rather require local approval prior to beginning a project to
ensure sensitive areas are protected. Additionally, as Bluffton already has a historical preservation
overlay and a Preserve District, establishing a wetlands protection overlay may comply well with
the zoning code. Although Bluffton’s Preserve District allows for very little development and
therefore protects wetland areas within the district, Bluffton might consider expanding the
Attachment 2
Resilience Analysis
Page 97
Section 3. Item # 1.
32
coverage of the Preserve District to cover other sensitive environmental areas through a Zoning
Map amendment.
Lastly, a different overlay that Bluffton could consider implementing is a marsh migration area
overlay district, which would help designate areas that can support future marsh migration as
resource protection through shoreland zoning. Flood protection-based requirements as shown in
an example from Hilton Head Island were deemed another viable option for Bluffton based on the
municipal structure for the Town of Hilton Head Island (n.d.). Like the overlay, this option doesn’t
require a large change in Bluffton’s ordinance or zoning in order to adopt and reach their goals,
like other more burdensome policy tools may. The use of overlay zoning districts and flood
protection requirements presents a viable and less disruptive solution. The National Sea Grant Law
Center found that these strategies have been successfully implemented in other local governments,
allowing them to protect environmentally sensitive areas (DeKalb County, Georgia, n.d.). By
adopting similar approaches, this is a possible avenue for Bluffton to effectively safeguard its
wetlands while maintaining political and developmental flexibility. For example, Bluffton’s
updated 2021 flood damage ordinance, which does not restrict development within flood hazard
areas, could be adapted to provide wetlands protection, similar to Hilton Head’s ordinance.
Per the final report by the National Sea Grant Law Center, wetlands protection at the municipal
level varies widely from very restrictive of all development to not very restrictive. Some
municipalities, like Tampa, FL do not limit development as much as simply impose additional
requirements/approval for developers to get prior to beginning their activities. The level of
protection often depends on whether there are state-level protections and requirements in place. In
Washington and Virginia, the state has provided requirements and model ordinances for
municipalities to adopt which allows for these ordinances to be more comprehensive and for
development to be more restricted at the local level. These models are not replicable everywhere
as not every state has deferred such power to the local level. As federal and state wetlands
regulations continue to change, it will be up to municipal governments to find and adopt the best
fit for them when they want to further protect these vital resources.
Financial Incentive Recommendations
Bluffton may also consider strengthening local financial incentive programs to guide development
away from vulnerable areas susceptible to flooding and to protect wetlands. Bluffton could
enhance its current Transfer of Development Rights (TDR) program by offering more significant
development density incentives in receiving areas to ensure that growth is concentrated in
appropriate zones. At the same time, Bluffton could narrow the areas designated as "sending areas”
to focus on the most flood-prone or environmentally sensitive lands.
Other incentives might include tax abatements (tax breaks), streamlined permitting processes, or
discounted application fees for development that occur outside vulnerable areas. Bluffton could
also consider impact fees, special study fees, or environmental protection fees for development in
sensitive areas. These measures would discourage growth in wetlands while helping offset the
costs of structural flood protection and conservation initiatives.
Attachment 2
Resilience Analysis
Page 98
Section 3. Item # 1.
33
Land Acquisition Policy Options and Recommendations
In addition to regulatory strategies, land acquisition remains a critical tool for advancing
conservation and flood mitigation goals in Bluffton. Among available approaches, maintaining
and strengthening partnerships with land trusts operating in this area of the state, such as the Open
Land Trust (OLT) and The Nature Conservancy (TNC), stand out as particularly effective. These
partners bring technical expertise, funding mechanisms, and longstanding experience in
negotiating with private landowners and securing conservation easements to protect critical
floodplains and wetland systems.
Fee simple acquisitions—such as Bluffton’s 44-acre purchase from Palmetto Bluff—should
continue to be pursued for high-priority parcels, particularly those vulnerable to flooding.
