Pickens County Council Committee of the Whole Meeting — Agenda Packet
Pickens County · Pickens County · Pickens County Council · meeting of Aug 19, 2024 · Agenda packets
Open the original document More from Pickens County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
222 MCDANIEL AVENUE, B-1 ∙ PICKENS, SC 29671 ∙ 864.898.5856 ∙ WWW.CO.PICKENS.SC.US
COUNCIL MEMBERS
CHRIS BOWERS, CHAIRMAN
ROY COSTNER, VICE CHAIRMAN
ALEX SAITTA, VICE CHAIR PRO-TEM
C. CLAIBORNE LINVILL
CHRIS LOLLIS
HENRY WILSON
COUNTY ADMINISTRATOR
KEN ROPER
CLERK TO COUNCIL
MEAGAN NATIONS
PICKENS COUNTY COMMITTEE OF THE WHOLE MEETING
Monday, August 19, 2024
6:00 PM
Main Conference Room, County Administration Facility
222 McDaniel Avenue, Pickens SC 29671
All meetings of Pickens County Council are held in accordance with the South Carolina Freedom of Information
Act, Section 30-4-70, et seq. of the Code of Laws of South Carolina, 1976, as amended, as well as the
Organizational Rules for Pickens County Council.
1. WELCOME AND CALL TO ORDER: Chairman Chris Bowers
INVOCATION AND PLEDGE OF ALLEGIANCE: Vice Chairman Roy Costner
2. COMMITTEE OF THE WHOLE:
a. Log No. 242 – Pickens County Regional Joint Water System
b. Log No. 241 – SDPC School Resource Officers
c. Log No. 141 – UDSO
i. Discussion on Multi-Family Residential
ii. Discussion on RV’s
iii. Discussion on Stormwater
iv. Recommendation from Planning Commission on building setbacks
3. ADJOURN
Committee of the Whole Log
Updated 08/6/2024
Log Number Description Date Refferred Meeting Date(s)
Action
2/22/2022 ◘ No action taken by Committee.
10/17/2022
◘ Chairman Chris Bowers made a motion to put out an
RFP for either/or the Project 25 UHF Standalone System
and the Project 25 800 MHz Standalone System. Motion
was seconded by Councilman Ensley Feemster and
carried unanimously (6-0).
5/15/2023 ◘ Vice Chairman Roy Costner made a motion to
allocate $10,366,737 of ARPA Funding towards the
County Radio System. Motion was seconded by
Councilman Alex Saitta. Motion carried unanimously
(6-0).
1/22/2024 ◘No Action Taken by the Committee.
10/15/2018 ◘ Committee recommends staff working with the
Historical Society to explore the logistics of the location
and report back to Committee. No action taken by
Committee.
8/19/2019 ◘ No action taken by Committee.
123 AN ORDINANCE No. 572 AMENDING
ARTICLE I OF CHAPTER 34 OF THE
PICKENS COUNTY CODE OF
ORDINANCES SO AS TO PROVIDE
REMEDIES AND PENALTIES FOR
ILLEGAL LITTER AND DUMPING IN THE
UNINCORPORATED AREAS OF
PICKENS COUNTY, AND MATTERS
RELATED THERETO.
5/13/2019 3/21/2022 .
80 County Radio System 11/6/2017
109 Fort Prince George 10/1/2018
1
Committee of the Whole Log
Updated 08/6/2024
12/16/2019 ◘ No Action Taken by the Committee.
3/15/2021 ◘ Councilman Trey Whitehurst made a motion to
approve moving an allocation of $358,400 from fund
balance, for this capital project, forward into this year’s
budget for Solid Waste. Motion was seconded by
Councilman Ensley Feemster and carried unanimously
(6-0).
7/19/2021 ◘ No Action Taken by the Committee.
2/21/2023 ◘ Chairman Chris Bowers made a motion to move
forward with expanding the piggyback at the landfill
and the purchase of an excavator for $142,000. Motion
was seconded by Councilman Henry Wilson and carried
(4-2), with Councilman Alex Saitta and Councilman Chris
Lollis opposed.
1/21/2020 ◘ No Action Taken by the Committee.
1/25/2021 ◘ No Action Taken by the Committee.
3/16/2020 ◘ Meeting cancelled due to COVID-19 Special Called
Meeting.
2/16/2021 ◘ No Action Taken by the Committee.
11/19/2022 ◘ No Action Taken by the Committee.
◘ Vice Chairman Roy Costner made a motion for a 6-
month Moratorium, with an option to be extended out
90 days, to be moved out of Committee and for staff to
provide recommendation on development size. Motion
was seconded by Henry Wilson and carried
unanimously (6-0).
141 UDSO 2/3/2020
1/17/2023
133 Solid Waste Needs 10/7/2019
134 Mental Health 10/7/2019
2
Committee of the Whole Log
Updated 08/6/2024
◘ After more discussion, Chairman Chris Bowers made a
motion for First Reading in Title Only to amend the
UDSO and return to Committee for further discussion.
Motion was seconded by Vice Chairman Roy Costner
and carried unanimously (6-0).
