PUBLIC WORKS
COMMITTEE MEETING
MONDAY, MARCH 6, 2023 | 6 PM
3rd Committee Meeting
The Committee will meet in Mauldin City Hall at 5 East
Butler Road in the Council Chambers at 6 p.m.
The meeting will be available remotely through Zoom. Please visit the City’s website at
https://cityofmauldin.org/your-government/meeting-minutes-agendas/ to access the
meeting via audio and videoconferencing.
A quorum of Council will be present.
1
PUBLIC WORKS COMMITTEE MEETING
MARCH 6, 2023, 6PM
CITY HALL - COUNCIL CHAMBERS
5 E. BUTLER ROAD
Committee Members: Jason Kraeling (Chair), Carol King, Michael Reynolds
1. Call to Order
2. Publ
ic Comment
3. Reading and Approval of Minutes
a.Public Works Committee Meeting: February 6, 2023 [Pages 3-6 ]
4. Reports or Communications from City Officers
a. PW Director Matthew Fleahman
i. Bu dget Review
5. Unfinished Business
There is no unfinished business.
6. New Business
a.GLDTC Participation Agreement 600.01 [Pages 7-10]
7. Public Comment
8. Committee Concerns
9. Adjournment
The Honorable Jason Kraeling
The Ho
norable Jason Kraeling
The Honorable Jason Kraeling
The Ho
norable Jason Kraeling
T
he Honorable Jason Kraeling
The Honorable Jason Kraeling
The Honorable Jason Kraeling
The Honorable Jason Kraeling
2
MINUTES
PUBLIC WORKS COMMITTEE MEETING FEBRUARY 6, 2023, 6PM
CITY HALL - COUNCIL CHAMBERS 5 E. BUTLER ROAD
4th committee meeting
Committee Members: Jason Kraeling (Chair) and Carol King. Committee member Michael
Reynolds was not present.
Others present: PW Director Matt Fleahman and City Administrator Seth Duncan
1. Call to Order- Chairman Kraeling
2. Public Comment- None
3. Reading and Approval of Minutes
a. Public Works Committee Meeting: January 3, 2023
Motion: Councilwoman King made a motion to approve the minutes with Chairman
Kraeling seconding.
Vote: The vote was unanimous (2-0).
4. Reports or Communications from City Officers
The division budgets look good.
a. Limb & Leaf Laydown Yard
The facility at East Standing Springs will be modified for limb and leaf storage. The
Jenkins Street facility where these are currently stored has been sold. A concrete
pad will be poured in the back corner of the property. The work will be done in-house.
b. E. Butler Road Sewer Relocation
As part of the Butler Road project, sewer pipes will be removed from the roadway and
relocated to the right-of-way. Staff went out and did a survey of the Butler Road corridor
of pipes and manholes. Any point where DOTs design is in conflict, we had to redesign.
The design has been finalized. Moving everything will cost about $4 million.
Chairman Kraeling asked when this has to be done. Mr. Fleahman answered once the
utilities are relocated, it will in time for the new budget process. Staff will do everything
to bring that total down. This has to be done, and there is no way around it.
5. Unfinished Business- There is no unfinished business.
3
6. New Business
a. Public Works Parking Lot Repaving RFP
Authorization is requested to execute a contract between the City of Mauldin and
Panagakos Asphalt Paving, Inc. (Panagakos) for the repaving of the Public Works Facility
Parking Lot. The City allocated $250,000 in its Capital Improvement Plan for the 2022 –
2023 annual budget for the repaving of the parking lot. The lowest bid was $269,823 by
Panagakos. It is recommended that $25,000 be pulled from the sewer fund to cover the
difference.
Motion: Councilwoman King made a motion to send this item to Council with Chairman
Kraeling seconding.
Councilwoman King asked if the Finance Director was in agreement that the $25,000 be
pulled from sewer. Mr. Duncan answered yes, it was her idea.
