_03022026-2132
Town of Mount Pleasant · Charleston County · meeting of Mar 2, 2026 · Minutes
Open the original document More from Town of Mount Pleasant
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
TOWN OF MOUNT PLEASANT SC
WATER SUPPLY AND RESOURCES COMMITTEE
Monday, March 2, 2026
9:15 a.m.
Municipal Complex, Council Chambers
100 Ann Edwards Lane, Mount Pleasant, SC 29464
MINUTES
Listen to recording here
1. Call To Order
Chairman Jake Rambo called the meeting to order at 9:20 a.m. Council
Members Howard Chapman and Laura Hyatt were present.
2. Approval Of Minutes From The August 4, 2025 meeting
Council Member Chapman moved to approve the minutes from the
August 4, 2025 meeting. Council Member Hyatt seconded the motion.
The motion passed unanimously.
3. Public Comments
There were no public comments.
4. Mount Pleasant Waterworks program and projects update
Mr. Allan Clum, General Manager of Mount Pleasant Water Works
delivered a comprehensive presentation regarding Mount Pleasant
Waterworks projects and initiatives.
Water Supply and Resources Committee
March 2, 2026
Page 2 of 9
Water Supply and Resources Committee
March 2, 2026
Page 3 of 9
There were two projects that Mr. Clum wanted to speak about. The first
being the Fleet Maintenance Facility project.
The next project is the Deep Well 6 project, which involves drilling into
the Gramling Aquifer at approximately 2,500 feet deep - the deepest well
the utility has ever drilled. The project represents a significant
infrastructure investment as the current well at Deep Well 6 is failing
after 50 years of service.
Water Supply and Resources Committee
March 2, 2026
Page 4 of 9
Layne Drilling was awarded the contract, with Jeff Hart assigned as the
well driller. Hart was notably the driller who rescued the Chilean miners
in 2010 after being called from Afghanistan where he was drilling wells
for the US government. Mr. Clum expressed confidence in Hart's
expertise for this challenging project.
Council Member Jake Rambo requested clarification on the significance
of drilling into the Gramling versus the Middendorf aquifer. Mr. Clum
explained that Mount Pleasant Water Works currently operates five
active wells in the Middendorf Aquifer, also known as the Charleston
Aquifer. This aquifer has been heavily used in the region for
approximately 60 years and has become depressurized through usage.
The Gramling Aquifer represents an untapped resource deeper than the
Charleston Aquifer, with no other entities currently using that water
source. This new well is expected to provide a sustainable water
resource for 100 years or beyond, particularly serving the north end of
Mount Pleasant where the water resource is critically needed.
The presentation continued with recognition of recent awards received
by Mount Pleasant Water Works.
The utility received a National Environmental Achievement Award for
Septic initiatives, having connected over 120 families to the collection
system over the past two years and implementing a septic maintenance
Water Supply and Resources Committee
March 2, 2026
Page 5 of 9
program serving approximately 35 individuals who cannot tie into the
collection system.
An Advanced Utility System Pioneering Excellence Award was received
for the 2025 metering system upgrade, which was completed in-house
rather than contracted out, saving approximately $360,000 for
customers.
Additionally, a 2026 Innovation Award was received for advancements
made with AMI meters, including innovative installations of gaskets for
Water Supply and Resources Committee
March 2, 2026
Page 6 of 9
better transmitter reception. These innovations resulted in 36 weeks
over the past 12 months where no truck rolls were required to read
meters that did not transmit properly.
Water Supply and Resources Committee
March 2, 2026
Page 7 of 9
The timing for the new customer e-newsletter proved fortuitous as the
first newsletter included an article about preparing pipes for cold
weather, which was sent out just before extremely cold temperatures
affected the region.
Water Supply and Resources Committee
March 2, 2026
Page 8 of 9
Chairman Jake Rambo inquired about progress on the Cooper Estates
project. Mr. Clum confirmed that the Pelzer Drive connection project,
which ties septic tanks on Pelzer Drive to the collection system, was
essentially complete except for final paving. The work involved cutting
into Coleman Boulevard for the final tie-in and was conducted during
scheduled night work to minimize traffic impacts.
Water Supply and Resources Committee
March 2, 2026
Page 9 of 9
Council Member Howard Chapman asked about complaints related to
the work. Mr. Clum acknowledged that initially there were valid traffic
complaints on Pelzer Drive when the project began, and the project was
shut down for two days until a better traffic plan was implemented. After
the traffic control improvements, no further traffic-related complaints
were received.
Regarding septic tank connections, all but one home on Pelzer Drive
agreed to tie into the system, with the lone holdout being a property in
the process of ownership transfer. Mr. Clum noted this represented a
very positive response from the community, contrasting it with what the
response would have been 20 years ago. The improved community
understanding of water quality importance and the need to protect Shem
Creek contributed to the positive reception.
5. Adjourn
There being no further business, Chairman Jake Rambo adjourned the
meeting at 9:33 a.m.
Respectfully submitted,
Lisa Canney
Deputy Clerk of Council
March 2, 2026
Source: Town of Mount Pleasant website. First collected Nov 7, 2026.