Partnering with TNC and OLT to jointly fund and manage future acquisitions would increase
Bluffton’s capacity to conserve key properties while minimizing municipal financial burden.
Bluffton may also benefit from articulating a long-term vision for land use and growth over a 50-
year planning horizon. Incorporating projections for sea-level rise, storm surge, and other climate-
related risks into future land use decisions will provide a forward-looking framework to guide
sustainable development. Land use planning should align with existing state and regional
conservation resources, including the South Carolina Conservation Bank map, the Southeast
Conservation Adaptation Strategy (SECAS) blueprint, and the South Atlantic Salt Marsh Initiative
(SASMI) map.
A flexible suite of acquisition options can further support Bluffton’s conservation objectives. For
example, Bluffton could consider using rolling easements to protect coastal and flood-prone lands.
These easements provide flexibility by allowing conservation protections to migrate inland as the
landscape changes due to sea-level rise or erosion, offering long-term resilience benefits. The
inland shift could be guided by a clear benchmark, such as the average elevation of the highest
daily tides (the mean higher high water, or MHHW), to ensure consistency and transparency over
time.
To guide land acquisition investment, a tiered approach based on risk and opportunity may be
helpful. In lower-risk scenarios, the purchase of conservation easements can reduce land value and
attract conservation-minded buyers. In medium-risk situations, Bluffton may benefit from
coordinating with partner organizations to acquire land for public use, with the potential for state
or federal reimbursement. For higher-risk or more complex acquisitions, Bluffton could consider
purchasing large tracts outright, then selling portions of the land under conservation easements to
offset costs.
Bluffton should maximize credit under the FEMA Community Rating System (CRS) by ensuring
that conserved land, including those tied to development agreements, are eligible. Doing so could
reduce flood insurance premiums and enhance Bluffton’s overall resilience. Large tracts such as
Palmetto Bluff should be prioritized as undeveloped lands become more limited.
Finally, Bluffton may consider strengthening its Land Acquisition Fund by identifying new and
diversified revenue sources. Potential mechanisms include a small fee on home sales in new
Attachment 2
Resilience Analysis
Page 99
Section 3. Item # 1.
34
Planned Unit Developments (PUDs), conservation contributions in development agreements, and
permit-linked development fees. Simultaneously, optimizing future PUD layouts by encouraging
cluster development and maximizing open space preservation could enhance ecological function
while maintaining allowable density.
Review of Local/State and Federal Land Acquisition Programs
Collaborating with land trusts which are eligible to apply for many of these grants, are effective
strategies Bluffton can take to leverage existing funding opportunities.
State Grant Programs:
1. Beaufort County Green Space Program
o Supports land conservation and preservation in Beaufort County.
o Continue submitting applications to this program, especially for corridor
preservation along the May River.
2. South Carolina Conservation Bank (SCCB)
o Provides grants for the voluntary conservation of natural resources, working
lands, and historic sites.
3. South Carolina Office of Resilience (SCOR) Buyout Program
o Focuses on relocating residents from flood-prone areas and restoring the natural
function of floodplains.
4. South Carolina Resilience Revolving Fund
o Assists local governments and homeowners with acquiring and restoring flood-
prone properties.
5. South Carolina Lowcountry Sentinel Landscape
o Supports conservation in ecologically significant areas to sustain military
readiness while protecting natural resources.
Federal Grant Programs:
1. Section 319 Nonpoint Source (NPS) Program
o Improves water quality by addressing nonpoint source pollution, including from
septic systems.
2. Coastal Wetlands Conservation Grant Program
o Funds acquisition, restoration, and management of coastal wetlands ecosystems.
Attachment 2
Resilience Analysis
Page 100
Section 3. Item # 1.
35
3. North American Wetlands Conservation Act (NAWCA) Program
o Supports conservation of wetlands and migratory bird habitats across North
America.
4. Land and Water Conservation Fund (LWCF) Program
o Provides funding for the acquisition of land for parks, outdoor recreation, and
public access.
