Town of Mount Pleasant
Bids and Purchases Committee
Monday, October 5, 2026
Municipal Complex, Council Chambers
100 Ann Edwards Lane, Mount Pleasant, SC 29464
Minutes
Click here to listen to recording
PowerPoint Presentation
1. Call To Order
Chairman Daniel Brownstein called the Bids and Purchases Committee
meeting to order at 8:00 AM on Monday, October 5, 2026. He noted that
many in attendance had spent the prior weekend at the local high school
homecoming. A brief moment of silence was observed. Council
Members Mike Tinkey and Alex Crosby were present.
2. Approval Of Minutes From The August 31, 2026 Meeting
Motion to approve the minutes from the August 31, 2026, meeting was
made by Council Member Alex Crosby and seconded by Council
Member Mike Tinkey. The motion carried 3-0.
3. Public Comment
Mr. Brownstein invited members of the public to address the committee.
No members of the public came forward, and the public comment period
was closed.
4. Employee Years Of Service
Ms. Harness recognized Kathy Frame for 10 years of service with the
Town of Mount Pleasant. Ms. Harness outlined Mrs. Frame’s extensive
background, noting more than 35 years of public procurement
experience, including 25 years of procurement experience in the Federal
Government arena including various procurement roles such as
Contracting Officer, Deputy Regional Acquisition Executive for the
General Services Administration, and Contract Manager for the
Bids and Purchases
October 5, 2026
Page 2
Department of Homeland Security. She added that Mrs. Frame later
worked as a consultant supporting firms with federal contracts before
joining the Town in 2016, where she has since served in procurement
roles, including Procurement Officer.
Ms. Harness praised Ms. Frame as thorough, detail-oriented, and
compliance-driven, noting that she ensures all procurements are
conducted in accordance with Town policies and protocols, and that she
is consistently a team player regardless of her workload.
5. Award Of The FY27 Lease-Purchase Financing Agreement For
Vehicles And Equipment
Ms. Harness presented the item, explaining that the Town had solicited
proposals for a 5-year lease-purchase financing agreement with an
acquisition value of $2,500,000 for vehicles approved in the FY27
budget resolution. Nine proposals were received. The institution offering
the lowest overall interest rate, inclusive of any additional fees, was TD
Equipment Finance Incorporated, at a rate of 4.26%.
Mr. Brownstein noted for the public's benefit that the equipment to be
financed includes four garbage trucks, a loader, a backhoe, two mini
dump trucks, and three pickup trucks.
Council Member Mike Tinkey asked about PNC Bank's proposal, and
Ms. Harness explained that PNC had included legal fees in their
submission, which ultimately elevated their total cost above TD
Equipment Finance's fee-free proposal.
Staff recommended awarding the financing to TD Equipment Finance
Incorporated. Ms. Harness noted that, as a debt obligation, this action
must be forwarded to the full Town Council, which must name the lessor
by resolution.
Motion to recommend approval of the FY27 Lease-Purchase Financing
Agreement to the full Town Council was made by Council Member Mike
Tinkey and seconded by Council Member Alex Crosby. The motion
carried 3-0.
6. Award Of A Contract For Shem Creek Dredging
Ms. Harness presented the item, explaining that the Town solicited bids
for dredging at three locations along Shem Creek: the Town's shrimp
docks, the floating day dock, and the fixed lease docks. The project
Bids and Purchases
October 5, 2026
Page 3
involves the removal of up to 6,520 total cubic yards of material and is
funded in part through a federal legislative earmark administered via an
award agreement between the South Carolina Department of Parks,
Recreation, and Tourism and the Town. The dredging window runs from
December 1, 2026, through March 1, 2027, with all work to be
completed by April 1, 2027.
Two bids were received. Staff determined Banks Construction Company
to be the lowest responsive and responsible bidder at $1,179,220.
Ms. Crosby asked how frequently Shem Creek requires dredging. Town
staff Kevin Mitchell, Deputy EDS Director, explained that the timeline
varies based on sediment accumulation — the shrimp docks being the
most pressing area — and that the floating docks and fixed pier had not
been dredged since 2014. Staff noted that state appropriations of over
$1,000,000, secured in part through the efforts of Christiane Farrell,
Assistant Town Administrator and the State, were instrumental in making
this project possible.
Mr. Tinkey inquired about the effect of the repositioned Crab Bank on
sedimentation in Shem Creek. Staff acknowledged the question but
noted that a dedicated study would be required to draw conclusions. Mr.
Tinkey also asked about the environmental benefits of dredging, and Mr.
Mitchell explained that increased water exchange and removal of
accumulated sediment at the bottom of the creek produce meaningful
water quality improvements, characterizing this as fundamentally an
environmental project.
When asked about the disposal site for the dredged material, Mr.
Mitchell confirmed that the sediment would be barged — not trucked
through neighborhoods — to the South Carolina Ports dredge disposal
site at the tip of Daniel Island, which had already been secured.
