Council has directed that they receive their agenda packages a week prior to each Council meeting, therefore, Agenda Items Summaries must be submitted to the
Administrator for his review/approval no later than 12 days prior to each Council meeting. It is the Department Head / Elected Officials responsibility to ensure that all
approvals are obtained prior to submission to the Administrator for inclusion on an agenda.
A calendar with due dates marked may be obtained from the Clerk to Council.
PROCUREMENT - AGENDA ITEM SUMMARY
OCONEE COUNTY, SC
COUNCIL MEETING DATE: April 15, 2025
ITEM TITLE:
Procurement #: ITB 24-12 Title: Alexander-Cannon-Hill (ACH) House Department(s): PRT Amount: $247,924.55
Improvements Contingency (10%): $ 24,792.46
Total: $272,717.01
FINANCIAL IMPACT:
Procurement was approved by Council in Fiscal Year 2024-2025 budget process.
Budget: $272,717.01 Project Cost: $272,717.01 Balance: $0.00 Finance Approval: __________________________
(Funding from Parks Recreation and Tourism Capital Fund (330))
BACKGROUND DESCRIPTION:
The main structure of the ACH House was built in 1831, with an addition constructed in the 1860s. Listed on the National Historic Register, it is one of the
oldest buildings in Oconee and Pickens counties, dating back to the Old Pickens District. The house was relocated to its current site in 1972. The goal of this
project is to remodel and preserve the historic structure to accommodate visitor interpretation, park offices, and a park retail space.
This project includes structural reinforcement of the floor joists on both the first and second floors per engineering specifications. It also includes Exterior
Improvements, lead paint / asbestos abatement, removal and replacement of windows, removal and replacement of the roofing with a standing seam metal
roof on both the main structure and porches, removal and replacement of siding, and painting.
On April 1, 2025 formal sealed bids were opened for the Alexander Cannon Hill (ACH) House Improvements. Twelve (12) companies downloaded this bid
opportunity. Two (2) companies submitted bids, with Radiant Renovations, LLC of Seneca, SC submitting the lowest, responsive bid in the amount of
$247,924.55. Staff is requesting a 10% owner’s contingency to allow for unforeseen items that may arise.
ATTACHMENT(S):
1. Bid Tab
STAFF RECOMMENDATION:
It is the staff’s recommendation that Council;
2. Approve the Award of ITB 24-12, Alexander, Cannon, Hill (ACH) House Improvements, to Radiant Renovations, LLC of Seneca, SC in the
amount of $247,924.55, plus a 10% contingency in the amount of $24,792.46, for a total award of $272,717.01.
3. Authorize the County Administrator to execute documents for this project and sign any change orders within the contingency amount.
Submitted or Prepared By:_______________________________Approved for Submittal to Council: ___________________________________
Tronda C. Popham, Procurement Director Amanda F. Brock, County Administrator
ITB 24-12
Alexander Cannon Hill (ACH) House Improvements
April 1, 2025 @ 2:00pm
Bidders Pelfrey Builders LLC
Radiant
Renovations, LLC
Palmetto Construction
& Services of Upstate
Address
633 Earle St.
West Union, SC
29696
273 Applewood
Center PL. STE 222
Seneca, SC 29678
412 Saluda Rd.
Williamston, SC
29697
Grand Total
(Lump Sum Bid) No Bid $ 247,924.55 $ 276,610.00
ATTENDED BID OPENING: Tronda Popham, Madison Addington, Amber Turner, Phil Shirley, Stephen Schutt, Tony Young (via zoom)
STATE OF SOUTH CAROLINA
COUNTY OF OCONEE
PROCLAMATION 2025-04
A PROCLAMATION RECOGNIZING THE 40TH ANNIVERSARY
OF GOLDEN CORNER FOOD PANTRY
WHEREAS, the Golden Corner Food Pa ntry, known then as “Golden Corner Ministr ies”,
served three families when it opened its doors on April 3, 1985; and
WHEREAS, since then, the Golden Corner Food Pa ntry has establi shed itself as an in tegral
resource for the people in Oconee County, providing free meals to senior citizens, disaster victims, and
unemployed, low-income and disadvantaged individuals and their families; and
WHEREAS, in the early 2 000s, the Golden Corner Food Pant ry was designated as the
donation point for local stores, resulting in a steady source of donated food and it opened the doors of
its larger, existing facility on May 24, 2011; and
WHEREAS, over the last four deca des, Golden Corner Food Pantry participated in relief
efforts for emergencies, including severe weather, an EF-3 tornado and the COVID pandemic, turning
into a food distribution hub for work crew s and displace d residents, in addition to its re gular clients;
and
WHEREAS, the Gol den Cor ner Food Pantry continuously adapts to meet the needs of the
community, as evident with the “ Brown Bag ” program, a drive -thru distribution for senior citizens
with mobility issues, as well as the Mobile Pantry Program that brings food assistance to people with
transportation issues in Westminster, Salem, Mountain Rest and Long Creek; and
WHEREAS, based on research and a dvisory meetings with clients , the Golden Corner Food
Pantry transitioned to a Clie nt-Choice Shopping Model , a grocery store expe rience that empowers
clients by giving them control over the food their families receive and reduces waste; and
WHEREAS, in 2024, with the support of 250 volunteers and 450 generous donors, the Golden
Corner Food Pantry distributed 1.5 million pounds of food in Oconee County.
NOW, THEREFORE, we, the Oconee County Council, do hereby e xtend our sincere
appreciation and congra tulations to Golden Corner Food Pantry on its 40
th Anniversary of operation
and service to the people of Oconee County.
APPROVED AND ADOPTED this 15th day of April, 2025.
OCONEE COUNTY, SOUTH CAROLINA
____________________________________
Matthew Durham, Chairman of County Council
Oconee County, South Carolina
Attest: _____________________________
Jennifer Adams, Clerk to County Council
Oconee County, South Carolina
Council has directed that they receive their agenda packages a week prior to each Council meeting, therefore, Agenda
Items Summaries must be submitted to the Administrator for his review/approval no later than 12 days prior to each
Council meeting. It is the Department Head / Elected Officials responsibility to ensure that all approvals are obtained
prior to submission to the Administrator for inclusion on an agenda. A calendar with due dates marked may be
obtained from the Clerk to Council.
AGENDA ITEM SUMMARY
OCONEE COUNTY, SC
COUNCIL MEETING DATE April 15, 2025
COUNCIL MEETING TIME: 6:00 PM____
ITEM TITLE [Brief Statement]:
Council consideration to approve an ordinance agreement between Project Shaker and Oconee County, and
acceptance of a $100,000 SC Set-Aside Grant Award Agreement to expand the project’s manufacturing operations in
Oconee County.
BACKGROUND DESCRIPTION:
Project Shaker is an advanced manufacturing company that is considering Oconee County as a location for an
expansion of their operation. The project will include the construction a 100,000 square foot additi on with an
expected capital investment of nearly $20 million and 41 new jobs. The Oconee Economic Alliance (OEA) has been
working with the project since January 2024. We have discussed with the company and SC Department of Commerce
property tax reductions and several state incentives to secure the project in Oconee. OEA is recommending the
following county incentives for the project:
1. A 30-Year Fee-In-Lieu-of- Tax (FILOT) agreement with an assessment rate of 6% and fixed millage rate of
214.9 mills.
2. A 7-Year Special Source Revenue Credit (SSRC) at 50% annually.
The South Carolina Coordinating Council for Economic Development (CCED) awarded the project a $100,000 grant
for building and site i mprovements. The grant is similar to most state economic development grants for new and
expanding businesses, whereby Oconee County serves as a pass through for the grant . Project Shaker will make the
improvements eligible under the grant and then submi t a request for payment and supporting documentation to
Oconee Count y. In turn, the County will forward that information, with a request for payment and supporting
documentation, to CCED. CCED will review the request and upon approval forwards the funds to the County. The
County will then cut a check to Proje ct Shaker. A performance agreement between the CCED, Project Shaker and
Oconee County is needed for the grant to be effective and should be available for the May 6 County Council Meeting.
SPECIAL CONSIDERATIONS OR CONCERNS [only if applicable]:
• The project would be making a strong commitment to strengthen their Oconee County operation.
• The project is competing with other company facilities in several states.
• Existing industry is our top prior ity and the county is committed to assisting businesses that seek to grow
their operations in the county.
FINANCIAL IMPACT [Brief Statement]:
• The project wo uld generate an estimated $ 1,434,627 in property taxes ove r the first 10 years, $3,549,798
over 20 years and $5,664,968 over 30 years.
• The FILOT and SSRC represent a property tax reduction of approximately $529,016 over the first 10 years,
$1,065,625 over 20 years and $2,030,274 over 30 years from the standard ad valorem taxes which includes
the state statutory 5-year manufacturers abatement.
Check here if Item Previously approved in the Budget. No additional information required.
Council has directed that they receive their agenda packages a week prior to each Council meeting, therefore, Agenda
Items Summaries must be submitted to the Administrator for his review/approval no later than 12 days prior to each
Council meeting. It is the Department Head / Elected Officials responsibility to ensure that all approvals are obtained
prior to submission to the Administrator for inclusion on an agenda. A calendar with due dates marked may be
obtained from the Clerk to Council.
Approved by: ________Finance
ATTACHMENTS
STAFF RECOMMENDATION [Brief Statement]:
It is the staf f’s recommendation that Council approve the ordinance and accept the s et-aside gran t agreement for
Project Shaker.
Submitted or Prepared By: Approved for Submittal to Council:
__________________________ _____________________________________
Jamie Gilbert, Economic Development Director Amanda F. Brock, County Administrator
PAGE 1 OF 7
STATE OF SOUTH CAROLINA
COUNTY OF OCONEE
ORDINANCE 2024-25
AN ORDINANCE AUTHORIZING, PURSUANT TO TITLE 12, CHAPTER
44 OF THE CODE OF LAWS OF SOUTH CAROLINA 1976, AS
AMENDED, THE EXECUTION AND DELIVERY OF A FEE-IN-LIEU OF
AD VALOREM TAXES AND SPECIAL SOURCE REVENUE CREDIT
AGREEMENT BY AND BETWEEN OCONEE COUNTY, SOUTH
CAROLINA, AND PROJECT SHAKER, ACTING FOR ITSELF, ONE OR
MORE CURRENT OR FUTURE AFFILIATES AND OTHER PROJECT
COMPANIES (COLLECTIVELY, “COMPANY”); PROVIDING FOR A
FEE-IN-LIEU OF AD VALOREM TAXES INCENTIVE; PROVIDING FOR
A SPECIAL SOURCE REVENUE CREDIT; DEVELOPING A JOINT
COUNTY INDUSTRIAL AND BUSINESS PARK BETWEEN OCONEE
COUNTY AND PICKENS COUNTY SO AS TO DESIGNATE THE
PROPERTY OF THE PROJECT AS PART OF A MULTI -COUNTY
INDUSTRIAL PARK; AND OTHER RELATED MATTERS.
WHEREAS, Oconee County, South Carolina ( “County”), acting by and through its County Council
(“Council”), is authorized and empowered, under and pursuant to the provisions of the Code of Laws of
South Carolina 1976, as amended through the date hereof (“Code”), particularly Title 12, Chapter 44 thereof
(“Negotiated FILOT Act”) and Title 4, Chapter 1 of the Code ( “Multi-County Park Act” or, as to Section
4-1-175 thereof, and, by incorporation, Section 4- 29-68 of the Code, “Special Source Act”) (collectively,
“Act”), and by Article VIII, Section 13 of the South Carolina Constitution: (i) to enter into agreements with
investors to establish projects through which the economic development of the State of South Carolina
(“State”) will be promoted and trade developed, thus utilizing and employing the manpower, agricultural
products, and natural resources of the State; (ii) to covenant with those investors to accept certain fee in
lieu of ad valorem tax (“FILOT”) payments, including, but not limited to, negotiated FILOT (“Negotiated
FILOT”) payments , and gra nting certain special source revenue credits ( “SSRCs”) to pay costs of
designing, acquiring, constructing improving or expanding (i) infrastructure serving a project or the County,
and (ii) for improved or unimproved real estate and personal property including machinery and equipment
used in the operating of a manufacturing or commercial enterprise ( “Infrastructure”); and (iii) to create or
expand, in conjunction with one or more other counties, a multi-county industrial or business park to allow
such special source revenue credits and certain enhanced income tax credits to those investors;
WHEREAS, the County has caused to be prepared and presented to the Council the form of an
agreement (“MCIP Agreement”) for Development of a Joint County Industrial Park (Project Shaker ) by
and between the County and Pickens County (“Park”), the substantially final form of which is attached as
Exhibit C , pursuant to which certain real property consisting of approximately [●] acres, as fur ther
described on the attached Exhibit A (“Project Site”) shall be designated as being part of the Park upon the
approval of this Ordinance by the Council and the approval of a separate ordinance by the Pickens County
Council;
WHEREAS, the property located in the Park is exempt from ad valorem taxation and the owners of
that property pay a non-negotiated fee in lieu of tax payment in the absence of a Negotiated FILOT (“Non-
Negotiated FILOT”);
WHEREAS, the County, acting by and through its Council, is further authorized and empowered under
and pursuant to the provisions of the Multi-County Park Act to provide for payments-in-lieu of taxes with
respect to property located in a multi -county business or industrial park created under the Multi-County
Park Act and to create, in conjunction with one or more other counties, a multi-county park to afford certain
enhanced tax credits to those investors;
PAGE 2 OF 7
WHEREAS, [●], formerly known to the County as Project Shaker, acting for itself, one or more current
or future affiliates and other project sponsors (collectively, “Company”) proposes to invest in, or cause
others to invest in, the establishment or expansion of a manufacturing facility in the County (“Project”),
which the Company expects will result in the investment of approximately $12,650,000 in taxable property
and the creation of approximately 41 new, full-time equivalent jobs;
WHEREAS, the Project Site, upon the approval of this Ordinance by the Council and the approval of
a separate ordinance by the Pickens County Council, is added to and will be located within the boundaries
of the Park;
WHEREAS, pursuant to an Inducement Resolution adopted by the Council on October 15, 2024, the
County identified the Project as a “project” as provided in the Act and gave preliminary approval to certain
incentives;
WHEREAS, the Company has caused to be prepared and presented to this meeting the form of the Fee
in Lieu of Ad Valorem Taxes and Special Source Revenue Credit Agreement, attached as Exhibit B, by and
between the County and the Company (“Fee Agreement”), which provides for (i) fee in lieu of tax payments
utilizing a 6% assessment ratio for a period of 30 years for the Project or each component thereof placed in
service during the investment period as provided according to the Act; and (ii) a fifty percent (50%) SSRC
with a term of 7 years with respect to the Negotiated FILOT payments; and
WHEREAS, it appears that the Fee Agreement , and the MCIP Agreement , each of which are now
before this meeting, are in appropriate form and are each an appropriate instrument to be executed and
delivered by the County for the purposes intended.
