Committee of the Whole Meeting — Agenda Packet
Pickens County · Pickens County · Pickens County Council · meeting of Mar 13, 2023 · Agenda packets
Open the original document More from Pickens County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
222 MCDANIEL AVENUE, B-1 ∙ PICKENS, SC 29671 ∙ 864.898.5856 ∙ WWW.CO.PICKENS.SC.US
COUNCIL MEMBERS
CHRIS BOWERS, CHAIRMAN
ROY COSTNER, VICE CHAIRMAN
ALEX SAITTA, VICE CHAIR PRO-TEM
C. CLAIBORNE LINVILL
CHRIS LOLLIS
HENRY WILSON
COUNTY ADMINISTRATOR
KEN ROPER
CLERK TO COUNCIL
MEAGAN NATIONS
PICKENS COUNTY COMMITTEE OF THE WHOLE MEETING
Monday, March 13, 2023
6:00 PM
(Immediately following the Special-Called Meeting)
Council Chambers, County Administration Facility
222 McDaniel Avenue, Pickens SC 29671
All meetings of Pickens County Council are held in accordance with the South Carolina Freedom of Information Act,
Section 30-4-70, et seq. of the Code of Laws of South Carolina, 1976, as amended, as well as the Organizational
Rules for Pickens County Council.
1. WELCOME AND CALL TO ORDER: Chairman Chris Bowers
INVOCATION AND PLEDGE OF ALLEGIANCE: Councilman Alex Saitta
2. COMMITTEE OF THE WHOLE:
a. Log No. 141 – UDSO
3. ADJOURN
1
UDSO Review
Staff Recommendations
for Implementing the Proposed Plan of Action for the UDSO Updates
The following pages represent staff’s response to the 15 items presented to Council on February 21, 2023 as a “Proposed
Plan of Action” to the UDSO updates.
1. Follow the Comprehensive Plan and encourage/allow high density (50 or more units per acre) only in areas closest to
Easley, Liberty, Central, and Clemson and the 123/93 corridors.
2. Meet with those four municipalities to discuss their desires and concerns related to growth and express ours. Use this
meeting to further our growth conversations and talk about our joint capacity for sewer, fire/rescue, schools, land fill, etc .
3. See if we can collectively create a “capacity for development map” which will largely be driven by sewer and transit. This
may mean that most of the intensive growth will not be in the unincorporated County and that due to limitations based on
infrastructure there may well be less potential for growth in and around the cities than some may think.
4. Propose that we either continue to NOT allow high density in the County and therefore encourage municipal annexation if
the cities will agree to our “terms” (which will include municipalities taking over any County roads on land the cities annex).
OR
5. Develop standards for “transition zones” that are comparable to developing within the various city limits and, therefore, a.)
address some of our concerns and b.) dissuade developers from first building in the County and then leaving to join a city.
6. Consider an overlay district or districts that include properties touching or within 1000’ of the 123 and 92 ROW’s and/or
touching or within 1000’ of the municipal boundaries of Easley, Liberty, Central, or Clemson.
7. These districts would allow for higher density growth with suitable standards.
Items 1 – 7 are being considered as a “unit” with the first step being to meet with the surrounding municipalities
to discuss matters of annexation, sewer capacity, transit, and growth in general. Administration is in the process
of coordinating the inaugural meeting. Once staff has some idea of the posit ion the cities have on these matters
we can start working on the boundaries of the overlays as well as the content.
8. Regardless of if Council elects to pursue #4 or #5 above (or something else Council wishes to employ) ensure that all
developments over 50 homes or units have potential through incentives to include an affordable/workforce housing
component. We can use sta ndard measures for what is “affordable”. For example: In order for a housing unit to be
considered affordable its cost (rent, mortgage, taxes, insurance, and utilities) must not exceed 30% of a person's annual
income of a resident who earns between 40% and 80% of Pickens County's average median household income, which was
$53,188 in 2020 according to the Census Bureau. Tax abatements are one traditional method of providing incentives for
affordable housing.
Staff has prepared a one- page document that outlines how the County could introduce an incentive program to
promote more attainable housing. If this is something Council wishes to pursue, then staff is prepared to take your
feedback and craft this into an ordinance/resolution.
9. Leave the rest of the basic content of the UDSO as it is in regard to Open Space, Planned Developments and Conventional
Subdivisions with a few exceptions:
A. Limit conventional subdivisions to 10 units. This promotes Open Space Subdivisions.
2
UDSO Review
B. Modify the Open Space Subdivision ordinance to require 25% open space (up from 20%) of which 75% has to remain
fenced off during construction and considered as “protected” moving forward.
As shown in the attached document, staff’s response to these issues are shown in red as simple (but significant)
amendments to the existing language in the UDSO.
C. Develop some sort of easier to read/follow matrix that addresses setbacks, lot sizes, frontages.
A matrix is attached for Council review.
D. Review with DHEC any changes in standards for minimum area needed for septic.
This matter was investigated and, as the attached response indicates, after speaking with DHEC and reviewing our
existing standards staff does not recommend making any changes to our current standards for minimum lot sizes.
E. Review County ordinances for ways to strengthen/provide for the protection/replacement of our tree canopy and
strengthen our standards for protecting our waterways.
Tree canopy protection and replacement language is included in the proposed Open Space Subdivision ordinance
and the Townhome Development ordinance. A proposed ordinance for providing tree canopy coverage in parking
lots with over 25-spaces is also included here. For waterways, the most effective way to provide protection is to
have a setback. Staff is proposing a setback of 30’ measured horizontally from the top of the bank/ordinary high
water mark of any surface waters of the State as shown on the USGS map. The setback could be up to 45’ for any
“Sensitive Waters”. Activities within the setback would be limited to low impact development such as pathways,
walkways and fishing/viewing platforms and would preclude development such as paving, parking, buildings or
other impervious structures.
10. Refine and submit the current drafts of our townhome, RV and Tiny Home ordinances with clear definitions of what we
mean by these terms.
Included here are draft ordinances for a Tiny Home Development Ordinance, Townhome Ordinance, and RV’s as
a Dwelling Ordinance.
11. Establish clear and realistic standards for the specific type and scope of traffic studies required based on a project’s size
and road type adjacency.
Staff is proposing that the County adopt a Traffic Study Policy, a draft of which is included here.
12. Make clear when and at what scale a traffic study will automatically be required to make it less emotional and/or
subjective and also make clear that any recommendations that the County Engineer makes as a result of a traffic study
will have to be implemented by the developer if they want to proceed.
Attached here is a sample “Notice of Action” letter which we send out to all applicants of Planning Commission
review after the Planning Commission has reviewed the project and taken action. Staff proposes to add language
that clarifies a) the PC can approve a project while a traffic study is under way and b) once that study is complete
any acti on(s) deemed necessary by the County Engineer will be required by the developer to complete. Also
attached here is proposed language for our Subdivision and Land Use applications reiterating this policy.
13. Review UDSO Section 10 (Roads) for improvements with specific attention being paid to the common, shared private
drive language and standards
There are two parts to this Item. The first is staff’s recommendation to eliminate common drives from our
ordinance (and our rationale for this recommendation) and, second, pointing out that the County Engineer is in
the process of reviewing the UDSO and Road Ordinance for opportunities to align and refine the two documents.
3
UDSO Review
14. Work with GPATS, SCDOT and others to maintain a thorough plan of action for roadway repairs, improvements, and
additions, alternate transportation features such as bikeways, transit, and general mobility throughout the County.
This is a long-range objective and one that staff expects to take 8-12 months to complete. Staff is sharing a
proposed overview of what a Countywide Mobility Plan would look like and what steps would be required. Staff
would like input from Council regarding this matter.
15. Encourage a County-wide fee study of all existing fees and explore the introduction of impact fees. Hopefully this would
include each department reviewing their entire fee structure and when it was last updated and compare it to local
(Upstate) counties as well as national averages and trends. Some departments may need help with this and the
consultant may have to help. The consultant can also help with looking at our overall fee structure – across the board – to
see if we are leaving something on the table. And – after they assess all of that - they could evaluate our posture in
regard to levying an impact fee or fees and make a recommendation there.
Staff has developed an RFP that is currently out for bid. Responses will be brought to Council for vetting.
1
UDSO Review
8. attainable Housing program
WHAT DOES THIS POLICY HOPE TO ACCOMPLISH?
• The Pickens County Council has publicly recognized the deficit of affordable / workforce housing options within the
County and the ongoing need for new affordable housing units.
• The Pickens County Council has created a Policy to guide Projects to be eligible for an abatement/reduction in
property taxes as an incentive for the building of affordable housing within the County.
• In order for a housing unit to be considered affordable its cost (rent, mortgage, taxes, insurance, and utilities) must not
exceed 30% of a person's annual income of a resident who earns between 40% and 80% of Pickens County's
average median household income, which was $53,188 in 2020 according to the Census Bureau.
WHAT AFFORDABLE HOUSING DEVELOPMENTS ARE ELIGIBLE?
• Any Project with 50 or more units or lots.
• Appropriate affordable/workforce unit “set aside” – more on this below.
• Affordable/workforce units must be substantially undifferentiated from the market rate units in form, finish and
placement within the overall project
• Project must comply with all requirements of the UDSO.
• Project Sponsor must enter into an Incentive Agreement with the County for a reduction in taxes.
GENERAL PROCESS
• An eligible Project presents to the Planning Commission to demonstrate that it qualifies for this offering.
• Upon approval by the Planning Commission, the Sponsor will then apply to the County Council for a reduction in their
taxes per the chat shown below.
• The Project Sponsor will then enter into an Agreement with the County for a reduction of taxes for a period of time not
to exceed 25 years.
WHAT TYPE OF AFFORDABLE PRODUCTION IS POSSIBLE THROUGH THIS POLICY?
