William Hilton Parkway Gateway Corridor Independent Review Advisory Committee — Agenda Packet
Town of Hilton Head Island · Beaufort County · William Hilton Parkway Gateway Corridor Independent Review Advisory Committee · meeting of Aug 14, 2024 · Agenda packets
Open the original document More from Town of Hilton Head Island
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Town of Hilton Head Island
William Hilton Parkway Gateway Corridor Independent
Review Advisory Committee Meeting
Wednesday, August 14, 2024, 1:00 PM
1 Town Center Court, Hilton Head Island, SC
Benjamin M. Racusin Council Chambers
The meeting can be viewed on the Town’s YouTube Channel, the Beaufort County
Channel, and Spectrum Channel 1304.
1. Call to Order
2. Approval of the Minutes
a. Regular Meeting Minutes of June 12, 2024
3. Unfinished Business
a. Update on Project Progress
b. Review of Downstream Impacts to William Hilton Parkway, Cross Island
Parkway, Palmetto Bay Road and Sea Pines Circle
c. Recommended Improvements to Consider for Intersections Downstream of
Gum Tree Road and Cross Island Parkway
d. Presentation and Acceptance of Final Report
4. New Business
5. Public Comment - Non Agenda Items
6. Adjournment
FOIA Compliance: Public notification of this meeting has been published, posted, and
distributed in compliance with the South Carolina Freedom of Information Act and the
requirements of the Town of Hilton Head Island.
In accordance with the requirements of Title II of the Americans with Disabilities Act of
1990 ("ADA"), the Town of Hilton Head Island will not discriminate against qualified
Page 1 of 234
individuals with disabilities on the basis of disability in its services, programs, or
activities. Auditory accommodations are available. Any person requiring further
accommodation should contact the Town of Hilton Head Island ADA Coordinator as
soon as possible but no later than 48 hours before the scheduled event.
Municipal Association of South Carolina (MASC) Civility Pledge:
“I pledge to build a stronger and more prosperous community by advocating for civil
engagement, respecting others and their viewpoints, and finding solutions for the
betterment of my city or town.”
Page 2 of 234
Town of Hilton Head Island William Hilton Parkway Gateway Corridor Independent Review Advisory
Committee
Meeting Minutes
6/12/2024 Page | 1
Town of Hilton Head Island
WILLIAM HILTON PARKWAY GATEWAY
CORRIDOR INDEPENDENT REVIEW
ADVISORY COMMITTEE MEETING
Wednesday, June 12, 2024, 1:00 PM
Minutes
1. Call to Order
Mayor Perry called the meeting to order at 1:00 PM.
2. Approval of the Minutes
a. Regular Meeting Minutes of April 22, 2024.
Mr. Advocaat raised questions pertaining to the April 22, 2024, Special Meeting Minutes
regarding the Town's venture to Columbia to discuss Lochmueller findings with SCDOT.
After some discussion and clarification, a motion was made by Mr. Advocaat to approve
the minutes of April 22, 2024, with a second by Mr. Warner. The motion passed
unanimously.
b. Regular Meeting Minutes of May 8, 2024.
Mr. Advocaat made a motion to approve the Regular Meeting Minutes of May 8, 2024.
Mr. Warner seconded. The motion passed unanimously.
3. Unfinished Business
a. Update on Project Progress
Prior to the beginning of the update, Mr. Advocaat proposed that the Committee move
'Appearance by Citizens' from item five to item three on the agenda as he felt it necessary
to hear public comment prior to presentations. Mayor Perry called for a vote in which Mr.
Advocaat made the motion to move the item, with a second by Mr. Walczak. The motion
tied with a 2-0-2 vote, and the motion did not carry. Shawn Colin, Assistant Town
Manager - Engineering and Capital Projects, opened up the floor to Nathan Nohren,
Senior Traffic Engineer for the Lochmueller consultant group, to give updates on the
project progress. Mr. Nohren also introduced Kate Swinford, Michelle Romine, and Chad
Costa who virtually attended the meeting to assist in presenting and addressing any
questions from the committee.
The project progress, along with the agenda items that follow, consider the selection of
Alternative #1 as previously presented by Lochmueller with the modification of having a
Page 3 of 234
Town of Hilton Head Island William Hilton Parkway Gateway Corridor Independent Review Advisory
Committee
Meeting Minutes
6/12/2024 Page | 2
single eastbound left turn and a single southbound right turn onto Squire Pope Road,
developing a Visum Model optimizing the timing considering the adaptive system from
Bluffton all the way through the Gum Tree Road, as well as incorporating the
intersections remaining within the study areas from Indigo Run down to the Sea Pines
Circle which Mr. Nohren noted are merely impacts and no mitigation strategies have been
evaluated pertaining to these intersections. Mr. Nohren stated that Lochmueller is
currently 75% completed with the entirety of the project, Task 1 is pending a meeting with
Town Staff and is near 100% complete, Task 3 is considered 90% complete with the
anticipation of presenting the findings to Town Council, Task 4 is considered 50%
complete with the understanding of what the impacts will be, and Task 5 is a
comprehensive document which will memorialize Lochmueller's work which will be
executed after completion of Task 4.
Mr. Advocaat expressed concern that the projects are moving at a rapid pace, and
questioned whether Lochmueller's work would be completed ahead of the June 17th
Town Council meeting. Mr. Nohren addressed this question and explained that
Lochmueller would be engaging council for the first time beginning June 17th, and the
meaning of the future Town Council meetings is to update Council with progress being
made from Task 1 through Task 3 explaning that all subject deliverables have been
completed and will be provided.
Kate Swinford addressed the committee by going over review items reiterating
Lochmueller's method of progress as well as answering questions received regarding
levels of service criteria and generation of base traffic data. Ms. Swinford reminded the
committee that Lochmueller's analysis was completed independently of outside input and
stated there was no significant variation between prior study efforts and their study efforts
with respect to previously considered alternatives. According to Ms. Swinford,
Lochmueller has not been involved in any meetings with SCDOT nor have they ever
coordinated with SCDOT in regards to the respective project. Not only did Lochmueller
evaluate previous ideas, but also brought new ideas to the table to provide for
consideration regarding Alternatives 2, 3 and 4. Ms. Swinford went on to explain that
levels-of-service is one method used among a three-pronged approach analyzing the
effectiveness of a certain approach with the remaining two prongs being queue and
volume-to-capacity ratio. Queue length speaks to the resulting number of cars waiting to
make their turn to enter the corridor based upon the configuration, while volume-to-
capacity ratio speaks to the lane capacity.
Ms. Swinford stated that all hourly volumes used as a basis for this independent analysis
and provided scenarios were collected in March of 2023, and both hourly volumes and
daily volumes are taken into consideration with the main bulk of analysis being based
upon hourly volumes. The 30th highest traffic volume day recorded was specifically
utilized to ensure the research conducted by Lochmueller responsibly reflected peak
conditions without overestimating or underestimating traffic volumes. Using a singular
growth rate, Lochmueller developed a model depicting the future scenario at the year
2045 which they explain would be the "worst case scenario" compared to years prior.
Page 4 of 234
Town of Hilton Head Island William Hilton Parkway Gateway Corridor Independent Review Advisory
Committee
Meeting Minutes
6/12/2024 Page | 3
4. New Business
a. Presentation of Findings for Downstream Intersection Impacts
Michelle Romine presented the Downstream Impacts by first building upon Kate
Swinford's statements stating that Lochmueller has provided some excerpts of traffic
volumes to show the hourly volumes used in the analysis. All traffic volumes were
provided as part of the William Hilton Parkway Gateway Corridor Independent Review
Advisory Committee meeting on March 27th, 2024 as well as within the corridor, an
Alternatives Analysis Memorandum which was submitted on May 3rd, 2024.
Ms. Romine explains that her focus for the presentation will be west of Section 9, which is
known as the Squire Pope area. The morning peak hour consists of approximately 2,800
vehicles traveling in the eastbound direction which includes 159 left turns, 2,620 through
vehicles, and two right turning vehicles. In the evening, just west of Section 9 at Squire
Pope, there are approximately 3,000 vehicles traveling in the westbound direction which
includes 2,687 through vehicles, 2 northbound left turns, and 341 southbound right turns.
Ms. Romine reiterated that these are the 2023 traffic volumes used in the analysis.
Lochmueller took these volumes and raised them by their determined growth rate of
0.56% which brings morning peak hour volume to approximately 3,150 vehicles traveling
eastbound and evening peak hour volume to 3,400 vehicles traveling westbound, these
volumes were then used for the 2045 scenarios with Squire Pope being an excerpt of one
intersection out of the many provided by Lochmueller.
Ms. Romine went on to present their Task 4 Scope of Findings. There were previously 4
alternatives considered between Moss Creek Drive and Gum Tree Road, and after review
of the findings and discussion with SCDOT, Lochmueller was directed by the Town of
Hilton Head Island to pursue Alternative 1 SCDOT Modified Recommended Preferred
with additional modifications to provide a single eastbound left turn lane, and a single
southbound right turn lane at U.S. 278 and Squire Pope. Lochmueller is in the process of
determining what impacts this alternative might have, as well as evaluating what, if any,
improvements need to be made. The analysis presented now includes the entire study
area including intersections near Indigo Run, traveling all the way down to the Sea Pines
Circle. The Visum Model, which is a simulation tool used to accurately replicate vehicles
and their interactions within complex traffic streams, travel time runs for the Modified
Alternative 1, as well as the SCDOT Alternative, match the numbers of the "No-Build"
scenario previously presented by Lochmueller. Ms. Romine presented the Synchro
results for the first time for the Modified Alternative 1 to serve as a comparison which
Lochmueller expected to be less pronounced than the original Visum Model, as it is noted
that Visum provides a more accurate representation. The values from these models
presented in the table included the use of an Adaptive Traffic Signal System along U.S.
278 along the Modified 1 Alternative Traffic System.
Under the 2045 "No-Build" scenario, it is expected that it would take approximately 26.3
minutes to travel eastbound along Hilton Parkway between Moss Creek and Indigo Run
Page 5 of 234
Town of Hilton Head Island William Hilton Parkway Gateway Corridor Independent Review Advisory
Committee
Meeting Minutes
6/12/2024 Page | 4
during the AM peak hour. Using the Visum Model, it is expected that this travel time
would be reduced to 10.5 minutes under the Modified Alternative 1. Under the same 2045
"No-Build" scenario, it is expected that is would take 25.7 minutes in the evening peak
hour to travel westbound along Hilton Parkway between Moss Creek and Indigo Run. It is
now expected that the travel time would be reduced to 10.3 minutes under the Modified
Alternative 1 Scenario, and these are expected to be the final travel times, assuming no
changes along U.S. 278 east of Gum Tree or along the Cross Island Parkway. However,
as Lochmueller proceeds through mitigation strategies, the values are subject to changes
that may reflect potential improvements. Ms. Romine displayed and narrated a simulated
video presentation to help visualize the 2045 Modified Alternative 1 Scenario displaying
both AM and PM peak hours as well as specific locations where queuing issues are being
addressed.
Ms. Romine elaborated further by displaying results based upon the operating conditions
expected from this scenario provided by Visum, with the operating conditions for each
intersection being included in the Appedix of the presentation for reference. The results
presented for key intersections of note were provided as follows: The intersections
between Squire Pope and Gum Tree are expected to operate acceptably overall during
the AM and PM peak hours. Each signalized intersection is expected to have an LOS-D
or better, which is the target LOS for an intersection overall, and the inidivual approaches
are expected to operate with an LOS-E or better, which Ms. Romine notes is typically
considered acceptable during peak hours concerning some of the side street approaches.
Ms. Romine states that Lochmueller is considering any additional improvements that can
be made, including reconfiguring intersections and turn lanes to improve efficiency,
addition of lanes to improve capacity, and most certainly looking to improve the Sea
Pines roundabout, which is performing the least efficiently out of all the performance
studies conducted. Mr. Advocaat had questions regarding traffic volumes and breakdown
lanes which Ms. Romine addressed. Mr. Walczak had additional questions regarding
emergency lanes, which were also addressed by Lochmueller as well as Shawn Colin,
Assistant Town Manager. There was a lengthy discussion by the Committee regarding
the option of a Southern Bypass which Lochmueller, Shawn Colin and Mayor Perry
addressed in detail.
b. Consideration of a Resolution to Accept the Findings of the William Hilton Parkway
Gateway Corridor Independent End to End Analysis
On February 21st, 2023 Town Council authorized the creation and appointment of the
William Hilton Parkway Gateway Corridor Independent Review Advisory Committee.
Shawn Colin, Assistant Town Manager, went over the resolution which created the
Committee stating the resolution required the Committee to secure a consultant to adopt
a scope of work to recommend to Town Council. On May 12th, 2023 the Committee
recommended an agreed upon scope of work, and on June 6th, 2023 Town Council
unanimously adopted a resolution approving the scope of work and request for
qualifications. On August 28th the Committee unanimously recommended the Town
negotiate a contract with Lochmueller group, and on October 12th, 2023 the Town
Page 6 of 234
Town of Hilton Head Island William Hilton Parkway Gateway Corridor Independent Review Advisory
Committee
Meeting Minutes
6/12/2024 Page | 5
executed the contract with Lochmueller tp preform the independent analysis. Since then,
the Town has held ten public meetings spanning from November 3rd, 2023 to June 12th,
2024 to review the consultants findings and recommendations for the William Hilton
Parkway Gateway Corridor Independent End-to-End Analysis as well as to receive public
input. As of today, the consultant has presented technical reports and deliverables as
outlined in the contract.
Shawn Colin requested consideration from the Committee to accept the findings and
recommendations of the William Hilton Parkway Gateway Corridor Independent End-to-
End Analysis delivered by the consultant. Secondarily, Mr. Colin asks that the Committee
authorize the Town Manager to use the findings and recommendations for future planning
purposes. Mayor Perry called for a motion, Mr. Warner made the motion to approve.
Mayor Perry passed the gavel to Mr. Warner and seconded the motion. The motion failed
with a vote of 2-2. Mr. Advocaat asked that the record reflect that he is not in favor of this
motion.
5. Appearance by Citizens:
Mayor Perry opened up the floor for public comment.
Christopher Cliff made comments regarding the letter from SCDOT as well as completion
percentages.
Jack Alderman, Chairman of the Housing Action Committee, stated that the development of
the roadways is a key component to the island's growth and economic vitality, and he was
disappointed to hear some of the same issues being discussed that were resolved early on in
the process.
Kris Ruffner commented that she is from Chicago and has experienced some of the worst
traffic delays. Further, Ms. Ruffner explained that further development will increase induced
demand and will not solve the issue, "if you build it, they will come."
Frank Babel, former member of the original Gateway Corridor Committee, made comments
regarding the need for development of the roadways and mentioned the frequency of
accidents. Mr. Babel stated the roadway does not work as it stands now, and that the traffic
has affected the businesses on the island.
Gerald Devito commented stating he believes Alternative #1 is the only viable option and
mentioned that the cross-sections would address various issues.
Tammy Becker, Member of Council, thanked Lochmueller for their review of the Southern
Bypass option. Ms. Becker then clarified that she does not remember Council ever being
further consulted regarding the Bypass which Lochmueller addressed.
Greg Whitaker stated that the simulation displayed at this afternoon's meeting was very
beneficial and requested that Lochmueller display it at the next Town Council meeting where
these alternatives will be discussed. Mr. Whitaker also suggested that Lochmueller discuss
why reversible lanes were considered but dismissed, and that they shed some light on the
Southern Bypass option.
Gray Smith noted that the amount of lanes are not the issue in his opinion, but how free
flowing the traffic is through the corridor. Mr. Smith also stated that he believes voting on the
findings is premature at this point.
Page 7 of 234
Town of Hilton Head Island William Hilton Parkway Gateway Corridor Independent Review Advisory
Committee
Meeting Minutes
6/12/2024 Page | 6
Richard Busy explained that he believes the Southern Bypass should have received the same
evaluation efforts as the other alternatives presented by Lochmueller.
Kathleen Redman stated she believes two lanes in each direction would suffice and she does
not think we need six lanes.
Carol Vuxxer made comment stating she agrees with Ms. Redman regarding the two lane
bridge as opposed to six. Ms. Vuxxer also noted that she is against taking any Stoney property
to complete this project.
6. Adjournment
The meeting was declared adjourned at 4:00 PM.
Approved:
The recording of this Meeting can be found on the Town’s website
at www.hiltonheadislandsc.gov
Page 8 of 234
Stephen G. Riley Municipal Complex
One Town Center Court Hilton Head Island South Carolina 29928
www.hiltonheadislandsc.gov
TOWN OF HILTON HEAD ISLAND
Willliam Hilton Parkway
Gateway Corridor Advisory Committee
TO: Advisory Committee
FROM: Shawn Colin, Assistant Town Manager
DATE: August 14, 2024
SUBJECT: Recommendation for the William Hilton Parkway Gateway Corridor
Independent Review Advisory Committee to accept the Final Report
for the William Hilton Parkway Independent Study
RECOMMENDATION:
Recommendation for the William Hilton Parkway Gateway Corridor Independent Review
Advisory Committee to accept the Final Report for the William Hilton Parkway
Independent Study.
BACKGROUND:
February 2023 – Town Council created the William Hilton Parkway Gateway Corridor
Independent Review Advisory Committee (Committee)
March 2023 - Appointments made on March 21, 2023.
May 2023 – Committee approved draft Request for Proposals and Scope of Work for
Independent Study and forwarded to Town Council for consideration
June 2023 - Town Council approved Request for Proposals and Scope of Work for
Independent Study
August to October 2023 – Consultant, The Lochmueller Group, Inc. procured to conduct
Independent Study
Oct 2023 to August 2024 – Hilton Head Island Procured Independent Study consultant
conducted 11 public meetings with the Committee between November 3, 2023, and
August 14, 2024 to present findings and recommendation to the Committee in
accordance with the Town Council approved Scope of Work. Presentation of the Final
Report completes the Scope of Work deliverables for this project.
ATTACHMENTS:
1. The Lochmueller Group Document Transmittal Memo – dated August 9, 2024
2. Presentation by the Lochmueller Group – dated August 14, 2024
3. Independent Study of the William Hilton Parkway Gateway Corridor Traffic
Operations and Safety Report – dated August 9, 2024
Page 9 of 234
TRANSMITTAL
To: Shawn Colin, AICP – Town of Hilton Head Island
From: Nate Nohren, PE, PTOE
Date: August 9, 2024
Subject: Copies of Presentation Materials for 8/14/2024 Advisor y Committee Meeting
RE: William Hilton Parkway Gateway Corridor Indepen dent Review
Hi Shawn,
Attached please find a PDF copy of the power point slides we will be presenting at the June 12, 2024,
Advisory Committee meeting. The content provided w ithin our presentation can be summarized as
follows:
• Update on Project Progress – we will provide the Committee an update on what our team has
been working on and/or completed since the June 10 C ommittee meeting. We also provide
current status of percent-of-work completed to date for the entire project, in relation to the
Town approved Scope of Services Addendum (9/29/2023).
• Review of Downstream Impacts to Task 4 Intersections (Assuming Implementation of Modified
Alternative 1 from Task 3) – we will provide a summary review of our findings that we
presented during the 6/12 Committee meeting, related t o the anticipated impacts to
intersections downstream of Gum Tree Road and Cross Island Parkway, assuming the
implementation of the “modified” Alternative #1, whi ch includes the implementation of a single
eastbound left-turn and a single southbound right-t urn lane at Squire Pope Road.
• Additional Mitigation Solutions for Local Intersect ions – we will present slides that summarize
our key findings related to the potential mitigatio n solutions for select intersections downstream
of Gum Tree Road and Cross Island Parkway; at locat ions where it was determined that the
suggested mitigation solutions would provide notice able operational benefits at the respective
intersections, as compared to 2045 No-Build conditions.
• Presentation of Final Results for Entire Study Area – we will present two slides that provide a
concise overview of key findings related comparison s of aforementioned mitigations strategies
for select intersections downstream of Gum Tree Road and Cross Island Parkway; as compared
to (1) the 2045 No-Build scenario results for Entire Stu dy Area, and (2) a scenario that considers
the 2045 Modified Alternative 1 results for intersection s upstream of Gum Tree Road and Cross
Island Parkway, but no improvements being implement ed downstream of Gum Tree Road and
Cross Island Parkway.
We have also attached a PDF copy of the draft Traff ic Operations and Safety Report (deliverable for Ta sk
5.1), which comprehensively details all work complete d to date by Lochmueller, as a part of this project .
We will have a copy of this report available during the meeting, should any questions arise pertaining to
our final study related findings that are not specifically mentioned within the Power Point presentati on.
For the sake of brevity, we do not intend to cover topics that have already been discussed in detail d uring
previous Committee meetings.
Please let me know if you have any questions regard ing the information shared above. Otherwise, we
look forward to speaking with you all on August 14.
Sincerely,
Nate Nohren, PE, PTOE
Page 10 of 234
William Hilton Parkway Gateway Corridor
Independent Review Advisory Committee Meeting
August 14
th , 2024
Page 11 of 234
Lochmueller Team Members Participating Today
Nate Nohren – Project Manager
Kate Swinford – Deputy Project Manager/Traffic Analysis Lead
Michelle Romine – Traffic Analysis Staff Engineer
Lorne Jackson – Roadway/ROW Impacts Lead
Page 12 of 234
Agenda
Update on Project Progress
Review of Downstream Impacts to Task 4 Intersections (Assuming
Implementation of Modified Alternative 1 from Task 3)
Additional Mitigation Solutions for Local Intersections
Presentation of Final Results for Entire Study Area
Questions
Page 13 of 234
Update on Project Progress
(Key Tasks Completed & Continuing to Work on Since Last Meeting )
Participated in 6/17 Town Council Workshop
Attended 6/20 Special Town Council Meeting
Completed traffic analyses, modeling (Synchro/VISSIM), and related
findings to determine proposed mitigation strategies for 2045 Build Year
conditions at intersections downstream of CIP
Prepared preliminary Traffic Operations & Safety Report (deliverable for
Task 5.1), which comprehensively details all work completed by
Lochmueller as a part of this project
Submitted draft report to Town staff on 8/9
Page 14 of 234
• Task #1: Project Initiation and Coordination
o ~100% Complete
• Task #2: Review of Travel Demand Model & Evaluation of
2023 Existing Operating Conditions (Entire Study Area)
o 100% Complete
• Task #3: Traffic Model and Operational Update – Modified Original
Project Study Area
o 100% Complete
• Task #4: Traffic Model and Operational Update – Entire Project Study Area
o 100% Complete
Update on Overall Project Progress (as of 8/9/24)
Overall ~95% Complete 95% 5%
100%
100%
100%
100%
Page 15 of 234
Update on Overall Project Progress (as of 8/9/24)
• Task #5: Final Report
o ~95% Complete
o Key Subtasks Remaining:
Finalize Traffic Operations & Safety Report, after receiving feedback
from Town staff
Presentation of final report findings to Town Council
95% 5%
Page 16 of 234
Review of Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
• Lochmueller previously analyzed four alternatives intended to improve the
operating conditions along US 278 between Moss Creek Dr and Gum Tree Rd.
• After review of the findings and discussion with SCDOT, Lochmueller was
directed by the Town of Hilton Head Island to pursue Alternative 1: SCDOT
Modified Recommended Preferred with modifications to provide a single
eastbound left-turn lane and a single southbound right-turn lane at US 278 at
Squire Pope Rd.
• Lochmueller then evaluated the impacts the modified Alternative 1 would have
on the entire project study area and determined what, if any, improvements
should be made to accommodate the 2045 forecasted traffic.
Page 17 of 234
Review of Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
Page 18 of 234
Corridor
2045 No Build Simulated
travel time (secs)
2045 Modified Alternative 1
Simulated Travel Time (secs) % Difference
AM PM AM PM AM PM
Hilton Parkway
between Moss
Creek and Indigo
Run
EB 1579
[26.3]
642
[10.7]
628
[10.5]
631
[10.5] -60.23% -1.71%
WB 584
[9.7]
1544
[25.7]
597
[10]
616
[10.3] 2.23% -60.10%
Hilton Parkway
@Moss Creek to
Cross Island
Parkway @Sea
Pine
SB 1984
[33.1]
873
[14.6]
1387
[23.1]
874
[14.6] -30.09% 0.11%
NB 823
[13.7]
2465
[41.1]
848
[14.1]
904
[15.1] 3.04% -63.33%
• VISSIM Travel Time Results:
Review of Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
Page 19 of 234
• Overall, even with no improvements in place east of Gumtree Road or along Cross Island
Parkway, it was found that the travel times would significantly improve when compared to
the 2045 no build scenario.
• The intersections would be expected to operate acceptably overall. However, the
eastbound and westbound approaches between Wilborn Road and Pembroke Drive are
expected to experience long queues and be over capacity in the year 2045.
• Additionally, the existing roundabout at Palmetto Bay Road and Sea Pines Circle is
expected to fail during both the AM and PM peak hours. As a result of the failing roundabout,
the queue lengths are expected to extend beyond nearby intersections.
• Therefore, Lochmueller evaluated two options with potential solutions to the local
intersections downstream of Gum Tree Road and Cross Island Parkway to help mitigate the
expected long queues and delays.
Review of Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
Page 20 of 234
Additional Mitigation Solutions for
Local Intersections – Option A
• Option A :
o William Hilton Parkway & Pembroke Drive:
Reconfigure the northbound approach to provide dual northbound left-turn
lanes, one through lane, and one right-turn lane
In addition to the roadway widening, this will require relocation of the shared
use path on the east side, adjustments to signal equipment and additional
ROW on the south leg
Estimated preliminary probable opinion of cost (including ROW) = $750,000
Estimated construction duration = 4 months
o Palmetto Bay Road & William Hilton Parkway (Sea Pines Circle):
Provide a two-lane roundabout
Each approach should have a right-turn bypass, with the exception of the
west leg
This will require pavement widening to the inside of the traffic circle and on
each of the four legs of the intersection to accommodate the additional lane
Estimated preliminary probable opinion of cost = $2,000,000
Estimated construction duration = 8 months
Page 21 of 234
Option A Operating Conditions (VISSIM)
Corridor
2045 No Build Simulated
travel time (secs) [min]
2045 Modified Alternative 1
Option A
Simulated Travel Time (secs) [min]
% Difference
AM PM AM PM AM PM
Hilton Parkway
between Moss
Creek and Indigo
Run
EB 1579
[26.3]
642
[10.7]
548
[9.1]
589
[9.8] -65.31% -8.21%
WB 584
[9.7]
1544
[25.7]
556
[9.3]
600
[10] -4.85% -61.12%
Hilton Parkway
@Moss Creek to
Cross Island
Parkway @Sea
Pine
SB 1984
[33.1]
873
[14.6]
833
[13.9]
856
[14.3] -58.01% -1.93%
NB 823
[13.7]
2465
[41.1]
814
[13.6]
845
[14.1] -1.04% -65.72%
• VISSIM Travel Time Results:
• Travel times along William Hilton Parkway between Moss Creek Drive and Indigo Run Drive are expected to
improve by approximately:
• 17.2 minutes during the AM peak hour in the eastbound direction
• 15.7 minutes during the PM peak hour in the westbound direction
• The travel times along William Hilton Parkway at Moss Creek to the Cross Island Parkway at Sea Pines C ircle
are expected to improve by approximately:
• 19.2 minutes during the AM peak hour in the southbound direction
• 27 minutes during the PM peak hour in the northbound direction
Page 22 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
13: Jarvis Park Rd/Wilborn Rd & Hilton Pkwy (signal)
Overall Intersection B (15.5) B (15.4)
Eastbound Approach A (9.0) [48] {424} A (9.8) [51] {410}
Westbound Approach B (13.8) [62] {635} B (16.8) [156] {1076}
Northbound Approach E (74.8) [46] {179} F (81.9) [53] {189}
Southbound Approach D (40.7) [72] {233} B (20.0) [31] {115}
14: Pembroke Dr/Museum St & Hilton Pkwy (signal)
Overall Intersection
B (19.2) C (20.8)
Eastbound Approach A (7.8) [80] {962} A (7.9) [36] {439}
Westbound Approach C (24.4) [115] {629} C (21.8) [286] {937}
Northbound Approach E (68.3) [84] {267} E (60.7) [85] {301}
Southbound Approach D (39.1) [27] {119} D (48.3) [37] {137}
15: Central Ave & Hilton Pkwy (un-signalized)
Eastbound Left Turn A (9.9) [<25] {<25} B (15.7) [<25] {<25}
Westbound Left Turn C (21.8) [<25] {<25} B (16.9) [<25] {<25}
Northbound Right Turn C (17.9) [<25] {27} B (13.4) [<25] {32}
Southbound Right Turn B (12.5) [<25] {44} B (19.3) [<25] {41}
16: Hatton Pl/Merchant St & Hilton Pkwy (un-signalized)
Northbound Right Turn A (7.7) [<25] {<25} A (7.0) [<25] {64}
Southbound Right Turn B (11.4) [<25] {37} B (15.8) [<25] {35}
17: Indigo Run Dr/Whooping Crane Way & Hilton Pkwy (signal)
Overall Intersection B (17.8) C (30.5)
Eastbound Approach A (6.8) [<25] {324} C (20.9) [133] {467}
Westbound Approach B (14.7) [43] {349} C (26.5) [192] {872}
Northbound Approach E (58.4) [34] {122} E (58.3) [53] {208}
Southbound Approach D (53.3) [64] {223} E (58.5) [79] {274}
15
16
Even with the adaptive signals and reconfiguration of the northbound
approach at Pembroke Dr to allow more of the cycle length to go to the
mainline, long queues would still be expected between Gumtree Rd and
Pembroke Ave. However, it is not expected that the maximum queue
would extend into nearby intersections.