NOW, THEREFORE, BE IT ORDAINED by the Council, as follows:
Section 1. Statutory Findings. Based solely on information provided to the County by the Company,
it is hereby found, determined, and declared by the County Council, as follows:
(a) The Project will constitute a “project” as that term is referred to and defined in the Act, and
the County’s actions herein will subserve the purposes and in all respects conform to the provisions
and requirements of the Act;
(b) The Project and the payments in lieu of taxes set forth herein are beneficial to the County,
and the County has evaluated the Project based on all criteria prescribed by law, including the
anticipated dollar amount and nature of the i nvestment to be made and the anticipated costs and
benefits to the County;
(c) The Project is anticipated to benefit the general public welfare of the County by providing
services, employment, recreation, or other public benefits not otherwise adequately provi ded
locally;
(d) The Project gives rise to no pecuniary liability of the County or any incorporated
municipality or a charge against the general credit or taxing power of either;
(e) The purposes to be accomplished by the Project, i.e., economic development, creat ion of
jobs, and addition to the tax base of the County, are proper governmental and public purposes;
(f) The inducement of the location or expansion of the Project within the County and State is
of paramount importance; and
(g) The anticipated benefits of the Project to the public will be greater than the costs.
Section 2. Multi-County Park . The County intends to use its commercially reasonable efforts to
designate the Project and the Project Site as part of the Park or a separate multi-county industrial or business
park, if not already so designated, and intends to use its commercially reasonable efforts to maintain the
PAGE 3 OF 7
Project and the Project Site within the boundaries of a multi-county industrial or business park pursuant to
the provisions of the Multi -County Park Act and Article VIII, Section 13(D) of the State Constitution on
terms which provide, for all jobs created at the Project through the end of the investment period set forth in
the MCIP Agreement, any additional job tax credits afforded by the laws of the State for projects located
within multi-county industrial or business parks, and on terms, and for a duration, which facilitate the
special source revenue credits set forth in the recitals of this Ordinance. Sharing of expenses and revenues
of the County and Pickens County shall be as set forth in the MCIP Agreement (or applicable agreement
related to any subsequent multi-county industrial or business park).
Section 3. Authorization of an A pproval of Form of Fee Agreemen t, and MCIP Agreement. To
promote industry, develop trade, and utilize and employ the manpower, products, and natural resources of
the State by assisting the Company to expand or locate a manufacturing facility in the State, the Fee
Agreement, and the MCIP Agreement are each authorized and approved. The form of the Fee Agreement,
and the MCIP Agreement presented at this meeting, respectively, as attached as Exhibit B, and Exhibit C,
are each approved, and all of the terms of each are incorporated in this Ordinance by reference as if the Fee
Agreement, and the MCIP Agreement were set out in this Ordinance in their entirety. The Chairman of the
County Council, and the Clerk to County Council are each authorized, empowered, and directed to execute,
acknowledge, and deliver the Fee Agreement , and the MCIP Agreement in the name of and on behalf of
the County, and to cause the executed Fee Agreement to be delivered to the Company and the executed
MCIP Agreement to be delivered to Pickens County. The Fee Agreement, and the MCIP Agreement are in
substantially the form now before this meeting, with such changes therein as shall not be materially adverse
to the County and as shall be approved by the officials of the County executing the same, on the advice of
Counsel to the County, such official’s execution thereof to constitute conclusive evidence of such official’s
approval of any and all changes or revi sions therein from the form of the Fee Agreement , and the MCIP
Agreement now before this meeting.
Section 4. Authorization for County Officials to Act. The Chairman of the County Council, the Clerk
to County Council, and the County Administrator, for and on behalf of the County, are each authorized and
directed to do each thing that is reasonably necessary and prudent to effect the execution and delivery of
the Fee Agreement, and the MCIP Agreement and the performance of all obligations of the County under
and pursuant to this Ordinance and Fee Agreement, and the MCIP Agreement.
Section 5. General Repealer. Each order, resolution, ordinance, or part of the same in conflict with
this Ordinance, is, to the extent of that conflict, repealed.
Section 6. Effective Date. This Ordinance is effective at its approval following a public hearing and
third reading.
[ONE SIGNATURE PAGE AND [] EXHIBITS FOLLOW]
[REMAINDER OF PAGE INTENTIONALLY BLANK]
PAGE 4 OF 7
Passed and approved: December ____, 2024
OCONEE COUNTY, SOUTH CAROLINA
By:
Matthew Durham, Chairman
Oconee County Council
[SEAL]
ATTEST:
By:
Jennifer C. Adams, Clerk to Council
Oconee County Council
First Reading: October 15, 2024
Second Reading: November 04, 2024
Public Hearing: April 15, 2025
Third Reading: April 15, 2025
PAGE 5 OF 7
EXHIBIT A
DESCRIPTION OF PROJECT SHAKER PROPERTY
ALL that certain piece, parcel, or tract of land situate in Oconee County, South Carolina and being shown
[●] [●] [●]. Said parcel being more fully described as follows: [●] [●] [●].
PAGE 6 OF 7
EXHIBIT B
FORM OF FEE IN-LIEU OF AD VALOREM TAXES AND
SPECIAL SOURCE REVENUE CREDIT AGREEMENT
[SEE ATTACHED]
PAGE 7 OF 7
EXHIBIT C
FORM OF MCIP AGREEMENT
[SEE ATTACHED]
FEE-IN-LIEU OF AD VALOREM TAXES AND
SPECIAL SOURCE REVENUE CREDIT AGREEMENT
Between
OCONEE COUNTY, SOUTH CAROLINA
and
[PROJECT SHAKER]
Dated as of [_________], 2024
RECAPITULATION OF CONTENTS OF
FEE AGREEMENT PURSUANT TO S.C. CODE §12-44-55(A)
The parties have agreed to waive this requirement pursuant to S.C. Code Ann. § 12-44-55(B).
1
FEE-IN-LIEU OF AD VALOREM TAXES AND
SPECIAL SOURCE REVENUE CREDIT AGREEMENT
THIS FEE-IN-LIEU OF AD VALOREM TAXES AND SPECIAL SOURCE REVENUE CREDIT
AGREEMENT (the “Fee Agreement”) is made and entered into as of [___], 2024 by and between OCONEE
COUNTY, SOUTH CAROLINA (the “County”), a body politic and corporate and a political subdivision
of the State of South Carolina (the “State”), acting by and through the Oconee County Council (the “County
Council”) as the governing body of the County, and [PROJECT SHAKER], (FORMERLY IDENTIFIED
AS PROJECT SHAKER), a corporation organized and existing under the laws of the State of South
Carolina (the “Company”).
RECITALS
1. Title 12, Chapter 44, Code of Laws of South Carolina, 1976, as amended (the “Act”)
authorizes the County (i) to induce industries to locate in the State; (ii) to encourage industries now located
in the State to expand their investments and thus make use of and employ manpower, products, and other
resources of the State; and (iii) to enter into a fee agreement with entities meeting the requirements of such
Act, which identifies certain property of such entities as economic development property.
2. Pursuant to Section 12-44-40(I)(1) of the Act, based solely on the information provided to
the County by the Company, the County finds that: (a) the Project (as defined herein) is anticipated to
benefit the general public welfare of the County by providing services, em ployment, recreation, or other
public benefits not otherwise adequately provided locally; (b) the Project gives rise to no pecuniary liability
of the County or any incorporated municipality and to no charge against its general credit or taxing power;
(c) the purposes to be accomplished by the Project are proper governmental and public purposes; and (d)
the benefits of the Project are greater than the costs.
3. Based solely on information provided to the County by the Company, the County has
evaluated the Project based on all relevant criteria that include, but are not limited to, the purposes the
Project is to accomplish, the anticipated dollar amount and nature of the investment, and the anticipated
costs and benefits to the County.
4. An Ordinance that the Count y Council enacted contemporaneously with the date of this
Fee Agreement (the “Fee Ordinance”) authorizes the County and the Company to enter into a Fee
Agreement that classifies the Project as Economic Development Property under the Act and provides for
the payment of fees in lieu of taxes, all as further described herein.
NOW, THEREFORE, FOR AND IN CONSIDERATION of the respective representations and
agreements hereinafter contained, the parties hereto agree as follows:
ARTICLE I
DEFINITIONS
Section 1.1 The terms that this sec tion defines shall for all purposes of this Fee Agreement
have the meanings herein specified, unless the context clearly requires otherwise:
2
“Act” shall mean Title 12, Chapter 44, Code of Laws of South Carolina, 1976, as amended, and all
future acts successor or supplemental thereto or amendatory thereof.
“Act Minimum Investment Requirement” shall mean an investment of at least $2,500,000 by the
Company and any Sponsors and sponsor affiliates of property within the Investment Period , provided,
however, that in the event of a reduction of the minimum investment level in Section 12-44-30(14) or any
successor section by legislative action, then the Act Minimum Investment Requirement shall equal such
reduced amount.
“Clawback Minimum Requirements” shall mean (a) an investment of at least [ $12,650,000] in
property subject to ad valorem taxation (in the absence of this Fee Agreement and/or the Industrial
Development Park) by the Company and any Sponsors and (b) the creation of at least [ 41 new], full-time
jobs by the Company.
“Commencement Date” shall mean the last day of the property tax year during which the Project
or the first Phase thereof is placed in service, which date must not be later than the last day of the property
tax year which is three years from the year in which the County and the Company enter into this Fee
Agreement.
“Company” shall mean [Project Shaker] (formerly identified as Project Shaker) and any surviving,
resulting, or transferee entity in any merger, consolidation, or transfer of assets; or any other person or
entity which may succeed to the rights and duties of the Company.
“County” shall mean Oconee County, South Carolina, a body politic and corporate and a political
subdivision of the State of South Carolina, its successors, and assigns, acting by and through the County
Council as the governing body of the County.
“County Council” shall mean the Oconee County Council, the governing body of the County.
“Department” or “SCDOR” shall mean the South Carolina Department of Revenue.
“Diminution in Value” in respect of the Project or any Phase of the Project shall mean any reduction
in the value using the original fair market value (without regard to depreciation) as determined in Step 1 of
Section 4.1(a) of this Fee Agreement, of the items which constitute a part of the Project or such Phase and
which are subject to FILOT payments which may be caused by (i) the Company’s removal and/or disposal
of equipment pursuant to Section 4.6 of this Fee Agreement; (ii) a casualty to the Project, such Phase of the
Project, or any part thereof, described in Section 4.7 of this Fee Agreement; or (iii) a condemnation of the
Project, such Phase of the Project, or any part thereof, described in Section 4.8 of this Fee Agreement.
“Economic Development Property” shall mean those items of real and tangible personal property
of the Project which are eligible for inclusion as economic development property under the Act, selected
and identified by the Company in its annual filing of a SCDOR PT -300S or comparab le form with the
Department (as such filing may be amended from time to time) for each year within the Investment Period.
“Equipment” shall mean all of the machinery, equipment, furniture, office equipment, and fixtures,
together with any and all additions, accessions, replacements, and substitutions thereto or therefor used or
to be used in the County by the Company for the purposes described in Section 2.2(b) hereof, provided,
however, that repairs, alterations, or modifications to personal property which is not economic development
property or property subject to a fee in lieu of taxes prior to this Fee Agreement, are not eligible to become
Economic Development Property, except for modifications which constitute an expansion of existing real
property improvements.
“Event of Default” shall mean any event of default specified in Section 5.1 of this Fee Agreement.
3
“Exemption Period” shall mean the period beginning on the first day of the property tax year after
the property tax year in which an applicable piece of Economic Development Property is placed in service
and ending on the Termination Date. In case there are Phases of the Project, the Exemption Period applies
to each year’s investment made during the Investment Period.
“Fee,” “Fee in Lieu of Taxes,” “FILOT,” or “Payments in Lieu of Taxes” shall mean the amount
paid or to be paid in lieu of ad valorem property taxes as provided herein.
“Fee Agreement” shall mean this Fee Agreement.
“Fee Term” shall mean the period from the date of this Fee Agreement until the Termination Date.
“Improvements” shall mean all improvements to the Real Property, including buildings, building
additions, roads, sewer lines, and infrastructure, together with any and all additions, fixtures, accessions,
replacements, and substitutions thereto or therefor used or to be used in the County for the purposes
described in Section 2.2(b) hereof; provided, however, that repairs, alterations, or modifications to real
property which is not economic development property or property subject to a fee in lieu of taxes prior to
this Fee Agreement, are not eligible to become Economic Development Property, except for modifications
which constitute an expansion of exis ting real property improvements and except as otherwise permitted
by Section 12-44-110 of the Act.
“Industrial Development Park” shall mean an industrial or business park created pursuant to the
MCIP Act.
“Infrastructure” shall mean infrastructure serving the Project, including the Improvements, to the
extent that the MCIP Act permits, provided that Infrastructure shall first be deemed to include real property
and infrastructure improvements prior to including any personal property, notwithstanding any
presumptions to the contrary in the Act or otherwise.
“Infrastructure Credit” shall mean the annual infrastructure credit provided to the Company
pursuant to the MCIP Act and Section 4.1(c) hereof, with respect to the Infrastructure.
“Investment Commitment” shall mean, with respect to the Project, investment by the Company and
any sponsor affiliates of at least $12,650,000 in Economic Development Property subject (non-exempt) to
ad valorem taxation (in the absence of this Fee Agreement).
“Investment Period” shall mean the period beginning with the first day of any purcha se or
acquisition of Economic Development Property and ending five years after the Commencement Date,
provided that the Company and the County may agree to a later date pursuant to Section 12- 44-30(13) of
the Act.
“Jobs Achievement Percentage” shall equal the quotient of the maximum number of jobs created
in the Investment period divided by forty-one (41).
“Jobs Commitment” shall mean the creation of at least forty -one (41) new, full -time jobs at the
Project.