• The Policy contains different levels of tax abatement levels. The greater % of affordable/workforce units that are
introduced into the Project, the greater % abatement the Project Sponsor Receives
• The County’s Policy requires the affordable/workforce units be split across income levels with the requirement of: at
least 20% of the total affordable/workforce units must be affordable to those earning 40% of Area Median Income
(“AMI”) (deeply affordable), at least 60% of the total affordable/workforce units must be affordable to those earning
60% of AMI, at least 20% of the total affordable/workforce units must be affordable to those earning 80% of AMI
(“workforce”)
AFFORDABLE HOUSING UNITS (as a % of Total Project Units) % TAX ABATED
20% 50%
30% 53%
40% 55%
50% 60%
70% 63%
80% 65%
90% 68%
100% 70%
1
UDSO Review
9A & 9B. subdivisions
Article 5. Conventional Subdivisions, Open Space Subdivisions and
Master Planned Developments
Article 5. Conventional Subdivisions, Open Space Subdivisions and
Master Planned Developments
Table of Contents page
Sec. 501 Purpose of Article 5. .................................................................................................................................5-1
Sec. 502 Minor and major subdivisions; defined..........................................................................................5-1
502 (a) Minor subdivision. ..................................................................................................... 5-1
502 (b) Major subdivision. ..................................................................................................... 5-2
Sec. 503 Subdivision activity. .................................................................................................................................5-2
503 (a) Creation of minor subdivision.................................................................................... 5-2
503 (b) Creation of major subdivisions. ................................................................................. 5-2
Sec. 504 Conventional subdivisions....................................................................................................................5-3
504 (a) Maximum number of lots........................................................................................... 5-3
504 (b) Minimum lot size. ...................................................................................................... 5-3
504 (c) Minimum lot width, setbacks. .................................................................................... 5-3
504 (d) Open space optional.................................................................................................. 5-3
Sec. 505 Open space subdivisions. ......................................................................................................................5-3
505 (a) Quality development standards. ................................................................................ 5-3
505 (b) Maximum number of lots........................................................................................... 5-3
505 (c) Minimum lot size ....................................................................................................... 5-3
Table 5.1: Minimum Lot Size—Open Space Subdivisions ............................................. 5-3
505 (d) Minimum lot widths and setbacks. ............................................................................. 5-4
Table 5.2: Lot Width and Principal Building Setbacks—Open Space Subdivisions ......... 5-4
505 (e) Reduction of minimum lot widths and setbacks. ........................................................ 5-4
Sec. 506 Master planned development option (MPD). ................................................................................5-4
506 (a) Quality Development Standards. ................................................................................ 5-4
506 (b) Criteria for approval. ................................................................................................. 5-4
506 (c) Development Parameters. .......................................................................................... 5-5
Table 5.3: Land Use Distribution in a Master Planned Development ............................ 5-6
506 (d) Maximum number of lots........................................................................................... 5-7
506 (e) Minimum lot size ....................................................................................................... 5-7
Table 5.4: Minimum Lot Size—Master Planned Developments ..................................... 5-7
506 (f) Minimum lot widths and setbacks. ............................................................................. 5-7
506 (g) Buffer requirements................................................................................................... 5-7
506 (h) Ownership Control. ................................................................................................... 5-7
506 (i) MPD Concept Plan. .................................................................................................... 5-8
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-i
UDSO Review
Sec. 507 Quality development standards. ........................................................................................................5-8
507 (a) Common open space. ................................................................................................ 5-9
507 (b) Residential development standards. .......................................................................... 5-9
507 (c) Nonresidential development standards. ................................................................... 5-10
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-i
Sec. 501 Purpose of Article 5.
Sec. 508
Sec. 509
5 09 (a)
5 09 (b)
5 09 (c)
Conservation easements..................................................................................................................... 5·11
Owner's association............................................................................................................................. . 5·11
Homeowner's association; when required................................................................ 5·11
Owners' association................................................................................................. 5·12
Condominium association........................................................................................ 5·12
Sec. 501 Purpose of Article 5.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-1
Article 5. Subdivisions and Master Planned Developments
Sec. 501 Purpose of Article 5.
This Article presents t he different ways t hat la nd can be su bdivided and develope d, ranging from
Conventional Subdivisions, t o Open Space Subdivisions where green space and natural features are
preserved by reducing lot sizes, to Master Planned Developments which allow a wider variety of housing
types in a well-planned mixed-use environment while also preserving green space and natural features.
Sec. 502 Minor and major subdivisions; defined.
502 (a) M inor subdivision.
A “minor subdivision” is one in wh ich no improvements (such as ne w s treets, storm- water d rainage
facilities or public utilities) are to be made. Minor subdivisions are de- fined as any one of the following:
(1) Combinations/Recombinations.
a. The combination or recombinations of portions of p reviously platted lot s where t he tota l
number of lots is not in creased a nd the resultant lots are equal to the standards of the County
and in accordance with the provisions of this Development Standards Ordinance. (2/16/10)
b. The combination or recombination of entire lots of record wh ere no ne w street or change in
existing streets is involved.
(2) Non-Developa ble/Non-Buildable Lot for Sale/Transfer
The sale of a proposed vacant parcel, or vacant portion of a parcel, for which no new streets, new utility
improvements, or no new sanitary sewer or a pproval of a septic tank is required (the p arcel or portion
thereof does not meet the minimum lot size or access requirements of this Development Ordinance). Any
plat for su ch s ale or transaction must first be p resented to Planning Department staff for r eview and
approval. The following caption must be clearly and predominately affixed onto the plat by the surveyor:
“The tract(s) de picted on this plat are not elig ible for con nection to a sa nitary sewer system or for
septic tank approval nor shall building permits, certificates of occupancy or any other development permit
be issued, nor shall any person construct or insta ll upon this t ract any building or structure unt il it has
been combined with a nother tract in a ma nner that creates a c onforming tract or re- su bdivided in
accordance with the UDSO, as amended.”
(3) Multiple Lot Rural Split.
The subdivision of an original tract that creates no more than 3 lot s, building sites, or other division
(including t he remaining portion of the original t ract). Each lot shall front on an ex isting public road
meeting the requirements of Sec.1010 or be accessed by a shared driveway as outlined in Sec. 1012(a) of
this development ordinance. Lots sizes and setbacks are as noted in Article 4. Any lot created under this
category, including the remainder of t he original tract, may not be further subdivided except as a major
subdivision.
(4) Large lot subdivision.
The subdivision of an original tract that creates any number of lots that are 5 acres in size or greater
(including the remaining portion of t he original t ract)
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-2
Sec. 504 Conventional subdivisions.
where no new street is involved. A ny lot c reated under this exemption, including the remainder of the
original tract, may not be further subdivided except as a major subdivision.
502 (b) Major subdivision.
A “major subdivision” is any subdivision that does not qualify as a “minor subdivision.” A major subdivision
commonly involves the construction of a new street or widening of an existing roadway, the provision of
stormwater drainage facilities, or the construction or improvement of public utilitie s, or which otherwise
has 4 or more lots (not in a large lot minor subdivision), building sites or other divisions.
Sec. 503 Subdivision activity.
503 (a) Cr eation of minor subdivision.
(1) A “minor subdivision” is t he subdivision of an original t ract in w hich each lot ha s frontage on an
existing State or County street or road, and the subdivision does not require the construction of a ne w
street or the widening of an existing road- way, the provision of stormwater drainage facilities (other than
driveway culverts), or the construction or improvement of any public utilities.
(2) New lots or tracts of la nd that are created from the subdivision of t he origin al tract as a mi nor
subdivision may not be further subdivided as a minor subdivision. Once the capacity of the original tract
to be divided as a minor subdivision is exhausted, the remaining portion of the original tract may not be
further su bdivided as a minor subdivision. A ny f urther subdivision of a lot created as part of a m inor
subdivision must be accomplished through the procedures for a major subdivision.
(3) T he term “original tract” as used in this S ection means the entire tract of land as it existed as a l egal
lot of record prior to the adoption of this Development Standards Ordinance.
503 (b) Cr eation of major subdivisions.
Major subdivisions fall into three categories for the purpose of development regulation:
(1) C onventional Subdivisions, in which the mini mum lot size requirement d etermines th e maxi mum
number of lots in the subdivision, and all of the lots meet the minimum lot size requirements as shown
on Table 4.1 of Article 4. Open space outside of the lots may be created, but is not required.
(2) Open Space Su bdivisions, in w hich the mini mum lot size requirement d etermines the maximum
number of lots in t he subdivision, but the mini mum lot size is reduced to a certain extent in response to
a higher level of development standards and in order to create open space and recreational amenities for
the residents.
(3) Master Planned Development s, in wh ich a de nsity limitation controls, but t he minimum lot size is
further reduced in response to a higher level of d evelopment standards a nd in order to create open
space and recreational am enities for the residents. Depending on t he area in w hich a master planned
development is located, flexibility in housing types, mixed-use projects and certain commercial uses are
allowed.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-3
Sec. 504 Conventional subdivisions.
Sec. 504 Conventional subdivisions.
504 (a) Maximum number of lots.
The maximum number of lots (or dwelling units) in a Conventional Subdivision shall be determined by the
gross acreage of the subdivision site divided by the minimum lot size allowed but shall not exceed 10 lots.
504 (b) M inimum lot size.
In a Conventional Subdivision, t he lot area per dwelling unit shown on Table 4.1 of Article 4 establishes
the minimum lot size for each lot.
504 (c) Minimum lot width, setbacks.
The lot width (Table 4.3) and s etback requirements (Table 4.4) of Article 4 a pply to each lot in a
Conventional Subdivision.
504 (d) Open space optional.
The developer may set aside open space in a Conventional Subdivision voluntarily, but open space is not
required by this Ordinance.
Sec. 505 Open space subdivisions.
Open Space Development provisions may be applied to any single-family detached subdivision. In addition
to any conditions of land use approval that may apply to a specific property, the following shall apply to
all Open Space Subdivisions:
505 (a) Quality development standards.
An Open Space Subdivision shall comply with the open space and residential developme nt standards of
Sec 507 as a prerequisite for approval.