13
• EB LT expected to fail
during PM peak hour
17
Option A Operating Conditions (VISSIM)
• SB LT expected to fail
during AM peak hour
• SB TH expected to fail
during PM peak hour
14
Page 23 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection
B (17.8) C (30.5)
Eastbound Approach A (6.8) [<25] {324} C (20.9) [133] {467}
Westbound Approach B (14.7) [43] {349} C (26.5) [192] {872}
Northbound Approach E (58.4) [34] {122} E (58.3) [53] {208}
Southbound Approach D (53.3) [64] {223} E (58.5) [79] {274}
28: Palmetto Bay Rd & Dunnagans Alley (un-signalized)
Westbound Left Turn E (40.2) [<25] {34} E (56.1) [<25] {79}
Westbound Right Turn A (8.0) [<25] {69} B (14.6) [<25] {113}
Southbound Left Turn A (7.0) [<25] {153} B (15.4) [<25] {37}
29: Palmetto Bay Rd & Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection A (8.9) B (10.8)
Eastbound Approach D (29.0) [75] {342} C (29.8) [122] {514}
Westbound Approach A (5.0) [<25] {123} B (10.2) [29] {191}
Northbound Approach A (2.8) [<25] {78} A (4.4) [<25] {158}
Southbound Approach A (6.6) [28] {296} A (5.5) [<25] {231}
27
28
• Implementation of a 2-lane
roundabout with right-turn
bypass legs at each
approach, with the
exception of the east leg,
significantly improves
queueing and congestion
29
Option A Operating Conditions (VISSIM)
Page 24 of 234
Additional Mitigation Solutions for
Local Intersections – Option B
• Option B :
o Extend the 6-lane section from Gumtree Road past Pembroke Drive. The 6-lane section can taper back
to a 4-lane section at Central Avenue.
o In addition to the roadway widening, this will require adjustments to the shared use path on the north
side of the road, new traffic signals at Wilborn and Pembroke, temporary construction easements and
possibly new ROW.
Estimated preliminary probable opinion of cost = $3,000,000
Estimated construction duration = 6 months
o William Hilton Parkway & Wilborn Road:
Provide dual southbound right-turn lanes
In addition to the roadway widening, this will require adjustments to the shared use path on the east
side of the road, temporary construction easements and possibly new ROW
Estimated preliminary probable opinion of cost = $1,000,000
Estimated construction duration = 4 months
Page 25 of 234
Additional Mitigation Solutions for
Local Intersections – Option B (cont.)
• Option B :
o Palmetto Bay Road & William Hilton Parkway (Sea Pines Circle):
Signalize the intersection rather than the existing roundabout
Provide a left-turn lane, two thru lanes, and a right-turn lane for every approach except the EB approach,
which will have dual left-turn lanes
In addition to the roadway widening on each leg of the intersection to accommodate the addition of turn
lane, this will require adjustments to the shared use path on the east side of the south leg, new traf fic
signals, temporary construction easements, and new ROW on the north and west legs
Estimated preliminary probable opinion of cost = $6,000,000
Estimated construction duration = 12 months
Page 26 of 234
Option B Operating Conditions (VISSIM)
Corridor
2045 No Build Simulated
travel time (secs) [min]
2045 Modified Alternative 1
Option B
Simulated Travel Time (secs) [min]
% Difference
AM PM AM PM AM PM
Hilton Parkway
between Moss
Creek and Indigo
Run
EB 1579
[26.3]
642
[10.7]
534
[8.9]
571
[9.5] -66.18% -11.06%
WB 584
[9.7]
1544
[25.7]
547
[9.1]
552
[9.2] -6.34% -64.25%
Hilton Parkway
@Moss Creek to
Cross Island
Parkway @Sea
Pine
SB 1984
[33.1]
873
[14.6]
820
[13.7]
840
[14] -58.67% -3.78%
NB 823
[13.7]
2465
[41.1]
816
[13.6]
848
[14.1] -0.86% -65.60%
• VISSIM Travel Time Results:
• Travel times along William Hilton Parkway between Moss Creek Drive and Indigo Run Drive are expected to
improve by approximately:
• 17.4 minutes during the AM peak hour in the eastbound direction
• 16.5 minutes during the PM peak hour in the westbound direction
• The travel times along William Hilton Parkway at Moss Creek to the Cross Island Parkway at Sea Pines C ircle
are expected to improve by approximately:
• 19.4 minutes during the AM peak hour in the southbound direction
• 27 minutes during the PM peak hour in the northbound direction
Page 27 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
13: Jarvis Park Rd/Wilborn Rd & Hilton Pkwy (signal)
Overall Intersection B (17.3) B (12.3)
Eastbound Approach B (12.8) [139] {463} A (9.1) [53] {239}
Westbound Approach A (9.8) [30] {434} A (6.7) [30] {407}
Northbound Approach E (73.3) [30] {175} E (67.9) [30] {168}
Southbound Approach D (49.7) [72] {248} D (44.6) [40] {172}
14: Pembroke Dr/Museum St & Hilton Pkwy (signal)
Overall Intersection
C (20.5) B (16.3)
Eastbound Approach A (9.3) [38] {307} B (12.7) [44] {306}
Westbound Approach C (29.2) [87] {440} A (7.7) [31] {214}
Northbound Approach E (58.3) [79] {284} E (59.5) [93] {320}
Southbound Approach C (34.4) [<25] {105} D (36.6) [<25] {127}
15: Central Ave & Hilton Pkwy (un-signalized)
Eastbound Left Turn B (12.6) [<25] {27} B (10.5) [<25] {<25}
Westbound Left Turn C (23.8) [<25] {27} B (12.7) [<25] {<25}
Northbound Right Turn C (18.5) [<25] {30} B (13.7) [<25] {32}
Southbound Right Turn A (3.6) [<25] {<25} A (5.6) [<25] {<25}
16: Hatton Pl/Merchant St & Hilton Pkwy (un-signalized)
Northbound Right Turn A (9.5) [<25] {28} A (8.2) [<25] {66}
Southbound Right Turn B (10.6) [<25] {38} B (15.2) [<25] {35}
17: Indigo Run Dr/Whooping Crane Way & Hilton Pkwy (signal)
Overall Intersection B (16.9) D (35.7)
Eastbound Approach A (5.2) [<25] {278} C (34.5) [154] {810}
Westbound Approach B (15.7) [47] {355} C (26.8) [195] {845}
Northbound Approach E (57.1) [32] {106} E (67.3) [64] {267}
Southbound Approach D (50.7) [59] {211} E (56.5) [75] {278}
15
16
By extending the 6-lane section east towards Central Avenue, the long
queue lengths between Gumtree Rd and Pembroke Dr would be
mitigated.
• EB LT and NB TH
expected to fail during
PM peak hour
17
Option B Operating Conditions (VISSIM)
• WB LT expected to fail
during PM peak hour
13
• WB LT expected to fail
during PM peak hour
14
Page 28 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection
A (8.5) B (16.6)
Eastbound Approach D (35.6) [<25] {125} D (41.5) [67] {250}
Westbound Approach D (39.1) [44] {154} C (29.2) [42] {148}
Northbound Approach A (5.0) [<25] {236} B (13.2) [82] {490}
Southbound Approach A (4.4) [28] {488} B (11.9) [68] {432}
28: Palmetto Bay Rd & Dunnagans Alley (un-signalized)
Westbound Left Turn D (30.3) [<25] {34} C (34.3) [<25] {64}
Westbound Right Turn A (8.3) [<25] {68} B (12.8) [<25] {98}
Southbound Left Turn A (6.2) [<25] {109} B (10.6) [<25] {46}
29: Palmetto Bay Rd & Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection C (24.2) C (25.0)
Eastbound Approach D (45.3) [93] {237} D (36.7) [90] {283}
Westbound Approach D (37.7) [104] {265} C (30.2) [107] {295}
Northbound Approach B (15.8) [31] {204} C (24.7) [88] {382}
Southbound Approach B (14.7) [62] {293} B (15.0) [55] {361}
27
28
• Implementation of a
signalized intersection
significantly improves
queueing and congestion
29
Option B Operating Conditions (VISSIM)
Page 29 of 234
Final Travel Time Comparison
Corridor
Hilton Parkway between
Moss Creek and Indigo
Run
% Difference
to 2045 No
Build
Hilton Parkway @Moss
Creek to Cross Island
Parkway @Sea Pine
% Difference
to 2045 No
Build
EB WB EB WB SB NB SB NB
2045 No Build Simulated travel
time (secs) [min]
AM 1579
[26.3]
584
[9.7] - - 1984
[33.1]
823
[13.7] - -
PM 642
[10.7]
1544
[25.7] - - 873
[14.6]
2465
[41.1] - -
2045 Modified Alternative 1
Simulated Travel Time (secs)
[min]
AM 628
[10.5]
597
[10] -60.23% 2.23% 1387
[23.1]
848
[14.1] -30.09% 3.04%
PM 631
[10.5]
616
[10.3] -1.71% -60.10% 874
[14.6]
904
[15.1] 0.11% -63.33%
2045 Modified Alternative 1
Option A
Simulated Travel Time (secs)
[min]
AM 548
[9.1]
556
[9.3] -65.31% -4.85% 833
[13.9]
814
[13.6] -58.01% -1.04%
PM 589
[9.8]
600
[10] -8.21% -61.12% 856
[14.3]
845
[14.1] -1.93% -65.72%
2045 Modified Alternative 1
Option B
Simulated Travel Time (secs)
[min]
AM 534
[8.9]
547
[9.1] -66.18% -6.34% 820
[13.7]
816
[13.6] -58.67% -0.86%
PM 571
[9.5]
552
[9.2] -11.06% -64.25% 840
[14]
848
[14.1] -3.78% -65.60%
Neither Option A nor Option B is expected to have a meaningful impact on travel times between Moss
Creek and Indigo run. But they are expected to have a meaningful impact from Moss Creek to Cross Island
@ Sea Pines
Page 30 of 234
Conclusions
• Lochmueller Group was directed to pursue Alternative 1: SCDOT Modified Recommended Preferred
with modifications to provide a single eastbound left-turn lane and a single southbound right-turn lane
at William Hilton Parkway at Squire Pope Road
• With the recommended improvements under Alternative 1: SCDOT Modified Recommended Preferred
in place, the rest of the downstream intersections would be expected to operate acceptably overall.
However, the eastbound and westbound approaches between Wilborn Road and Pembroke Drive are
expected to experience long queues in the year 2045 and the existing roundabout at Palmetto Bay
Road and Sea Pines Circle is expected to fail during both the AM and PM peak hours
• Two additional options for mitigation are provided for The Town of Hilton Head Island’s consideration
in the final report to help ease congestion between Gumtree Road and Indigo Run Drive as well as
along the Cross Island Parkway towards Sea Pines Circle.
• Physical improvements east of Gum Tree Road have a marginal impact on the travel times along
the William Hilton Parkway corridor between Moss Creek and Indigo Run but can improve key
intersection performance and help reduce queueing.
• Improvements such as expanding the existing roundabout at Sea Pines Circle or signalizing the
intersection would significantly improve the travel times along Cross Island Parkway.
Page 31 of 234
QUESTIONS?
https://www.islandpacket.com/news/local/traffic/article235209867.html
Page 32 of 234
APPENDIX
https://www.islandpacket.com/news/local/traffic/article235209867.html
Page 33 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
9: Chamberlin Dr/Squire Pope Rd & Hilton Pkwy (signal)
Overall Intersection A (8.4) B (11.8)
Eastbound Approach A (7.0) [102] {697} B (11.3) [124] {484}
Westbound Approach A (8.2) [28] {237} A (5.8) [36] {524}
Northbound Approach C (30.4) [<25] {56} E (67.0) [<25] {109}
Southbound Approach C (22.6) [<25] {170} D (51.1) [128] {521}
10: Old Wild Horse Rd & Hilton Pkwy (un-signalized)
Southbound Approach A (4.7) [<25] {56} B (12.5) [<25] {32}
11: Spanish Wells Rd/Wild Horse Rd & Hilton Pkwy (signal)
Overall Intersection B (16.6) C (23.8)
Eastbound Approach B (11.0) [106] {998} C (27.9) [198] {861}
Westbound Approach B (11.2) [56] {248} B (11.9) [84] {779}
Northbound Approach D (48.6) [45] {135} E (65.2) [77] {196}
Southbound Approach E (75.9) [74] {292} E (60.6) [49] {197}
12: Gumtree Rd & Hilton Pkwy (signal)
Overall Intersection
D (37.1) D (43.8)
Eastbound Approach C (33.4) [164] {682} E (57.1) [184] {562}
Westbound Approach D (40.8) [130] {369} D (35.4) [236] {786}
Northbound Approach C (26.6) [61] {264} D (37.3) [98] {327}
Southbound Approach D (50.2) [93] {302} D (52.7) [119] {453}
10
• EB LT expected to fail during AM
peak hour
• SB LT expected to fail during PM
peak hour
• SB RT expected to have queues
of over 500 ft during PM peak
hour
• EB, WB, and SB LT expected to
fail during both peak hours
11
9
• WB LT expected to fail
during AM peak hour
12
Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
Page 34 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
13: Jarvis Park Rd/Wilborn Rd & Hilton Pkwy (signal)
Overall Intersection C (26.7) B (18.8)
Eastbound Approach C (25.4) [439] {1480} B (16.3) [103] {735}
Westbound Approach C (21.6) [101] {686} B (18.2) [295] {1202}
Northbound Approach E (68.6) [43] {170} F (87.6) [56] {191}
Southbound Approach D (39.1) [66] {228} B (19.2) [29] {112}
14: Pembroke Dr/Museum St & Hilton Pkwy (signal)
Overall Intersection
C (23.1) C (24.5)
Eastbound Approach B (18.9) [403] {1224} B (17.2) [128] {910}
Westbound Approach C (20.9) [75] {532} C (21.6) [171] {903}
Northbound Approach D (53.1) [71] {257} E (60.1) [92] {299}
Southbound Approach C (30.4) [<25] {89} D (40.3) [<25] {111}
15: Central Ave & Hilton Pkwy (un-signalized)
Eastbound Left Turn A (7.1) [<25] {<25} C (19.3) [<25] {25}
Westbound Left Turn C (24.1) [<25] {26} A (9.5) [<25] {<25}
Northbound Right Turn C (16.5) [<25] {27} B (13.9) [<25] {32}
Southbound Right Turn B (12.5) [<25] {45} C (18.3) [<25] {38}
16: Hatton Pl/Merchant St & Hilton Pkwy (un-signalized)
Northbound Right Turn A (9.5) [<25] {28} A (7.8) [<25] {63}
Southbound Right Turn B (11.3) [<25] {36} C (22.9) [<25] {41}
17: Indigo Run Dr/Whooping Crane Way & Hilton Pkwy (signal)
Overall Intersection C (25.1) D (36.1)
Eastbound Approach C (21.1) [134] {846} C (33.6) [128] {751}
Westbound Approach B (17.3) [53] {359} C (28.0) [207] {887}
Northbound Approach E (56.6) [33] {114} E (66.9) [65] {268}
Southbound Approach D (47.7) [56] {192} E (57.6) [77] {264}
14
15
16
*Highlighted cells indicate that the maximum queues are expected to
extend into the next intersection
• WB LT expected to fail
during AM peak hour
13
• EB LT and NB TH
expected to fail during
PM peak hour
17
Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
Page 35 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection
C (29.0) B (19.0)
Eastbound Approach D (36.9) [1380] {1512} B (15.9) [142] {823}
Westbound Approach B (12.9) [39] {249} B (15.8) [85] {539}
Northbound Approach C (26.6) [<25] {105} D (39.5) [65] {263}
Southbound Approach D (35.7) [34] {151} C (25.5) [37] {140}
28: Palmetto Bay Rd & Dunnagans Alley (un-signalized)
Westbound Left Turn F (1,033.8) [80] {183} F (101.3) [<25] {99}
Westbound Right Turn F (91.9) [109] {217} B (13.3) [35] {134}
Southbound Left Turn C (22.0) [278] {513} B (13.7) [29] {465}
29: Palmetto Bay Rd & Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection F (53.4) F (79.2)
Eastbound Approach F (314.9) [809] {838} F (179.8) [805] {838}
Westbound Approach B (14.0) [56] {420} F (189.7) [1644] {1658}
Northbound Approach A (4.1) [<25] {209} F (52.9) [463] {788}
Southbound Approach C (18.5) [307] {461} A (9.1) [111] {460}
27
28
• Significant queueing along
Palmetto Bay Rd is
anticipated as a result of the
failing roundabout. This
queuing will result in long
delays for WB left-turns at
unsignalized intersections.
29
Downstream Impacts to Task 4 Intersections
(Assuming only the Implementation of Modified
Alternative 1)
Page 36 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
9: Chamberlin Dr/Squire Pope Rd & Hilton Pkwy (signal)
Overall Intersection A (9.4) B (11.8)
Eastbound Approach A (6.9) [100] {676} B (11.0) [117] {489}
Westbound Approach B (11.7) [41] {263} A (6.2) [40] {552}
Northbound Approach C (30.8) [<25] {56} E (67.0) [<25] {109}
Southbound Approach C (22.3) [<25] {171} D (52.3) [132] {518}
10: Old Wild Horse Rd & Hilton Pkwy (un-signalized)
Southbound Approach A (4.6) [<25] {50} B (11.2) [<25] {32}
11: Spanish Wells Rd/Wild Horse Rd & Hilton Pkwy (signal)
Overall Intersection B (16.6) C (26.4)
Eastbound Approach B (11.2) [109] {990} C (28.2) [206] {845}
Westbound Approach B (11.2) [56] {207} B (17.1) [113] {525}
Northbound Approach D (48.4) [45] {140} E (65.2) [77] {196}
Southbound Approach E (76.0) [74] {292} E (60.6) [49] {197}
12: Gumtree Rd & Hilton Pkwy (signal)
Overall Intersection
C (31.5) D (37.2)
Eastbound Approach C (31.3) [168] {705} E (58.2) [187] {559}
Westbound Approach C (24.2) [90] {261} B (19.9) [126] {651}
Northbound Approach C (32.4) [89] {305} D (41.2) [143] {359}
Southbound Approach D (48.6) [91] {306} D (51.9) [117] {428}
10
• EB LT and WB LT expected to fail
during AM peak hour
• SB LT expected to fail during PM
peak hour
• SB RT expected to have queue of
approximately 500 ft during PM
peak hour
• EB, WB, and SB LT expected to
fail during both peak hours
11
9
• WB LT expected to fail
during AM peak hour
• EB LT expected to fail
during PM peak hour
12
Option A Operating Conditions (VISSIM)
Page 37 of 234
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
9: Chamberlin Dr/Squire Pope Rd & Hilton Pkwy (signal)
Overall Intersection A (7.1) B (12.5)
Eastbound Approach A (6.9) [101] {590} B (11.3) [119] {513}
Westbound Approach A (4.5) [<25] {158} A (7.5) [58] {670}
Northbound Approach C (33.2) [<25] {57} E (67.0) [<25] {109}
Southbound Approach C (23.2) [<25] {174} D (50.9) [127] {508}
10: Old Wild Horse Rd & Hilton Pkwy (un-signalized)
Southbound Approach A (5.5) [<25] {74} B (12.6) [<25] {26}
11: Spanish Wells Rd/Wild Horse Rd & Hilton Pkwy (signal)
Overall Intersection C (20.6) C (21.8)
Eastbound Approach B (11.5) [112] {1032} C (24.6) [158] {771}
Westbound Approach C (23.7) [113] {536} B (10.9) [162] {951}
Northbound Approach D (48.6) [45] {135} E (65.2) [77] {186}
Southbound Approach E (75.9) [74] {292} E (59.8) [49] {193}
12: Gumtree Rd & Hilton Pkwy (signal)
Overall Intersection
C (30.9) C (29.7)
Eastbound Approach D (37.4) [160] {658} C (33.0) [103] {485}
Westbound Approach B (13.2) [53] {195} B (18.8) [111] {575}
Northbound Approach C (30.6) [90] {316} D (40.5) [139] {359}
Southbound Approach D (51.5) [99] {366} D (51.4) [118] {443}
10
• EB LT expected to fail during AM
peak hour
• SB LT expected to fail during PM
peak hour
• SB RT expected to have queue of
approximately 500 ft during PM
peak hour
• EB, WB, and SB LT expected to
fail during both peak hours
11
9
• EB LT expected to fail
during both peak hours
12
Option B Operating Conditions (VISSIM)
Page 38 of 234
Independent Study of
William Hilton Parkway Gateway Corridor
Traffic Operations and Safety Report
Town of Hilton Head Island, South Carolina
Prepared for:
Town of Hilton Head Island
1 Town Center Court
Hilton Head Island, South Carolina
843.341.4600
Prepared by:
Lochmueller Group
Huntington Tower, 201 W Springfield Avenue
Suite 1012
Champaign, Illinois 61820
217.673.7633
AUGUST 9, 2024
Page 39 of 234
P A G E | i
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
CONTENTS
List of Figures ............................................................................................................................................... iii
List of Tables ................................................................................................................................................ iv
Executive Summary ....................................................................................................................................... v
Existing and No-Build Conditions .............................................................................................................. v
Corridor Study Goals ................................................................................................................................. v
Proposed Alternatives Selected for Analysis ........................................................................................... vi
Introduction .................................................................................................................................................. 1
Study Objective ......................................................................................................................................... 1
Study Overview ......................................................................................................................................... 3
Background ................................................................................................................................................... 3
Data Collection and Field Inventory .......................................................................................................... 3
Analysis Methodology ............................................................................................................................... 5
Existing Conditions ........................................................................................................................................ 8
Existing Synchro Traffic Operational Analysis ........................................................................................... 8
Existing VISSIM Traffic Operational Analysis............................................................................................. 9
Existing VISSIM Network Performance ..................................................................................................... 9
2045 No-Build Conditions ........................................................................................................................... 10
2045 No-Build Synchro Traffic Operational Analysis .............................................................................. 11
2045 No-Build VISSIM Traffic Operational Analysis ................................................................................ 11
2045 No-Build VISSIM Network Performance ........................................................................................ 11
2045 Alternatives Analysis .......................................................................................................................... 13
Corridor Study Goals ............................................................................................................................... 14
Alternatives Considered .......................................................................................................................... 14
2045 Alternative 1: SCDOT Modified Recommended Preferred ............................................................ 22
2045 Alternative 2: Bowties at Squire Pope and Spanish Wells ............................................................. 23
2045 Alternative 3: Echelon / Center Turn Overpass ............................................................................. 26
2045 Alternative 4: Elevated Bypass ....................................................................................................... 30
Alternatives Comparison and Conclusions ............................................................................................. 32
Town Selected Alternative ...................................................................................................................... 38
Downstream Impacts of Town Selected Modified Alternative 1 ................................................................ 39
Page 40 of 234
P A G E | ii
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Modified Alternative 1 Traffic Analysis ................................................................................................... 39
Additional Mitigation Solutions for Local Intersections ............................................................................. 42
Options A and B VISSSIM Traffic Operational Analysis ........................................................................... 44
Options A and B VISSIM Travel Time Comparison .................................................................................. 44
Options A and B Network Performance .................................................................................................. 46
Multimodal and Safety Recommendations for Local Intersections ........................................................ 47
Conclusions ................................................................................................................................................. 50
2045 Altneratives Analysis ...................................................................................................................... 50
Downstream Impacts of Town Selected Alternative 1 ........................................................................... 53
Additional Mitigation Solutions for Local Intersections ......................................................................... 53
Appendix ..................................................................................................................................................... 55
Appendix A: 2023 Existing Traffic Volumes .......................................................................................... A-1
Appendix B: 2023 Existing Operating Conditions (Synchro) .................................................................. B-1
Appendix C: 2023 Existing Operating Conditions (VISSIM) .................................................................... C-1
Appendix D: Traffic Forecasting Memorandum .................................................................................... D-1
Appendix E: 2045 No-Build Traffic Volumes .......................................................................................... E-1
Appendix F: 2045 No-Build Traffic Operating Conditions (Synchro)...................................................... F-1
Appendix G: 2045 No-Build Traffic Operating Conditions (VISSIM) ..................................................... G-1
Appendix H: Four Lane Viability Review Technical Memorandum; Seismic Study Review; Cursory
Review of Southern Bypass ................................................................................................................... H-1
Appendix I: 2045 Alternative 1 Traffic Volumes and Operating Conditions (Synchro) ........................... I-1
Appendix J: Technical Environmental Overview .................................................................................... J-1
Appendix K: 2045 Alternative 2 Traffic Volumes and Operating Conditions (Synchro) ........................ K-1
Appendix L: 2045 Alternative 3 Traffic Volumes and Operating Conditions (Synchro) ......................... L-1
Appendix M: 2045 Alternative 4 Traffic Volumes and Operating Conditions (Synchro) ..................... M-1
Appendix N: 2045 Modified Alternative 1 Operating Conditions (VISSIM) .......................................... N-1
Appendix O: 2045 Local Intersections Operating Conditions (VISSIM) ................................................ O-1
Page 41 of 234
P A G E | iii
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
LIST OF FIGURES
Figure 1. Entire Project Study Area ............................................................................................................... 2
Figure 2. Modified Original Project Study Area ............................................................................................ 2
Figure 3. Alternative 1: SCDOT Modified Recommended Preferred .......................................................... 15
Figure 4. Example Bowtie Intersection (Provided by Virginia DOT) ........................................................... 16
Figure 5. Example Echelon (Provided by Virginia DOT) .............................................................................. 18
Figure 6. Example Center Turn Overpass (Provided by Virginia DOT) ........................................................ 18
Figure 7. Example of Elevated Bypass - 01 .................................................................................................. 20
Figure 8. Example of Elevated Bypass - 02 .................................................................................................. 20
Figure 9. Example of Elevated Bypass - 03 .................................................................................................. 21
Figure 10. Example of Elevated Bypass - 04 ................................................................................................ 21
Figure 11. Proposed Roundabout Configuration at Sea Pines Circle Under Option A ................................ 43
Page 42 of 234
P A G E | iv
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
LIST OF TABLES
Table 1. Intersection Level of Service Criteria .............................................................................................. 6
Table 2. 2023 Existing VISSIM Calibration Travel Time Results .................................................................... 7
Table 3. 2023 Existing VISSIM Calibration Traffic Volumes Results .............................................................. 8
Table 4. Existing Corridor Speeds (VISSIM) ................................................................................................. 10
Table 5. Network Performance – Existing Conditions ................................................................................ 10
Table 6. 2045 No-Build VISSIM Calibration Travel Time Results ................................................................. 12
Table 7. 2045 No-Build VISSIM Calibration Traffic Volumes Results .......................................................... 12
Table 8. Network Performance – 2045 No-Build Conditions ...................................................................... 13
Table 9. Travel Time Comparison for Alternative 1 .................................................................................... 23
Table 10. Travel Time Comparison for Alternative 2 .................................................................................. 25
Table 11. Expected Change in Travel Time for Left-Turning Vehicles at Bowtie Intersections .................. 25
Table 12. Travel Time Comparison for Alternative 3 .................................................................................. 28
Table 13. Travel Time Comparison for Alternative 4 .................................................................................. 31
Table 14. Traffic Operations Overview Matrix ............................................................................................ 33
Table 15. Bicycle and Pedestrian Overview Matrix..................................................................................... 34
Table 16. Right-of-Way Overview Matrix ................................................................................................... 35
Table 17. Environmental Overview Matrix ................................................................................................. 36
Table 18. Overall Scoring Matrix ................................................................................................................. 37
Table 19. 2045 Modified Alternative 1 VISSIM Travel Time Results ........................................................... 40
Table 20. Network Performance – 2045 Modified Alternative 1 Without Improvements to Downstream
Intersections ............................................................................................................................................... 41
Table 21. Comparison of Final Travel Times for Entire Study Area ............................................................ 46
Table 22. Network Performance for Entire Study Area .............................................................................. 47
Page 43 of 234
P A G E | v
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
EXECUTIVE SUMMARY
The Town of Hilton Head Island, South Carolina commissioned an independent study of the William
Hilton Parkway Gateway Corridor to assess the need for improvements along US 278 (William Hilton
Parkway) from Moss Creek Drive to Indigo Run Drive, as well as along US 278 (Palmetto Bay Road) from
Cross Island Parkway to Sea Pines Circle. This report summarizes Existing and future year No-Build traffic
operations along the corridor to quantify mobility issues that exist today and that would be expected in
the future, absent any upgrades to the roadway network.
