Joint Hilton Head Island Town Council and County Council Meeting — Agenda Packet
Beaufort County · Beaufort County · County Council Meeting · meeting of Feb 12, 2025 · Agenda packets
Open the original document More from Beaufort County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Joint Hilton Head Island Town Council and County Council
Meeting
Beaufort County, SC
Buckwalter Recreation Center
905 Buckwalter Parkway, Bluffton SC 29910
Wednesday, February 12, 2025
5:00 PM
AGENDA
COUNCIL MEMBERS:
ALICE HOWARD, CHAIR ANNA MARIA TABERNIK, VICE CHAIR
DAVID P. BARTHOLOMEW PAULA BROWN
LOGAN CUNNINGHAM GERALD DAWSON
YORK GLOVER MARK LAWSON
LAWRENCE MCELYNN JOSEPH PASSIMENT
THOMAS REITZ
1. CALL TO ORDER: Alice Howard, County Council Chair
2. PLEDGE OF ALLEGIANCE AND INVOCATION: Alice Howard, County Council Chair
3. STATEMENT OF COMPLIANCE WITH FOIA: Alice Howard, County Council Chair
4. APPROVAL OF AGENDA
5. REVIEW OF SCDOT PROPOSALS RECEIVED ON JANUARY 30, 2025
6. REVIEW OF FUNDING AVAILABLE FOR THE PROJECT.
7. DISCUSSION OF JOINT RESOLUTION
8. ELECTED OFFICIAL COMMENT PERIOD
9. PUBLIC COMMENT PERIOD – 30 MINUTES TOTAL
10. ADJOURNMENT
TO WATCH COMMITTEE OR COUNTY COUNCIL MEETINGS OR FOR A COMPLETE LIST OF AGENDAS AND
BACKUP PACKAGES, PLEASE VISIT:
https://beaufortcountysc.gov/council/council-committee-meetings/index.html
1
3-lane Bridge (capable of accommodating 4 th lane) with using portion of Westbound bridge for o island and one of the old Skull Creek for access to Pinckney Island
Retain existing 2 -lane Westbound traic as -is
Remove eastbound Mackay Creek Bridge
Retain existing 2 -lane Westbound traic as -is
Retain eastbound Skull Creek Bridge to allow for
2-way traic to and from Pinckney Island
Build new 3 -lane “lifeline” bridge over
Mackay, Pinckney and Skull Creek
(capable of carrying 4-lanes (two-lanes in
each direction) temporarily)
Build new Hogg Island connector
required for “lifeline” bridge
connection to existing US 278
2
Item 5.
3-lane roadway from Moss Creek to Spanish Wells – lifeline bridge (3-lanes with accommodations for 4th lane)
3
Item 5.
TRAFFIC PATTERN ON NEW BRIDGE CONSTRUCTION - TYPICAL SECTION WITHOUT SHARED-USE PATH
TRAFFIC PATTERN ON NEW BRIDGE CONSTRUCTION - TYPICAL SECTION WITH SHARED-USE PATH
EXISTING WESTBOUND MACKAY CREEK BRIDGE - TYPICAL SECTION
OPTION 2 & 4
OPTION 1 & 3
KCI TECHNOLOGIES
3014 SOUTHCROSS BOULEVARD, ROCK HILL, SC 29730
22'-0"
34'-0"
(T
Y
P
.)
3
'-6
"
0.02 ft/ft 0.02 ft/ft
1'-0" MASH BARRIER
US 278 EASTBOUND
58'-3" (OUT-TO-OUT )
SHOULDER
10'-0"
LANE
12'-0"
LANE
12'-0"
LANE
12'-0"
SHOULDER
10'-0"
FINISHED GRADE
"2
1
1
SLIPFORM EDGE (TYP.)
GUTTERLINEGUTTERLINE
� RELOCATED US 278 EASTBOUND
22'-0"
34'-0"
(T
Y
P
.)
3
'-6
"
0.02 ft/ft 0.02 ft/ft
1'-0" MASH BARRIER
US 278 EASTBOUND
73'-3" (OUT-TO-OUT )
SHOULDER
10'-0"
LANE
12'-0"
LANE
12'-0"
LANE
12'-0"
SHOULDER
10'-0"
FINISHED GRADE
"2
1
1
SLIPFORM EDGE (TYP.)