505 (b) Permanent Open Space
25% of the total acreage for all Open Space Subdivisions is to be set aside as permanent open space per
507 (a).
505 (c) Maximum number of lots.
The maximum number of lots shall not exceed the gross acreage of the site divided by the minimum lots
size as allowed in Table 5.1.
505 (d) M inimum lot size
The minimum lot size per dwelling unit shall be as shown on Table 5.1, depending on the source of water
supply and method of sewage disposal:
Table 5.1: Minimum Lot Size—Open
Space Subdivisions
Minimum Lot Size per Dwelling Unit (square feet)
Well and Septic Tank 43,560 sf*
Public Water and Septic Tank: 21,780 sf*
Public Sewer 5,000 sf
* DHEC may allow for smaller lots sizes based on sewage disposal methods.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-4
Sec. 506 Master planned development option (MPD).
505 (e) Minimum lot widths and setbacks.
The minimum lot widths and minimum s etbacks for principal buildings for lots in any op en space
subdivision shall be as required on Table 5.2, depending on the minimum lot size required for the open
space subdivision.
Table 5.2: Lot Width and Principal Building Setbacks—Open Space Subdivisions
Minimum Lot Size allowed in the Subdivision (in square feet)
43,560 21,780 5,000
Minimum Lot
Width* 50 feet 30 feet 20 feet
Front Setback 20 feet 15 feet 10 feet Side Setback 7feet
5 feet 0 feet** Rear Setback 10 feet 5 feet
0 feet**
** For developments divided into fee simple lots, no side or rear yard setback is required along the property line that separates the dwelling units,
however, building code requirements for separation will apply between adjacent dwellings.
(2/16/10)
505 (f) Reduction of minimum lot widths and setbacks.
(1) Front setbacks.
A front setback may be reduced administratively up to 5 feet from that required under Table 5.2, provided
that the minimum sight distance requirements for streets is maintained in accordance with the Project
Design Standards Article of this Code.
(2) Side setbacks.
A side setback may be reduced administratively up to 50 percent of that required under Table 5.2, provided
that the side yard on the adjacent lot is increased by an equal amount.
Sec. 506 Master Planned Development option (MPD).
506 (a) Quality Development Standards.
A Master Planned Development must comply with the open space, residential development standards
and nonresidential development standards of Section 507 as a pre- requisite for approval.
506 (b) Criteria for approval.
(1) Provisions are included to encourage the development of Master Planned Developments (MPDs) in
appropriate locations throughout the County that allow the use of innovative techniques, s uch as
traditional n eighborhood d esign, resource conservation subdivisions, village concepts and mixed use
development. Such master planned developments should be brought together as a compatible and unified
development by allowing flexibility within the current development regulations.
(2) Benefits of MPDs include innovative design, the protection and accommodation of important natural
resources and open space within the County, and the cost savings of less infrastructure. MPDs are reviewed
individually to determine compatibility, suitability, and health, safety and welfare issues. Individual
requirements relating
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-5
Sec. 506 Master planned development option (MPD).
to such developments become part of the site through conditions of land use approval.
(3) Each MPD shall comply with the intent statement regarding MPDs. (4) Review
criteria.
The following is a list of criteria that will be used by the County to determine the suitability of a proposed
MPD in addition to the standards for land use approval contained in the Procedures and Permits Article of
this Development Ordinance:
a. The uses proposed will not be detrimental to present and potential surrounding uses.
b. Exceptions from this Ordinance are warranted by the design and amenities incorporated in the
development plan.
c. Land surrounding the proposed development can be planned in coordination with the proposed
development and will be compatible in use.
d. Master Planned Development is in conformance with the general intent of this
Ordinance and the Comprehensive Plan.
e. Every MPD must be deemed by the Planning Commission to incorporate features of exceptional
architectural, l andscaping or site design p rior to MPD approval. Such plans upon which this
determination is made shall be incorporated into the MPD approval of the project, or shall be
approved by the Planning Commission prior to building permitting.
506 (c) Development Parameters.
The following general conditions apply to master planned developments (MPDs). (1) General
requirements.
a. A Master Planned Development must contain at least 10 contiguous acres.
b. The primary access (i.e., main entrance) to the Master Planned Development must be from a
minor collector road or higher.
(2) The proportion and distribution of nonresidential to residential uses in a MPD is determined by the
size of the property. The property size also determines the maximum number of dwelling units and the
type of commercial development that can be allowed in the MPD. These limitations and the distribution of
residential density are shown on Table 5.3. Unless otherwise noted, the provisions of Table
5.3 override restrictions contained elsewhere in this ordinance.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-6
Sec. 506 Master planned development option (MPD).
Table 5.3: Land Use Distribution in a Master Planned Development
Maximum Density*
Property
Use Distribution
Percent of Total Site by Housing
Well &
Public
Water &
Public
Water &
Size (Percent of Total Site) Type (and open space) Septic Septic Sewer
10-35 No less than 95% residential and open space 95% single-family detached 1.0 du/a 2.0du/a 2.5 du/a
acres No more than 5% neighborhood commercial .25 FAR .25 FAR .25 FAR
No less than 90% residential and open space Min. 40% single-family detached, 1.5 du/a 2.5 du/a 3.5 du/a
OR …
Min. 40% Two-Family 1.5 du/a 2.5 du/a 3.5 du/a
36-75
acres Max. 50% Townhouse subdivision, 1.5 du/a 2.5 du/a 3.5 du/a
OR …
Max. 50% Townhouse Condo 1.5 du/a 2.5 du/a 3.5 du/a
No more than 10% neighborhood commercial .25 FAR .25 FAR .25 FAR
No less than 80% residential and open space Min. 30% single-family detached, 1.5 du/a 2.5 du/a 4.0 du/a
OR …
Min. 30% Two-Family 1.5 du/a 2.5 du/a 4.0 du/a
76-100 Max. 50% Townhouse Subdivision, 1.5 du/a 2.5 du/a 6.0 du/a
acres OR …
Max. 50% Townhouse Condo or 1.5 du/a 2.5 du/a 6.0 du/a
Multi-Family
No more than 20% community commercial .50 FAR .50 FAR .50 FAR
No less than 70% residential and open space Min. 0% single-family detached, 1.5 du/a 2.5 du/a 6.0 du/a
OR …
Min. 0% Two-Family 1.5 du/a 2.5 du/a 6.0 du/a
101 + Max. 30% Townhouse Subdivision, 1.5 du/a 2.5 du/a 8.0 du/a
acres OR …
Max. 30% Townhouse Condo or 1.5 du/a 2.5 du/a 8.0 du/a
Multi-Family
No more than 30% community commercial .50 FAR .50 FAR .50 FAR
Du/ac: dwelling units per gross residential acre. The gross residential acreage is the total acreage of the property excluding any
acreage to be used for commercial development.
FAR (Floor Area Ratio): The gross floor area of the commercial building(s) divided by the net area of the commercial site. The net
area of the commercial site excludes public and private rights-of-way and buffers.
(3) Commercial stru ctures and uses are to be lo cated and de signed as a unified developme nt where
feasible. Residential and commercial uses may either be located in freestanding buildings within a site, or
combined together within the same building. Loft dwellings in a mixed use building will be considered part
of the commercial floor area but not part of the maximum residential density on the site.
(4) Developme nt is to be carefully planned to e nsure t he bene fits of MP Ds are fully realized a nd
potential n egative impacts of one u se on a nother are minim ized, both within t he developme nt a nd
along its periphery. Factors include separation of mixed use areas from single use area, pedestrian access
linkages, placement of open space and community amenities to define neighborhoods and provide com-
munity focus, appropriate internal and peripheral buffers and transitions in u se or intensity approaching
the MPD boundary.
(5) A ll Master Planned Developments must provide internal pedest rian access including connections to
external access points. The type of access such as sidewalks, bike paths, lanes and trails, will be established
during the review period to deter- mine the best way to serve a particular development.
Commented [TS1]: These density allowances seem very low.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-7
Sec. 506 Master planned development option (MPD).
506 (d) Maximum number of lots.
Maximum number of lots will be set as a condition of land use approval provided by the Planning
Commission.
506 (e) Minimum lot size
The minimum lot size per dwelling unit shall be as shown on Table 5.4, depending on the source of
water supply and method of sewage disposal:
Table 5.4: Minimum Lot Size—Master Planned Developments
Minimum Lot Size per Dwelling Unit (square feet)* Well and Septic Tank 21,780
Public Water and Septic Tank 10,890
Public Sewer No Minimum
*Or as required by DHEC to meet the standards for septic systems.
506 (f) Minimum lot widths and setbacks.
The minimum lot widths and minimum setbacks for lots in any MPD shall be as established on the concept
plan approved for the MPD. No variances will be granted for individual lot development because someone
desires to build a structure that will not fit on the lot as designed and platted since all setbacks were
proposed by the developer and approved by the Planning Commission when the concept plan was
presented.
506 (g) Buffer requirements.
(1) A permanent 50-foot buffer area shall be established around the perimeter of any MPD. Except for a
fence along the property line, no structure of any type shall be permitted in the buffer area.
a. Any such buffer located on a lot shall be identified as such on the final subdivision plat.
b. The buffer shall meet the requirements for buffers under the Buffer Article of this Ordinance.
(2) Internal buffers as would otherwise be required by the Buffer Article of this Ordinance between land
use areas within a master planned development are waived, subject to conditions of land use approval for
the master planned development.
506 (h) Ownership Control.
(1) All of the land in a MPD initially shall be in single ownership by an individual, a partnership, tenants
in common, a corporation or by some other legal entity.
(2) The use of common open space and open green space and other common areas shall be governed
by an owner’s association which shall provide for: all users to have equal access and right of use to all
shared facilities; perpetual and continued maintenance of open and shared space; tax liability in the case
of default; mandatory membership in the owner’s association and i ts c reation is required b efore any
individual properties are sold; the method of assessment for dues and related co sts; and where
appropriate, party wall maintenance and restoration in the event of damage or destruction.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-8
Sec. 507 Quality development standards.
