Town of Hilton Head Island
Town Council Workshop Meeting
Wednesday, October 30, 2024, 9:00 AM
1 Town Center Court, Hilton Head Island, SC
Benjamin M. Racusin Council Chambers
The meeting can be viewed on the Town’s YouTube Channel, the Beaufort County
Channel, and Spectrum Channel 1304.
1. Call to Order
2. Adoption of the Agenda
3. Workshop Discussion
a. Beach Renourishment Update - Shawn Colin, Assistant Town Manager
b. Resilience Plan Status Update - Shawn Colin, Assistant Town Manager
c. Stormwater Utility Update - Jeff Netzinger, Engineering and Projects Director
4. Public Comment
5. Adjournment
Town Council Workshops consist of discussion items only - no action will be taken.
FOIA Compliance: Public notification of this workshop has been published, posted, and
distributed in compliance with the South Carolina Freedom of Information Act and the
requirements of the Town of Hilton Head Island.
In accordance with the requirements of Title II of the Americans with Disabilities Act of
1990 ("ADA"), the Town of Hilton Head Island will not discriminate against qualified
individuals with disabilities on the basis of disability in its services, programs, or
activities. Auditory accommodations are available. Any person requiring further
accommodation should contact the Town of Hilton Head Island ADA Coordinator as
soon as possible but no later than 48 hours before the scheduled event.
Municipal Association of South Carolina (MASC) Civility Pledge:
Page 1 of 59
“I pledge to build a stronger and more prosperous community by advocating for civil
engagement, respecting others and their viewpoints, and finding solutions for the
betterment of my city or town.”
Page 2 of 59
2025 Beach Renourishment Project
Town Council Workshop
October 30, 2024
Town of Hilton Head Island
Shawn Colin
Assistant Town Manager
Page 3 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PRESENTATION OVERVIEW
Presentation Overview
o Project Overview
o Program Background
o Project Status and Schedule
o 2025 Project Description
o South Beach
o Central Island
o The Heel / Port Royal
o Fish Haul Creek
o Pine Island
o Project Funding
o Communication Plan
1
Page 4 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT OVERVIEW
Project Overview
o Hilton Head Island’s Beach has been renourished
several times, beginning in the 1990’s. Major
renourishment projects were completed in 1990,
1997, 2006, and 2016
o The proposed project will include:
o Placement of approximately 2.2 million cubic
yards of sand, and
o Installation of six rip -rap breakwaters on the
Port Royal Sound shoreline at Pine Island
o The sand will be sourced from up to four offshore
borrow areas located roughly 8 miles offshore
o The project is being implemented per the Town’s
Beach Management Plan with scheduled
renourishment every 8 to 10 years
o The estimated project cost is $42 million
o Disruptions at individual properties generally last one week or less as
the moving operation progresses
o Once the operation is up and running, the project will advance along
the beach at a rate of 200 to 300 feet/day
o The project schedule was developed to avoid significant impacts to
nesting turtles and migratory shore birds, including piping plovers and
red knots
o Construction windows are set by US Fish and Wildlife Service
2
Page 5 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROGRAM BACKGROUND
3
Page 6 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROGRAM BACKGROUND
North Forest Beach (1990) Prior to First Renourishment 4
Page 7 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROGRAM BACKGROUND
The Folly/Singleton Beach (1990) Prior to First Renourishment
5
Page 8 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROGRAM BACKGROUND
Port Royal (1990) Prior to First Renourishment
6
Page 9 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT STATUS
Project Status & Schedule
o US Fish & Wildlife Service (USFWS) Biological Opinion (BO)
o Issued on August 8, 2024
o Included in State Permit Terms and Conditions
o Permit is currently being reviewed by the State and USACE
o Project Schedule
o Preconstruction
o Anticipated permit issue date: Dec 31, 2024