Additionally, this report details the numerous corridor alternatives considered for implementation along
William Hilton Parkway between Moss Creek Drive and Gum Tree Road. Proposed alternatives consisting
of two at-grade solutions and two grade separated solutions were analyzed in further detail. The goal of
the corridor alternatives analysis was to provide an objective, data-driven evaluation of the four
alternatives. This evaluation was then used to assist with the selection of a single recommended
alternative for the corridor between Moss Creek and Gum Tree Road.
EXISTING AND NO -BUILD CONDITIONS
CONGESTION AND CORRIDOR MOBILITY
• In 2045, out of a total of 105 intersection approaches, 19 and 24 intersection approaches
experienced levels of service between E/F throughout the study corridor during the AM
and PM peak hours, respectively.
• The existing vehicle speeds along William Hilton Parkway between Moss Creek Drive and
Indigo Run Drive average at approximately 19 miles per hour (mph) in the eastbound
direction during the AM peak hour and approximately 17 mph in the westbound direction
during the PM peak hour. This is well below the posted speed limits, indicating significant
congestion along the corridor today.
• It was found that an over-saturation of the study area under the 2045 No-Build scenario
resulted in vehicles not being able to enter the VISSIM simulation network. Therefore,
some of the vehicles in the model were not processed through each intersection.
• The 2045 No-Build travel times along the William Hilton Parkway corridor between Moss
Creek Drive and Indigo Run are higher than existing conditions. It is expected that the travel
time in the eastbound direction during the AM peak hour will increase from approximately
19.3 minutes to 26.3 minutes, an increase of 7 minutes (36%) when compared to existing
conditions. During the PM peak hour, it is expected that the travel time in the westbound
direction will increase from 20.9 minutes to 25.7 minutes, an increase of approximately 5
minutes (23%) when compared to existing conditions.
CORRIDOR STUDY GOALS
The following goals for improving the William Hilton Parkway Gateway Corridor were established by
Town of Hilton Head representatives to guide the development of alternatives and form the basis for
the alternatives analysis:
Page 44 of 234
P A G E | vi
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
• Fix the transportation issues in the corridor in a way that improves the safety and quality of
life for all residents, workers, and visitors to Hilton Head Island
a) Address transportation needs for natural disasters and resiliency of island access
b) Consider future transportation alternatives
• Improve the safety and quality of life for the residents of the neighborhoods and businesses
directly impacted by the US 278 corridor
a) Stoney Community
b) Neighborhoods on Jenkins and Hog Islands (including but not limited to Windmill
Harbor)
• Have a gateway to and from Hilton Head Island that the region will be proud of:
a) Aesthetically pleasing and reflecting the Hilton Head Island/Low Country values
b) Safe and functional pathways for pedestrians and cyclists
c) Minimizes environmental impacts and enhances the national asset of Pinckney Island
PROPOSED ALTERNATIVES SELECTED FOR ANALYSIS
Four proposed corridor alternatives were developed to help mitigate congestion along William Hilton
Parkway between Moss Creek Drive and Gum Tree Road.
ALTERNATIVE 1: SCDOT MODIFIED RECOMMENDED PREFERRED
• Alternative 1 considers the SCDOT Modified Recommended Preferred alternative with
adaptive signals in place and improvements at Gum Tree Road.
• The improvements at Gum Tree Road include keeping the intersection at-grade, completely
reconfiguring the intersection to improve its efficiency, and providing dual left-turn lanes for
the westbound, northbound, and southbound approaches.
ALTERNATIVE 2: BOWTIES
• Alternative 2 considers bowties at Squire Pope Road and Spanish Wells Road with adaptive
signals in place and aforementioned improvements at Gum Tree Rd.
• A bowtie intersection removes left-turns from the intersection and requires vehicles to
navigate through roundabouts along the side-street to return to the signal and continue in
their intended direction of travel.
ALTERNATIVE 3: ECHELON / CENTER TURN OVERPASS
• Alternative 3 considers either an echelon or a center turn overpass at either Squire Pope
Road or Spanish Wells Rd. Echelons or Center Turn Overpasses at both Squire Pope Road
and Spanish Wells Road were not considered because there is not enough distance
between intersections for both to be independently grade-separated.
• Alternative 3 also considers the aforementioned improvements at Gum Tree Road.
Page 45 of 234
P A G E | vii
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
• An echelon is a grade-separate intersection where one approach on both roadways is
elevated. For example, the northbound and eastbound approaches would be elevated and
the southbound and westbound approaches would remain at-grade to create two
intersections. Both intersections would be signalized and all pedestrian and bicycle
movements would remain at-grade.
• A center turn overpass is also a grade-separated intersection which raises only the left-turn
movements from the main intersection using ramps to create two intersections. Both
intersections would be signalized and all pedestrian and bicycle movements would remain
at-grade.
ALTERNATIVE 4: ELEVATED BYPASS
• Alternative 4 considers an elevated bypass which would begin west of Squire Pope Road
and end east of Gum Tree Road. The elevated bypass takes the four internal lanes, two in
each direction, and elevates them over the study intersections. This would allow free-flow
movement for the eastbound and westbound thru traffic from just east of the Jenkins
Island causeway to just west of Wilborn Road. One lane in each direction along William
Hilton Parkway would remain at grade along with a separate eastbound right-turn lane at
Squire Pope Road and left-turn lanes at Squire Pope Road and Spanish Wells Road. This
allows for full access to be maintained at Squire Pope Road and Spanish Wells Road. Full
access could also be provided at Old Wild Horse Rd, which is currently a right-in/right-out
intersection, in this scenario.
• The elevated bypass would directly connect to the Cross Island Parkway and allow thru
vehicles to bypass Gum Tree Road. In the eastbound direction, the two eastbound lanes
would expand to provide one lane to the Cross Island Pkwy, one lane to William Hilton
Parkway at-grade for access to Gum Tree Road, and two lanes will continue along the
elevated bypass and connect to the at-grade section just east of Gum Tree Road, allowing
thru vehicles to also bypass Gum Tree Road.
The goal of the alternatives analysis was to provide an objective, data-driven evaluation of the four
corridor alternatives. Therefore, various matrices were compiled with respect to traffic operations,
bicycle and pedestrian accommodations, right-of-way (ROW) requirements, and environmental factors
to inform an overall scoring matrix. Each of the matrices includes scores for various categories. A score
of 1 is the highest ranking, whereas a score of 4 is the lowest ranking. The ranking for each category
were tallied to reach a total aggregate score per alternative.
Alternative 1 ranked first with a total score of 20. Alternative 4 ranked second with a total score of 21.
Alternative 2 ranked third with a total score of 24, and Alternative 3 ranked last with a total score of 28.
Page 46 of 234
P A G E | viii
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Resource/Category
Alternative 1
(Mod. SCDOT
Recommended
Preferred)
Alternative 2
(Bowties at Squire
Pope and Spanish
Wells)
Alternative 3
(Echelon / Center Turn
Overpass)
Alternative 4
(Elevated Bypass)
Traffic Operations (Throughput
and Traffic Simulations) 4 3 3 1
ROW Impact 2 4 4 1
Environmental Impact 1 3 4 2
Safety 4 3 3 1
Bike/Pedestrian Impact 4 3 1 2
Community and Social Impact 1 3 4 2
Aesthetic 2 1 3 4
Preliminary Probable Opinion
of Cost 1 2 3 4
Construction Duration 1 2 3 4
TOTAL 20 24 28 21
RANK 1 3 4 2
Page 47 of 234
P A G E | ix
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Per the direction of the Town of Hilton Head Island, Lochmueller Group was directed to pursue corridor
Alternative 1: South Carolina Department of Transportation (SCDOT) Modified Recommended Preferred
with modifications to provide a single eastbound left-turn lane and a single southbound right-turn lane
at the intersection of William Hilton Parkway at Squire Pope Road.
With the recommended improvements under Alternative 1: SCDOT Modified Recommended Preferred
in place, this report further provides an evaluation on the impacts to the intersections downstream (i.e.,
east of Gum Tree Road to Indigo Run, and south of Cross Island Parkway to Sea Pines Circle). Two
additional options for mitigation are provided herein for the Town of Hilton Head Island’s consideration
to help ease congestion along the local intersections between Gum Tree Road and Indigo Run Drive, as
well as along the Cross Island Parkway towards Sea Pines Circle.
Page 48 of 234
P A G E | 1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
INTRODUCTION
The Town of Hilton Head Island, South Carolina commissioned an independent review of the William
Hilton Parkway Gateway Corridor to assess congestion related issues along US 278 (William Hilton
Parkway) from Moss Creek Drive to Indigo Run Drive, as well as along US 278 (Palmetto Bay Road) from
Cross Island Parkway to Sea Pines Circle. This report summarizes Existing and future year No-Build traffic
operations along the William Hilton Parkway corridor to quantify mobility issues that exist today and
that would be expected in the future, absent any upgrades to the corridor.
Additionally, this report details the numerous alternatives considered for implementation along William
Hilton Parkway between Moss Creek Drive and Gum Tree Road. Proposed alternatives consisting of two
at-grade solutions and two grade separated solutions were then analyzed to help alleviate congestion
along the corridor. The goal of the corridor alternatives analysis was to provide an objective, data-driven
evaluation of the four alternatives.
After review of the four corridor alternatives, the Town of Hilton Head Island directed Lochmueller
Group to pursue further evaluation of Alternative 1: SCDOT Modified Recommended Preferred with
modifications to provide a single eastbound left-turn lane and a single southbound right-turn lane at
William Hilton Parkway at Squire Pope Rd. This report details the final projected operating conditions for
the selected alternative and addresses the potential downstream impacts to the intersections along
William Hilton Parkway between Gum Tree Road and Indigo Run Drive, as well as along Cross Island
Parkway to Sea Pines Circle assuming no additional improvements are in place. Lastly, two additional
mitigation solutions were developed to address congestion issues at the local intersections between
Gum Tree Road and Indigo Run Drive, as well as along Cross Island Parkway to Sea Pines Circle.
STUDY OBJECTIVE
The objective of this study was to provide an independent review and end-to-end analysis of the William
Hilton Parkway Gateway Corridor. This study assessed congestion related issues along the corridor
between Moss Creek Drive and Indigo Run Drive, as well as along the Cross Island Parkway to Sea Pines
Circle. The intention of this study was to evaluate several corridor alternatives to help address the
existing and future projected congestion in order to provide the Town of Hilton Head Island with a data
driven analysis.
Page 49 of 234
P A G E | 2
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Figure 1. Entire Project Study Area
Figure 2. Modified Original Project Study Area
Moss Creek Dr
Indigo Run Dr
Gum Tree Rd
Sea Pines Circle
Buckingham
Plantation Dr
Moss Creek Dr
Gum Tree Rd
Buckingham
Plantation Dr
Page 50 of 234
P A G E | 3
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
STUDY OVERVIEW
William Hilton Parkway (US 278) is currently classified as a principal arterial oriented in the east-west
direction within the study area, providing connectivity to Hilton Head Island. This study was completed
in several phases. The first phase evaluated the 2023 Existing conditions and 2045 No-Build conditions
for the entire project area, which includes William Hilton Parkway from Moss Creek Drive to Indigo Run
Drive, as well as Palmetto Bay Road from Cross Island Parkway to Sea Pines Circle, as shown in Figure 1.
The second phase evaluated four alternatives to help reduce congestion along the William Hilton
Parkway corridor between Moss Creek Drive and Gum Tree Road. This is referred to as the Modified
Original Project Study Area and is shown in Figure 2. Of those four corridor alternatives, one was
selected for further evaluation to assess the impacts throughout the Entire Project Study Area.
The third and final phase evaluated the impacts of the selected corridor alternative from the second
phase of analysis, and further recommendations were made to help improve the overall operations of
the Entire Project Study Area (Figure 1).
BACKGROUND
DATA COLLECTION AND FIELD INVENTORY
TRAFFIC DATA
Traffic volumes were collected by others at the following intersections on March 22, 2023, and provided
to Lochmueller Group for use in this analysis:
• Buckingham Plantation Dr and Bluffton Pkwy
• Buckingham Plantation Dr and US 278
• Moss Creek Dr and US 278
• WB Bluffton Pkwy Ramp and WB US 278
• EB Bluffton Pkwy Ramp and EB US 278
• Fording Island Rd Extension and US 278
• Pinckney Wildlife Refuge and US 278
• Blue Heron Point Rd and US 278
• Crosstree Dr and US 278
• Jenkins Rd and US 278
• Squire Pope Rd and US 278
• Spanish Wells Rd and US 278
• Cross Island Pkwy Diverge and EB US 278
• Cross Island Pkwy Merge and WB US 278
• Gum Tree Rd and Cross Island Pkwy Off and On
Ramps
• Gum Tree Rd and Business US 278
• Jarvis Park Rd and Business US 278
• Pembroke Dr and Business US 278
• Indigo Run Dr and Business US 278
• Marshland Rd and Spanish Wells Rd
• Marshland Rd and SB Cross Island Pkwy Ramps
• Marshland Rd and NB Cross Island Pkwy Ramps
• Arrow Rd and US 278
• Target Rd and US 278
• Sea Pines Circle and US 278
This study evaluated conditions during the morning and evening peak periods of a typical weekday, as
these periods represent the most critical times of day for traffic operations within the study area for
commuter peaks. If traffic can be accommodated during these peak periods, it stands to reason that
adequate capacity would be available throughout the remainder of the day.
Page 51 of 234
P A G E | 4
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Traffic data utilized for this study is based on a combination of historical traffic counts obtained from
SCDOT supplemented with new counts performed in March 2023. From the data, the weekday peak
hours of traffic for the entire project study area were determined to occur between 7:00 AM and 8:00
AM in the morning and from 4:30 PM to 5:30 PM during the afternoon.
Corridor studies often reference the 30th highest day for traffic volumes to ensure that the volumes
used in the analysis reflect peak conditions, while not over- or under-estimating the traffic volumes.
Therefore, it was necessary to ensure that the counts collected accurately reflect the 30th highest day.
Historical traffic data was obtained from SCDOT from the most recent 365 days. Given that the study
focuses on commuter peak hours, the hourly data from 6:00 AM – 6:00 PM was referenced. After
reviewing the traffic volumes throughout the year, it was determined that March 30, 2023 was the 30th
highest day out of the year for traffic volumes. The counts collected on March 22, 2023 were grown by
the percent difference between the two dates to bring them up to the estimated traffic volumes on
March 30, 2023 (30th highest day). The resulting 2023 traffic volumes used in this study are provided in
Appendix A.
Page 52 of 234
P A G E | 5
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
FIELD INVENTORY
A detailed inventory of field conditions was performed to capture both physical and operational
characteristics of the study area network. The physical inventory emphasized static features of the
roadway and included items such as posted speed limits, number of travel lanes, lane designations at
intersections, adaptive signal operations, and traffic signal phasing (e.g., protected turn arrows versus
permissive turning movements).
This detailed inventory of field conditions, as well as traffic observations focused on traffic flows during
the peak periods, was performed over the course of two weekdays in December 2023. Locations of
congestion and traffic backups were identified and monitored to determine sources of constrained
flows. Prevailing queue lengths at intersections were inventoried. Traffic signal operations were
monitored to determine the quality of traffic progression along the William Hilton Parkway corridor and
to identify the operations of the recently installed (late Fall 2023) adaptive signal system. Travel time
runs and average speeds were conducted during the AM and PM peak periods along William Hilton
Parkway between Moss Creek Drive and Indigo Run Drive, as well as from William Hilton Parkway at
Moss Creek Drive to Cross Island Parkway at Sea Pines Circle, as detailed in the model calibration section
of this document.
ANALYSIS METHODOLOGY
TRAFFIC
A preliminary analysis was completed using Synchro 11 traffic modeling software, which is based upon
the methodologies outlined in the “Highway Capacity Manual” (HCM) published by the Transportation
Research Board. Intersection performance or traffic operations are quantified by six Levels of Service
(LOS), which range from LOS A ("Free Flow”) to LOS F ("Fully Saturated"). LOS D is considered acceptable
for peak period conditions in urban and suburban areas. However, at side-street stop-controlled
intersections, LOS E or even F is common occurrence for peak period conditions as it is typical for delays
to be longer for vehicles along the side-street as they wait to find acceptable gaps in the traffic to turn
into the traffic stream. Table 1 shows the LOS criteria for signalized and unsignalized intersections.
Levels of service for intersections are determined based on the average delay experienced by motorists.
Signalized intersections reflect higher delay tolerances as compared to unsignalized and roundabout
locations because motorists are accustomed to and accepting of longer delays at signals. For signalized
and all-way stop intersections, the average control delay per vehicle is estimated for each movement
and then aggregated for each approach and the intersection as a whole. For intersections with partial
(side-street) stop control, the delay is calculated for the minor movements only (side-street approaches
and major road left-turns) since thru traffic on the major road is not required to stop.
Page 53 of 234
P A G E | 6
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 1. Intersection Level of Service Criteria
Level of
Service
Control Delay per Vehicle (sec/veh)
Signalized Unsignalized
A ≤ 10 0 - 10
B > 10 - 20 > 10 - 15
C > 20 - 35 > 15 - 25
D > 35 - 55 > 25 -35
E > 55 - 80 > 35 - 50
F > 80 > 50
Source: HCM 6th Edition
In addition to Synchro, VISSIM software was also used, which is a microsimulation tool that accurately
replicates individual vehicles and their interactions within complex traffic streams, such as interchanges,
freeways, and expressway corridors with signalized intersections. A robust amount of data and field
observations were conducted, as previously described, to calibrate the VISSIM models to closely
replicate field conditions.
MODEL CALIBRATION
The VISSIM traffic simulation model calibration process began with the development of a base model,
which aims to replicate Existing conditions. As previously noted, a robust data collection effort was
required to support this effort, including roadway geometry, turning speeds, traffic signal timings, etc.
The first step in base model development involved coding the roadway geometry (number of lanes, lane
configurations, link lengths, etc.) with links and connectors using a recent aerial as a template.
Once the network backbone was established, free-flow speed distributions were created. Reduced
speed zones were also established for turning movements and locations in the network where the
roadway geometry physically limits speeds below the free-flow speed or posted speed limits. The next
steps addressed traffic control. The adaptive traffic signal timings obtained from Q-Free were input into
the simulation, with detectors coded where applicable. Stop-controlled movements received stop signs
coded into the network. Locations where yielding or traffic control priority needed to be established
(such as a right-turn-on-red) were coded with conflict areas or priority rules. Conflict areas are most
commonly used unless further refinement of the gap times or yielding characteristics was necessary, in
which case priority rules were deployed.
Traffic volumes were then represented in the VISSIM model as an origin-destination matrix estimated
from turning movement counts. The matrix specifies the model’s traffic patterns and the routes vehicles
take to traverse the model network. Traffic entering the model network was coded using vehicle inputs.
Vehicle inputs specify volumes and vehicle type compositions, which were grouped into passenger
vehicles, trucks, light-goods, and buses. The origin-destination matrix was routed statically with routes
traversing the entire network for optimum accuracy rather than simply intersection by intersection.
Page 54 of 234
P A G E | 7
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Since VISSIM starts with zero vehicles in the network, a warm-up period is needed to initiate the model
with traffic prior to capturing data. The warm-up period is known as the seeding period and its length
and volume characteristics were adjusted as part of the calibration process. Given the scale of the
network, a 60-minute seeding period was used to establish background traffic before recording results.
Given the inherent stochastic nature of simulation (imposed by random seeds), multiple simulation runs
using different seed numbers were required for each scenario and the reported model results were
averaged across runs. Ten simulation runs were completed, which is typically sufficient to obtain an
appropriate level of confidence in the results.
The model calibration process finished with a detailed review of model parameters and thorough
consideration of adjustments to improve the model’s ability to replicate field conditions. The final
calibration process compared data output from the model, such as travel times and flow rates, to field
measurements of the same attributes.
As part of the calibration criteria, it was determined that the travel times reported in the VISSIM model
should be within 10% of the travel times recorded in the field. The travel times calculated in the VISSIM
model were inflated by 15% to account for higher volumes in March (when traffic counts were collected)
versus in December (when the travel times were collected). The travel time results are provided in Table
2. As shown, all the travel times reported by the Existing conditions VISSIM model were within 10% of
the observed travel times recorded during field observations. Therefore, all travel time targets were
satisfied.
Table 2. 2023 Existing VISSIM Calibration Travel Time Results
Corridor
Observed Travel
Time (secs) [min]
Simulated Travel
Time (secs) [min] % Difference
AM PM AM PM AM PM
William Hilton Pkwy
between Moss Creek and
Indigo Run
EB 1108
[18.5 min]
672
]11.2 min]
1157
[19.3 min]
619
[10.3 min] 4.42% -7.91%
WB 605
[10.1 min]
1202
[20 min]
572
[9.5 min]
1252
[20.9 min] -5.50% 4.17%
William Hilton Pkwy from
Moss Creek to Sea Pine Circle
via Cross Island Pkwy
SB 1378
[23 min]
821
[13.7 min]
1356
[22.6 min]
857
[14.3 min] -1.58% 4.37%
NB 800
[13.3 min]
1516
[25.3 min]
826
[13.8 min]
1520
[25.3 min] 3.20% 0.25%
In addition to travel time calculations, traffic volumes were also used to help calibrate the VISSIM
model. Similar to the travel times, it was determined that the traffic volumes reported in the VISSIM
model should be within 10% of the 2023 existing traffic volumes provided in Appendix A. The traffic
volume results are provided in Table 3. As shown, all the traffic volumes reported by the existing
conditions VISSIM model were within 10% of the calculated 2023 existing corridor traffic volumes.
Therefore, all traffic volume targets were satisfied.
Page 55 of 234
P A G E | 8
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 3. 2023 Existing VISSIM Calibration Traffic Volumes Results
Location
Observed Traffic
Volumes
(vehicles)
Simulated Traffic
Volumes
(vehicles)
% Difference
AM PM AM PM AM PM
William Hilton Pkwy west of Squire Pope EB 2774 2237 2970 2240 7.07% 0.13%
William Hilton Pkwy west of Squire Pope WB 1639 3030 1650 2898 0.67% -4.36%
William Hilton Pkwy east of Spanish Wells EB 2729 1991 2929 1955 7.33% -1.81%
William Hilton Pkwy east of Spanish Wells WB 1408 2623 1423 2614 1.07% -0.34%
Cross Island Pkwy north of Marshland Rd NB 975 1422 964 1371 -1.13% -3.59%
Cross Island Pkwy north of Marshland Rd SB 1416 1190 1486 1167 4.94% -1.93%
EXISTING CONDITIONS
EXISTING SYNCHRO TRAFFIC OPERATIONAL ANALYSIS
A preliminary analysis was completed using Synchro 11 traffic modeling software, which is based upon
the methodologies outlined in the “Highway Capacity Manual” (HCM) published by the Transportation
Research Board.
Operating conditions at the study intersections were evaluated using Synchro 11 and are summarized in
Appendix B. The measures of effectiveness reported include LOS, delay, queue, and volume-to-capacity
ratio (v/c). The delay is reported in seconds per vehicle. The queue is reported in feet as the 95th
percentile queue, which represents a value that is only expected to be exceeded once or twice during a
peak hour. The v/c ratio compares vehicle demand to the capacity of an associated lane group. A v/c
ratio of 1.0 represents a road segment that is at full capacity. A v/c ratio that exceeds 1.0 represents a
road segment that is oversaturated or has more vehicular demand than the provided roadway geometry
can theoretically support.
It was found that the eastbound traffic experiences significant congestion during the AM peak period,
whereas westbound traffic experiences significant congestion during the PM peak period. This is
consistent with the commuter traffic patterns in the Town of Hilton Head.
While several intersections experience long delays and queue lengths during the AM peak hour, the PM
peak hour appears to have overall worse operating conditions. Long delays occur along side-streets at
unsignalized intersections throughout the entire study area. Additionally, a rolling queue begins at
Wilborn Road and continues in the westbound lanes of William Hilton Parkway over the bridge during
the PM peak hour. The westbound queue length reaches up to approximately 2,500 ft (101 cars) at
Squire Pope during the PM peak hour. It is evident that the study area currently experiences congestion
during both the AM and PM peak periods.
Page 56 of 234
P A G E | 9
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
EXISTING VISSIM TRAFFIC OPERATIONAL ANALYSIS
A VISSIM traffic model was also completed to further evaluate conditions during the morning and
afternoon peak hours, and provides performance measures as outputs. The LOS criteria for signalized
and unsignalized intersections are the same as Table 1. The measures of effectiveness (MOE) reported
include levels of service, delay, average queue length, and maximum observed queue length. The delay
is reported in seconds per vehicle and the queue is reported in feet.
The 2023 Existing operating conditions based on the VISSIM model are summarized in Appendix C. The
traffic operations largely agree with those shown in Appendix B from the Synchro analysis. The PM peak
hour appears to have overall worse operating conditions than the AM peak period. The long delays
presented in the Synchro analysis along side-streets at unsignalized intersections throughout the entire
study area were confirmed in the VISSIM analysis. The study area experiences significant congestion
during both the existing AM and PM peak periods.
EXISTING VISSIM NETWORK PERFORMANCE
The existing average recorded speeds along William Hilton Parkway between Moss Creek Drive and
Indigo Run range from approximately 19 miles per hour (mph) in the AM peak hour to 35 mph during
the PM peak hour for the eastbound direction, as shown in Table 4. The posted speed limit along the
corridor ranges between 45-55 mph. Therefore, it is evident that the existing average recoded speeds
are well below the posted speed limit, which is an indication that there is significant congestion along
the corridor. The westbound direction experiences average speeds of approximately 38 mph during the
AM peak hour and 17 mph during the PM peak hour. This indicates significant congestion in the
westbound direction during the PM peak hour, as is evidenced by the commuter peaks.
Between Moss Creek Drive and Sea Pines Circle via the Cross Island Parkway in the southbound
direction, the average recorded speed is approximately 27 mph during the AM peak hour and the
average recorded speed is 42 mph during the PM peak hour. In the opposite direction, the average
recorded speed is approximately 44 mph during the AM peak hour and 24 mph in the PM peak hour.
Similar to the William Hilton Parkway corridor between Moss Creek Drive and Indigo Run, this corridor
also experiences congestion in relation to the commuter peaks.
Table 5 further breaks down overall network performance for the existing peak period conditions. As
shown, throughout the entire project area, vehicles are required to stop on average between 6 to 10
times when traveling along the corridor.
Page 57 of 234
P A G E | 10
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 4. Existing Corridor Speeds (VISSIM)
Routes
Average Speed (mph)
AM Peak Hour PM Peak Hour
Moss Creek Drive to Indigo Run Drive – Eastbound 18.9 35.2
Indigo Run Drive to Moss Creek Drive – Westbound 38.0 17.4
Moss Creek Drive to Sea Pines Circle – Southbound 26.6 42.1
Sea Pines Circle to Moss Creek Drive – Northbound 43.9 23.8
Table 5. Network Performance – Existing Conditions
Peak Hour
Average Number
of Stops per
Vehicle
Average Speed
(mph)
Total Vehicles
(vph)
Existing AM 6.5 25 10,497
Existing PM 9.9 22 12,393
2045 NO -BUILD CONDITIONS
2045 was selected as the project’s design year for purposes of evaluating traffic operations conditions
into the future. The 2045 No-Build conditions analysis is intended to reflect future conditions within the
study area while accounting for an increase in “background” traffic. No modifications were made to the
lane configurations. The 2045 No-Build scenario does include the effects of the adaptive signal system
implemented in the Fall of 2023, as well as the inclusion of Windmill Harbour into the adaptive signal
system.
In order to evaluate traffic conditions through the year 2045, it was necessary to forecast the
anticipated growth within the study area based on an increase in “background” traffic resulting from
increasing population and commercial and employment growth in The Town of Hilton Head.
An annual background growth rate of 0.56% was determined after careful consideration of the
Lowcountry Area Transportation Study (LATS) Travel Demand Model (TDM), census data, Beaufort
County historic growth trends, historic traffic growth on the US 278 bridge, sale and restaurant tax
revenue, public parking revenue, and short term rental data. A memorandum detailing the methodology
behind the 0.56% growth rate is provided in Appendix D. The 2023 Existing traffic volumes were grown
annually by 0.56% to 2045 in order to produce the 2045 No-Build traffic volumes which are provided in
Appendix E.