2/21/2023 ◘ No Action Taken by the Committee.
4/17/2023 ◘ No Action Taken by the Committee.
7/17/2023 ◘ No Action Taken by the Committee.
8/21/2023 ◘ No Action Taken by the Committee.
8/31/2023 ◘ No Action Taken by the Committee.
9/18/2023 ◘ Councilman Henry Wilson made a motion to leave
the common roads out of the ordinance and discussion
for the time being until discussed at a future date.
Motion was seconded by Vice Chairman Roy Costner
and carried (5-0). Councilman Henry Wilson made a
motion to extend the moratorium for 90 days. Motion
was seconded by Councilman Chris Lollis and carried
unanimously (5-0).
10/16/2023 ◘ See minutes for motions made.
11/20/2023 ◘ See minutes for motions made.
1/22/2024 ◘ No Action Taken by the Committee.
2/26/2024 ◘ No Action Taken by the Committee.
2/10/2020 ◘ No Action Taken by the Committee.
8/17/2020 ◘ Vice Chairman Chris Bowers made a motion to implement a
Memorandum of Understanding, laying out a plan on how
Reverend Moss will implement the facility. Motion was
seconded Councilman Whitehurst and carried unanimously (6-
0).
Discussion on Old Jail142 2/3/2020
141 UDSO 2/3/2020
1/17/2023
3
Committee of the Whole Log
Updated 08/6/2024
3/21/2022 ◘ Chairman Chris Bowers made a motion to allocate funding,
totaling $98,000 towards this project at the Old Stockade.
Councilman Trey Whitehurst seconded the motion. The
motion carried (5-1), with Councilman Alex Saitta opposed.
8/30/2021 ◘ No Action Taken by the Committee.
9/20/2021 ◘ Chairman Chris Bowers made a motion to use
American Rescue Act Funding towards the first bill from
the Broadband Project and towards twenty (20) Solid
Waste Containers for the Solid Waste Department.
Motion was seconded by Councilman Alex Saitta and
carried (5-0).
◘ Chairman Chris Bowers made a motion to go into
executive session to discuss one-time funding for
county employees out of American Rescue Act Funding.
Motion was seconded by Vice Chairman Roy Costner
and carried (6-0).
◘ (second motion) Chairman Chris Bowers made a motion
to recommend to move forward to council meeting
American Rescue Act Funding compensation 5/25/2/1
plan and to exempt county council from the plan.
Motion was seconded by Vice Chairman Roy Costner
and carried (6-0).
◘ Vice Chairman Roy Costner made a motion to use the
lost revenue to purchase a bailer for $750,000. Motion
was seconded by Councilman Alex Saitta and carried
unanimously (6-0).
Discussion on Old Jail142 2/3/2020
10/18/2021
11/15/2021
177 American Rescue Act Funding 6/7/2021
4
Committee of the Whole Log
Updated 08/6/2024
◘ Councilman Alex Saitta made a motion to amend to
add a refund of $75,000 for the Clean Up Pickens
Program. Motion was seconded by Roy Costner and
carried unanimously (6-0).
◘ Councilman Henry Wilson made a motion for staff to
create a process for Non-Profits to apply for ARPA
funding based on the principles set forth. Motion was
seconded by Chairman Chris Bowers. The motion
carried (4-2), with Councilman Alex Saitta and
Councilman Trey Whitehurst opposed.
5/15/2023 ◘ No Action Taken by the Committee.
178 Hagood Mill MOU 6/14/2021
9/20/2021 ◘ Chairman Chris Bowers made a motion to bring in
Liberty City Dispatch for the reasons Chief Gibson
explained, for Emergency Services to continue to give
updates to Council, and to include the updates in
Administrator Roper’s report each month. The motion
was seconded by Councilman Henry Wilson and carried
unanimously (5-0).
10/18/2020 ◘ No Action taken by the Committee.
2/22/2022 ◘ No Action taken by the Committee.
196 Arial Mill Rehab Project 2/7/2022
203 Updating County Tire Policy Per
DHEC Requirement
5/3/2022
208 County Employee Handbook 8/8/2022 1/22/2024 ◘ No Action taken by the Committee.
11/15/2021
177 American Rescue Act Funding 6/7/2021
182 Unified Dispatch Plan from Staff 9/13/2021
5
Committee of the Whole Log
Updated 08/6/2024
209 County Constables and
Certification Process
10/3/2022 10/17/2022 ◘ Councilman Henry Wilson made a motion to table for
future consideration. Motion was seconded by
Councilman Ensley Feemster and carried (5-1), with
Councilman Alex Saitta opposed.
210 2023 Recreation Funding
Applications
4/3/2023
211 2023 ATAX Funding Applications 4/3/2023 ◘ Please see minutes for motions.
212 AMENDMENTS TO CHAPTER 6 OF
THE PICKENS COUNTY CODE OF
ORDINANCES SPECIFIC TO THE
OPERATIONS OF THE PICKENS
COUNTY AIRPORT AND MATTERS
RELATED THERETO.