5. Flood Mitigation Assistance (FMA) Program
o Funds flood mitigation projects, including voluntary property acquisitions, to
reduce long-term flood damage.
Attachment 2
Resilience Analysis
Page 101
Section 3. Item # 1.
36
City of Charleston. (2021). Charleston City Plan. Retrieved 10 February, 2025 from
https://www.charleston-sc.gov/DocumentCenter/View/31227/Final-City-Plan-Adopted-October-12-2021
Connell, H. (2024). Application of Coastal Vulnerability Models Toward Future Land Use Planning in the
Town of Bluffton, SC, USA. Proquest.
DeKalb County, Georgia. (n.d.). Code of ordinances. Municode Library. Retrieved 25 November, 2024
from https://library.municode.com/ga/dekalb_county/codes/code_of_ordinances
Drescher, S., Ellis, K., Berg, C., Caraco, D., & Hoffmann, G. (2014). Low impact development in coastal
South Carolina: A planning and design guide. National Oceanic and Atmospheric Administration.
https://repository.library.noaa.gov/view/noaa/42004
Fly, E., Bath, S., & Brennan, A. (2017). U.S. Climate Resilience Toolkit. Retrieved 7 February, 2025 from
https://toolkit.climate.gov/case-studies/lowcountry-lowdown-sea-level-rise
National Oceanic and Atmospheric Administration (NOAA). (2025). Relative Sea Level Trend 8670870
Fort Pulaski, Georgia. Retrieved 7 February, 2025 from
https://tidesandcurrents.noaa.gov/sltrends/sltrends_station.shtml?id=8670870
National Sea Grant Law Center (2024). Options for Local Wetlands Protection Ordinances in South
Carolina (NSGLC-24-04-06). Retrieved 6 November, 2024 from
https://nsglc.olemiss.edu/Advisory/pdfs/sc-wetland-protection.pdf
Ongaga, C. O., Makokha, M., Obiero, K., Kipkemoi, I., & Diang’a, J. (2024). Urbanization and
hydrological dynamics: a 22-year assessment of impervious surface changes and runoff in an urban
watershed. Frontiers in Water, 6, 1455763. https://doi.org/10.3389/frwa.2024.1455763
Pew Charitable Trusts. (2019). Norfolk’s Revised Zoning Ordinance Aims to Improve Flood Resilience.
Retrieved 10 February, 2025 from https://www.pewtrusts.org/en/research-and-analysis/issue-
briefs/2019/11/norfolks-revised-zoning-ordinance-aims-to-improve-flood-resilience
Sulliván, S. M. P., & Gardner, R. C. (2023). US Supreme Court opinion harms watersheds. Science,
381(6656), 385-385. https://doi.org/10.1126/science.adj0227
Town of Bluffton. (2020). May River Watershed Action Plan Update & Modeling Report. Retrieved from
https://www.townofbluffton.sc.gov/226/May-River-Watershed-Action-Plan
Town of Bluffton. (2022). South Carolina Comprehensive Plan. Retrieved from
https://www.townofbluffton.sc.gov/203/Planning
Town of Hilton Head Island. (n.d.). Section 16-6-102: Wetlands protection. Hilton Head Island Land
Management Ordinance. Retrieved 25 November, 2024, from
https://library.municode.com/sc/hilton_head_island/codes/land_management_ordinance?nodeId=CH16-
6NAREPR_SEC.16-6-102WEPR
USACE (United States Army Corps of Engineers). (2022). The South Atlantic Coastal Study. Retrieved
from https://chs.erdc.dren.mil/Home/Library
Attachment 2
Resilience Analysis
Page 102
Section 3. Item # 1.
3737
Appendix A: Current Development Flood Vulnerability Result
Figure 1919: Current development parcel vulnerability to the 1-inin-2-2-yr storm in 2023 conditions
Attachment 2
Resilience Analysis
Page 103
Section 3. Item # 1.
3838
Figure 2020: Current development parcel vulnerability to the 1-inin-20-yr storm in 2023 conditions
Attachment 2
Resilience Analysis
Page 104
Section 3. Item # 1.
