County Council Workshop — Agenda Packet
Beaufort County · Beaufort County · County Council Meeting · meeting of Jun 26, 2025 · Agenda packets
Open the original document More from Beaufort County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
County Council Workshop
Beaufort County, SC
Bluffton Public Library, 120 Palmetto Way, Bluffton, SC 29910
Thursday, June 26, 2025
10:00 AM
AGENDA
COUNCIL MEMBERS:
ALICE HOWARD, CHAIR ANNA MARIA TABERNIK, VICE CHAIR
DAVID P. BARTHOLOMEW PAULA BROWN
LOGAN CUNNINGHAM GERALD DAWSON
YORK GLOVER MARK LAWSON
LAWRENCE MCELYNN JOSEPH PASSIMENT
THOMAS REITZ
1. CALL TO ORDER
2. PLEDGE OF ALLEGIANCE
3. STATEMENT OF COMPLIANCE WITH FOIA
4. APPROVAL OF AGENDA
5. PUBLIC COMMENT PERIOD – 30 MINUTES TOTAL
6. TECHNICAL COLLEGE OF THE LOWCOUNTRY REGIONAL WORKFORCE CENTER UPDATE – Mary Lee Carnes
7. UNIVERSITY OF SOUTH CAROLINA BEAUFORT SAND SHARK 20/20 ARENA PRESENTATION & DISCUSSION
– Dick Stewart
8. BREAK FOR LUNCH
9. 2018 REFERENDUM PROJECT LIST DISCUSSION - Jared Fralix, Assistant County Administrator & Bryan
Bauer, Director of Engineering
10. 278 PROJECT STATUS UPDATE - Michael Moore, Administrator
11. ADJOURNMENT
TO WATCH COMMITTEE OR COUNTY COUNCIL MEETINGS OR FOR A COMPLETE LIST OF AGENDAS AND
BACKUP PACKAGES, PLEASE VISIT:
https://beaufortcountysc.gov/council/council-committee-meetings/index.html
1
2
BEAUFORT COUNTY COUNCIL
AGENDA ITEM SUMMARY
ITEM TITLE:
Discussion of Council’s Intent in Passing Resolution 2024/20 to fund TCL’s Regional Workforce Training Center
MEETING NAME AND DATE:
Beaufort County Council Workshop, June 26th, 2025
PRESENTER INFORMATION:
Dr. Rich Gough, President TCL and Mary Lee Carns, Vice President for Advancement
ITEM BACKGROUND:
During the May 1, Finance Committee meeting, it was presented to Council to contribute via
Resolution 2024/20 (approved at the May 28th, 2024 County Council meeting), a total of
$7.5M towards Technical College of the Lowcountry (TCL)’s Regional Workforce Training
Center. The $6M portion of the funds were to come from the 2025 Bonds issued, giving an
additional .1mil to cover the debt service and to reimburse Beaufort County for the bond
payment. Previously this was presented in two parts: $6M of the 2025 Bond Issuance & $1.5M over
the course of the following three fiscal years. The County closed on the bonds in Feb 2025, and we
reached out to TCL with their debt schedules as scheduled meeting for MOUs regarding the servicing
of the debt, they made us aware that the was debt associated with their funding. They would like to
discuss options with Council regarding the commitment made by Council.
PROJECT / ITEM NARRATIVE:
Ordinance 2024/25, Section IV, Item F – Higher Education Allocation reads as follows:
“The amount of $6,222,500 is appropriated for the Higher Education Allocation to help sustain
operations. The amount collected will be disbursed as follows: $2,975,500 to University of South
Carolina-Beaufort and $2,861,790 to the Technical College of the Lowcountry. An amount up to but
not exceeding $385,210 of collections will be appropriated for debt service, to be paid by the County,
for the Technical College of the Lowcountry for the issuance of $6,000,000 in G.O. Bonds for the
construction of a workforce development center. Should the tax collections exceed the amounts
appropriated herein, the surplus revenue will be divided equally between the University of South
Carolina-Beaufort and the Technical College of the Lowcountry and paid no later than August 31,
2025.”
Recently the County approached TCL seeking payment for debt service on a $6M G.O. Bond.
The only documentation the college has regarding this matter is County Resolution 2024/20,
which commits $7.5 million toward the construction of the Arthur E. Brown Regional
Workforce Training Center, to be distributed over multiple years, with the County’s stated
intent to fulfill this obligation by the end of fiscal year 2027.
On May 16, 2024, the college informed the County in writing: “The college cannot carry the
cost of a bond. If this is the case, we need to stand down the architects.”
3
On that same date, a County representative stated in writing: “You will not have to pay over
funds to the county each year for this debt service… You all will not have to come out of
pocket for any debt payment. You will continue receiving your 1.1 mills of revenue as well.”
The language in Ordinance 2024/25, Section IV, Item F, explicitly states that debt service will
be “paid by the County” on behalf of the Technical College of the Lowcountry. This appears to
align with the written assurances made by the County representative on May 16, 2024.
Therefore, the college requests clarification regarding the County’s position and support for the
Arthur E. Brown Regional Workforce Training Center. In addition, it has been the college’s
understanding that the Higher Education Allocation is intended to be distributed equally—on a parity
basis—between the Technical College of the Lowcountry and the University of South Carolina–
Beaufort. However, Ordinance 2024/25 reflects a difference of $113,710 in the allocations. We would
appreciate clarification on how this variance was determined.
FISCAL IMPACT:
A Total of $7.5M toward Council’s commitment to contribute funding for TCL Regional Workforce
Training Center.
STAFF RECOMMENDATIONS TO COUNCIL:
Council confirm commitment to the TCL Regional Workforce Training Center.
Council direct staff to enter into negotiations for an IGA regarding funding for the TCL Workforce
project.
OPTIONS FOR COUNCIL MOTION:
Approve/Deny
4
5
6
7
8
9
10
11
12
13
14
15
• If Beaufort County funding is withdrawn and EDA funding is awarded: TCL will scale the
Center to approximately 42,000 sq ft. Additional delays expected for architectural revisions
and program adjustments.
• If both Beaufort County and EDA funding are unavailable: TCL will scale the Center to
approximately 31,000 sq ft. Additional delays expected for architectural revisions and
program adjustments.
The region's economy is overreliant on low-wage, disaster-prone sectors like Retail Trade and
Leisure & Hospitality. This has led to underemployment, low labor force participation, and stagnant
incomes. Workforce training has been shown to increase wages, increase labor force
participation and expand the area's tax base. The Regional Workforce Training Center will be a
durable economic asset that builds the region's capacity for skilled employment and drives the
private and public prosperity.
Occupation by Sector Median Hourly Wage
.. (SC) .... -·--..
Annual Median Salary
---· .......... ···················-····-·-·-·-····· --
Manufacturing and Engineering Technology
Sector
Robotics Technicians $ 34.02 $
.......................................
32.62 $ Advanced Manufacturing Technician I $
---- ................... ......... _____________
Electro-mechanical Technician $
______________ ., __ ______ ............ _,_
Industrial Machinery Mechanics j $
29.54 $
30.04 $
(SC) _ __
70,760.00
61,430.00
61,430.00
61,260.00
---------+----------
Leisure & Hospitality and Retail Trade
Sector ------------------····••!••··············· ·······
Retail Manager
Retail Salesperson
Cooks
Food Preparation Workers
Food Servers
Dishwashers
Maids and Housekeeping Cleaners
$
$
$
$
$
22.75 $ 47,320.00
16.62 $ 34,580.00
21.27 $ 39,310.00
14.85 $ 30,050.00
14.56 $ 30,150.00
14.13 $ 29,200.00
14.20 $ 29,290.00
Note. Table data was provided by U.S. Bureau of Labor Statistics, Occupational Employment and
Wage Statistic, State of South Carolina, May 2024; and Occupational Information Network (O*NET)
sponsored by U.S. Department of Labor/Employment and Training Administration.
Page 2 of 2
16
17
18
PROGRAMMING
SITE PLAN
ADVANCED MANUFACTURING
BUILDING TECHNOLOGY
BUSINESS
COMPOSITE MATERIALS
FLEX
UTILITY
---------· ------
mcmillan I pazdan I smith
ARCH:TECTURE
TECHNICAL COLLEGE OF THE LOWCOUNTRY
BEAUFORT, SOUTH CAROLINA
07117/24
T
SITE PLAN
19
20
21
22
2018 Sales Tax Workshop
June 26, 2025
23
2018 Sales Tax – Project Amounts
Org. Funding Rev. Funding Spent Remaining
US 278 Corridor $ 80M $80M $19.25M $60.75M
Lady’s Island Corridor $ 30M $30M $6.7M $23.33M
Pathways $ 10M $30.5M $9.10M $21.74M
Total $120M $140.5M $35.05M $105.82M
Total Available for Spending = $23.33M + $21.74M + $11M = $56.07M
*Total collections = $146.5M; $11M still available for appropriation
2
24
Lady’s Island – Main Corridor
• “The Heart” – Signal modifications, resurfacing, striping,
pedestrian improvements at intersection of SC 802 & US
21 (in coordination with SCDOT safety project)
• RI/RO from intersection to Ferry Dr
• Widen US 21 to 4 lanes from Lost Island Rd to last
Walmart entrance
• LIMS School Access
Estimated Costs
$4.30M
$9.16M
$9.06M
$22.52M
3
25
Lady’s Island – Access Roads
Estimated Costs
$7.69M
$1.83M
$.76M
$10.28M
• Scaled Down Hazel Farm & Gay Project
• Dirt road improvements and roundabout
• Signal at US 21 and Gay Dr
• Finish design for pedestrian improvements but
do not implement
• Scaled down Sunset Dr & Miller Rd
• 3-way stop with raised intersection at
Sunset/Miller
• Traffic calming on Miller Rd.