o Bid Phase: Jan – Mar 2025
o Contract Awards: April 1, 2025
o Construction (3 Phases)
o Phase 1 (Renourishment): June 2025 to Oct 2025
o Sand placement on the Island’s north end
o Phase 2 (Renourishment): Sept 2025 to May 2026
o Sand placement on south beach and central island
o Phase 3 (Breakwater Structures): To Be Determined
o Rock breakwater structures at Pine Island
7
Page 10 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT DESCRIPTION
2025 Project Scope
Project Scope
Permit 1
o South Beach: place 750,000 cubic
yards of sand
o Central Atlantic: place 700,000 cubic
yards of sand
o The Heel/Port Royal: place 500,000
cubic yards of sand
o Fish Haul: place 50,000 cubic yards
of sand
Permit 2
o Pine Island: place 200,000 cubic
yards of sand and install six rock
breakwaters to mitigate against
sand accretion
8
Page 11 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT DESCRIPTION
South Beach
o Beach Restoration
9
Page 12 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT DESCRIPTION
Central Island
o Beach Restoration
10
Page 13 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT DESCRIPTION
Central Island
o Beach Restoration
11
Page 14 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT DESCRIPTION
“The Heel”
o Beach Restoration
Fish Haul
o Beach Restoration
12
Page 15 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT DESCRIPTION
Pine Island
o Beach Restoration
o Rip-rap Breakwater Installation
(6 structures)
13
Page 16 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT FUNDING
Project Funding
o Estimated Project Cost $42.0 million
o FY 2025 (CIP) Budget $16.5 million (Source of Funding: Beach
Preservation Fee)
o FY 2026 Funding $25.5 million (Source of Funding: To Be
Determined)
FUNDING OPTIONS
o Beach Preservation Fund Balance, reducing fund balance to $13 million +/ -
o Issue Debt for ± $42.5 million; paid for with future Beach Preservation Fees
o Beach Preservation Fund Balance + Debt Issuance.
14
Page 17 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PREVIOUS PROJECT FUNDING
Remaining 2017 Beach Preservation Fee Bonds – Original $30.1 Million
15
Pays 2017 Bond Issue in Full, with Zero Balance
Page 18 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT FUNDING
Projected FY2025 & FY2026 Cash Flows
16
Page 19 of 59
Town of Hilton Head Island
2025 BEACH RENOURISHMENT – PROJECT STATUS
Communications Plan
o Plan Goals
o Create widespread awareness and engagement related to the project
o Share timely information about the projects prior to and throughout each
phase
o Target audiences include
o Island residents and visitors
o The Chamber of Commerce and business owners
o HOAs and property management firms
o Partner groups (Shore Beach Services, Island Rec, and others)
o School Groups
o Environmental Groups
o Media
o Outreach will be managed by the Communications Team
o Social Media, Web postings, News releases
o Interactive, real- time mapping during implementation
17
Page 20 of 59
2025 Beach Renourishment Project
Town Council Workshop
October 30, 2024
Town of Hilton Head Island
Questions?
Page 21 of 59
Resilience Plan Update
Town Council Workshop
October 30, 2024
Town of Hilton Head Island
Shawn Colin
Assistant Town Manager
Page 22 of 59
Overview of Presentation
• Background
• Town Council Approved Scope of Work
• Resilience Planning Project Overview
• Project Approach and Timeline
• Public Engagement
• Next Steps
• Resilience Plan Contents
1
Page 23 of 59
Background
• Priority initiative in the Town of Hilton Head Island 2023-25 Strategic Action Plan to
identify Strengths, Weaknesses, Opportunities & Threats (SWOT) of Hilton Head
Island Resiliency and Establish an Island Resiliency Plan
• Town Council approved a Resolution June 6, 2023, supporting the proposed
approach and scope of services outline to complete the SWOT assessment
• Staff procured Dewberry, an expert consultant firm in the field of resiliency
planning, to conduct this assessment
2
Page 24 of 59
Resilience – The ability of
communities, economies, and
ecosystems within South
Carolina to anticipate, absorb,
recover, and thrive when
presented with environmental
change and natural hazards.”