GUTTERLINEGUTTERLINE
� RELOCATED US 278 EASTBOUND
19'-8"
US 278 WESTBOUND
39'-4" (OUT-TO-OUT)
19'-8"
1'-8"
1'-8"
LANE
12'-0"
SHOULDER
6'-0"
LANE
12'-0"
SHOULDER
6'-0"
SHARED-USE PATH
14'-0"
####
SHEET
-B01030450P
BRIDGE PLANS ID
QUAN.
DR.
DATECHK.BY
REVIEWED
DES.
REV.
REV.
DATECHK.BY
REV.
DESCRIPTION OF REVISION
Adam.Lansing 1/8/2025 9:22:38 AM US 278 Alt Typical Sections.dgn
BEAUFORTCOUNTY: US 278ROUTE:
DEPARTMENT OF TRANSPORTATION
SOUTH CAROLINA
MACKAY CREEK
TRAFFIC PATTERN OVER
JCM
R
I
IF
ETAC
T
R
E
C
UAFO
OHT
ZI
N
O
ITA
NO
S
HTU
RAC
ILO
A
NO. 651
KCI
TECHNOLOGIES
INC.
4
Item 5.
ALTERNATE TRAFFIC PATTERN ON EXISTING SKULL CREEK BRIDGE - TYPICAL SECTION
TRAFFIC PATTERN ON NEW BRIDGE CONSTRUCTION - TYPICAL SECTION WITH SHARED-USE PATH
TRAFFIC PATTERN ON NEW BRIDGE CONSTRUCTION - TYPICAL SECTION WITHOUT SHARED-USE PATH
OPTION 2 & 4
OPTION 1 & 3
KCI TECHNOLOGIES
3014 SOUTHCROSS BOULEVARD, ROCK HILL, SC 29730
22'-0"
34'-0"
(T
Y
P
.)
3
'-6
"
0.02 ft/ft 0.02 ft/ft
1'-0" MASH BARRIER
US 278 EASTBOUND
58'-3" (OUT-TO-OUT)
SHOULDER
10'-0"
LANE
12'-0"
LANE
12'-0"
LANE
12'-0"
SHOULDER
10'-0"
FINISHED GRADE
"2
1
1
SLIPFORM
EDGE (TYP.)
GUTTERLINEGUTTERLINE
� RELOCATED US 278 EASTBOUND
19'-8" 19'-8" 19'-8" 19'-8"
LANE
12'-0"
SHOULDER
6'-0"
LANE
12'-0"
SHOULDER
6'-0"
LANE
12'-0"
SHOULDER
6'-0"
LANE
12'-0"
SHOULDER
6'-0"
1'-8"
1'-8"
US 278 WESTBOUND
39'-4" (OUT-TO-OUT)
PINCKNEY ISLAND ACCESS (CURRENT US 278 EASTBOUND)
39'-4" (OUT-TO-OUT)
22'-0"
34'-0"
(T
Y
P
.)
3
'-6
"
0.02 ft/ft 0.02 ft/ft
1'-0" MASH BARRIER
US 278 EASTBOUND
73'-3" (OUT-TO-OUT )
SHOULDER
10'-0"
LANE
12'-0"
LANE
12'-0"
LANE
12'-0"
SHOULDER
10'-0"
FINISHED GRADE
"2
1
1
GUTTERLINEGUTTERLINE
� RELOCATED US 278 EASTBOUND
SHARED-USE PATH
14'-0"
1'-0"
####
SHEET
B02-030450P
BRIDGE PLANS ID
QUAN.
DR.
DATECHK.BY
REVIEWED
DES.
REV.
REV.
DATECHK.BY
REV.
DESCRIPTION OF REVISION
Adam.Lansing 1/8/2025 9:22:38 AM US 278 Alt Typical Sections.dgn
BEAUFORTCOUNTY: US 278ROUTE:
DEPARTMENT OF TRANSPORTATION
SOUTH CAROLINA
SKULL CREEK
TRAFFIC PATTERN OVER
JCM
R
I
IF
ETAC
T
R
E
C
UAFO
OHT
ZI
N
O
ITA
NO
S
HTU
RAC
ILO
A
NO. 651
KCI
TECHNOLOGIES
INC.