“MCIP Act” shall mean Article VIII, Section 13 (D) of the Constitution of the State of South
Carolina, Sections 4-1-170, 4-1-172, and 4-1-175 of the Code of Laws of South Carolina, 1976, as amended,
and Section 4-29-68 of the Code of Laws of South Carolina, 1976, as amended.
“Phase” or “Phases” in respect of the Project shall mean that the Equipment, Improvements, and/or
Real Property of the Project are placed in service during more than one year in the Investment Period, and
the word “Phase” shall therefore refer to the applicable portion of the Pr oject placed in service in a given
year in the Investment Period.
4
“Project” shall mean all the Equipment, Improvements, and/or Real Property in the County that the
Company determines to be necessary, suitable, or useful for the purposes that Section 2.2(b) describes, and
first placed in service in calendar year 2024 or thereafter. The Project shall not include existing buildings
and improvements on the Real Property, as of the date of the commencement of the Project by the Company,
and any machinery and equipment which have previously been subject to South Carolina ad valorem
taxation, except as expressly permitted by Section 12-44-110 of the Act.
“Real Property” shall mean real property that the Company uses or will use in the County for the
purposes that Section 2.2(b) describes, and initially consisting of the land identified on Exhibit A hereto,
together with all and singular the rights, members, hereditaments, and appurtenances belonging or in any
way incident or appertaining thereto, and any improvements located thereon.
“Removed Components” shall mean the following types of components or Phases of the Project or
portions thereof which are subject to FILOT payments, all of which the Company shall be entitled to remove
from the Project with the result that the same shall no longer be subject to the terms of the Fee Agreement:
(a) components or Phases of the Project or portions thereof which the Company, in its sole discretion,
determines to be inadequate, obsolete, worn- out, uneconomic, damaged, unsuitable , undesirable, or
unnecessary pursuant to Section 4.6 hereof or otherwise; or (b) components or Phases of the Project or
portions thereof which the Company in its sole discretion, elects to be treated as removed pursuant to
Section 4.7(c) or Section 4.8(b)(iii) of this Fee Agreement.
“Replacement Property” shall mean any property which is placed in service as a replacement for
any item of Equipment, any Improvement, or any Real Property previously subject to this Fee Agreement
regardless of whether such property serves the same functions as the property it is replacing and regardless
of whether more than one piece of property replaces any item of Equipment, any Improvement, or any Real
Property, to the fullest extent that the Act permits.
“Sponsor” shall mean an entity that joins with or is an affiliate of, the Company and that participates
in the investment in, or financing of, the Project and which meets the requirements under the Act to be
entitled to the benefits of this Fee Agreement w ith respect to its participation in the Project. Any Sponsor
joining in the investment at the Project will be effective on delivery of a Joinder Agreement, the form of
which is attached as Exhibit B
, executed by the Company and the Sponsor, and consented to by the County,
as reflected by its execution of the Joinder Agreement.
“Streamlined FILOT Act” shall mean Title 4, Chapter 12 of the Code of Laws of South Carolina,
1976, as amended.
“Termination Date” shall mean in case the entire Project is placed in service in one year, the end
of the last day of the property tax year which is the 29th year following the first property tax year in which
the entire Project is placed in service, or in case there are Phases of the Project, the Termination Date shall
mean with respect to each Phase of the Project the end of the last day of the property tax year which is the
29th year following the first property tax year in which such Phase of the Project is placed in service,
provided, that the intention of the parties is that the Company will make at least 30 annual FILOT payments
under Article IV hereof with respect to each Phase of the Project and provided further, that if this Fee
Agreement is terminated earlier in accordance with the terms hereof, the Termin ation Date is the date of
such termination.
Section 1.2 Any reference to any agreement or document in this Article I or otherwise in this
Fee Agreement shall include any and all amendments, supplements, addenda, and modifications to such
agreement or document.
Section 1.3 The ter m “investment” or “invest” as used herein shall include not only
investments made by the Company or a Sponsor , but also to the fullest extent permitted by law, those
investments made by or for the benefit of the Company in connection with the Project through federal, state,
5
or local grants, to the extent such investments are subject to ad valorem taxes or FILOT payments by the
Company.
ARTICLE II
REPRESENTATIONS, WARRANTIES, AND AGREEMENTS
Section 2.1 Representations, Warranties, and Agreements of the County . The County hereby
represents, warrants, and agrees as follows:
(a) The County is a body politic and corporate and a political subdivision of the State
and acts through the County Council as its governing body. The Act authorizes and empowers the County
to enter into the transac tions that this Fee Agreement contemplates and to carry out its obligations
hereunder. The County has duly authorized the execution and delivery of this Fee Agreement and any and
all other agreements described herein or therein and has obtained all consents from third parties and taken
all actions necessary or that the law requires to fulfill its obligations hereunder.
(b) Based solely on representations by the Company, the Project constitutes a
“project” within the meaning of the Act, and the County is a Count y that the Act authorizes to enter into
fee in lieu of tax agreements with companies that satisfy the Act Minimum Investment Requirement within
the County.
(c) The County has agreed that each item of real and tangible personal property
comprising the Project which is eligible to be economic development property under the Act and that the
Company selects shall be considered Economic Development Property and is thereby exempt from ad
valorem taxation in South Carolina.
(d) The millage rate in Section 4.1 hereof is the lowest millage rate permissible under
the Act, which the parties understand to be 214.9 mills, the millage rate in effect with respect to the location
of the proposed Project on June 30, 2024, as provided under Section 12-44-50(A)(1)(d) of the Act.
(e) The County will not be in default in any of its obligations (contractual or
otherwise), including any violation of its statutory debt limit, as a result of entering into and performing
under this Fee Agreement and/or as a result of creating an Industrial Development Park encompassing the
Project.
(f) The County agrees to use its commercially reasonable efforts to cause the Real
Property to be added to and become part of the Multi-County Park, and the County will diligently take all
reasonable acts to ensure that the Project will continuously be included with the boundaries of the Multi -
County Park or another multi -county park during the Fee Term in order that the tax benefits afforded by
the laws of the State of South Carolina for projects in the County located within multi- county industrial
parks will be available to the Sponsor.
Section 2.2 Representations, Warranties, and Agreements of the Company . The Company
hereby represents, warrants, and agrees as follows:
(a) The Company is in good standing under the laws of the State of South Carolina, is
duly authorized to transact business in the State of South Carolina, has power to enter into this Fee
Agreement, and has duly authorized the execution and delivery of this Fee Agreement.
(b) The Company intends to operate the Project as a “project” within the meaning of
the Act as in effect on the date hereof. The Company intends to operate the Project for the purpose of
manufacturing, and for such other purposes that the Act permits as the Company may deem appropriate.
6
(c) The Company will use commercially reasonable efforts to ensure that its total
capital investment will equal or exceed the Act Minimum Investment Requirement.
(d) The Company’s execution and delivery of this Fee Agreement and its compliance
with the provisions hereof will not result in any material default, not waived, or cured, under any company
restriction or any material agreement or instrument to which the Company is now a party or by which it is
bound.
(e) The Company intends to operate the Project as a “project” within the meanin g of
the Act as in effect on the date hereof. The Company intends to develop, construct, install and operate, as
applicable, certain facilities on the Real Property to conduct its distribution and/or manufacturing facility,
and any other legal activities and functions with respect thereto, and for such other purposes permitted
under the Act as the Company may deem appropriate.
(f) The availability of the payment in lieu of taxes regarding the Economic
Development Property authorized by the Act has, together wit h other incentives offered, induced the
Company to undertake the Project in the County.
(g) The Company plans and intends t o achieve its Investment Commitment and Jobs
Commitment by the end of the Investment Period.
(h) The income tax year of the Company, and accordingly the property tax year, for
federal income tax purposes, ends on March 31.
(i) The Company has retained legal counsel to confirm or has had a reasonable
opportunity to consult legal counsel to confirm, its eligibility for the FILOT and other incentives granted
by this Fee Agreement and has not relied on the County, its officials, employees, or legal representatives
with respect to any question of eligibility or applicability of the FILOT and other incentives granted by this
Fee Agreement.
ARTICLE III
COMMENCEMENT AND COMPLETION OF THE PROJECT
Section 3.1 The Project. The Company intends to invest in Equipment, Improvements, and/or
Real Property, which together comprise the Project and which are anticipated to create at least the Act
Minimum Investment Requirement in eligible Economic Development Property investment subject to
Payments in Lieu of Taxes in the County.
The parties hereto agree that, to the extent that applicable law allows or is revised or construed to
allow the benefits of the Act, in the form of FILOT Payments to be made under Article IV hereof, to be
applicable to leased assets including, but not limited to a building and/or personal property to be installed
in the buildings and leased to but not purchased by the Company from one or more Sponsors under any
form of lease, then such property shall, at the election of the Company, be subject to FILOT Payments to
the same extent as the Company’s assets covered by this F ee Agreement, subject, at all times, to the
requirement of such applicable law. The parties hereto further agree that this Fee Agreement may be
interpreted or modified as may be necessary or appropriate in order to give proper application of this Fee
Agreement to such tangible property without such construction or modification constituting an amendment
to this Fee Agreement, and thus not requiring any additional action by the County Council. The County
Administrator, after consulting with the County Attorne y, shall be and hereby is authorized to make such
modifications, if any, as may be necessary or appropriate in connection therewith. Such leased property
shall constitute a part of the Project for all purposes of this Fee Agreement, including the calculation of the
Clawback Minimum Requirements, removal, replacement, and termination, and such Sponsor shall be
deemed to be a party to this Fee Agreement provided, however, that no Sponsor shall be liable for any
payments pursuant to Section 4.2(b) hereof, which shall remain the Company’s liability.
7
Pursuant to the Act and subject to Section 4.2 hereof, the Company and the County hereby agree
that the Company shall identify annually those assets which are eligible for FILOT payments under the Act
and which the Company selects for such treatment by listing s uch assets on the applicable schedule in its
annual PT-300 form (or comparable form) to be filed with the Department (as such may be amended from
time to time) and that by listing such assets, such assets shall automatically become Economic Development
Property and therefore be exempt from all ad valorem taxation during the Exemption Period, subject to
provisions of the Act, and Article V, hereof, and provided, however, the Company makes FILOT payments,
as, if, and when due under the Act and this Fee Agreement . Anything contained in this Fee Agreement to
the contrary notwithstanding, the Company shall not be obligated to complete the acquisition of the Project.
However, if the Company does not meet the Act Minimum Investment Requirement, this Fee Agreement
shall be terminated as provided in Section 4.2 hereof.
Section 3.2 Diligent Completion. The Company agrees to use its reasonable efforts to cause
the completion of the Project as soon as practicable, but in any event on or prior to the end of the Investment
Period.
Section 3.3 Filings and Reports.
(a) Each year during the term of the Fee Agreement, the Company shall deliver to the
County, the County Auditor, the County Treasurer, the County Assessor, and the County Treasurer, a copy
of its most recent annual filings with the Department with respect to the Project, not later than 30 days
following delivery thereof to the Department.
(b) The Company shall cause a copy of this Fee Agreement, as well as a copy of the
completed Form PT-443 of the Department, to be filed with the County Auditor, the County Treasurer, and
the County Assessor of the County and any partner county, when the Project is placed in an Industrial
Development Park, and the Department within 30 days after the date of execution and delivery hereof by
all parties hereto.
ARTICLE IV
PAYMENTS IN LIEU OF TAXES
Section 4.1 Negotiated Payments.
(a) Pursuant to Section 12- 44-50 of the Act, the Company is required to make
payments in lieu of ad valorem taxes to the County with respect to the Economic Development Property.
Inasmuch as the Company anticipates an initial investment of sums sufficient for the Project to qualify for
a fee in lieu of tax arrangement under the Act, the County and the Company have negotiated the amount of
the FILOT Payments in accordance therewith. The Company shall make FILOT Payments on all Economic
Development Property which comprises the Project and is placed in service, as follows: the Company shall
make FILOT Payments during the Exemption Period with respect to the Economic Development Property
or, if there are Phases of the Economic Development Property, with respect to each Phase of the Economic
Development Property, said payments to be made annually and to be due and payable and subject to penalty
assessments on the same dates and in the same manner as prescribed by the County for ad valorem taxes.
The determination of the amount of such annual FILOT Payments shall be in accordance with the following
procedure (subject, in any event, to the procedures that the Act requires):
Step 1: Determine the fair market value of the Economic Development Property (or
Phase of the Economic Development Property) placed in service during the
Exemption Period using original income tax basis for State income tax
purposes for any Real Property and Improvements without regard to
depreciation (provided, the fair market value of real property, as the Act
defines such term, that the Company obtains by construction or purchase in an
arms-length transaction is equal to t he original income tax basis, and
8
otherwise, the determination of the fair market value is by appraisal) and
original income tax basis for State income tax purposes for any personal
property less depreciation for each year allowable for property tax purpos es,
except that no extraordinary obsolescence shall be allowable. The fair market
value of the Real Property for the first year of the Fee Term remains the fair
market value of the Real Property for the life of the Fee Term. The
determination of these valu es shall take into account all applicable property
tax exemptions that State law would allow to the Company if the property were
taxable, except those exemptions that Section 12 -44-50(A)(2) of the Act
specifically disallows.
Step 2: Apply an assessment ratio of six percent (6%) to the fair market value in Step
1 to establish the taxable value of the Economic Development Property (or
each Phase of the Economic Development Property) in the year it is placed in
service and in each of the 29 years thereafter or such longer period of years in
which the Act permits the Company to make annual fee payments.
Step 3: Use a fixed millage rate equal to the lowest millage rate permissible under the
Act, which the parties mutually understand to be the millage rate in effe ct on
June 30, 2023, which is 214.9 mills, as Section 12-44-50(A)(1)(d) of the Act
provides, during the Exemption Period against the taxable value to determine
the amount of the Payments in Lieu of Taxes due during the Exemption Period
on the payment dates that the County prescribes for such payments or such
longer period of years in which the Act permits the Company to make annual
fee payments.
(b) The FILOT Payments shall be in lieu of all ad valorem tax payments and any other
charges that would have appeared on the property tax bills otherwise generated by the County in the absence
of this Fee Agreement.
In the event that a final order of a court of competent jurisdiction or an agreement of the parties
determines that the calculation of the minimum FILOT Payment applicable to this transaction is to be other
than by the procedure herein, the payment shall be reset at the minimum permitted level so determined.