Vote: The vote was unanimous (2-0).
b. Sale of Old/Damaged Equipment
With the purchase of new trucks and equipment over the past three years, Public Works
now has several old, outdated, and/or damaged equipment which is stored at the Public
Works Facility. Municipalities have historically gotten rid of the old equipment at
auctions. This process requires staff hours to both set up and manage the process. This
whole process can now be managed easily with the use of the Gov Deals website. Public
Works does not use any of the items currently, nor does the department intend to use in
the future. All revenue from the sale of the equipment will be added to the General Fund
for the City of Mauldin.
Motion: Councilwoman King made a motion to send this item to Council with Chairman
Kraeling seconding.
Vote: The vote was unanimous (2-0).
c. KCI Task Order 1 Amendment
Task Order 01 has been completed with the exception of the public meetings and the
Flooding and Erosion Assessment Report. These items will be assessed later in the
Stormwater Master plan. Due to their later inclusion, it is recommended to eliminate
these items from Task Order 01. The City allocated 1,129,724 dollars in year one of the
ARPA spending to fund necessary stormwater management projects that improve the
City’s stormwater infrastructure systems. The engineering services associated with this
4
task order were proposed at 226,600. Amending the task order to eliminate one section
reduces the cost 25,000 dollars to a total of $201,600.
Motion: Councilwoman King made a motion to send this item to Council with Chairman
Kraeling seconding.
Vote: The vote was unanimous (2-0).
d. KCI Task Order 2 Amendment
Authorization is requested to approve an amendment to Task Order 02 with KCI to
provide stormwater asset inventory, on-call GIS services, stormwater modeling, grant
assistance, and a City-Wide Stormwater Master Plan. The engineering services associated
with this task order are proposed at $411,600. Removing GIS services from the Task
Order ($10,500) and increasing the additional fee to complete the asset survey ($165,000)
brings the services associated with this task to $566,100.
Motion: Councilwoman King made a motion to send this item to Council with Chairman
Kraeling seconding.
Councilwoman King asked if this would be funded through ARPA. Mr. Fleahman
answered yes.
Vote: The vote was unanimous (2-0).
7. Public Comment-
Mr. Fleahman said staff needs some direction on a proposed development at Ashmore Bridge
near Bonnie Brae. The annexation agreement stipulates Metro Connects be the sewer
provider.
The proposed 90 townhomes cannot connect to sewer without a pump station. The
Annexation agreement would have to be amended. This will have to go back to the Planning
Commission. City Council needs to decide if they want another pump station. If we do this,
there will be an ordinance to put fees on tax bills. If the City does not want another pump
station, the development would still have to receive planning commission approval. There is
no guarantee the commission would approve the development. It is 12 acres.
Mr. Duncan said this could be brought to committee next month with more information from
staff. Councilwoman King said she is concerned with 90 townhomes on 12 acres as well
as another pump station. That is a densely populated area already.
8. Committee Concerns- None
5
9. Adjournment- Chairman Kraeling adjourned the meeting at 7:11 p.m.
Respectfully Submitted,
Cindy Miller
Municipal Clerk
6
PUBLIC WORKS COMMITTEE
AGENDA ITEM
MEETI
NG DATE: March 6, 2023
AGE
NDA ITEM: 6a
TO:
Public Works Committee
FROM: Public Works Director, Matthew Fleahman
SUBJECT: GLDTC Participation Agreement
REQUEST
The Public Works Department is requesting Committee and Council to authorize the City of Mauldin 2023
paving schedule under the Greenville Legislative Delegation Transportation Committee (GLDTC) Project
#600.01.
HISTORY/BACKGROUND
In 2021, IMS conducted an evaluation of the City’s road inventory and presented Council with a five-year
paving schedule. The City paved sixty (60) roadways for a total of 11.74 miles during the 2021 calendar
year. In 2022, the City paved seventeen (17) roadways for a total of 2.51 miles.
ANALYSIS or STAFF FINDINGS
In the Council approved FY2022-2023 budget, $372,622 was budgeted in the Streets Division of the Public
Works Department for Road Paving. The GLDTC cost share for this project is $189,996.78. Follow ing
the road paving list provided from IMS the City will pave 1.27 miles of roadway along: Sweetland Ct ,
Middleton Ln, New Commerce Ct, Setters Ct, Sickle Ct, Ashwood Ave, and Mapleton Dr.