506 (i) MPD Concept Plan.
(1) Concept plan; administration
a. Development of a MPD shall be guided by an a pproved concept plan for t he overall pr oject.
Prior to a ny la nd developme nt activity or the issuance of a building p ermit, the concept plan
shall have b een a pproved by the Planning and Codes Department or the Planning Commission,
as appropriate, and subsequent development must substantially conform to the approved concept
plan.
b. The level of detail to be shown on a MPD concept plan shall reflect t he scale of the proposed
project. For a mixed-use development, the various areas by housing type and land use category
are to be identified and the parameters of development identified for each area. A MPD involving
only one ty pe of housing would present more detail regarding the layout of the development.
1. The conce pt plan for a MPD involving only one ty pe of housing shall con- form to the
requirements for a development under Article 12.
2. The concept plan for a mixed-u se MPD must designate the type of developme nt planned
for each area. The concept plan shall illust rate the individual lot line s within each
subdivision and the building outlines in each condominium, multi-family or non residential
project, a nd must conform to the requirement for a developme nt under Sections Article
12.
(2) Impa ct analyses.
a. Land Use impact analysis.
Every initially pr oposed MPD concept plan shall be accompanied by a n arrative specifically
addressing each of the standards set forth in Section 1205(f).
b. Every initially proposed Open Space Subdivision or MPD concept plan that is capable of generating
1,000 average daily vehicle trips or more shall be ac- companied by a traffic analysis.
(3) Modifi cations to the concept plan.
Development of each portion of a MPD must substantially conform to the approved concept plan. If any
preliminary site plan or preliminary subdivision plat is proposed that does not substantially conform, the
concept plan must first be modified before the preliminary site plan or preliminary subdivision plat can be
approved. Modifications of t he concept plan for an MPD can only be a pproved by the Pla nning
Commission, following t he same pr ocedures as t he initial a pproval of the original concept plan under
Section 1205.
(4) Conce pt Plan updates required.
The MPD concept plan is to be updated as individual site plans are approved for cons truction or final
subdivision pl ats are recorde d. Updating is a n administrative proc ess for submission to t he Planning
Department, and is in- tended to provide a record of the MPD as build-out progresses. No update will be
allowed that does not substantially conform to the approved concept plan.
Sec. 507 Quality development standards.
In order for an Open Space Subdivision or Master Planned Development to be approved, the development
must meet or exceed the Quality Development Standards of this Section.
Commented [TS2]: What determines who approves; PC or
staff?
Commented [TS3]: Move and insert after 505€
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-9
Sec. 507 Quality development standards.
507 (a) Common open space.
Acreage not utilized for residential lots, roadway access and utilities shall be placed in common open
space or devoted to recreation amenities.
(1) A minimum percent of the gross project site area shall be reserved for common open space, as
follows: no less than 25% of the total site must be set aside as open space for conservation, preservation
or passive recreational use, such as walking trails and picnicking. Examples of areas to be considered for
open space protection are scenic vistas, natural water courses, woodlands, waterfalls, coves, geologic
features, wetlands, floodplains, lakes, creeks, and land with slopes exceeding twenty-five (25) percent.
(2) Land devoted to stormwater detention facilities may not be counted toward the
25% minimum unless the facility is a permanent lake or pond, and is designed and intended for recreational
access and use by the occupants of the development.
(3) In Master Planned Developments, additional common open space may be provided and may include
active recreation areas for the proposed development, such as swimming pools, tennis courts, community
facilities, etc.
(4) Required buffers on the perimeter of the property may be included in the mini- mum open space
requirement.
(5) While common open space shall not be required to be contiguous, no individual portion of the 25%
minimum required open space shall be less than 50 feet wide in it s narrowest dimension, except as
follows:
a. The open space area, by the very nature of its designated boundaries, is less than 50 feet in
width. Examples include strips of steep slopes and “fingers” of floodplains that extend up drainage
swales.
b. Parkways between road travel ways, which must be at least 26 feet in width in order to be counted
as part of the minimum 25% requirement.
(6) No portion of the residential lots shall be credited toward the minimum open space requirement
unless the portion is included within the conservation easement. No portion of any street right-of-way or
public or private utility easement shall be credited toward the minimum open space requirements.
(7) The required common open space shall be platted at the same time that adjacent residential lots are
platted, in whole or in phases.
(8) 75% of the required open space shall be protected prior to construction and remain protected
throughout construction.
(9) Open Space Subdivisions require planting two (2) 2.5” caliper canopy trees per lot or dwelling unit.
These trees are to be planted in the common open space, rights -0f-ways, buffers, and or other areas
approved by the Planning Department.
507 (b) Residential development standards.
(1) Every residence must be connected to a public or community water system.
(2) The subdivision may be served by a community sanitary sewer system approved by DHEC and the
applicable sewerage jurisdiction.
(3) Recreation amenity (master planned developments).
In addition to common open space, every Master Planned Development must contain a community
recreation amenity of adequate size or variety to serve the development, such as a community pool, tennis
courts, active play area or basketball courts,
(4) Private open space required (Master Planned Developments).
In a Master Planned Development, every single-family or two-family dwelling on a lot smaller than 10,000
square feet, and every townhouse dwelling shall have a minimum 400 square foot private yard or patio.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-10
Sec. 507 Quality development standards.
a. The private yard or patio shall be arranged for use by the occupants of the dwelling and located
in the side or rear yard.
b. The private yard or patio must be enclosed by any combination of the following: a masonry wall,
wood fence, trellis or lattice with a minimum height of 6 feet; or an evergreen hedge, shrubs or
trees that will achieve a height of 6 f eet within 3 years of pl anting under normal growing
conditions.
(5) Lots within the subdivision shall be serviced with underground utilities (electric power, natural gas,
telephone, TV cable. etc.).
(6) All dwelling units shall have front, side and rear façades matching a common theme or
architectural detail that is consistent throughout the development. While it is the intent for all dwellings
to be sided entirely of brick, stucco or stone finish, or painted wood or fiber cement lap siding (such as
Hardiplank), vinyl siding may be used, provided it is certified by the Vinyl Siding Institute and is in-
stalled by an installer certified and recognized by the VSI.
(7) All single-family detached dwellings must include at least a 2-car garage. ????[Attached? Detached?
Not parking spaces?]
507 (c) Nonresidential development standards.
Restrictions within through-road corridors apply to all commercial and institutional uses within a Master
Planned Development (MPD).
(1) Through-road corridor defined
Land lying along and within 200 feet of the right-of-way of a public street or highway that adjoins or
traverses a MPD and that provides for movement of through traffic (in contrast to internal local streets)
shall constitute a through- road corridor.
(2) Any commercial property or public or community use property or portion of such property within the
MPD that is located within a through-road corridor shall comply with the following special d esign
standards:
a. Building setbacks.
No principal or accessory building shall be located within 50 feet from the right-of-way of a through
road. This entire setback area shall be landscaped as a landscape strip.
b. Signage.
Signs shall be limited to ground mounted of monument signs. Signs which have exposed
structures shall not be permitted.
c. Landscaping.
Any property or portion of a property that is located within a through-road corridor shall provide
at least 20 percent of its gross land area in landscaping. Landscape areas and treatments shall
be identified on the site plan for the development, subject to approval by the County.
d. Building materials.
1. The exterior walls of any building that are located within a through-road corridor [Isn’t this
in conflict with (2) a.? ] and/or is visible from a through road corridor shall be of masonry
and/or stucco-type-construction. These finish building materials shall be applied to all sides of
the building visible from the through road. Colors and materials shall be harmonious and
compatible with colors of ot her buildings within and immediately adjacent to the district.
Material colors shall be natural, muted earth tones, gray or muted color brick, stone,
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-11
Sec. 508 Conservation easements.
and/or neutral shades of concrete. Bright or accent colors may be used with discretion where appropriate
on ornamental locations on the building’s exterior, but shall not be used as the primary building material
col- or.
No buildings with metal exterior facades will be permitted within the corridor nor shall any metal façade
buildings be visible from the corridor. Metal roofs, including mansard roofs, are not considered part of a
facade.
Sec. 508 Conservation easements.
(1) All areas in Op en Sp ace Subdivisions or Master Pl anned D evelopments that are pro tected by the
provisions of these Development Standards, shall be permanently prot ected from further subdivision,
development, and unauthorized use by a conservation easement.
(2) Land within conservation easements may be included within the lots in a subdivision, or ownership
may be transferred to a homeowners’ association or to a non- profit conservation organization or land
trust organized under South Carolina law.
Sec. 509 Owner’s association.
509 (a) Homeowner’s association; when required.
For any residential development containing common open space or other lands in common ownership, a
Homeowner’s Association which provides for building and grounds maintenance and repair, insurance and
working capital shall be required.
(1) Membership in the Homeowner’s Association must be mandatory for each proper- ty in the
development.
(2) Such associations must also include homeowner’s declaration and bylaws, including covenants,
conditions and regulations applicable to each property in the development.
(3) The declaration and bylaws shall be enforced by the Association or by an Association Management
Company designated by them, which shall have the power to compel the payment of membership dues
and assessments.
(4) The homeowners' association shall be formed under the provisions of South Carolina State Law and
shall contain adequate provisions to qualify it as a “holder” un- der the South Carolina Law governing
conservation easements, if it is to act as a holder of a conservation easement.
(5) The documents creating the Homeowner’s Association must provide that an adequate reserve fund
for the Association will exist at the time that control of the Association transfers from the developer to
the purchasers of homes in the development. The reserve fund must be equal to no less than one year’s
expenses reasonably expected for the minimum operations legally required of the Association. In lieu of
a reserve fund, documents creating the Homeowner’s Association may provide for a contract committing
the developer to pay for all reasonable expenses of the Association for the one-year period following
transfer of control.