4/3/2023 ◘ Chairman Chris Bowers made a motion to move out
of Committee. Motion was seconded by Councilman
Alex Saitta and carried unanimously (5-0).
213 Pickens County Water Authority 5/1/2023 5/15/2023 ◘ No Action taken by the Committee.
214 Sewer Capacity 5/1/2023 7/17/2023 ◘ Chairman Chris Bowers made a motion allow the City
of Clemson into the sewer capacity study. Motion was
seconded by Councilman Henry Wilson and carried
unanimously (6-0).
5/15/2023 ◘ Councilman Henry Wilson made a motion to remove
Section 7:2 (a)(8) in Council Organization Rules, which
states, “Board or commission members should resign
their appointment prior to announcing or filing for
candidacy for an elective office.” Councilman Alex Saitta
seconded the motion and the motion carried
unanimously (6-0).
215 Council Rules 5/1/2023
6
Committee of the Whole Log
Updated 08/6/2024
7/17/2023 ◘ See minutes for motions.
216 American Flood Coalition 7/10/2023
217 Workforce/Childcare Task Force 7/10/2023
218 Proposed Changes to the Pickens
County Solid Waste Management
Plan to adhoc SW Committee
7/10/2023
219 Administration Roof Replacement 8/7/2023
220 Emergency Services 8/7/2023 1/22/2024 ◘ Councilman Alex Saitta made a motion to approve
this recommendation. Vice-Chairman Roy Costner
seconded the motion.; Vice Chairman Roy Costner
amended the original motion, stating he would like to
allocate funding through ARPA funding. Councilman
Alex Saitta seconded the motion. The motion carried
unanimously (6-0).
221 Reassessment 9/5/2023 9/18/2023 ◘ Vice Chairman Roy Costner made a motion to move
this out of Committee for First Reading in Title Only.
Motion was seconded by Councilman Henry Wilson and
carried (4-1), with Councilman Alex Saitta opposed.
222 Animal Control Ordinance 10/2/2023 10/16/2023 ◘ No Action Taken by the Committee
223 Council Facebook Page 11/6/2023 11/20/2023 See minutes
215 Council Rules 5/1/2023
7
Committee of the Whole Log
Updated 08/6/2024
224 Library Renovations/Construction
Methods
12/4/2023 ◘ Councilman Alex Saitta made a motion to go big build
design and the project be managed by the
Administration. Councilman Henry Wilson seconded the
motion. The motion was carried (5-1), with
Councilwoman Claiborne Linvill opposed.
225 Review of County Holidays 1/8/2023 1/22/2024 ◘ No Action Taken by the Committee
226 Library Programing and
Media/Materials Policy
2/5/2024 2/26/2024 ◘ No Action Taken by the Committee
227 Gateway Signage 2/5/2024
228 AN ORDINANCE No. 633 OF
CERTAIN AMENDMENTS TO
PICKENS COUNTY CODE OF
ORDINANCES RELATED TO
UNSAFE DILAPIDATED OR
OTHERWISE SUBSTANDARD
PROPERTY CONDITIONS AND
MATTERS RELATED THERETO.
2/5/2024
229 AN ORDINANCE No. 634 OF
AMENDMENTS TO PICKENS
COUNTY CODE OF ORDINANCES
RELATED TO THE EFFICIENT, SAFE
OPERATION AND MAINTENANCE
OF THE COUNTY ROAD SYSTEM
AND MATTERS RELATED
THERETO.
2/5/2024
230 2024 Recreation Funding
Applications
3/4/2024
231 2024 ATAX Applications 3/4/2024
232 Boggs Mountain 4/1/2024
5/28/2024 See minutes for motions. 233 FY 24-25 Budget Work Session 4/1/2024
8
Committee of the Whole Log
Updated 08/6/2024
6/17/2024
234 FY 23 Audit to Budget Work
Session
4/1/2024
235 AN ORDINANCE REGARDING
AMENDMENTS TO SECTION 302
OF THE UNIFIED DEVELOPMENT
STANDARDS ORDINANCE
RELATED TO RECREATIONAL
VEHICLE (RV) PARKS AND
CAMPGROUNDS, ALONG WITH
MATTERS RELATED THERETO.
5/6/2024
236 Pickens County Airport Hangers &
Tax Rate on Aircraft
6/3/2024 6/17/2024 ◘ No Action Taken by the Committee
237 CONSIDERATION OF A
RESOLUTION AUTHORIZING A
PEDESTRIAN TRAFFIC STUDY IN
ORDER TO PROVIDE FOR MORE
SAFE AND EFFICIENT OPERATION
OF THE PICKENS COUNTY
DETENTION CENTER, ALONG
WITH SOURCE OF FUNDS AND
MATTERS RELATED THERETO.