5
Item 5.
0.025 FT/FT0.020 FT/FT0.020 FT/FT
12'12'
16'
12' 11' 11' 11' 12'2'2' 5'10' 15'
12' 12' 12' 12' 12' 12'5'10'2'
0.020 FT/FT
0.020 FT/FT
2:1
4:1
4:1
2:1
8% 8%
2'
PLANS PREPARED BY:
TYPICAL SECTION
PAVEMENT DESIGN
TO STA.CLASSIFICATION
FUNCTIONAL
NO.
03_Typical_Section
MPH FROM STA.
DESIGN SPEED
NO.
SHEETPROJECT ID NO.COUNTYSTATEDIV. NO.
FED. RD.
3 S.C.
COLUMBIA, S.C.
SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION
TYPICAL SECTION OF IMPROVEMENT
SCALE 1"H =SCALE 1"V =
COLUMBIA, S.C.
DEPARTMENT OF TRANSPORTATION
SOUTH CAROLINA
NTS NTS
TYPICAL
ROUTE
BEAUFORT US 278 3P030450
NOT FOR CONSTRUCTION
RIGHT-OF-WAY PLANS
R/W
EX.
R/W
EX.
100'R/W
NEW
R/W
EX.
(40' SHOWN)
VARIES 40'-55'R/W
EX.
L
LRELOC. C
EXIST. US 278 C
LEXIST. US 278 C
(40' SHOWN)
VARIES 40'-55'R/W
NEW
20'
R/W
EX.
R/W
EX.
R/W
NEW
(55' SHOWN)
VARIES 55'-70'
(55' SHOWN)
VARIES 55'-66'
8'
LEXIST. US 278 C
2'
2'12'
50'
12'12'2'8'4'2'10'
14'
2'
0.020 FT/FT
4:1
2:1
6:1
8% 0.020 FT/FT 0.020 FT/FT
TYPICAL SECTION BETWEEN SQUIRE POPE & SPANISH WELLS - OPTION 4
TYPICAL SECTION IN STONEY COMMUNITY - OPTION 4
TYPICAL SECTION ON JENKINS ISLAND - OPTION 4
STILL IMPACTS PRESENT R/W
NOTE: EB 3-LANE SECTION
RTE./RD.
6
Item 5.
Options: Bridge Roadway R/W Mitigation Utility Subtotal CEI Total
1. Lifeline option w/o MUP (roadway only to tie in) 185.0 14.7 1.5 9.8 23.3 234.3 23.4 257.7
2. Lifefline option w/ MUP (roadway only to tie in) 240.0 15.7 1.5 9.8 23.3 290.3 29.0 319.3
3. Lifeline option w/o MUP (roadway w/ 3-Lane EB from Moss Creek to Spanish Wells) 185.0 22.8 2.9 11.2 26.9 248.8 24.9 273.7
4. Lifeline option w/ MUP (roadway w/ 3-lane EB from Moss Creek to Spanish Wells) 240.0 24.4 4.0 12.6 28.8 309.8 31.0 340.8
5. 2024 anticipated cost for full project 331.3 43.8 5.8 14.0 29.5 424.4 42.4 466.8
6. Replace only Mackay EB Bridge 45.0 14.7 0.8 7.5 12.5 80.5 8.1 88.6
7
Item 5.
Here’s a summary of the information as well as answers obtained from the SCDOT meeting held on
January 30, 2025, at 2:00 pm in Columbia, South Carolina:
Attendees:
Meeting Attendees:
• SCDOT:
Justin Powell, Secretary of Transportation
Rob Perry, PE, Deputy Secretary for Engineering
John Boylston, Chief Engineer for Program Delivery
Maggie Hendry, Chief Administrative Officer
Craig Winn, PE, Lowcountry Program Manager
• Town of Hilton Head Island:
Alan Perry, Mayor
Alex Brown, Councilman
Steve Desimone, Councilman
Marc Orlando, Town Manager
Shawn Colin, Assistant Town Manager
• Beaufort County:
Alice Howard, County Council Chair
Tab Tabernik, County Council
Michael Moore, Administrator
Jared Fralix, Assistant Administrator
1
. Bridge/Project Options Overview:
• Option 1: $257.7M – Lifeline option without multiuse pathway. Includes a 3-lane bridge with
breakdown lanes. The bridge would be stripped for two-lanes. Cost Comparison: The costs
of half the project may not necessarily be half the total cost.
