1
Join from PC, Mac, iPad, or Android:
https://us02web.zoom.us/j/84032156754?pwd=WYvEQ9nd18mQ6gqBuvDo9ulsSObJis.1
Passcode: 029160 +16469313860 Webinar ID: 840 3215 6754
City of Beaufort
1911 Boundary Street
Beaufort Municipal Complex
Beaufort, South Carolina 29902
(843) 525-7070
City Council Quarterly Capital Projects Workshop Agenda
November 17, 2026
Statement of Media Notification
"In accordance with South Carolina Code of Laws, 1976, Section 30-4-80(d), as amended, all
local media was duly notified of the time, date, place and agenda of this meeting."
Quarterly Capital Projects Workshop - Planning Conference Room - 5:00 PM
Please note, this meeting will be broadcast via zoom and live-streamed on YouTube. You
can view the meeting at the City's page; City Beaufort Government
I. Call to Order - Philip Cromer, Mayor
II. Discussion
A. Quarterly Capital Improvements Program (CIP) Update
III. Adjourn
Page 1 of 41
City of Beaufort
Department Request for City Council Agenda Item
To: City Council Date: 11/05/2026
From: Raul Dominguez, Capital Projects Director
Item Name: Quarterly Capital Improvements Program (CIP) Update
Meeting Date: November 17, 2026
Department: City Managers Office
Background Information:
Introduction:
Capital Improvements Director, Raul Dominguez, and David Gregory, Capital Improvements
Program Coordinator, will be providing an update on current and completed Capital Projects.
Background:
Legal Authority:
Staff Recommendation:
Placed on Agenda For:
Attachments:
1. 11-17-26 Quarterly Capital Projects Workshop
Page 2 of 41
Capital Improvement
Quarterly Meeting
November 17, 2026
Presented By
Raul Dominguez and David Gregory
Page 3 of 41
Project Recap and Status
• This reporting period the CIP department would like to provide
council and stakeholders with a 24-month recap of progress being
made to improve the cities infrastructure, sustainability and resiliency
for future growth.
• The outcome supports the hard work by management and staff to
fulfill the strategic plan as set forth by our City leaders.
Page 4 of 41
Total Projects Undertaken: 25
• Streetscapes 2
• Parks 4
• Facilities 5
• Stormwater 6
• Roadway 1
• Trails 2
• Other Infrastructure 2
• Streetscape Stormwater 3
Page 5 of 41
Project Identification: Streetscapes
• 170/21 Sidewalk
• Airport Road
Page 6 of 41
170/21 Sidewalk
Description
City project to complete the sidewalk from
Boundary Street along US 21 to the Spanish
Moss Trail and install lighting.
Schedule:
Initiated in 2021 postponed in May 2024.
Page 7 of 41
Airport Road
Description
The project was two-lane urban section with
an 8’ multi use path on one side. It also
included a traffic signal and left turn lane
improvements on US 21 (Sea Island Pkwy).
Schedule:
Completed July 2024
Page 8 of 41
Project Identification: Parks
• Southside Phase 1 & 2
• Washington St. Park
• Pigeon Point Park
• 1st South Carolina Volunteer of African Descent Park
Page 9 of 41
Southside Park
Phase 1 and 2
Description
Phase 1: Included parking lot, pavilion and
restrooms, two age-appropriate playgrounds and
safety surfaces, fencing, benches, picnic tables,
fountains and landscaping .
Phase 2: Elements are in engineering and design this will
include Fitness Nodes, additional Trails, and Dog Park
improvements.
Schedule:
Phase 1 completed February 2025
Funding for Phase 2:
Park and Tourism Fund: $275,000
Consultant Contractor
Davis and Floyd TBD
Page 10 of 41
Washington
Street Park
Description:
The proposed improvements to Washington Park
included a new Pavilion, Basketball ½ Court,
Rolling mounds, Benches, and Small walking trail.
Schedule:
Official Opening and Ribbon Cutting : May 2026
Consultant Contractor
Davis and Floyd Beaufort Construction
Page 11 of 41
Pigeon Point
Park
Description:
Pigeon Point Playground serves children
ages 2–12 with a variety of play features
designed to meet different age groups and
ADA requirements.
Schedule:
Completed July 2025
Page 12 of 41
1st South Carolina
Volunteer Park
Description:
Park is located off Boundary St. along the bluff. The team comprised of
stakeholders and staff are currently working through design. This will be a passive
park with visual displays and interactive areas for visitors to enjoy. Focus will be on
the history of the 1st SCVIOAD.