7/22/2024
238 Pickens County Conservation Fund
Rules and Procedures
7/22/2024
239 Magistrates and Municipals Court 7/22/2024
240 Consolidation of County Facilities 7/22/2024
241 SDPC-School Resource Officers 7/22/2024
233 FY 24-25 Budget Work Session 4/1/2024
9
Committee of the Whole Log
Updated 08/6/2024
242 Pickens Regional Joint Water
System
7/22/2024
10
NEWS RELEASE
FOR IMMEDIATE RELEASE Contact: Tom Ponder
August 5, 2024 Chairman
864-430-1386
prjwspcsc@gmail.com
Pickens Regional Joint Water System was formed in 2019 with 3 member water systems: Easley
Central Water District, Six Mile Rural Community Water District, and the City of Pickens; along
with the Pickens County Water Authority. In 2021, the City of Liberty joined our efforts. Last
month, the City of Pickens voted to withdraw from our System, once again leaving 3 water
systems and the County Water Authority.
Together, our members remain committed to our mission, a water system of, by, and for the
people of Pickens County, using Pickens County water to serve the citizens of Pickens County
today and for years to come.
Our county is growing. Having affordable, abundant, clean drinking water available to our
citizens is more important than ever before. Our new water system will be there for our families
and businesses, for all the new families and businesses coming to Pickens County, and to bring
clean drinking water to parts of our county that have never had it.
In the coming months, we will break ground on phase one of our water transmission system.
This network will connect our members and allow us to work together for the benefit of our
customers. Our plan is to break ground on our water treatment plant on Lake Keowee in 2025.
This will give us local, clean drinking water for all our members and for other Pickens County
water systems that may need it for their growth.
To be clear, once our joint water system is fully functioning, our members will continue to
operate just as they are today, serving their individual customers with the support of the joint
system supplying water. Together we will all be stronger.
We are excited about the future of Pickens County and the Pickens Regional Joint Water System.
Our vision has not changed. Our mission has not changed. Our commitment to the people of
Pickens County and building together for our future is as strong as it was when we started in
2019.
NEWS RELEASE
FOR IMMEDIATE RELEASE Contact: Bill Smith
August 7, 2024 Chairman
864-414-7068
pcwabs@gmail.com
The Pickens County Water Authority (Water Authority) was a founding member of the Pickens
Regional Joint Water System (Pickens Regional). In 2019, we joined with Six Mile Rural
Community Water District, Easley Central Water District and the City of Pickens to start the
effort. In 2021, the City of Liberty joined us. Last month, the City of Pickens voted to withdraw
from our System, once again leaving 3 water systems and the Water Authority.
We remain committed to the mission of Pickens Regional, a water system of, by, and for the
people of Pickens County, using Pickens County water to serve the citizens of Pickens County
today and for years to come.
Pickens County is growing. Having affordable, abundant, clean drinking water available to our
citizens is more important than ever before. Pickens Regional will be there for our families and
businesses, for all the new families and businesses coming to our county, and to bring clean
drinking water to our neighbors in parts of our county that have never had it.
In the coming months, Pickens Regional will break ground on phase one of a new water
transmission system. This network will connect Pickens Regional members and allow us to work
together for the benefit of our customers. Our plan is to break ground on the Pickens Regional
water treatment plant on Lake Keowee in 2025. This will give us local, clean drinking water for
the Pickens Regional members and for other Pickens County water systems that may need it for
their growth.
To be clear, once Pickens Regional is fully functioning, the Water Authority will still continue to
pursue our mission to ensure abundant supplies of fresh water are available in Pickens County.
Together we will all be stronger.
The Pickens County Water Authority is excited about the future of Pickens County and the
Pickens Regional Joint Water System. Our shared vision has not changed. Our shared mission
has not changed. Our commitment to the people of Pickens County and building together for
our future is as strong as it was when we started Pickens Regional in 2019.
Fw: Additional School Resource Officers
Ken Roper <kenr@pickenscountysc.gov>
Mon 8/12/2024 11:49 AM
To: Meagan Nations <meaganb@pickenscountysc.gov> Cc: Jessica Varney <jessicav@pickenscountysc.gov>
for COW packet
From: Ralph Guarino <ralphg@pickenscountysc.gov>
Sent: Thursday, July 18, 2024 4:32 PM
To: 'Ma Owens' <maowens@pickens.k12.sc.us>; Ken Roper <kenr@pickenscountysc.gov>
Subject: Addional School Resource Officers
Matt, Thank you for you and Josh speaking with me today regarding the four (4) additional School Resources Officers (SRO) for thePickens County School District. I wanted to memorialize our conversation this afternoon to make sure we have a clearcommunication moving forward with these four new positions and our existing eleven (11) SRO’s that we discussed. PickensCounty will add 4 SROs in FY 2025, with the County Administrator and County Councils approval if the School District agrees tothe following guidelines. 1. Pickens County School District will reimburse the County for 100% of all actual cost related to the SROs for four (4)positions for FY 2025 including but not limited to Salaries and benefits (wages, medical insurance, retirement, worker’s compensation, life insurance, social security)Patrol vehicle including any additional equipment including radios, security cages, lights, and any other related itemsfor the vehicle to be placed in service. This cost will be spread over a seven (7) year period to eliminate fluctuatingpayments from one year to the next year.Fuel for the SRO’s vehicle to commute to and from work and home.Auto insurance for the patrol vehicleAll necessary expenses to outfit the SRO for normal duty as a Pickens County Sheriff’s Officer (such as weapons,ammunition, uniform, badge, etc.)It is estimated the total cost will be $82,000 per year per SRO 2. The School District will reimburse the existing eleven (11) SRO positions for FY 2025 at the following rates. This will bebilled on quarterly basis.One (1) Administrative SRO at $ 66,000.00 per yearTen (10) SROs at $62,000.00 per year per SROTotal annual cost of $686,000. 