HP-20-15, 30 N. Main St. (City)
I. THE REQUEST
Applicant: R. Scott Bell
Status of the Applicant: Project Architect
Request: Design Review for proposed 900 sq. ft. metal canopy attached
to the rear of the existing structure
Location: 30 N. Main St.
Present Use/Zoning: Commercial / CBD
Tax Map Reference: 228-12-04-039
Adjacent Property
Land Use and
Zoning:
North – Commercial / CBD
South – Commercial / CBD
East – Commercial / CBD
West – Commercial / CBD
II. BACKGROUND
The applicant is requesting design review
approval to install a metal canopy on the rear
elevation of a commercial building that fronts
on N. Main St. between W. Hampton and W.
Liberty St. , and that back s up to the
municipal parking garage at the corner of
Sumter St. and W. Hampton Ave. The
building presently is occupied by kitchen
staff operations and storage associated with
the neighboring Sidebar Restaurant.
Architectural/Historic Context
Based on available records from the South Carolina Department of Archives and History
and the Sumter City-County Planning Department, the structure under review is within
the Historic Downtown and is also part of the National Register Historic District.
2
30 N Main St. was constructed circa 1880. It is known colloquially as “The Berger
Building,” and has some historical significance as The Lyric Theater was located in this
building. It appears on the Sanborn Maps in 1894. One of the oldest Sumter stores, it has
been primarily used throughout the years as retail commercial space, under the name
“The Happiness Store,” and “Levi Brothers.” Beryl’s Dress Shop and the Berger
Department Store were located here as well.
The structure is brick, 2-stories tall and has a rectangular floor plan. Previously approved
work included uncovering second-story windows on the front and rear façades, the
application of stabilizing metal star-shaped anchor bolts on the rear elevation, painting
the entire building and replacing the storefront and awnings. These renovations were
designed to return the building to a more historic appearance.
Site Photos:
Above: Rear elevation of 30 N. Main St
as viewed from the west
Above: Rear Elevation of 30 N Main Street
as viewed from the south.
Scope of Work:
The Applicant intends to complete rear elevation renovations, which face an existing alley.
Renovations include construction of a 900 sq. ft. metal canopy and railings attached to the
rear of the building to serve as a cover for two commercial meat smokers.
Based upon the submitted architectural elevation/rendering, the following is proposed:
1. Installation of a 900 sq. ft. galvanized steel canopy attached to rear face of 30 N.
Main St.
2. Installation of four (4) steel columns, painted to match the existing door color of the
adjacent building at 2 W. Hampton Ave.
3. Installation of a metal pipe safety railing at ground level around the perimeter of
the canopy, painted to match the existing door color of the adjacent building at 2 W .
Hampton Ave.
4. Installation of a new 450 sq. ft. concrete pad under the canopy.
3
4
Design review approval is required prior to the proposed work.
The Design Review Guidelines Manual states:
6.1 Commercial Properties (Additions)
Exterior additions to historic buildings in the Downtown Historic District can provide
valuable addition al s pace to accommodate new uses or growing businesses. However,
insensitively designed additions can radically alter the historic appearance of the building
and destroy important features. Careful design and location of new additions can
complement rather than detract from the character of a historic building and the district as
a whole.
K. Distinguish a new addition from the historic bu ilding with a simple and unobtrusive
design.
Design an additi on to be subordinate to the existing building in size , desig n, and
detailing.
Locate a new addition on the rear elevation where it will not be highly visible from
the public right of way.
Include simpl ified a rchitectural features derived from similar features on the
historic building.
Ensure that colors and materials are harmonious wi th the materials of the h istoric
building.
Staff Analysis:
The proposed addition meets the above standard s. The proposed material for the
metal canopy is galvanized steel , as are the support beams. The railing and steel
beams will be painted to match the existing brown color found on the doors of the
adjacent building at 2 W. Hampton Ave . This colo r choice is consistent with the City
of Sumter’s Historic Preservation Color Palette.
III. STAFF RECOMMENDATION
Staff recommends approval of this request . The overall proposal is compat ible with
established guidelines.
IV. DRAFT MOTION
1.) I move that the Sumter Historic Preservation Design Review Committee approve
HP-20-15 in accordance with the materials, photographs, and co nstruction details
submitted an d referenced in the Staff Report based on compliance with Design
Review Guidelines.
5
2.) I move that the Sumter Historic Preservation Design Review Committee deny HP -
20-15.
3.) I move that the Sumter Historic Preservation Design Rev iew Committee enter an
alternative motion.
VI. HISTORIC PRESERVATION – JULY 23, 2020