3939
Figure 2121: Current development parcel vulnerability to the 1-inin-100-yr storm in 2023 conditions
Attachment 2
Resilience Analysis
Page 105
Section 3. Item # 1.
4040
Figure 2222: Current development parcel vulnerability to the 1-1-inin-500-yr storm in 2023 conditions
Attachment 2
Resilience Analysis
Page 106
Section 3. Item # 1.
4141
Figure 2323: Current development parcel vulnerability to the 1-inin-2-2-yr storm in 2053 conditions
Attachment 2
Resilience Analysis
Page 107
Section 3. Item # 1.
4242
Figure 2424: Current development parcel vulnerability to the 1-inin-20-yr storm in 2053 conditions
Attachment 2
Resilience Analysis
Page 108
Section 3. Item # 1.
4343
Figure 2525: Current development parcel vulnerability to the 1-inin-100-yr storm in 2053 conditions
Attachment 2
Resilience Analysis
Page 109
Section 3. Item # 1.
4444
Figure 2626: Current development parcel vulnerability to the 1-inin-500-yr storm in 2053 conditions
Attachment 2
Resilience Analysis
Page 110
Section 3. Item # 1.
4545
Appendix B: Maximum Buildout Flood Vulnerability Results
This appendix contains results of the maximum buildout flood vulnerability analysis for each
Planned Unit Development (PUD) considered within this study. Results are displaye d as number
of buildout parcels which are touched by flood waters in each of the model scenarios for each
study year (2023, 2053).
Please note: the vertical scale bar displaying number of parcels has a different range for each chart,
with Schultz Tract an d Village at Verdier in hundreds of parcels versus thousands for the other
PUDs in this study.
Figure 2727: Vulnerable buildout parcels (thousands) for each flood scenario with year 2053 flood conditions shown in addition to
year 2023 flood conditions (larger PUDs shown). BW = Buckwalter, JE = Jones Estate, NR = New Riverside, PB = Palmetto Bluff
0
1010
2020
3030
BWBW JEJE NRNR PBPB BWBW JEJE NRNR PBPB BWBW JEJE NRNR PBPB BWBW JEJE NRNR PBPB
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Buildout Parcel Vulnerability (PUDs)
2023
2053
Attachment 2
Resilience Analysis
Page 111
Section 3. Item # 1.
4646
Figure 2828: Vulnerable buildout parcels ( hundreds) for each flood scenario with year 2053 flood conditions shown in addition to
year 2023 flood conditions (smaller PUDs shown). ST = Schultz Tract, VV = Village at Verdier
0
1
2
3
4
5
STST VVVV STST VVVV STST VVVV STST VVVV
1-in-2 1-in-20 1-in-100 1-in-500
Hundreds of ParcelsHundreds of Parcels
Buildout Parcel Vulnerability (PUDs)
2023
2053
Attachment 2
Resilience Analysis
Page 112
Section 3. Item # 1.
4747
Appendix C: Forested Wetlands Analysis Results
This appendix contains results of the forested wetlands analysis for each Planned Unit
Development (PUD) considered within this study. Results are displayed as number of buildout
parcels which are touched by flood waters in each of the model scenarios for each study year
(2023, 2053).
Please note: the vertical scale bar displaying number of parcels has adifferent range for each PUD
so that the full range of data can be best visualized for each figure. A major point of difference is
that the vertical scales for Schultz Tract and Village at Verdier are in hundreds of parcels versus
thousands for the other PUDs in this study.
Figure 2929: Vulnerable Buckwalter buildout parcels (thousands) for each flood scenario and each study year with parcels within
freshwater wetlands (orange) shown in addition to those outside of those wetlands (blue)
0
5
1010
1515
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Wetlands - Buildout Parcel Vulnerability
Buckwalter
Non-Wetland
Wetland
Attachment 2
Resilience Analysis
Page 113
Section 3. Item # 1.