(6) The covenants, conditions and regulations shall, at a minimum, regulate and control the following:
a. Equal access and right of use to all shared facilities;
b. Perpetual and continued maintenance of open and shared space, specifically including storm
water detention facilities;
c. Tax liability in the case of default;
d. The method of assessment for dues and related costs;
e. Where appropriate, party wall maintenance and restoration in the event of damage
or destruction;
f. Animals, including household pets;
g. Signs;
Sec. 508 Conservation easements.
Pickens County UDSO: Amended 2/16/10, 9/19/16 5-12
h. Exterior items such as fences, lawn ornaments, and landscape areas and buffers;
i. Building improvements;
j. Outside storage; and
k. Overnight parking of vehicles
(7) For subdivisions, the Homeowner’s Association must be formed and incorporated at the
same time the final plat for the subdivision or any portion of the subdivision is first recorded. A
copy of the proposed Homeowner’s Association documents is to be submitted with an
application for final subdivision plat approval.
509 (b) Owners’ association.
For nonresidential development projects, an association of the property o wners that is
consistent with the requirements for a homeowners’ association will serve in lieu of the
requirements of this Section
509 (c) Condominium association.
For condominium projects, incorporation of a Condominium Association consistent with
state law will serve in lieu of the requirements of this Section, provided that:
(1) Specific maintenance responsibilities for storm water detention facilities are included; and
(2) The documents creating the Condominium Association must provide that an adequate
reserve fund for the Association will exist at the time that control of the Association transfers
from the developer to the purchasers of units in the development. The reserve fund must contain
an amount equal to no less than one year of expenses reasonably expected for the minimum
operations legally required of the Association.
1
UDSO Review
9c. matrix
Table 5.5: land use Matrix
WELL & SEPTIC
TANK
PUBLIC WATER &
SEPTIC TANK
PUBLIC WATER &
PUBLIC SEWER
MULTIPLE LOT
RURAL SPLIT
Min Size 0.5 acre (21,780 sf) 0.5 acre (21,780sf) 8,000 sf
Width 50 ft 50 ft 50 ft
Front 20 ft 20 ft 20 ft
Side 7 ft 7 ft 7 ft
Rear 10 ft 10 ft 10 ft
CONVENTIONAL
SUBDIVISION
Min Size 1 acre (43,560 sf) 0.5 acre (21,780 sf) 8,000 sf
Width 50 ft 50 ft 50 ft
Front 20 ft 20 ft 20 ft
Side 7 ft 7 ft 7 ft
Rear 10 ft 10 ft 10 ft
OPEN SPACE
SUBDIVISION
Min Size 1 acre (43,560 sf) 0.5 acre (21,780 sf) 5,000 sf
Width 50 ft 30 ft 20 ft
Front 20 ft 15 ft 10 ft
Side 7 ft 5 ft 0 ft
Rear 10 ft 5 ft 0 ft
MASTER
PLANNED
DEVELOPMENT
Min Size 0.5 acre (21,780 sf) 10,890 No Min
Width
Front
Side
Rear
Concept Plan Concept Plan Concept
Plan
COMMERCIAL
Min Size 1 acre (43,560 sf) 0.5 acre (21,780sf) 10,000 sf
Width 100 ft 50 ft 50 ft
Front 20 ft 20 ft 20 ft
Side 7 ft 7 ft 7 ft
Rear 10 ft 10 ft 10 ft
FAR 0.50 0.50 0.50
INDUSTRIAL
Min Size 1 acre (43,560 sf) 0.5 acre (21,780sf) 20,000 sf
Width 100 ft 100 ft 50 ft
Front 20 ft 20 ft 20 ft
Side 7 ft 7 ft 7 ft
Rear 10 ft 10 ft 10 ft
FAR 0.75 0.75 0.75
1
UDSO Review
9d. dhec requirements
Staff contacted a DHEC representative to inquire about the ordinance and standards as it pertains to the UDSO. Planning obtained DHEC’s
ordinance and received clarity on how DHEC measures for minimum area.
Staff’s recommendation is to keep the 0.5 acre as a minimum. The reason for this is that DHEC works on a case-by-case basis regardless
of the property size. If the soil doesn’t percolate then a septic tank cannot be installed. Additionally, DHEC has many diffe rent setback
requirements. By maintaining the 0.5 a cre minimum, it increases the chances for a property to be able to accommodate septic tank and
drain field.
1
UDSO Review
9E. tree canopy/waterway protection
PARKING LOT CANOPY STANDARDS
Vehicular use areas are defined as any area used for movement, circulation, parking and/or display of any type of vehicle, including but not
limited to parking lots, loading and unloading areas and sales service areas. Vehicular use areas under the jurisdiction of t his ordinance
shall be located screened with a ten (10) foot Class I buffer and shall comply with the following standards:
A. When a parking lot contains twenty -five (25) or more spaces, an area equal to twenty (20) percent of the total interior square
footage of the vehicular use area shall be dedicated to landscaping. The twenty (20) percent landscape requirement is in addition
to any required buffers as outlined in this ordinance and in Article 8 of the Pickens County Unified Development Standards
Ordinance.
B. Landscaped areas shall contain a mixture of native canopy trees, understory trees, evergreens/conifers and shrubs. Article 8 of
the Pickens County Unified Development Standards Ordinance details the minimum standards for plant sizes, substitutions,
installation and maintenance of landscaped areas.
C. All paved area planting plans must demonstrate the likelihood of achieving 90% canopy coverage from hardwood trees after fifteen
(15) years of growth. The objective is to prove reasonable likelihood of achieving this coverage at the time of planting/final approval.
D. The minimum landscape area for each tree shall be no less than one hundred seventy (170) square feet with four (4) foot minimum
distance between all trees and any paving at the time of planting, measured at the base of the tree.
Note: Class 1 Buffers require two (2) canopy trees, four (4) understory trees and eight (8) shrubs per 100 lineal feet.
2
UDSO Review
PICKENS COUNTY RIPARIAN SETBACK PROPOSAL
WHAT ARE RIPARIAN AREAS AND SETBACKS?
• The word “riparian” refers to land alongside streams, creeks, rivers, lakes, and other waterbodies.
• Riparian areas stabilize stream banks, limit erosion, reduce flooding, filter out pollutants, and provide habitat.
• Riparian setbacks are one tool communities can use to maintain riparian area function as land is developed or redeveloped.
Riparian setbacks are intended to manage the location of land disturbance and development within the riparian zone. Setbacks
protect waterways from impacts of development and protect residents from flooding damage and land loss through erosion.
WHICH AREAS AND STREAMS ARE REGULATED?
This ordinance would apply to lands within unincorporated areas within the jurisdiction of Pickens County.
To be protected by this ordinance, the waterbody must:
• Be a Surface Water of the State and appear on the following resource map:
The USGS Topographical Map
*Surface Waters of the State -- any stream, river, brook, swamp, lake, sound, tidal estuary, bay, creek, reservoir,
waterway, or other body or accumulation of water. They can be public or private, natural or artificial.
THE SETBACK WIDTHS
Setback distances extend horizontally from the Ordinary High Water Mark.
• 30 feet on each side of Surface Waters of the State.
• 45 feet on each side of Surface Waters of the State that meet the criteria for “Sensitive Waters”.
*OHWM -- line on the shore established by the fluctuations of water and indicated by clear physical characteristics.
*Sensitive Waters -- identified by the State to be impaired or threatened by pollutants, or classified as Outstanding
National Resource Waters, Outstanding Resource Waters, Trout Waters, or Shellfish Harvesting Waters.
BENEFITS
• Physical: Promote the health and safety of citizens by restoring and maintaining the physical, chemical, and biological integrity of
water resources.
• Economic: Preserve land characteristics, sustain or increase aesthetic value of property, save costs associated with stream
restoration or remediation projects.
• Environmental: Filtration of pollutants preventing them from entering waterbodies, satisfying NPDES Phase II requirements for
Pickens County’s designation as an SMS4.
1
UDSO Review
10. rvs, tiny homes, townhomes
Sec. 302 Recreational Vehicle (RV) Parks and Campgrounds.
302 (a) P urpose.
The purpose of this section is to provide opportunities and standards for the parking and utilization of RV’s as a
residential unit and for developed campgrounds and recreational vehicle parks that are properly sited with adequate
public st reet access and adequate access to ot her public ser vices which may be necessary. In order to create a
desirable and successful re creation envi ronment w hile pro tecting the pu blic heal th, s afety, and welfare, Pl anning
Commission review and consideration will be required for all RV Parks and Campgrounds; u nless exempted in the
following sections.
Definitions:
RV Park: A site of two-acres or more dedicated solely for the purpose of leasing individual sites for parking RV’s on a
temporary basis.
Campground: A site of two-acres or more dedicated solely for the purpose of leasing individual sites for tent camping
or individual cabins rented on a temporary basis
Site: a designated piece of land within an RV park or Campgrounds upon which an RV or tent may be placed.
302 (b) Use Standards for an RV Park or Campground
(1) Each park must have direct frontage a nd access to a collec tor or arterial st reet.
Access to each individual RV site or camp site and any other provided structures shall be from internal/private
streets. Individual sites shall not be accessed directly from a public road.
(2) RV parks and campgrounds must be a minimum of 2-acres in size.
(3) No site within an RV park or campground shall be used as a permanent residence and sha ll only
be for the use of tra vel trai lers, pickup cam pers, coaches, m otor homes, cam ping trailers, other ve hicular
accommodations, tents, park m odel un its, a nd on-site rental cabins. N o occupant may stay in a given
campground for m ore th an one hun dred eighty (180) days in any ca lendar year.
(4) Overall density of the park or camp ground shall be lim ited to no m ore than four (4) sites per acre. When a
proposed park or campground will have 4 sites or less Planning Commission review as enumerated in Section
1203 will not be required.
(5) Each site in the campground or park shall have a m inimum area of eight hundred (800) square feet and have a
stabilized and compacted vehicular parking pad of packed gravel, paving, or oth er suitable material large enough
for the standard sizes of the types of recreational vehicles allowed plus room for one additional car or truck. At
least one site must be AD A accessible. When permanent units (Cabins) are provided, at least one (1) unit must
be ADA accessible.