Subject to Section 6.8 hereof, in the event that a final order of a court of competent jurisdiction
from which no further appeal is allowable declares the Act and/or the herein -described Payments in Lieu
of Taxes invalid or unenforceable, in whole or in part, for any reason, the parties express their intentions to
reform such payments so as to effectuate m ost closely the intent hereof and so as to afford the Company
with the benefits to be derived herefrom, the intention of the County being to offer the Company a strong
inducement to locate the Project in the County. If the Economic Development Property is deemed to be
subject to ad valorem taxation, this Fee Agreement shall terminate, and the Company shall pay the County
regular ad valorem taxes from the date of termination, but with appropriate reductions equivalent to all tax
exemptions which are afforded to the Company. Any amount determined to be due and owing to the County
from the Company, with respect to a year or years for which the Company previously remitted Payments
in Lieu of Taxes to the County hereunder, shall (i) take into account all applicable tax exemptions to which
the Company would be entitled if the Economic Development Property was not and had not been Economic
Development Property under the Act; and (ii) be reduced by the total amount of Payments in Lieu of Taxes
the Company had made with respect to the Project pursuant to the terms hereof. Notwithstanding anything
contained herein to the contrary, neither the Company nor any successor in title or interest shall be required
to pay FILOT payments and ad valorem taxes for the same property over the same period in question.
(c) The County agrees that all qualifying capital expenses of the Company during the
Investment Period shall qualify for a seven-year, 50% Infrastructure Credit. The Company shall receive an
annual credit in an amount equal t o 50% of the FILOT revenues for the Project to offset the aggregate
9
Infrastructure costs incurred for the first seven FILOT Payments hereunder. The Infrastructure Credit shall
be applied as a setoff against the FILOT owed for the then current year.
To claim each Infrastructure Credit, the Sponsor shall file with the County Administrator, the County
Auditor, and the County Treasurer, no later than the date on which the FILOT Payment is due in each year
in which the Sponsor is entitled to claim a n Infrast ructure Credit, an Annual Infrastructure Credit
Certificate, the form of which is attached as Exhibit C (the “Certification”), showing the amount of
aggregate investment in qualifying infrastructure and the calculation of the Infrastructure Credit. Failure to
timely file the Certification shall not result in a forfeiture of the Infrastructure Credit for such year, but the
County will not deduct the Infrastructure Credit from the FILOT bill until the Certification is submitted by
the Sponsor, provided, further, however, failure to file the Certification on or before the close of the
County’s then-current fiscal year shall result in the forfeiture of the Infrastructure Credit for such year. The
County is entitled to confirm the information (including the calcu lation) on the Certification prior to
deducting the amount of the Infrastructure Credit from the FILOT payment due by the Sponsor on the
FILOT bill. If the information contained on the Certification is correct, then the County shall deduct the
Infrastructure Credit amount from the FILOT bill. In no event is the County required to deduct any
Infrastructure Credit amount from the FILOT bill while any of the Sponsor’s taxes or FILOT Payments
have been invoiced by the County but remain outstanding, including for any taxes or FILOT Payments that
may have been protested by the Sponsor.
Section 4.2 Failure to Achieve Act Minimum Investment Requirement ; Failure to Achieve
Clawback Minimum Requirements.
(a) In the event that the cost of the Economic Development Property (without regard
to depreciation) that the Company acquires does not reach the Act Minimum Investment Requirement by
the end of the Investment Period, this Fee Agreement shall terminate as to such entity failing to meet the
minimum investment level. In such event, the Company shall pay the County an amount (the “Additional
Payment”) pursuant to the Act which is equal to the excess, if any, of (i) the total amount of ad valorem
taxes as would result from taxes levied on the Project by the County, municipality or municipalities, school
district or school districts, and other political units as if the items of property comprising the Economic
Development Property were not Economic Development Property, but with appropriate reductions
equivalent to all tax exempt ions and abatements to which the Company would be entitled in such a case,
through and including the end of the Investment Period, over (ii) the total amount of FILOT payments the
Company has made with respect to the Economic Development Property through and including the end of
the Investment Period. Any amounts determined to be owing pursuant to the foregoing sentence shall be
subject to the minimum amount of interest that the Act may require.
(b) If the Company fails to achieve the Clawback Minimum Requirements by the end
of the Investment Period, the Infrastructure Credits shall be reduced retroactively and prospectively, as
follows:
Reduction Factor = 100% - Overall Achievement Percentage
Overall Achievement Percentage = (Investment Achievement Percentage + Jobs Achievement
Percentage) / 2
Investment Achievement Percentage = Maximum Capital Investment Achieved Within the
Investment Period / $12,650,000
Jobs Achievement Percentage = Maximum Jobs Created Within the Investment Period / 41
Repayment Amount = Infrastructure Credits Received x Reduction Factor
The Company shall pay the Repayment Amount within 60 days after the deadline for filing property tax
returns for the last year of the Investment Period. Any future Infrastructure Credits shall be reduced by the
10
Reduction Factor, provided that either the Company or the County may request a redetermination of the
Reduction Factor for any future Infrastructure Credits in any property tax year based on the capital
investment and jobs achieved as of the last day of the Company’s applicable fiscal year , subject to the
statutory interest if not paid when due pursuant to Section 12- 54-25 of the Code, and/or as otherwise
allowed under the FILOT Act.
(c) The remedies stated herein shall be the County’s sole remedies for the Company’s
failure to meet any required investment or job creation level.
Section 4.3 Payments in Lieu of Taxes on Replacement Property . If the Company elects to
replace any Removed Components and to substitute such Removed Components with Replacement
Property as a part of the Economic Development Property, or the Company otherwise utilizes Replacement
Property, then, pursuant, and subject to Section 12- 44-60 of the Act, the Company shall make statutory
payments in lieu of ad valorem taxes with regard to su ch Replacement Property in accordance with the
following:
(i) Replacement Property does not have to serve the same function as the
Economic Development Property it is replacing. Replacement Property is deemed
to replace the oldest Economic Development Property subject to the Fee, whether
real or personal, which is disposed of in the same property tax year in which the
Replacement Property is placed in service. Replacement Property qualifies as
Economic Development Property only to the extent of the original income tax basis
of Economic Development Property which is being disposed of in the same
property tax year. More than one piece of property can replace a single piece of
Economic Development Property. To the extent that the income tax basis of the
Replacement Property exceeds the original income tax basis of the Economic
Development Property which it is replacing, the excess amount is subject to annual
payments calculated as if the exemption for Economic Development Property were
not allowable. Replacement Property is entitled to treatment under the Fee
Agreement for the period of time remaining during the Exemption Period for the
Economic Development Property which it is replacing; and
(ii) The new Replacement Property which qualifies for the Fee shall be
recorded using its income tax basis, and the calculation of the Fee shall utilize the
millage rate and assessment ratio in effect with regard to the original property
subject to the Fee.
Section 4.4 Reductions in Payments of Taxes Upon Removal, Condemnation, or Casualty
. In
the event of a Diminution in Value of the Economic Development Property or any Phase of the Economic
Development Property, the Payment in Lieu of Taxes with regard to the Economic Development Property
or that Phase of the Economic Development Property shall be reduced in the same proportion as the amount
of such Diminution in Value bears to the original fair market value of the Economic Development Property
or that Phase of the Economic Development Property as determined pursuant to Step 1 of Secti on 4.1(a)
hereof; provided, however, that if at any time subsequent to the end of the Investment Period, the total value
of the Project based on the original income tax basis of the Equipment, Real Property, and Improvements
contained therein, without deduction for depreciation, is less than the Act Minimum Investment
Requirement, beginning with the first payment thereafter due hereunder and continuing until the end of the
Fee Term, the Company shall no longer be entitled to the incentive provided in Section 4.1, and the
Company shall therefore commence to pay regular ad valorem taxes on the Economic Development
Property part of the Project. However, the Company will not be required to make any retroactive payment
such as the Additional Payment under Section 4.2.
Section 4.5 Place of Payments in Lieu of Taxes. The Company shall make the above-described
Payments in Lieu of Taxes directly to the County in accordance with applicable law.
11
Section 4.6 Removal of Economic Development Property. Subject, always, to the other terms
and provisions hereof, the Company shall be entitled to remove and dispose of components or Phases of
the Project from the Project in its sole discretion with the result that said components or Phases shall no
longer be considered a part of the Project and, to the extent such constitute Economic Development
Property, shall no longer be subject to the terms of this Fee Agreement to the fullest extent allowed by the
Act, as amended. Economic Development Property is disposed of only when it is scrapped or sold, or it is
removed from the Project. If it is removed from the Project, it is subject to ad valorem property taxes to the
extent the Property remains in the State and is otherwise subject to ad valorem property taxes.
Section 4.7 Damage or Destruction of Economic Development Property.
(a) Election to Terminate . In the event the Economic Development Property is
damaged by fire, explosion, or any other casualty, the Company shall be entitled to terminate this Fee
Agreement. The Company shall only be required to make FILOT payments as to all or any part of the tax
year in which the damage or casualty occurs to the extent property subject to ad valorem taxes would
otherwise have been subject to such taxes under the same circumstances for the period in question.
(b) Election to Rebuild. In the event the Economic Development Property is damaged
by fire, explosion, or any other casualty, and if the Company does not elect to terminate this Fee Agreement,
the Company may commence to restore the Economic Development Property with such reductions or
enlargements in the scope of the Economic Development Property, changes, alterations, and modifications
(including the substitution and addition of other property) as may be desired by the Company. All such
restorations and replacements shall be consider ed, to the fullest extent permitted by law and this Fee
Agreement, substitutions of the destroyed portions of the Economic Development Property and shall be
considered part of the Economic Development Property for all purposes hereof, including, but not li mited
to, any amounts due by the Company to the County under Section 4.1 hereof.
(c) Election to Remove . In the event the Company elects not to terminate this Fee
Agreement pursuant to subsection (a) and elects not to rebuild pursuant to subsection (b), the da maged
portions of the Economic Development Property shall be treated as Removed Components.
Section 4.8 Condemnation.
(a) Complete Taking. If at any time during the Fee Term title to or temporary use of
the Economic Development Property should become vested in a public or quasi-public authority by virtue
of the exercise of a taking by condemnation, inverse condemnation, or the right of eminent domain; by
voluntary transfer under threat of such taking; or by a taking of title to a portion of the Economic
Development Property which renders continued use or occupancy of the Economic Development Property
commercially unfeasible in the judgment of the Company, the Company shall have the option to terminate
this Fee Agreement by sending written notice to the County within a reaso nable period of time following
such vesting.
(b) Partial Taking . In the event of a partial taking of the Economic Development
Property or a transfer in lieu thereof, the Company may elect: (i) to terminate this Fee Agreement; (ii)
subject to the Act and the terms and provisions of this Fee Agreement, to repair and restore the Economic
Development Property, with such reductions or enlargements in the scope of the Economic Development
Property, changes, alterations, and modifications (including the substitution and addition of other property)
as the Company may desire, and all such changes, alterations, and modifications shall be considered as
substitutions of the taken parts of the Economic Development Property; or (iii) to treat the portions of the
Economic Development Property so taken as Removed Components.
(c) The Company shall only be required to make FILOT payments as to all or any part
of the tax year in which the taking occurs to the extent property subject to ad valorem taxes would otherwise
have been subject to such taxes under the same circumstances for the period in question.
12
Section 4.9 Confidentiality/Limitation on Access to Project . The County acknowledges and
understands that the Company utilizes confidential and proprietary processes and materials, services,
equipment, trade secrets, and techniques (herein “Confidential Information”) and that any disclosure of
Confidential Information concerning the Company’s operations may result in substantial harm to the
Company and could thereby have a significant detrimental impact on the Company’s employees and also
upon the County. The Company acknowledges that the County is subject to the Freedom of Information
Act, and, as a result, must disclose certain documents and information on request absent an exemption. For
these reasons, the Company shall clearly label all Confidential Information it delivers to the County
“Confidential Information.” Therefore, the County agrees that, except as required by law, neither the
County nor any employee, agent, or contractor of the County shall (i) request or be entitled to receive any
such Confidential Information, or (ii) disclose or otherwise divulge any such Confidential Information to
any other person, firm, governmental body or agency, or any other entity unless specifically required to do
so by law; provided, however, that the County shall have no less rights concerning information relating to
the Project and the Company than concerning any other property or property taxpayer in the County, and,
provided further, that the confidentiality of such confidential or proprietary information is clearly disclosed
to the County in writing as previously described. Prior to disclosing any Confidential Information, subject
to the requirements of law, the Company may r equire the execution of reasonable, individual,
confidentiality and non-disclosure agreements by any officers, employees, or agents of the County or any
supporting or cooperating governmental agencies who would gather, receive, or review such information.
In the event that the County is required to disclose any Confidential Information obtained from the
Company to any third party, the County agrees to provide the Company with as much advance notice as
possible of such requirement before making such disclosure, and to cooperate reasonably with any attempts
by the Company to obtain judicial or other relief from such disclosure requirement.
Section 4.10 Assignment. If Section 12-44-120 of the Act or any successor provision requires
consent to an assignment, the Company may assign this Fee Agreement in whole or in part with the prior
written consent of the County or a subsequent written ratification by the County, which consent or
ratification the County will not unreasonably withhold. The Company agrees to notify the County and the
Department of the identity of such transferee within 60 days of the transfer. In case of a transfer, the
transferee assumes the transferor’s basis in the Project for purposes of calculating the Fee. No approval is
required for transfers to sponsor affiliates or other financing related transfers, as defined in the Act.
Section 4.11 No Double Payment; Future Changes in Legislation.
(a) Notwithstanding anything contained herein to the contrary, and except as expressly
required by law, neither the Company nor any Spons or shall ever be required to make a Payment in Lieu
of Taxes in addition to a regular property tax payment in the same year over the same piece of property,
nor shall the Company or any Sponsor be required to make a Payment in Lieu of Taxes on property in cases
where, absent this Fee Agreement, property taxes would otherwise not be due on such property.
In case there is any legislation enacted which provides for more favorable treatment for property to
qualify as, or for the calculation of the fee related to, Economic Development Property under Sections 4.4,
4.6, 4.7, 4.8, or the calculation of the Investment Period, the County agrees to give expedient and full
consideration to such legislation.