• Resurface Sunset & Miller
• Airport Frontage Phase 2
• Complete Design
Total Lady’s Island Corridor = $22.52M + $10.28M = $32.8M
4
26
Lady’s Island
5
Remaining Projects Expended to Date Remaining Budget Cumulative Remaining Total Status
Airport Frontage Road - Phase II $ 242,000.48 $ 761,258.57 $ 761,258.57 $ 1,003,259.05 90% Design
Hazel Farm Road & Gay Drive (S-497) $ 556,012.07 $ 7,686,832.93 $ 8,448,091.50 $ 8,242,845.00 65% Design
Lady's Island Middle School Access Road $ 517,102.43 $ 9,062,398.06 $ 17,510,489.56 $ 9,579,500.49 80% Design
Sunset Boulevard (S-186) & Miller Drive W (S-187) (1) $ 458,350.53 $ 1,825,000.00 $ 19,335,489.56 $ 2,283,350.53 Rescoping
US 21 Bus/US 21 (Sea Island Parkway) & US 21 (Lady's Island
Drive)/SC 802 (Sam's Point Road) (2) $ 607,676.49 $ 13,463,980.50 $ 32,799,470.06 $ 14,071,656.99 Rescoping
$ 2,381,142.00 $ 32,799,470.06 $ 35,180,612.06
27
Priority One – Nearing Construction
- Alljoy Road 1, 3, c
- Salem Road 1, c
- Burnt Church Road 1, 3, c, *
- Stuart Point Rd 1, 3, c
- Depot Rd 1, c
1 Resolution 2019/22 Priorities
2 On BC Connects Plan
3 Direct Access to School/Park
*Not ready for construction but should
be included as high priority project
a Dependent on input from Representatives
b Dependent on Developer
c In design
6
28
Priority Two
- Dr. Martin Luther King Jr. Dr. 1, 2, 3, c
- Big Estate Rd 1, 2, c
1 Resolution 2019/22 Priorities
2 On BC Connects Plan
3 Direct Access to School/Park
a Dependent on input from Representatives
b Dependent on Developer
c In design
7
29
Priority Three
- Broad River Blvd & Riley Rd 1, 2, 3, c
- Middle Rd 1, 3, c (Portion)
- Joe Frazier Rd 2, 3(Portion)
- Pine Grove Rd
& Burton Wells Rd 2, 3 (Portion)
- Broad River Dr 1, 2, 3, c (Portion)
1 Resolution 2019/22 Priorities
2 On BC Connects Plan
3 Direct Access to School/Park
a Dependent on input from Representatives
b Dependent on Developer
c In design
8
30
Priority Four
- Meridian Rd 1, 2, 3, a, c
- Old Salem Rd 2, b
- Burton Hill Rd 2, b
- Chowan Creek Bluff 2, 3
- Bruce K Smalls Rd 3
- Ulmer Rd & Shad Rd 2, 3 (should
be completed with or after Burnt
- Church and Alljoy)
1 Resolution 2019/22 Priorities
2 On BC Connects Plan
3 Direct Access to School/Park
a Dependent on input from Representatives
b Dependent on Developer
c In design
9
31
Priority Five
- US 17 Pathway Extension 2
- Seabrook Rd 2
- Paige Point Rd
- Big Road
- Spanish Moss Trail Extension
- Lake Point Dr & Old Miller Rd d
1 Resolution 2019/22 Priorities
2 On BC Connects Plan
3 Direct Access to School/Park
d Can be included with private development
10
32
11
Remaining Projects Expended to Date Remaining Budget Cumulative Remaining Project Total Status
Alljoy Road $ 263,138.70 $ 3,007,148.81 $ 3,007,148.81 $ 3,270,287.51 Bidding
Salem Road $ 200,360.10 $ 2,375,825.61 $ 5,382,974.42 $ 2,576,185.71 65% Design
Burnt Church Road $ 5,103.40 $ 3,359,496.60 $ 8,742,471.02 $ 3,364,600.00 Rescoping
Stuart Point Road $ 393,865.29 $ 3,116,879.11 $ 11,859,350.13 $ 3,510,744.40 ROW Acquisition
Depot Road $ 86,022.60 $ 908,004.37 $ 12,767,354.50 $ 994,026.97 Bidding
Dr Martin Luther King Jr Drive $ 225,775.45 $ 2,624,429.86 $ 15,391,784.36 $ 2,850,205.31 70% Design
Big Estate Road $ 234,201.95 $ 3,182,236.65 $ 18,574,021.01 $ 3,416,438.60 65% Design
Broad River Boulevard & Riley Road $ 67,499.90 $ 1,426,289.24 $ 20,000,310.25 $ 1,493,789.14 40% Design
Middle Road (original limits) $ 262,896.35 $ 3,117,127.90 $ 23,117,438.15 $ 3,380,024.25 70% Design
Joe Frazier Road $ - $ 3,432,000.00 $ 26,549,438.15 $ 3,432,000.00
Pine Grove Road (A-North , B-North) $ - $ 3,162,337.50 $ 29,711,775.65 $ 3,162,337.50
Burton Wells Road (West) $ - $ 2,339,225.00 $ 32,051,000.65 $ 2,339,225.00
Broad River Drive (West limits) $ 238,394.43 $ 1,489,673.20 $ 33,540,673.85 $ 1,728,067.63 55% Design
Meridian Road (original limits) $ 220,810.98 $ 4,550,270.19 $ 38,090,944.03 $ 4,771,081.17 35% Design
Old Salem Road $ 52,477.86 $ 1,190,602.14 $ 39,281,546.17 $ 1,243,080.00 30% Design
Burton Hill Road (original limits) $ 91,216.06 $ 2,926,035.62 $ 42,207,581.79 $ 3,017,251.68 30% Design
Chowan Creek Bluff $ - $ 1,346,000.00 $ 43,553,581.79 $ 1,346,000.00
Bruce K Smalls Road $ - $ 1,504,600.00 $ 45,058,181.79 $ 1,504,600.00
Ulmer Road $ 49,147.39 $ 2,574,388.90 $ 47,632,570.69 $ 2,623,536.29
Shad Avenue $ 33,899.27 $ 1,900,348.04 $ 49,532,918.73 $ 1,934,247.31 20% Design
US 17 Pathway Extension $ 6,749.68 $ 1,922,800.32 $ 51,455,719.05 $ 1,929,550.00 20% Design
Seabrook Road $ - $ 3,343,100.00 $ 54,798,819.05 $ 3,343,100.00
Paige Point Road $ - $ 3,123,700.00 $ 57,922,519.05 $ 3,123,700.00
Big Road (includes connection) $ - $ 2,726,000.00 $ 60,648,519.05 $ 2,726,000.00
Lake Point Drive/Old Miller Road $ - $ 1,445,000.00 $ 62,093,519.05 $ 1,445,000.00
$ 2,431,559.41 $ 62,093,519.05 $ 64,525,078.46
33
Updated Project Cost Estimates
Total Available for Spending = $23.33M + $21.74M + $11M = $56.07M
Total For 6/26/25 Scopes = $32.8M + $23.12M = $55.92M
12
34
Thank You
Visit connect.beaufortcountysc.gov for
more information on Beaufort County, or scan here!
35
RESOLUTION NO. 2025/ XX
A RESOLUTION TO REFINE AND SET AN ORDER OF PRIORITY OF THE PROJECT
LIST FOR THE 2018 ONE-CENT TRANSPORTATION SALES TAX PROGRAM
WHEREAS, On November 13th, 2017, by ordinance number 2017/34, Beaufort County
Council ("County Council") adopted enabling legislation authorizing the levy and collection of a
one-cent transportation sales tax; and
WHEREAS, the tax was approved in a referendum vote on November 6, 2018; and
WHEREAS, the tax was originally estimated to generate $120,000,000 over a four-year
collection period; and
WHEREAS, the referendum defined three project categories: US 278 Corridor Traffic
Improvements ($80 million), Lady's Island Corridor Traffic Improvements ($30 million) , and
Sidewalks and Multi-Use Pathways ($10 million); and
WHEREAS, actual collections exceeded expectations, and a total of $146.5 million was
collected from the 2018 One Cent Transportation Sales Tax Referendum; and
WHEREAS, inflationary pressures and rising construction costs have significantly
increased the estimated costs of delivery for the original projects, resulting in insufficient funds
being available to complete all projects as originally envisioned; and
WHEREAS, a new transportation sales tax referendum was proposed for the November
5, 2024, election to address the funding shortfall for the 2018 One Cent Transportation Sales Tax
Referendum projects; however, the Referendum was not approved by the voters and
WHEREAS, without an additional funding source, the approved project list for the 2018
One Cent Transportation Sales Tax Referendum projects must be refined and prioritized to
clearly identify the projects that can be completed with the available funds; and
WHEREAS, several projects identified in the 2018 One Cent Transportation Sales Tax
Referendum have been completed, including SC 802 (Sam’s Point Rd) Right Turn Lane, Airport
Frontage Road – Phase 1, Bluffton Parkway Pathway, Laurel Bay Road Pathway, and Ribaut
Road Sidewalk.
NOW, THEREFORE, BE IT ORDAINED BY BEAUFORT COUNTY
COUNCIL, in meeting duly assembled, establishes the refined project list in order of priority
and project scopes within the three project categories for the 2018 One Cent Transportation Sales
Tax funds;
36
US 278 Corridor Traffic Improvements
Construction of a new three-lane eastbound bridge (striped for two lanes) spanning both
Mackay Creek and Skull Creek, with direct access to Pinckney Island.
Demolition of the existing Mackay Creek bridge.
Lady’s Island Corridor Traffic Improvements
1. US 21/SC 802 Intersection
o Safety and capacity improvements, including restriping, signal upgrades, and the
addition of dual turn lanes in both directions on Sea Island Parkway.
o Includes resurfacing and median improvements in all four approaches to the
intersection.
2. US 21 Widening near Wal-Mart
o Approximately 4,000 linear feet of widening to create four travel lanes through
the US 21/Airport Frontage Road intersection.
o Includes turn lane and signal improvements.
3. Lady’s Island Middle School Access
o New access road to the Lady’s Island Middle School connecting to US 21 at a
new signalized intersection at Gay Drive.
o Removal of the existing Cougar Drive entrance.
o Construction of a 5-foot sidewalk along Robin Drive from the school to Sam’s
Point Way.
4. Hazel Farm Road and Gay Drive
o Paving of the unpaved section of Hazel Farm Road.
o Construction of a roundabout at Hazel Farm Road and Gay Drive.
o Resurfacing of Hazel Farm Road and Gay Drive from SC 802 to US 21.
5. Sunset Boulevard and Miller Drive West
o Reduce the speed limit from 35 mph to 30 mph.
o Realign the intersection of Sunset Boulevard and Miller Drive West for a
perpendicular approach.
o Install a 3-way stop and raised intersection.
o Add two speed humps on Miller Drive East.
o Resurface both roads from US 21 to SC 802.
6. Airport Frontage Road – Phase 2
o Complete design, permitting, right-of-way acquisition, and wetland mitigation.
o Construction will not be undertaken at this time.
Pathways
1. Alljoy Road
o 6-foot concrete sidewalk on the east side from Burnt Church Road to Shad
Avenue, then shifting to the west side from Shad Avenue to Thomas Lawton
Drive.
2. Salem Road
o 8-foot concrete pathway on the east side from Old Salem Road to SC 170.
o Includes a short section of 5-foot sidewalk and a midblock crossing to serve
apartments on the west side.
o Includes a 10-foot-wide wooden boardwalk over the creek
37
3. Burnt Church Road
o 6-foot concrete sidewalk on the east side from Alljoy Road to Bluffton Parkway.
4. Stuart Point Road
o 8-foot concrete pathway on the north side from US 21 to Delaney Circle.
5. Depot Road
o 10-foot concrete pathway on the south side from Ribaut Road to the Spanish
Moss Trail.
6. Dr. Martin Luther King Jr. Drive
o 5-foot concrete sidewalk on the east side from US 21 to Jonathan Francis Sr.
Road.
o Includes a 10-foot-wide wooden boardwalk over the tidal marsh.