Mr. Brownstein commended Town staff for their proactive approach in
securing federal and state funding, emphasizing the importance of
maintaining Shem Creek as a working and vibrant waterfront.
Council Member Mike Tinkey motioned to approve the contract award
for Shem Creek Dredging to Banks Construction Company in the
amount of $1,179,220 and to forward the recommendation to the full
Town Council. The motion was seconded by Council Member Alex
Crosby. This motion was corrected to remove forwarding to full Town
Council as that was not necessary. The revised motion carried 3-0.
Bids and Purchases
October 5, 2026
Page 4
7. Award Of A Contract For Construction Engineering And
Inspection Services For The Billy Swails Boulevard – Section 4B
Project
Ms. Harness explained that construction engineering and inspection
(CE&I) services are required for the Billy Swails Boulevard Section 4B
project. A recommendation for a different firm had been presented in
June 2026, but SCDOT award concurrence for that firm was not
received, necessitating a new proposal from another approved on-call
engineering firm. Staff determined that Mead & Hunt Incorporated
should perform the CE&I services, which include quality assurance
inspection, independent assurance services, EEO compliance including
Davis-Bacon reviews, and inspection and testing. The completion date
for these services is November 7, 2027.
Staff recommended awarding the contract to Mead & Hunt Incorporated,
pending SCDOT award concurrence, in the amount of $466,171.39.
Mr. Tinkey commended staff and specifically acknowledged the efforts of
Town representatives in working to preserve a Heritage Tree at the
beginning of the Billy Swails Boulevard corridor. Town Staff, Rion
Longfellow, Project Engineer, confirmed that an arborist's
recommendations are being followed and that the contractor is actively
working to save the tree. Mr. Longfellow noted the project is
approximately 15% complete with a fall 2027 completion target.
Motion to approve the contract award for CE&I services for the Billy
Swails Boulevard – Section 4B Project to Mead & Hunt Incorporated in
the amount of $466,171.39, pending SCDOT award concurrence, was
made by Council Member Alex Crosby and seconded by Council
Member Mike Tinkey. The motion carried 3-0.
8. Award Of A Design Contract For The Shem Creek Boardwalk
Replacement Project
Ms. Harness presented the item, explaining that staff had identified GEL
Engineering LLC, an approved on-call consultant, to perform
engineering design services for the replacement of Shem Creek
Boardwalk 1, Boardwalk 2, and the timber pile-supported portion of
Boardwalk 3 west of the pre-engineered pedestrian bridge. The tasks for
this project include project management, oversight, coordination, a
boardwalk pile as-built, survey along boardwalks to be replaced, limited
boundary survey, survey along east portion of boardwalk 3, development
of construction documents, and permitting application package. Design
Bids and Purchases
October 5, 2026
Page 5
and permitting are estimated to take 12 months. Staff recommended
contracting GEL Engineering LLC in the amount of $378,978.
Town Staff, Andrew Weis, Public Services Director, provided additional
context, noting that the boardwalks are inspected every few years and
that recent inspections have shown increasing deterioration. He clarified
that this is not a CIP project but will be funded with CMP funds and likely
phased over time. The design contract will produce engineered drawings
and secure permits necessary to proceed with replacements.
Mr. Weis noted that the Town is exploring more resilient materials,
including fiberglass pilings in place of wood pilings and composite
decking — the latter of which has already been installed in areas subject
to regular flooding with strong results. Mr. Brownstein observed that
saltwater, wind, and tidal conditions are particularly harsh on the
structures, and Mr. Weis confirmed this, adding that the goal is materials
that are lower maintenance and more resilient. Mr. Weis confirmed that
material options would be evaluated and presented as part of the design
process.
Mr. Tinkey asked whether the design would consider elevation changes,
and Mr. Weis indicated no elevation changes are anticipated at this time
but that the drawings will clarify all necessary details.
Motion to approve the design contract for the Shem Creek Boardwalk
Replacement Project with GEL Engineering LLC in the amount of
$378,978 was made by Council Member Alex Crosby and seconded by
council Member Mike Tinkey. The motion carried 3-0.
9. Award Of A Design Contract For Pitt Street Bridge Feasibility
Study
Ms. Harness presented the item, explaining that GEL Engineering LLC
was also selected to perform engineering services for a feasibility study
of the Pitt Street Bridge and Causeway. The study includes a feasibility
analysis of repairing or installing sheet piles to protect deteriorating
seawalls at Pitt Street Causeway and Bridge, as well as a feasibility
analysis of a fishing pier — either in the same location as the existing
pier or in a new adjacent location. Conceptual renderings and estimated
construction costs for all options will be developed. The scope also
includes causeway improvements such as improved pathways, native
plantings, and outdoor lighting, as well as an archaeological assessment
expected to take four months. The full feasibility study is expected to be
Bids and Purchases
October 5, 2026
Page 6
completed within six months of contract award. Staff recommended
contracting GEL Engineering LLC in the amount of $318,387.