South Carolina Office of Resilience
Strategic Statewide Resilience Risk and Reduction Plan
Built Systems
Social Systems
Natural Systems
Background
3
Page 25 of 59
Historical Rates of Sea Level:
Historic Data
Ft. Pulaski, GA (Savannah)
water level station
Historical Flood events:
Last 40 Years:
0.18 ft/decade
Last 30 Years:
0.21 ft/decade
Last 20 Years:
0.36 ft/decade
Last 10 Years:
0.38 ft/decade
USACE Sea Level Analysis Tool
Background
4
Page 26 of 59
Scope of Work Approved By Town Council
Collect and compile information and conduct an analysis of the strengths,
weaknesses, opportunities, and threats (SWOT) that the Town possesses and faces
with respect to changing conditions
• Compilation and assessment of existing
relative data and programs
• Sea Level Rise forecast analysis and
selection of design forecast
• Public outreach and solicitation of
stakeholder input
• Public policy and regulation assessment and
identify those for change
• Recommendations related to floodplain
management and future development
• Storm Drainage System assessment (tidal
backflow prevention at tidal culverts and
outfalls, pump stations, hydraulic capacity,
design standards)
• Beach Renourishment program (including
sustainability analysis)
• Flood Inundation Mapping
• SWOT (Strengths, Weaknesses,
Opportunities and Threats) analysis
5
Page 27 of 59
Assessing Risks
Resilience Plan
Next Steps
Q1 2025 Q4 2025
Conduct a SWOT analysis of the
island’s assets
• Step 1: Understand the threats
and hazards posed to assets
• Step 2:
• Identify vulnerable assets and
public policy and evaluate
potential impacts
• Climate Change Projections
• Sea-Level Rise and Flooding
Risk
• Storm Surge and Hurricanes
• Environmental Degradation
and Erosion
• Infrastructure Vulnerabilities
(Transportation, Utilities)
• Social and Economic
Vulnerabilities (Public Health,
Housing, Businesses)
• Public policy assessment
• Step 3: SWOT findings , including
GIS mapping and geodatabase to
drive decision-making on future
actions for planning, policy, and
engineering programs presented
to Town Council
• Step 4: Additional Community
Engagement to present SWOT
findings and receive input
• Step 5: Town Council Prioritizes
actions for Resilience Planning
Resilience Planning Project Overview
• Step 6: Identify and evaluate
mitigation, adaptation, and
recovery actions for built, social
and natural systems
• Step 7: Draft Plan for Town
Council consideration for built,
social and natural systems
Mar 2024 – Jan 31, 2025
Project Approach and Timeline
6
Page 28 of 59
First Public Open House
Two meetings were held on June 11th and
included three stations to gather feedback:
Station 1 – Shared information
about the project and related
Town efforts
Station 2 – Interacted with the
public to gain information on
observed flood impacts
Station 3 – Collected
preferences of potential
strategy types
Results:
• Recorded ~50 locations of
previous flood impacts or
areas of concern across
the island
• Nature Based and
Infrastructure Solutions
supported the most from
the public
Resilience Planning Project Overview
Public Engagement
7
Page 29 of 59
Community Survey:
• 459 survey responses received across the
Island
Stakeholder Interviews:
• 12 virtual interviews completed on
flooding challenges and strategies for
improvement
Project Story Map:
• Upcoming, will provide information to
public on project and findings
Distribution of survey
responses to “What
area of the Island are
you most concerned
about flooding?”
Resilience Planning Project Overview
Public Engagement
8
Page 30 of 59
Assessing Risks
Resilience Plan
Next Steps
Q1 2025 Q4 2025
Conduct a SWOT analysis of the
island’s assets
• Step 1: Understand the threats
and hazards posed to assets
• Step 2: Identify vulnerable assets
and public policy and evaluate
potential impacts
• Climate Change Projections
• Sea-Level Rise and Flooding
Risk
• Storm Surge and Hurricanes
• Environmental Degradation
and Erosion
• Infrastructure Vulnerabilities
(Transportation, Utilities)
• Social and Economic
Vulnerabilities (Public Health,
Housing, Businesses)
• Public policy assessment
• Step 3: SWOT findings , including
GIS mapping and geodatabase to
drive decision-making on future
actions for planning, policy, and
engineering programs presented
to Town Council
• Step 4: Additional Community
Engagement to present SWOT
findings and receive input
• Step 5: Town Council Prioritizes
actions for Resilience Planning
Resilience Planning Project Overview
• Step 6: Step 6: Identify and
evaluate mitigation, adaptation,
and recovery actions for built,
social and natural systems
• Step 7: Draft Plan for Town
Council Consideration
Mar 2024 – Jan 31, 2025
Next Steps
9
Page 31 of 59
1. Executive Summary
a. Overview of the Resilience Plan
b. Key Goals and Objectives
c. Summary of Challenges and Opportunities
d. Action Plan Highlights
2. Introduction
a. Purpose of the Plan
b. Background on Hilton Head Island’s Resilience Efforts
c. Stakeholder Involvement
d. Guiding Principles and Vision