3. For FY 2026 and beyond, the School District will reimburse the County for all fifteen (15) SROs based on the actual costsdirectly related to the SRO’s as defined by item 1. Please reply to this email by tomorrow at 5:00 pm if the School District agrees with the above-mentioned sections. This willallow the County Administrator to review this understanding so he can communicate this with County Council at Monday night’sCouncil meeting. Please forward to Josh since I do not have his email address. Regards Have a great weekend
From: Ma Owens <maowens@pickens.k12.sc.us>Sent: Wednesday, July 17, 2024 7:21 AMTo: Ralph Guarino <ralphg@pickenscountysc.gov>Subject: Tomorrow 2:30 Will tomorrow at 2:30 work to talk with Josh and myself? Thank you, Ma OwensChief Financial OfficerSchool District of Pickens County1348 Griffin Mill RoadEasley, SC 29640864-397-1022 This e-mail may contain confidential, proprietary, or legally privileged information. The sender does not intend to waive anyprivilege that may attach to this e-mail. If you are not the named addressee, you are not authorized to read, print, retain, copy, ordisseminate this communication. If you received this communication in error, please immediately notify the sender by e-mail anddelete this communication and any copies. Any views or opinions expressed are solely those of the author and do notnecessarily represent those of the School District of Pickens County. E-mail transmission cannot be guaranteed to be secure orerror-free as information could be intercepted, corrupted, lost, destroyed, arrive late or incomplete, or contain viruses. UnderSouth Carolina law, non-privileged e-mail correspondence to and from a District e-mail account may be considered publicinformation and subject to release.
Committee of
the whole
August 19, 2024
CONTINUED DISCUSSION OF UPDATES TO
THE UNIFIED DEVELOPMENT STANDARDS
ORDINANCE
APPALACHIAN HERITAGE AREA:
• Leave the Highway 11 Corridor standards in place.
• For areas in the Appalachian Heritage Area outside the Highway 11 Corridor, leave the amended UDSO as it is with two exceptions:
o Open Space Subdivisions shall have a 2-acre minimum lot size only and require 50% open space, sidewalks, proper road widths
and Dark Sky lighting.
o RV Parks and Campgrounds shall be limited to 10-acres in size.
AGRICULTURAL HERITAGE AREA:
• Leave the amended UDSO as is with the following two changes:
o Open Space Subdivisions shall have a 1-acre minimum lot size only and require 40% open space, sidewalks, proper road widths
and Dark Sky lighting.
o RV Parks and Campgrounds shall be limited to 10-acres in size.
NATURAL HERITAGE AREA:
• Leave the UDSO as is (assuming the adoption of the proposed changes) with the following changes:
o Open Space Subdivisions shall have a 1/2-acre minimum lot size only and require 40% open space, sidewalks, proper road widths
and Dark Sky lighting.
o RV Parks and Campgrounds shall be limited to 10-acres in size.
COMMUNITY CENTER AREA:
• Leave everything in the existing and proposed UDSO and add or change the following items for any site that has access to public sewer
and for which all required traffic studies have been completed and roadway modifications agreed to and for which Emergency Services and
the School District approve:
o Allow open space subdivisions with 5000 square foot lots and 30% open space and encourage contiguous open spaces with
adjacent development (for property that does not have access to public sewer and water the minimum lot size shall be 1/2-acre).
o Allow a townhome density of 20 dwellings per acre
o Allow a duplex density of 8 structures (16 dwellings) per acre
o Allow a multi-family density of 25 units or 75 bedrooms per acre and a height of 3 stories
o Allow mixed use buildings with a density of 25 units or 75 bedrooms per acre and a height of 4 stories
o Allow a parking ratio of .75 per bedroom for multi-family and mixed use. Single family, duplex, and townhomes would remain at 2
spaces per dwelling unit
o Do not allow RV’s as dwelling units
GATEWAY AREA:
• Leave everything in the existing and proposed UDSO and add or change the following items for any site that has access to public sewer
and for which all required traffic studies have been completed and roadway modifications agreed to and for which Emergency Services and
the School District approve:
o Allow open space subdivisions with 5000 square foot lots with 20% open space and encourage contiguous open spaces with
adjacent development (for property that does not have access to public sewer and water the minimum lot size shall be 1/2 -acre).
o Allow a townhome density of 20 dwellings per acre.
o Allow a duplex density of 8 structures (16 dwellings) per acre.
o Allow a multi-family density of 40 units or 120 bedrooms per acre and a height of 5 stories.
o Allow mixed use buildings with a density of 40 units or 120 bedrooms per acre and a height of 5 stories.
o Allow a parking ratio of .75 per bedroom for multi-family and mixed use. Single family, duplex, and townhomes would remain at 2
spaces per dwelling unit.
o Do not allow RV’s as dwelling units
Proposed discussion for August 2024 Committee of the Whole Meeting
TEXT AMENDMENT TO UDSO ARTICLE 3 - TOWNHOME DEVELOPMENTS
Overview:
The Ordinance introduces design standards and regulations for townhome developments within the county. The aim is to provide clear guidelines for
the development of townhomes in response to the increasing demand over the past year. The standards cover aspects such as density, lot size,
setbacks, and design requirements to ensure organized growth and community welfare.