(6) All sites shall be setback from all side and rear property lines by a minimum of ten (10) feet and a m inimum of
twenty (20) from the edge of any public road right-of- way or the edge of any private road or drive. When the park
or campground is adjacent to a residential use, that ten (10) feet of separation must be vegetated and maintained
to provide a solid evergreen screen 8’ high.
(7) Sites may be ser ved by on-site sewa ge disposal system as p ermitted by SCDHEC; however, each individual
site may not be served with an individual system.
(8) For sites wit hin the p ark that are not otherwise serv ed with sew age disposal conn ections, an onsite bath
house (provisions for restro om a nd bathing facilities) mu st be provided.
(9) Sites sha ll not be serv ed by individually m etered power or wat er service . Wh en multiple sites are being
provided, master meter(s) must provide service to the entire park. All sites must have acce ss to public water,
either directly or communally.
(10) For parks with more than 4 sites a storm shelter shall be provided per IRC standards.
Recreational Vehicle (RV) as a Private Dwelling
302 (a) Purpose: T he purpose of this section is to provide standards for the parking and utilization of RV’s as a residential unit on private
property. The purpose of this ordinance is to ensure that RV’s are properly sited with adequate vehicular access and adequate access to
other public services while protecting the public health, safety, and welfare,
302 (b) Use Standards for RV’s as a private dwelling.
(1) Each request to use an RV as a private dwelling shall require the applicant to complete and submit an application provided by the
Building Codes Department. This application must be approved prior to an RV being authorized as a private dwelling.
(2) RV’s being utilized as a dwelling shall meet all the same standards for a traditional dwelling in regard to minimum lot si zes, street
frontage, setbacks, and curb cuts.
(3) RV’s shall count as a principal building in regard to Section 104(d) of the UDSO and only one RV shall be allowed per residential
property
(4) No RV can be parked within a FEMA designated Flood Plain or Flood Way.
(5) 911 Addressing shall be applied for each RV.
(6) Emergency Vehicle Access shall be provided.
(7) Each RV must maintain registration through the Department of Motor Vehicles so that vehicles stay in a “mobile-ready” state.
(8) RV’s built 15-years prior to the date of application shall sign an affidavit that the RV is free from dents, broken windows, loose
parts, window AC units, leaks, or duct tape.
(9) All RV’s must be anchored per American National Standards Institute (ANSI) standards for RV’s
(10) Each RV must be connected to a public sewer system or DHEC approved septic system
(11) Each RV must have its own power meter and power connection that has been inspected and approved per the International
Residential Code (IRC).
(12) RV’s shall be equipped with smoke alarms per IRC standards.
(13) RV’s shall be added to the County Assessment/Tax system the same as Mobile Homes (by VIN) and shall be taxed separate
from the land but still linked to the Parcel.
(14) RV’s shall be subject to an annual inspection by the Building Codes Department to ensure adherence to all of the standards cited
in 302(b). It is the responsibility of the RV owner to schedule this inspection annually.
Tiny Home Developments
302 (a) Purpose: T he purpose of this section is to provide standards for tiny homes as a residential unit on private property
whether as a stand -alone dwelling or part of a tiny home development. The purpose of this ordinance is to ensure that tiny
homes are properly sited with adequate vehicular access and adequate access to other public services while protecting the public
health, safety, and welfare, of the citizens of Pickens County.
302 (b) Definition: For the purposes of this ordinance, Pickens County considers a tiny home to be a self -contained dwelling
unit that is not on wheels and is less than 600 square feet.
302 (c) Tiny Homes Development Standards
(1) Each tiny home development must have direct frontage and access to a collector or arterial street.
Access to each home site and any other provided structures shall be from internal/private streets. Individual sites
shall not be accessed directly from a public road.
(1) Tiny home developments must be a minimum of 5-acres in size.
(2) Overall density of the development shall be limited to no more than four (4) homes/lots per acre.
(3) Each home shall be sited on an individually deeded lot.
(4) Each lot in a tiny home development shall have a minimum area of twelve-hundred (1200) square feet with a
stabilized and compacted vehicular parking pad of packed gravel, or paving, no smaller than 400 square feet.
(5) All lots shall be setback from all side and rear property lines by a minimum of ten (10) feet and a minimum of twenty
(20) from the edge of any public road right-of- way or the edge of any private road or drive. When the park or campground
is adjacent to a residential use, that ten (10) feet of separation m ust be vegetated and maintained to p rovide a sol id
evergreen screen 8’ high.
(6) Setbacks within a tiny home lot in a tiny home development shall be 5’ for the front, sides, and rear.
(7) Sites shall be served by an on-site sewage disposal system permitted by SCDHEC;
(8) Sites shall be served by individually metered power and water service.
(9) All sites must have access to public water.
(10) All tiny home developments shall require Planning Commission review and approval.
Sec. 315 Townhome Developments
The following design standards shall govern the development of townhouse developments.
315 (a) Requirements:
(1) Recreation amenities.
Every townhome devel opment must cont ain open space equal to 20% of the total acreage of the property with that parcel set aside as a
separate parcel of land dedicated for open space in perpetuity.
1. Lot size:
Each townhome shall be sited on an individual lot at least 2000 Square feet in size.
2. Dimensional Requirements:
1. Front setbacks 25’ with a 15’ setback allowed if using rear yard parking or rear alleys loading driveways
2. Side setbacks are 0’ for interior lot lines and 15’ for exterior lot lines (resulting in a minimum distance of 30’ between
townhome buildings).
3. Rear setback shall be 15’
4. Maximum building height shall be 35’
5. Maximum impervious surface coverage allowed is 65%.
6. Minimum lot width shall be 20’
3. Density
Density of tow nhome developmen ts (3 or m ore attached sing le family u nits) shall not exceed two (2) units per acre when served
by individual on-site septic systems and (8) eight units per acre when served by a public system.
4. Access
1. Direct v ehicular access of an individual tow nhouse sha ll be limited to the in ternal street network. Wh ere a
development exceeding 10 units fr onts on a co llector or arterial street, at least two access points shall be allowed. No
direct access for individual units shall be permitted on collector or arterial street.
2. Off-St reet parking shall be governed by Article VI
3. Bu ffers requirements shall be governed by Article VIII (4) Height restrictions shall be governed by Section IV-14
315 (b) Design and other Requirements:
Townhouse projects shall meet the following requirements:
(a) Buildings housing a series of townhouse units having a maximum length exceeding 120 feet shall have a change in plane or significant
architectural detail for each 40 feet of unbroken plane having a minimum depth of five feet with a significant feature such as a courtyard
or plaza incorporated into the façade's overall length. The plaza or courtyard shall have a minimum depth of 20' in depth and 20' in width. In
no case shall an individual building exceed 200' in length.
(b) For townhouses with front loading garages, the garage shall comprise less than 50% of the individual dwelling's width.
(c) Driveways and walkways accessing individual townhouses shall be separated by landscaped strips at least 3' in width.
(d) One upperstory tree shall be required along the front property line of the townhouses for every 20 feet of street frontage.
i. The required street trees must be indicated on the landscape plan; and
ii. New trees planted to meet this requirement shall be a minimum two-inch caliper.
(e) Parallel parking shall be designed as part of new streets and may be permitted subject to approval by County Engineer on existing County-
maintained streets.
(f) Underground utilities shall be provided.
1
UDSO Review
11. Traffic Study Policy
PURPOSE
The purpose of the Pickens County Traffic Study Policy is to standardize the requirements for various development-
related traffic studies in Pickens County. By establishing a set of metrics tied to best practices and commonly accepted
data, the decision to require or not require a traffic study shall be made based on empirical data.
TRIGGERS FOR A TRAFFIC STUDY BEING REQUIRED
The following chart shows the type and scope of traffic studies required for various projects:
Development
Trips/Day
Generated
Traffic
Impact
Analysis
Traffic
Circulation
Analysis
Traffic
Volume
Study
Speed
Study
Origin &
Destination
Study
Traffic
Capacity
Study
0-500 None1 None1 None1 None1 None1 None1
500-1000 Required None1 None1 None1 None1 Required
1000-1250 Required Required None1 None1 None1 Required
Greater 1250 Required Required Required Required Required Required
1 Unless a development has a single entrance on an existing road that has previously had a traffic volume study that stated that the road was at capacity
after previous development and would require structural changes to accommodate additional traffic flow.
REQUIRED ACTIONS AND RANGE OF STUDY BASED ON TRIGGERS
Development
Trips/Day
Generated
Peak Hour
Calculation
Un-Signalized
Intersection
Range
Signalized
Intersection
range
Future Time
Horizon
Traffic
Capacity
Study
0-500 Yes
500-1000 Yes ¼ mile ¼ mile 10 years 1 mile
1000-1250 Yes ½ mile ½ mile 15 years 1.5 miles
Greater 1250 Yes 2 miles 2 miles 20 years 2 miles
TRIP GENERATION
Trip Generation calculations shall follow the most current edition of the ITE (Institute of Transportation Engineers). At
the time of adoption of this policy the most current edition is the Eleventh (11th).
2
UDSO Review
ROADWAY/PAVING IMPACT ANALYSIS
Based on the outcome of the studies outlined above, the County Engineer shall review the data and make a
recommendation regarding, but not limited to:
• Roadway widening
• Addition of travel lanes
• Acceleration, deceleration, turning, or queuing lanes
• The addition or removal of sidewalks
• The addition or removal of bust stops
• Curb/stormwater management work
• Intersection signage including full signalization
• Roadway resurfacing or reconstruction
• Other signage as necessary
• Parking study
NOTES AND ADDENDUM
The County reserves the right to waive or require traffic studies based on unique factors specific to a particular project
or location.
DEFINITIONS
Average Daily Trips. Average Daily Trips (ADT} are the total number of trips, both in- bound and out -bound,
within a 24 hour weekday period, generated by a particular use or development.