Page 58 of 234
P A G E | 11
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
2045 NO -BUILD SYNCHRO TRA FFIC OPERATIONAL ANALYSIS
The 2045 No-Build operating conditions at the study intersections were preliminarily evaluated using
Synchro 11 and are summarized in Appendix F. The previously failing conditions and congestion
experienced in the 2023 Existing conditions are expected to be exacerbated by 2045 with the forecasted
background traffic growth. Significant congestion is expected throughout the study area. Therefore, it
can be concluded that the study intersections cannot accommodate the forecasted traffic growth in
their existing state.
2045 NO -BUILD VISSIM TRAFFIC OPERATIONAL ANALYSIS
The 2045 No-Build operating conditions at the study intersections were further evaluated using VISSIM
and are summarized in Appendix G. The operating conditions largely agree with those shown in the
2045 No-Build Synchro operating conditions (Appendix F) and validate the travel time and volume
conclusions above. Significant congestion is expected throughout the study area through the year 2045.
The congestion that currently exists throughout the study area is expected to be exacerbated by 2045
with the forecasted growth.
2045 NO -BUILD VISSIM NETWORK PERFORMANCE
The VISSIM differences in reported travel time calculations and traffic volumes between the 2023
Existing conditions and 2045 No-Build conditions were evaluated and shown in Table 6 and Table 7,
respectively.
It is expected that the travel time in the eastbound direction along Hilton Parkway between Moss Creek
Drive and Indigo Run Drive during the AM peak hour will increase from approximately 19.3 minutes to
26.3 minutes, an increase of 7 minutes (36%) when compared to existing conditions. During the PM
peak hour along Hilton Parkway between Moss Creek Drive and Indigo Run Drive, it is expected that the
travel time in the westbound direction will increase from 20.9 minutes to 25.7 minutes, an increase of
approximately 5 minutes (23%) when compared to existing conditions
It is expected that the travel time in the southbound direction along Hilton Parkway at Moss Creek to
Cross Island Parkway at Sea Pines Circle during the AM peak hour will increase from approximately 22.6
minutes to 30.1 minutes, an increase of 7.5 minutes (46%) when compared to existing conditions.
During the PM peak hour along Hilton Parkway at Moss Creek to Cross Island Parkway at Sea Pines
Circle, it is expected that the travel time in the northbound direction will increase from 25.3 minutes to
41.1 minutes, an increase of approximately 16 minutes (62%) when compared to existing conditions
Multiple locations have negative percent differences for traffic volume results where the 2045 No-Build
simulated volumes are less than the 2023 Existing simulated volumes. This is due to over-saturation of
the study area in the model, and results in vehicles not being able to enter the simulation network to
process through each intersection. Therefore, it is evident that the study area is expected to experience
significant congestion through the year 2045.
Page 59 of 234
P A G E | 12
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 6. 2045 No-Build VISSIM Calibration Travel Time Results
Corridor
Existing Simulated
Travel Time (secs)
[min]
2045 No-Build
Simulated Travel Time
(secs) [min]
% Difference
AM PM AM PM AM PM
William Hilton Pkwy
between Moss Creek and
Indigo Run
EB 1157
[19.3 min]
619
[10.3 min]
1579
[26.3 min]
642
[10.7 min] 36.47% 3.72%
WB 572
[9.5 min]
1252
[20.9 min]
584
[9.7 min]
1544
[25.7 min] 2.10% 23.32%
William Hilton Pkwy from
Moss Creek to Sea Pine
Circle via Cross Island Pkwy
SB 1356
[22.6 min]
857
[14.3 min]
1984
[30.1 min]
873
[14.6 min] 46.31% 1.87%
NB 826
[13.8 min]
1520
[25.3 min]
823
[13.7 min]
2465
[41.1 min] -0.36% 62.17%
Table 7. 2045 No-Build VISSIM Calibration Traffic Volumes Results
Location
Existing
Simulated
Volume
Results
(vehicles)
2045 No-Build
Simulated
Volume
Results
(vehicles)
% Difference
AM PM AM PM AM PM
William Hilton Pkwy west of Squire Pope EB 2970 2240 2783 2524 -6.30% 12.68%
William Hilton Pkwy west of Squire Pope WB 1650 2898 1843 2754 11.70% -4.97%
William Hilton Pkwy east of Spanish Wells EB 2929 1955 2748 2198 -6.18% 12.43%
William Hilton Pkwy east of Spanish Wells WB 1423 2614 1570 2413 10.33% -7.69%
Cross Island Pkwy north of Marshland Rd NB 964 1371 1065 919 10.48% -32.97%
Cross Island Pkwy north of Marshland Rd SB 1486 1167 1440 1299 -3.10% 11.31%
Table 8 summarizes overall network performance for the 2045 No-Build scenario as compared to the
Existing conditions through the entire study area. During the PM peak hour, vehicles stops will increase
throughout the study area. Vehicles will be required to stop on average 10 to 15 times. Additionally, the
average vehicle speeds during the PM peak hour will degrade to an average of 16 mph. These metrics
are indicative of stop and go conditions and peak hour congestion. This is below the already congested
existing average off-peak speed for the corridor which is 25 mph and 22 mph for AM and PM peak
hours, respectively.
Page 60 of 234
P A G E | 13
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Due to congestion during the 2045 No-Build condition, approximately 10% of total network vehicles
were unable to enter the model network, and therefore are not captured in the network performance
results shown in Table 8.
Table 8. Network Performance – 2045 No-Build Conditions
Scenario
Average Number
of Stops per
Vehicle
Average Speed
(mph)
Total Vehicles
(vph)
Existing AM 6.5 25 10,497
Existing PM 9.9 22 12,393
2045 No-Build AM 9.9 21 11,143
2045 No-Build PM 15.4 16 12,393
2045 ALTERNAT IVES ANALYSIS
In addition to the simulation modeling of the study area, Lochmueller evaluated several strategies in
order to determine the viability of maintaining four lanes along William Hilton Parkway between
Windmill Harbour and Squire Pope Road. The strategies included:
• Implementation of a second bridge
• Modifications to the existing mass transit system
• Implementation of a new ferry system
• Implementation of a facility usage fee
Ultimately, it was determined that it would be highly unlikely that modifications to the existing transit
system, the implementation of a new ferry system, or the implementation of a facility usage fee would
reduce traffic volumes enough to maintain the existing four-lane section. Furthermore, it was
determined that a six-lane section of William Hilton Parkway onto Hilton Head Island would be needed
independently of a second bridge. Additional preliminary evaluations pertaining to the financial
feasibility of structurally rehabilitating and/or seismically retrofitting the existing Mackay Creek and Skull
Creek bridges in lieu of building a new six-lane structure were completed. A cursory, high-level
evaluation of a potential southern bypass was also completed. Additional information regarding the
above stated topics are provided in Appendix H.
As evidenced by the Existing and No-Build conditions, some of the existing traditional signalized
intersections will no longer be able to process the volume of vehicles within the William Hilton Parkway
corridor study area by the year 2045. Therefore, innovative concepts to improve the capacity of the
corridor were considered. Both at-grade and grade separated innovative intersections were evaluated to
improve safety, reduce delay, and increase efficiency.
Page 61 of 234
P A G E | 14
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
CORRIDOR STUDY GOALS
The following goals for improving the William Hilton Parkway corridor were established by The Town of
Hilton Head Island to guide the development of alternatives and form the basis of the alternatives
analysis:
• Fix the transportation issues in the corridor in a way that improves the safety and quality of life
for all residents, workers, and visitors to Hilton Head Island
a) Address transportation needs for natural disasters and resiliency of island access
b) Consider future transportation alternatives
• Improve the safety and quality of life for the residents of the neighborhoods and businesses
directly impacted by the US 278 corridor
a) Stoney Community
b) Neighborhoods on Jenkins and Hog Islands (including but not limited to Windmill Harbor)
• Have a gateway to and from Hilton Head Island that the region will be proud of:
a) Aesthetically pleasing and reflecting the Hilton Head Island/Low County values
b) Safe and functional pathways for pedestrians and cyclists
c) Minimizes environmental impacts and enhances the national asset of Pinckney Island
ALTERNATIVES CONSIDERED
With the guiding principles in mind, the following four corridor alternatives were recommended for
further study:
• Alternative 1: SCDOT Modified Recommended Preferred
• Alternative 2: Bowties at Squire Pope and Spanish Wells
• Alternative 3: Echelon / Center Turn Overpass
➢ Grade-Separated Intersection at either Squire Pope or Spanish Wells, but not both
• Alternative 4: Elevated Bypass
As agreed upon with the Town of Hilton Head, the alternative analysis was completed for the Modified
Original Project Study Area shown in Figure 2.
ALTERNATIVE 1: SCDOT MODIFIED RECOMMENDED PREFERRED
Alternative 1 considers the SCDOT Modified Recommended Preferred alternative with adaptive signals
in place and improvements at Gum Tree Road. The improvements at Gum Tree Road include keeping the
intersection at-grade, completely reconfiguring the intersection to improve its efficiency, and providing
dual left-turn lanes for the westbound, northbound, and southbound approaches. Figure 3 shows the
improvements recommended as part of Alternative 1, as provided by SCDOT. It should be noted that the
improvements at Gum Tree Road are not reflected in Figure 3, which was provided by SCDOT.
Page 62 of 234
P A G E | 15
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Figure 3. Alternative 1: SCDOT Modified Recommended Preferred
Page 63 of 234
P A G E | 16
ALTERNATIVE 2: BOWTIES AT SQUIRE POPE AND SPANISH WELLS
Alternative 2 considers bowties at Squire Pope Road and Spanish Wells Road with adaptive signals in
place and improvements at Gum Tree Road. The improvements at Gum Tree Road are the same as what
was included in Alternative 1, which keeps the intersections at-grade, reconfigures the intersection to
improve its efficiency, and provides dual left-turn lanes for the westbound, northbound, and
southbound approaches.
A bowtie intersection removes left-turns from the intersection and requires vehicles to navigate through
roundabouts along the side-street to return to the signal and continue in the intended direction of
travel. Figure 4 shows an example of a bowtie intersection. Note that this is only an example and not a
schematic drawing of William Hilton Parkway.
Figure 4. Example Bowtie Intersection (Provided by Virginia DOT)
Page 64 of 234
P A G E | 17
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Bowtie intersections provide several benefits. They improve safety as fewer conflicting vehicle and
pedestrian movements are allowed. Bowtie intersections have 12 fewer conflict points when compared
to traditional intersections, which have 32 conflict points. Bowtie intersections also encourage lower
vehicle speeds through the roundabouts. The size of main intersections can be reduced as left-turn lanes
are removed. Lastly, bowtie intersections increase the efficiency of the signalized intersections as more
of the signal time can go to the main thru movements, improving traffic operations.
However, bowtie intersections require a change in decision making for drivers as all left-turn
movements would be required to navigate the adjacent roundabouts along Squire Pope Road and
Spanish Wells Road. Bowtie intersections also may increase the amount of travel time for left-turning
vehicles and may require additional ROW for the roundabouts.
ALTERNATIVE 3: ECHELON / CENTER TURN OVERPASS
Alternative 3 considers either an echelon or a center turn overpass at either Squire Pope Road or
Spanish Wells Road. Echelons or center turn overpasses at both Squire Pope Road and Spanish Wells
Road were not considered because there is not enough distance between the two intersections for both
to be independently grade-separated.
Alternative 3 includes the adaptive signals in place as well as the previously detailed improvements at
Gum Tree Road. The improvements at Gum Tree Road are the same as what was included in Alternative
1, which keeps the intersections at-grade, reconfigures the intersection to improve its efficiency, and
provides dual left-turn lanes for the westbound, northbound, and southbound approaches.
An echelon is a grade-separated intersection where one approach on both roadways is elevated. For
example, the northbound and eastbound approaches would be elevated and the southbound and
westbound approaches would remain at-grade to create two intersections. Both intersections would be
signalized and all pedestrian and bicycle movements would remain at-grade. Figure 5 shows an example
of an echelon. Note that this is only an example and not a schematic drawing of William Hilton Parkway.
An echelon improves safety as fewer conflicting vehicle and pedestrian movements are allowed. Echelon
intersections have 10 fewer conflict points when compared to traditional intersections (32 conflict
points). They do not require a change in decision making for drivers as all movements would remain at
Squire Pope Road and Spanish Wells Road. Echelons increase the efficiency of the signalized
intersections as more of the signal time can go to the main thru movements, improving traffic
operations. While each approach would likely need the same lane configurations as shown in Alternative
1, only two approaches would conflict.
However, echelons do require grade separation of intersections and large intersections would likely
remain as all movements (left-turn, thru, and right-turn) are still allowed.
A center turn overpass is also a grade-separated intersection which raises only the left-turn movements
from the main intersection using ramps to create two intersections. Both intersections would be
signalized and all pedestrian and bicycle movements would remain at-grade. Figure 6 shows an example
of a center turn overpass. Note that this is only an example and not a schematic drawing of William
Hilton Parkway.
Page 65 of 234
P A G E | 18
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
A center turn overpass improves safety as fewer conflicting vehicle and pedestrian movements are
allowed. Center turn overpass intersections have 8 fewer conflict points when compared to traditional
intersections (32 conflict points). They increase the efficiency of the signalized intersections as more of
the signal time can go to the main thru movements, improving traffic operations.
However, similar to echelons, center turn overpasses require grade separation and large intersections
would likely remain as all movements (left-turn, thru, and right-turn) are still allowed.
Figure 5. Example Echelon (Provided by Virginia DOT)
Figure 6. Example Center Turn Overpass (Provided by Virginia DOT)
Page 66 of 234
P A G E | 19
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
ALTERNATIVE 4: ELEVATED BYPASS
Alternative 4 considers an elevated bypass which would begin west of Squire Pope Road and end east of
Gum Tree Road. The elevated bypass would take the four internal lanes, two in each direction, and
elevate them over the study intersections. This would allow free-flow movement for the eastbound and
westbound thru traffic from just east of the Jenkins Island causeway to just west of Wilborn Road. One
lane in each direction along William Hilton Parkway would remain at grade along with a separate
eastbound right-turn lane at Squire Pope Road and left-turn lanes at Squire Pope Road and Spanish
Wells Road. This allows for full access to be maintained at Squire Pope Road and Spanish Wells Rd. Full
access could also be provided at Old Wild Horse Road, which is currently a right-in/right-out intersection
today.
The elevated bypass would directly connect to the Cross Island Parkway. In the eastbound direction, the
two eastbound lanes would expand to provide one lane to the Cross Island Pkwy, one lane to William
Hilton Parkway at-grade for access to Gum Tree Road, and two lanes will continue along the elevated
bypass and connect to the at-grade section just east of Gum Tree Road, allowing thru vehicles to also
bypass Gum Tree Road. In the westbound direction, two lanes would be provided along William Hilton
Parkway just east of Gum Tree Road. These lanes would be reduced to one lane prior to the merge with
the westbound Cross Island Parkway ramp. The westbound Cross Island Parkway ramp and the single
elevated westbound bypass ramp would then merge into a two-lane elevated section.
Alternative 4 also assumes the adaptive signal system would remain in operation. However, the
improvements needed at Gum Tree Road in Alternatives 1, 2, and 3 would no longer be needed. In fact,
the Gum Tree Road intersection would be able to be reduced in size, as most of the eastbound and
westbound thru traffic would remain on the bypass rather than navigating thru the at-grade
intersection. Similarly, the at-grade intersections at Squire Pope Road and Spanish Wells Road would
also be able to be reduced in size. An elevated bypass would improve safety, as fewer thru vehicles
would remain at grade, thereby reducing the conflicts between vehicles and pedestrians. In addition,
the efficiency of the at-grade signalized intersections would be increased despite the reduction in the
size of the intersection. Lastly, Alternative 4 provides the most capacity for traffic growth along the
corridor.
However, this alternative would be the most expensive and would result in the largest construction
impact. Alternative 4 also requires grade separation and a change in decision making, as drivers looking
to continue traveling eastbound or westbound would need to enter the bypass, rather than go thru the
local intersections of Squire Pope Road, Old Wildhorse Road, and Spanish Wells Road as they do today.
Full access would still be provided at-grade. Figure 7 through Figure 10 provide an example schematic of
the elevated bypass.
Page 67 of 234
P A G E | 20
Figure 7. Example of Elevated Bypass - 01
Figure 8. Example of Elevated Bypass - 02
Spanish
Wells Rd
Page 68 of 234
P A G E | 21
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Figure 9. Example of Elevated Bypass - 03
Figure 10. Example of Elevated Bypass - 04
Elevated Bypass
Spanish Wells Rd
Page 69 of 234
P A G E | 22
2045 ALTERNATIVE 1: SCDOT MODIFIED RECOMMENDED PREFERRED
2045 ALTERNATIVE 1 TRAFFIC VOLUMES
The traffic volumes used for the 2045 Alternative 1 analysis were largely similar to the 2045 No-Build
traffic volumes. However, some intersections were combined in this alternative, requiring traffic
diversions. The 2045 Alternative 1 traffic volumes are provided in Appendix I.
2045 ALTERNATIVE 1 TRAFFIC OPERATIONAL ANALYSIS
As agreed upon with the Town of Hilton Head, a preliminary traffic analysis was completed using
Synchro 11. The 2045 Alternative 1 operating conditions were evaluated using the same methodology
applied to the 2023 Existing and 2045 No-Build conditions. The operating conditions for the 2045
Alternative 1 scenario are shown in Appendix I.
Overall the study intersections are expected to operate acceptably under Alternative 1. Each signalized
intersection is expected to operate with a LOS D or better overall. However, side-street and unsignalized
approaches may still experience long delays. This is to be expected given the heavy volumes
experienced along the mainline of William Hilton Parkway and the inability of side-street traffic to find
gaps in the mainline traffic to complete their movement.
In addition to the Synchro operating conditions, preliminary travel time calculations were performed in
Synchro along the William Hilton Parkway corridor between Moss Creek Drive and Indigo Run Drive.
Synchro was used for the purposes of evaluating alternatives at a high level, as its results provide a
reasonable comparison useful for preferred alternative selection. Final travel time results for the chosen
preferred alternative were conducted in VISSIM.
Table 9 shows the changes in travel time for the 2045 Alternative 1 scenario when compared to the
2045 No-Build scenario travel time results gathered from Synchro. As shown, Alternative 1 is expected
to improve the travel time along eastbound William Hilton Parkway by approximately 16% during the
AM peak period and westbound William Hilton Parkway by approximately 34% during the PM peak
period.
It should be noted that westbound William Hilton Parkway during the AM peak period and eastbound
William Hilton Parkway during the PM peak period are not expected to experience significant congestion
in the 2045 No-Build scenario, as traffic patterns in the study area largely follow commuter travel
patterns. Therefore, the increase in travel time shown is not expected to significantly impact the
operating conditions of the study area.
Page 70 of 234
P A G E | 23
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 9. Travel Time Comparison for Alternative 1
Scenario
Difference in Travel Time (seconds)
when Compared to 2045 No-Build % Difference
AM PM AM PM
2045 Alternative 1: SCDOT Modified
Recommended Preferred
EB -109 [-1.8 min] +18 [<1 min] -16.1% 2.7%
WB +43 [<1 min] -276 [-4.6 min] 6.3% -34.2%
2045 ALTERNATIVE 1 RIGHT -OF -WAY IMPACTS
The proposed modifications to the SCDOT Preferred Alternative in this alternative involve reconfiguring
the Gum Tree Road intersection to provide dual left-turn lanes for the westbound, northbound, and
southbound approaches. These improvements will require a strip of additional ROW of approximately
0.2 acre on Town owned land, in the northeast quadrant to accommodate the additional southbound
left turn lane. The lane additions on the westbound and northbound approaches can be accommodated
within existing ROW. It should be noted that the ROW estimates refer to permanent ROW needed for
the completed improvements only, and do not consider temporary ROW needed for construction or
staging.
2045 ALTERNATIVE 1 ENVIRONMENTAL ANALYSIS
As noted above, Alternative 1 would require 0.2 acre of additional ROW. The additional ROW impacts
are located within the Squire Pope neighborhood. The additional ROW to be acquired is owned by the
Town of Hilton Head. The SCDOT Environmental Assessment (EA) determined that this area is an
environmental justice community. One hazardous material site, Shell Food Mart Station 101 (165
William Hilton Pkwy), is located near the corridor. No impacts to the site are anticipated as a result of
Alternative 1. The SCDOT recommended preferred alternative was determined to have a “may affect-
not likely to adversely affect” finding for threatened and endangered species. Alternative 1 is not
anticipated to alter this finding. Coordination with the USFWS and the NOAA National Marine Fisheries
Service (NMFS) will need to occur to affirm this finding. Alternative 1 would not result in additional
impacts to National Wetland Inventory (NWI) wetlands, streams, floodplains, or essential fish habitat
types. No additional relocations would occur as a result of Alternative 1. No additional impacts to
cultural resources or Section 4(f) properties would occur as a result of Alternative 1.
Please refer to the Technical Environmental Overview in Appendix J for additional details.
2045 ALTERNATIVE 2: BOWTIES AT SQUIRE POPE AND SPANISH WELLS
2045 ALTERNATIVE 2 TRAFFIC VOLUMES
The traffic volumes used for the 2045 Alternative 2 analysis were largely similar to the 2045 No-Build
traffic volumes. However, given that the left-turns along William Hilton Parkway were removed at Squire
Pope Road and Spanish Wells Road, some traffic diversions were necessary. The 2045 Alternative 2
traffic volumes are provided in Appendix K.
Page 71 of 234
P A G E | 24
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
It should be noted that Lochmueller agrees with the improvements proposed along William Hilton
Parkway between Moss Creek Drive and Crosstree Drive in Alternative 1. These improvements include
the following:
• Widen William Hilton Parkway from four lanes to six lanes from Salt Marsh Drive through
Spanish Wells Drive
• Reconfigure the intersection of William Hilton Parkway and Wildlife Refuge Driveway to
eliminate left-turns and provide right-in/right-out access only
• Consolidate Jenkins Island access to one signalized location at Crosstree Drive
Therefore, those improvements were included in Alternative 2. As such, the traffic volumes at those
intersections would be the same between Alternative 2 and Alternative 1.
2045 ALTERNATIVE 2 TRAFFIC OPERATIONAL ANALYSIS
As agreed upon with the Town of Hilton Head, the preliminary traffic analysis was completed using
Synchro 11. The 2045 Alternative 2 operating conditions were evaluated using the same methodology
applied to the 2023 Existing and 2045 No-Build conditions. The operating conditions for the 2045
Alternative 2 scenario are shown in Appendix K.
The bowties at Squire Pope and Spanish Wells are expected to improve operations throughout the study
area. Overall, the study intersections are expected to operate acceptably under Alternative 2. Each
signalized intersection is expected to operate with a LOS D or better overall. However, side-street and
unsignalized approaches may still experience long delays. Similar to Alternative 1, this is to be expected
given the heavy volumes experienced along the mainline of William Hilton Parkway and the inability of
side-street traffic to find gaps in the mainline traffic to complete their movement.
In addition to the Synchro operating conditions, preliminary travel time calculations were performed in
Synchro along the William Hilton Parkway corridor between Moss Creek Drive and Indigo Run Drive.
Synchro was used for the purposes of evaluating alternatives at a high level, as its results provide a
reasonable comparison useful for preferred alternative selection. Final travel time results for the chosen
preferred alternative were conducted in VISSIM.
Table 10 shows the changes in travel time for the 2045 Alternative 2 scenario when compared to the
2045 No-Build scenario travel time results gathered from Synchro. As shown, Alternative 2 is expected
to improve the travel time along eastbound William Hilton Parkway by approximately 15% during the
AM peak period and westbound William Hilton Parkway by approximately 36% during the PM peak
period.
Page 72 of 234
P A G E | 25
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 10. Travel Time Comparison for Alternative 2
Scenario
Difference in Travel Time (seconds)
when Compared to 2045 No-Build % Difference
AM PM AM PM
2045 Alternative 2: Bowties at
Squire Pope and Spanish Wells
EB -104 [-1.7 min] -39 [<1 min] -15.3% -6.6%
WB +9 [<1 min] -290 [-4.8 min] 1.4% -36.4%
As previously noted, bowtie intersections may increase the total travel time for left-turning vehicles as
they must alter their course to navigate through a roundabout and return to the main intersection to
complete their movement. Therefore, the expected change in travel time was calculated in Synchro to
better determine the additional time for the re-routed left-turn movements. The changes in travel time
are shown in Table 11. As shown, it could take an additional two minutes for a vehicle making a
northbound left-turn at Squire Pope Road to navigate through the bowtie intersection. However, several
left-turning movements, such as the eastbound left-turn at Spanish Wells Rd, are expected to
experience a decrease in travel time as compared to the 2045 No-Build scenario, due to the long delay
those movements are expected to face absent any changes to the intersection.
Table 11. Expected Change in Travel Time for Left-Turning Vehicles at Bowtie Intersections
Intersection
Difference in Travel Time (seconds)
for Left-Turning Vehicles
AM PM
Squire Pope Road
EB Left-Turn +63 [1.1 min] +42 [<1 min]
WB Left-turn +82 [1.4 min] +81 [1.4 min]
NB Left-Turn +101 [1.7 min] +120 [2 min]
SB Left-Turn +44 [<1 min] +4 [<1 min]
Spanish Wells Road
EB Left-Turn -10 [<1 min] -26 [<1 min]
WB Left-turn -13 [<1 min] -7 [<1 min]
NB Left-Turn +89 [1.5 min] -42 [<1 min]
SB Left-Turn +43 [<1 min] +61 [1 min]
2045 ALTERNATIVE 2 RIGHT -OF -WAY IMPACTS
The proposed Bowtie configurations of Alternative 2 will require the 0.2 acre of additional ROW at Gum
Tree Road, as well as additional ROW along the crossroads to accommodate the construction of the
roundabouts. It should be noted that the ROW estimates refer to permanent ROW needed for the
completed improvements only, and do not consider temporary ROW needed for construction or staging.
At the Squire Pope Road intersection, the north roundabout would be located along Squire Pope Road at
Old Stony Lane, requiring approximately 0.2 acres of additional ROW from privately owned land. The
Page 73 of 234
P A G E | 26
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
south roundabout would be located at the end of Chamberlin Road and would require approximately
0.4 acre of additional ROW from Town owned land.
At the Spanish Wells Road intersection, the north roundabout would be located along Wild Horse Road
at Old Wild Horse Road, requiring approximately 0.2 acre of additional ROW from Town owned land.
The south roundabout would be located south of Humane Way and would require approximately 0.1
acre of additional ROW from Town owned land.
This alternative could potentially reduce the ROW required for the widening of William Hilton Parkway
by 0.5 acre or more due to the elimination of the left turn lanes at the intersections.
2045 ALTERNATIVE 2 ENVIRONMENTAL ANALYSIS
As noted above, Alternative 2 would require 1.10 acres of additional ROW. The Town of Hilton Head
owns 0.9 acre of the ROW that would need to be acquired. The additional ROW impacts are located
within the Stoney and Squire Pope neighborhoods. The SCDOT EA determined that the Stoney
neighborhood is an environmental justice community. The Squire Pope neighborhood was outside of the
SCDOT EA investigation area, but is also a Gullah Geechee community. The Gullah Geechee people are
the only African-American population in the United States that have maintained a separate language
and a distinct culture. Therefore, the Squire Pope neighborhood is likely an environmental justice
community. The SCDOT recommended alternative was determined to have a “may affect- not likely to
adversely affect” finding for threatened and endangered species. Alternative 2 is not anticipated to alter
this finding. Coordination with the U.S. Fish and Wildlife Service (USFWS) and the National Oceanic and
Atmospheric Administration-National Marine Fisheries Service (NOAA-NMFS) would need to occur to
affirm this finding. Alternative 2 would require additional impacts to the Stoney Traditional Cultural
Property (TCP). The SCDOT identified the Stoney community as a TCP and as a resource eligible for
inclusion in the National Register of Historic Places (NRHP). As a NRHP-eligible resource, it is also
considered a Section 4(f) property. Alternative 2 would not result in additional impacts to hazardous
materials sites, NWI wetlands, streams, floodplains, or essential fish habitat types. No additional
relocations would occur as a result of Alternative 2.
Please refer to the Technical Environmental Overview in Appendix J for additional details.
2045 ALTERNATIVE 3: ECHELON / CENTER TURN OVERPASS
2045 ALTERNATIVE 3 TRAFFIC VOLUMES
The traffic volumes used for the 2045 Alternative 3 analysis were largely similar to the 2045 No-Build
traffic volumes. The traffic volumes for the intersections impacted by Alternative 3 are provided in
Appendix L.
It should be noted that Lochmueller agrees with the improvements proposed along William Hilton
Parkway between Moss Creek Drive and Crosstree Drive in Alternative 1, as detailed below:
Page 74 of 234
P A G E | 27
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
• Widen William Hilton Parkway from four lanes to six lanes from Salt Marsh Drive through
Spanish Wells Drive
• Reconfigure the intersection of William Hilton Parkway and Wildlife Refuge Driveway to
eliminate left-turns and provide right-in/right-out access only
• Consolidate Jenkins Island access to one signalized location at Crosstree Drive
Therefore, those improvements were included in Alternative 3. As such, the traffic volumes at those
intersections would be the same between Alternative 3 and Alternative 1.