Purpose:
This ordinance aims to address the rising number of townhome development requests by establishing comprehensive guidelines that ensure
sustainable, aesthetically pleasing, and functional townhome communities within the county.
Key Provisions:
1. DEFINITION OF TOWNHOME:
o A townhome is a privately owned, attached single-family dwelling on its parcel, connected to other units by a party wall without
windows, doors, or passageways.
2. OPEN SPACE REQUIREMENT:
o Every townhome development must allocate 40% of its total acreage as open space, to be preserved in perpetuity.
3. LOT SIZE AND DIMENSIONAL STANDARDS:
o Minimum Lot Size: 2,000 sq. ft. per unit.
o Setbacks:
Front: 25’ (or 15’ with rear yard parking/alleys).
Side: 0’ (interior), 15’ (exterior).
Rear: 15’.
o Maximum Building Height: 35’.
o Impervious Surface Coverage: 65%.
o Minimum Lot Width: 20’.
4. DENSITY REGULATIONS:
o On-site Septic Systems: Maximum of 2 units per acre.
o Public Systems: Community Center Area and Gateway Area allow 20 dwellings per acre.
5. ACCESS REQUIREMENTS:
o Direct vehicular access limited to internal streets.
o For developments with more than 10 units on collector/arterial streets, at least two access points are required.
o A minimum 4-foot sidewalk is required connecting parking areas and units.
6. DESIGN REQUIREMENTS:
o Building Length: Maximum of 200’; architectural variation required every 40’ on buildings longer than 120’.
o Garage Width: Must not exceed 50% of the unit’s width.
o Driveways/Walkways: Separated by a 3’ landscaped strip.
o Street Trees: One tree per 30 feet of frontage, minimum 2.5” caliper.
o Utilities: Underground and Dark Sky compliant lighting required.
7. ADDITIONAL STANDARDS:
o Off-street parking and buffer requirements are governed by respective Articles VI and VIII of the UDSO.
MULTI-FAMILY PROPOSED STANDARDS BY AREA
These provisions are intended to guide the planning and development within specific areas of the county, ensuring that infrastructure
and community services can support the increased density.
COMMUNITY CENTER AREA:
• Duplex Density: 8 structures (16 dwellings) per acre.
• Multi-Family Density: 25 units or 75 bedrooms per acre; 3-story height limit.
• Parking: 0.75 spaces per bedroom for multi-family; duplexes remain at 2 spaces per unit.
• Mixed-Use: Same density as multi-family; 4-story height limit.
• Note: Only applies to areas with public sewer, approved traffic studies, and relevant emergency services and school district
approvals.
GATEWAY AREA:
• Duplex Density: 8 structures (16 dwellings) per acre.
• Multi-Family Density: 40 units or 120 bedrooms per acre; 5-story height limit.
• Parking: Same as Community Center Area.
• Mixed-Use: Same density as multi-family; 5-story height limit.
TEXT AMENDMENT TO UDSO ARTICLE 3: PROPOSED STANDARDS FOR RECREATIONAL VEHICLE (RV)
PARKS AND CAMPGROUNDS
OVERVIEW:
This ordinance outlines the standards for the development and operation of RV parks and campgrounds within the county. It aims to
ensure these facilities are properly located, provide a quality recreational environment, and maintain public health, safety, and welfare.
KEY PROVISIONS:
1. PURPOSE:
o The ordinance sets criteria for establishing RV parks and campgrounds, requiring adequate public street access and
other public services. Planning Commission review is mandatory unless exemptions apply. Two or more RVs on one
parcel classify the property as an RV park.
2. ACCESS AND ROADWAYS:
o Street Frontage: Parks must have direct frontage and access to a collector or arterial street.
o Internal Roads: Access to individual sites must be from internal/private roads, not directly from public roads. Roads
must be all-weather, with specified widths and turning radii to accommodate emergency vehicles.
3. SIZE AND DENSITY:
o Minimum Size: Parks must be at least 5 acres. In designated areas like Appalachian, Agricultural, and Natural
Heritage, they cannot exceed 10 acres.
o Site Density: Limited to 4 sites per acre.
4. USAGE RESTRICTIONS:
o Temporary Use: Sites cannot be used as permanent residences. They are intended for temporary accommodations
like travel trailers, campers, and motor homes. No occupant may stay longer than 180 days in a calendar year.
5. SITE REQUIREMENTS:
o Minimum Site Area: Each site must be at least 800 square feet with a parking pad for the RV and one additional
vehicle.
o Setbacks: Sites must be set back at least 10 feet from side and rear property lines and 20 feet from public road
rights-of-way. Adjacent residential areas require vegetated screening.