Pass-By Trip. Trips generated by the proposed Project that would be attracted from traffic passing the proposed
project site on an adjacent street that contains direct access to the Project.
Peak Hour Trip. Peak Hour Trips are vehicle trips, both in- bound and out -bound, occurring during a 1 hour
period either during the AM Peak (7AM to 9AM ) or the PM Peak (4PM to 6PM), generated by a particular use
or Project.
Project. A Project subject to this policy encompasses all land use development projects affecting the built
environment, including changes in occupancy or intensification of existing uses, over which the City has
administrative or legislative authority, that require review and approval and issuance of a building permit,
certificate of occupancy, or other land use approval by County staff, Commissions, or Council.
Traffic Count. A traffic count is a count of traffic along a particular road, either done a digital counter (hose),
electronically via photography and OCR technology, or by human counters.
Traffic Impact Analysis (TIA) . A TIA is provided to assess the near -term and long- term effects of specific
development activity on the roadway system in a comprehensive manner. Development activity may include
rezoning, platting, development plan approvals, Thoroughfare Plan amendments, and annexations.
Traffic Circulation Analysis (TCA). A TCA is provided to determine how a development's traffic relates to existing
traffic on internal and adjacent roadways. A TCA can be required during the same stages of the development
process as a TIA, or it can be required at the time of building permit, driveway permit, development plan, or
certificate of occupancy. A TCA is smaller in scope and magnitude than a TIA and focuses primarily on localized
impacts.
3
UDSO Review
Traffic Volume Study . Traffic volume studies are conducted to determine the number, movements, and
classifications of roadway vehicles at a given location. These data help to identify critical flow time periods,
determining the influence of large vehicles or pedestrians on vehicular traffic flow.
Speed Study. Spot speed studies are conducted to estimate the distribution of speeds of vehicle in the traffic
stream at a particular position on highway. This is done by recording the speeds of vehicle at the specified location.
Origin and Destination Study. An origin-destination study is used to determine travel patterns of traffic on an
installation during a typical day. This is a study to determine and analyze trips. Trips are defined as one- way
movement, from where a person starts (origin) to where the person is going (destination).
Traffic Flow Characteristics. Traffic flow is the study of the movement of individual drivers and vehicles between
two points and the interactions they make with one another.
Traffic capacity Study. A traffic capacity study is done to deter mine the maximum number of vehicles in a lane
or a road that can pass a given point in unit time per hour per lane or roadway. The traffic capacity indicates a
capability or maximum rate of flow with a certain level of service characteristics that can be c arried by the road.
The traffic capacity of a roadway depends upon a number of prevailing roadways and traffic conditions.
Parking Study. A parking study is defined as the ratio of number of bays occupied in a time duration to the total
space available. It gives an aggregate measure of how effectively the parking space is utilized.
Roadway/Paving Impact Analysis. This is recommended by the County Engineer to determine the ability of a
given section of roadway to handle any proposed increase of various types of traffic based upon a proposed
development.
UDSO Review
12. Traffic study responsibilities
LAND USE APPLICATION
Insert as Item #9 of Land Use/Subdivision Application Process:
Each project shall be reviewed according to the County Traffic Study Policy. If a project requires a traffic study of
any type, the project may still be approved by the Planning Commission with the condition that upon completion of
the study and the subsequent review of the study by the County Engineer, any roadway, t ransit, or mobility
modifications or additions recommended by the County Engineer be agreed to and implemented by the developer.
Failure to satisfy the County Engineer would mean the project is no longer approved and would require a resubmittal
to the Planning Commission in order to proceed.
222 MCDANIEL AVENUE, B-10 • PICKENS, SC 29671 • 864.898.5950 • WWW.CO.PICKENS.SC.US
Community development
BUILDING CODES ADMINISTRATION • PLANNING • ADDRESSING
STORMWATER MANAGEMENT • ENVIRONMENTAL ENFORCEMENT
May 10, 2022
John Q. Public Delivery via Email to:
Table Rock Road jqpublic@gmail.com
Pickens, South Carolina 29671
RE: NOTICE OF ACTION
SD-22-0002 Subdivision Land Use for a 100 lot single-family residential development located at 123
Oak Street, Easley. The proposed development is located on approximately 102.71 acres of a larger
183 acre development. The applicant is John Q Public, LLC. The property owner of record is John
Q. Public. TMS# 5009-16-93-2137, 5009-20-91-2303
Dear Mr. Public:
On May 9, 2022, the Pickens County Planning Commission voted to Approve with Conditions the Subdivision Land
Use request referenced above.
The conditions for approval are:
This project is approved as submitted with the condition that a traffic study be conducted in accordance with the County’s
Traffic Study Policy and that upon completion of the study and the subsequent review of the study by the County Engineer,
any roadway, transit, or mobility modifications or additions recommended by the County Engineer be agreed to and
implemented by the developer. Failure to satisfy the County Engineer would mean the project is no longer approved and would
require a resubmittal to the Planning Commission in order to proceed.
This letter provides notification of the final decision of the Planning Commission. An appeal from this decision may be
taken to the circuit court within thirty (30) days after the date of this letter (per SC Code of Laws 6-29-1150).
Approval is only granted as applied for by the applicant and as otherwise approved by the Planning Commission; any
revision to the approved project plan should be submitted to staff to determine if it requires re-submittal to the Planning
Commission.
Approval by the Planning Commission shall be limited to the time constraints and conditions as set by the County
regarding project approval and the establishment of vested rights.
Please note that Planning Commission approval grants the applicant the right to proceed through the normal permitting
process. This is the first step. Once you are ready to begin actual work, an Application for Development Review needs
to be submitted and approved and a Development Permit issued prior to the commencement of any soil disturbance or
construction.
It has been a pleasure working with you through the Planning Commission process and we look forward to working with
you toward development permitting, project construction permitting, and site compliance. A copy of the applicable
development permit application can be found on the Pickens County website and can be submitted via our Citizen Self
Service portal.
If you have any questions, please contact Todd Steadman at (864) 898-5830. For questions regarding the submittal of
building permits for your project, please reach out to Building Codes at (864) 898-5950.
Sincerely,
Planner
1
UDSO Review
13. roads
The County Engineer is in the process of reviewing the existing Road Ordinance and Article 10 of the UDSO (which covers roadways). The
goal is to have the two documents contain the appropriate information and to be in alignment.
Staff has reviewed the UDS O in regard to shared drives, common drives, and private roads. Staff’s recommendation is to leave shared
drives and private roads as written and to eliminate common drives.
The reason for this is that it is not at all uncommon for what starts out as a common drive to later be asked to be accepted by the County
as a road yet it is not built to the appropriate standards. In addition, by not having the surfacing requirements, maximum slope requirements,
or hammerhead/cul-de-sac requirements to allow for emergency vehicle access, having up to 10 homes being serviced by a common drive
places these properties and their inhabitants at risk.
1
UDSO Review
14. county-wide mobility plan
1. Review existing materials:
• Mobility Alliance
• GPATS
• CAT Routes
• Upstate Forever
• SCDOT
• GCT
• Doodle Trail
• Swamp Rabbit
• Upstate Trail Alliance
2. Work with County agencies to identify current problem areas - whether it is the actual road condition or the traffic conditions.
• Seek input from Sheriff’s office, Emergency Services, Road and Bridges, County Engineer, County staff in general
• Reach out to our municipalities and citizens for their input on road conditions and transit/multimodal concerns
3. Generate a County map that identifies the following layers:
• Transit routes
• Bus stops/shelters
• Intersections that need signalization
• Intersections that need signage
• Roads that need widening
• Roads that need repair
• Existing multi-modal trails
• Planned multi-modal trails
4. Generate a County Map that shows the following:
• Priority investments
REQUEST FOR PROPOSALS-202319
Date Issued: March 8, 2023
Deadline for Submittal: April 10, 2023
PART 1. INTRODUCTION
Pickens County (“the County”) is seeking qualified consultants or multi qualified firms to evaluate adoption of a
County Development Impact Fee structure. The County is researching adoption of impact fees that are reflective of
our community and respond to the needs of current and anticipated growth. The impact fee or cost to future and/or
existing users to use the facility is determined by the impact each connection/user will place on the facility. The
specific study should include the following: 1) Evaluate the county’s existing fee structures 2) Recommend impact
fees in compliance with state law (S.C. Code of Law § 6-1-910, et. seq.), 3) Development of a residential and
commercial impact fee schedule, and 4) other related work detailed in Part 3 of this document.
Pickens County desires to be proactive when developing infrastructure for the provision of the services to serve new
developments, as well as serve the existing residents and businesses.
Impact Fees are one-time payments for a new development’s proportionate share of the capital cost of infrastructure.
Impact Fees are imposed on a developer by Pickens County at the time of permitting.
The purpose of the Impact Fee Study is to evaluate Pickens County’s need for development impact fees and future
capital improvement needs. The County requests a study that will include municipal facilities, transportation, fire,
stormwater, roads and bridges, and parks and recreation impact fees for the City. The proposal shall be prepared
pursuant to S.C. Code of Law § 6-1-910, et. seq.
Three (3) copies of the firm’s or team of firm’s proposal must be provided and should be hand-carried or delivered by
traceable means by 5:00 PM EST on April 10, 2023 to the following address:
Pickens County
Attn: Ralph Guarino
222 McDaniel Avenue
Pickens, SC 29671
All responses should be clearly marked on the outside of a sealed envelope with the following: “Pickens County
Impact Fee Study 202319”. For information, questions or to obtain the full RFP please contact Ralph Guarino,
Pickens County, pcfinance@co.pickens.sc.us. This RFP does not commit Pickens County to enter into a contract or
proceed with the procurement of the project. The County assumes no obligations, responsibilities and liabilities, fiscal
or otherwise, to reimburse all or part of the cost incurred by parties responding to this RFP. All such costs shall be
borne solely by each Firm.