Section 4.12 Administration Expenses
. The Company agrees to pay the reasonable and
necessary expenses that the County incurs with respect to the execution and administration of this Fee
Agreement, including without limitation reasonable and actual attorneys’ fees (the “Administration
Expenses”); provided, however, that no such expense shall be an Administration Expense until the County
has furnished to the Company a statement in writing indicating the amount of such expense and the general
reason for its incurrence. As used in this section, “Administration Expenses” shall include the reasonable
and necessary expenses, including attorneys’ fees, incurred by the County with respect to: (i) this Fee
Agreement; (ii) all other documents related to this Fee Agreement and any related documents; and (iii) the
fulfillment of its obligations under this Fee Agreement and any related documents and the implementation
and administration of the terms and provisions of the documents after the date of execution thereof, but
13
only as a result of a request by the Company for a modification, ass ignment, or a termination of such
documents by the Company, or as a result of a bankruptcy of the Company or a default by the Company
under the terms of such documents. Reimbursement for the County’s attorneys’ fees shall be according to
the typical fee arrangement with the County, not to exceed $15,000, provided however, this limit does not
apply to Section 4.14 or Section 5.5 of this Fee Agreement.
Section 4.13 Execution of Lease. The parties acknowledge that the intent of this Fee Agreement
is to afford the Company the benefits of the FILOT Payments in consideration of the Company’s decision
to locate the Project within the County and that this Fee Agreement has been entered into in reliance upon
the validity and enforceability of the Act. In the event that a court of competent jurisdiction holds that the
Act is unconstitutional or that this Fee Agreement or agreements similar in nature to this Fee Agreement
are invalid or unenforceable in any material respect, or should the parties determine that there is a reasonable
doubt as to the validity or enforceability of this Fee Agreement in any material respect, then the County,
upon the provision by the Company of evidence acceptable to the County that the Project is free from
environmental contamination and the conveyance of title to the Project to the County at the expense of the
Company, agrees to lease the Project to the Company pursuant to the Streamlined FILOT Act and, to the
extent permitted under the law in effect at such time, use its best efforts to ensure that the Company receives
the benefits of the FILOT arrangement as contemplated by this Fee Agreement.
Section 4.14 Indemnification Covenants.
(a) Except as provided in paragraph (d) below, the Company shall indemnify and save the County,
its employees, elected officials, officers and agents (each, “Indemnified Party”) harmless against and
from all liability or claims arising from the County’s execution of this Fee Agreement, performance of
the County’s obligations under this Fee Agreement or the administration of its duties pursuant to this
Fee Agreement, or otherwise by virtue of the County having entered into this Fee Agreement
(collectively, “Losses”).
(b) Any Indemnified Party seeking to be indemnified hereunder shall promptly notify the Company
in writing of any claim that could reasonably be expected to result in Losses, specifying in reasonable
detail the nature of such Losses. The Indemnified Party shall provide to the Company as promptly a s
practicable thereafter all information and documentation reasonably requested by the Company to
verify the Losses asserted. Upon the Company’s receipt of any notice of a claim pursuant to this Section
4.14, the Company may, by giving written notice to the Indemnified Party within 15 days following
such notice, elect to assume the defense thereof, including the employment of counsel at the Company’s
cost to carry out such defense; provided, that if the Indem nified Party is the County, in the event the
County reasonably believes there are defenses available to it that are not being pursued or that the
counsel engaged by the Company reasonably determines that a conflict of interest exists between the
County and the Company, the County may, in its reasonable discretion, hire independent counsel to
assume such defense, and the Company shall be liable for the reasonable cost of such counsel. Whether
or not the Company chooses to defend such claim, all the parties hereto shall cooperate in the defense
thereof and shall furnish such records, information and testimony and shall attend such conferences,
discovery proceedings and trials as may be reasonably requested in connection therewith. The Company
shall not be entitled to settle any such claim without the prior written consent of the Indemnified Party,
which consent shall not be unreasonably withheld, conditioned or delayed. In the event that the
Company does not elect to assume the defense of such claim pursuant to this Section 4.14, the
Indemnified Party shall not settle any such claim without the prior written consent of the Company,
which consent shall not be unreasonably withheld, conditioned or delayed.
(c) Notwithstanding anything in this Fee Agreement to the contrary, the Company is not required
to indemnify any Indemnified Party against or reimburse the County for Losses or any other amounts
due under this Section 4.14: (i) occasioned by the acts of that Indemnified Party, which are unrelated
to the execution of this Fee Agreement, performance of the County’s obligations under this Fee
Agreement, or the administration of its duties under this Fee Agreement, or otherwise by virtue of the
County having entered into this Fee Agreement; or (ii) to the extent that such Losses result from any
14
Indemnified Party’s negligence, bad faith, fraud, deceit, breach of this Fee Agreement or willful
misconduct.
(d) An Indemnified Party may not avail itself of the indemnification or reimbursement of costs
provided in this Section 4.14 unless it provides the Company with prompt notice, reasonable under the
circumstances, of the existence or threat of any claim or liability, including, without limitation, copies
of any citations, orders, fines, charges, remediation requests, or other claims or threats of claims, to
afford the Company notice, reasonable under the circumstances, within which to defend or otherwise
respond to a claim.
The indemnity specified in this Section 4.14 shall survive the termination of this Fee Agreement
with respect to liability arising out of any event or act occurring prior to such termination.
(e) The County is entitled to use counsel of its choice and the Company shall, reimburse the County
for all of its costs, including attorneys’ fees, incurred in conne ction with the response to or defense
against such liability or claims as described in paragraph (a), above. The County shall provide a
statement of the costs incurred in the response or defense, and the Company shall pay the County within
30 days of receipt of the statement. The Company may request reasonable documentation evidencing
the costs shown on the statement. However, the County is not required to provide any documentation
which may be privileged or confidential to evidence the costs.
ARTICLE V
DEFAULT
Section 5.1 Events of Default . The following shall be “Events of Default” under this Fee
Agreement, and the term “Events of Default” shall mean, whenever used with reference to this Fee
Agreement, any one or more of the following occurrences:
(a) Failure by the Company to ma ke the Payments in Lieu of Taxes described in
Section 4.1 hereof , which failure shall not have been cured within 30 days following receipt of written
notice thereof from the County ; provided, however, that the Company shall be entitled to all redemption
rights granted by applicable statutes; or
(b) A representation or warranty made by the Company which is deemed materially
incorrect when deemed made; or
(c) Failure by the Company to perform any of the terms, conditions, obligations, or
covenants hereunder (other than those under (a) above), which failure shall continue for a period of 30 days
after written notice from the County to the Company specifying such failure and requesting that it be
remedied, unless the Company shall have instituted corrective act ion within such time period and is
diligently pursuing such action until the default is corrected, in which case the 30- day period shall be
extended to cover such additional period during which the Company is diligently pursuing corrective action;
or
(d) A rep resentation or warranty made by the County which is deemed materially
incorrect when deemed made; or
(e) Failure by the County to perform any of the terms, conditions, obligations, or
covenants hereunder, which failure shall continue for a period of 30 days af ter written notice from the
Company to the County specifying such failure and requesting that it be remedied, unless the County shall
have instituted corrective action within such time period and is diligently pursuing such action until the
default is corr ected, in which case the 30 -day period shall be extended to cover such additional period
during which the County is diligently pursuing corrective action.
15
Section 5.2 Remedies on Default.
(a) Whenever any Event of Default by the Company shall have occurred and shall be
continuing, the County may take any one or more of the following remedial actions:
(i) terminate the Fee Agreement , upon 30 days’ notice to the Company and
any Sponsor (which notice period shall not be applicable in the case of the failure
to make any payments due under this Fee Agreement); or
(ii) take whatever action at law or in equity may appear necessary or desirable
to collect the amounts due hereunder. In no event shall the Company be liable to
the County or otherwise for monetary damages resulting from the Company’s
failure to meet the Act Minimum Investment Requirement, other than as expressly
set forth herein.
(b) Whenever any Event of Default by the County shall have occurred or shall be
continuing, the Company may take one or more of the following actions:
(i) bring an action for specific enforcement;
(ii) take whatever action at law or in equity may appear necessary or desirable
to collect the amounts due hereunder.
Section 5.3 Additional Collect ion and Enforcement Rights of County
. The parties
acknowledge that, as provided in Section 12-44-90 of the Code, the County’s right to receive payments in
lieu of taxes hereunder shall be the same as its rights conferred under Title 12 of the Code relating to the
collection and enforcement of ad valorem property taxes and, for purposes of this application, payments in
lieu of taxes due hereunder shall be considered a property tax.
Section 5.4 Remedies Not Exclusive. No remedy conferred upon or reserved to the County or
the Company under this Fee Agreement is intended to be exclusive of any other avail able remedy or
remedies, but each and every remedy shall be cumulative and shall be in addition to every other lawful
remedy now or hereafter existing. No delay or omission to exercise any right or power accruing upon any
continuing default hereunder shall impair any such right or power or shall be construed to be a waiver
thereof, but any such right and power may be exercised from time to time and as often as may be deemed
expedient.
Section 5.5 Reimbursement of Legal Fees and Expenses and Other Expenses . Upon the
occurrence of an Event of Default hereunder, should a party be required to employ attorneys or incur other
reasonable expenses for the collection of payments due hereunder or for the enforcement of performance
or observance of any obligation or agreement, the successful party shall be entitled, within 30 days of
demand therefor, to reimbursement of the reasonable fees of such attorneys and such other reasonable
expenses so incurred.
ARTICLE VI
MISCELLANEOUS
Section 6.1 Notices. Any notice, election, demand, request, or other co mmunication to be
provided under this Fee Agreement shall be effective when delivered to the party named below or when
deposited with the United States Postal Service, certified mail, return receipt requested, postage prepaid,
addressed as follows (or addr essed to such other address as any party shall have previously furnished in
writing to the other party), except where the terms hereof require receipt rather than sending of any notice,
in which case such provision shall control:
16
IF TO THE COMPANY:
[Project Shaker]
Attn: ___________
________________
________________
WITH A COPY TO (which shall not constitute notice):
Haynsworth Sinkler Boyd, P.A.
Attn: Katherine Busbee
P.O. Box 2048
Greenville, SC 29602
IF TO THE COUNTY:
Oconee County, South Carolina
Attn: County Administrator
415 S. Pine Street
Walhalla, SC 29691
WITH A COPY TO (which shall not constitute notice):
King Kozlarek Root Law LLC
Attn: David A. Root
Post Office Box 565
Greenville, South Carolina 29602-0565
AND
King Kozlarek Root Law LLC
Attn: Michael E Kozlarek
Post Office Box 565
Greenville, South Carolina 29602-0565
Section 6.2 Binding Effect
. This Fee Agreement and each document contemplated hereby or
related hereto shall be binding upon and inure to the benefit of the Company, the County, and their
respective successors and assigns. In the event of the dissolution of the County or the consolidation of any
part of the County with any other political subdivision or the transfer of any rights of the County to any
other such political subdivision, all of the covenants, stipulations, promises, and agreements of this Fee
Agreement shall bind and inure to the benefit of the successors of the County from time to time and any
entity, officer, board, commission, agency, or instrum entality to whom or to which any power or duty of
the County has been transferred.
Section 6.3 Counterparts. This Fee Agreement may be executed in any number of counterparts,
and all of the counterparts taken together shall be deemed to constitute one and the same instrument.
Section 6.4 Governing Law. This Fee Agreement and all documents executed in connection
herewith shall be construed in accordance with and governed by the laws of the State of South Carolina.
Section 6.5 Headings. The headings of the articles and sections of this Fee Agreement are
inserted for convenience only and shall not be deemed to constitute a part of this Fee Agreement.
17
Section 6.6 Amendments. The provisions of this Fee Agreement may only be modified or
amended in writing by any agreement, or agreements entered into between the parties.
Section 6.7 Further Assurance. From time to time, and at the expense of the Company, to the
extent any expense is incurred, the County agrees to execute and deliver to the Company such additional
instruments as the Comp any may reasonably request and as are authorized by law and reasonably within
the purposes and scope of the Act and Fee Agreement to effectuate the purposes of this Fee Agreement.
Section 6.8 Invalidity; Change in Laws. In the event that the inclusion of property as Economic
Development Property or any other issue is unclear under this Fee Agreement, the County hereby expresses
its intention that the interpretation of this Fee Agreement shall be in a manner that provides for the broadest
inclusion of property under the terms of this Fee Agreement and the most commensurate incentive
permissible under the Act, to the extent not inconsistent with any of the explicit terms hereof. If any
provision of this Fee Agreement is declared illegal, invalid, or unenforceable for any reason, the remaining
provisions hereof shall be unimpaired, and such illegal, invalid, or unenforceable provision shall be
reformed to effectuate most closely the legal, valid, and enforceable intent thereof and so as to afford the
Company with the benefits to be derived herefrom, it being the intention of the County to offer the Company
the strongest inducement possible, within the provisions of the Act, to locate the Project in the County. In
case a change in the Act or South Carolina laws eliminates or reduces any of the restrictions or limitations
applicable to the Company and the Fee incentive, the parties agree that the County will give expedient and
full consideration to reformation of this Fee Agreement, with a view toward providing the Company with
the benefits of such change in the Act or South Carolina laws.
The County agrees that in case the FILOT incentive described herein is found to be invalid or otherwise
does not provide the Company with the economic benefit it is intended to receive from the County as an
inducement to locate in the County, the savings lost as a result of such invalidity will be considered a special
source revenue credit or infrastructure improvement credit to the Company (in addition to the Infrastructure
Credit explicitly provided for above) to the maximum extent permitted by law, and the County will provide
a special source revenue credit or infrastructure improvement credit against all FILOT payments or fee
payments made or to be made by the Company equal to the amount that the Company would have saved if
the FILOT had been valid, to the maximum extent permitted by law.
Section 6.9 Force Majeure
. The Company shall not be responsible for any delays or non-
performance caused in whole or in part, directly or indirectly, by strikes, accidents, freight embargoes, fires,
floods, inability to obtain materials, conditions arising from governmental orders or regulations, war, or
national emergency, acts of God, and any other cause, similar or dissimilar, beyond the Company’s
reasonable control , provided, however, this Section 6.9 shall not apply to any payment(s) due by the
Company to the County under this Fee Agreement.