6. UTILITIES AND AMENITIES:
o Sewage: Sites may use a communal on-site sewage disposal system; individual systems for each site are not
allowed. A bathhouse is required for sites without sewage connections.
o Utilities: No individual metering for power or water; a master meter must serve the entire park. All sites must have
access to public water.
o Storm Shelter: Required for parks with more than four sites, compliant with International Residential Code (IRC)
standards.
7. MANAGEMENT AND SAFETY:
o A site management plan must be submitted with the land use application.
o 911 Addressing is required for all parks and campgrounds.
Sec. 302 Recreational Vehicle (RV) Parks and Campgrounds.
302 (a) Purpose.
The purpose of this section is to provide opportunities for quality developed campgrounds and recreational vehicle parks that
are properly sited where there is adequate public street access and adequate access to other public services which may be
needed by such endeavor. In order to create a desirable and successful recreation environment while protecting the public
health, safety, and welfare, Planning Commission review and consideration will be required; unless exempted in the following
sections. Two or more RVs on one single parcel constitutes an RV Park.
302 (b) Use Standards.
1) Each park or campground must have direct frontage and access to a collector or arterial street.
2) Access to each individual site and other provided structures shall be from internal/private roads. Individual sites shall
not be accessed directly from a public road.
a. Roadways within an RV Park or Campground shall be constructed to all -weather standards: graded and/or
graveled road or road of equivalent materials that is passable by vehicles under both wet and dry weather
conditions.
b. All roadways shall have a minimum travel width of twelve feet (12’) for single lane travel and twenty-four feet
(24’) for two lane travel, and a thirty -five foot (35’) turning radius required on all curves to allow access by
emergency vehicles.
3) RV parks and campgrounds must be a minimum of five (5) -acres in size and shall not exceed ten (10) -acres in the
Appalachian, Agricultural, and Natural Heritage Areas and shall be a minimum of five (5) -acres in the Community
Center and Gateway Areas.
4) No site shall be used as a permanent residence and shall only be for the use of travel trailers, pickup campers, coaches,
motor homes, camping trailers, other vehicular accommodations, tents, park model units, and on -site rental cabins.
No site may be used for more than one hundred eighty (180) days in any calendar year by the same occupant.
5) Overall density of the park or campground shall be limited to no more than four (4) sites per acre.
6) Each site in the campground or park shall have a minimum area of eight hundred (800) square feet and have a
stabilized and compacted vehicular parking pad of packed gravel, paving, or other suitable material large enough for
the recreational vehicle and one additional car or truck. At least one site must be ADA accessible. When permanent
units (Cabins) are provided, at least one (1) unit must be ADA accessible.
7) All sites shall be setback from all side and rear property lines by a minimum of ten (10) feet and a minimum of twenty
(20) from the edge of any public road right-of- way. When the park or campground is adjacent to a residential use, that
ten (10) feet must be vegetated to provide a solid evergreen screen.
8) Sites may be served by on-site sewage disposal system as permitted by SCDHEC; however, each individual site may
not be served with an individual system.
9) For s ites within the park that are not otherwise served with sewage disposal connec tions, an onsite bath house
(provisions for restroom and bathing facilities) must be provided.
10) Sites shall not be served by individually metered power or water service. When multiple sites are being provided,
master meter(s) must provide service to the entire park. All sites must have access to public water, either directly or
communally.
11) For parks with more than four (4) sites a storm shelter shall be provided per IRC standards.
12) At the time of application for land use approval, RV parks and campgrounds must include a proper site management
plan to be instituted once operational.
13) 911 Addressing is required for all RV parks and campgrounds.
TEXT AMENDMENT TO UDSO ARTICLE 1 - USE OF RECREATIONAL VEHICLES (RVS) AS DWELLING
UNITS
Overview:
This ordinance establishes guidelines for the use of Recreational Vehicles (RVs) as private dwelling units within the county. This
ordinance aims to ensure that RVs used as residences meet the necessary standards for safety, access, and public welfare, while also
providing a framework for their integration into residential areas.
Key Provisions:
1. PURPOSE:
o The ordinance provides standards for parking and utilizing RVs as residential units, ensuring they are properly sited
with access to public services and infrastructure while safeguarding public health, safety, and welfare.
2. APPLICATION AND APPROVAL:
o An application, provided by the Building and Codes Department, must be submitted and approved before an RV can
be authorized as a private dwelling.