PART 2. BACKGROUND
The recent wave of growth in Pickens County has elicited concern among staff, leadership, and citizens in regard to
ensuring that proper protections are in place to manage this growth in a sustainable fashion that is in keeping with
the vision the leadership has for the County.
The wave of growth is also causing concerns about the ability for the County to fund essential services both currently
and as a result of the growth. The effect of this study is to see what role – if any – developers should have in
mitigating the financial hardships the County may face due to rapid growth.
To date, Pickens County has not imposed development impact fees on new development. Current growth projections
indicate that increasing demands will be placed upon the County to provide necessary infrastructure and facilities and
additional capital facilities may be required to maintain current or targeted levels of service. The amount of the impact
fee to be imposed shall be a fair and equitable percentage of the cost of additional capital facilities needed due to
new development. An impact fee imposed upon residential and nonresidential development to finance specified
public facilities for which the demand is created by such development is in the best interests of the County and the
majority of its citizens.
Due to the growth and increased level of service to its residents, Pickens County would like to study the update and
addition to its construction impact fees to be used for Capital Improvement Projects and Capital Purchases; in
accordance with S.C. Code of Law § 6-1-910, et. seq.
This study is in line with the Element Goals of Pickens County’s most recent Comprehensive Plan:
Population: “Our vision is to encourage population growth in areas which have the necessary supporting
infrastructure and community facilities; preserving both a rural lifestyle and personal property rights.”
Transportation: “Our vision is to improve and maintain transportation networks for the purpose of traffic safety,
efficiency and pedestrian accommodation; and to plan a self -sustaining local and regional transportation
system.”
Land Use: “Our vision is to mitigate the impact of development by encouraging the conservation of the
agricultural character and natural resources of Pickens County; while protecting the rights of landowners.”
Community Facilities: “Our vision is to provide strategically located and high -quality infrastructure providing
sewer, water, solid waste, fire, emergency services and public safety, along with cultural/educational
community facilities, to meet the needs of the residents of Pickens County.”
PART 3. SCOPE OF WORK
The general purpose of this project is a comprehensive review of anticipated growth on Pickens County departments,
facilities, and infrastructure. Impact fees, if adopted, would be consistent with the goals and objectives of the
County’s Comprehensive Plan. The County is requesting qualified consultants to conduct a comprehensive
Development Impact Fee Study to determine the County’s development impact fees based on proposed facility and
infrastructure requirements and support a county-wide impact fee program that meets the requirements.
Proposed scope to include:
● Recommend a proposed schedule of impact fees in compliance with state law (S.C. Code of Law § 6-1-910,
et. seq.). The County would like to explore the addition of new Impact Fees. Potential impact fees could
include, but are not limited to:
o County Facilities,
o Transportation,
o Fire,
o EMS,
o Stormwater,
o Roads and Bridges,
o Parks and Recreation.
● Analysis of services to be covered by an impact fee program for growth often requires additional public
investment in new, expanded, or i mproved public facilities such as local streets, parks and trails, water and
sewer system, etc.
● A written assessment of how an impact fee in the County could assist in meeting financial needs either directly
or indirectly for the County’s attainable housing goals.
● Provide enough information and the necessary findings to help the County determine a full slate of the
development impact fees based on the proposed infrastructure requirements to support the County’s growth
projections and the County’s Capital I mprovement Plan. The consultant will work with County staff to
determine other supporting infrastructure (i.e., equipment, vehicles, etc.) or other operational services that
could rightfully be included in the fee program to ensure the costs of such suppor ting infrastructure are paid
by the new developments.
● The County and Consultant will plan any necessary meetings as needed. The chosen consultant will need to
attend and present the final findings of the study to the County Council.
● Prepare draft and fin al reports to submit to the County containing background information, methodology,
findings, and recommendations. More specifically, consultant shall prepare a report containing, but not limited
to, the following:
o Background information
o Description of the overall methodology
o Supporting justification
o Recommended Impact Fee Structure
o The analysis and calculations that provide each legal nexus between the recommended fee and the
impact created by the new development.
o The relationship between the fee’s use and the type of project on which it would be imposed.
PART 4. QUALIFICATION REQUIREMENTS
Firms should have experience with the type of study requested and must be capable of providing the proposal and
have the ability to respond to requests in a timely manner.
Submittal Requirements
Firms shall submit written qualifications that clearly demonstrate their ability to provide quality services in a timely and
cost-effective manner. Submittals should include the following and be limited to 20 pages, not including any standard
forms or project team resumes:
● Firm Description- provide a brief description of the firm including firm size and area of specialization, location
of corporate headquarters, and potential satellite office proposed to handle this project;
● Project Team- Provide names and resumes of key professionals who would be assigned to the project. Each
team member’s education and experience shall be listed. The project manager and team structure shall be
clearly identified;
● Statement of Project Understanding- The consultant shall state in succinct terms their understanding of what
is required by this Request for Proposals;
● Scope of Services- The Consultant is encouraged to elaborate and improve on the tasks listed in the R FP;
however, the Consultant shall not delete any requested scope tasks unless explicitly noted;
● Project consulting services itemized by task and an estimated total project cost provided as line items
concerning scope of work;
● Examples of similar projects completed by the Consultant;
● Three (3) references, including current contact name and phone number for similar recent projects; and
● All required forms in Appendix A.
Addendums and Contractor Questions
All questions should be submitted to Ralph Guarino at p cfinance@co.pickens.sc.us. All questions will be addressed
through addendums that will be submitted to all qualified Consultants. Pickens County will make every attempt to
answer all questions. However, questions received after the April 10, 2023 deadline may not be addressed.
PART 5. SELECTION
A committee of County staff representatives will review all submitted proposals. The intent is to select the most qualified
firm. The evaluation criteria are as follows:
● Qualifications, experience and technical competence of the firm and specific individuals; 25pts
● Specific related experience in terms of type and scope of past studies/projects; 20pts
● Ability to respond and complete the work in a timely manner; 30pts
● Cost; 25pts
Notification
All responding firms will receive written notification regarding the status of their proposal. This work may be awarded
in whole or in part at the sole discretion of the County. The County will execute a contract with the selected firm prior
to the beginning of actual service. In general, the contract will comply with applicable laws and standard provisions
and shall contain the following terms:
● Detailed scope of services;
● Schedule for providing services; and
● Cost of services.
Award of Contract – Rejection of Proposal
Pickens County reserves the right to consider as unqualified to do the work any Consultant who does not habitually
perform, or does not plan to perform, with his own forces the major portion of the work involved in this Contract. The
maximum amount of subcontract work shall not exceed thirty percent (30%) of the total project cost without prior
approval of Pickens County. Pickens County reserves the right to either accept or reject any proposal where the
planned subcontract amount exceeds thirty percent (30%) of the total bid amount.
Reserved Rights
The County shall not be responsible for any of the costs associated with responding to this request for qualifications
and all submitted materials shall become the property of the County. Furthermore, the County expressly reserves the
following rights and options:
● To reject any or all terms and re-advertise if deemed necessary;
● Waive any or all formalities and technicalities; and
● Approve, disapprove or cancel all services associated with the project.
Pickens County does not discriminate on the basis of race, color, national origin, sex, religion, age or disability in
employment or the provision of services.
APPENDIX A
RESPONDENT INTRODUCTION FORM
Respondent Organization Information: If the respondent is a joint venture, include information from each member
of the joint venture
Business Name
Business Address
Business Type:
(corporation, partnership,
joint venture, etc.)
Respondent(s) Point of Contact: This person will be the single point of contact on behalf of the respondent(s)
organization, responsible for correspondence to and from the organization to the County. The County will send all
Project-related communications to this contact person
Name:
Address:
Telephone number:
E-mail Address:
Major Participants:
Major Participant Name/Contact Address of Head Office Description of
Role/Prequalification
Acknowledgement of RFP Addenda: Identify and acknowledge all RFP addenda provided or question responses
by number and date.
Addenda Number: Addenda Date: Acknowledgement: (check box)
◻
◻
◻
Signatures: This form is required to be signed by authorized representatives of the respondent(s) organization. If the
respondent(s) is a joint venture, the joint venture members shall sign the form. If the respondent(s) is not yet a legal
entity, the known Major Participants shall sign the form. By signing below, the respondent(s) certifies the truth and
correctness of the information in the above sections, including this respondent(s) Introduction Form.
Printed Name: Signature: Date: Organization/Role:
APPENDIX B
Proposal Form: This form is required to be filled out to determine service cost for the items listed below.
Item Unit Price
Evaluate and update the County’s existing fees,
including:
● Fire,
● EMS,
● Permitting,
● Planning, and
● Stormwater.
Lump Sum
Recommend new impact fees in compliance with state
law (S.C. Code of Law § 6-1-910, et. seq.), including
but not limited to:
● Transportation,
● Fire,
● Stormwater,
● Roads and Bridges,
● County Facilities, and
● Parks and Recreation.
Lump Sum
Development of a residential and commercial impact
fee schedule.
Lump Sum
Develop an Impact Fee Study Report Lump Sum
Present reports and fee schedule to County Council. Lump Sum
TOTAL
-
1205 (j): PC Review of Modifications to Approved Projects:
In addition to any requirements described elsewhere in this document, the following circumstances shall necessitate
that a project previously approved by the Planning Commission be brought back to the Planning Commission for
approval:
1. There is a change of use (in any way introducing in any form or altogether deleting a commercial,
institutional, or residential use from the project).
2. There is an increase in density greater than 5% of what was approved.
3. There is a decrease in open space by more than 5% of what was approved.
4. There is an increase in vehicular trip generation by 500 or more trips regardless of project size.
5. Change in location of access drive (if not approved by County Engineer).
6. Change in location of structures by more than 35’ in any direction.
7. Change in orientation of any structure by an angle greater than 45-degrees.
8. Change in any specific condition previously stipulated by Commission.
9. Other changes deemed substantive by Planning, Engineering, Stormwater, or Emergency Services
Source: Pickens County website. First collected Nov 14, 2026.