• Option 2: $319.3M – Lifeline option with multiuse pathway. Includes a 3-lane bridge with
b
reakdown lanes and a protected multiuse pathway.
• Option 3: $273.7M – Lifeline option without multiuse pathway. Includes 3 lanes eastbound
from Moss Creek to Spanish Wells Road.
• Option 4: $340.8M – Lifeline option with multiuse pathway. Includes 3 lanes eastbound
from Moss Creek to Spanish Wells Road, a protected multiuse pathway on the bridge, and a
pathway connection to Moss Creek and Jenkins Island.
• Option 5: $466.8M – Full project cost anticipated for 2024.
• Option 6: $88.6M – Replacement of only the MacKay Creek eastbound bridge.
o Option 3 or 4 may take longer to move through the process and construction
p
hases.
o Projects beyond the bridge scope may be included in the Lowcountry Area
Transportation Study for programming and funding considerations.
8
Item 5.
2. SCDOT is considering a Design Build approach to the project to help with pricing.
• A design-build option will consider design alternatives, including bike and pedestrian
connections.
• SCDOT has seen a 70 percent project cost escalation over the past few years.
3. Tolls and Reversible Lanes:
• Tolls: Tolls are prohibited on existing free facilities (as per South Carolina Statute).
o Tolls for express routes (e.g., to Cross Island Parkway) would require extended
evaluation, including a toll study, environmental review, and permitting.
• Reversible Lanes: SCDOT opposes reversible lanes due to safety, compliance issues, and
the high cost of operation and maintenance. SCDOT is not in the business of reversible
lanes.
4. Utility Relocation and Funding:
Utility relocation costs are part of the project; SCDOT will pay per South Carolina code Act
36.
SCDOT will cover utility relocation costs in accordance with the Utility Relocation Act, and
additional funding could come from local funds
5. Pinckney Island/Skull Creek Bridges:
The preference is for a new eastbound bridge to be elevated over Pinckney Island. Touching
down on Pinckney Island would increase costs, and reduce safety by having at grade
movements.
6. Skull Creek Bridge Substructure:
• The existing substructure supports both the eastbound and westbound bridge decks. The
eastbound deck must be kept if the westbound deck remains. The existing eastbound
bridge over Skull Creek would provide two-way traffic between Jenkins Island and Pinckney
Island.
7. On-Island Grade Separation and Relocation:
• Grade Separation for Squire Pope Road/Spanish Wells Road would require multiple
residential relocations, dramatically increasing costs.
• The Windmill Harbor signal will remain as part of the project regardless of the option,
excluding Option 6.
8. Mitigation Elements and Community Impact:
• Costs for Stoney Community mitigation are only funded if the project extends into the
Stoney area. If Option 3 or 4 is selected, funding for Stoney mitigation (as outlined in the
Environmental Assessment) would be included.
9
Item 5.
9. Project Timing:
• Timeframe for project changes:
o Updates to environmental documents would take 6+ months.
o Design/build project process will take 14 months.
o Right-of-way (ROW) phase takes 12 months.
o Construction will span 24-36 months.
o Estimate is +/- 32months to get to construction and 24-36 months for construction.
10. Project Coordination and Scope:
• Coordination: SCDOT emphasized the need to coordinate efforts.
• Meeting with SIB: SCDOT suggested a with the State Infrastructure Bank (SIB) chairman and
executive director after local coordination to ensure alignment.
• Project Scope Considerations:
o A joint resolution by the Town of Hilton Head Island and Beaufort County outlining
approved project scope and funding strategy is suggested to resolve concerns and
allow SIB consideration.
11. Steps Forward:
• The Town of Hilton Head Island and Beaufort County need to continue discussions to reach
an agreed-upon position and preference for project advancement.
• A joint resolution approved by the Town and County to address concerns raised by the SIB
was recommended to be delivered before the March 31, 2025 deadline.