2045 ALTERNATIVE 3 TRAFFIC OPERATIONAL ANALYSIS
As agreed upon with the Town of Hilton Head, the preliminary traffic analysis was completed using
Synchro 11. The 2045 Alternative 3 operating conditions were evaluated using the same methodology
applied to the 2023 Existing and 2045 No-Build conditions. The operating conditions for the 2045
Alternative 3 scenario are shown in Appendix L.
Overall the study intersections are expected to operate acceptably under Alternative 3. Each signalized
intersection is expected to operate with a LOS D or better overall for either configuration. Similar to the
previous scenarios, side-street and unsignalized approaches may still experience long delays. The long
queues and delays that are expected under the 2045 No-Build Scenario would be expected to be
improved overall.
It should be noted that while operating conditions overall would be expected to improve when
compared to the 2045 No-Build conditions, some movements would be expected to experience failing
levels of service. When considering an echelon at Squire Pope Road, the southbound approach at Squire
Pope Road is expected to fail. This is caused by a reduction in green time for the heavy southbound
right-turns. Additionally, when considering a center turn overpass at Squire Pope Road, the northbound
approach at Spanish Wells Road is expected to experience failing operating conditions. This is due to the
limited amount of green time allowed for this movement under this scenario. However, overall each
option in Alternative 3 is an improvement when compared to the 2045 No-Build scenario.
In addition to the Synchro operating conditions, preliminary travel time calculations were performed in
Synchro along the William Hilton Parkway corridor between Moss Creek Drive and Indigo Run Drive.
Synchro was used for the purposes of evaluating alternatives at a high level, as its results provide a
reasonable comparison useful for preferred alternative selection. Final travel time results for the chosen
preferred alternative were conducted in VISSIM.
Table 12 shows the changes in travel time for the 2045 Alternative 3 scenario when compared to the
2045 No-Build scenario travel time results gathered from Synchro. As shown, between the four options
provided in Alternative 3, the travel time calculations indicate that the travel time along eastbound
William Hilton Parkway would improve between approximately 18-32% during the AM peak period and
westbound William Hilton Parkway would improve between approximately 41-60% during the PM peak
period.
Page 75 of 234
P A G E | 28
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 12. Travel Time Comparison for Alternative 3
Scenario
Difference in Travel Time (seconds)
when Compared to 2045 No-Build % Difference
AM PM AM PM
2045 Alternative 3: Echelon at
Squire Pope
EB -191 [-3.2 min] -68 [-1.1 min] -32.1% -12.1%
WB -79 -[1.3 min] -407 [-6.8 min] -13.9% -60.0%
2045 Alternative 3: Echelon at
Spanish Wells
EB -140 [-2.3 min] -11 [<1 min] -21.6% -1.8%
WB -15 [<1 min] -331 [-5.5 min] -2.3% -44.0%
2045 Alternative 3: Center Turn
Overpass at Squire Pope
EB -122 [-2 min] +23 [<1 min] -18.4% 3.5%
WB -21 [<1 min] -319 [-5.3 min] -3.3% -41.6%
2045 Alternative 3: Center Turn
Overpass at Spanish Wells
EB -134 [-2.2 min] -17 [<1 min] -20.6% -2.9%
WB -16 [<1 min] -339 [-5.7 min] -2.5% -45.4%
2045 ALTERNATIVE 3 RIGHT -OF -WAY IMPACTS
The proposed Echelon or Center Turn Overpass configurations of Alternative 3 would still require the 0.2
acres of additional ROW at Gum Tree Road, as well as additional ROW along William Hilton Parkway for
turn lanes and additional ROW along the crossroads to accommodate the construction of the turn
arounds and/or roundabouts to maintain full access to parcels near the intersections. It should be noted
that the ROW estimates refer to permanent ROW needed for the completed improvements only, and do
not consider temporary ROW needed for construction or staging.
At the Squire Pope Road intersection, the north roundabout would be located along Squire Pope Road at
Old Stony Lane, requiring approximately 0.2 acres of additional ROW from privately owned land. The
south roundabout would be located at the end of Chamberlin Road and would require approximately
0.4 acres of additional ROW from Town owned land. Widening of Chamberlin Road would require
approximately 0.05 acres of additional ROW from private land and 0.05 acres of ROW from Town owned
land. Widening along the north side of William Hilton Parkway will require approximately 0.1 acres of
additional ROW from Town owned land.
At the Spanish Wells Road intersection, the north roundabout would be located along Wild Horse Road
at Old Wild Horse Road, requiring approximately 0.2 acres of additional ROW from Town owned land.
The south turn around would require approximately 0.35 acres of additional ROW from private land.
Widening along the south side of William Hilton Parkway would require approximately 0.3 acres of
additional ROW from Town owned land and approximately 0.05 acres of additional ROW from private
land.
Page 76 of 234
P A G E | 29
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
2045 ALTERNATIVE 3 ENVIRONMENTAL ANALYSIS
The environmental impacts for Alternative 3 were evaluated for an echelon at the Squire Pope Road
intersection and an echelon at the Spanish Wells Road/Wild Horse Road intersection. A center turn
overpass would result in more impacts than an echelon at either intersection. Therefore, a center turn
overpass was dismissed from further consideration.
An echelon at the Squire Pope intersection would require the 1.0 acre of additional ROW. The Town of
Hilton Head owns 0.75 acre of the ROW that would need to be acquired. The additional ROW impacts
are located within the Stoney and Squire Pope neighborhoods. The SCDOT EA determined that the
Stoney neighborhood is an environmental justice community. The Squire Pope neighborhood is a Gullah
Geechee community and is likely an environmental justice community. The SCDOT recommended
preferred alternative was determined to have a “may affect- not likely to adversely affect” finding for
threatened and endangered species. An echelon at the Squire Pope intersection is not anticipated to
alter this finding. Coordination with the USFWS and the NOAA-NMFS would need to occur to affirm this
finding. An echelon at Squire Pope Road would result in additional impacts to the Stoney TCP, a cultural
resource and Section 4(f) property. The addition of a grade separated intersection at Squire Pope Road
also has the potential to create visual barriers within the Stoney TCP. It would not result in additional
impacts to hazardous materials sites, NWI wetlands, streams, floodplains, or essential fish habitat types.
No additional relocations would occur as a result of Alternative 3.
An echelon at the Spanish Wells Road/ Wild Horse Road intersection would require 1.1 acres of
additional ROW. The Town of Hilton Head owns 0.7 acre of the ROW that would need to be acquired.
The additional ROW impacts are located within the Stoney and Squire Pope neighborhoods. The SCDOT
EA determined that the Stoney neighborhood is an environmental justice community. The Squire Pope
neighborhood is a Gullah Geechee neighborhood and likely an environmental justice community. The
SCDOT recommended preferred alternative was determined to have a “may affect- not likely to
adversely affect” finding for threatened and endangered species. An echelon at the Spanish Wells Road
intersection is not anticipated to alter this finding. Coordination with the USFWS and the NOAA-NMFS
would need to occur to affirm this finding. An echelon at Spanish Wells Road would result in 0.29 acre of
additional impacts to floodplains. It would result in additional impacts to the Stoney TCP, a cultural
resource and Section 4(f) property. It would also result in 0.03 acre of additional impacts to the public
park at 152 William Hilton Pkwy, a Section 4(f) property. The addition of a grade separated intersection
at Spanish Wells Road / Wild Horse Road also has the potential to create visual barriers within the
Stoney TCP. An echelon at Spanish Wells Road would not result in additional impacts to hazardous
materials sites, NWI wetlands, streams, or essential fish habitat types. No relocations would occur as a
result of Alternative 3.
Please refer to the Technical Environmental Overview in Appendix J for additional details.
Page 77 of 234
P A G E | 30
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
2045 ALTERNATIVE 4: ELEVATED BYPASS
2045 ALTERNATIVE 4 TRAFFIC VOLUMES
The traffic volumes used for the 2045 Alternative 4 analysis were largely similar to the 2045 No-Build
traffic volumes. The traffic volumes for the intersections impacted by Alternative 4 are provided in
Appendix M.
It should be noted that Lochmueller agrees with the improvements proposed along William Hilton
Parkway between Moss Creek Drive and Crosstree Drive in Alternative 1, as detailed below:
• Widen William Hilton Parkway from four lanes to six lanes from Salt Marsh Drive through
Spanish Wells Drive
• Reconfigure the intersection of William Hilton Parkway and Wildlife Refuge Driveway to
eliminate left-turns and provide right-in/right-out access only
• Consolidate Jenkins Island access to one signalized location at Crosstree Drive
Therefore, those improvements were included in Alternative 4. As such, the traffic volumes at those
intersections would be the same between Alternative 4 and Alternative 1.
2045 ALTERNATIVE 4 TRAFFIC OPERATIONAL ANALYSIS
As agreed upon with the Town of Hilton Head, the preliminary traffic analysis was completed using
Synchro 11. The 2045 Alternative 4 operating conditions were evaluated using the same methodology
applied to the 2023 Existing and 2045 No-Build conditions. The operating conditions for the 2045
Alternative 4 scenario are shown in Appendix M.
As shown, the intersections at Squire Pope Road, Spanish Wells Road, and Gum Tree Road would be
expected to operate at an overall LOS C or better. Overall, the study intersections are expected to
operate acceptably under Alternative 4. The signalized intersections throughout the corridor are
expected to operate with a LOS C or better overall. Similar to the previous scenarios, side-street and
unsignalized approaches throughout the corridor may still experience long delays. It should be noted
that the results provided are for the at-grade intersections only, and the operating conditions for the
elevated bypass traffic are not provided in Synchro.
In addition to the Synchro operating conditions, preliminary travel time calculations were performed in
Synchro along the William Hilton Parkway corridor between Moss Creek Drive and Indigo Run Drive.
Synchro was used for the purposes of evaluating alternatives at a high level, as its results provide a
reasonable comparison useful for preferred alternative selection. Final travel time results for the chosen
preferred alternative were conducted in VISSIM.
Table 13 shows the changes in travel time for the 2045 Alternative 4 scenario when compared to the
2045 No-Build scenario travel time results gathered from Synchro. As shown, Alternative 4 is expected
to improve the travel time along the remaining at grade eastbound William Hilton Parkway by
approximately 19% during the AM peak period and at grade westbound William Hilton Parkway by
approximately 44% during the PM peak period. It should be noted that the travel times reflect
Page 78 of 234
P A G E | 31
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
operations of at-grade intersections only. VISSIM software will allow for modeling of the bypass itself
and will therefore yield greater reductions in travel times than those shown in the table.
Table 13. Travel Time Comparison for Alternative 4
Scenario
Difference in Travel Time (seconds)
when Compared to 2045 No-Build % Difference
AM PM AM PM
2045 Alternative 4: Elevated Bypass
EB -126 [-2.1 min] 27 [<1 min] -19.1% 4.1%
WB +4 [<1 min] -330 [-5.5 min] 0.5% -43.7%
2045 ALTERNATIVE 4 RIGHT -OF -WAY IMPACTS
Based upon available GIS and parcel map data made available to Lochmueller during the completion of
the corridor alternatives analysis process, it appears the proposed Elevated Bypass Alternative could be
contained within the proposed ROW footprint of the SCDOT Preferred alternative and, unlike the other
alternatives, would not require adding turn lanes to the Gum Tree Road intersection and the additional
strip of ROW required by those improvements, resulting in no additional ROW being required for this
alternative. It should be noted that the ROW estimates refer to permanent ROW needed for the
completed improvements only, and do not consider temporary ROW needed for construction or staging.
2045 ALTERNATIVE 4 ENVIRONMENTAL ANALYSIS
Alternative 4 would impact an additional 0.03 acre of National Wetland Inventory (NWI) wetlands and
an additional 0.03 acre of essential fish habitats. Approximately 65 linear feet of Jarvis Creek would be
impacted. Alternative 4 would require no additional ROW. The SCDOT recommended preferred
alternative was determined to have a “may affect- not likely to adversely affect” finding for threatened
and endangered species. Alternative 4 is not anticipated to alter this finding. Coordination with the
USFWS and the NOAA-NMFS would need to occur to affirm this finding.
The Honey Horn Plantation is a collection of historic farm buildings and landscape and would be
considered a Section 4(f) resource. It is also home to the Coastal Discovery Museum, which educates the
public on the region’s cultural and natural history. Alternative 4 intersects the current boundary of
Honey Horn plantation according to the South Carolina Department of Archives and History website.
This is unlikely to be considered a Section 4(f) use as the proposed improvements associated with this
alternative would occur entirely within existing transportation ROW. Therefore, there is likely no
conversion of the resource from a non-transportation use to a transportation one. The current boundary
of the site extends into the existing footprint of U.S. 278. However, this part of the site has likely been
disturbed by previous construction. Further investigation and coordination with the applicable agencies
would be needed to determine the exact cultural and Section 4(f) impacts to this site. No additional
relocations would be required. The addition of an elevated bypass lane on a combination of fill or
structure also has the potential to create visual barriers within the Stoney TCP. However, this alternative
would not result in additional encroachment on the Stoney TCP and, as such, is not quantified as a direct
Page 79 of 234
P A G E | 32
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
impact. No additional impacts to hazardous materials sites, neighborhoods, or environmental justice
communities are anticipated. No impacts to floodplains are anticipated. Please refer to the Technical
Environmental Overview in Appendix J for additional details.
ALTERNATIVES COMPARISON AND CONCLUSIONS
The goal of the alternatives analysis is to provide an objective, data-driven evaluation of the four
corridor alternatives, with respect to US 278/William Hilton Parkway between Moss Creek Drive and
Gum Tree Road. Therefore, various matrices were compiled with respect to traffic operations, bicycle
and pedestrian accommodations, ROW requirements, and environmental factors to inform an overall
scoring matrix. Each of the matrices includes scores for various categories. A score of 1 is the highest
ranking, whereas a score of 4 is the lowest ranking. The ranking for each category were tallied to reach a
total aggregate score per alternative.
As shown in Table 18, Alternative 1 ranked first with a total score of 20. Alternative 4 ranked second
with a total score of 21. Alternative 2 ranked third with a total score of 24, and Alternative 3 ranked last
with a total score of 28.
Page 80 of 234
P A G E | 33
The matrix for traffic operations is presented in Table 14.
Table 14. Traffic Operations Overview Matrix
Resource/Category
Alternative 1
(Mod. SCDOT Recommended
Preferred)
Alternative 2
(Bowties at Squire
Pope and Spanish
Wells)
Alternative 3
(Echelon / Center Turn
Overpass)
Alternative 4
(Elevated Bypass)
Travel Time along US
278 4 4 2 1
Overall Intersection
Operations 4 3 3 1
Side-Street
Operations
4
Movements with a LOS F at a
signalized intersection:
Squire Pope:
Northbound approach (PM)
2
No movements have
a LOS F at a signalized
intersection.
However, some
movements are
expected to have a
LOS E at signalized
intersections between
Squire Pope and Gum
Tree.
4
Movements with a LOS F at a
signalized intersection:
Echelon at Squire Pope:
Squire Pope:
Southbound approach (PM)
Center Turn Overpass at
Squire Pope:
Spanish Wells: Northbound
Approach (PM)
1
All movements are
expected to have a
LOS D or better at
signalized
intersections
between Squire
Pope and Gum
Tree.
TOTAL 12 9 9 3
RANK 4 3 3 1
Page 81 of 234
P A G E | 34
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
The matrix for bicycle and pedestrian impact is presented in Table 15.
Table 15. Bicycle and Pedestrian Overview Matrix
Resource/Category
Alternative 1
(Mod. SCDOT
Recommended
Preferred)
Alternative 2
(Bowties at Squire
Pope and Spanish
Wells)
Alternative 3
(Echelon / Center Turn
Overpass)
Alternative 4
(Elevated Bypass)
Pedestrian
Crossing Distance
Longest pedestrian
crossing distances.
Reduced pedestrian
crossing distances and
exposure to motor
vehicle traffic.
Reduced pedestrian
crossing distances and
exposure to motor
vehicle traffic.
Reduced pedestrian crossing
distances and exposure to motor
vehicle traffic.
Potential for
Refuge Islands
No refuge islands on
north-south crossings.
Potential for median
refuge island on east
and west crosswalk
legs at Squire Pope
Refuge islands between
directional traffic allow
pedestrians to more
comfortably navigate the
complex intersection.
Refuge islands between directional
traffic allow pedestrians to more
comfortably navigate the complex
intersection; HOWEVER, multiple
refuge islands per leg and long end-
to-end crossing distances increase
intersection complexity and the
likelihood of pedestrians needing
two or more stages to complete a
north-south crossing.
Conflict Points
Multiple turning
movements and
potential conflict points
along each leg.
Fewer ped/vehicle
conflict points and
vehicle turning
movements.
Fewer ped/vehicle
conflict points and
vehicle turning
movements.
Fewer ped/vehicle conflict points
and vehicle turning movements.
Page 82 of 234
P A G E | 35
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
The matrix for ROW impact is presented in Table 16.
Table 16. Right-of-Way Overview Matrix
Resource/Category
Alternative 1
(Mod. SCDOT
Recommended
Preferred)
Alternative 2
(Bowties at Squire
Pope and Spanish
Wells)
Alternative 3
(Echelon / Center Turn
Overpass)
Alternative 4
(Elevated Bypass)
Estimated Additional Right-of-
Way Acres – Public
Estimated Additional Right-of-
Way Acres – Private
Approx. TOTAL Additional
Right-of-Way Acres
0.2 ac
0.0 ac
0.2 ac
0.9 ac
0.2 ac
1.1 ac
0.7 ac
0.4 ac
1.1 ac
0 ac
Right-of-Way Score 2 4 4 1
Estimated Preliminary Probable
Opinion of Cost $426 $430M $440M to $450M $545M to $575M
Cost Score 1 2 3 4
Estimated Construction
Duration 36 months 38 months 42 months 48 months
Construction Duration Score 1 2 3 4
TOTAL 4 8 10 9
RANK 1 2 4 3
Page 83 of 234
P A G E | 36
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
The matrix for environmental impacts is presented in Table 17.
Table 17. Environmental Overview Matrix
Resource/Category
Alternative 1
(Mod. SCDOT
Recommended
Preferred)
Alternative 2
(Bowties at Squire
Pope and Spanish
Wells)
Alternative 3
(Echelon / Center Turn
Overpass)
Alternative 4
(Elevated Bypass)
NWI Wetlands 1 1 1 4
Streams 1 1 1 4
Floodplains 1 1 4 1
Essential Fish Habitat 1 1 1 4
Threatened & Endangered
Species 1 1 1 1
Hazardous Material Sites 1 1 1 1
Relocations 1 1 1 1
Right-of-Way 2 4 4 1
Neighborhoods 2 4 4 1
Environmental Justice 2 4 4 1
Cultural Resources 1 4 4 4
Section 4(f) Resources 1 3 4 1
Total 15 26 30 24
Rank 1 3 4 2
Page 84 of 234
P A G E | 37
Table 18. Overall Scoring Matrix
Resource/Category
Alternative 1
(Mod. SCDOT
Recommended
Preferred)
Alternative 2
(Bowties at Squire
Pope and Spanish
Wells)
Alternative 3
(Echelon / Center Turn
Overpass)
Alternative 4
(Elevated Bypass)
Traffic Operations (Throughput
and Traffic Simulations) 4 3 3 1
ROW Impact 2 4 4 1
Environmental Impact 1 3 4 2
Safety 4 3 3 1
Bike/Pedestrian Impact 4 3 1 2
Community and Social Impact 1 3 4 2
Aesthetic 2 1 3 4
Preliminary Probable Opinion
of Cost 1 2 3 4
Construction Duration 1 2 3 4
TOTAL 20 24 28 21
RANK 1 3 4 2
Page 85 of 234
P A G E | 38
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
TOWN SELECTED ALTERNATIVE
Based upon the preceding alternatives analysis, Lochmueller was directed by the Town of Hilton Head
Island to pursue Alternative 1: SCDOT Modified Recommended Preferred with modifications to provide
a single eastbound left-turn lane and a single southbound right-turn lane at the intersection of William
Hilton Parkway at Squire Pope Road through to the final phase of this analysis.
TOWN SELECTED ALTERNATIVE MULTIMODAL RECOMMENDATIONS
The roadway improvements recommended under Modified Alternative 1 were further evaluated with
respect to improving the multimodal experience and safety within the study area. As previously stated,
Alternative 1 considers the SCDOT Modified Recommended Preferred alternative with adaptive signals
in place and improvements at Gum Tree Road. However, unlike the original SCDOT Modified
Recommended Preferred Alternative, a single eastbound left-turn lane and a single southbound right-
turn lane at the intersection of William Hilton Parkway at Squire Pope Road will be provided. The SCDOT
Modified Recommended Preferred Alternative will also provide a separated shared use path (SUP) for
bicycles. Due to the heavy traffic volumes, on street facilities are not being considered. Therefore, the
multimodal recommendations mainly focus on how to accommodate pedestrians. The following
improvements along William Hilton Parkway between Moss Creek Drive and Gum Tree Road are
recommended as part of the Modified Alternative 1:
• William Hilton Parkway & Pinckney Island Refuge
o If pedestrians are going to be encouraged to cross the south leg of the intersection
immediately adjacent to William Hilton Parkway, a high visibility marked crosswalk
should be incorporated, and if possible, the proposed channelized island should be
expanded/extended to provide a refuge area. Alternatively, the pedestrians could be
directed to cross the south leg at a location further away from William Hilton Parkway,
with appropriate signage and pavement markings to accommodate.
• William Hilton Parkway & Crosstree Drive (Windmill Harbour)
o This signalized intersection should be incorporated into the adaptive signal system as
soon possible to ensure optimal traffic signal progression along William Hilton Parkway.
• William Hilton Parkway & Squire Pope Road
o Provide high visibility crosswalks.
o If continuous sidewalk facilities are not planned to be installed along the south side of
William Hilton Parkway west of Squire Pope Road, consider eliminating the William
Hilton Parkway pedestrian crossing on the west leg to instead encourage pedestrians to
cross William Hilton Parkway at the east leg only.
o Consider moving the north crosswalk slightly northward, so as to provide greater
distance between pedestrians within the crosswalk and the adjacent westbound travel
lanes along William Hilton Parkway.
o During final design efforts, seek to increase extents of raised center medians along
William Hilton Parkway to provide pedestrian refuge, if possible, given ROW and other
geometric factors that must be considered.
Page 86 of 234
P A G E | 39
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
o During final design efforts, seek to tighten curb radii to shorten pedestrian crossing
distances on all approaches.
• William Hilton Parkway & Spanish Wells Road
o Provide high visibility crosswalks.
o Consider moving the north crosswalk slightly northward, so as to provide greater
distance between pedestrians within the crosswalk and the adjacent westbound travel
lanes along William Hilton Parkway.
o During final design efforts, seek to increase extents of western raised center median
along William Hilton Parkway to provide pedestrian refuge for west leg crossing, if
possible, given ROW and other geometric factors that must be considered.
o During final design efforts, seek to tighten curb radii to shorten pedestrian crossing
distances across north and west leg of the intersection.
DOWNSTREAM IMPACTS OF TOWN SELECTED MODIFIED ALTERNATIVE 1
As a next step, Lochmueller evaluated the impacts Modified Alternative 1 would have on the entire
project study area (Figure 1) and determined what, if any, improvements should be made to
accommodate the 2045 forecasted traffic at the intersections downstream (i.e., east of Gum Tree Road
to Indigo Run Drive, and south of Cross Island Parkway to Sea Pines Circle).
MODIFIED ALTERNATIVE 1 TRAFFIC ANALYSIS
The travel time calculations and traffic volumes between the 2045 No-Build conditions and the 2045
Modified Alternative 1 conditions were evaluated using VISSIM. It should be noted that this analysis was
conducted assuming only the improvements under the Modified Alternative 1 were in place to better
understand how the entire study area would operate if no geometric roadway improvements were
implemented east of Gum Tree Road to Indigo Run Drive, or along Cross Island Parkway to Sea Pines
Circle.
As shown in Table 19, under the 2045 No-Build scenario, it is expected that it would take approximately
26.3 minutes to travel eastbound along Hilton Parkway between Moss Creek Drive and Indigo Run Drive
during the AM peak hour. It is expected that the travel time will be reduced to approximately 10.5
minutes (60%) under the Modified Alternative 1. Under the 2045 No-Build scenario, it is expected that it
would take approximately 25.7 minutes to travel westbound along Hilton Parkway between Moss Creek
Drive and Indigo Run Drive during the PM peak hour. It is expected that the travel time will be reduced
to approximately 10.3 minutes (60%) under the Modified Alternative 1.
Page 87 of 234
P A G E | 40
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 19. 2045 Modified Alternative 1 VISSIM Travel Time Results
Corridor
2045 No-Build
Simulated Travel Time
(secs) [min]
2045 Modified
Alternative 1 Without
Improvements to
Downstream
Intersections
Simulated Travel Time
(secs) [min]
% Difference
AM PM AM PM AM PM
William Hilton Pkwy
between Moss Creek and
Indigo Run
EB 1579
[26.3 min]
642
[10.7 min]
628
[10.5 min]
631
[10.5 min] -60.23% -1.71%
WB 584
[9.7 min]
1544
[25.7 min]
597
[10 min]
616
[10.3 min] 2.23% -60.10%
William Hilton Pkwy from
Moss Creek to Sea Pine
Circle via Cross Island
Pkwy
SB 1984
[30.1 min]
873
[14.6 min]
1387
[23.1 min]
874
[14.6 min] -30.09% 0.11%
NB 823
[13.7 min]
2465
[41.1 min]
848
[14.1 min]
904
[15.1 min] 3.04% -63.33%
In addition, with the improvements in place, the approximately 10% of total network vehicles that were
unable to enter the model network during the 2045 No-Build scenario are able to be accommodated
under this scenario.
Table 20 summarizes overall network performance for the 2045 Modified Alternative scenario assuming
no improvements to intersections east of Gum Tree Road or along Cross Island Parkway as compared to
the 2045 No-Build scenario. During the PM peak hour, vehicles stops will decrease when compared to
the 2045 No-Build scenario throughout the study area. Vehicles will be required to stop on average 6
times during both peak periods. Additionally, the average vehicle speeds during the PM peak hour will
improve to an average of 28 and 30 mph, during the AM and PM peak hours, respectively.
In addition, with the improvements in place, the approximately 10% of total network vehicles that were
unable to enter the model network during the 2045 No-Build scenario are able to be accommodated
under this scenario.
Page 88 of 234
P A G E | 41
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 20. Network Performance – 2045 Modified Alternative 1 Without Improvements to Downstream
Intersections
Peak Hour
Average Number
of Stops per
Vehicle
Average Speed
(mph)
Total Vehicles
(vph)
2045 No-Build AM 9.9 21 11,143
2045 No-Build PM 15.4 16 12,393
2045 Modified Alternative 1:
AM Peak Hour 6.3 28 11,355
2045 Modified Alternative 1:
PM Peak hour 6.7 29.8 13,531
The 2045 Modified Alternative 1 operating conditions at the study intersections were evaluated using
VISSIM and are provided in Appendix N. As shown, with the improvements proposed under the
Modified Alternative 1, the study intersections are largely expected to operate acceptably in the year
2045, with some exceptions. The eastbound and westbound thru movements along William Hilton
Parkway are expected to operate with an overall LOS D or better between Moss Creek Drive and Gum
Tree Road. While some of the side-street approaches at unsignalized intersections are still expected to
experience failing conditions, the operations overall are significantly improved from the 2045 No-Build
scenario as vehicles can better complete their turning movement due to the reduction in congestion
along the eastbound and westbound mainline.
The intersections east of Gum Tree Road are largely expected to operate favorably in 2045 with no
improvements in place. However, long eastbound queues extending from Pembroke Drive through Gum
Tree Road are expected during the AM peak hour. Similarly, the westbound queue at Jarvis Park
Road/Wilborn Road is expected to extend back to Pembroke Drive during the PM peak hour.
Furthermore, the mainline is expected to be over capacity in the year 2045. However, overall, the
intersections are expected to operate acceptably with an overall LOS D or better during both peak
periods. Even though the mainline functions over capacity in 2045 (which is evidenced by the resulting
queue lengths), the adaptive signal system is expected to perform well enough to still provide overall
LOS D or better during both peak periods.
As shown, the northbound approach at Jarvis Park Road/Wilborn Road is expected to have a failing LOS
during the PM peak hour. It should be noted that this approach has minimal traffic volumes and the
maximum queue expected is only approximately 200 ft. The eastbound left-turn movement at Indigo
Run Drive is also expected to fail during the PM peak hour. The maximum queue length is expected to
be approximately 335 ft, which would be contained within the existing turn lane.