FINANCIAL IMPACT
The cost for the FY2022-2023 road paving is budgeted at $372,622.
RECOMMENDATION
Staff recommends the Public Works Committee and the City Council approve the GLTDC Participation
Agreement for the repaving of the City’s roadway inventory.
7
PARTICIPATION AGREEMENT
Greenville Legislative Delegation Transportation
Committee Project # 600.01
Dated: February 21, 2023
WHEREAS, the City of Mauldin desires the Greenville Legislative Delegation
Transportation Committee (GLDTC) to assist the City of Mauldin in the resurfacing
of various roads/streets within the city limits of the City of Mauldin as part of the
Municipal Match Resurfacing Program for FY 22-23, known as GLDTC Project #
600.01; and
WHEREAS, the GLDTC is a duly authorized agent of the State of South Carolina with
the authority to enter into contracts necessary for the proper discharge of its functions and
duties; and
WHEREAS, the City of Mauldin is duly authorized to enter into contracts necessary for
the proper discharge of its functions and duties; and
WHEREAS, the GLDTC has agreed to assist the City of Mauldin with GLDTC Project #
600.01; and
NOW THEREFORE, in consideration of the several promises to be faithfully performed
by the parties hereto as set forth, the GLDTC and the City of Mauldin do hereby agree as
follows:
Project Description:
The project is divided into two (2) parts as follows:
a) Preliminary Engineering (PE): Includes field stakeout, compilation of contract
quantities, Bid Proposal Preparation, Advertisement and receipt of bid
packages, bid evaluation and recommendation for award.
b) Construction, Engineering and Inspection (CEI): Includes monitoring the
actual construction performance, construction inspection, sampling testing of
materials, recommendation for contractor payments, and other items
associated tasks as necessary.
The term PROJECT is intended to refer to the above two Parts collectively unless
otherwise indicated.
__________ ___________
City initial GLDTC initial
Page 1
8
PARTICIPATION AGREEMENT
Greenville Legislative Delegation Transportation
Committee Project # 600.01
Dated: February 21, 2023
COMMITTED PROJECT FUNDING:
GLDTC: $189,996.78 (50%)
City of Mauldin: $372,622.00 (50% + additional))
The GLDTC shall:
a) Provide the GLDTC’s cost share for the PROJECT, not to exceed the
$189,996.78; and
b) Provide all preliminary engineering services, bid advertisement, awarding of
construction contract, inspection of contractor work during execution of
contract, and sampling and testing of construction procedures for compliance
with all State and local requirements; and
c) Verify all contractor pay requests prior to payment.
The City of Mauldin shall:
a) Provide construction funding equal to the commitment of $372,622.00; and
b) Provide funds for all cost overruns (if any).
The GLDTC shall:
a) Enter into and execute all necessary contracts required to complete the
approved project; and
b) Be responsible for approval of payment requests and payments of all
contractors and subcontractors pay requests; and
c) Secure from the City of Mauldin all remaining funds as described
below.
__________ ___________
City initial GLDTC initial
Page 2
9
PARTICIPATION AGREEMENT
Greenville Legislative Delegation Transportation
Committee Project # 600.01
Dated: February 21, 2023
The City of Mauldin shall:
a) Pay all GLDTC invoices within 30 days; and
b) Make 1st Partial Payment of 50% of the matching funds on May 1st
2023; and
c) Make 2nd Partial Payment of 25% of the matching funds on July 1st
2023; and
d) Make Final Payment of 25% and cost overruns, if any, of the matching
funds on November 30th, 2023.
Note: Every possible effort will be made to utilize 100% of the available funding for the
execution of this contract. However: due to factors beyond everyone’s control (PG64-22
price adjustment, utility conflicts, contract underruns/overruns, etc.) it will be impossible
to exactly match the dollar amount of funding to the final dollar amount of the work.
Therefore: the GLDTC will “roll-forward” to the next Municipal Match Program any
surpluses or deficits of funds.
This document may not be modified or revoked without the written consent of all
parties.
_________________________________________________
For: the City of Mauldin (name and title) (date)
__________________________________________________
Greenville Legislative Delegation Transportation Committee Chairman (date)