• This will provide clarity to SCDOT regarding the local preference for advancing the project.
• Beaufort County would need to revise its Intergovernmental Agreement with the SIB as well
as its agreement with SCDOT for project scope.
10
Item 5.
EXHIBIT A
11
Item 5.
OPTIONS BRIDGE ROADWAY RIGHT OF
WAY
ENVIRONMENTAL
MITIGATION
UTILITY
RELOCATIONS SUBTOTAL
CONSTRUCTION
ENGINEERING
INSPECTION
TOTAL
Lifeline Bridge without Multiuse Path
(roadway only to tie in) 185.0 14.7 1.5 9.8 23.3 234.3 23.4 257.7
Lifeline Bridge with Multiuse Path
(roadway only to tie in) 240.0 15.7 1.5 9.8 23.3 290.3 29.0 319.3
Lifeline Bridge without Multiuse Path
(roadway with 3-lanes from Moss Creek
to Spanish Wells)
185.0 22.8 2.9 11.2 26.9 248.8 24.9 273.7
Lifeline Bridge with Multiuse Path
(roadway with 3-lanes from Moss
Creek to Spanish Wells)
240.0 24.4 4.0 12.6 28.8 309.8 31.0 340.8
2024 Anticipated costs for full project 331.3 43.8 5.8 14.0 29.5 424.4 42.4 466.8
Replace only the Mackay Creek
Eastbound Bridge 45.0 14.7 0.8 7.5 12.5 80.5 8.1 88.6
*Costs shown are in millions
US 278 Corridor Improvements
EXHIBIT A
12
Item 5.
13
Item 5.
14
Item 5.
15
Item 5.
16
Item 5.
17
Item 5.
OPTIONS BRIDGE ROADWAY RIGHT OF
WAY
ENVIRONMENTAL
MITIGATION
UTILITY
RELOCATIONS SUBTOTAL
CONSTRUCTION
ENGINEERING
INSPECTION
TOTAL
Lifeline Bridge without Multiuse Path
(roadway only to tie in) 185.0 14.7 1.5 9.8 23.3 234.3 23.4 257.7
Lifeline Bridge with Multiuse Path
(roadway only to tie in) 240.0 15.7 1.5 9.8 23.3 290.3 29.0 319.3
Lifeline Bridge without Multiuse Path
(roadway with 3-lanes from Moss Creek
to Spanish Wells)
185.0 22.8 2.9 11.2 26.9 248.8 24.9 273.7
Lifeline Bridge with Multiuse Path
(roadway with 3-lanes from Moss
Creek to Spanish Wells)
240.0 24.4 4.0 12.6 28.8 309.8 31.0 340.8
2024 Anticipated costs for full project 331.3 43.8 5.8 14.0 29.5 424.4 42.4 466.8
Replace only the Mackay Creek
Eastbound Bridge 45.0 14.7 0.8 7.5 12.5 80.5 8.1 88.6
*Costs shown are in millions
US 278 Corridor Improvements
18
Item 5.