Along Palmetto Bay Rd, the roundabout at Sea Pines is expected to fail during both AM and PM peak
hours. The failing conditions result in long queue lengths. The southbound queue is expected to extend
past the study intersection at Target Road and towards Point Comfort Road during the AM peak hour.
This results in failing movements for the westbound left-turns out of the unsignalized intersections
along Palmetto Bay Road as vehicles are unable to find a gap in the traffic to complete their turning
movement. During the PM peak hour, nearly every approach of Sea Pines Circle is expected to fail in
Page 89 of 234
P A G E | 42
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
2045 with no improvements in place as the roundabout is unable to accommodate the expected traffic
volumes.
Overall, with the improvements proposed under the Modified Alternative 1, the downstream study
intersections are largely expected to operate acceptably in the year 2045. However, the eastbound and
westbound approaches between Wilborn Road and Pembroke Drive are expected to experience long
queues and be over capacity in the year 2045, and the existing roundabout at Palmetto Bay Road and
Sea Pines Circle is expected to fail during both the AM and PM peak hours. As a result of the failing
roundabout, the southbound queue lengths are expected to extend beyond nearby intersections.
Therefore, it was necessary to evaluate potential improvements to the local intersections downstream
of Gum Tree Road and Cross Island Parkway to help mitigate the expected long queues and delays.
ADDITIONAL MITIGATION SOLUTIONS FOR LOCAL INTERSECTIONS
As previously stated, some of the local downstream intersections would be expected to experience long
queues and delays. As such, two options were developed to help mitigate the local intersections east of
Gum Tree Road to Indigo Run Drive, and south of Cross Island Parkway to Sea Pines Circle.
Option A minimizes the physical impacts along the corridor, with suggested improvements for only one
intersection along William Hilton Parkway. Physical improvements are also recommended at Sea Pines
Circle in order to accommodate the expected increase in traffic over time. Option A considers keeping
Sea Pines Circle as a roundabout intersection, but expanding the lanes to increase capacity.
Option B considers a more significant approach to help mitigate the expected queue lengths along
William Hilton Parkway between Gum Tree Road and Pembroke Drive. Option B also provides a separate
solution for Sea Pines Circle via signalizing the intersection.
The improvements recommended under the two options to help mitigate the local intersections east of
Gum Tree Road and along Cross Island Parkway are detailed below:
• Local Intersection Option A:
o William Hilton Parkway & Pembroke Drive
▪ Reconfigure the northbound approach to provide dual northbound left-turn lanes,
one thru lane, and one right-turn lane.
▪ In addition to the roadway widening, this will require relocation of the shared
use path on the east side, adjustments to signal equipment and additional ROW
on the south leg.
▪ Estimated preliminary probable opinion of cost, including ROW of $750,000 and
a construction duration estimated at 4 months.
o Palmetto Bay Road & William Hilton Parkway (Sea Pines Circle)
▪ Provide a two-lane roundabout.
▪ Each approach should have a right-turn bypass, with the exception of the west
leg, as shown in Figure 11.
▪ This will require pavement widening to the inside of the traffic circle and on
each of the four legs of the intersection to accommodate the additional lane.
Page 90 of 234
P A G E | 43
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
▪ Estimated preliminary probable opinion of cost of $2,000,000 and a
construction duration estimated at 8 months.
Figure 11. Proposed Roundabout Configuration at Sea Pines Circle Under Option A
• Local Intersection Option B:
o Extend the 6-lane section from Gum Tree Road past Pembroke Drive. The 6-lane section
can taper back to a 4-lane section at Central Avenue.
▪ In addition to the roadway widening, this will require adjustments to the shared
use path on the north side of the road, new traffic signals at Wilborn and
Pembroke, temporary construction easements and possibly new ROW.
▪ Estimated preliminary probable opinion of cost of $3,000,000 and a
construction duration estimated at 6 months.
o William Hilton Parkway & Wilborn Road
▪ Provide dual southbound right-turn lanes.
▪ In addition to the roadway widening, this will require adjustments to the shared
use path on the east side of the road, temporary construction easements and
possibly new ROW.
▪ Estimated preliminary probable opinion of cost of $1,000,000 and a
construction duration estimated at 4 months.
o Palmetto Bay Road & William Hilton Parkway (Sea Pines Circle)
▪ Signalize the intersection rather than the existing roundabout.
▪ Provide a left-turn lane, two thru lanes, and a right-turn lane for every approach
except the EB approach, which will have dual LT lanes.
Page 91 of 234
P A G E | 44
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
▪ In addition to the roadway widening on each leg of the intersection to
accommodate the addition of turn lane, this will require adjustments to the
shared use path on the east side of the south leg, new traffic signals, temporary
construction easements and new ROW on the north and west legs.
▪ Estimated preliminary probable opinion of cost of $6,000,000 and a
construction duration estimated at 12 months.
It should be noted that the improvements recommended at Sea Pines Circle could be implemented
independently of the improvements along William Hilton Parkway.
OPTIONS A AND B VISSSIM TRAFFIC OPERATIONAL ANALYSIS
The operating conditions for all of the study intersections under Options A and B are provided in
Appendix O. Overall, the study intersections are largely expected to operate acceptably in the year 2045
under both Options.
Under Option A, the previous operating conditions along William Hilton Parkway west of Gum Tree Road
would be maintained. The intersections downstream of Gum Tree Road are largely expected to operate
acceptably in 2045 with the improvements under Option A in place. The reconfiguration of the
northbound approach at the intersection of William Hilton Parkway and Pembroke Drive is expected to
help reduce the eastbound and westbound queue lengths as more of the cycle length can go towards
the mainline. However, even with adaptive signals and the reconfiguration of the northbound approach,
long eastbound and westbound queues would still be expected under this scenario. That being said, the
queue lengths are not expected to impact the nearby intersections with the improvements in place and
are well served, as evidenced by the expected overall LOS D’s at each signalized intersection.
Along Palmetto Bay Road, the two-lane roundabout with bypass lanes for all legs except for the east leg
at Sea Pines is expected to operate favorably during both AM and PM peak hours. The roundabout is
expected to operate with an overall LOS B or better during both peak periods. The previously failing
approaches would be mitigated and the queue lengths would be minimized.
Under Option B, the intersections downstream of Gum Tree Road are expected to operate favorably in
2045. The long eastbound and westbound queues between Pembroke Drive and Gum Tree Road would
be minimized. The roadways would have adequate capacity to accommodate traffic through 2045.
Option B removes the roundabout at Sea Pines Circle and replaces it with a signalized intersection. It
was found that a signalized intersection would also operate acceptably through the year 2045 at Sea
Pines. The overall LOS would be a C during both the AM and PM peak hours and the queue lengths
would not be expected to impact nearby intersections.
OPTIONS A AND B VISSIM TRAVEL TIME COMPARISON
A comparison of the calculated travel times between the 2045 No-Build conditions and the 2045
Modified Alternative 1 without any improvements to the downstream intersections as well as with the
recommended improvements under both Option A and Option B were evaluated using VISSIM. These
travel times represent the final travel time calculations for the study area and are presented in Table 21.
Page 92 of 234
P A G E | 45
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Under Option A, the travel times are expected to improve along William Hilton Parkway between Moss
Creek Drive and Indigo Run Drive by approximately 17.2 minutes (65%) during the AM peak hour in the
eastbound direction and by approximately 15.7 minutes (61%) during the PM peak hour in the
westbound direction. The travel times along William Hilton Parkway at Moss Creek to the Cross Island
Parkway at Sea Pines Circle are expected to improve by approximately 19.2 minutes (58%) during the
AM peak hour in the southbound direction and by approximately 27 minutes (66%) during the PM peak
hour in the northbound direction.
Under Option B, the travel times are expected to improve along William Hilton Parkway between Moss
Creek Drive and Indigo Run Drive by approximately 17.4 minutes (65%) during the AM peak hour in the
eastbound direction and by approximately 16.5 minutes (64%) during the PM peak hour in the
westbound direction. The travel times along William Hilton Parkway at Moss Creek to the Cross Island
Parkway at Sea Pines Circle are expected to improve by approximately 19.4 minutes (59%) during the
AM peak hour in the southbound direction and by approximately 27 minutes (66%) during the PM peak
hour in the northbound direction.
As shown in Table 21, the travel times along William Hilton Parkway between Moss Creek Drive and
Indigo Run Drive are relatively comparable between the three scenarios. The 2045 Modified Alternative
1 without improvements to downstream intersections is already expected to operate under largely free-
flowing conditions. While the recommended improvements under Options A and B help to reduce long
queues, they do not largely impact the travel times.
However, the travel times along William Hilton Parkway between Moss Creek Drive to the Cross Island
Parkway at Sea Pines Circle are expected to vastly improve under Options A and B.
Page 93 of 234
P A G E | 46
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 21. Comparison of Final Travel Times for Entire Study Area
Corridor
William Hilton
Pkwy Between
Moss Creek and
Indigo Run
% Difference
to 2045 No-
Build
William Hilton
Pkwy from Moss
Creek to Sea Pine
Circle via Cross
Island Pkwy
% Difference
to 2045 No-
Build
EB WB EB WB SB NB SB NB
2045 No-Build Simulated Travel
Time (secs) [min]
AM 1579
[26.3]
584
[9.7] - - 1984
[33.1]
823
[13.7] - -
PM 642
[10.7]
1544
[25.7] - - 873
[14.6]
2465
[41.1] - -
2045 Modified Alternative 1
Without Improvements to
Downstream Intersections
Simulated Travel Time (secs)
[min]
AM 628
[10.5]
597
[10] 60.23% 2.23% 1387
[23.1]
848
[14.1] 30.09% 3.04%
PM 631
[10.5]
616
[10.3] -1.71% 60.10% 874
[14.6]
904
[15.1] 0.11% 63.33%
2045 Modified Alternative 1
Option A
Simulated Travel Time (secs)
[min]
AM 548
[9.1]
556
[9.3] 65.31% -4.85% 833
[13.9]
814
[13.6] 58.01% -1.04%
PM 589
[9.8]
600
[10] -8.21% 61.12% 856
[14.3]
845
[14.1] -1.93% 65.72%
2045 Modified Alternative 1
Option B
Simulated Travel Time (secs)
[min]
AM 534
[8.9]
547
[9.1] 66.18% -6.34% 820
[13.7]
816
[13.6] 58.67% -0.86%
PM 571
[9.5]
552
[9.2] 11.06% 64.25% 840
[14]
848
[14.1] -3.78% 65.60%
OPTIONS A AND B NETWORK PERFORMANCE
Table 22 summarizes overall network performance for the 2045 Modified Alternative 1 with the
improvements to the local intersections under Option A and Option B as compared to the 2045 No-Build
conditions. As shown, the network performance is expected to drastically improve under both options.
During the AM peak hour, vehicles stops will decrease throughout the study area. Vehicles will be
required to stop on average 1.6 times under both Options A and B. Additionally, the average vehicle
speeds during the AM peak hour will increase to an average of 38 to 37 mph for Option A and B,
respectively.
During the PM peak hour, vehicles will be required to stop on average 2.1 to 1.9 times under Options A
and B, respectively, both of which are significantly lower than the 2045 No-Build scenario. Additionally,
the average vehicle speeds during the PM peak hour will increase to an average of 36 mph.
Page 94 of 234
P A G E | 47
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Table 22. Network Performance for Entire Study Area
Scenario
Average
Number of
Stops per
Vehicle
Average Speed
(mph)
Total Vehicles
(vph)
2045 No-Build AM 9.9 21 11,143
2045 No-Build PM 15.4 16 12,393
2045 Modified Alternative 1: No
Improvements to Local
Intersections AM
6.3 28 11,355
2045 Modified Alternative 1: No
Improvements to Local
Intersections PM
6.7 29.8 13,531
2045 Modified Alternative 1:
Option A AM 1.6 38 11,697
2045 Modified Alternative 1:
Option A PM 2.1 36 14,060
2045 Modified Alternative 1:
Option B AM 1.6 37 11,693
2045 Modified Alternative 1:
Option B PM 1.9 36 14,064
MULTIMODAL AND SAFETY RECOMMENDATIONS FOR LOCAL INTERSECTIONS
In order to help improve the multimodal experience and improve safety along the local intersections
east of Gum Tree Road and along Cross Island Parkway, the following additional improvements for the
local intersections are recommended:
• William Hilton Parkway & Wilborn Road
o Realign north crosswalk to ensure pedestrian path is routed through the existing raised
channelized islands to provide pedestrian refuge areas within the northwest and
northeast quadrants of the intersection. Remove existing crosswalk related pavement
markings and wooden stop signs associated with the north crosswalk. Ensure pedestrian
signal actuation is provided across southbound left-turn and thru lanes; however,
pedestrian signal actuation across the southbound and westbound right-turn lanes
would not be necessary.
o Realign east crosswalk further to the east toward the existing raised channelized island
to provide pedestrian refuge area. Remove portions of the existing channelized
pavement marking between the westbound thru and left-turn lanes, and implement a
raised median to provide pedestrian refuge, similar to what is currently in place for the
westbound approach at Pembroke Drive.
o Ensure Accessible Pedestrian Signal (APS) infrastructure is installed for all signalized
pedestrian crossings, and located in compliance with current Public ROW Accessibility
Guidelines (PROWAG) requirements. This may require modifications to existing curb
Page 95 of 234
P A G E | 48
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
ramps and/or sidewalk segments at the intersection, if the existing pedestrian path
surfaces that are not PROWAG compliant.
o Ensure pedestrian clearance interval signal timing data complies with MUTCD
requirements.
o Ensure vegetation is maintained within each quadrant to ensure optimal intersection
sight distance for side-street motorists entering William Hilton Parkway, as well as that
the presence of pedestrians are clearly visible to northbound/southbound/westbound
right-turning vehicles.
• William Hilton Parkway & Pembroke Drive
o Improve pedestrian path crossing landing area on the north side of the intersection to
provide more refuge for waiting pedestrians
o Ensure APS infrastructure is installed for all signalized pedestrian crossings, and located
in compliance with current PROWAG requirements. This may require modifications to
existing curb ramps and/or sidewalk segments at the intersection, if the existing
pedestrian path surfaces that are not PROWAG compliant.
o Ensure pedestrian clearance interval signal timing data complies with MUTCD
requirements.
• William Hilton Parkway & Central Avenue
o Currently, pedestrians must cross in front of the uncontrolled eastbound left-turn.
Therefore, it is recommended that the west leg pedestrian crossing be improved to
provide for shorter crossing distances/fewer lane crossings at once.
• Palmetto Bay Road & Arrow Road
o Ensure an ADA compliant detectable warning is installed in the northwest quadrant’s
curb ramp.
o Ensure APS infrastructure is installed for all signalized pedestrian crossings, and located
in compliance with current PROWAG requirements. This may require modifications to
existing curb ramps and/or sidewalk segments at the intersection, if the existing
pedestrian path surfaces that are not PROWAG compliant.
o Ensure pedestrian clearance interval signal timing data complies with MUTCD
requirements.
• Palmetto Bay Road & Target Road
o Ensure APS infrastructure is installed for all signalized pedestrian crossings, and located
in compliance with current PROWAG requirements. This may require modifications to
existing curb ramps and/or sidewalk segments at the intersection, if the existing
pedestrian path surfaces that are not PROWAG compliant.
o Ensure pedestrian clearance interval signal timing data complies with MUTCD
requirements.
• Palmetto Bay Road & William Hilton Parkway (Sea Pines Circle)
o Incorporate pedestrian facilities and crossings for each approach where feasible.
Page 96 of 234
P A G E | 49
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
Additionally, from a safety perspective, congested corridors often lead to an increase in crashes because
of stop-and-go conditions. By alleviating the congestion along William Hilton Parkway, it is expected that
the total number of crashes along the corridor would decrease. It should also be noted that access
points throughout the study area were not restricted to a point where emergency vehicles would be
significantly impacted or be required to alter their response routes.
Page 97 of 234
P A G E | 50
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
CONCLUSIONS
The Town of Hilton Head Island, South Carolina commissioned an independent study of the William
Hilton Parkway Gateway Corridor to assess the need for improvements along US 278 (William Hilton
Parkway) from Moss Creek Drive to Indigo Run Drive, as well as along US 278 (Palmetto Bay Road) from
Cross Island Parkway to Sea Pines Circle. This report summarized Existing and future year No-Build traffic
operations and safety along the corridor to quantify mobility issues that exist today and that would be
expected in the future, absent any upgrades to the roadway network.
This report also detailed the numerous corridor alternatives considered for implementation along
William Hilton Parkway between Moss Creek Drive and Gum Tree Road. Four proposed corridor
alternatives consisting of two at-grade solution and two grade separated solutions were analyzed. The
goal of the alternatives analysis was to provide an objective, data-driven evaluation of the four
alternatives. This evaluation was then used to assist with the selection of a single recommended
alternative for the corridor.
Per the direction of the Town of Hilton Head Island, Lochmueller Group was directed to pursue corridor
Alternative 1: SCDOT Modified Recommended Preferred with modifications to provide a single
eastbound left-turn lane and a single southbound right-turn lane at the intersection of William Hilton
Parkway at Squire Pope Road.
With the recommended improvements under Alternative 1: SCDOT Modified Recommended Preferred
in place, this report further evaluated the impacts to the intersections downstream (i.e., east of Gum
Tree Road to Indigo Run, and south of Cross Island Parkway to Sea Pines Circle). Two additional options
for mitigation were then provided for The Town of Hilton Head Island’s consideration to help ease
congestion at the local intersections between Gum Tree Road and Indigo Run Drive, as well as along the
Cross Island Parkway towards Sea Pines Circle.
The following conclusions were reached:
2045 ALTNERATIVES ANALYSIS
CONGESTION AND CORRIDOR MOBILITY
• Under Alternative 1, the northbound approach of Squire Pope Road during the PM peak
hour is expected to operate with a LOS F. All other approaches at signalized intersections
between Squire Pope Road and Gum Tree Road are expected to operate with a LOS E or
better.
• Under Alternative 2, there are no movements between Squire Pope Road and Gum Tree
Road that are expected to operate with a LOS F at a signalized intersection; however, some
movements between Squire Pope Road and Gum Tree Road are expected to have a LOS E.
• Under Alternative 3, if an echelon at Squire Pope is pursued, then the southbound
approach at Squire Pope Road during the PM peak hour would be expected to have a LOS
F. If a center turn overpass at Squire Pope is pursued, then the northbound approach at
Spanish Wells would be expected to operate with a LOS F. All other approaches at
Page 98 of 234
P A G E | 51
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
signalized intersections between Squire Pope Road and Gum Tree Road are expected to
operate with a LOS E or better.
• Under Alternative 4, all movements at signalized intersections are expected to operate at a
LOS D or better between Squire Pope Road and Gum Tree Road.
• All four proposed alternatives show significant improvements to corridor-wide metrics as
compared to the 2045 No-Build condition.
• While all four proposed alternatives are expected to result in improved travel times along
William Hilton Parkway between Moss Creek Drive and Gum Tree Road when compared to
the 2045 No-Build, Alternative 4 is expected to have the lowest, and therefore best, travel
times. Alternative 3 is expected to have the second best travel times, and the travel times
between Alternative 1 and 2 are expected to be comparable.
SAFETY AND MULTIMODAL CONSIDERATIONS
• Alternative 1 results in the longest pedestrian crossing distances at the study intersections.
The amount of ROW needed in Alternative 1 may limit the ability to add median refuge
islands. In addition, each intersection would have multiple turning movements and
potential conflict points along each leg.
• Alternative 2 results in a reduced pedestrian crossing distance at the study intersections
which reduces pedestrians’ exposure to vehicular traffic. Alternative 2 also allows the
potential for median refuge islands. Bowtie intersections have fewer pedestrian and
vehicle conflict points than a traditional intersection.
• Alternative 3 results in a reduced pedestrian crossing distance at the study intersections
which reduces pedestrians’ exposure to vehicular traffic. Alternative 3 also allows the
potential for median refuge islands to help pedestrians navigate the more complex
intersections. Both echelons and center turn overpass intersections have fewer pedestrian
and vehicle conflict points than a traditional intersection.
• Alternative 4 also results in a reduced pedestrian crossing distance at the study
intersections which reduces pedestrians’ exposure to vehicular traffic. With an elevated
bypass, refuge islands can be provided between directional traffic flow. However, it should
be noted that multiple refuge islands per leg may result in a more complex intersection.
The elevated bypass would be expected to have fewer pedestrian and vehicle conflict
points when compared to Alternative 1 given the smaller intersections. Alternative 4 would
also divert a majority of thru traffic onto the elevated by-pass, thereby greatly reducing the
number of vehicles that pedestrians and bicyclists must contend with while
crossing/navigating William Hilton Parkway.
RIGHT -OF -WAY (ROW)/PRELIMINARY PROBABLE OPINION OF COST
• From a ROW perspective, each of the four proposed alternatives were compared to
Alternative 1 (SCDOT Modified Recommended Preferred). The proposed alternatives were
not compared to existing conditions for ROW purposes. ROW estimates refer to permanent
Page 99 of 234
P A G E | 52
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
ROW needed for the completed improvements only, and do not consider temporary ROW
needed for construction or staging.
• Alternative 1:
o When compared to the original SCDOT Modified Recommended Preferred, Alternative 1
is expected to require an additional 0.2 acres of ROW to allow for the improvements at
Gum Tree Road.
o Alternative 1 has an estimated preliminary probable opinion of cost of $426 million
dollars and a construction duration estimated at 36 months.
• Alternative 2:
o When compared to the original SCDOT Modified Recommended Preferred, Alternative 2
is expected to require an additional 1.1 acres of ROW to allow for the improvements at
Gum Tree Road as well as for the bowtie intersections.
o Alternative 2 has an estimated preliminary probable opinion of cost of $430 million
dollars and a construction duration estimated at 38 months.
• Alternative 3:
o When compared to the original SCDOT Modified Recommended Preferred, Alternative 3
is expected to require an additional 1.1 acres of ROW to allow for the improvements at
Gum Tree Road as well as for the echelon / center turn overpass intersections.
o Alternative 3 has an estimated preliminary probable opinion of cost between $440-$450
million dollars and a construction duration estimated at 42 months.
• Alternative 4:
o When compared to the original SCDOT Modified Recommended Preferred, Alternative 4
is not expected to require any additional ROW.
o Alternative 4 has an estimated preliminary probable opinion of cost between $545-$575
million dollars and a construction duration estimated at 48 months.
ENVIRONMENTAL
• Similar to the ROW, each of the four proposed corridor alternatives were compared to
Alternative 1 (SCDOT Modified Recommended Preferred) for the environmental
assessment.
• Several categories were evaluated with respect to the environmental impact such as
streams, floodplains, relocations, neighborhoods, environmental justice, cultural resources,
and Section 4(f) resources.
• Alternative 1 is expected to have the least environmental impact when compared to the
original SCDOT Modified Recommended Preferred alternative, followed by Alternative 4,
Alternative 2, then Alternative 3, respectively.
Page 100 of 234
P A G E | 53
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
TOWN SELECTED ALTERNATIVE
After evaluating the four proposed corridor alternatives, Lochmueller was directed by the Town of
Hilton Head Island to pursue corridor Alternative 1: SCDOT Modified Recommended Preferred with
modifications to provide a single eastbound left-turn lane and a single southbound right-turn lane at the
intersection of William Hilton Parkway at Squire Pope Road through to the final phase of analysis.
DOWNSTREAM IMPACTS OF TOWN SELECTED ALTERNATIVE 1
An analysis was conducted assuming only the improvements under the Modified Alternative 1 were in
place, to better understand how the entire study area would operate if no geometric roadway
improvements were implemented east of Gum Tree Road or along Cross Island Parkway.
Even with no improvements in place east of Gum Tree Road or along Cross Island Parkway, travel times
would significantly improve as compared to the 2045 No-Build scenario. The intersections would be
expected to operate acceptably overall. However, long queues were noted between Wilborn Road and
Pembroke Drive. Additionally, the existing roundabout at Palmetto Bay Road and Sea Pines Circle is
expected to fail during both the AM and PM peak hours. As a result of the failing roundabout, the
southbound queue lengths are expected to extend beyond nearby intersections.
ADDITIONAL MITIGATION S OLUTIONS FOR LOCAL INTERSECTIONS
To help mitigate the long queue lengths and operational failures at Sea Pines Circle, two options with
potential improvements to the local intersections downstream of Gum Tree Road and Cross Island
Parkway were developed for the Town of Hilton Head Island’s consideration:
• Option A was developed to help address congestion between Wilborn Road and Pembroke Drive
while minimizing the physical impacts along the corridor by reconfiguring the northbound
approach at the intersection of William Hilton Parkway and Pembroke Drive. Under Option A,
the existing roundabout at Sea Pines Circle was expanded to a two-lane roundabout with right-
turn bypass lanes for each approach except for the east leg.
• Option B considered a more significant approach to help mitigate the expected queue lengths
between Wilborn Road and Pembroke Drive by extending the six-lane section through Central
Avenue. Under Option B, the existing roundabout at Sea Pines Circle was reconfigured into a
signalized intersection.
• The 2045 Modified Alternative 1 without improvements to downstream intersections is already
expected to operate under largely free-flowing conditions. While the recommended
improvements under Options A and B help to reduce long queues, they do not largely improve
the travel times. However, the travel times along William Hilton Parkway between Moss Creek
Drive to the Cross Island Parkway at Sea Pines Circle are expected to vastly improve under
Options A and B.
Page 101 of 234
P A G E | 54
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
SAFETY AND MULTIMODAL CONSIDERATIONS
• The SCDOT Modified Recommended Preferred Alternative will provide a separated SUP for
bicycles. Due to the heavy traffic volumes, on street facilities are not being considered.
Therefore, the recommendations made mainly focus on how to best accommodate
pedestrians. In order to help improve safety as well as the multimodal experience, it is
recommended that pedestrian refuge islands be provided wherever possible. Some specific
locations include the east and west legs of William Hilton Parkway at Squire Pope Road; the
west leg of William Hilton Parkway at Spanish Wells Road; and the east leg of William
Hilton Parkway at Wilborn Road.
• If continuous sidewalk facilities are not planned to be installed along the south side of
William Hilton Parkway west of Squire Pope Road, consider eliminating the William Hilton
Parkway pedestrian crossing on the west leg at Squire Pope Road to instead encourage
pedestrians to cross William Hilton Parkway at the east leg only.
• During final design efforts for the intersections of William Hilton Parkway at Squire Pope
Road and Spanish Wells Road, provide high visibility crosswalks, and also seek to tighten
curb radii to shorten pedestrian crossing distances across applicable legs of the
intersections.
• It is recommended that the north crosswalk at William Hilton Parkway and Wilborn Road
be relocated further north away from traffic, and that the right-turn channelized islands be
reconfigured to provide a pedestrian refuge. It is also recommended that the east
crosswalk be relocated further east toward the existing raised channelized island in the
northeast quadrant to provide a pedestrian refuge.
• Ensure Accessible Pedestrian Signal (APS) infrastructure is installed for all signalized
pedestrian crossings, and located in compliance with current Public ROW Accessibility
Guidelines (PROWAG) requirements. This may require modifications to existing curb ramps
and/or sidewalk segments at the intersection, if the existing pedestrian path surfaces that
are not PROWAG compliant.
• Ensure pedestrian clearance interval signal timing data complies with MUTCD requirements
for all signalized pedestrian crossings.
• Congested corridors often lead to an increase in crashes because of stop-and-go
conditions. By alleviating the congestion along William Hilton Parkway, it is expected that
the total number of crashes along the corridor would decrease.
• It should also be noted that access points throughout the study area were not restricted to
a point where emergency vehicles would be significantly impacted or required to alter their
response routes.