7. Big Estate Road
o 8-foot concrete sidewalk on the west side from US 17 to African Baptist Church
Road.
8. Broad River Boulevard and Riley Road
o 5-foot concrete sidewalk beginning at Broad River Elementary School and
extending along Broad River Boulevard.
o Turns onto Riley Road and continues to the intersection with Fair Road, serving
the Shadow Moss neighborhood.
9. Middle Road
o 8-foot concrete sidewalk on the east side beginning at SC 802 (Sam’s Point Rd) to
Fly Catcher Lane and will be reduced in width to extend from Coosaw
Elementary to Walnut Hill St.
Adopted this ____ day of __________, 2025.
COUNTY COUNCIL OF BEAUFORT COUNTY
BY:
Alice Howard, Chairman
ATTEST:
_____
Sarah W. Brock, Clerk to Council
38
Salem Road Sidewalk Location – East Side versus West Side
Summary
East Side
This is currently 65% designed, pending final approval from SCDOT to begin R/W acquisition. It has a
budget of $2,675,000 and will be completed, including construction, within 2 years (Fall 2027).
West Side
No design has been performed. It has a budget of $3,896,422, which includes the expended amount for
the design on the East Side, and will be completed, including construction, within 4 years (Fall 2029).
Project Status and Budget
East Side
Design - 65% complete and addressing SCDOT’s comments to finalize right of way plans
o Includes boardwalk/bridge at creek whic h requires bridge hydraulic study and
geotechnical investigations
o Addresses public comments for connection to Garden Oaks and Residence at Battery
Creek apartment complexes – obtained additional survey and performed design for a 5-
ft sidewalk connection to the proposed 8-ft sidewalk
o Permit packages have been developed and will be submitted following SCDOT approval
of R/W plans
o Utility Coordination is underway
Public Meetings
o 1
st: Virtual Public Meeting with other priori ty projects held October 19, 2020, to
November 20, 2020
o 2nd: Public Meeting held on October 29, 2024, with virtual meeting from October 15, 2024,
to November 14, 2024
39
Page | 2
Schedule
Task Schedule Note
Complete R/W Plans Late Summer/Fall
2025
Approx. 3 months pending SCDOT review and addressing
final comments, if needed
R/W Acquisition 8 months – 1 year 20 tracts, Complete Summer/Early Fall 2026
Permits 6 months – 1 year Submit for approval at beginning of R/W acquisition
Final Construction Plans 3 – 6 months Complete while R/W acquisition is in progress
Begin Construction Fall 2026 – 8 months
– 1 year
Anticipate advertising in Fa ll 2026 and/or following
completion of R/W acquisition
Time to Complete Project, including construction: 2 years (Fall 2027)
Budget
Design* R/W Acquisition Utilities Construction CEI Mitigation Total
$275,000
($196,422.60)
$425,000 $225,000 $1,500,000 $225,000 $25,000 $2,675,000
*This is showing expended amount to date and will take approximately $75,000 to complete final construction plans,
permitting, geotechnical investigations for bridge, and other items as required.
o Utilities and CEI are 15% of construction budget. The utility budget incorporates Act 36 and any
utilities with prior rights.
o The Mitigation budget is included for impacts near the creek but may not be required.
o R/W Acquisition incorporates compensation to property owners, R/W Manager and agent fees,
potential condemnations.
West Side
Design
o Only conceptual plans have been developed as part of the virtual public meeting
o No design or surveys have been performed for the west side
o A boardwalk/bridge will be required at the creek and may be longer than the east side
due to topography
o Final R/W plans will take approximately 2 years +/- to complete once design is started
o Final construction plans will be developed while R/W acquisition is in progress
R/W Acquisition – approximately 15 tracts and will take 8 months to 1 year to complete
Public Meeting – will need to conduct another public meeting at 65% plans
40
Page | 3
Schedule
Task Schedule Note
Complete R/W Plans Fall 2027 No design/surveys have been performed
R/W Acquisition 8 months – 1 year 15 tracts, Complete Summer/Early Fall 2028
Permits 6 months – 1 year Submit for approval at beginning of R/W acquisition
Final Construction Plans 3 – 6 months Complete while R/W acquisition is in progress
Begin Construction Fall 2028 – 8 months
– 1 year
Anticipate advertising in Fa ll 2028 and/or following
completion of R/W acquisition
Time to Complete, including construction: 4 years (Fall 2029)
Budget
Design R/W Acquisition Utilities Co nstruction CEI Mitigation Total
$300,000
(+$196,422.60)
$425,000 $337,500 $2,250,000 $337,500 $50,000 $3,896,422
The above budgets are in addition to the amount expended for the design on the east side. The increase
in the budgets is for a longer boardwalk/bridge at the creek, potential for additional critical area impacts
at creek, potential for increase in utility impacts, etc.
Utilities, Trees, Critical Area
East Side
Utilities
The project has been designed to minimize/eliminate impacts for utilities, by meandering where feasible.
The budget is for compliance with Act 36 which allows wet utilities up to 4% of the construction cost for
the design and relocation/adjustment of existing fac ilities and for utilities with prior rights. The budget
will be updated once the utility coordination has been completed based on executed agreements.
Trees
Like the utilities, the project has also been designed to minimize/eliminate impacts for trees. The sidewalk
will meander where feasible. There is also an area where a bifurcated sidewalk – two 4’ sidewalks – have
been designed to reduce impacts to trees.
41
Page | 4
Critical Area
A critical area has been delineated at the existi ng creek, as this creek is tidal. The proposed
bridge/boardwalk over the creek will minimize impacts. A small area will be impacted for the sidewalk
connection to the bridge.
West Side
Utilities
The project will be designed to minimize/eliminate impacts for utilities, where feasible. Based on a field
review, underground dry and wet utilities are located on th is side. The overhead utilities are also on this
side, as the line crosses from the east to the west. To avoid the utilities, it will require an increase in right-
of-way acquisition.
Trees
The sidewalk would be designed to minimize/eliminate impacts for trees, where feasible.
Critical Area
Impacts to the critical area are anticipated based on the delineation. To minimize impacts, a longer
boardwalk/bridge would be required, but avoidance is not feasible.
Google Earth Image - View Looking North
Utilities on West Side near approach to bridge
BJWSA Lift Pump Station
Tract 17 on plans
Bridge over creek
42
Page | 5
Proposed Design from Plans for East Side at Bridge
CA = Critical Area Delineation
Potential impacts or
longer bridge to avoid CA
Increase in R/W to avoid
BJWSA Lift Pump Station
(Tract 17)
Minimal CA impacts for
sidewalk connection to
bridge/boardwalk
CA impacts for sidewalk
connection to bridge/
boardwalk on West side
Existing road bridge
43
Page | 6
Project Background and Safety
In Fall 2020, a virtual public meeting was held fr om October 19, 2020, to November 20, 2020, for the 14
priority public pathways which included Salem Road. The Salem Road exhibit showed the 8-ft shared use
path/sidewalk on both sides but was noted as: “Multiple paths are shown as options for public input. Only
one pathway will actually be constructed.”
For this virtual meeting, Salem Road in conjunction with Old Salem Road received 42 total comments with
31 “Yes” and 11 “No” responses. There were also only 5 written comments on the two projects with no
specific comments on which side should be selected.
Following the virtual meeting a nd presentation at the January 19, 2021 Public Facilities Committee
meeting for the Pathways Public Meeting No. 1 Summary and Recommendation, the projects moved
forward into design and the east side of Salem Road was selected based on the existing developments
and safety which applies for the newer developments.
Spanish Moss Trail
SC 170
Salem Road
Old Salem Road
Burton Hill Road
Battery Point
subdivision:
200+ homes
Salem Plantation
subdivision:
80 +/- homes
Island – 8 lots
Existing Residential:
130 +/- lots
2021 Developments
Residence at
Battery Creek
Oaks at Salem
Road, 123 Club,
and Residence at
Battery Creek
44
Page | 7
The Google Earth image below showcases the existing developments, shown on the previous map, and
the new developments, with only the new developments labeled. Two new developments – Garden Oaks
(apartments) and Salem Bay (single family residential) - have been or are being constructed along Salem
Road. Based on the additional developments, the sidewalk location on the east side serves more
residential development and reduces conflicts between pedestrians/bicyclists and vehicles.
The sidewalk location on the east side reduces conf licts between pedestrians/bicyclists and vehicles. On
the east side, approximately 520 residential properti es would have direct connection to the sidewalk
without crossing Salem Road. This would serve Sa lem Plantation, Salem Bay, 8 island lots, 130 +/-
residential lots, and other individual residences. There are also reduced conflicts for Battery Point
subdivision.
Battery Point subdivision has two entrances. Its main entrance – Battery Point Lane – is located on Old
Salem Road near the Old Salem Road/Burton Hill Road intersection. Its second entrance – Prescott Drive
2024 Developments
Salem Bay
Subdivision:
300 +/- homes
Garden Oaks
apartments:
288 units
SC 170
Spanish Moss Trail
Salem Road
Burton Hill Road
Old Salem Road
45
Page | 8
– is located at the Salem Road/Old Salem Road/Salem Drive W intersection, which is an all-way stop. The
main travel patterns for the all-way stop intersection are the following:
Old Salem Road to Salem Road
Old Salem Road to Prescott Drive
Salem Road to Prescott Drive
There are minimal vehicle trips from the above road s to Salem Drive W as Salem Drive W serves the 8
island properties and 19 residences. With the sidewalk on the east side, the Battery Point citizens would
cross Salem Drive West for access which has fewer vehicular trips.
Battery Point
subdivision
Prescott Drive
Salem Drive W
Salem Road
Old Salem Road
Burton Hill Road
All-way Stop Intersection
Battery Point Lane
46
Page | 9
Also, with the sidewalk located on the east side, there is a direct connection from Salem Road to the
Spanish Moss Trail, eliminating conflicts between pede strians/bicyclists and vehicles, only for the Salem
Road sidewalk users. The existing 5-ft sidewalk from Salem Road to the Spanish Moss Trail would be
replaced with an 8-ft sidewalk fo r improved connectivity. Pedestrians/bicyclists on the SC 170 sidewalk
crossing Salem Road would still need to be aware of vehicles turning left or right from SC 170 onto Salem
Road as well as vehicles from Sale m Road turning onto SC 170. The side walk on the east side of Salem
Road reduces the overall potential conflicts for pedestrians/bicyclists with vehicles.
The east side location improves safety for three ex isting developments on Old Salem Road. When the 8-
ft sidewalk is constructed on the north side of Old Salem Road connecting Oaks at Salem Road, 123 Club,
and Residence at Battery Creek to the Salem Road si dewalk, the pedestrians/bicyclists will cross Salem
Road at the all-way stop intersection. While ther e is a potential for pedestrian/bicycle and vehicle
conflicts at all intersections, an all-way stop assist s with reducing the potential for conflicts and/or the
severity of impact. In addition, the Old Salem Road users would be on the east side of Salem Road at the
SC 170 intersection, eliminating their conflict with vehicles. The SC 170 intersection has a greater potential
for conflicts since only Salem Road is stop-controlled, and SC 170 is free-flow.