1
R
ESOLUTION 2025 /__
A J
OINT RESOLUTION OF BEAUFORT COUNTY & TOWN OF HILTON HEAD
ISLAND TO REDEFINE THE US 278 CORRIDOR PROJECT (ALSO KNOWN AS THE
WILLIAM HILTON PARKWAY GATEWAY CORRIDOR PROJECT) TO ALIGN
WITH THE AVAILABLE FUNDING
W
HEREAS, the current proposed project includes a six- lane bridge with a multi- use
pathway and roadway improvements spanning from Moss Creek Road to Spanish Wells Road; and
W
HEREAS, the current available funding totals $298.85 million, consisting of $101
million from Beaufort County (sales tax and impact fees), $3.35 million from the Town of Hilton
Head Island (right-of- way donations), $74.5 million from the South Carolina Department of
Transportation (SCDOT), and $120 million from the State Infrastructure Bank (SIB); and
W
HEREAS, in February 2024, SCDOT provided an updated project cost estimate,
increasing the projected cost from $305 million to $488 million; and
W
HEREAS, this updated cost estimate was reflected in our following quarterly report to
the SIB, and upon receipt, the SIB requested a meeting with the County to address the project
status and funding shortfall; and
W
HEREAS, at a meeting on May 29, 2024, between SIB, SCDOT, state representatives,
and Beaufort County, the County proposed a pro- rata cost -sharing arrangement between SIB,
SCDOT, and the County to cover the $190 million shortfall; and
W
HEREAS, in a follow-up letter to SIB dated July 3, 2024, the County formally requested
$90 million from SIB to match a $90 million contribution from the County, contingent upon voter
approval of a proposed Transportation Sales Tax Referendum in November 2024; and
W
HEREAS, on November 5, 2024, the Transportation S ales Tax Referendum was
defeated by a 55% margin, rendering the County’s proposed match unavailable; and
W
HEREAS, on November 7, 2024, SIB issued a letter to the County requesting a response
within 15 days regarding the County’s plan to address the $190M funding shortfall; and
W
HEREAS, at its November 12, 2024, County Council meeting, the Council voted to not
allocate additional funds to the project; and
W
HEREAS, in a letter to Beaufort County dated November 18, 2024, SCDOT reiterated
the deteriorating condition of the eastbound Mackay Creek Bridge, which its condition has been
rated a 4 out of 10, and emphasized that a decision on a viable project must be made by March 31,
2025, to proceed with construction by 2027; and
W
HEREAS, at the November 20, 2024, SIB meeting, an extension was granted to
Beaufort County until March 31, 2025, for the County to provide a revised funding plan; and
19
Item 7.
2
WHEREAS, on January 9, 2025, Senator Tom Davis, with support from the state
delegation, presented a proposal to redefine the project to match available funding; and
WHEREAS, SCDOT has provided six project options along with cost estimates for each
option, including the proposal endorsed by Senator Tom Davis; and
WHEREAS, only two of the six options, (excluding the standalone Mackay Creek Bridge
replacement) fall within the available $298.85 million budget.
NOW THEREFORE, BE IT RESOLVED, THAT THE COUNTY COUNCIL OF
BEAUFORT COUNTY, SOUTH CAROLINA AND THE TOWN COUNCIL OF THE
TOWN OF HILTON HEAD ISLAND, SOUTH CAROLINA hereby adopt a revised scope for
the US 278 Corridor P roject (also known as the William Hilton Parkway Gateway Corridor
Project) to align with the available funds. The revised project includes the following elements:
Revised Project Scope:
1. Replacement of the two eastbound bridges over Mackay Creek and Skull Creek, while
retaining the existing two-lane westbound bridges.
2. Construction of a three-lane eastbound lifeline bridge without a multi-use pathway.
3. Striping the new bridge for two lanes, with only necessary road tie-ins included.
4. Designing the bridge width to accommodate temporary four-lane use in the future if
westbound bridge replacement is required.
5. No access to Pinkney Island from the new bridge; the existing eastbound Skull Creek
bridge will be repurposed for two-way access to Pinkney Island.
6. Removal of the eastbound Mackay Creek Bridge.
7. Construction of a Hog Island connector road/bridge to provide access to Mariner’s Cove,
Blue Heron Point, and Hog Island, linking back to US 278 at the Windmill Harbor
intersection.
8. Retention and improvement of the Windmill Harbor traffic signal with mast arms.
*These project elements are identified in SCDOT’s “Option 1,” attached as Exhibit A.
Funding Elements:
Funding Source Amount (in millions)
Current Project Funding $295.50M
Additional SCDOT Funding $ 16.10 M
Spent to Date - $ 13.07 M
Total Available Funding $298.53M
Planned Project Costs Amount (in millions)
Revised Project Costs $257.70M
Reserve Funds $ 25.83M
Local PSD Relocation Funds $ 10.00M
Stoney Community Safety Project $ 5.00M
Total Costs $298.53M
20
Item 7.
3
1. Reserve funds will cover potential project overruns. If unspent, they may be used for
other local road improvements along the corridor between Moss Creek Rd and Spanish
Wells Road.
2. The project will fund the replacement of the 24” waterline up to the limits defined in
State Act 36. The $10 million appropriation will assist with the difference between the
actual relocation costs and the costs covered by the project. Any relocation cost above the
project funds and this appropriation would be the responsibility of the Public Service
District (PSD).