3. USE STANDARDS:
o Compliance: RVs used as dwellings must comply with the same standards as traditional dwellings, including lot size,
setbacks, and street frontage.
o Principal Building: Each RV is considered a principal building, with only one RV allowed per residential property.
o Flood Plain Restrictions: RVs cannot be parked in FEMA-designated Flood Plains or Flood Ways.
o Registration: RVs must remain mobile-ready, maintaining registration with the Department of Motor Vehicles.
o Physical Condition: The RV must be free from damage such as dents, broken windows, and leaks, and must not
have window AC units or duct tape repairs.
o Anchoring: RVs must be anchored according to ANSI standards.
o Utilities: RVs must connect to a public sewer system or DHEC-approved septic system and have their own power
meter and connection inspected per the International Residential Code (IRC).
o Safety Features: Smoke alarms are required in all RVs.
o Taxation: RVs will be added to the County Assessment/Tax system, taxed separately from the land but linked to the
parcel by VIN.
o Annual Inspection: RVs are subject to annual inspections by the Building Codes Department, with the responsibility
for scheduling on the RV owner.
o Development Areas: RVs are prohibited for use as residential units in the Community Center Area and Gateway
Area.
4. PURPOSE OF ORDINANCE:
o This ordinance addresses the rising number of requests to use RVs as permanent residences, establishing safety
and neighborhood protection standards to allow this practice to continue under regulated conditions.
WHAT ARE RIPARIAN AREAS AND
SETBACKS?
The word “riparian” refers to land alongside
streams, creeks, rivers, lakes, and other
waterbodies.
Riparian areas stabilize stream banks, limit
erosion, reduce flooding, filter out pollutants, and
provide habitat.
Riparian setbacks are one tool communities can
use to maintain riparian area function as land is
developed or redeveloped. Riparian setbacks are
intended to manage the location of land
disturbance and development within the riparian
zone. Setbacks protect waterways from impacts of
development and protect resident s from flooding
damage and land loss through erosion.
WHICH AREAS AND STREAMS ARE
REGULATED?
This ordinance applies to lands within
unincorporated areas within the jurisdiction of
Pickens County.
To be protected by this ordinance, the waterbody
must:
• Be a Surface Water of the State and
appear on the selected resource maps:
i. The USGS Topographical Map
ii. Soils Map
iii. Pickens County GIS Map
iv. Sediment and Erosion Control
Plans
*Surface Waters of the State -- any stream, river,
brook, swamp, lake, sound, tidal estuary, bay,
creek, reservoir, waterway, or other body or
accumulation of water. They can be public or
private, natural or artificial.
THE SETBACK WIDTHS
Setback distances extend horizontally from the
Top of Bank.
• 50 feet on Waters of the State
• 100 feet on a subset on “sensitive waters”
*Top of Bank – the point where the bank meets the
adjacent upland or terrace, and is typically the
boundary between the land and the waterbody.
*Sensitive W aters identified in the ordinance
include Outstanding National Resource Waters,
Outstanding Resource Waters, and Trout Waters.
BENEFITS
Physical: Promote the health and safety of citizens
by restoring and maintaining the physical,
chemical, and biological integrity of water
resources.
Economic: Preserve land characteristics, sustain
or increase aesthetic value of property, save costs
associated with stream restoration or remediation
projects.
Environmental: Filtration of pollutants preventing
them from entering waterbodies, satisfying
NPDES Phase II requirements for Pickens
County’s designation as an SMS4.
Pickens County Riparian Setback: Fact Sheet
STORMWATER DESIGN MANUAL RECOMMENDATIONS
Current Recommendation
Hydraulic Design
Current peak flow control references
the 2- and 10-yr 24-hr storm event.
Current design storm language
identifies the design storm for
channels and diversion ditches as the
10-yr event.
25-yr, 24-hr event, and checking all
drainage systems for flooding
hazards for the 100-yr, 24-hr event
for local flooding and possible flood
hazards to adjacent structures and/or
property.
Hydraulic Design –
Downstream
Assessment
Existing conditions + 10% rule to
identify point of concern for
downstream analysis.
In addition, consider to the following
as points of concern: first
downstream crossing, known
locations of flooding, drainage, or
erosion, etc.
Analysis of the 25- and 100-yr 24-hr
storm events.
Detention Waiver Detention waivers may be granted for
water quantity and/or quality.
In addition, consider specific types of
adverse impacts that would disallow a
detention waiver: channel erosion,
peak flow rates higher than
downstream culvert/bridge capacity,
flow depth that would flood
outbuildings, AC units, crawl spaces,
or finished floor elevations.
STORMWATER ORDINANCE MAJOR UPDATES SUMMARY TABLE
Previous Current
Land Disturbance
Permitting
Land disturbance greater than one
acre or part of a Larger Common Plan
o
f development or sale required a land
d
isturbance permit
Land disturbance activities greater
than one-quarter acre require a
simplified grading permit.
Land disturbance activities greater
than one acre or part of a Larger
Common Plan of development or sal
e
still require a land disturbance permit
Riparian Setbacks
from Waters of the
State
50-foot buffer around Lake Hartwell,
Keowee, and Jocassee
30-foot/45-foot buffer during
c
onstruction only for activities requiring
a
land disturbance permit.
50-foot buffer around Waters of the
State shown on USGS topographical
a
nd other select maps.
100’ buffer around Outstanding
Natural Resource Waters,
Outstanding Resource Waters, an
d
Na
tural Trout Waters.
Buffer around the 100-year floodplain
if
floodplain is wider than the 50’/100’
riparian setback.
Source: Pickens County website. First collected Nov 7, 2026.