Mr. Tinkey expressed strong support for approaching the Pitt Street
Bridge as a historically significant structure — noting it has a history
spanning 250 years and is widely recognized as a defining feature of
Mount Pleasant — and emphasized the importance of exploring options
that are sensitive to the historical character of the site, including the
tabby walls and buttress walls.
Town Staff, Andrew Weis, Public Services Director provided substantial
additional context. He noted that rough cost estimates for tabby wall
restoration have ranged from $11,000,000 to $15,000,000–$20,000,000,
which is why the Town is exploring all options — including sheet pile
encasement of the existing tabby wall as a preservation measure
pending future restoration funding, rather than its removal. He explained
that the pier component of the study is necessary because the existing
pier is likely too low to meet current flood standards, and options for
improving the existing pier or constructing a parallel pier while
conserving historical elements will be evaluated. The study will also
include limited geotechnical work to better understand the condition and
depth of the existing pilings. Ms. Crosby asked if the bridge would be
closed for the entire time. Mr. Weis noted the bridge will not be closed
for extended periods during the study phase, though brief closures for
geotechnical testing may be necessary. Mr. Tinkey asked if the
archeological work was being subcontracted to Brockington. Mr. Weis
noted that Brockington Associates will serve as the archaeological
subconsultant, which Mr. Tinkey characterized as "the gold standard."
Mr. Brownstein asked if the project would be phased. Mr. Weis
confirmed that the intent, per Council direction, remains to address the
bridge as a single construction project, though the ultimate scope and
phasing will depend on costs revealed through the feasibility study. He
indicated the project would need to be permitted and that work would
likely be scheduled for the off-season, with no firm construction timeline
yet established
Mr. Brownstein called for the vote to approve the award of the design
contract for the Pitt Street Bridge Feasibility Study with GEL Engineering
LLC in the amount of $318,387. The vote carried 3-0.
Bids and Purchases
October 5, 2026
Page 7
10. Award Of A Contract For 516 Coleman Boulevard Parking Lot
Construction
Mr. Brownstein noted at the outset that the full Town Council had
expressed a desire to weigh in on this project and immediately moved to
defer the item to Town Council with no recommendation.
The motion was seconded by Council Member Alex Crosby.
Ms. Harness explained that the Town had solicited bids for the
construction of a parking lot at 516 Coleman Boulevard. The scope of
work includes concrete sidewalk and curb construction, pipe installation,
two EV charging stations, asphalt paving, grass pavers, tree planting,
tree relocation per ANSI A300 Part 6 by a certified arborist and a
pollinator garden. Work also includes pavement marking and striping.
The construction period is 150 calendar days from notice to proceed.
Ms. Harness explained that during the bid qualification process, the
apparent low bidder, Palmetto Tractor Services of South Carolina LLC,
was asked to verify one line item. A subcontractor error was identified,
and a revised bid was submitted, resulting in a corrected base bid of
$453,219.21. Following review, staff determined Palmetto Tractor
Services of South Carolina LLC to be the lowest responsive and
responsible bidder. Town Staff further recommended awarding the base
bid plus Add Alternate B — which involves conveying stormwater via
underground pipe rather than underground storage, the latter having
been deemed excessive in cost — for a total recommended award of
$588,883.64.
Mr. Brownstein asked what Alternate B was and Town Administrator,
Eric DeMoura noted that it was direct pipe as underground storage
detention was too expensive.
Town Staff, Project Engineer Rion Longfellow confirmed that the project
maintains the existing number of parking spaces, adds two EV charging
spaces, and adds five boat trailer parking spaces to help alleviate
pressure on the nearby Shem Creek boat landing. The bid price for tree
relocation is $52,500.
Mr. Tinkey stated that he would vote against the motion to defer,
expressing the view that the project had already been discussed at
length and should move forward. He further indicated that he would
prefer the matter not to go to Town Council.
Ms. Crosby raised a question about the ingress and egress arrangement
for boats and trailers. Town Administrator, Eric DeMoura clarified that
vehicles enter from one roadway and exit onto Simmons Street, and that
Bids and Purchases
October 5, 2026
Page 8
the angled parking design accommodates boat trailers with a proper
circulatory flow.
Mr. Brownstein noted the connection between this project and the
Charleston County Parks and Recreation Commission's concurrent effort
to expand parking at the Shem Creek boat ramp, which had recently
appeared before the Design Review Board.
Motion to defer the award of contract for 516 Coleman Boulevard
Parking Lot Construction to the full Town Council with no
recommendation was made by Council Member Daniel Brownstein and
seconded by Council Member Alex Crosby. The motion carried 2-1, with
Council Member Tinkey opposed.
11. Adjourn
Council Member Brownstein adjourned the meeting at 8:34 a.m.
Respectfully submitted by,
Katie Wagner
October 5, 2026