4848
Figure 3030: Vulnerable Jones Estate buildout parcels (thousands) for each flood scenario and each study year with parcels within
freshwater wetlands (orange) shown in addition to those outside of those wetlands (blue)
Figure 3131: Vulnerable New Riverside buildout parcels (thousands) for each flood scenario and each study year with parcels within
freshwater wetlands (orange) shown in addition to those outside of those wetlands (blue)
0
1
2
3
4
5
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Wetlands - Buildout Parcel Vulnerability
Jones Estate
Non-Wetland
Wetland
0
5
1010
1515
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Wetlands - Buildout Parcel Vulnerability
New Riverside
Non-Wetland
Wetland
Attachment 2
Resilience Analysis
Page 114
Section 3. Item # 1.
4949
Figure 3232: Vulnerable Palmetto Bluff buildout parcels (thousands) for each flood scenario and each study year with parcels within
freshwater wetlands (orange) shown in addition to those outside of those wetlands (blue)
Figure 3333: Vulnerable Schultz Tract buildout parcels ( hundreds) for each flood scenario and each study year with parcels within
freshwater wetlands (orange) shown in addition to those outside of those wetlands (blue)
0
5
1010
1515
2020
2525
3030
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Wetlands - Buildout Parcel Vulnerability
Palmetto Bluff
Non-Wetland
Wetland
0
1
2
3
4
5
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Hundreds of ParcelsHundreds of Parcels
Wetlands - Buildout Parcel Vulnerability
Schultz Tract
Non-Wetland
Wetland
Attachment 2
Resilience Analysis
Page 115
Section 3. Item # 1.
5050
Figure 3434: Vulnerable Village at Verdierbuildout parcels (hundreds) for each flood scenario and each study year with parcels within
freshwater wetlands (orange) shown in addition to those outside of those wetlands (blue)
0
1
2
3
4
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Hundreds of ParcelsHundreds of Parcels
Wetlands - Buildout Parcel Vulnerability
Village at Verdier
Non-Wetland
Wetland
Attachment 2
Resilience Analysis
Page 116
Section 3. Item # 1.
5151
Appendix D: Elevation Analysis Results
This appendix contains the results of the elevation analysis for each Planned Unit Development
(PUD) considered within this study. Results are displayed as number of buildout parcels which are
touched by flood waters in each of the model scenarios for each study year (2023, 2053).
Please note: the vertical scale bar displaying number of parcels has a different range for each PUD
so that the full range of data can be best visualized for each figure. A major point of difference is
that the vertical scales fo r Schultz Tract and Village at Verdier are in hundreds of parcels versus
thousands for the other PUDs in this study.
Figure 3535: Vulnerable Buckwalter buildout parcels (thousands) for each flood scenario and each study year with parcels from each
elevation group that are touched by that flood condition shown
0
5
1010
1515
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Elevation Groups - Buildout Parcel Vulnerability
Buckwalter
Marginal Land
Moderate Risk
Low Risk
Attachment 2
Resilience Analysis
Page 117
Section 3. Item # 1.
5252
Figure 3636: Vulnerable Jones Estate buildout parcels (thousands) for each flood scenario and each study year with parcels from
each elevation group that are touched by that flood condition shown
Figure 3737: Vulnerable New Riverside buildout parcels (thousands) for each flood scenario and each study year with parcels from
each elevation group that are touched by that flood condition shown
0
1
2
3
4
5
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Elevation Groups - Buildout Parcel Vulnerability
Jones Estate
Marginal Land
Moderate Risk
Low Risk
0
5
1010
1515
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Elevation Groups - Buildout Parcel Vulnerability
New Riverside
Marginal Land
Moderate Risk
Low Risk
Attachment 2
Resilience Analysis
Page 118
Section 3. Item # 1.