Spanish Moss Trail
SC 170 (Robert
Smalls Parkway)
Salem Road
Sidewalk on east
side of Salem Road
connects directly to
Spanish Moss Trail
with no conflicts
between
peds/bikes and
vehicles
47
Page | 10
Other improvements are being incorporated based on public comments from the 2 nd Public Meeting.
Additional survey and design have been performed to address connectivity from Garden Oaks and
Residence at Battery Creek apartment complexes. A 5-ft sidewalk is proposed from the Salem Road/Salem
Bay Drive intersection to the Garden Oaks sidewalk around the pond and a 5-ft sidewalk along Salem Road
to the Residence at Battery Creek Driveway. It will include a new crosswalk across Salem Road at Salem
Bay Drive which aligns with Salem Bay’s sidewalk. The sidewalk has been designed for ADA compliance
from Salem Road to the Garden Oaks sidewalk. Since th ere is a horizontal curve on Salem Road near this
intersection, the stopping sight distance was checked for the crosswalk, and it meets/exceeds the design
standard.
Salem Road
Garden Oaks
sidewalk
Residence at
Battery Creek
driveway
Salem Bay Road
Sidewalk location
Crosswalk and
pedestrian
signs will be
installed on
Salem Road
Sidewalk
Connections
meeting ADA
compliance
48
Page | 11
Below is the proposed design for the 5-ft sidewalk connection to the two apartment complexes that has
been incorporated following the public meeting.
Existing Garden Oaks
sidewalk at pond
Proposed sidewalk
meeting ADA
compliance
Proposed sidewalk
from Garden Oaks
Proposed sidewalk to
Residence at Battery
Creek Driveway
Crosswalk and connection to
Salem Road 8-ft sidewalk and
Salem Bay Drive 5-ft sidewalk
Salem Bay Drive
Proposed 8-ft sidewalk
49
T a b l e o f C o n t e n t s P a g e
Lady’s Island Projects
• US 21 Corridor Public Meeting 1 Summary 1
• US 21/SC 802 Corridor 1
• Lady’s Island Access Road Public Meeting Summary 2
• C o m p l e t e d P r o j e c t s 3
o SC 802 (Sam’s Point Road) Right Turn Lane
o Airport Frontage Road Phase I
• P r o j e c t s O n - h o l d 4
o Beaufort High School Access Realignment
o Mayfair Court Extension
o Meadowbrook Road Extension
• Lady’s Island Middle School Access Road 5
• H a z e l F a r m R o a d & G a y D r i v e 6
• A i r p o r t F r o n t a g e R o a d P h a s e I I 7
• Sunset Boulevard & Miller Drive W 8
Pathway & Sidewalk Projects
• Pathways & Sidewalks Public Meeting 1 Summary 9
• C o m p l e t e d P r o j e c t s 1 0
o BluƯton Parkway
o Laurel Bay Road
o Ribaut Road
• A l l j o y R o a d 1 1
• S a l e m R o a d 1 2
• B u r n t C h u r c h R o a d 1 3
• S t u a r t P o i n t R o a d 1 4
• D e p o t R o a d 1 5
• D r . M a r t i n L u t h e r K i n g J r D r i v e 1 6
• B i g E s t a t e R o a d 1 7
• Broad River Boulevard and Riley Road 18
• M i d d l e R o a d 1 9
• J o e F r a z i e r R o a d 2 0
• P i n e G r o v e R o a d 2 0
• B u r t o n W e l l s R o a d 2 1
• B r o a d R i v e r D r i v e 2 2
• M e r i d i a n R o a d 2 3
• O l d S a l e m R o a d 2 4
• B u r t o n H i l l R o a d 2 4
50
Pathway & Sidewalk Projects (cont’d)
• Chowan Creek BluƯ 2 5
• B r u c e K S m a l l s D r i v e 2 5
• U l m e r R o a d 2 6
• S h a d A v e n u e 2 6
• U S 1 7 P a t h w a y E x t e n s i o n 2 7
• S e a b r o o k R o a d 2 7
• P a i g e P o i n t R o a d 2 8
• B i g R o a d 2 8
• L a k e P o i n t D r i v e / O l d M i l l e r R o a d 2 9
51
Page | 1
US 21 Corridor Public Meeting 1 Summary
virtual meeting February 8 through March 7, 2021, with virtual Town Hall on February 18, 2021
Exhibit
Selection of Exhibit
Preferred Not Preferred
East Area Exhibit 1 9 7
West Area Exhibit 1 12 10
West Area Exhibit 2 4 16
West Area Exhibit 3 6 15
West Area Exhibit 4 7 14
Pedestrian and Bicycle Accommodations
Question Yes No
Do you currently utilize the existing bicycle/pedestrian facilities? 14 19
Would you use the proposed bicycle and pedestrian improvements? 17 16
Rank the Importance of: Average Rank (Scale from 0-10)
Bicycle/Pedestrian Facilities 5.3
Vehicle Capacity 5
US 21/SC 802 Corridor
Improvements to the intersection of US 21 BUS (Sea Island Parkway)/US 21 (Lady’s Island Drive)/ SC 802 (Sams Point
Rd); and capacity/widening improvements from Airport Circle east to beyond Wal-mart’s second driveway
Funding: Sales Tax
Current Status: Preliminary R/W Plans for original project; rescoping will require redesign and/or plan revisions to
remove portions which are no longer included
Notes:
1. US 21/SC 802 (A): Revising design and separating from corridor project, includes replacing pipe at Wal-greens
2. US 21/SC 802 (B): Widening for dual left turn lanes and access management, separating plans from original corridor project,
preparing permits
3. US 21 near Wal-mart (approx. 4000 lf) - Separating plans from original corridor project, completing final construction plans,
preparing permits
Original US 21/SC 802 (A) US 21/SC 802 (B) US 21 near Wal-mart Expended to Date
Design 620,000.00 $ 100,000.00 $ 100,000.00 $ 100,000.00 $ 607,676.49 $
R/W Acquisition - $ - $ 1,938,168.00$ 688,980.50 $
Utilities 100,000.00 $ 175,000.00 $ 1,014,000.00$ 350,000.00 $
Construction 8,039,787.43$ 3,500,000.00 $ 6,760,000.00 $ 7,000,000.00 $
CEI 220,000.00 $ 525,000.00 $ 1,014,000.00$ 875,000.00 $
Contingency 1,795,957.49$
Mitigation - $ 150,000.00 $
Total 10,775,744.92 $ 4,300,000.00 $ 10,826,168.00 $ 9,163,980.50 $ 607,676.49 $
52
Page | 2
Lady’s Island Access Road Public Meeting 1 Summary
virtual meeting January 18 through February 21, 2021, with virtual Town Hall on January 21, 2021
Roadway
“In Favor Of” “Resides Near” “Utilizes Roadway”
Yes No Yes No Yes No
Airport Frontage Road 11 8 2 17 11 9
Beaufort High School Access Realignment 18 8 13 11 21 4
Hazel Farm Road and Gay Drive 12 7 7 14 13 8
Mayfair Court Extension 11 9 9 11 10 10
Meadowbrook Drive Extension 11 3 5 12 9 8
Sunset Boulevard and Miller Drive West 10 30 31 10 35 6
Roadway
“In Favor Of” “Resides Near” “Utilizes Roadway”
Option 1 Option 2 Neither Yes No Yes No
Lady’s Island Middle School Access Rd 5 3 8 4 15 8 10
Pedestrian and Bicycle Accommodations
Yes No
In Favor of Both 20 6
Facility Types
Pedestrian Only 13 2
Bicycle Only (Shared Travel Lane) 3 6
Bicycle Only (4’ Bike Lane) 8 5
Pedestrian and Bicycle (Shared-use Path) 14 5
Note: Recommendation was to proceed with the design on all projects except Mayfair Court Extension.
53
Page | 3
Completed Projects
SC 802 (Sam’s Point Road) Right Turn Lane
A dedicated right turn lane was constructed allowing the ou tside travel lane to be restriped as a through lane. The
existing conditions for the westbound approach to the signal at the US 21 BUS/US 21/SC 802 intersection were: 1) the
outside travel lane became a dedicated right turn lane, 2) th e inside travel lane was a single through lane, and 3) the
paved median became a dedicated left turn lane. By constructing the right turn lane, this allowed for two through lanes
which improved the operations and capacity of the intersection.
Airport Frontage Road Phase I
A new 2- lane road from the existing signal at US 21 (Sea Island Parkway)/Airport Circle intersection to Lost Island Road.
The road provides improved safety for property owners on Lost Island Road by allowing users access to the signalized
intersection since future improvements will convert the Lost Island Road intersection at Sea Island P arkway to right-
in/right-out. The project also constructed an 8’ sidewalk on one side and incorporated lighting and landscaping.
Amount
Design 49,164.35 $
R/W Acquisition 124,103.42$
Utilities 71,154.28 $
Construction 384,110.57$
CEI 106,469.56 $
Mitigation - $
Total 735,002.18 $
Amount
Design 78,688.29 $
R/W Acquisition 14,850.00$
Utilities 5,294.62 $
Construction 2,793,663.97$
CEI 310,179.34 $
Mitigation - $
Total 3,202,676.22 $
54
Page | 4
Projects On-hold
Note: The remaining budgets were removed and will be utilized for other projects since the original budgets from the
2017 study did not include right of way acquisition and other items.
Beaufort High School Access Realignment
A new road for access to the high school. The existing access is located on
US 21 Bus (Sea Island Parkway) approximately 500 lf west of the Sunset
Boulevard intersection. Multiple options for a new access road were
reviewed, and since an option was not selected, the project was placed
on-hold.
Mayfair Court Extension
This was an extension of Mayfair Court to William Street (private road) and
it included paving the existing Mayfair Court. The extension to William
Street provided alternate access for residents since Mayfair Court is
proposed to be right-in/right-out with the SC 802 (Sam’s Point Road)
access management improvements. The project was placed on-hold
following the first public meeting based on comments.
Meadowbrook Road Extension
Meadowbrook Road Extension, as shown in the 2017 study, was a new road
from Meadowbrook Drive/Lupo Drive intersection to Dow Road and
provided alternate access for several properties along US 21 (Sea Island
Parkway). Prior to the 2018 Sales Tax, Meadowbrook Baptist Church
acquired the property, and through coordination with the church, it was
agreed to revise the road limits to for the access. Preliminary right of way
plans were developed and the project was placed on-hold based on
funding for other projects, coordination with SCDOT, and public comments.