3. Risk and Vulnerability Assessment
a. Climate Change Projections
b. Sea-Level Rise and Flooding Risk
c. Storm Surge and Hurricanes
d. Environmental Degradation and Erosion
e. Infrastructure Vulnerabilities (Transportation, Utilities)
f. Social and Economic Vulnerabilities (Public Health, Housing, Businesses)
4. Resilience Goals and Priorities
a. Environmental Protection and Sustainability
b. Infrastructure Strengthening and Adaptation
c. Public Safety and Emergency Preparedness
d. Community Well-being and Social Resilience
e. Economic Resilience
Resilience Plan Contents
Focus on near-term
issues and actions,
awareness and plan
for long-term
challenges
10
Page 32 of 59
5. Climate and Environmental Strategies
a. Flood Mitigation Measures
b. Shoreline Protection and Beach Renourishment
c. Wetland Restoration and Conservation
d. Water Resource Management
e. Tree Canopy and Greenspace Protection
f. Integrated Pest Management (IPM) Policy
6. Infrastructure and Community Planning
a. Transportation Resilience (Roadways, Public Transport)
b. Utility Resilience (Stormwater, Water/Sewer, Energy, Solid Waste and Recycling)
c. Growth Management and Zoning
d. Public Facilities and Critical Infrastructure Adaptation
e. Future-Proofing New Development
7. Public Safety and Emergency Preparedness
a. Hurricane Preparedness and Response
b. Evacuation Routes and Sheltering Plans
c. Community Warning Systems and Communications Strategy
d. Lifeguard and Public Safety Programs on Beaches
e. Medical and Health Services for Disaster Scenarios
8. Community and Economic Resilience
a. Housing Resilience
b. Small Business and Tourism Support Strategies
c. Workforce Retention Programs
d. Social Services Support
Resilience Plan Contents
Focus on near-term
issues and actions,
awareness and plan
for long-term
challenges
11
Page 33 of 59
Resilience Plan Contents
9. Governance and Partnerships
a. Coordination with County, State, and Federal Agencies
b. Public-Private Partnerships
c. Community Engagement and Public Education Programs
d. Intergovernmental Collaboration and Policy Alignment
10. Infrastructure and Community Planning
a. Transportation Resilience (Roadways, Public Transport)
b. Utility Resilience (Stormwater, Water/Sewer, Energy, Solid Waste and Recycling)
c. Growth Management and Zoning
d. Public Facilities and Critical Infrastructure Adaptation
e. Future-Proofing New Development
11. Public Safety and Emergency Preparedness
a. Hurricane Preparedness and Response
b. Evacuation Routes and Sheltering Plans
c. Community Warning Systems and Communications Strategy
d. Lifeguard and Public Safety Programs on Beaches
e. Medical and Health Services for Disaster Scenarios
12. Community and Economic Resilience
a. Housing Resilience
b. Small Business and Tourism Support Strategies
c. Workforce Retention Programs
d. Social Services Support
Focus on near-term
issues and actions,
awareness and plan
for long-term
challenges
12
Page 34 of 59
Resilience Plan Update
Town Council Workshop
October 30, 2024
Town of Hilton Head Island
Questions?
Page 35 of 59
Stormwater Utility Program Overview
Town Council Workshop
October 30, 2024
Town of Hilton Head Island
Jeff Netzinger
Director of Engineering and Projects
Page 36 of 59
Town of Hilton Head Island
STORMWATER UTILITY – PRESENTATION OVERVIEW
o Stormwater Utility Overview
o Staffing
o Revenue
o Expenses
o Fund Balance
o Targeted Discussion
o Capital Improvement Program SWU
o Routine Maintenance Program
o Channels
o Street Sweeping
o Ponds
o Pump Stations
o Corrective Maintenance Program
o Extent of Service
o Drainage Agreements
o Ranking & Project Prioritization
o Service Request Evaluation
o Annual SWU and CIP Budget Development
o Stormwater Utility Program Challenges/Opportunity
1
Page 37 of 59
Town of Hilton Head Island
STORMWATER UTILITY OVERVIEW – STAFFING
Stormwater
Program Manager
Jeff Netzinger, PE
Watershed
Manager
Jacob Terry, CEPSCI
Stormwater
Inspector
Mark Lobe, CEPSCI
Senior Stormwater
Project Manager
Kelli Uyesugi, PE
Stormwater
Asset Manager
Mike Pomposelli
Stormwater Maintenance
Program Administrator
Cary Schumacher, CEPSCI
Stormwater
Inspector
Adam Worrell, CEPSCI
Operations
Regulation
Support
The Utility Staff Consists of
Seven Full - time Professionals
Added 1 Full Time Employee in FY2024
2
Page 38 of 59
Town of Hilton Head Island
STORMWATER UTILITY OVERVIEW – ALLOCATION OF STAFF RESOURCES
Staff time allocation distributed over
12 significant activity categories:
o Utility Management
o LMO Plan Review
o NPDES Permit Compliance
o Regulatory Inspections
o Service Request Data Management
o Infrastructure Asset Management
o Inventory & Modeling Program
o Water Quality Programs
o Capital Improvement Program
o Pump Station Maintenance Program
o Routine Maintenance Programs
o Corrective Maintenance Program
Annual SWU Staff Effort by Activity Category (Manhours) 3
Page 39 of 59
Town of Hilton Head Island
STORMWATER UTILITY OVERVIEW – REVENUE
Stormwater Utility Revenue
o The Utility was established in 2001 per an IGA with Beaufort County.