5353
Figure 3838: Vulnerable Palmetto Bluff buildout parcels (thousands) for each flood scenario and each study year with parcels from
each elevation group that are touched by that flood condition shown
Figure 3939: Vulnerable Schultz Tract buildout parcels (hundreds) for each flood scenario and each study year with parcels from each
elevation group that are touched by that flood condition shown
0
5
1010
1515
2020
2525
3030
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Thousands of ParcelsThousands of Parcels
Elevation Groups - Buildout Parcel Vulnerability
Palmetto Bluff
Marginal Land
Moderate Risk
Low Risk
0
1
2
3
4
5
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Hundreds of ParcelsHundreds of Parcels
Elevation Groups - Buildout Parcel Vulnerability
Schultz Tract
Marginal Land
Moderate Risk
Low Risk
Attachment 2
Resilience Analysis
Page 119
Section 3. Item # 1.
5454
Figure 4040: Vulnerable Village at Verdier buildout parcels (hundreds) for each flood scenario and each study year with parcels from
each elevation group that are touched by that flood condition shown
0
1
2
3
4
2023 2053 2023 2053 2023 2053 2023 2053
1-in-2 1-in-20 1-in-100 1-in-500
Hundreds of ParcelsHundreds of Parcels
Elevation Groups - Buildout Parcel Vulnerability
Village at Verdier
Marginal Land
Moderate Risk
Low Risk
Attachment 2
Resilience Analysis
Page 120
Section 3. Item # 1.
55
Appendix E: Mapping and Modeling Methods
Vulnerability Mapping
Digital Elevation Models (DEMs) and Digital Surface Models (DSMs) were created for the full
study area (see Appendix F). The DEM represents the most accurate and up to date
geomorphological representation of Bluffton and surrounding HUC-12 boundaries. A contextual
analysis was additionally performed using NLCD (National Land Cover Database) data from 2001
and 2024 to analyze changing development conditions.
The flooding data selected for this analysis was the First Street Foundation flood dataset obtained
via use agreement from the South Carolina Office of Resilience (SCOR). Provided by this state
agency, the dataset is regarded as an authoritative model for flood risks in the region, having been
used for the state’s Strategic Statewide Resilience and Risk Reduction Plan. Its credibility as a
vetted source helps to minimize potential disputes related to flood mapping. To determine the
mean flood depth per parcel to understand what areas of Bluffton had the most susceptibility to
inundation, zonal statistics were applied to SCOR First Street flood data. This data includes
scenarios for 1-in-2-, 1-in-20-, 1-in-100-, and 1-in-500-year flooding for the years of 2023 and
2053, resulting in comparison of current and future conditions.
Current Development Flood Vulnerability
Parcel-based flood depth analysis for Bluffton highlights areas most susceptible to flooding, both
now and under future projections. Using zonal statistics with flood data and Bluffton parcel data,
mean flood depths per parcel were calculated across flood scenarios of 1-in-2-, 1-in-20-, 1-in-100-
, and 1-in-500-year flooding for 2023 and 2053. Flood depths were categorized based on the
College of Charleston’s Flood Disruption Scale, which describes flood disruption based on impacts
to access the parcel. The lowest flooding hazard (0–4 inches of flood depth) represents nuisance
flooding while the most extreme flooding (over 36 inches) indicates potentially life-threatening
conditions that could necessitate emergency rescue. This classification offers a real-world
understanding of the severity of projected flood depths, emphasizing that future conditions may
require significant adaptation and planning to manage both everyday flooding and more extreme
events. Tabular analyses were generated summarizing the extent of flooding across various land
use categories obtained from Bluffton’s GIS data. This dataset provides insights into Bluffton’s
current flood exposure and its expected increase under future climate conditions.
Maximum Buildout Flood Vulnerability
A buildout analysis was conducted to analyze the potential future flood vulnerability of Bluffton.
The purpose of the buildout analysis was to simulate the subdivision of all developable parcels
into their maximum development density in order to run future flood vulnerability models as well
as if/then scenarios. Since it is impossible to forecast the exact location of future development, the
analysis was run for all developable parcels regardless of the cap on maximum dwelling units.