Section 6.10 Termination by Company . The Company is authorized to terminate this Fee
Agreement at any time with respect to all or part of the Project upon providing the County with written
notice of termination, and such termination shall be effective as of the date determined by the Company ;
provided, however, that (i) any monetary obligations existing hereunder and due and owing at the time of
termination to a party hereto; and (ii) any provisions which are intended to survive termination, shall survive
such termination. In the year following the effective date of termination, all property shall be subject to ad
valorem taxation or such other taxation or fee in lieu of taxation that would apply absent this Fee
Agreement. The Company’s obligation to make fee in lieu of tax payments under this Fee Agreement shall
terminate in the year following the effective date of such termination pursuant to this section.
Section 6.11 Entire Understanding. This Fee Agreement expresses the entire understanding and
all agreements of the parties hereto with each other with respect to its subject matter , and neither party
hereto has made or shall be bound by any agreement or any representation to the other party which is not
expressly set forth in this Fee Agreement or in certificates delivered in connection with the execution and
delivery hereof.
18
Section 6.12 Waiver. Either party may waive compliance by the other party with a ny term or
condition of this Fee Agreement only in a writing signed by the waiving party.
Section 6.13 Business Day. In the event that any action, payment, or notice is, by the terms of
this Fee Agreement, required to be taken, made, or given on any day which is a Saturday, Sunday, or legal
holiday in the jurisdiction in which the person obligated to act is domiciled, such action, payment, or notice
may be taken, made, or given on the following business day with the same effect as if given as required
hereby, and no interest shall accrue in the interim.
Section 6.14 Limitation of Liability . Anything herein to the contrary notwithstanding, any
financial obligation the County may incur hereunder, including for the payment of money, shall not be
deemed to constitute a pecuniary liability or a debt or general obligation of the County; provided, however,
that nothing herein shall prevent the Company from enforcing its rights hereunder by suit for mandamus or
specific performance.
Section 6.15 State Law Considerations. The authorization, execution, and delivery of this Fee
Agreement, and any obligations of the County under this Fee Agreement, are subject to any law that may
relate to the FILOT Payments or Infrastructure Credit
, or both, and State law generally. This Fee Agreement
and any obligations of t he County under this Fee Agreement are not intended to violate State law in any
respect.
[ONE SIGNATURE PAGE AND ONE EXHIBIT FOLLOW]
[REMAINDER OF PAGE SUBSTANTIVELY BLANK]
19
IN WITNESS WHEREOF, the County, acting by and through the County Council, has caused this
Fee Agreement to be executed in its name and behalf by the County Administrator or County Council
Chairman and to be attested by the Clerk of the County Council; and the Company has caused this Fee
Agreement to be executed by its duly authorized officer, all as of the day and year first above written.
OCONEE COUNTY,
SOUTH CAROLINA
Signature:
Name:
Title:
ATTEST:
Signature:
Name:
Title: Clerk to County Council
[PROJECT SHAKER]
Signature:
Name:
Title:
20
EXHIBIT A
LEGAL DESCRIPTION
[To come.]
[TMS No. to come]
21
EXHIBIT B
FORM OF JOINDER AGREEMENT
JOINDER AGREEMENT
Reference is hereby made to the Fee Agreement, effective [________] , 2024 ( “Fee Agreement”),
between Oconee County, South Carolina (“County”), and [Project Shaker] (collectively, with any Sponsor
Affiliate, “Sponsor”).
1. Joinder to Fee Agreement. [], a [state] [corporation/limited liability company/limited partnership]
authorized to conduct business in the State, hereby (a) joins as a party to, and agrees to be bound by and
subject to all of the terms and conditions of, the Fee Agreement as if it were a Sponsor; (b) shall receive the
benefits as provided under the Fee Agreement with respect to the Economic Development Property placed
in service by the [Sponsor] [Affiliate] as if it were a Sponsor; (c) acknowledges and agrees that (i) according
to the Fee Agreement, the undersigned has been designated as a [ Sponsor] [Affiliate] by the Sponsor for
purposes of the Project; (ii) the undersigned qualifies or will qualify as a [Sponsor] [Affiliate] under the
Fee Agreement and Section 12-44-30(20) and Section 12-44-130 of the Act; and (iii) agrees that electronic
signatures, whether digital or encrypted, of the parties to this Joinder Agreement are intended to authenticate
this writing and to have the same force and effect as manual signatures. Electronic signature means any
electronic sound, symbol, or process attached to or logistically associated with a record and executed and
adopted by a party with the intent to sign such record, including facsimile or email signatures.
2. Capitalized Terms. Each capitalized term used, but not defined, in this Joinder Agreement has the
meaning of that term set forth in the Fee Agreement.
3. Representations of the [Sponsor] [Affiliate]. The [Sponsor] [Affiliate] represents and warrants to
the County as follows:
1. The [Sponsor] [Affiliate] is in good standing under the laws of the state of its
organization, is duly authorized to transact business in the State (or will obtain such authority prior
to commencing business in the State), has power to enter into this Joinder Agreement, and has duly
authorized the execution and delivery of this Joinder Agreement.
2. The [Sponsor] [Affiliate]’s execution and delivery of this Joinder Agreement, and
its compliance with the provisions of this Joinder Agreement, do not result in a default, not waived,
or cured, under any agreement or instrument to which the [ Sponsor] [Affiliate] is now a party or
by which it is bound.
3. The execution and delivery of this Joinder Agreement and the a vailability of the
FILOT and other incentives provided by this Joinder Agreement has been instrumental in inducing
the [Sponsor] [Affiliate] to join with the original Sponsor in the Project in the County.
4. Request of [ Sponsor] [Affiliate]. The [Sponsor] [Affiliate] hereby requests and consents to its
addition, as a “[sponsor] [affiliate]” to the Fee Agreement.
5. Request of Sponsor. The original Sponsor hereby requests and consents to the addition of [] as a
“[sponsor] [affiliate]” to the Fee Agreement.
6. Governing Law. This Joinder Agreement is governed by and construed according to the laws,
without regard to principles of choice of law, of the State.
7. Notice. Notices under Section 6.1 of the Fee Agreement shall be sent to the [Sponsor] [Affiliate] at:
[ ]
22
IN WITNESS WHEREOF, the Sponsor requests and consents to the County’s consenting to the addition
of the above-named entity as a Sponsor Affiliate under the Fee Agreement effective as of the date set
forth below.
Date: _______________________ [PROJECT SHAKER]
By:
Its:
IN WITNESS WHEREOF, the undersigned has executed this Joinder Agreement to be effective as of
the date set forth above.
[NAME OF ADDITIONAL
SPONSOR/SPONSOR AFFILIATE]
By:
Its:
IN WITNESS WHEREOF, at the Sponsor’s and the Sponsor Affiliate’s request, the County
acknowledges it has consented to the addition of the above -named entity as a Sponsor Affiliate under the
Fee Agreement effective as of the date set forth above.
OCONEE COUNTY, SOUTH CAROLINA
By:
[Name], Chairman
Oconee County Council
[SEAL]
23
EXHIBIT C
FORM OF ANNUAL INFRASTRUCTURE CREDIT CERTIFICATE
ANNUAL INFRASTRUCTURE CREDIT CERTIFICATE
Reference is hereby made to the Fee Agreement, effective [_______] , 2024 ( “Fee Agreement” ),
between Oconee County, South Carolina ( “County”), and [_____________] (collectively, with any
Sponsor Affiliate, “ Sponsor”). Each capitalized term used in this Cert ificate, but not defined in this
Certificate has the meaning ascribed to that term in the Fee Agreement.
According to Section 4.1 of the Fee Agreement, the undersigned authorized officer of the Sponsor
certifies to the County as follows:
1. The Sponsor is entitled to claim an Infrastructure Credit (“Credit”) against each FILOT Payment, on
or before the date after which ad valorem taxes become delinquent in which a FILOT Payment is due with
respect to the Project, as follows: The Credit commences with the property tax year after the year in which
the first Phase of the Project is placed in service and shall remain effective and wil l be a 50 % Credit for
years one (1) through seven (7).
2. The Sponsor expended, in aggregate, $___________________________ in Qualifying Infrastructure
Costs in the Project.
3. The Sponsor is entitled to a Credit for this tax year, calculated as follows:
FILOT Payment x 50% (years 1 through 7); = $____________________________
4. The total amount that the Sponsor is entitled to deduct and that the County will deduct from the
FILOT Payment, is: $________________________________.
5. The Credit specified in this Certificate for the current property tax year, together with the amount of
all Credits previously claimed pursuant to the Fee Agreement, do not, in the aggregate, exceed the total cost
of all infrastructure improvements funded by the Sponsor for which a Credit is permitted under the Act.
IN WITNESS WHEREOF, I have executed this Certificate as of ______________________.
[PROJECT SHAKER]
Signature:
Name:
Title:
2025-08
STATE OF SOUTH CAROLINA
COUNTY OF OCONEE
ORDINANCE 2025-08
AN ORDINANCE AMENDING CHAPTER 38 OF THE
OCONEE COUNTY CODE OF ORDINANCES, IN CERTAIN
LIMITED REGARDS AND PARTICULARS ONLY, WITH
RESPECT TO ALLOWING RETAINING WALLS AND
THEIR APPURTENANCES TO BE LOCATED IN LOT
SETBACK AREAS ; AND OTHER MATTERS RELATED
THERETO.
WHEREAS, consistent with the powers granted county governments by S.C. Code § 4-9-
25 and S.C. Code § 4-9-30, Oconee County (“County”), a body politic and corporate and a political
subdivision of the State of South Carolina, acting by and through its governing body, the Oconee
County Council (“County Council”), has the authority to enact regulations, resolutions, and
ordinances, not inconsistent with the Constitution and the general law of the State of South
Carolina, including the exercise of such powers in relation to health and order within its boundaries
and respecting any subject as appears to it necessary and proper for the security, general welfare,
and convenience of the County or for preserving health, peace, order, and good government
therein;
WHEREAS, t he County has adopted multiple ordinances for the effective, efficient
governance of the County, which, subsequent to adoption, are codified in the Oconee County Code
of Ordinances (“Code of Ordinances”), as amended;
WHEREAS, the County is authorized by Section 4 -9-30(9) and Chapter 29 of Title 6 of
the South Carolina Code of Laws, among other sources, to impose land use standards in the
unincorporated areas of the County;
WHEREAS, County Council recognizes that there is a need to revise the law of the County
to meet the changing needs of the County and that there is a need to amend, specifically, Chapter
38 of the Code of Ordinances by allowing for retaining walls and their appurtenances to be located
in the setback areas prescribed in the Code of Ordinances;
WHEREAS, the Oconee County Planning Commission has recommended that Chapter 38
of the Code of Ordinances be revised to allow for retaining walls and their appurtenances to be
located in the setback areas prescribed in the Code of Ordinances. (See E xhibit A , attached
hereto.); and
WHEREAS, County Council has therefore determined to modify Chapter 38 of the Code
of Ordinances and to affirm and preserve all other provisions of the Code of Ordinances not
specifically, or by implication, amended hereby.
2025-08
NOW THEREFORE, it is hereby ordained by the Oconee County Council, in meeting
duly assembled, that:
1. Section 38-9.3(2)(j), Chapter 38 of the Code of Ordinances, entitled “Dimensional
requirements: General provisions and exceptions ” is hereby revised, rewritten, and
amended to read as follows:
Steps and heating and cooling units may project into a required yard a distance not
to exceed five feet but no closer than five feet of a property line. Fences,
freestanding walls, retaining walls and appurtenances, hedges, and septic lines may
be located in any setback, so long as they remain on the property.
2. All other parts and provisions of the Oconee County Code of Ordinances not amended
hereby, either explicitly or by implication, remain in full force.
3. Should any part or provision of this Ordinanc e be deemed unconstitutional or
unenforceable by any court of competent jurisdiction, such determination shall not affect
the remainder of this Ordinance, all of which is hereby deemed separable.
4. All ordinances, orders, resolutions, and actions of County Council inconsistent herewith
are, to the extent of such inconsistency only, hereby repealed, revoked, and rescinded.
5. This Ordinance shall take effect and be in full force from and after third reading and
enactment by County Council.
ORDAINED in meeting, duly assembled, this ______ day of _________________, 2025.
ATTEST:
______________________________ _______________________________
Jennifer C. Adams Matthew Durham
Clerk to Oconee County Council Chair, Oconee County Council
First Reading: April 1, 2025
Second Reading: April 15, 2025
Public Hearing: May 6, 2025
Third Reading: May 6, 2025
2025-08
Exhibit A
[See attached]
OCONEE COUNTY
PLANNING COMMISSION
415 S. Pine St. Room 212 | Walhalla, SC 29691
864.638.4218
OconeeSC.com
Rev. 09/2023
Date: March 4, 2025
To: Oconee County Council Chairman Matthew Durham
From: James Coley via Planning Commission
Re: Recommendation on an amendment to Chapter 38 Sec. 38-9.3(2)j
• By a vote of 6-0 the Oconee County Planning Commission DOES recommend adding
retaining walls and appurtenances to Chapter 38 Sec 38-9.3(2)j
Background:
• The Planning Commission met on Monday, March 3, 2025, to discuss including retaining
walls in the exempted items from setback requirements.
• Current language:
Steps and heating and cooling units may project into a required yard a distance not to
exceed five feet but no closer than five feet of a property line. Fences, freestanding
walls, hedges, and septic lines may be located in any setback, so long as they rem ain
on the property.
• Proposed language:
• Steps and heating and cooling units may project into a required yard a distance not to
exceed five feet but no closer than five feet of a property line. Fences, freestanding
walls, retaining walls and appurtenances , hedges, and septic lines may be located in
any setback, so long as they remain on the property.
• The Planning Commission voted on a motion to recommend the amendment 6-0
2024-09
STATE OF SOUTH CAROLINA
COUNTY OF OCONEE
ORDINANCE 2025-09
AN ORDINANCE TO REZONE PARCEL S 111-24-01-001 AND 111- 24-01-
010 SUCH THAT THEY WILL LIE COMPLETELY WITHIN THE
COMMUNITY COMMERCIAL DISTRICT , PURSUANT TO OCONEE
COUNTY CODE OF ORDINANCES CHAPTER 38, ARTICLE 8.