Schedule
The relocation of the 1st South Carolina Volunteers of African Descent historic
marker was moved to 2248 Boundary Street in May 2026.
Final Package Deliver to Council anticipated November 2026
Funding
General Fund, Beaufort County Contribution
CIP team seeking funding for construction
Consultant Contractor
Davis and Floyd TBD
Page 13 of 41
Project Identification: Facilities
• Carnegie Library
• 500 Carteret
• Arsenal
• Fire Station 1
Page 14 of 41
Carnegie Library
Exterior
Improvements
Description:
Project to include roof repairs, gutters and
downspouts, soffit and eave repair, engineering
services and interior repairs. Roof repair continues in
coordination with SHPO
Current Schedule
Construction started Mar 2026
Estimated completion Nov 2026
Funding
ARPA Funds: $276,000
Contractor
Luna Roofing and Meadors Architecture
Page 15 of 41
Carnegie Library
Interior
Description:
The City plans to undertake interior restoration of
the Carnegie Library. The Library project will
focus on preserving and enhancing its historic
interior.
Current Schedule
Contract Approved Aug 26
Funding
Parks & Tourism $200,000
Consultant Contractor
Meadors Mashburn
Page 16 of 41
500 Carteret Street
Window
Replacement
Description:
The repairs on building included the
replacement of old aging windows, and
windowsills along with some wood rot.
Current Schedule
Project partially completed in August 2025
with the replacement of 40 windows.
Remaining window replacement is pending
funding
Page 17 of 41
Arsenal Windows
Restoration
Description:
The Arsenal, originally constructed between 1795 and 1798, is
undergoing window restoration that includes the removal of
all exterior window components, including jambs, trim, sashes,
and sills, for restoration and rehabilitation.
Current Schedule
Contract Awarded Aug 2026
Funding
State Accommodations Tax Fund:: $200,000
Consultant Contractor
Meadors Shenandoah Restorations
Page 18 of 41
Arsenal Walls
Restoration
Description:
The City plans to undertake the Arsenal wall
restoration to enhance and preserve the
architectural integrity.
Current Schedule
Contract Awarded Aug 2026
Funding
State Accommodations Tax Fund: $239,639
Consultant Contractor
Meadors Mashburn
Page 19 of 41
Fire Station One
Renovation
Description
The City is conducting much needed renovations
to Fire Station #1 at 135 Ribaut Road. The scope
of work includes roof and window replacement,
a new secure entry, office renovations, raising the
front and rear middle bay doors.
Schedule:
Recommendation to Council : Nov 2026
Funding:
General Fund: $800,000
Contractor
Contract award pending
Page 20 of 41
Project Identification: Stormwater
• King St
• Charles & Craven St
• Bayard St
• Port Republic
• Pigeon Point Study
• Battery Shores Drainage
Page 21 of 41
King Street - The
Point Downtown
Drainage
Description
The project included upgrading the drainage network
on King Street between Hamilton and West Streets
Current Schedule
Construction started December 2025
Completed August 2026
Funding
SCIIP Grants: $6,031,314
ARPA Fund: $727,827
Consultant Contractor
Davis and Floyd JH Hiers
Page 22 of 41
Charles &
Craven Street
Stormwater
Description:
SCOR ASIP-funded project to upgrade storm drainage along Charles
Street from Craven Street to the Harbor, including portions of Craven
Street and North Street
Current Schedule
Construction started November 2025
Completion estimate December 2026
Funding
ASIP-funded : $11,962,093.51
Managing Agency
SCOR
Consultant Contractor
McCormick Taylor and Davis Floyd Gulf Stream Construction
Page 23 of 41
Bayard Street-
Drainage
Improvement
Description
The work within the Beaufort River critical area is part of
the Bayard Street Drainage Improvements Project, which
is designed to improve stormwater conveyance along
Bayard Street.
Current Schedule
USACE and SCDOT permits have been received
Still waiting for EPA Funding
Funding
Stormwater Fund- $419,091
EPA Grant Fund- $683,464 (anticipated)
Consultant Contractor
Davis and Floyd TBD
Page 24 of 41
Port Republic &
Carteret Streets-
Drainage
Description
Project to upgrade storm drainage along Port
Republic Street from Scott Street to the Harbor,
including portions of Carteret Street.
Current Schedule
Project postponed due to funding and staff
continues to seek funding sources
Page 25 of 41
Pigeon Point
Drainage Study
Description:
A professional study is needed to determine the best path forward
for improving and then maintaining appropriate stormwater
drainage in the Pigeon Point neighborhood.