3. To address immediate safety concerns in the Stoney community, $5 million in local
County funds will be allocated to a local road project, with the Town overseeing design
and construction.
Adopted this ____ day of ____________, 2025.
COUNTY COUNCIL OF BEAUFORT COUNTY
BY:
Alice Howard, Chairman
ATTEST:
Sarah W. Brock, Clerk to Council
Adopted this ____ day of ____________, 2025.
COUNTY COUNCIL OF BEAUFORT COUNTY
BY:
Alan Perry, Mayor
ATTEST:
Kimberly Gammons, Clerk to Council
21
Item 7.
3-lane Bridge (capable of accommodating 4th lane) with using portion of Westbound bridge for o island and one of the old Skull Creek for access to Pinckney Island
Retain existing 2-lane Westbound traic as-is
Remove eastbound Mackay Creek Bridge
Retain existing 2-lane Westbound traic as-is
Retain eastbound Skull Creek Bridge to allow for
2-way traic to and from Pinckney Island
Build new 3-lane “lifeline” bridge over
Mackay, Pinckney and Skull Creek
(capable of carrying 4-lanes (two-lanes in
each direction) temporarily)
Build new Hogg Island connector
required for “lifeline” bridge
connection to existing US 278
Exhibit A
22
Item 7.
Options: Bridge Roadway R/W Mitigation Utility Subtotal CEI Total
1. Lifeline option w/o MUP (roadway only to tie in) 185.0 14.7 1.5 9.8 23.3 234.3 23.4 257.7
2. Lifefline option w/ MUP (roadway only to tie in) 240.0 15.7 1.5 9.8 23.3 290.3 29.0 319.3
3. Lifeline option w/o MUP (roadway w/ 3-Lane EB from Moss Creek to Spanish Wells) 185.0 22.8 2.9 11.2 26.9 248.8 24.9 273.7
4. Lifeline option w/ MUP (roadway w/ 3-lane EB from Moss Creek to Spanish Wells) 240.0 24.4 4.0 12.6 28.8 309.8 31.0 340.8
5. 2024 anticipated cost for full project 331.3 43.8 5.8 14.0 29.5 424.4 42.4 466.8
6. Replace only Mackay EB Bridge 45.0 14.7 0.8 7.5 12.5 80.5 8.1 88.6
23
Item 7.
1
R
ESOLUTION 2025 /__
A J
OINT RESOLUTION OF BEAUFORT COUNTY & TOWN OF HILTON HEAD
ISLAND TO REDEFINE THE US 278 CORRIDOR PROJECT (ALSO KNOWN AS THE
WILLIAM HILTON PARKWAY GATEWAY CORRIDOR PROJECT) TO ALIGN
WITH THE AVAILABLE FUNDING
W
HEREAS, the current proposed project includes a six- lane bridge with a multi- use
pathway and roadway improvements spanning from Moss Creek Road to Spanish Wells Road; and
W
HEREAS, the current available funding totals $298.85 million, consisting of $101
million from Beaufort County (sales tax and impact fees), $3.35 million from the Town of Hilton
Head Island (right-of- way donations), $74.5 million from the South Carolina Department of
Transportation (SCDOT), and $120 million from the State Infrastructure Bank (SIB); and
W
HEREAS, in February 2024, SCDOT provided an updated project cost estimate,
increasing the projected cost from $305 million to $488 million; and
W
HEREAS, this updated cost estimate was reflected in our following quarterly report to
the SIB, and upon receipt, the SIB requested a meeting with the County to address the project
status and funding shortfall; and
W
HEREAS, at a meeting on May 29, 2024, between SIB, SCDOT, state representatives,
and Beaufort County, the County proposed a pro- rata cost -sharing arrangement between SIB,
SCDOT, and the County to cover the $190 million shortfall; and
W
HEREAS, in a follow-up letter to SIB dated July 3, 2024, the County formally requested
$90 million from SIB to match a $90 million contribution from the County, contingent upon voter
approval of a proposed Transportation Sales Tax Referendum in November 2024; and
W
HEREAS, on November 5, 2024, the Transportation S ales Tax Referendum was
defeated by a 55% margin, rendering the County’s proposed match unavailable; and
W
HEREAS, on November 7, 2024, SIB issued a letter to the County requesting a response
within 15 days regarding the County’s plan to address the $190M funding shortfall; and
W
HEREAS, at its November 12, 2024, County Council meeting, the Council voted to not
allocate additional funds to the project; and
W
HEREAS, in a letter to Beaufort County dated November 18, 2024, SCDOT reiterated
the deteriorating condition of the eastbound Mackay Creek Bridge, which its condition has been
rated a 4 out of 10, and emphasized that a decision on a viable project must be made by March 31,
2025, to proceed with construction by 2027; and
W
HEREAS, at the November 20, 2024, SIB meeting, an extension was granted to
Beaufort County until March 31, 2025, for the County to provide a revised funding plan; and
24
Item 7.