WHEREAS, Oconee County, South Carolina (“County”), a body politic and corporate and a political
subdivision of the State of South Carolina, acting by and through its County Council (“C ounty Council”), is
authorized by the South Carolina Local Government Comprehensive Planning Enabling Act of 1994 (the “Act”),
codified in Title 6, Chapter 29 of the South Carolina Code of Laws, to adopt zoning regulations and districts;
WHEREAS, Oconee County Council has enacted zoning regulations and established districts, now codified
in Chapter 38 of the Oconee Code of Ordinances (“O.C. Code”);
WHEREAS, through prior lot divisions and mergers, parcels identified by tax map numbers 111-24-01-001
and 111-24-01-010 are currently zoned in both the Lake Residential District and the Community Commercial
District;
WHEREAS, consistent with Section 38- 8 of the O.C. Code , a petition to rezone parcels identified by tax
map numbers 111- 24-01-001 and 111-24-01-010, such that they will be located fully within the Community
Commercial District, was presented to the Oconee County Planning Commission for review and recommendation.
(See petition attached hereto as Exhibit A.);
WHEREAS, the Oconee County Planning Commission reviewed the petition and recommended that County
Council approve the request. (See Planning Commission recommendation attached hereto as Exhibit B.); and
WHEREAS, County Council has considered the recommendation of the Oconee County Planning
Commission, held a duly noticed and advertised public hearing, and hereby approves the recommendation to
rezone the parcel s currently identified by tax map number s 111-24-01-001 and 111-24-01-010 such that the
parcels will be located fully within the Community Commercial District.
NOW, THEREFORE, it is hereby ordained by the Oconee County Council, in meeting duly assembled that:
1. The parcels currently identified by tax map numbers 111-24-01-001 and 111-24-01-010, previously zoned
in both the Lake Residential District and the Community Commercial District and duly identified on the
Official Zoning Map to be in said districts , are hereby rezoned such that they lie completely within the
Community Commercial District, and shall be shown as such on the Official Zoning Map in the manner
depicted on Exhibit C to this Ordinance. The parcels, and associated uses and activities conducted
thereupon, shall be subject to all standards, limitations, and requirements established for the Community
Commercial District in Chapter 38 of the O.C. Code.
2. All other parts and provisions of the Oconee County Code of Ordinances not amended hereby, either
explicitly or by implication, remain in full force.
3. Should any part or provision of this Ordinance be deemed unconstitutional or unenforceable by any court
of competent jurisdiction, such determination shall not affect the remainder of this Ordinance, all of which
is hereby deemed separable.
4. All ordinances, orders, resolutions, and actions of Oconee County Council inconsis tent herewith are, to
the extent of such inconsistency only, hereby repealed, revoked, and rescinded.
2024-09
5. This Ordinance shall take effect and be in full force from and after third reading and enactment by Oconee
County Council.
ORDAINED in meeting, duly assembled, this ______ day of _________________, 2025.
ATTEST:
______________________________ _______________________________
Jennifer C. Adams Matthew Durham
Clerk to Oconee County Council Chair, Oconee County Council
First Reading: April 1, 2025
Second Reading: April 15, 2025
Public Hearing: May 6, 2025
Third Reading: May 6, 2025
2024-09
EXHIBIT A
Attached
2024-09
EXHIBIT B
Attached
2024-09
EXHIBIT C
Attached
OCONEE COUNTY
PLANNING COMMISSION
415 S. Pine St. Room 212 | Walhalla, SC 29691
864.638.4218
OconeeSC.com
Rev. 09/2023
Date: March 4, 2025
To: Oconee County Council Chairman Matthew Durham
From: James Coley via Planning Commission
Re: Recommendation to rezone parcels 111-24-01-010 and 111-24-01-001
• By a vote of 6-0 the Oconee County Planning Commission recommends rezoning of
parcels 111-24-01-010 and 111-24-01-001 from split zoning LRD (Lake Residential
District) and CCD (Community Commercial District) to fully in CCD.
Background:
• The Planning Commission met on Monday, March 3, 2025, to discuss the request to
rezone parcels 111-24-01-010 and 111-24-01-001 from split zoning LRD (Lake
Residential District) and CCD (Community Commercial District) to fully in CCD.
• Parcels 111-24-01-010 and 111-24-01-001 are split-zoned, with a portion of each parcel
in both LRD and CCD zoning. The split zoning occurred through multiple divisions and
combinations of the parcels. The owner would like to have both parcels in the same
zoning district as the other parcels within the commercial development.
• The Planning Commission voted on a motion to recommend the rezoning 6-0
0
-Roads
CZ] Lake Residential Zoning
.. Proposed Community Commercial District
c:::J Parcels
25 50
Feet
100
Exhibit C Proposed Rezoning
cco
N
A
OCSCGIS - 3.20.2025
This map is property of Oconee County Government.
This map ( or data product) was created by Oconee County South Carolina Geographic Information Systems Office (OCSCGIS)
and is solely intended to be used as a graphical representation. This map ( or data product) is not purposed to depict legal boundaries
or to identify the lawful owner or current legal status of the subject property. The maps and data distributed by OCSCGIS are derived
from a variety of public and private sector sources considered to be dependable, but the accuracy, completeness, and currency thereof
are not guaranteed. OCSCGIS makes no warranties, expressed or implied, as to the accuracy, completeness, cunency, reliability,
or suitability for any particular purpose of the information or data contained in or generated from OCSCGIS. The user acknowledges
and accepts all inherent limitations of the maps and data, including the fact that the maps and data are in a constant state of maintenance,
correction, and revision. The n'll!ps and associated data do not represent a survey and are not survey grade.
2025-10
STATE OF SOUTH CAROLINA
COUNTY OF OCONEE
ORDINANCE 2025-10
AN ORDINANCE AUTHORIZING THE EXECUTION AND
DELIVERY OF A REAL PROPERTY SUB LEASE
AGREEMENT BETWEEN THE WEST UNION
VOLUNTEER FIRE DEPARTMENT, AS SUBLESSOR, AND
OCONEE COUNTY, SOUTH CAROLINA, AS SUBLESSEE,
WITH THE APPROVAL AND CONSENT OF THE TOWN
OF WEST UNION AND TORRINGTON ROAD, LLC, AS
LESSORS, FOR CERTAIN REAL PROPERTY LOCATED
WITHIN THE TOWN OF WEST UNION, ADJACENT TO
WEST RAILROAD STREET, NEVILLE STREET, AND S.C.
HIGHWAY 11; AND OTHER MATTERS RELATED
THERETO.
WHEREAS, Oconee County, South Carolina (“County”) is a body politic and corporate
and a political subdivision of the State of South Carolina and is authorized by the provisions of
Title 4, Chapter 9 of the Code of Laws of South Carolina 1976, as amended, to lease real property
and to make and execute contracts;
WHEREAS, the West Union Volunteer Fire Department (as “Sublessor”) and County (as
“Sublessee”), with the approval and consent of the Town of West Union and Torrington Road,
LLC (as “Lessors”), desire to enter into a Real Property Sublease Agreement in order for the
County to sublease certain real property located within the Town of West Union, adjacent to West
Railroad Street, Neville Street, and S.C. Highway 11 (the “Premises”);
WHEREAS, a copy of the Real Property Sublease Agreement (the “Sublease”) is attached
hereto as Exhibit A;
WHEREAS, the Oconee County Council (“Council”) has reviewed the form of the
Sublease and determined that it is in the best interest of the County and its residen ts and citizens
for the County to execute and enter into the Sublease, and Council wishes to approve the same and
to authorize the County Administrator to execute and deliver the Subl ease and all related
agreements and documents necessary or incidental thereto.
NOW THEREFORE, be it ordained by Council in meeting duly assembled that:
Section 1. Sublease Approved. The Sublease is hereby approved, and the County
Administrator is hereby authorized to execute and deliver the Sublease in substantially the same
form as Exhibit A, attached hereto.
2025-10
Section 2. Related Documents and Instruments; Future Acts . The County
Administrator is hereby authorized to negotiate such documents and instruments which may be
necessary or incidental to the Sublease and to execute and deliver any such documents and
instruments on behalf of the County.
Section 3. Severability. Should any term, provision, or content of this O rdinance be
deemed unconstitutional or otherwise unenforceable by any court of competent juri sdiction, such
determination shall have no effect on the remainder of this Ordinance.
Section 4. General Repeal . All ordinances, orders, resolutions, and actions of the
Oconee County Council inconsistent herewith are, to the extent of such inconsistency only, hereby
repealed, revoked, and superseded.
Section 5. Effective Date. This Ordinance shall become effective and be in full force
from and after public hearing and third reading in accordance with the Code of Ordinances of
Oconee County, South Carolina.
ORDAINED in meeting, duly assembled, this ____ of ________________, 2025.
ATTEST:
Jennifer C. Adams Matthew Durham
Clerk to Oconee County Council Chair, Oconee County Council
First Reading: April 1, 2025
Second Reading: April 15, 2025
Third Reading: May 6, 2025
Public Hearing: May 6, 2025
2025-10
EXHIBIT A
[See attached]
1
REAL PROPERTY SUBLEASE AGREEMENT
This Real Property Sublease Agreement (“Agreement” or “Sublease”), effective as of the _____
day of __________________, 2025 (the “Sublease Commencement Date”) is made and entered into
by the West Union Volunteer Fire Department (“Sublessor”) and Oconee County, South Carolina
(“Sublessee”), with the approval and consent of the Town of West Union and Torrington Road, LLC
(collectively, “Lessors”).
RECITALS:
WHEREAS, Lessors are owner s of that certain real property , including all improvements
thereon, located within the Town of West Union, South Carolina, a djacent to West Railroad Street,
Neville Street, and S.C. Highway 11, bearing TMS ## 510-04-01-001 and 510-06-01-001, as shown
on Exhibit A, attached hereto and incorporated herein (“Lessors’ Property”);
WHEREAS, Lessors leased to Sublessor the Lessors’ Property pursuant to that certain Real
Estate Lease Agreement, dated as of ____________________, 2024 (the “Lease”);
WHEREAS, Sublessor now, with Lessors’ approval and consent, desires to sublease to
Sublessee Lessors’ Property (the “Sublease Premises”); and
WHEREAS, Sublessee purposes to use the Sublease Premises as a station from which to provide
fire control, emergency response, and related services.
NOW, THEREFORE, in consideration of the mutual covenants and promises of the parties, the
receipt and sufficiency of which are hereby acknowledged, the parties hereto agree that the foregoing
recitals are true and correct and incorporated herein by this reference, and further agree as follows:
ARTICLE 1 - DEMISE OF SUBLEASE PREMISES
Section 1.1. Sublease Premises. Sublessor, for and in consideration of the rents, covenants, and
conditions herein set forth, does hereby lease to Sublessee, and Subl essee does hereby lease from
Sublessor, all with the approval and consent of Lessors, the Sublease Premises , subject to all
easements, restrictions, rights of way, and encroachments of record and subject to the terms,
conditions, and provisions hereof. The Sublease Premises shall not include Sublessor’s office space,
and Sublessor maintains the right to use other portions of the Sublease Premises for fire service
purposes, all in cooperation and coordination with Sublessee.
Section 1.2. Quiet Enjoyment. Sublessor covenants and agrees that Sublessee, upon paying the
rent herein provided and observing and keeping the covenants, conditions, and terms of this
Agreement on Sublessee’s part to be kept or performed, shall lawfully and quietly hold, occupy, and
enjoy the Sublease Premises during the “Term” (as hereinafter defined) of this Agreement without
hindrance of Sublessor or Lessors, or any person claiming through or under Sublessor or Lessors.
Notwithstanding the foregoing, Sublessee’s rights established under this Agreement are subject to
Sublessor’s rights to use the Sublease Premises as provided for herein.
ARTICLE 2 - SUBLEASE TERM
Section 2.1. Sublease Term . The term of this Agreement (the “Term”) shall be twenty (20)
years, commencing on the Subl ease Commencement Date and continuing through the day
immediately preceding the twentieth (20th) anniversary of the Sublease Commencement Date, unless
earlier terminated as provided herein. Provided Sublessee has not defaulted in relation to a provision
of this Agreement, the Term shall autom atically extend for successive four (4) year periods, up to a
2
maximum of two such four (4) year extensions. The Term shall not automatically extend, however,
if either party gives at least ninety (90) days’ written notice of its desire to terminate this Agreement
prior to the end of the then current term.
Section 2.2. Non-reversion. Any structures, machinery, equipment, or other property owned by
Sublessee and located at the Sublease Premises shall remain the property of Sublessee and may be
removed by Sublessee; provided, however, Sublessee shall remove or cause such property’s removal
at, or prior to, the expiration of this Agreement.
Section 2.3. Termination of Lease , effect on Sublease
. If the Lease between Lessors and
Sublessor is terminated, for whatever reason, prior to the expiration of this Agreement, Lessors and
Sublessee agree to negotiate in good faith in order to establish a direct lease agreement between them,
with terms and provisions substantially similar to those contained in this Agreement.
ARTICLE 3 - RENT, TAXES, AND UTILITIES
Section 3.1. Rent. In consideration for use of the Sublease Premises, Sublessee shall pay
Sublessor the sum of ten dollars ($10.00) upon execution of this Agreement as rent for the full Term
of this Sublease.
Section 3.2. Taxes. Sublessee shall be responsible for any and all taxes, fees, assessments, and
charges, if any, that are attributable to the Sublessee’s property located at the Sublease Premises.
Section 3.3. Utilities. Sublessee shall be responsible for all charges incurred for water, heat, gas,
electricity, internet, trash disposal, and any and all other charges for utilities that directly result from
Sublessee’s use of the Sublease Premises.
Section 3.4. Security Deposit. Not required.
ARTICLE 4 - USE OF SUBLEASE PREMISES
Section 4.1. Permitted Uses. Sublessor shall allow Sublessee, its agents, employees, successors,
and assigns to use the Sublease Premises as a station from which to provide fire control, emergency
response, and related services (collectively, the “Permitted Uses ”). Sublessee shall only use the
Sublease Premises for the Permitted Uses unless written consent for any other purpose is given by
Sublessor, which consent shall not be unreasonably withheld, conditioned, or delayed.