Expended to Date
Design 283,409.92 $
R/W Acquisition 2,226.28$
Utilities - $
Construction - $
CEI - $
Mitigation - $
Total 285,636.20 $
Expended to Date
Design 1,847.75 $
R/W Acquisition - $
Utilities - $
Construction - $
CEI - $
Mitigation - $
Total 1,847.75 $
Expended to Date
Design 114,904.94 $
R/W Acquisition - $
Utilities - $
Construction - $
CEI - $
Mitigation - $
Total 114,904.94 $
55
Page | 5
Lady’s Island Middle School Access Road
Project will be completed as scoped with a new access road from US 21 (Sea Island Parkway)/Gay Drive intersection to
Robin Drive/Katy Circle intersection. Improvements include a 10’ shared-use path on the east side and a 5’ sidewalk on
the west side. A 5’ sidewalk is included along Robin Drive on the south side from Sam’s Point Way to the new road. The
existing Cougar Drive will either be closed or converted to Right In/Right Out.
Funding: Sales Tax
Current Status: R/W Acquisition
Notes;
1. Design: R/W plans complete. Beginning final design.
2. Utilities: Utility coordination in progress.
3. R/W Acquisition is in progress.
Public Meeting 2: May 14, 2024, with virtual meeting May 1 through June 2, 2024
(joint meeting with Airport Frontage Road Phase 2; summary is for Lady’s Island Middle School Access Road)
Questions Yes No
Do you live near the proposed project? 7 3
Would you utilize the proposed project? 7 3
Are you in favor of the proposed project? 6 4
Original Revised Expended to Date
Design 115,000.00 $ 457,780.49 $ 436,652.43 $
R/W Acquisition - $ 2,046,720.00$ 80,450.00 $
Utilities 20,000.00 $ 750,000.00$ - $
Construction 1,030,733.33$ 5,500,000.00 $ - $
CEI 70,000.00 $ 825,000.00$ - $
Contingency 247,146.67$
Mitigation - $ - $ - $
Total 1,482,880.00 $ 9,579,500.49 $ 517,102.43 $
56
Page | 6
Hazel Farm Road & Gay Drive
The original project scope was to complete improvements al ong Hazel Farm Rd and Gay Drive to include paving Hazel
Farm Road, roundabout at the intersection of Hazel Farm Road, Gay Drive, and Inlet Drive, pedestrian accommodations
along Gay Drive and street scaping. The project will be rescoped to complete the paving of Hazel Farm Road,
constructing the roundabout and roadway improvements along Gay Drive, including resurfacing. Pedestrian
improvements will be designed but will not be completed at this time. A traffic signal will be installed at the intersection
of US 21 (Sea Island Parkway) and Gay Drive.
Funding: Sales Tax
Current Status: Preliminary R/W Plans
Notes:
1. Design: Significant scope change and re vamping of plans. The $300K is in addition to their cu rrent budget. Wetland permit
has been received.
2. R/ W : Ha ze l F a rm Rd a nd r o u nda bo u t wi ll ha v e 16 tra c ts fo r rev i sed sc o pe. O nly 1 0 a ddi ti o na l ri g ht o f wa y tra c ts a nd 1 4
permission only tracts for full design.
3. Utilities: Utility coordination is in progress. Original scope assume potential underground of overhead utilities. If no
undergrounding, then 15% of construction is approx. $1 M and would need to confirm utilities with prior rights.
Public Meeting 2: January 30, 2025, with virtual meeting January 15 through February 15, 2025
(joint meeting with Sunset Boulevard/Miller Drive W; summary is for Hazel Farm Road/Gay Drive – note multiple participants near
Sunset Boulevard/Miller Drive W were also opposed to th ese improvements, summary and recommendation has not been
published pending approval to proceed with original/revised scope)
Questions Yes No
Do you live near the proposed project? 13 32
Would you utilize the proposed project? 12 28
Are you in favor of the proposed roadway? 11 31
Original Revised Revised Scope Expended to Date
Design 250,500.00 $ 582,171.34 $ 300,000.00 $ 536,377.35 $
R/W Acquisition - $ 1,365,292.62$ 1,092,845.00 $ 14,689.50 $
Utilities 50,000.00 $ 2,000,000.00$ 825,000.00 $ - $
Construction 2,045,964.04$ 7,500,000.00 $ 5,500,000.00 $
CEI 140,000.00 $ 825,000.00 $ 525,000.00 $ 4,945.22 $
Contingency 497,292.81$ - $
Mitigation - $ - $ - $ - $
Total 2,983,756.85 $ 12,272,463.96 $ 8,242,845.00 $ 556,012.07 $
Total: Revised scope, complete current design, expended 8,798,857.07$
57
Page | 7
Airport Frontage Road Phase II
T h i s i s a r e a l i g n m e n t o f L i t t l e C r e e k R o a d t o t h e L o s t I s l a n d R o a d / A i r p o r t F r o n t a g e R o a d P h a s e 1 i n t e r s e c t i o n . T h e
existing Little Creek Road from the realignment to US 21 (S ea Island Parkway) will be removed and the intersection
closed on Sea Island Parkway. The project includes an 8’ sidewalk and connects residents to the existing traffic signal
at Airport Frontage Road/Airport Circle/Sea Island Parkway intersection. Lost Island Road would also be converted to
right-in/right-out. Project design and permitting will be completed but the project will not be constructed.
Funding: Sales Tax
Current Status: R/W Acquisition
Notes:
1. Original: Remainder not expended on Phase 1 which has been constructed.
2. Design: Final construction plans approximately 95%.
3. R/W Acquisition: This is in progress.
4. Permits: These have been submitted and are in progress.
5. CEI: RCE initial review of plans, quantities, and constructability.
Public Meeting 2: May 14, 2024, with virtual meeting May 1 through June 2, 2024
(joint meeting with Lady’s Island Middle School Access Road; summary is for Airport Frontage Road Phase 2)
Questions Yes No
Do you live near the proposed project? 2 2
Would you utilize the proposed project? 3 0
Are you in favor of the proposed project? 2 2
Original Revised Expended to Date
Design 512,026.71 $ 370,395.40 $ 234,104.24 $
R/W Acquisition - $ 334,151.29$ 2,850.00 $
Utilities 94,705.38 $ 90,000.00 $
Construction 1,170,895.55$ 3,000,000.00 $
CEI - $ 330,000.00$ 5,046.24 $
Mitigation - $ 298,712.36$
Total 1,777,627.64 $ 4,423,259.05 $ 242,000.48 $
58
Page | 8
Sunset Boulevard & Miller Drive W
Scope will be reduced to include resurfacing of both roads and traffic calming including three-way stops and raised
intersections.
Funding: Sales Tax
Current Status: Preliminary R/W Plans
Notes:
1. Design: The fee is in addition to the expended to date to recreate plans and details for revised scope.
Public Meeting 2: January 30, 2025, with virtual meeting January 15 through February 15, 2025
(joint meeting with Hazel Farm Road/Gay Drive; summary is for Sunset Boulevard/Miller Drive W; summary and recommendation
has not been published pending approval to proceed with original/revised scope)
Questions Yes No
Do you live near the proposed project? 57 13
Would you utilize the proposed project? 28 37
Are you in favor of the proposed roadway? 16 55
Original Revised Revised Scope Expended to Date
Design 375,000.00 $ 574,309.92 $ 100,000.00 $ 458,350.53 $
R/W Acquisition - $ 2,514,652.35$ - $
Utilities 100,000.00 $ 2,000,000.00$ - $
Construction 3,390,129.18$ 7,320,258.36 $ 1,500,000.00 $
CEI 170,000.00 $ 805,228.42 $ 225,000.00 $
Contingency 807,025.84$
Mitigation - $ - $
Total 4,842,155.02 $ 13,214,449.05 $ 1,825,000.00 $ 458,350.53 $
59
Page | 9
Pathways & Sidewalks Public Meeting 1 Summary
virtual meeting October 19 through November 20, 2020, for all priority projects – approved in January 2021 Public Facilities
Committee meeting
Public Comments (“In Favor of” summary)
Recommendations: (for the initial projects with the original $10M budget)
• Burnt Church Road – Design and construct with road project
• Depot Road – City of Beaufort obtained CDBG funds
• Bluffton Parkway
• Ribaut Road to Parris Island Gateway
• Alljoy Road – In place of Shad Avenue and Ulmer Road since significant comments were received, and it could
remain within SCDOT’s present R/W. It also did not require any wetland permits.
• Salem Road
• Dr. Martin Luther King Jr Drive
• Middle Road
• Stuart Point Road
If additional funding is available, then the following projects would be designed and constructed:
• Big Estate Road
• Broad River Boulevard and Riley Road
• Broad River Drive
• Burton Hill Road and Old Salem Road
• Meridian Road
• Shad Avenue and Ulmer Road
Pathway Location (District) Yes No Total % Yes Pathway Location (District) Yes No Total % Yes
Big Estate Rd (1) 21 16 37 57 Meridian Rd (3) 41 13 54 76
Bluffton Pkwy (9) 47 13 60 78 Middle Rd (2) 30 11 41 73
Broad River Blvd and Riley Rd (5) 24 12 36 67 Dr. Martin Luther King, Jr. Dr (3) 24 11 35 69
Broad River Dr (4) 29 12 41 71 Salem Road and Old Salem Rd (5) 31 11 42 74
Burnt Church Rd (9) 94 7 101 93 Ribaut Rd to Parris Island Gateway (4) 37 10 47 79
Burton Hill Rd (5) 31 9 40 78 Shad Ave and Ulmer Rd (9) 36 10 46 78
Depot Rd (4) 35 13 48 73 Stuart Point Rd (1) 20 14 34 59
60
Page | 10
Completed Projects
Bluffton Parkway
An extension of the existing 8’ path, on the south side, along Blu ffton Parkway from the Soperton Drive intersection to
the roundabout at SC 46 (Bluffton Road). The project required additional right of way from two tracts.
Laurel Bay Road
The project improved the connectivity from the Marine Co rps Air Station with the Laurel Bay Housing Complex and
connectivity for everyone with the Spanish Moss Trail by re placing the existing asphalt sidewalk, which was in poor
condition, with a 10’ concrete shared-use path. The project also incorporated a 5’ sidewalk along Shanklin Road for
access to two commercial properties and installed pedestrian signs and crosswalk to improve safety.
Ribaut Road
This was an extension of the existing 5’ sidewalk from near Rahn Lane to Lenora Drive. The project required new right
of way from several tracts.
Amount
Design 51,132.93 $
R/W Acquisition 90,493.74$
Utilities - $
Construction 192,589.97$
CEI 51,373.88 $
Mitigation - $
Total 385,590.52 $
Amount
Design 316,271.45 $
R/W Acquisition - $
Utilities - $
Construction 4,831,889.91$
CEI 650,131.22 $
Mitigation 37,824.60$
Total 5,836,117.18 $
Amount
Design 63,013.83 $
R/W Acquisition 55,751.50$
Utilities 4,525.62 $
Construction 236,842.05$
CEI 50,009.47 $
Mitigation - $
Total 410,142.47 $
61
Page | 11
Remaining Projects
Alljoy Road
A 6’ concrete sidewalk along the east side of Alljoy Road from Burnt Church Road to Shad Avenue and the west side
from Shad Avenue to Thomas Lawton Drive. Path to be constructed per SCDOT standards within current Right-of-Way.