Schedule:
As of June 2026, Davis & Floyd recommended expanding the
study area to address drainage concerns; the City is currently
seeking eligibility confirmation before proceeding.
Proposed completion date of November 2026
Funding:
Stormwater Fund-$54,000
Grant Fund- $162,000
Consultant
Davis and Floyd
Page 26 of 41
Battery Shores
Drainage
Description
Battery Shores subdivision main outfall that
provides drainage for over 50% of the
properties within the subdivision requires
repairs and re-engineering. Stormwater runoff
was not allowed to escape the system and was
backing up onto the properties of homeowners.
Current Schedule
Completed 2026
Page 27 of 41
Project Identification: Roadway
• Battery Shores Paving
Page 28 of 41
Battery Shores
Paving
Description
The City entered an MOU with the County on
November 12, 2024, for the County's
contracted paving provider to repair and
completely repave the roads within the Battery
Shores neighborhood.
Current Schedule
Completed 2026
Page 29 of 41
Project Identification: Trails
• Depot Road-Spanish Moss Trail Extension
• Spanish Moss Trail- North Street Sidewalk
Extension
Page 30 of 41
Depot Road-Spanish
Moss Trail Extension
Description
This is a pass through CDBG grant to Beaufort
County for a Pedestrian Pathway to connect the
Spanish Moss Trail, down Depot Road, crossing
Ribaut Rd, to Bay Street. Beaufort County is
managing this project.
Current Schedule
Beaufort County's Spanish Moss Trail Downtown
Connection Grand Opening and Kids In Parks
National Designation was held February 2026
Page 31 of 41
Spanish Moss Trail- North
Street Sidewalk Extension
Description
North St. connector to the Spanish Moss Trail
(SMT). This would allow access to the SMT at
the end of North St.
Current Schedule
Completed 2024
Page 32 of 41
Project Identification: Other Infrastructure
• Pigeon Point Landing
• Henry C. Chambers Waterfront/Preserving the
Promenade
Page 33 of 41
Pigeon Point Boat
Landing
Improvements
Description:
Pigeon Point Boat Landing consists of a dock with five
floating units totaling 122 L.F., single launch boat ramp
15’wide x 90’long, approximately 11 parking spaces, and
Pinckney park with crabbing dock.
Schedule
SCDES permit has been issued, USACE still pending
Preliminary Estimate for Construction : $1,500,000+
Funding
TBD
Consultant
Davis and Floyd
Page 34 of 41
Henry C. Chambers
Waterfront Park
(Preserving the
Promenade)
Description:
The project moves to the design and permitting phases, where the
consultant team will focus on marine, coastal, geotechnical, and structural
engineering; landscape architecture; NEPA and environmental review
support; permitting; grant writing and administration; public engagement;
bidding assistance.
Schedule
Recommend Contract to Council Nov 2026
Funding
Park and Tourism Fund: $925,000
State: $3,000,000
County A&H: $2,000,000
Sale of Property: $1,266,595
Consultant Contractor
TBD TBD
Page 35 of 41
Project Identification: Streetscape
Stormwater
• Allison Road
• Calhoun St.
• Duke St.
Page 36 of 41
Allison Road
Description
Construction of a 10-foot multipurpose
bicycle/ pedestrian path connecting Ribaut
Rd to the SMT. Other major improvements
include utility undergrounding and improved
drainage.
Current Schedule
Project Completed 2025
Page 37 of 41
Calhoun Street
Description
This is a streetscape and drainage project. It
includes a closed drainage system, and it
includes 2 street lanes, on street parking, and
5’ foot sidewalks.
Current Schedule
Postponed due to funding
Page 38 of 41
Duke Street -
Streetscape &
Drainage
Description
Streetscape and Drainage Improvements from Hamar
Road to Bladen Street
Current Schedule
Construction started August 2026
Completion estimate January 2027
Funding
ARPA Fund- $1,013,180
General Fund- $655,031
BJWSA Partnership- $428,441
Consultant Contractor
Davis and Floyd JH Hiers
Page 39 of 41
Summary
As you can see the city has been very busy over the last 2 years completing a
variety of projects in different locations. Just to recap:
• Projects Completed – 11
• Projects Postponed – 3
• Projects Under Construction – 3
• Projects in Plan & Design – 7
• Projects out for Bid – 1
Page 40 of 41
QUESTIONS?
Page 41 of 41