Maximum dwelling units refer to the highest number of individual residential units allowed to be
built on a specific piece of land, as defined by Bluffton’s zoning regulations. All of the
development agreements have had residential development occur since the agreement was
executed, so the number of remaining dwelling units for each development area was obtained from
Bluffton as of December 2024. The number of remaining dwelling units (homes that have yet to
Attachment 2
Resilience Analysis
Page 121
Section 3. Item # 1.
56
be built but are authorized in the agreement) were utilized to determine whether certain policy
conditions would still allow the necessary development to occur within each Planned Unit
Development (PUD).
To obtain maximum buildout conditions, the active PUD agreements within Bluffton’s jurisdiction
were obtained from Bluffton staff as well as the municipality’s website. Maximum allowed density
for single family residential units was obtained from each PUD agreement, which designates the
smallest home lot size and therefore the maximum number of homes that are allowable per acre
(e.g. 1/4-acre lot size = 4 homes per acre). Parcels coded as R/W (right of way) were first removed
from the parcel database. Parcels within zoning categories of PUD (Planned Unit Development),
AG (Agricultural), and RG (Residential General) were isolated for analysis, as those zoning
districts have established maximum density of development standards either through Development
Agreements or the Unified Development Ordinance (UDO). Only parcels equal to or greater than
five (5) acres were included in the buildout analysis, as that is the standard size used for these
analyses representing likely areas for subdivision. Next, the following National Wetlands
Inventory (NWI) categories were grouped to represent either SC Department of Environmental
Services Critical Area or open water inland systems and therefore unlikely to be subdivided for
development: Estuarine and Marine Deepwater, Estuarine and Marine Wetland, Freshwater Pond,
Lake, Riverine. The Erase tool was used to remove any parcels or segments of parcels which
overlapped those features.
The remaining parcels were then subdivided based on the maximum allowed density obtained from
the zoning documents (e.g. 8 dwelling units per acre = 1/8-acre subdivided parcels) resulting in
buildout parcels. The water layer from the 2021 NOAA Coastal Change Analysis Program (C-
CAP) land cover data was then isolated and any buildout parcels still overlapping water features
were removed. Next, the buildout parcels were intersected with road network data and any areas
of overlap were removed. This resulted in the maximum buildout for each of the development
areas of Bluffton with maximum allowed densities established. The maximum buildout performed
here produced far more parcels than what will be realized within Bluffton’s boundaries; however,
it demonstrates the locations of potential development. Next, the average depth of flooding for
each flood scenario for the years 2023 and 2053 was assigned to each buildout parcel using the
zonal statistics tool. An additional analysis was conducted to determine buildout parcels with and
without any level flooding.
To calculate potential damage if every parcel were developed, there first needed to be a home
value assigned to each of the buildout parcels. This home value was assigned by downloading the
U.S. Census Bureau 2021 American Community Survey (ACS) 5-year Block Group Dataset for
the area and assigning the average home value for each Block Group to the buildout parcel
contained within it. A Jupyter Notebook was then written to recreate depth-damage-curves from
the USACE Economic Guidance Memorandum (EGM) 04-01, Generic Depth-Damage
Relationships for Residential Structures with Basements. These curves assign a generalized
percentage of damage which would result from different depths of flooding depending on the size
and type of the home, which is based on actual losses from flood events. Since the development in
this analysis is theoretical and it is unknown the size of these future buildings, the damage
Attachment 2
Resilience Analysis
Page 122
Section 3. Item # 1.
57
functions for 1-story and 2 or more story structures without basements were averaged to result in
a single depth-damage-curve for the study area. This methodology assumes half of the future
structure will be 1-story structures and half will be 2 or more stories. It also assumes that all homes
are slab on grade. A USACE Chief of Economics confirmed the validity of this application.
Potential flood damage for each scenario was then calculated by multiplying the average flood
depth by the depth-damage-curve for each buildout parcel.