Page 102 of 234
P A G E | 55
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC OPERATIONS AND SAFETY REPORT
APPENDIX
Appendix A. 2023 Existing Traffic Volumes
Appendix B. 2023 Existing Operating Conditions (Synchro)
Appendix C. 2023 Existing Operating Conditions (VISSIM)
Appendix D. Traffic Forecasting Memorandum
Appendix E. 2045 No-Build Traffic Volumes
Appendix F. 2045 No-Build Traffic Operating Conditions (Synchro)
Appendix G. 2045 No-Build Traffic Operating Conditions (VISSIM)
Appendix H. Four Lane Viability Review Technical Memorandum; Seismic Study Review; Cursory Review
of Southern Bypass
Appendix I. 2045 Alternative 1 Traffic Volumes and Operating Conditions (Synchro)
Appendix J. Technical Environmental Overview
Appendix K. 2045 Alternative 2 Traffic Volumes and Operating Conditions (Synchro)
Appendix L. 2045 Alternative 3 Traffic Volumes and Operating Conditions (Synchro)
Appendix M. 2045 Alternative 4 Traffic Volumes and Operating Conditions (Synchro)
Appendix N. 2045 Modified Alternative 1 Operating Conditions (VISSIM)
Appendix O. 2045 Local Intersections Operating Conditions (VISSIM)
Page 103 of 234
P A G E | A-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
APPENDIX A: 2023 EXISTING TRAFFIC VOLUMES
Page 104 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2023 Existing Traffic Volumes
AM Peak Hour – Pg 1 of 6
1
2
3
4
5
7
8
6
9
11
12
10
74
2
4 16
436
627
11
28
232
879
25
Bluffton Pkwy
Buckingham
Plantation Dr
US 278
78
0
8 86
1084
60
0
45
8
1792
2
US 278
Salt Marsh Dr
1162
414
15
1843
2
US 278
Fording
Island Rd Ext
68
25
42
Buckingham
Plantation Dr
23
1119
2029
60
170
62
1590
35
US 278
Wildlife
Refuge
0
0
0 0
1624
0
0
0
2
2
2763
4
1
14
0
40
US 278
Crosstree Dr
3
1607
30
2740
32
US 278
Jenkins Rd
5
1634
6
4
6
2774
1622
02
10
2762
3
US 278
Blue Heron
Point Rd
212
0
45
43
1425
2
2
0
5
156
2620
2
US 278
Squire Pope
Rd
12
70
127
43
2481
146
56
1281
71121
43
121
US 278
Spanish Wells
Rd
US 278
Old Wild
Horse Rd20
1394
76
2670
92
179
212
US 278
Gum Tree
Rd
189
775
1938
144
290
154
1527
6
Page 105 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2023 Existing Traffic Volumes
AM Peak Hour – Pg 2 of 6
23
24
13
15
16
14
17
18
20
19
21
22
181
27
244
302
953
2
23
45
0
253
1708
68
US 278
Jarvis Park Rd
20 20
997
55
5
1676
5
US 278
Central Ave
US 278
Hatton Pl
US 278
Pembroke Dr
10 41
1012101589
92 45
12
18
31
953
33259
21
37
80
1631
241
US 278
Indigo Run Dr
111
68
214
166
862
33
80
51
33
129
1415
556
374
2
0
Honey Horn Rd
Cross Island Pkwy SB
79
18471
58
126
122
Marshland Rd
Cross Island
Pkwy NB
Marshland Rd
Cross Island
Pkwy SB140
115
36
0
23
225
242
0
1714
5
899
0
5
Bay Pines Rd
Palmetto Bay Rd
Arrow Rd
Palmetto Bay
Rd
1603
16 5
5745
5
Genesta St
Palmetto Bay
Rd
53
1443
223 118
11
38
44
672
34
114
15
138
5
5745
0
1583
25
Palmetto
Business Park RdPalmetto Bay Rd
Page 106 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2023 Existing Traffic Volumes
AM Peak Hour – Pg 3 of 6
25
26
28
27
29
5
5740
20
1548
40
Bow Cir
Palmetto Bay Rd
5
10755
23
1503
50
Archer Rd
Palmetto Bay Rd
87
1279
147
53
34
97
55
679
25
46
17
46
Target Rd
Palmetto Bay
Rd
Dunnagans
Alley
Palmetto Bay Rd
1306
116
10
5749
50
465
688
158 160
252
18336
376
177
263
132
50
Greenwood Dr
Palmetto Bay
Rd
Page 107 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2023 Existing Traffic Volumes
PM Peak Hour – Pg 4 of 6
1
2
3
4
5
7
8
6
9
11
12
10
99
12
2
10
923
20
24
12
26
88
654
22
Bluffton Pkwy
Buckingham
Plantation Dr
122
36
67 45
1992
2150
40
20
94
1441
56
US 278
Buckingham
Plantation Dr
78
0
5 56
1980
280
0
40
24
1496
8
US 278
Salt Marsh Dr
US 278
Fording
Island Rd Ext
2044
1620
201517
24
US 278
Wildlife
Refuge
US 278
Crosstree Dr
US 278
Jenkins Rd
10
0
4 6
3001
2
2
0
6
4
2211
40
5
2975
5032
0
52
2195
30
10
3020
10
6
10
2237
3005
24
12
2213
8
US 278
Blue Heron
Point Rd
341
2
41 57
2687
2
2
25
2
222
1992
29
US 278
Squire Pope
Rd
33
78
62 84
2508
31
259
47
60
51
1869
115
US 278
Spanish Wells
Rd
US 278
US 278
Old Wild
Horse Rd
64
2736
10
2035
107
183
242
326
1542
195224
207
277
125
1065
23
Gum Tree
Rd
Page 108 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2023 Existing Traffic Volumes
PM Peak Hour – Pg 5 of 6
23
24
13
15
16
14
17
18
20
19
21
22
246
8
86 64
1761
456
8
10
113
1422
49
US 278
Jarvis Park Rd
5 21
1515
5
10
5
1299
5
US 278
Central Ave
US 278
Hatton Pl
US 278
Pembroke Dr
10 10
1531
591304
5 51
27
14
27
1462
31316
35
37
57
1258
203
US 278
Indigo Run Dr
111
115
251
304
1366
5164
115
49
164
1152
478
397
40
15
Honey Horn Rd
Cross Island Pkwy SB
37
305252
142
48
143
Marshland Rd
Cross Island
Pkwy NB
Marshland Rd
Cross Island
Pkwy SB420
137
78
2
61
130
135
10
1313
20
1721
10
10
Bay Pines Rd
Palmetto Bay Rd
Arrow Rd
Palmetto Bay
Rd
1188
5 5
51537
4
Genesta St
Palmetto Bay
Rd
86
1062
175
328
36
38
120
1346
76
67
29
93
10
51531
5
1188
5
Palmetto
Business Park RdPalmetto Bay Rd
Page 109 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2023 Existing Traffic Volumes
PM Peak Hour – Pg 6 of 6
25
26
28
27
29
10
101526
10
1183
10
Bow Cir
Palmetto Bay Rd
10
101526
10
1183
10
Archer Rd
Palmetto Bay Rd
53
1083
57
111
44
78111
1253
46
172
44
76
Target Rd
Palmetto Bay
Rd
Dunnagans
Alley
Palmetto Bay Rd
Greenwood Dr
Palmetto Bay
Rd
1227
10 61
291349
10
484
667
105 383
347
120
55
618
355
358
177
181
Page 110 of 234
P A G E | B-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
APPENDIX B: 2023 EXISTING OPERATING CONDITIONS (SYN CHRO)
Page 111 of 234
P A G E | B-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Table B-1. 2023 Existing Operating Conditions (Synchro)
Intersection & Movements LOS (Delay, sec) [95th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
1: Buckingham Plantation Dr & Bluffton Pkwy (signal)
Overall Intersection B (10.4) B (15. 2)
Eastbound Approach A (7.1) [196] <0.37> A (9.1) [166] <0.29>
Westbound Approach B (12.4) [146] <0.21> B (17.5) [346] <0.46>
Northbound Approach D (41.9) [63] <0.14> C (34.2) [48] <0.15>
Southbound Approach B (18.4) [55] <0.25> C ( 23.4 ) [m8 9] <0.30>
2: Buckingham Plantation Dr/Moss Creek Dr & William Hilton Pkwy (signal)
Overall Intersection B (19.2) C (29.6)
Eastbound Approach B (15.0) [413] <0.56> B ( 19.5 ) [ 391 ] <0.64>
Westbound Approach B (14.6) [291] <0.36> C (2 6.8 ) [ 710 ] <0. 71 >
Northbound Approach D (45.5) [126] <0.67> E (75.9) [ 103 ] <0. 56 >
Southbound Approach E (59.4) [107] <0.57> F ( 81.3 ) [174 ] < 0.91 >
3: Salt Marsh Dr/Moss Creek Village & William Hilton Pkwy (un -signal ized )
Eastbound Left Turn C (16.5) [<25] <0.03> E (43.4) [<25] <0.22>
Westbound Left Turn D (33.5) [<25] <0.05> D (26.6) [<25] <0.15>
Northbound Approach D (26.5) [<25] <0.23> C (21.7) [<25] <0.23>
Southbound Approach D (30.8) [45] <0.41> F (165.4) [150] <0.99>
4: Fording Island Rd Ext & William Hilton Pkwy (un -signalized)
Westbound Left Turn C (18.0) [<25] <0.02> B (14.8) [<25] <0.04>
Northbound Approach F (242.4) [75 ] <0.81> F ($744.7) [168] <1.97>
5: Boat Landing Driveway/Wildlife Refuge Driveway & William Hilton Pkwy (un -signalized)
Eastbound Left Turn C (15.4) [<25] <0.01> E (45.1) [<25] <0.05>
Westbound Left Turn No volumes observed C (22.7) [<25] <0.01>
Northbound Approach E (38.1) [<25] <0.02> F ($2538.4) [68] <2.99>
Southbound Approach No volumes observed F (50.4) [<25] <0.17>
6: Blue Heron Point Rd & William Hilton Pkwy (un -signalized)
Westbound Left Turn No volumes observed C (23.8) [<25] <0.01>
Northbound Approach F ($794.0) [58] <1.19> F ($2033.9) [118] <3.51>
B-2
Page 112 of 234
P A G E | B-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
7: Crosstree Dr (Windmill Harbour) & William Hilton Pkwy (signal)
Overall Intersection B (15.5) E (59.1)
Eastbound Approach C (21.2) [#1701] <0.97> B (10.3) [697] <0.82>
Westbound Approach A (5.2) [291] <0.62> F (93.2) [#2084] <1.16>
Northbound Approach D (38.0) [65] <0.42> E (68.0) [105] <0.72>
Southbound Approach 0 (0.0) [<25] <0.01> 0 (0.0) [<25] <0.00>
8: Jenkins Rd & William Hilton Pkwy (un -signalized)
Eastbound Left Turn C (15.6) [<25] <0.02> F (56.9) [<25] <0.13>
Southbound Approach F ($469.6) [45] <0.73> F ($7285.9) [158] <12.12>
9: Chamberlin Dr/Squire Pope Rd & William Hilton Pkwy (signal)
Overall Intersection B (12.5) F (101.4)
Eastbound Approach A (6.3) [530] <0.66> B (14.4) [#387] <0.93>
Westbound Approach A (9.4) [264] <0.55> F (140.5) [ m#2353 ] <1.26>
Northbound Approach C (24.0) [<25] <0.03> E (79.9) [70] <0.22>
Southbound Approach F (97.3) [#319] <1.01> F (296.1) [#709] <1.61>
10: Old Wild Horse Rd & William Hilton Pkwy (un -signalized)
Southbound Approach C (21.5) [28] <0.28> F (53.5) [<25] <0.13>
11: Spanish Wells Rd/Wild Horse Rd & William Hilton Pkwy (signal)
Overall Intersection C (30.1) D (36.0)
Eastbound Approach C (26.2) [1224] <0.85> B (16.7) [383] <0.62>
Westbound Approach B (18.2) [274] <0.66> C (25.2) [ 631 ] <0.80>
Northbound Approach E (61.8) [223] <0.62> F (214.3) [#667] <1.46>
Southbound Approach F (117.7) [#284] <1.00> E (65.7) [187] <0.36>
12: Gumtree Rd & William Hilton Pkwy (signal)
Overall Intersection E (59.1) E (66.1)
Eastbound Approach E (64.3) [#1177] <0.98> E (65.7) [763] <0.90>
Westbound Approach C (33.6) [#41 1] <0.93> D (54.5) [ 602 ] <1.00>
Northbound Approach E (72.0) [#312] <0.89> E (61.5) [351] <0.86>
Southbound Approach F (90.7) [#418] <0.90> F (115.5) [#517] <1.07>
B-3
Page 113 of 234
P A G E | B-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
13: Jarvis Park Rd/Wilborn Rd & William Hilton Pkwy (signal)
Overall Intersection C (2 1.5 ) B (16.5)
Eastbound Approach B (16.6) [m516] <0.7 1> B (15.8) [m405 ] <0.7 6>
Westbound Approach B (11.3) [316] <0. 49 > A (9.7) [# 1297 ] <0. 87 >
Northbound Approach F (99.7) [143] <0.61> F (108.7) [146] <0.76>
Southbound Approach E (6 0.7 ) [262] <0.77> C (26.9) [102 ] <0. 60 >
14: Pembroke Dr/Museum St & William Hilton Pkwy (signal)
Overall Intersection B (19.7) C ( 31.2 )
Eastbound Approach B (11.2) [560] <0.73> C (21.9) [704] <0. 60>
Westbound Approach A (9.0) [155] <0.44> C (22.9) [508] <0.82>
Northbound Approach F (101.1) [#317] <0.86> F (89.3) [324] <0.84>
Southbound Approach D (39.8) [78] <0.39> D (49.2) [95] <0.60>
15: Central Ave & William Hilton Pkwy (un -signalized)
Eastbound Left Turn B (10.7) [<25] <0.01> B (14.9) [<25] <0.01>
Westbound Left Turn C (16.0) [<25] <0.02> B (12.3) [<25] <0.01>
Northbound Right Turn C (18.3) [<25] <0.02> B (14.5) [<25] <0.03>
Southbound Right Turn B (12.8) [<25] <0.05> C (17.1) [<25] <0.02>
16: Hatton Pl/Merchant St & William Hilton Pkwy (un -signalized)
Northbound Right Turn C (17.6) [<25] <0.04> C (16.1) [<25] <0.17>
Southbound Right Turn B (12.7) [<25] <0.02> C (17.5) [<25] <0.04>
17: Indigo Run Dr/Whooping Crane Way & William Hilton Pkwy (signal)
Overall Intersection C (31.1) D (42.1)
Eastbound Approach C (27.3) [693] <0.65> C (30. 9) [634] <0.71>
Westbound Approach B (16.2) [343] <0.41> C (31.3) [891] <0.75>
Northbound Approach E (70.1) [112] <0.48> E (68.9) [205] <0.68>
Southbound Approach E (70.3) [#188] <0.78> F (96.0) [#247] <0.98>
18: Cross Island Pkwy SB Ramp/Gumtree Rd & Honey Horn Rd (un -signalized)
Eastbound Approach B (11.0) [<25] <0.00> B (12.8) [<25] <0.1 6>
19: Cross Island Pkwy SB Ramp & Marshland Rd (un -signalized)
Westbound Left Turn A (8.9) [<25] <0.12> A (8.4) [<25] <0.14>
Southbound Left Turn C (17.2) [<25] <0.08> D (33.6) [35] <0.35>
Southbound Right Turn A (9.2) [<25] <0.04> B (12.9) [<25] <0.16>
B-4
Page 114 of 234
P A G E | B-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
20: Cross Island Pkwy NB Ramp & Marshland Rd (un -signalized)
Eastbound Left Turn A (8.2) [<25] <0.11> A (8.4) [<25] <0.05>
Northbound Left Turn B (14.5) [<25] <0.17> C (23.0) [100] <0.61>
Northbound Right Turn A (9.2) [<25] <0.07> B (10.2) [<25] <0.20>
21: Palmetto Bay Rd & Bay Pines Rd (un -signalized)
Eastbound Left Turn No volumes observe d F (209.4) [30] <0.40>
Eastbound Right Turn C (18.7) [<25] <0.02> B (14.9) [<25] <0.03>
Northbound Left Turn C (16.4) [<25] <0.02> B (13.0) [<25] <0.05>
22: Palmetto Bay Rd & Point Comfort Rd/Arrow Rd (signal)
Overall Intersection B (13.8) C (21.1)
Eastbound Approach D (43.3) [175] <0.70> C (30.2) [101] <0.38>
Westbound Approach C (28.0) [74] <0.44> D (46.9) [249] <0.88>
Northbound Approach A (5.4) [75] <0.30> B (17.8) [756] <0.66>
Southbound Approach B (11.5) [535] <0.61> B (15.4) [432] <0.65>
23: Palmetto Bay Rd & Genesta St (un -signalized)
Westbound Approach D (3 2.5 ) [<25] <0.08> F ( 80.7 ) [<25] <0.19>
Southbound Left Turn A (9.6) [<25] <0.02> B (14.6) [<25] <0.01>
24: Palmetto Bay Rd & Palmetto Business Park Rd (un -signalized)
Westbound Approach D (33.8) [<25] <0.08> F (61.2) [<25] <0.20>
Southbound Left Turn A (9.6) [<25] <0.03> B (14.6) [<25] <0.01>
25: Palmetto Bay Rd & Bow Cir (un -signalized)
Westbound Left Turn C (23.7) [<25] <0.03> E (41.3) [<25] <0.10>
Westbound Right Turn B (11.1) [<25] <0.01> C (16.7) [<25] <0.03>
Southbound Left Turn A (9.8) [<25] <0.05> B (14.6) [<25] <0.03>
26: Palmetto Bay Rd & Archer Rd (un -signalized)
Westbound Left Turn C (24.7) [<25] <0.06> E (41.3) [<25] <0.10>
Westbound Right Turn B (11.2) [<25] <0.01> C (16.7) [<25] <0.03>
Southbound Left Turn A (9.9) [<25] <0.07> B (14.6) [<25] <0.03>
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection B (10.6) B (18.6)
Eastbound Approach D (39.4) [82] <0.32> E (59.5) [247] <0.80>
Westbound Approach E (56.6) [154] <0.68> C (33.7) [119] <0.49>
Northbound Approach A (8.7) [199] <0.31> B (15.3) [530] <0.59>
Southbound Approach A (3.9) [102] <0.58> A (8.7) [155] <0.53>
B-5
Page 115 of 234
P A G E | B-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
28: Palmetto Bay Rd & Dunnagans Al y (un -signalized)
Westbound Left Turn D (26.5) [<25] <0.03> E (40.3) [<25] <0.24>
Westbound Right Turn B (11.4) [<25] <0.02> C (17.1) [<25] <0.18>
Southbound Left Turn B (10.6) [<25] <0.16> B (13.0) [<25] <0.02>
29: Palmetto Bay Rd & William Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection D (25.8) C (24.4)
Eastbound Approach D (34.2) [200] <0.81> E (45.6) [300] <0.92>
Westbound Approach C (16.4) [125] <0.64> E (36.6) [ 225 ] <0.85>
Northbound Approach B (12.1) [75] <0.54> D (32.4) [275] <0.88>
Southbound Approach F (59.4) [500] <1.03> E (39.2) [375] <0.94>
# – 95 th Percentile volume exceeds capacity
$ – Delay more than 300 seconds
m – Upstream metering is in effect
B-6
Page 116 of 234
P A G E | C-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
APPENDIX C: 2023 EXISTING OPERATING CONDITIONS (VIS SIM)
Page 117 of 234
P A G E | C-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Table C-1. 2023 Existing Traffic Operations (VISSIM)
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
1: Buckingham Plantation Dr & Bluffton Pkwy (signal)
Overall Intersection B (12.2) B (11.4)
Eastbound Approach B (12.5) [43] {324} B (11.7) [<25] {178}
Westbound Approach A (8.3) [<25] {171} A (9.3) [<25] {234}
Northbound Approach D (38.1) [<25] {73} C (32.2) [<25] {65}
Southbound Approach A (9.0) [<25] {68} B (12.6) [<25] {84}
2: Buckingham Plantation Dr/Moss Creek Dr & William Hilton Pkwy (signal)
Overall Intersection D (47.2) B (19.5)
Eastbound Approach E (70.7) [807] {1620} B (15.6) [65] {522}
Westbound Approach B (14.4) [35] {353} B (19.1) [100] {633}
Northbound Approach D (35.9) [37] {263} D (53.6) [<25] {104}
Southbound Approach D (42.4) [<25] {92} C (33.6) [29] {161}
3: Salt Marsh Dr/Moss Creek Village & William Hilton Pkwy (un-signalized)
Eastbound Left Turn E (35.3) [720] {1302} C (19.7) [<25] {47}
Westbound Left Turn F (414.9) [37] {107} B (11.2) [<25] {41}
Northbound Approach B (10.1) [<25] {61} A (7.3) [<25] {55}
Southbound Approach C (19.7) [<25] {76} A (8.0) [<25] {73}
4: Fording Island Rd Ext & William Hilton Pkwy (un-signalized)
Westbound Left Turn E (40.7) [46] {102} C (16.8) [<25] {28}
Northbound Approach F (591.0) [120] {186} C (17.5) [<25] {41}
5: Boat Landing Driveway/Wildlife Refuge Driveway & William Hilton Pkwy (un-signalized)
Eastbound Left Turn C (21.4) [691] {1658} D (33.1) [<25] {<25}
Westbound Left Turn No volumes observed C (20.9) [<25] {<25}
Northbound Approach F (270.5) [<25] {38} C (20.8) [<25] {46}
Southbound Approach No volumes observed C (18.2) [<25] {39}
6: Blue Heron Point Rd & William Hilton Pkwy (un-signalized)
Westbound Left Turn No volumes observed D (27.7) [<25] {<25}
Northbound Approach F (1,270.4) [123] {228} C (23.8) [<25] {60}
7: Crosstree Dr (Windmill Harbour) & William Hilton Pkwy (signal)
Overall Intersection B (10.4) A (8.2)
Eastbound Approach A (8.4) [335] {1093} A (5.4) [62] {890}
Westbound Approach B (10.7) [53] {655} A (7.5) [292] {1626}
Northbound Approach E (67.8) [30] {164} E (79.0) [52] {214}
Southbound Approach B (17.3) [<25] {<25} A (0.0) [<25] {<25}
C-2
Page 118 of 234
P A G E | C-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
8: Jenkins Rd & William Hilton Pkwy (un-signalized)
Eastbound Left Turn A (8.2) [<25] {<25} F (98.0) [<25] {54}
Southbound Approach F (51.8) [<25] {44} F (109.4) [<25] {92}
9: Chamberlin Dr/Squire Pope Rd & William Hilton Pkwy (signal)
Overall Intersection D (39.2) E (67.3)
Eastbound Approach E (56.8) [451] {1334} B (19.3) [283] {1132}
Westbound Approach A (7.0) [39] {618} F (104.8) [874] {1383}
Northbound Approach C (31.9) [<25] {38} E (78.6) [<25] {76}
Southbound Approach C (21.7) [<25] {147} F (91.6) [220] {638}
10: Old Wild Horse Rd & William Hilton Pkwy (un-signalized)
Southbound Approach A (1.3) [<25] {<25} A (6.4) [<25] {25}
11: Spanish Wells Rd/Wild Horse Rd & William Hilton Pkwy (signal)
Overall Intersection C (29.8) F (240.4)
Eastbound Approach C (26.6) [270] {1027} B (17.1) [103] {622}
Westbound Approach C (21.9) [87] {471} F (415.7) [892] {989}
Northbound Approach E (57.1) [85] {321} F (395.1) [1241] {1288}
Southbound Approach F (89.0) [103] {319} E (63.9) [58] {242}
12: Gumtree Rd & William Hilton Pkwy (signal)
Overall Intersection D (40.7) E (66.4)
Eastbound Approach D (40.6) [765] {1592} D (49.9) [203] {779}
Westbound Approach C (30.3) [136] {357} E (75.2) [961] {1610}
Northbound Approach C (29.0) [75] {291} D (45.2) [175] {338}
Southbound Approach E (77.2) [182] {579} F (93.4) [234] {779}
9: Chamberlin Dr/Squire Pope Rd & William Hilton Pkwy (signal)
Overall Intersection D (39.2) E (67.3)
Eastbound Approach E (56.8) [451] {1334} B (19.3) [283] {1132}
Westbound Approach A (7.0) [39] {618} F (104.8) [874] {1383}
Northbound Approach C (31.9) [<25] {38} E (78.6) [<25] {76}
Southbound Approach C (21.7) [<25] {147} F (91.6) [220] {638}
10: Old Wild Horse Rd & William Hilton Pkwy (un-signalized)
Southbound Approach A (1.3) [<25] {<25} A (6.4) [<25] {25}
C-3
Page 119 of 234
P A G E | C-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
11: Spanish Wells Rd/Wild Horse Rd & William Hilton Pkwy (signal)
Overall Intersection C (29.8) F (240.4)
Eastbound Approach C (26.6) [270] {1027} B (17.1) [103] {622}
Westbound Approach C (21.9) [87] {471} F (415.7) [892] {989}
Northbound Approach E (57.1) [85] {321} F (395.1) [1241] {1288}
Southbound Approach F (89.0) [103] {319} E (63.9) [58] {242}
12: Gumtree Rd & William Hilton Pkwy (signal)
Overall Intersection D (40.7) E (66.4)
Eastbound Approach D (40.6) [765] {1592} D (49.9) [203] {779}
Westbound Approach C (30.3) [136] {357} E (75.2) [961] {1610}
Northbound Approach C (29.0) [75] {291} D (45.2) [175] {338}
Southbound Approach E (77.2) [182] {579} F (93.4) [234] {779}
13: Jarvis Park Rd/Wilborn Rd & William Hilton Pkwy (signal)
Overall Intersection C (21.8) C (25.8)
Eastbound Approach B (17.1) [178] {929} B (13.8) [67] {754}
Westbound Approach B (17.9) [73] {543} C (34.2) [668] {1285}
Northbound Approach F (81.1) [45] {168} E (77.4) [43] {186}
Southbound Approach D (45.4) [72] {233} C (21.7) [28] {120}
14: Pembroke Dr/Museum St & William Hilton Pkwy (signal)
Overall Intersection B (18.7) C (33.7)
Eastbound Approach B (12.6) [134] {991} B (14.3) [76] {754}
Westbound Approach B (12.7) [39] {443} D (42.4) [645] {1261}
Northbound Approach E (72.0) [84] {274} E (69.4) [93] {310}
Southbound Approach D (37.3) [<25] {91} D (42.2) [<25] {115}
15: Central Ave & William Hilton Pkwy (un-signalized)
Eastbound Left Turn A (8.5) [<25] {<25} F (55.9) [<25] {50}
Westbound Left Turn C (16.5) [<25] {<25} A (9.7) [<25] {<25}
Northbound Right Turn C (21.6) [<25] {27} B (12.4) [<25] {32}
Southbound Right Turn B (11.3) [<25] {41} F (165.1) [<25] {65}
16: Hatton Pl/Merchant St & William Hilton Pkwy (un-signalized)
Northbound Right Turn B (11.5) [<25] {25} A (7.7) [<25] {61}
Southbound Right Turn B (10.6) [<25] {46} F (93.1) [<25] {72}
C-4
Page 120 of 234
P A G E | C-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
17: Indigo Run Dr/Whooping Crane Way & William Hilton Pkwy (signal)
Overall Intersection C (23.3) D (44.1)
Eastbound Approach B (18.9) [115] {848} C (30.6) [116] {772}
Westbound Approach B (15.3) [40] {333} D (44.8) [592] {1536}
Northbound Approach D (54.0) [29] {103} E (58.6) [46] {190}
Southbound Approach D (49.7) [52] {187} E (73.4) [83] {324}
18: Cross Island Pkwy SB Ramp/Gumtree Rd & Honey Horn Rd (un-signalized)
Eastbound Approach A (9.1) [<25] {45} B (10.9) [<25] {61}
19: Cross Island Pkwy SB Ramp & Marshland Rd (un-signalized)
Westbound Left Turn A (3.7) [<25] {63} A (2.1) [<25] {60}
Southbound Left Turn A (8.8) [<25] {47} B (10.6) [<25] {77}
Southbound Right Turn A (6.1) [<25] {80} A (7.9) [<25] {110}
20: Cross Island Pkwy NB Ramp & Marshland Rd (un-signalized)
Eastbound Left Turn A (1.3) [<25] {36} A (1.4) [<25] {<25}
Northbound Left Turn B (10.8) [<25] {69} C (21.3) [31] {193}
Northbound Right Turn A (6.0) [<25] {94} A (7.0) [46] {218}
21: Palmetto Bay Rd & Bay Pines Rd (un-signalized)
Eastbound Left Turn No volumes observed E (40.7) [<25] {33}
Eastbound Right Turn B (14.3) [<25] {25} B (12.5) [<25] {31}
Northbound Left Turn A (9.0) [<25] {<25} A (7.1) [<25] {34}
22: Palmetto Bay Rd & Point Comfort Rd/Arrow Rd (signal)
Overall Intersection B (13.2) B (16.9)
Eastbound Approach C (33.3) [52] {191} C (32.0) [37] {175}
Westbound Approach B (18.8) [<25] {106} C (23.2) [56] {261}
Northbound Approach B (10.5) [29] {261} B (15.7) [92] {612}
Southbound Approach B (10.9) [94] {873} B (14.2) [67] {606}
23: Palmetto Bay Rd & Genesta St (un-signalized)
Westbound Approach C (17.1) [<25] {50} C (18.1) [<25] {52}
Southbound Left Turn A (3.2) [<25] {<25} B (13.2) [<25] {<25}
24: Palmetto Bay Rd & Palmetto Business Park Rd (un-signalized)
Westbound Approach C (18.0) [<25] {53} C (17.4) [<25] {53}
Southbound Left Turn A (4.0) [<25] {37} A (7.5) [<25] {<25}
C-5
Page 121 of 234
P A G E | C-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
25: Palmetto Bay Rd & Bow Cir (un -signalized)
Westbound Left Turn D (27.5) [<25] {<25} D (30.0) [<25] {35}
Westbound Right Turn A (8.4) [<25] {58} B (13.1) [<25] {68}
Southbound Left Turn A (3.6) [<25] {40} B (11.0) [<25] {26}
26: Palmetto Bay Rd & Archer Rd (un-signalized)
Westbound Left Turn D (30.6) [<25] {27} D (32.8) [<25] {39}
Westbound Right Turn A (8.8) [<25] {63} B (11.4) [<25] {75}
Southbound Left Turn A (4.3) [<25] {98} B (11.9) [<25] {<25}
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection B (16.0) B (17.6)
Eastbound Approach C (33.3) [<25] {110} D (41.8) [62] {248}
Westbound Approach D (37.1) [35] {151} C (29.4) [38] {149}
Northbound Approach A (9.7) [28] {214} B (13.3) [71] {508}
Southbound Approach B (15.4) [287] {1309} B (13.9) [99] {742}
28: Palmetto Bay Rd & Dunnagans Alley (un-signalized)
Westbound Left Turn F (184.7) [<25] {50} F (65.5) [<25] {75}
Westbound Right Turn A (9.1) [<25] {84} B (13.1) [<25] {110}
Southbound Left Turn B (10.4) [112] {512} B (12.5) [<25] {383}
29: Palmetto Bay Rd & William Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection E (37.0) F (51.8)
Eastbound Approach F (208.4) [615] {814} F (51.0) [285] {770}
Westbound Approach A (7.5) [<25] {263} F (168.3) [1635] {1658}
Northbound Approach A (4.2) [<25] {223} D (30.8) [228] {738}
Southbound Approach B (12.9) [194] {461} A (8.4) [85] {460}
C-6
Page 122 of 234
P A G E | D-1
APPENDIX D: TRAFFIC FORECASTING MEMORANDUM
Page 123 of 234
MEMORANDUM
Lochmueller Group (Lochmueller) was retained by the Town of Hilton Head Island to conduct an
independent study of the William Hilton Parkway (WH P) Gateway Corridor. This memorandum
summarizes the review of the existing Lowcountry Ar ea Transportation Study (LATS) Travel
Demand Model (TDM) and recommends future traffic gr owth at the William Hilton Parkway
Bridge connecting Hilton Head Island with the mainland. The future traffic growth estimation was
based on a thorough review of historic traffic volu mes, socio-economic trends for Jasper and
Beaufort Counties, and accommodation and restaurant tax revenues collected per year by the
Town of Hilton Head.