o A stormwater fee is included on annual property tax bills.
o Fees are calculated based on three components:
o Administrative Fee (flat rate per account)
o Impervious Area (based on total measured in square feet)
o Gross Area (measured in acres)
o Fees are based on a 4,906 ft 2 Single-family Unit (SFU).
o Town Council elected to increased the base SFU fee rate from
$108.70 to $150.00 for a Single -family unit in 2017.
o Beaufort County collects the fees and transfers all funds to the
Town, less an administrative fee.
o The FY 2025 administrative fee is $3.90 per account based on
35,865 accounts, totaling $139,873.
o Total Stormwater Fee revenue was $5,275,035 in FY 2024
Town of Hilton
Head Island
Beaufort
County
Town of
Bluffton
City of
Beaufort
Town of
Port Royal
Administrative Fee
(flat rate/account) $24.00 $19.00 $5.00 $5.00 $5.07
Impervious Area Unit
(unit: square feet)
$105.00 $71.00 $85.00 $95.00 $43.50
Gross Area Unit
(unit: acres)
$21.00 $10.00 $25.00 $35.00 $11.43
Total $150.00 $100.00 $115.00 $135.00 $60.00
FY 2024 Stormwater Fee Structure Comparison (based on One Single Family Unit)
4
Page 40 of 59
Town of Hilton Head Island
STORMWATER UTILITY OVERVIEW – EXPENSES (FY2025 BUDGET ALLOCATION)
o Personnel & Benefits $ 842,381
o Operations/Transfer to General Fund $ 273,574
o Debt Service (P&I) $1,298,570
o Monitoring Programs
o Water Quality Monitoring $ 140,000
o Tide Monitoring $ 4,000
o Weather Monitoring $ 50,000
o Modeling and Analysis Programs
o Inventory & Modeling $ 375,271
o Resiliency Planning $ 305,161
o Routine Maintenance Programs
o Channel Maintenance $ 360,000
o Street Sweeping $ 340,000
o Pond Maintenance $ 28,595
o Pump Station Maintenance $1,050,277
o Maintenance Programs Contingency $ 500,000
o Corrective Maintenance Program $2,332,309
o Transfer to CIP Program $2,258,310
Programs Total $10,158,448 FY 2025 Budget Allocation, Including the 10/15 Budget Amendment
5
Page 41 of 59
Town of Hilton Head Island
STORMWATER UTILITY OVERVIEW – FUND BALANCE
Stormwater Fund Balance
o The fund balance increased by 46.3% between 2019 and 2024
o The fund balance will decrease in FY2025 per Town Council approval of both:
o the FY2025 Budget (supported in part with prior year unspent fund balance), and
o the October 2025 Budget Amendment to address recent tropical storm impacts
6
Page 42 of 59
Town of Hilton Head Island
CAPITAL IMPROVEMENT PROGRAM - SWU
Project Name Budget Project Description FY 2025 Scope of Work
1 Wexford Pump Station Overhaul
$ 1,190,994
Facility rehabilitation and improvement Chamber wall rehab; consultant design
2 Gum Tree Road Drainage Improvements
$ 85,000
Drainage system improvements Design, permitting, and construction
3 Jarvis Creek Outfall Improvements
$ 165,000
Resilience improvements Design and permitting
4 Folly Field/Moonshell Rd Drainage Improvements
$ 120,000
Drainage system improvements Design and permitting
5 Main Street Drainage Improvements
$ 250,000
Drainage system improvements System cleaning and inspection
6 Palmetto Hall Outfall Improvements
$ 100,000
Drainage system improvements Design and easement acquisition
7 Howell Tract Access Control System
$ 20,000
Security improvements Control system installation
8 Cordillo Courts Drainage Improvements $ 70,000 Drainage system improvements Design, permitting, and construction
9 Lawton Pump Station Overhaul – Pump Replacement $ 327,316 Replacement of a third pump Purchase and Installation (complete)
TOTAL $ 2,328,310
FY2025 CIP Projects
7
Page 43 of 59
Town of Hilton Head Island
ROUTINE MAINTENANCE PROGRAM
► CHANNELS (CONTRACTED SERVICES)
Routine System Maintenance Location Map - 41 locations
8
Page 44 of 59
Town of Hilton Head Island
ROUTINE MAINTENANCE PROGRAM
► STREET SWEEPING (CONTRACTED SERVICES)
Street Sweeping Program Map 9