Associated drainage improvements will be constructed as well.
Funding: $1,177,868.71 TAP grant for construction and Sales Tax
Current Status: Procurement – pending approvals to award contract for construction, anticipate NTP in September
Notes:
1. Design: Balance remaining should accommodate constr uction phase services by engineers if there are any
questions by the contractor or RCE/CEI team.
2. Utilities: One utility agreement executed with Dominion Energy; one MOA with BJWSA in compliance with Act 36 for
in contract utility relocation, eligible for 4% max construction cost. BJWSA is responsible for costs above 4% max and
will be required to submit funds to the County prior to construction for the amount above 4%.
3. Construction: Project was advertised for construction and bids were received June 6, 2025. Evaluation of bids is
underway and a recommendation to award has been submitted to SCDOT in compliance with the TAP grant.
4. CEI: RCE review of plans and setting up files in advance of construction.
Public Meetings:
• Community Meeting – Saturday, June 12, 2021
• Public Meeting 1 – July 1, 2021, with virtual meeting July 1 through July 30, 2021
• Public Meeting 2 – September 14, 2021
• Public Meeting 3 – October 28, 2021
• Public Meeting 4 – January 10, 2023
Initial meetings were based on conceptual plans. Public Meeting 4 presented the proposed design.
From Public Meeting 4:
Questions Yes No
Are you in favor of the proposed 6’ sidewalk? 31 12
Do you reside near the proposed 6’ sidewalk? 41 3
Will you utilize the proposed 6’ sidewalk? 33 9
Original Revised Expended to Date
Design 289,769.75 $ 289,769.75 $ 256,007.96 $
R/W Acquisition - $ - $ - $
Utilities 112,500.00 $ 95,717.46 $ - $
Construction 750,000.00$ 2,508,522.00$ - $
CEI 75,000.00 $ 376,278.30$ 7,130.74 $
Mitigation - $ - $ - $
Total 1,227,269.75 $ 3,270,287.51 $ 263,138.70 $
62
Page | 12
Salem Road
An 8’ concrete sidewalk along the east side of Salem Road from Old Salem Road to SC 170 (Robert Smalls Parkway). A
5’ sidewalk will be constructed for a minimal section along with a midblock crossing to provide access to apartments
on the west side. Path to be constructed per SCDOT standards within current Right-of-Way with additional Right-of-Way
needed. Associated drainage improvements will be constructed as well. A 10’ boardwalk will be constructed over the
creek. Proposed sidewalk meanders where feasible for avoidance of trees. Sta ff is reviewing the feasibility of the
sidewalk being constructed on the opposite side of the road.
Funding: Sales Tax
Current Status: Preliminary R/W plans, updated plans base d on public comments for connection to apartments, and
will resubmit to SCDOT within 1 month for final approval to receive R/W authorization
Notes:
1. Design: Preliminary R/W plans have been developed and updated for new developments. Original design fee did
not include boardwalk structural design and additional H&H analysis.
2. Utilities: Utility coordination is in progress.
Public Meeting 2:
Questions Yes No
Do you live near the proposed project? 34 2
Would you utilize the proposed project? 35 1
Are you in favor of the proposed 8’ sidewalk? 34 2
Original Revised Expended to Date
Design 177,847.31 $ 177,847.31 $ 200,360.10 $
R/W Acquisition 139,800.00$ 423,338.40 $
Utilities 225,000.00 $ 225,000.00 $
Construction 1,500,000.00$ 1,500,000.00 $
CEI 150,000.00 $ 225,000.00 $
Mitigation 25,000.00$ 25,000.00 $
Total 2,217,647.31 $ 2,576,185.71 $ 200,360.10 $
63
Page | 13
Burnt Church Road
A 6’ concrete sidewalk along Burnt Church Road from Alljoy Road to Blu ffton Parkway. Sidewalk to be installed on the
east side of the road. Path to be constructed per SCDOT standards within current Right-of-Way with minimal additional
Right-of-Way expected. Associated drainage improvements will be constructed as well.
Funding: Impact Fees – road widening project with pathway
Current Status: Originally removed and combined with road widening project, not programmed for design under sales
tax
Notes:
1. Design: Length is approx. 7,000 LF; assumes survey could be used from widening project. Expended to date
includes conceptual exhibit for first virtual public meeting.
2. R/W Acquisition: 24 tracts
3. Mitigation: No wetlands shown on National Wetland Inventory.
Budget Expended to Date
Design 157,500.00 $ 5,103.40 $
R/W Acquisition 1,159,600.00$ - $
Utilities 236,250.00 $ - $
Construction 1,575,000.00$ - $
CEI 236,250.00 $ - $
Mitigation - $ - $
Total 3,364,600.00 $ 5,103.40 $
64
Page | 14
Stuart Point Road
An 8’ concrete sidewalk along the north side of Stuart Point Road from US 21 (Trask Parkway) to Delaney Circle. Path to
be constructed per SCDOT standards within current Right-of-Way with additional Right-of-Way needed. Associated
drainage improvements will be constructed as well. Project includes CDBG funding.
Funding: $200,000 CDBG for construction and Sales Tax
Current Status: Completing R/W acquisition, pending Council approval of condemnations; if approved, advertise for
construction once LCOG & Commerce concur. SCDOT has provided construction authorization.
Notes:
1. Design: Final construction plans approved by SCDOT. Update completed for 2025 specifications and pay items.
2. R/W Acquisition: This is being finalized and will require Council to approve condemnations.
3. Utilities: Final utility coordination is in progress and will require agreements. Revised budget updated for Act 36
and utilities with prior rights.
4. CEI: RCE initial review of quantities.
Public Meetings:
• Public Meeting 2: October 5, 2021, with virtual meeting from October 6 through October 20, 2021
• Public Meeting 3: November 16, 2021 – presentation of recommendation to community for meeting 2
• Public Meeting 4: April 4, 2023, with virtual meeting from March 20 through April 20, 202
Initial meetings were based on conceptual plans. Public Meeting 4 presented the proposed design.
From Public Meeting 4:
Questions Yes No
Are you in favor of the proposed 8’ sidewalk? 8 0
Do you reside near the proposed 8’ sidewalk? 7 0
Will you utilize the proposed 8’ sidewalk? 8 0
Original Revised Expended to Date
Design 386,958.00 $ 386,958.00 $ 265,095.21 $
R/W Acquisition 209,232.00$ 333,412.00 $ 128,428.00 $
Utilities 225,000.00 $ 138,600.00 $
Construction 1,500,000.00$ 2,376,000.00 $
CEI 150,000.00 $ 275,774.40 $ 342.08 $
Mitigation - $ - $
Total 2,471,190.00 $ 3,510,744.40 $ 393,865.29 $
65
Page | 15
Depot Road
A 10’ concrete pathway along the south side of Depot Road from Ribaut Road terminating near the Spanish Moss Trail.
Path to be constructed per SCDOT standards within current Right-of-Way with minimal additional Right-of-Way needed.
Associated drainage improvements will be constructed as well.
Funding: $200,000 CDBG for construction and Sales Tax
Current Status: Procurement – pending approvals to award contract for construction, anticipate NTP in September
Notes:
1. Design: Contract was held by others.
2. R/W: 2 tracts were approved for condemnation. This includes R/W team, attorney fees to date and checks deposited
with the Clerk of Court.
3. Utilities: Final utility coordination in progress and on e utility agreement executed wi th BJWSA for compliance with
ACT 36 (max 4% of construction cost).
4. Construction: Project was advertised, and bids were received May 15. Recommen dation to award has been
submitted to SC Dept. of Commerce (Commerce) and Lowc ountry Council of Governments (LCOG) for approval in
compliance with CDBG funding.
5. CEI: RCE review of plans and setting up files in advance of construction.
Original Revised Expended to Date
Design - $ - $ - $
R/W Acquisition 18,800.00$ 160,000.00$ 81,077.38 $
Utilities 62,500.00 $ 28,034.52 $ - $
Construction 250,000.00$ 700,863.00 $
CEI 25,000.00 $ 105,129.45$ 4,945.22 $
Mitigation - $ - $ - $
Total 356,300.00 $ 994,026.97 $ 86,022.60 $
66
Page | 16
Dr. Martin Luther King Jr. Drive
A 5’ concrete sidewalk along the east side of Dr. Martin Lu t h e r K i n g J r . D r i v e f r o m U S 2 1 ( S e a I s l a n d P a r k w a y ) t o
Johnathan Francis Sr Road. Sidewalk to be constructed per SCDOT standards within current Right-of-Way with
additional Right-of-Way needed. Associated drainage improv ements will be constructed as well. A 10’ wide wooden
boardwalk will be constructed over the tidal marsh. Staff is reviewing the utilization of pervious concrete.
Funding: Sales Tax
Current Status: Preliminary R/W Plans, coordinating with SCDOT on final plan and report comments to receive R/W
authorization
Notes:
1. Design: R/W plans resubmitted to SCDOT requesting R/W au thorization. Original design fee did not include boardwalk
structural design & geotechnical investigation, infiltration testing, additional H&H analysis for boardwalk, etc.
2. Utilities: Utility coordination is in progress.
Public Meetings:
• Public Meeting 2: November 4, 2021, with virtual meeting from October 22 through November 19, 2021
• Public Meeting 3: June 27, 2024, with virtual meeting from June 10 through July 12, 2024
Initial meetings were based on conceptual plans. Public meeting 3 presented the proposed design.
From Public Meeting 3:
Questions Yes No
Do you live near the proposed project? 17 11
Would you utilize the proposed project? 23 5
Are you in favor of the proposed 10’ pathway? 21 6
Stakeholder Coordination:
• Penn Center
• Brick Baptist Church in association with the National Park Service
• Ebeneezer Baptist Church
Original Revised Expended to Date
Design 275,000.00 $ 275,000.00 $ 225,775.45 $
R/W Acquisition 129,000.00$ 226,803.50 $
Utilities 225,000.00 $ 225,000.00 $
Construction 1,500,000.00$ 1,746,624.00 $
CEI 150,000.00 $ 261,993.60 $
Mitigation 100,000.00$ 114,784.21 $
Total 2,379,000.00 $ 2,850,205.31 $ 225,775.45 $
67
Page | 17
Big Estate Road
An 8’ concrete sidewalk along the west side of Big Estate Road from US 17 to African Ba ptist Church Road. Path to be
constructed per SCDOT standards within current Right-of-W ay with additional Right-of-Way needed. Associated
drainage improvements will be constructed as well. Project includes wetland impacts including the installation of an
additional 72” culvert pipe to convey stormwater.
Funding: Sales Tax
Current Status: R/W acquisition
Notes:
1. Design: R/W plans have been approved by SCDOT. Additional design in progress for crossing at African Baptist
Church Rd and final construction plans.