Forested Wetlands Analysis
An analysis was conducted to determine the potential vulnerability reduction resulting from
limiting future development within wetland areas that are no longer protected because of the
Sackett decision. The buildout parcels from the Maximum Buildout Flood Vulnerability analysis
were overlaid with the following NWI categories representing freshwater wetlands: Freshwater
Emergent Wetland, Freshwater Forested/Shrub Wetlands (Figure 41). The total damages for each
scenario were calculated for the buildout parcels overlaying those wetland features demonstrating
the potential damages reduced by limiting future development in these areas.
Attachment 2
Resilience Analysis
Page 123
Section 3. Item # 1.
5858
Figure 4141: National Wetlands Inventory (NWI) categories within and surrounding the Town of Bluffton
Attachment 2
Resilience Analysis
Page 124
Section 3. Item # 1.
59
Elevation Analysis
An additional analysis was conducted to determine the potential vulnerability reduction resulting
from prioritizing development in upland zones within each development area. The average
elevation was first calculated for each of the buildout parcels by using the zonal statistics tool on
the DEM created in prior steps. Next, the mean and standard deviation of elevations within each
development zone (e.g. individual PUDs, AG, or RG) were calculated with buildout parcels
assigned to categories of low, moderate, or high elevation. Low elevation parcels were defined as
those with an elevation of more than one standard deviation less than the mean, moderate elevation
parcels had an elevation within one standard deviation +/- of the mean, and high elevation parcels
had an elevation greater than one standard deviation higher than the mean. These zones were
labeled Marginal Land for low elevation, Moderate Risk for moderate elevation, and Low Risk for
high elevation (Figures 42 and 43). The total damages for each scenario were then calculated for
the buildout parcels in each elevation category within each development zone.
Attachment 2
Resilience Analysis
Page 125
Section 3. Item # 1.
60
Figure 42: Elevations within and surrounding Bluffton
Attachment 2
Resilience Analysis
Page 126
Section 3. Item # 1.
61
Figure 43: Elevation groups generated for buildout analysis
Attachment 2
Resilience Analysis
Page 127
Section 3. Item # 1.
62
Appendix F: Digital Elevation Models (DEMs) and Digital Surface Models (DSMs)
DSMs, including an all-points DSM, upper story DSM, mid-story DSM, and lower story DSM
were produced. Simultaneously, the generation of DEMs such as the Last Return DEM, Ground
Return DEM, was created to capture current terrain characteristics precisely (Tanim et al., 2023).
LiDAR data was accessed from South Carolina LiDAR Data Access. Desired data was obtained
by selecting Beaufort County and navigating to Data Access, NOAA LAS Bulk Download. This
dataset included data for the entire state of SC. Data for Bluffton was downloaded from Block 6,
based on information provided by the 2020 USGS Lidar: Savannah Pee Dee, SC website. After
downloading the LiDAR data files, they were extracted and converted to LAS format for usability.
The resolution is 2 points per square meter, with a 0.71-meter nominal point spacing.
The Geoprocessing Tool used to create the DEM and DSM from the las data points was the LAS
Dataset to Raster tool. Due to the flat topography and nature of LAS data, the chosen interpolation
type of Binning, cell assignment of Inverse Distance Weighting (IDW), and Void Fill Method of
Natural Neighbor was chosen. In order to achieve maximum resolution from the DEM and DSM
raster, a sampling value of 2 was chosen, due to the data’s 0.71-meter nominal point spacing,
converted to feet and adjusted to minimize interpolation error.
Attachment 2
Resilience Analysis
Page 128
Section 3. Item # 1.
6363
Appendix G: Supplemental Information: Supplemental Information
Figure 4444: Online (left) Survey123 form and paper (right) form for community flood observationsOnline (left) Survey123 form and paper (right) form for community flood observationsOnline (left) Survey123 form and paper (right) form for community flood observations
Attachment 2
Resilience Analysis
Page 129
Section 3. Item # 1.
Source: Town of Bluffton website. First collected Nov 7, 2026.