Page 45 of 59
Town of Hilton Head Island
ROUTINE MAINTENANCE PROGRAM
► PONDS (CONTRACTED SERVICES)
Routine Pond Inspection & Maintenance Map
10
Page 46 of 59
Town of Hilton Head Island
Wexford Stormwater Pump Station (June 2021)
Pump Pull - Jarvis Creek SWPS
o The Town operates and maintains 4 stormwater
pump stations:
o Lawton ○ Jarvis Creek
o Wexford ○ Shipyard
o Maintaining these critical facilities is imperative to
protecting our community from the risk of flooding
during extreme weather events
o Maintenance at each facility includes pumps, gates,
screens, electrical controls, diesel generators, SCADA
monitoring systems, control buildings, and pump
chambers
o Rigorous maintenance and inspections are conducted
each winter to ensure operational readiness prior to
Hurricane Season
o Each pump station is inspected weekly by Town staff,
including operational testing and exercising each
pump
o A SCADA system installed at each pump station
provides remote monitoring, alert notifications, daily
run-time, and water volume reporting
Stormwater Pump Station Locations
11
ROUTINE MAINTENANCE PROGRAM
► PUMP STATIONS (CONTRACTED SERVICES)
Page 47 of 59
Town of Hilton Head Island
CORRECTIVE MAINTENANCE PROGRAM
Pipe joint failure causing sinkhole in roadway
Blocked pipe causes ponding
o The Corrective Maintenance Program identifies, evaluates, prioritizes and
corrects system deficiencies, including:
o Pipe Failure (collapse, joint failure, pipe wall compromise)
o Sinkholes caused by pipe and structure failures
o Inlet structure deterioration and safety issues
o Blockages caused by sediment build -up or pipe failure
o Control structure failure (weirs, risers, flapgates, etc.)
o Channel bank erosion and instability
o All Repair and rehabilitation projects are prioritized based on Service
Request vetting and risk -based evaluation scoring
o Staff tracks all Service Requests that qualify for Town Service in an Asset
Management database
12
Page 48 of 59
Town of Hilton Head Island
CORRECTIVE MAINTENANCE PROGRAM – EXTENT OF SERVICE
Corrective Maintenance Program – Extent of Service
EXTENT OF SERVICE (EOS)
o Town System
o Town ROW
o Town Easements
o Town Property
o PUD/POA Agreements
o 22 Active Agreements
o 4 2024 Applicants
o 34 Potential Candidates
(potential for 60 agreements)
o Not Included in EOS
o State Roads & Easements
o State Property
o County Roads & Easements
o County Property
o Private Property
13
Page 49 of 59
Town of Hilton Head Island
STORMWATER SYSTEM MAINTENANCE – DISPARITIES IN EXTENT OF SERVICE
o Disparities in the Town’s ability to provide equitable
service to residents; an example in Point Comfort:
o Bay Pines (42 homes) – County System
o Services provided are outside the control of the Town
o Cedar Woods (50 homes) – Private System
o No public services are provided
o Point Comfort Woods (40 homes) – Town System
o Routine and Corrective Maintenance Services are provided
o All 3 communities were developed by Sea Pines in the
1960s and 1970s to provide housing for employees
o These communities are low -lying and susceptible to
storm surge flooding
o The Dirt Road Acquisition and Paving Program involves
taking over existing unpaved roads; at the same time,
the Town has been historically reluctant to adopt
existing paved roads
14
Page 50 of 59
Town of Hilton Head Island
CORRECTIVE MAINTENANCE PROGRAM – DRAINAGE AGREEMENTS
o The Stormwater Utility provides corrective maintenance service
within active Drainage Agreement Partner communities
o Service is provided per the standardized terms and conditions of
each Drainage Agreement
o Routine and proactive maintenance services are not provided .
o The Town uses contractors to correct deficiencies
o Agreement partners can also complete projects on their own.