2
WHEREAS, on January 9, 2025, Senator Tom Davis, with support from the state
delegation, presented a proposal to redefine the project to match available funding; and
WHEREAS, SCDOT has provided six project options along with cost estimates for each
option, including the proposal endorsed by Senator Tom Davis; and
WHEREAS, only two of the six options, (excluding the standalone Mackay Creek Bridge
replacement) fall within the available $298.85 million budget.
NOW THEREFORE, BE IT RESOLVED, THAT THE COUNTY COUNCIL OF
BEAUFORT COUNTY, SOUTH CAROLINA AND THE TOWN COUNCIL OF THE
TOWN OF HILTON HEAD ISLAND, SOUTH CAROLINA hereby adopt a revised scope for
the US 278 Corridor P roject (also known as the William Hilton Parkway Gateway Corridor
Project) to align with the available funds. The revised project includes the following elements:
Revised Project Scope:
1. Replacement of the two eastbound bridges over Mackay Creek and Skull Creek, while
retaining the existing two-lane westbound bridges.
2. Construction of a three-lane eastbound lifeline bridge without a multi-use pathway.
3. Striping the new bridge for two lanes, with only necessary road tie-ins included.
4. Designing the bridge width to accommodate temporary four- lane use in the future if
westbound bridge replacement is required.
5. No access to Pinkney Island from the new bridge; the existing Skull Creek bridge, either
the eastbound or westbound lanes, will be repurposed for two- way access to Pinkney
Island.
6. Removal of the eastbound Mackay Creek Bridge.
7. Construction of a Hog Island connector road/bridge to provide access to Mariner’s Cove,
Blue Heron Point, and Hog Island, linking back to US 278 at the Windmill Harbor
intersection.
8. Retention and improvement of the Windmill Harbor traffic signal with mast arms.
*These project elements are identified in SCDOT’s “Option 1,” attached as Exhibit A.
Funding Elements:
Funding Source Amount (in millions)
Current Project Funding $295.50M
Additional SCDOT Funding $ 16.10 M
Spent to Date - $ 13.07 M
Total Available Funding $298.53M
Planned Project Costs Amount (in millions)
Revised Project Costs $257.70M
Remaining Engineering Costs $ 15.00M
Reserve Funds $ 15.83M
Local PSD Relocation Funds $ 6.50M
Stoney Community Safety Project $ 3.50M
Total Costs $298.53M
25
Item 7.
3
1. Reserve funds will cover potential project overruns. If unspent, they may be used for
other local road improvements along the corridor between Moss Creek Rd and Spanish
Wells Road.
2. The project will fund the replacement of the 24” waterline up to the limits defined in
State Act 36. The $6.5 million appropriation will assist with the difference between the
actual relocation costs and the costs covered by the project. Any relocation cost above the
project funds and this appropriation would be the responsibility of the Public Service
District (PSD).
3. To address immediate safety concerns in the Stoney community, $3.5 million in local
County funds will be allocated to a local road project, with the Town overseeing design
and construction.
Adopted this ____ day of ____________, 2025.
COUNTY COUNCIL OF BEAUFORT COUNTY
BY:
Alice Howard , Chairman
ATTEST:
Sarah W. Brock, Clerk to Council
Adopted this ____ day of ____________, 2025.
COUNTY COUNCIL OF BEAUFORT COUNTY
BY:
Alan Perry, Mayor
ATTEST:
Kimberly Gammon, Clerk to Council
26
Item 7.
27
Item 9.