2. R/W Acquisition: SCDOT has approved R/W authorization and the acquisition process has started.
3. Utilities: Utility coordination is in progress.
Public Meeting 2: January 28, 2025, with virtual meeting January 8 through February 7, 2025
Questions Yes No
Do you live near the proposed project? 12 2
Would you utilize the proposed project? 12 2
Are you in favor of the proposed 8’ sidewalk? 11 2
Original Revised Expended to Date
Design 269,408.69 $ 269,408.69 $ 227,201.95 $
R/W Acquisition 141,806.00$ 216,451.40 $ 7,000.00 $
Utilities 300,000.00 $ 300,000.00 $
Construction 2,000,000.00$ 2,000,000.00 $
CEI 200,000.00 $ 300,000.00 $
Mitigation - $ 330,578.51$
Total 2,911,214.69 $ 3,416,438.60 $ 234,201.95 $
68
Page | 18
Broad River Blvd and Riley Road
A 5’ concrete sidewalk along the south side of Broad River Boulevard providing a safe route from Broad River Elementary
to the Shadow Moss neighborhood. The sidewalk will begin at the school, travel down Broad River Boulevard, before
turning left onto Riley Road. It will run the length of Riley Road until the intersection with Fair Rd. Sidewalk to be
constructed per SCDOT standards within current Right-of-W ay with additional Right-of-Way needed. Associated
drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: 50% complete and working on preliminary R/W plans
Note:
1. Design: Design is approximately 50% complete. Infiltration testing has been performed and was not included in
the original budget.
Public Meeting 2: TBD pending SCDOT review of preliminary R/W plans
Original Revised E xpended to Date
Design 208,877.14 $ 208,877.14 $ 67,499.90 $
R/W Acquisition 42,000.00$ 216,072.00 $
Utilities 112,500.00$ 112,500.00 $
Construction 750,000.00$ 831,600.00 $
CEI 75,000.00 $ 124,740.00 $
Mitigation - $ - $
Total 1,188,377.14 $ 1,493,789.14 $ 67,499.90 $
69
Page | 19
Middle Road
An 8’ concrete sidewalk along the east side of Middle Ro ad. The original project scope extended from SC 802 (Sams
Point Rd) to Fly Catcher Lane but will be reduced to extend from Coosaw Elementary to Walnut Hill St, pending Council
recommendation. Path to be constructed per SCDOT standard s within current Right-of-Way with additional Right-of-
Way needed. Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: R/W Acquisition (47 tracts total) – 12 permission only tracts secured
Notes:
1. Design: R/W plans have been approved by SCDOT. Cons truction plans would be minimal to complete based on
current design. Infiltration testing was additional and included in expended to date. To revise would require additional
work to change the limits.
2. R/W Acquisition: SCDOT has approved R/W authorization and it is recommended to acquire all R/W as only 3 tracts
(2 Property Owoners) would be removed for the revised limits.
3. Utilities: This is in progress and will be on-going for the next few months.
Public Meeting 2: April 30, 2024, with virtual meeting from April 17 through May 15, 2024
(joint meeting with Meridian Road, summary below is for Middle Road)
Questions Yes No
Do you live near the proposed project? 11 16
Would you utilize the proposed project? 14(+1)* 12
Are you in favor of the proposed 8’ sidewalk? 20 7
Original Revised Revised: New Limits Expended to Date
Design 451,173.25 $ 451,173.25 $ 451,173.25 $ 262,896.35 $
R/W Acquisition 450,017.12$ 538,806.20 $ 538,806.20 $
Utilities 225,000.00 $ 275,774.40 $ 210,194.40 $
Construction 1,500,000.00$ 1,838,496.00 $ 1,401,296.00 $
CEI 150,000.00 $ 275,774.40 $ 210,194.40 $
Mitigation - $ - $
Total 2,776,190.37 $ 3,380,024.25 $ 2,811,664.25 $ 262,896.35 $
70
Page | 20
Joe Frazier Road
A 6’ concrete sidewalk along Joe Frazier Road from Cherokee Farms Road to Burton Wells Road. Speci fic side of road
will need to be determined once preliminary engineering is performed but should correspond with County’s Joe Frazier
Corridor Study. Path to be constructed per SCDOT standards within current Right-of-Way with additional Right-of-Way
needs not know at this time. Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: not programmed for design
Notes:
1. Design: Length is approx. 7,300 LF
2. R/W Acquisition: North has 23 tracts with 1 tract as the park; South, 34 tracts
3. Mitigation: Based on National Wetlands Inventory, possible impacts on north and maybe one area on south.
Pine Grove Road
Two 6’ concrete sidewalk sections along Pine Grove Road. The first will extend from Burton Wells Road to County Shed
Road and the second from Joe Frazier Road to Shanklin Road. Specific side of road will need to be determined once
preliminary engineering is performed but the western end is expected to be on the north side of the road and the
eastern end is expected to be on the south side. Path to be constructed per SCDOT standards within current Right-of-
Way with additional Right-of-Way needs not know at this time. Associated drainage improvements will be constructed
as well.
Funding: Sales Tax
Current Status: not programmed for design
Budget: North Budget: South
Design 273,750.00 $ 273,750.00 $
R/W Acquisition 571,350.00$ 685,750.00 $
Utilities 273,750.00$ 273,750.00 $
C onstruction 1,825,000.00$ 1,825,000.00 $
C EI 273,750.00 $ 273,750.00 $
Mitigation 40,000.00$ 100,000.00 $
Total 3,257,600.00 $ 3,432,000.00 $
71
Page | 21
Notes:
1. Design: (A) is approx. 3,250 LF; (B), approx. 3,300 LF
2. R/W Acquisition: (A) North has 31 tracts; South, 19 Tracts; (B) 19 tracts on north and south
3. Mitigation: (A) No wetlands shown on National Wetland Inventory. (B) Wetland on 19 north side, and stream on
both
Burton Wells Road
A n 8 ’ c o n c r e t e s i d e w a l k a l o n g B u r t o n W e l l s R o a d f r o m J o e F r a z i e r R o a d t o P i n e G r o v e R o a d . I t i s e x p e c t e d t h a t t h e
sidewalk will be on the west side of the road but it will need to be confirmed once preliminary engineering is performed.
Path to be constructed per SCDOT standards within current Right-of-Way with additional Right-of-Way needs not know
at this time. Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: not programmed for design
Notes:
1. Design: Length is approx. 4,750 LF
2. R/W Acquisition: West has approx. 13 tracts with 1 tract as the park; East, 11 tracts with 1 tract as the park
3. Mitigation: Based on National Wetlands Inventory, possible impacts on the west for entire length and maybe one
area on east.
Budget: North Budget: South Budget: North Budget: South
Design 146,250.00 $ 146,250.00 $ 148,500.00 $ 148,500.00 $
R/W Acquisition 470,275.00$ 345,475.00 $ 347,750.00 $ 347,750.00 $
Utilities 109,687.50$ 109,687.50 $ 111,375.00 $ 111,375.00 $
Construction 731,250.00$ 731,250.00 $ 742,500.00 $ 742,500.00 $
CEI 146,250.00 $ 146,250.00 $ 148,500.00 $ 148,500.00 $
Mitigation - $ - $ 60,000.00$ 10,000.00 $
Tota l 1,603,712.50$ 1,478,912.50 $ 1,558,625.00 $ 1,508,625.00 $
Burton Wells Rd to C ounty Shed Rd (A) Joe Frazier Rd to Shanklin Rd (B)
Budget: West Budget: East
Design 178,125.00 $ 178,125.00 $
R/W Acquisition 467,350.00$ 446,550.00 $
Utilities 178,125.00$ 178,125.00 $
C onstruction 1,187,500.00$ 1,187,500.00 $
C EI 178,125.00 $ 178,125.00 $
Mitigation 150,000.00$ 40,000.00 $
Total 2,339,225.00 $ 2,208,425.00 $
72
Page | 22
Broad River Drive
A 5’ concrete sidewalk along the south side of Broad River Drive. The original project scope extended from
Shell Point Road to US 21 (Parris Island Gateway). The project may be reduced to either end, splitting at the
Lowcountry Montessori School, dependent on responses from a community meeting on May 15, 2025. Path
to be constructed per SCDOT standards within current Right-of-Way with additional Right-of-Way needed.
Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: 55% design for original project limits
Notes:
1. Design: Original design, 1.697 miles, is Shell Point Rd to Parris Island Gateway, but budget was based on 1 mile.
Revised: West, approx. 3,700 LF, is Shell Point Rd to school; Revised: East, approx. 5,300 LF, is school to Parris
Island Gateway.
2. R/W Acquisition: Revised: West has 27 tracts; Revised: East, 45 tracts
Public Meetings
• Community Meeting: May 15, 2025
• Public Meeting 2: TBD, pending SCDOT review of preliminary R/W plans and decision on project limits
Original Revised Revised: West Revised: East Expended to Date
Design 189,328.00 $ 300,000.00 $ 83,250.00 $ 119,250.00$ 238,394.43 $
R/W Acquisition 180,000.00$ 1,109,446.24$ 425,100.00 $ 674,700.00 $
Utilities 300,000.00 $ 300,000.00 $ 138,750.00 $ 198,750.00 $
Construction 2,000,000.00$ 2,240,040.00 $ 925,000.00 $ 1,325,000.00$
CEI 200,000.00 $ 336,006.00 $ 138,750.00 $ 198,750.00 $
Mitigation - $ 34,435.26$ 17,217.63 $ 17,217.63 $
Total 2,869,328.00 $ 4,319,927.50 $ 1,728,067.63 $ 2,533,667.63 $ 238,394.43 $
73
Page | 23
Meridian Road
A 10’ concrete multi-use path along Meridian Road from US 21 (Lady’s Island Drive) to US 21 BUS (Sea Island Parkway)
with a 5’ sidewalk along Youmans Drive for connection to Beaufort High School. The project scope may be reduced to
construct a 10’ path from US 21 BUS to Rue Du Bois with a 5’ sidewalk along Youmans Drive. Scope will be determined
per Council. Path to be constructed per SCDOT standards wi thin current Right-of-Way with additional Right-of-Way
needs not know at this time. Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: 45% design for original project limits
Notes:
1. Design: Both sides were surveyed and preliminary plans prepared to determine preferred design. Path is on west
from Lady's Island Dr to Rue Du Bois, and east from Rue Du Bois to Sea Island Parkway. It includes sidewalk on
Youmans Dr. Infiltration testing will be required and was not originally scoped. Remainder of design budget shown
for US 21 Bus to Rue Du Bois.