Projects are eligible for reimbursement if they comply with all
procedures stipulated in the Agreement terms and conditions
o Systems must drain a platted roadway ROW in the community
to qualify for service
34 other communities have been identified that would potentially
qualify for Drainage Agreements (4 interested + 30 additional)
o Adding all of these would add approximately 2% to the total
quantity of infrastructure covered by current agreements
o Adding all of these would require additional staff time to
manage agreement partner communication and request vetting
15 15
Page 51 of 59
Town of Hilton Head Island
CORRECTIVE MAINTENANCE PROGRAM – DRAINAGE AGREEMENTS
Agreement Partner Reimbursements
o The reimbursement process is clearly stipulated in the Drainage
Agreement, including the following:
o Procurement of services to correct deficiencies must comply with the
Town’s Procurement Policy
o The Town must approve the scope and cost before work begins
o The Town must inspect and approve the work once the project is complete
and receive all required documentation as stipulated in the Agreement
o The Town provides all agreement partners with a procedure and a
reimbursement request checklist
o During each fiscal cycle, the average number of reimbursement
requests is relatively low
o There are currently 6 open reimbursement requests in our database
o Reimbursements are scheduled based on their evaluation score in
accordance with the annual budget process; reimbursements are not
guaranteed in any specific future year
16
Page 52 of 59
Town of Hilton Head Island
CORRECTIVE MAINTENANCE PROGRAM
RANKING & PROJECT PRIORITIZATION
Receive Request
Vet & Evaluate Request
Develop Project Scope & Budget
Prioritize Project List
Take Corrective Maintenance Action
Service Request Evaluation Tool
18
17
Page 53 of 59
Town of Hilton Head Island
CORRECTIVE MAINTENANCE PROGRAM – SERVICE REQUEST EVALUATION
SERVICE REQUEST EVALUATION
o All requests received are evaluated by staff if the request is determined to
qualify for Town Service
o Staff uses a customized evaluation tool (developed in 2018) to complete a
Risk Assessment and to apply Assessment Modifiers for each request.
o The Risk Assessment evaluates a variety of deficiency components:
o Inundation and Flooding Considerations as it relates to:
o Roadway/Pathway Inundation and Flooding Impacts
o Structure Inundation and Flooding Impacts
o Amenities Inundation and Flooding Impacts
o Integrity and Safety Considerations as it relates to:
o Roadway/Pathway Integrity and Safety Impacts
o Structure Integrity and Safety Impacts
o Amenities Integrity and Safety Impacts
o Drainage System Integrity Considerations as it relates to:
o Conveyance Reduction Impacts
o Drainage System Integrity Impacts
o Drainage System Maintenance Impacts
o Assessment Modifiers are applied in several categories, including:
o Ownership (applies a 2 -point increase if Town -owned)
o Multiple Unique requests (high level of public concern)
o Town Leadership Directive
o Evaluation Scores are based on a 20 -point scale
SAMPLE EVALUATION
Deficiency: Sinkhole in Parking Lot Causing Localized Flooding (Bristol Sports Arena)
o RISK ASSESSMENT (greatest of each component evaluation score) 10
o Amenities Inundation and Flooding Impacts 10
o Facility Category: Parking Lot Drive Aisle
o Description/Severity: Inundation >6 inches, more than 24 hours 8
o Rainfall Event Category: Chronic Issue; rainfall less than 4.6 inches 2
o Amenities Integrity and Safety Impacts 8
o Facility Category: Parking Lot Stall(s)
o Description/Severity: Sinkhole, Minor Safety Hazard 6
o Inaction Modifier: Severity likely to increase within 3 months 2
o Drainage System Conveyance Reduction Impacts 9
o Facility Category: Tertiary System
o Description/Severity: Conveyance Capacity Reduced, >90% 9
o Inaction Modifier: Severity not likely to increase within 1 year 0
o ASSESSMENT MODIFIER (greatest of each component modifier score) 2
o Ownership Factor Located on Town Property 2
o Multiple Unique Requests Fewer Than Three 0