ARTICLE 5 – HAZARDOUS MATERIALS
Section 5.1. Throughout the Term, Sublessee and Sublessee’s employees, agents, sublessees,
invitees, licensees, and contractors shall not cause, permit, or allow any substances, chemicals,
materials, or pollutants (whether solid, liquid, or gaseous) deemed to be toxic or hazardous or the
manufacture, storage, transport, or disposal of which is regulated, governed, restricted, or prohibited
by any federal, state, or local agency or authority, or under any federal, state, or local law, ordinance,
rule, or regulation related to the environment, health, or safety (collectively, “Environmental Laws”),
including, without limitation, any oil, gasoline, petroleum, petroleum by- products, hazardous
substances, toxic substances, hazardous waste, asbestos, or asbestos containing materials
(collectively, “Hazardous Materials”), to be handled, placed, stored, dumped, released,
manufactured, used, transported, or located on, in, under, or about the Sublease Premises .
Notwithstanding the foregoing, Sublessee shall not be prohibited from handling, placing, storing,
using and transporting Hazardous Materials that are required to be used by Sublessee consistent with
3
the Permitted Uses, so long as such materials are handled, used, stored and transported in accordance
with applicable laws and regulations.
Section 5.2. Sublessee shall give Sublessor immediate written notice of any problem, spill,
discharge, threatened discharge, or discovery, or claim thereof, of any Hazardous Materials on or
about the Sublease Premises.
ARTICLE 6 – IMPROVEMENTS
Section 6.1. Improvements and Alterations . Sublessee shall not undertake to materially
improve, alter, or change the exterior or interior of the Sublease Premises without prior written
consent of Sublessor.
ARTICLE 7 – MAINTENANCE
Section 7.1. Maintenance, Repairs, and Upkeep Provided by Sublessee . Sublessee shall be
responsible for all necessary repairs and maintenance to the Sublease Premises that are made
necessary as a direct result of Sublessee’s use of the Sublease Premises. Sublessee shall be responsible
for any abuse or destruction of the Sublease Premises that it causes, ordinary wear and tear excluded.
Section 7.2. As Is Condition of the Subl ease Premises. The Sublease Premises is presented to
Sublessee by Sublessor without representation or warranty as to the condition of the Sublease
Premises in general, or as to Sublessee’s contemplated uses specifically, and Sublessee is accepting
the Sublease Premises as is, with all faults.
ARTICLE 8 – LIENS
Section 8.1. Prohibition of Liens. Sublessee shall not suffer, create, or permit any mechanic’s
liens or other liens to be filed against the Sublease Premises , or any part thereof, by reason of any
work, labor, services, or materials supplied or claimed to have been supplied to Sublessee.
ARTICLE 9 – CONDEMNATION
Section 9.1. Condemnation. In the event the entire Sublease Premises shall be appropriated or
taken under the power of eminent domain by any public or quasi -public authority, this Agreement
shall terminate and expire as of the date of such taking or conveyance made in lieu thereof , and
Sublessor and Sublessee shall thereupon be released from any further duties or obligations hereunder.
ARTICLE 10 - ASSIGNMENT AND SUBLETTING
Section 10.1. Limitation on Assignment and Subletting. Sublessee may not sell, assign, sublease,
convey, or transfer all or any portion of Sublessee’s interest in this Agreement and the leasehold estate
created hereby, without the prior written consent of Sublessor and Lessors, which consent will not be
unreasonably withheld. Any assignment, sublease, conveyance, or transfer of Sublessee’s interest in
this Agreement shall be subject to compliance with the provisions of this Agreement. In the event of
an assignment, sale, or transfer of all, or substantially all, of Sublessee ’s interest in this Agreement,
any such assignee, buyer, or transferee shall be required to assume in writing all of the Sublessee’s
obligations and shall be bound by all of the terms of this Agreement.
4
ARTICLE 11 – INSURANCE AND INDEMNITY
Section 11.1. Liability Insurance . Sublessee shall maintain its policy of General Liability
insurance with the South Carolina Insurance Reserve Fund, or similar entity, in amounts customarily
held by similar political subdivisions of the State of South Carolina.
Section 11.2. Workers’ Compensation Insurance. Sublessee shall maintain an insurance policy
covering Workers’ Compensation claims, in a form and with l imits as required by the Workers’
Compensation Act of South Carolina.
Section 11.3. Fire and Property Insurance. Sublessor or Lessors shall, at their cost and expense
and at all times during the Term, maintain in force a policy of insurance ensuring the Sublease
Premises and any improvements/infrastructure thereon against loss or damage by such perils as are
customarily covered by such policies.
Section 11.4. Additional Insurance
. Sublessor will not be responsible for any loss to personal
property of Sublessee due to fire, theft, or any other damage, including any acts of nature. Sublessor
or Lessor will maintain coverage as indicated in Section 11. 3, but Sublessee understands that such
insurance does not cover personal property due to loss and that it is Sublessee’s responsibility to
obtain insurance to cover such property.
ARTICLE 12 - DEFAULT AND REMEDIES
Section 12.1. Default. The failure of either Sublessor or Sublessee to observe or perform any of
its material covenants, representations, conditions, agreements under, or terms of, this Agreement,
shall constitute an “Event of Default.”
Section 12.2. Notice and Right to Cure. The defaulting party shall have sixty (60) days to cure an
Event of Default after written notice is given it by the non- defaulting party, specifying the nature of
the default.
Section 12.3. Remedies. If any Event of D efault shall continue uncured by the defaulting party
upon expiration of the applicable cure period, the non- defaulting party may exercise any remed y
available in law or equity.
ARTICLE 13 - SURRENDER AND REMOVAL
Section 13.1. Surrender of Possession. Upon the expiration of the Term or any earlier termination
thereof, Sublessee shall surrender to Sublessor possession of the Sublease Premises . Sublessee may
remove, or cause to be removed, all property and equipment of Sublessee from the Sublease Premises
at or prior to the expiration or effective date of termination of this Agreement.
ARTICLE 14 – GENERAL PROVISIONS
Section 14.1. Conditions and Covenants. All of the provisions of this Agreement shall be deemed
as running with the land, and construed to be “conditions” as well as “covenants” as though the words
specifically expressing or imparting covenants and conditions were used in each separate provision.
Section 14.2. Survival. All representations and warranties of Sublessee or Sublessor under this
Agreement shall survive the expiration or sooner termination of this Agreement for acts occurring
prior to expiration or termination of this Agreement.
5
Section 14.3. No Waiver of Breach. No failure by either Sublessor or Sublessee to insist upon the
strict performance by the other of any covenant, agreement, term, or condition of this Agreement, or
to exercise any right or remedy consequent upon a breach thereof, shall constitute a waiver of any
such breach or of such covenant, agreement, term, or condition. No waiver of any breach shall affect
or alter this Agreement , but each and every covenant, condition, agreement , and term of this
Agreement shall continue in full force and effect with respect to any other then existing or subsequent
breach.
Section 14.4. Unavoidable Delay - Force Majeure. If either party shall be delayed or prevented
from the performance of any act required by this Agreement by reason of acts of God, strikes,
lockouts, labor troubles, inability to procure materials, restrictive governmental laws or regulations ,
or other cau se, without fault and beyond the reasonable control of the party obligated (financial
inability excepted), performance of such act shall be excused for the period of the delay; and the
period for the performance of any such act shall be extended for a peri od equivalent to the period of
such delay.
Section 14.5. Notices. Unless otherwise specifically provided in this Agreement or by law, any
and all notices or other communications required or permitted by this Agreement or by law to be
served on, given to, or delivered to any party to this Agreement shall be in writing and shall be deemed
duly served, given, delivered and received when personally delivered (including confirmed overnight
delivery service to the party to whom it is directed), or in lieu of such personal delivery, when three
(3) business days have elapsed following deposit thereof in the United States mail, first-class postage
prepaid, certified, return receipt requested, addressed to:
SUBLESSOR:
West Union Volunteer Fire Department
220 SC-11
West Union, SC 29696
Attn: Jess Neville
SUBLESSEE:
Oconee County
415 South Pine Street
Walhalla, SC 29691
Attn: County Administrator
Either party may change its address for the purpose of this paragraph by giving written notice
of such change to the other party in the manner provided in this paragraph.
Section 14.6. Captions
. Captions in this Agreement are inserted for convenience of reference only
and do not define, describe , or limit the scope or the intent of this Agreement or any of the terms
hereof.
Section 14.7. Waiver; Amendment. No modification, waiver, amendment, discharge , or change
of this Agreement shall be valid unless the same is in writing and signed by the party against which
the enforcement of such modification, waiver, amendment, discharge, or change is or may be sought.
Section 14.8. Time. Time is of the essence of each obligation of each party hereunder.
6
Section 14.9. Governing Law. This Agreement shall be construed and enforced in accordance
with the laws of the State of South Carolina, without regard to conflict of law principles.
Section 14.10. Binding Effect. Subject to any provision of this Agreement that may prohibit or
curtail assignment of any rights hereunder, this Agreement shall bind and inure to the benefit of the
respective heirs, assigns, personal representatives, and successors of the parties hereto.
Section 14.11. Execution of Other Instruments. Each party agrees that it shall, upon the other’s
request, take any and all steps, and exec ute, acknowledge, and deliver to the other party any and all
further instruments necessary or expedient to effectuate the purpose of this Agreement.
Section 14.12. Severability. If any term, provision, covenant , or condition of this Agreement is
held by a court of competent jurisdiction to be invalid, void, or unenforceable or is otherwise
challenged and determined to be invalid, illegal, or incapable of being enforced as a result of any rule
of law or public policy issued by an administrative or judicial forum that is not subject to further
appeal or is not actually appealed, the remainder of the provisions shall remain in full force and effect
and shall in no way be affected, impaired, or invalidated. In such event or if an opinion of counsel is
provided to the effect that this Agreement is not so enforceable, the parties hereto shall negotiate in
good faith to modify this Agreement so as to effect the original intent of the parties as closely as
possible and to comply with applicable law, reg ulations, or published governmental interpretations
thereof, in an acceptable manner to the end that the transactions contemplated hereby are fulfilled to
the extent possible.
Section 14.13. Counterparts. This Agreement may be executed in one or more counterparts, each
of which shall be deemed an original and when taken together will constitute one instrument.
SIGNATURES ON FOLLOWING PAGE
7
IN WITNESS WHEREOF , Sublessor and Sublessee have caused this Agreement to be
executed and delivered as of the day and year first above written.
IN THE PRESENCE OF:
SUBLESSOR: THE WEST UNION VOLUNTEER
FIRE DEPARTMENT
___________________________ By: _______________________________
___________________________ Its: _______________________________
SUBLESSEE: OCONEE COUNTY, SOUTH
CAROLINA
___________________________ By: _______________________________
___________________________ Its: _______________________________
WE APPROVE AND CONSENT:
IN THE PRESENCE OF: LESSOR: THE TOWN OF WEST UNION
___________________________ By: _______________________________
___________________________ Its: _______________________________
LESSOR: TORRINGTON ROAD, LLC
___________________________ By: _______________________________
___________________________ Its: _______________________________
8
EXHIBIT A
LESSOR’S PROPERTY AND SUBLEASE PREMISES
[See attached]
STATE OF SOUTH CAROLINA
COUNTY OF OCONEE
RESOLUTION 2025-02
A RESOLUTION RECOGNIZING AND DESIGNATING
APRIL 2025 AS FAIR HOUSING MONTH.
WHEREAS, Oconee County desires that all of its citizens be afforded the
opportunity to attain a decent, safe, and sound living environment;
WHEREAS, Oconee County rejects discrimination on the basis of race,
religion, color, sex, national origin, disability, or familial status in the sale, rental, or
provision of housing services;
WHEREAS, the State of South Carolina enacted the South Carolina Fair
Housing Law in 1989; and
WHEREAS, April is recognized nationally as Fair Housing Month.
NOW, THEREFORE, BE IT RESOLVED, that Oconee County does hereby
recognize April 2025 as Fair Housing Month and designates it as such.
RESOLVED this 15th day of April 2025, in meeting duly assembled.
OCONEE COUNTY, SOUTH CAROLINA
By: ____________________________________
Matthew Durham
Chair, Oconee County Council
(SEAL)
ATTEST:
By: __________________________________
Jennifer C. Adams
Clerk to the Oconee County Council
Oconee County
Council
Oconee County
Administrative Offices
415 South Pine Street
Walhalla, SC 29691
Phone: 864-718-1023
Fax: 864 718-1024
E-mail:
jennifercadams@oconeesc.com
John Elliott
District I
Matthew Durham
Chairman
District II
Don Mize
Vice Chairman
District III
Thomas James
District IV
J. Glenn Hart
Chairman Pro Tem
District V
The Oconee County Council will meet in 2025 on the first and third Tuesday of each
month with the following exceptions:
• July, August, and November meetings, which will
be only on t he third Tuesday of each of these
months;
• March, June and December meetings, which will
be only on the first Tuesday of each of these
months.
All Council meetings, unless otherwise noted, are held in Council Chambers,
Oconee County Administrative Offices, 415 South Pine Street, Walhalla, South
Carolina.
Oconee County Council will also hold a Planning Retreat beginning at 9:00
a.m. on Thursday, February 20, 2025 to establish short- and long-term goals. This
meeting will be held off-site in the Tri-County Technical College, Oconee Campus,
conference room located at 552 Education Way, Westminster, South Carolina.
Oconee County Council will also meet on Tuesday, January 6, 2026 in
Council Chambers at which point they will establish their 2026 Council and
Committee meeting schedules.
Additional Council meetings, workshops, and/or committee meetings may
be added throughout the year as needed.
Oconee County Council Committees will meet in 20 25 prior to County
Council meetings on the following dates/times in Council Chambers located at 415
South Pine Street, Walhalla, South Carolina unless otherwise advertised.
The Law Enforcement, Public Safety, Health, & Welfare Committee at
4:30 p.m. on the following dates: February 18, May 2 0, July 15, &
September 16, 2025.
The Transportation Committee at 4:30 p.m. on the following dates: February
18, May 20, July 15, & September 16, 2025.
The Real Estate, Facilities, & Land Management Committee at 4:30 p.m. on
the following dates: April 1, June 3, August 19, & October 21, 2025.
The Planning & Economic Development Committee at 4:30 p.m. on the
following dates: April 1, June 3, August 19, & October 21, 2025.
The Budget, Fina nce, & Administration Committee at 9:00 a.m. on t he
following dates: February 20
[Strategic Planning Retreat] and 4:30 p.m. on the following
dates: March 4 [4 p.m.], April 15, & May 6, 2025.
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
CITIZEN PROVIDED MATERIAL
NOT OFFICIAL
OCONEE COUNTY DOCUMENT
Source: Oconee County website. First collected Nov 14, 2026.