2. R/W Acquisition: US 21 Bus to Rue Du Bois has 21 tracts. Entire length has 45 tracts.
Public Meeting 2: April 30, 2024, with virtual meeting from April 17 through May 15, 2024
(joint meeting with Middle Road, summary below is for Meridian Road)
Questions Yes No
Do you live near the proposed project? 60 13
Would you utilize the proposed project? 57 15
Are you in favor of the proposed 10’ pathway? 49 20
Original Budget Revised Budget US 21 Bus to Rue Du Bois Expended
Design 310,000.67 $ 310,000.67 $ 89,189.69 $ 220,810.98$
R/W Acquisition 659,880.00$ 1,460,040.00$ 604,500.00 $
Utilities 300,000.00 $ 334,950.00 $ 187,200.00 $
Construction 2,000,000.00$ 2,233,000.00 $ 1,248,000.00 $
CEI 200,000.00 $ 334,950.00 $ 187,200.00 $
Mitigation - $ 98,140.50$ - $
Total 3,469,880.67 $ 4,771,081.17 $ 2,316,089.69 $ 220,810.98 $
74
Page | 24
Old Salem Road
An 10’ concrete shared-use path along Old Salem Road on the north side from Burton Hill Road to Salem Road. Path to
be constructed per SCDOT standards within current Right-of-Way and additional Right-of-Way as required. Associated
drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: Preliminary Design
Burton Hill Road
An 8’ concrete sidewalk and/or 10’ concrete shared-use path along Burton Hill Road on the east side from Old Salem
Road to Broad River Boulevard with a connection on Broad River Boulevard to the Spanish Moss Trail. Sidewalk and Path
to be constructed per SCDOT standards within current Ri ght-of-Way and additional Right-of-Way as required.
Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: Preliminary Design
Notes:
1. Phase 1, approx. 1900 lf, is from Pointe Grande development/Lowe's 2nd entrance to Industrial Village Road and would include
connecting the 5' sidewalk on the west side from the car dealership to Industrial Village Road for approx. 300 lf. Phase 2, approx.
2500 lf, is from Industrial Village Road to Broad River Boulevard/Spanish Moss Trail.
2. The proposed sidewalk will be coordinated with/connected to the Pointe Grand development sidewalk near Old Salem Road
intersection.
3. Entire length has been surveyed, and preliminary design has been started for the east side.
4. Phase 1 has 10 tracts and Phase 2, 13 tracts.
Original Budget Revised Budget Expended
Design 82,587.90 $ 100,000.00$ 52,477.86 $
R/W Acquisition 25,180.00$ 182,120.00$
Utilities 150,000.00 $ 110,880.00 $
Construction 1,000,000.00$ 739,200.00 $
CEI 100,000.00 $ 110,880.00 $
Mitigation - $ - $
Total 1,357,767.90 $ 1,243,080.00 $ 52,477.86 $
Original Budget Revised Budget Phase 1 Phase 2 Expended
Design 201,001.68 $ 201,001.68 $ 109,785.62 $ 120,000.00 $ 91,216.06 $
R/W Acquisition 1,309,000.00$ 1,136,000.00 $ 559,000.00 $ 539,500.00 $
Utilities 112,500.00 $ 193,875.00 $ 99,000.00 $ 112,500.00$
Construction 750,000.00$ 1,292,500.00$ 660,000.00 $ 750,000.00 $
CEI 75,000.00 $ 193,875.00$ 99,000.00 $ 112,500.00$
Mitigation - $ - $
Total 2,447,501.68 $ 3,017,251.68 $ 1,526,785.62 $ 1,634,500.00 $ 91,216.06 $
75
Page | 25
Chowan Creek Bluff
A 6’ concrete sidewalk along Chowan Creek Blu ff on the east side fr om US 21 (Sea Island P arkway) to Lady’ s Island
Elementary School. Sidewalk to be constructed per SCDOT standards within current Right-of-Way and additional Right-
of-Way as required. Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: not programmed for design
Notes:
1. The project is approx. 2500 lf.
2. There are 12 tracts.
Bruce K Smalls Drive
A 6’ concrete sidewalk along Bruce K Smalls Drive on the we st side from Big Road to Carolina Avenue, which is an
extension of the existing sidewalk. Sidewalk to be constructed per SCDOT standards within current Right-of-Way and
additional Right-of-Way as required. Associated drainage im provements will be constructed as well. Signal upgrades
and crosswalk should be installed at Trask Parkway with a connection to the Spanish Moss Trail on Clarendon Road.
Funding: Sales Tax
Current Status: not programmed for design
Notes:
1. The project is approx. 1600 lf for the extenstion to Carolina Avenue and 600 lf to Spanish Moss Trail on Clarendon
Road with signal improvements and crosswalk.
2. There are 11 tracts.
Budget
Design 150,000.00 $
R/W Acquisition 221,000.00$
Utilities 112,500.00 $
Construction 750,000.00$
CEI 112,500.00 $
Mitigation - $
Total 1,346,000.00 $
Budget
Design 176,000.00 $
R/W Acquisition 184,600.00$
Utilities 132,000.00 $
Construction 880,000.00$
CEI 132,000.00 $
Mitigation - $
Total 1,504,600.00 $
76
Page | 26
Ulmer Road
An 10’ concrete shared-use path along Ulmer Road on the west side from Shad Avenue to Burnt Church Road. Path to
be constructed per SCDOT standards within current Right-of-Way and additional Right-of-Way as required. Associated
drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: preliminary design
Notes:
1. The project is approx. 3800 lf
2. There are 10 tracts.
Shad Avenue
A 5’ concrete sidewalk/10’ concrete shared-use path along Sh ad Avenue on the west side from Alljoy Road to Ulmer
Road. Sidewalk/Path to be constructed per SCDOT standards within current Right-of-Way and additional Right-of-Way
as required. Associated drainage improvements will be constructed as well.
Funding: Sales Tax
Current Status: preliminary design
Notes:
1. The project is approx. 2700 lf
2. There are 19 tracts.
Original Budget Revised Budget Expended
Design 139,600.29 $ 139,600.29 $ 49,147.39 $
R/W Acquisition 157,060.00$ 851,312.00 $
Utilities 150,000.00 $ 171,072.00 $
Construction 1,000,000.00$ 1,140,480.00 $
CEI 100,000.00 $ 171,072.00 $
Mitigation 50,000.00$ 150,000.00$
Total 1,596,660.29 $ 2,623,536.29 $ 49,147.39 $
Shad Avenue
Original Budget Revised Budget Expended
Design 106,829.42 $ 177,847.31 $ 33,899.27 $
R/W Acquisition 251,920.00$ 555,200.00 $
Utilities 150,000.00 $ 138,600.00 $
Construction 1,000,000.00$ 924,000.00 $
CEI 100,000.00 $ 138,600.00 $
Mitigation - $ - $
Total 1,608,749.42 $ 1,934,247.31 $ 33,899.27 $
77
Page | 27
US 17 Pathway Extension
A 10’ concrete shared-use path along US 17 on the south side from Big Estate Road/Jacob White Road to Jenkins Road.
Path to be constructed per SCDOT standards within curren t Right-of-Way and additional Right-of-Way as required.
Associated drainage improvements will be constructed as well.
Notes:
1.The project is approx. 3300 lf.
2. The expended to date involved a conceptual exhibit for the limits.
3. There are 13 tracts.
Seabrook Road
An 8’ concrete sidewalk along Seabrook Road from US 21 to Whale Branch Fishing Pier. Sidewalk to be constructed per
SCDOT standards within current Right-of-Way and additional Right-of-Way as required. Associated drainage
improvements will be constructed as well.
Notes:
1. The project is approx. 6600 lf.
2. There are 25 tracts on the north side and 22 tracts on the south side.
Budget Expended to Date
Design 173,250.00 $ 6,749.68 $
R/W Acquisition 254,800.00$ - $
Utilities 173,250.00 $ - $
Construction 1,155,000.00$ - $
CEI 173,250.00 $ - $
Mitigation - $ - $
Total 1,929,550.00 $ 6,749.68 $
Budget: North Budget: South
Design 247,500.00 $ 247,500.00 $
R/W Acquisition 496,600.00$ 457,600.00 $
Utilities 297,000.00 $ 297,000.00 $
Construction 1,980,000.00$ 1,980,000.00 $
CEI 297,000.00 $ 297,000.00 $
Mitigation 25,000.00$ 50,000.00 $
Total 3,343,100.00 $ 3,329,100.00 $
78
Page | 28
Paige Point Road
An 8’ concrete sidewalk along Paige Point Road from Cuthbert Farm Road to Johnson Road. Sidewalk to be constructed
per SCDOT standards within current Right-of-Way and addi tional Right-of-Way as required. Associated drainage
improvements will be constructed as well.
Notes:
1. The project is approx. 6200 lf .
2. There are 25 tracts on the west side and 12 tracts on the east side, assuming a portion of the path is within the former railroad
R/W.
Big Road
A 6’ concrete sidewalk along Big Road from Trask Parkway to Bruce K Smalls Drive. Sidewalk to be constructed per
SCDOT standards within current Right-of-Way and additional Right-of-Way as required. Associated drainage
improvements will be constructed as well. The sidewalk will connect to the existing sidewalk on Bruce K Smalls Drive.
Potentially coordinate with Grays Hill Baptist Church for sidewalk/path along Trask Parkway to Bruce K. Smalls
intersection.
Notes:
1. The project is approx. 3600 lf along Big Road. A connection from Big Road along Trask Parkway to the signal at Bruce K Smalls
Drive intersection is 900 lf.
2. There are 15 tracts on the north side and 19 tracts on the south side. 1 additional tract for the connection on Trask Parkway.
Budget: West Budget: East
Design 232,500.00 $ 232,500.00 $
R/W Acquisition 473,200.00$ 278,200.00 $
Utilities 279,000.00 $ 279,000.00 $
Construction 1,860,000.00$ 1,860,000.00 $
CEI 279,000.00 $ 279,000.00 $
Mitigation - $ 50,000.00$
Total 3,123,700.00 $ 2,978,700.00 $
Budget: North Budget: South Conn. on Trask Pkwy
Design 189,000.00 $ 189,000.00 $ 54,000.00 $
R/W Acquisition 288,600.00$ 340,600.00 $ 36,400.00 $
Utilities 189,000.00 $ 189,000.00 $ 54,000.00 $
Construction 1,260,000.00$ 1,260,000.00 $ 360,000.00 $
CEI 189,000.00 $ 189,000.00 $ 54,000.00 $
Mitigation - $ - $ - $
Total 2,115,600.00 $ 2,167,600.00 $ 558,400.00 $
Total + Connection 2,674,000.00$ 2,726,000.00 $
79
Page | 29
Lake Point Drive/Old Miller Road
A 10’ concrete shared-use path connecting Lake Point Drive to Old Miller Drive as both roads end with no connection.
Path to be constructed per SCDOT standards within curren t Right-of-Way and additional Right-of-Way as required.
Associated drainage improvements will be constructed as well.
Notes:
1. The project is approx. 2200 lf connecting Lake Point Drive to Old Miller Road
2. There would be 1 or 2 tracts, dependent on connection.
Budget
Design 132,000.00 $
R/W Acquisition 169,000.00$
Utilities 132,000.00 $
Construction 880,000.00$
CEI 132,000.00 $
Mitigation - $
Total 1,445,000.00 $
80
Source: Beaufort County website. First collected Nov 8, 2026.