o Town Leadership Directive No Priority Directive 0
PRIORITY SCORE (RISK ASSESSMENT + ASSESSMENT MODIFIER ) 12
18
Page 54 of 59
Town of Hilton Head Island
o Personnel & Benefits $ 842,381
o Operations/Transfer to General Fund $ 273,574
o Debt Service (P&I) $1,298,570
o Monitoring Programs
o Water Quality Monitoring $ 140,000
o Tide Monitoring $ 4,000
o Weather Monitoring $ 50,000
o Modeling and Analysis Programs
o Inventory & Modeling $ 375,271
o Resiliency Planning $ 305,161
o Routine Maintenance Programs
o Channel Maintenance $ 360,000
o Street Sweeping $ 340,000
o Pond Maintenance $ 28,595
o Pump Station Maintenance $1,050,277
o Maintenance Programs Contingency $ 500,000
o Corrective Maintenance Program $2,332,309
o Transfer to CIP Program $2,258,310
Programs Total $10,158,448 FY 2025 Budget Allocation, Including the 10/15 Budget Amendment
ANNUAL SWU & CIP BUDGET DEVELOPMENT
19
Page 55 of 59
Town of Hilton Head Island
ANNUAL SWU & CIP BUDGET DEVELOPMENT
CAPITAL IMRPOVEMENT PROGRAM
o Will be developed based on a 5 -year program plan
CORRECTIVE MAINTENANCE PROGRAM
o As of September 26, there were 136 open, qualifying corrective
maintenance projects
o The list of qualifying projects is updated dynamically
throughout the year as new requests come in and others are
completed
o Tropical Storm Debby generated 72 new service requests, 30 of
which are still being evaluated by staff (as of 10/25)
o The FY 2025 Corrective Maintenance Program budget includes
twenty-one (21) projects (5 public and 16 PUD/POA)
o Four (4) high-priority projects were added during the first quarter
of FY 2025 (3 public and 1 PUD/POA)
o Total project budgets are summarized below:
o FY25 Budgeted Projects (≥10) 25 $1,912,000
o Non-budgeted Projects (<10) 111 $1,593,000
Open Qualifying Service Requests (09/25/2024)
The Corrective Maintenance Program Goal
for FY 2025 is to complete all 25 projects
with an Evaluation Score of 10 or higher
20
Page 56 of 59
Town of Hilton Head Island
o The Corrective Maintenance Program budget is determined based on several
factors, including:
o Available funding
o Staff capacity to implement projects
o Contractor capacity to complete projects
o The number of open qualifying requests is increasing
o The increase is related to:
o Aging systems experiencing increasing rates of failure (metal pipe and
perforated pipe are examples) MORE REQUESTS
o Increasing extent of service as the Town adds new drainage agreement
partners * MORE REQUESTS
o Staff capacity to implement projects remains flat
o Contractor capacity is limited on Hilton Head Island; many entities compete
to utilize the same pool of contractors with the necessary expertise, skilled
workers, and equipment
* The amount of infrastructure that might be added via future agreements
with remaining potential new partners is limited (roughly an additional 2%)
21
ANNUAL SWU & CIP BUDGET DEVELOPMENT
Page 57 of 59
Town of Hilton Head Island
STORMWATER UTILITY – PROGRAM CHALLENGES/OPPORTUNITY
o Extent of Service
o Will continue to increase as new Drainage Agreement Partners are added
o Will increase as new drainage easements are acquired
o Level of Service
o Will increasing as routine maintenance programs expand to provide improved and more
consistent service
o Will increase to allow for proactive condition assessment of existing infrastructure
o Project Delivery Limitations for CIP and Corrective Maintenance Programs
o Staff Capacity
o Funding Capacity
o Contractor Availability
o Emergent Needs
o Aging infrastructure continues to experience failure at higher rates requiring repair,
rehabilitation, or replacement
o Resilience improvements will be necessary, informed by the Resilience Study followed by an
Island-wide Stormwater Master Plan
o Opportunity for Consideration
o Utilize fund balance in FY26 to accommodate Drainage Agreement Partner reimbursement
requests to address lower priority projects
22
Page 58 of 59
Stormwater Utility Program Overview
Town Council Workshop
October 30, 2024
Town of Hilton Head Island
QUESTIONS ?