LATS TDM Evaluation
The Lowcountry TDM was updated in December 2021 wit h a new base year, 2019, and a new
horizon year, 2045. Lochmueller completed a thorough review of the TDM to determine its ability
to forecast traffic growth along WHP.
The detailed review of the LATS TDM revealed the following:
• The latest update was limited/minor in nature and d id not include any major model
changes.
• 2045 Horizon year roadway network did not include all future planned projects.
• Socio-economic (e.g., population, household, employ ment) growth for the horizon year
2045 was forecasted by simply extrapolating 2040 at tributes of the previous version of
the TDM.
• Socio-economic projections did not consider recent land-use plan updates from
municipalities within the TDM boundaries.
• The TDM update did not include a complete model re-estimation and re-calibration.
• The LATS Long-Range 2045 Transportation Plan forecasts 48,500 more future population
in Jasper and Beaufort Counties than incorporated into the TDM.
To: Shawn Colin, AICP (Town of Hilton Head)
Cc: Bryan McIlwee, PE (Town of Hilton Head)
Jim Iwanicki, PE (Town of Hilton Head)
From: Nate Nohren, PE, PTOE
Sharif Ullah, PE, PTP
Date: February 12, 2024
Subject: Independent Study of WHP Gateway Corridor
Traffic Forecasting Memorandum
Page 124 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 2 of 8
Based on these findings, Lochmueller staff determin ed the LATS TDM may not provide accurate
traffic forecasts for WHP. To that end, alternative methods of traffic forecasting were
investigated. First, key data indicators of traffic growth were researched.
Socio-Economic Trends for Hilton Head Island, Jasper County, and Beaufort
County
Hilton Head Island is located in Beaufort County. B eaufort and neighboring Jasper County
experienced significant growth over the last 20 yea rs. Table 1 shows population growth trends
for Beaufort and Jasper Counties and Hilton Head Is land based on the US Census. This data
reflects permanent residents.
Table 1: Population Trends 1
Geographic
Unit
Year Annual
Growth (%)
(2000 -2010)
Annual
Growth (%)
(2010 -2020) 2000 2010 2020
Beaufort
County
120,937 162,233 187,117 3.0 1.4
Jasper
County
20,678 24,777 28,791 1.8 1.5
Hilton
Head Island
33,862 37,099 37,661 0.9 0.2
As shown in Table 1 , both Beaufort and Jasper Counties experienced sig nificant population
growth since 2000. However, population growth was m uch slower between 2010 and 2020
compared to 2000 to 2010. Hilton Head Island experi enced a modest growth rate of 0.2% from
2010 and 2020.
Table 2 shows the total employment for Beaufort and Jasper Counties and Hilton Head Island for
2010 and 2020.
Page 125 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 3 of 8
Table 2: Total Employment Trend 1
Geographic
Unit
Year Annual
Growth (%)
(2010 -2020)
2010 2020
Beaufort
County 51,761 62,001 1.8
Jasper
County 6,522 9,819 4.2
Hilton Head
Island 21,346 21,854 0.2
As can be seen in Table 2 , both Jasper and Beaufort Counties experienced sig nificant growth in
jobs between 2010 and 2020. Overall job growth in H ilton Head Island was small and similar to
the island’s population growth rate.
Population Growth Projections for Beaufort and Jasper Counties
Population growth estimates are a key element in forecasting traffic growth for a region. For this
study, Lochmueller staff researched reliable population growth estimates for Beaufort and Jasper
counties. The State of South Carolina’s Revenue and Fiscal Affairs Office provides population
growth estimates for all counties within the state through 2035. Table 3 shows the population
projections for Beaufort and Jasper Counties for 2035 and the corresponding growth rates.
Table 3: Population Growth Projections 2
County
Year Annual
Growth
Rate (%) 2020 2035
Beaufort 187,691 204,374 0.56
Jasper 29,073 34,046 1
Total 216,764 238,420 0.6
Page 126 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 4 of 8
Historic Annual Average Daily Traffic Volume Trends at the WHP Bridge
Lochmueller staff obtained Annual Average Daily Tra ffic (AADT) volumes on WHP near the WHP
Bridge (Site ID #0035) from the South Carolina Department of Transportation’s Traffic Data Site 3.
Table 4 shows the AADT volumes by year. These volumes effe ctively represent the volume of
traffic entering and exiting Hilton Head Island via US 278.
As shown in Table 4 , there was a significant reduction in growth betwe en 2019 and 2020 and a
significant increase in growth between 2020 and 202 1. Such sudden changes were attributed to
COVID-19 pandemic-related restrictions. Overall tra ffic growth on WHP from 2010 to 2023 was
approximately 16.5%.
Table 4: AADT Volumes on WHP near the WHP Bridge
3
Year AADT Annual
Growth (%)
2010 49,600
2011 49,900 0.60%
2012 50,700 1.60%
2013 52,200 2.96%
2014 53,200 1.92%
2015 54,700 2.82%
2016 54,700 0.00%
2017 56,300 2.93%
2018 56,100 -0.36%
2019 57,100 1.78%
2020 51,400 -9.98%
2021 57,400 11.67%
2022 57,400 0.00%
2023 57,800 0.70%
Page 127 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 5 of 8
Short-Term Rental Permit and Tax Revenue Data
Lochmueller staff received information on the short -term rental units per year and the
accommodation (hotel) and restaurant tax revenues c ollected by the Town of Hilton Head. The
short-term rental unit information was available on ly for 2023. Thus, this information was not
used in statistical analysis. The accommodation and restaurant tax revenue information was
available from 2018 to 2023. Lochmueller staff eval uated the revenue data to test any relation
between revenues and the volume of traffic entering and exiting Hilton Head Island. These
measures are intended to represent the visitor popu lation as compared to permanent residents
reflected in the Census data. Table 5 shows the annual accommodation and restaurant tax
revenue information for the Town of Hilton Head Island.
Table 5: Annual Accommodation and Hospitality Tax (Source: Town of Hilton Head Island)
Year
Tax Revenue (2021 USD)
Accommodation
Tax
Hospitality
Tax
2018 $3,827,423 $7,419,881
2019 $3,964,475 $6,807,961
2020 $3,624,196 $6,598,684
2021 $5,561,900 $8,051,256
2022 $6,534,674 $9,213,533
2023 $6,260,297 $8,905,425
As shown in Table 5 , the tax revenues have increased significantly sin ce 2020 after a reduction
due to Covid-19 Pandemic-related impacts. These inc reases have outpaced traffic growth on
WHP entering/exiting the island and can be at least partially attributed to factors beyond the
number of visitors to the island, such as high rates of inflation in recent years.
Traffic Growth Estimation Using Available Data
Lochmueller staff performed regression analyses utilizing the preceding available socio-economic
and revenue information data as indicators of traffic on WHP at the WHP bridge. The regression
analyses considered AADT volumes as the dependent v ariable and evaluated whether different
independent variables (e.g., population, employment , tax revenue) had a statistically significant
influence on the AADT volumes.
In regression analysis, the coefficient of determination (R
2) and the P-values were used to identify
independent variables with significant impact on th e dependent variable. R 2 values explain to
what degree an independent variable (e.g., populati on) explains the variation of the dependent
variable (AADT). R2 values range from 0 to 1. An R 2 value of 0.7 indicates that 70% of the variation
in the output variable can be explained by the independent variable(s).
Page 128 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 6 of 8
The P-value is the probability that the observed di fference between the dependent and
independent variables is due to chance. Its value r anges from 0 to 1. A P-value close to 0 means
that any observed difference in the dependent varia ble is more likely due to the independent
variable (not by chance). For regression analysis w ith a 95% confidence interval, a P-value less
than 0.05 would represent a strong correlation betw een the dependent and independent
variables.
Table 6 shows the simple regression analysis (95% Confidence Interval) results in terms of R
2 and
P-values for various independent variables relative to the dependent variable (AADT).
Table 6: Simple Regression Analysis Results with Different Independent Variables
Independent Variable
Co-efficient of
Determination
(R 2)
P-Value
Total Population of Beaufort and
Jasper Counties 0.95 1.5E-08
Total Employment in Beaufort and
Jasper Counties 0.9 8.1E-07
Accommodation Tax 0.64 0.1
Hospitality Tax 0.37 0.28
As shown in Table 6, the total population and total employment in Beaufort and Jasper Counties
clearly influence the AADT volumes. P-values in both of these cases are very close to zero, which
confirms the differences in AADT are influenced by changes in population and employment
numbers in the two counties. On the other hand, there is no clear correlation between hospitality
tax and AADT and between accommodation tax and AADT.
Lochmueller staff also completed a more complex mul tiple regression analysis combining both
independent variables (population and employment). With the multiple regression analysis, the
adjusted R
2 value showed almost no improvement. Therefore, the simple regression analysis
using the total population of Beaufort and Jasper Counties was utilized to formulate an equation
for estimating AADT on WHP as a function of populat ion in the counties. Equation 1 shows the
regression equation for the AADT estimate.
Equation 1: Regression Equation for AADT Estimate
AADT = 0.262684*(Total Population of Beaufort and Jasper Counties) + 830
Page 129 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 7 of 8
Equation 1 was then used to forecast future traffic on WHP ba sed on anticipated population
growth. Lochmueller estimated the 2045 population of Beaufort and Jasper Counties utilizing the
following assumptions:
• Annual population growth in Hilton Head Island from 2020 to 2045 will be very small
(0.1%). As the population within Hilton Head Island is stable and available land for
development is very limited. Moreover, population growth in Hilton Head Island from
2010 to 2020 was only 0.2% per year.
• Annual population growth from 2020 and 2045 for the rest of Beaufort County and
Jasper County will be 0.6%, as suggested by the State of South Carolina’s Revenue and
Fiscal Affairs Office, referenced in Table 3 .
Based on the above-mentioned population growth assu mptions, Table 7 shows the projected
2045 population for the Beaufort and Jasper Counties.
Table 7: Projected Population
Geographic Unit
Projected
Annual
Growth
Rate
Population
2020 2045
Hilton Head Island 0.10% 37,661 38,614
Jasper County and
Beaufort County
(Excluding Hilton Head
Island)
0.60% 178,247 207,000
Total 215,908 245,614
As shown in Table 7 , the total population in 2045 for Beaufort and Jasper Counties was estimated
at 245,614. Applying Equation 1 , that population number would translate to 65,349 AADT on
WHP at the WHP Bridge.
Table 8 shows the estimated annual traffic growth rate fro m 2023 to 2045 based on the 2045
forecast of 65,425 compared to the 2023 traffic count.
Page 130 of 234
Independent Study of the WHP Gateway Corridor:
Traffic Forecasting Memorandum
February 12, 2024
Page 8 of 8
Table 8: Projected Traffic Growth Rate at the WHP Bridge
Year AADT
Annual
Growth
Rate (%)
2023 57,800 0.56
2045 65,349
Conclusion
Lochmueller determined that the LATS TDM may not be a reliable source of future traffic on WHP.
Through careful application of statistical analysis, an alternative method for forecasting traffic on
WHP was developed using the population of Beaufort and Jasper Counties as the key indicator.
Based on this method, traffic on WHP at the WHP Bridge is expected to increase by 0.56 percent
annually, resulting in an AADT forecast of 65,349 daily vehicles in 2045.
Lochmueller Group appreciates the opportunity to serve the Town of Hilton Head by performing
this independent analysis to determine the appropri ate annual background growth rate that
should be utilized for the overall corridor study. Should you have any questions regarding the
information shared within this technical memorandum , please do not hesitate to contact us at
nnohren@lochgroup.com or 217-821-8435.
Reference
1. U.S. Census Bureau (www.census.gov )
2. South Carolina Revenue and Fiscal Affairs Office. (www.rfa.sc.gov ).
3. South Carolina Department of Transportation Traffic Counts Website.
(www.scdot.org/travel/travel-trafficdata.aspx )
Page 131 of 234
P A G E | E-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
APPENDIX E: 2045 NO-BUILD TRAFFIC VOLUMES
Page 132 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2045 No Build Traffic Volumes
AM Peak Hour – Pg 1 of 6
1
2
3
4
5
7
8
6
9
11
12
10
84
2
5 18
493
731
12
32
263
994
28
Bluffton Pkwy
Buckingham
Plantation Dr
US 278
Buckingham
Plantation Dr
88
0
9 97
1226
70
0
51
9
2026
2
US 278
Salt Marsh Dr
1314
516
17
2083
3
US 278
Fording
Island Rd Ext
77
28
47 26
1265
2333
68
192
70
1798
40
US 278
Wildlife
Refuge
US 278
Crosstree Dr
US 278
Jenkins Rd
0
0
0 0
1837
00
0
2
2
3124
5
1 3
1818
3416
0
453098
36
6
1848
7
5
7
3136
1835
02
11
3123
3
US 278
Blue Heron
Point Rd
240
0
51
49
1612
2
2
0
6
176
2963
2
US 278
Squire Pope
Rd
14
79
144 63
1449
80137
49
137
49
2806
165
US 278
Spanish Wells
Rd
US 278
US 278
Old Wild
Horse Rd
23
1577
86
3020104
202
240 214
876
2189
163
328
174
1727
7
Gum Tree
Rd
Page 133 of 234
3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2045 No Build Traffic Volumes
AM Peak Hour – Pg 2 of 6
1
2
23
24
13
15
16
14
17
18
20
19
21
22
205
31
276 341
1077
226
51
0
286
1932
77
US 278
Jarvis Park Rd
23
23
1125
6
6
6
1895
6
US 278
Central Ave
US 278
Hatton Pl
US 278
Pembroke Dr
11 46
1143
121797
104 51
14
20 35
1076
37293
24
42
90
1845
273
US 278
Indigo Run Dr
126
77
242 188
973
3790
58
37
146
1601
627
422
2
0
Honey Horn Rd
Cross Island Pkwy SB
89
20880
66
142
138
Marshland Rd
Cross Island
Pkwy NB
Marshland Rd
Cross Island
Pkwy SB158
130
41
0
26
254
274
0
1938
7
1018
0
6
Bay Pines Rd
Palmetto Bay Rd
Arrow Rd
Palmetto Bay
Rd
1813
18 6
6842
6
Genesta St
Palmetto Bay
Rd
60
1632
252
135
12
43
50
760
38
130
17
156
6
6842
0
1791
28
Palmetto
Business Park DrPalmetto Bay Rd
Page 134 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2045 No Build Traffic Volumes
AM Peak Hour – Pg 3 of 6
25
26
28
27
29
6
6836
23
1752
45
Bow Cir
Palmetto Bay Rd
6
11853
26
1702
56
Archer Rd
Palmetto Bay Rd
98
1449
166
60
38
11062
767
28
52
19
52
Target Rd
Palmetto Bay
Rd
Dunnagans
Alley
Palmetto Bay
Rd
526
778
179 181
285
207
41
425
200
297
149
57
Greenwood Dr
Palmetto Bay
Rd
1472
139
7
11850
53
Page 135 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2045 No Build Traffic Volumes
PM Peak Hour – Pg 4 of 6
1
2
3
4
5
7
8
6
9
11
12
10
112
14
2 11
1044
2327
14
29
100
739
25
Bluffton Pkwy
Buckingham
Plantation Dr
138
41
76
51
2252
2457
45
23
106
1629
63
US 278
Buckingham
Plantation Dr
88
0
6 63
2239
320
0
45
27
1692
9
US 278
Salt Marsh Dr
US 278
Fording
Island Rd Ext
2311
1823
23
1716
27
US 278
Wildlife
Refuge
US 278
Crosstree Dr
US 278
Jenkins Rd
11
0
5 7
3394
2
2
0
7
5
2499
5
0
6
3364
5736
0
59
2482
34
11
3416
11
7
11
2530
3398
25
14
2502
9
US 278
Blue Heron
Point Rd
386
2
46 64
3039
2
2
28
2
251
2253
33
US 278
Squire Pope
Rd
37
88
70 95
2837
35
293
53
68
58
2113
130
US 278
Spanish Wells
Rd
US 278
US 278
Old Wild
Horse Rd
73
3094
11
2301121
207
274
369
1745
220253
234
313
141
1204
26
Gum Tree
Rd
Page 136 of 234
3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2045 No Build Traffic Volumes
PM Peak Hour – Pg 5 of 6
1
2
23
24
13
15
16
14
17
18
20
19
21
22
278
9
97
72
1993
5
63
9
11
128
1608
55
US 278
Jarvis Park Rd
6
24
1715
6
11
6
1468
6
US 278
Central Ave
US 278
Hatton Pl
US 278
Pembroke Dr
11 11
1734661473
6 58
30
16
31
1655
35357
39
42
64
1422
230
US 278
Indigo Run Dr
126
130
284
344
1547
5872
130
55
185
1301
539
449
45
17
Honey Horn Rd
Cross Island Pkwy SB
42
345285
161
54
162
Marshland Rd
Cross Island
Pkwy NB
Marshland Rd
Cross Island
Pkwy SB475
155
88
2
69
147
153
11
1486
21
1947
11
11
Bay Pines Rd
Palmetto Bay Rd
Arrow Rd
Palmetto Bay
Rd
1343
6 6
61737
5
Genesta St
Palmetto Bay
Rd
98
1201
198
371
41
43136
1521
86
76
33
105
11
61731
6
1343
6
Palmetto
Business Park RdPalmetto Bay Rd
Page 137 of 234
1
2 3 4
5
6 7 8
9 10 11 12
13 17
14 15 1618
19 20
22
21
29
24
2827
25
26
23
2045 No Build Traffic Volumes
PM Peak Hour – Pg 6 of 6
25
26
28
27
29
11
111726
11
1338
11
Bow Cir
Palmetto Bay Rd
11
111726
11
1338
11
Archer Rd
Palmetto Bay Rd
60
1225
64
126
50
88
126
1417
52
194
50
86
Target Rd
Palmetto Bay
Rd
Dunnagans
Alley
Palmetto Bay
Rd
Greenwood Dr
Palmetto Bay
Rd
1388
11 69
321526
11
547
754
119 433
392
13662
699
401
405
200
205
Page 138 of 234
P A G E | F-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
APPENDIX F: 2045 NO-BUILD TRAFFIC OPERATING CONDITI ONS (SYNCHRO)
Page 139 of 234
P A G E | F-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Table F-1. 2045 No Build Operating Conditions (Synchro)
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
1: Buckingham Plantation Dr & Bluffton Pkwy (signal)
Overall Intersection B (17.6) C (25.5)
Eastbound Approach B (15.1) [298] <0.54> B (16.0) [207] <0.50>
Westbound Approach C (25.4) [202] <0.38> D (36.7) [#496] <0.86>
Northbound Approach B (15.9) [37] <0.08> B (15.7) [30] <0.11>
Southbound Approach A (9.9) [m23] <0.18> A (6.1) [m21] <0.23>
2: Buckingham Plantation Dr/Moss Creek Dr & William Hilton Pkwy (signal)
Overall Intersection B (18.2) C (26.9)
Eastbound Approach B (16.9) [443] <0.64> B (17.1) [345] <0.75>
Westbound Approach B (17.9) [290] <0.51> C (28.1) [#644] <0.89>
Northbound Approach C (21.2) [98] <0.56> D (49.7) [m#76] <0.74>
Southbound Approach C (31.2) [70] <0.45> E (60.9) [#123] <0.88>
3: Salt Marsh Dr/Moss Creek Village & William Hilton Pkwy (un -signalized)
Eastbound Left Turn C (18. 9) [<25] <0.0 4> F (65.8) [33] <0.33>
Westbound Left Turn E (44.8) [<25] <0.08> D (34.9) [<25] <0.22>
Northbound Approach D (34.4) [33] <0.31> D (26.7) [30] <0.30>
Southbound Approach F (57.0) [88] <0.63> F ( $649.6) [273] <2.05>
4: Fording Island Rd Ext & William Hilton Pkwy (un -signalized)
Westbound Left Turn C (21.6) [<25] <0.02> C (17.0) [<25] <0.06>
Northbound Approach F ( $684.9) [115] <1.63> F ($1880.2) [225] <4.10>
5: Boat Landing Driveway/Wildlife Refuge Driveway & William Hilton Pkwy (un -signalized)
Eastbound Left Turn C (17.8) [<25] <0.01> F (67.3) [<25] <0.08>
Westbound Left Turn No volumes observed D (28.7) [<25] <0.01>
Northbound Approach F (50.7) [<25] <0.03> D (32.3) [<25] <0.09>
Southbound Approach No volumes observed F (74.9) [<25] <0.26>
6: Blue Heron Point Rd & William Hilton Pkwy (un -signalized)
Westbound Left Turn No volumes observed D (30.2) [<25] <0.01>
Northbound Approach F ($1763.6) [73] <2.35> F ($5024.3) [145] <8.33>
F-2
Page 140 of 234
P A G E | F-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
7: Crosstree Dr (Windmill Harbour) & William Hilton Pkwy (signal)
Overall Intersection E (67.8) F (92.1)
Eastbound Approach F (105.5) [#2262] <1.19> C (33.3) [#1547] <1.00>
Westbound Approach A (5.9) [320] <0.64> F (133.8) [ #2434 ] <1.26>
Northbound Approach B (14.6) [34] <0.39> E (77.5) [#106] <0.86>
Southbound Approach 0 (0.0) [<25] <0.01> 0 (0.0) [<25] <0.00>
8: Jenkins Rd & William Hilton Pkwy (un -signalized)
Eastbound Left Turn C (18.3) [<25] <0.03> F (91.5) [<25] <0.22>
Southbound Approach F ($1398.4) [65] <1.86> F (151.3) [73] <.69>
9: Chamberlin Dr/Squire Pope Rd & William Hilton Pkwy (signal)
Overall Intersection C (23.4) F (144.6)
Eastbound Approach B (15.2) [918] <0.81> B (12.6) [370] <0.91>
Westbound Approach C (31.1) [625] <0.74> F (233.2) [m#2394] <1.49>
Northbound Approach B (13.0) [<25] <0.02> E (70.6) [67] <0.29>
Southbound Approach E (69.0) [#286] <0.92> F (231.6) [#577] <1.46>
10: Old Wild Horse Rd & William Hilton Pkwy (un -signalized)
Southbound Approach D (26.7) [40] <0.36> F (77.9) [<25] <0.20>
11: Spanish Wells Rd/Wild Horse Rd & William Hilton Pkwy (signal)
Overall Intersection D (37.5) D (45.1)
Eastbound Approach D (38.7) [#1280] <1.02> C (20.5) [381] <0.89>
Westbound Approach C (24.0) [34 4] <0.91> D (45.2) [m909] <0.99>
Northbound Approach D (51.5) [214] <0.60> F (171.7) [#606] <1.35>
Southbound Approach F (94.1) [#306] <0.97> D (49.3) [168] <0.34>
12: Gumtree Rd & William Hilton Pkwy (signal)
Overall Intersection F (84.2) F (8 2.7 )
Eastbound Approach F (94.6) [~1146] <1.16> D (54.0) [#842] <0.99>
Westbound Approach D (43.1) [#39 0] <0.90> D ( 50.3 ) [ m5 94 ] <0. 99>
Northbound Approach F (113.6) [#372] <1.13> F (137.9) [#466] <1.29>
Southbound Approach F (119.0) [#473] <1.09> F (178.8) [#506] <1.33>
F-3
Page 141 of 234
P A G E | F-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
13: Jarvis Park Rd/Wilborn Rd & William Hilton Pkwy (signal)
Overall Intersection B (19.7) C (27.2)
Eastbound Approach B ( 15.9 ) [ m199 ] <0. 89> A (7. 2) [m262] <0. 77>
Westbound Approach B ( 11.8 ) [306] <0. 68> C (33.4) [#1335] < 0.99 >
Northbound Approach F (82.7) [136] <0.58> F (259.8) [#208] <1.33>
Southbound Approach D ( 49.4 ) [249] <0. 75> C (24.8) [100 ] < 0.65 >
14: Pembroke Dr/Museum St & William Hilton Pkwy (signal)
Overall Intersection C (27. 9) D (38.3)
Eastbound Approach B (15. 8) [#1252] <0.91> B ( 14.1 ) [351] <0.71>
Westbound Approach D (36.7) [681] <0.55> D (47.7) [1072] <0.89>
Northbound Approach E (73.6) [254] <0.76> F (86.1) [#355] <0.89>
Southbound Approach C (32.7) [74] <0.36> D (49.5) [93] <0.68>
15: Central Ave & William Hilton Pkwy (un -signalized)
Eastbound Left Turn B (11.4) [<25] <0.01> C (17.2) [<25] <0.02>
Westbound Left Turn C (18.7) [<25] <0.02> B (13.6) [<25] <0.01>
Northbound Right Turn C (21.0) [<25] <0.03> C (15.9) [<25] <0.04>
Southbound Right Turn B (13.8) [<25] <0.06> C (19.5) [<25] <0.03>
16: Hatton Pl/Merchant St & William Hilton Pkwy (un -signalized)
Northbound Right Turn C ( 20.2 ) [<25] <0. 05> C ( 18.4 ) [<25] <0. 21 >
Southbound Right Turn B ( 13.6 ) [<25] <0. 03> C ( 20.1 ) [<25] <0. 05>
17: Indigo Run Dr/Whooping Crane Way & William Hilton Pkwy (signal)
Overall Intersection B (18.0) D (36.4)
Eastbound Approach A (3.5) [<25] <0.79> B (16.9) [#297] <0.93>
Westbound Approach B (19.2) [407] <0.51> D (38.4) [#951] <0.92>
Northbound Approach E (62.2) [112] <0.52> E (70.5) [#245] <0.82>
Southbound Approach D (54.9) [178] <0.71> E (67.7) [212] <0.86>
18: Cross Island Pkwy SB Ramp/Gumtree Rd & Honey Horn Rd (un -signalized)
Eastbound Approach B ( 13.8 ) [<25] <0. 19 > B (13.8) [<25] <0.19>
19: Cross Island Pkwy SB Ramp & Marshland Rd (un -signalized)
Westbound Left Turn A (9. 2) [<25] <0.14> A (8.6) [<25] <0.17>
Southbound Left Turn C (19.7) [<25] <0.1> E (49.9) [58] <0.49>
Southbound Right Turn A (9.4) [<25] <0.05> B (14.1) [<25] <0.19>
F-4
Page 142 of 234
P A G E | F-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
20: Cross Island Pkwy NB Ramp & Marshland Rd (un -signalized)
Eastbound Left Turn A (8.3) [<25] <0.1 3> A (8.6) [<25] <0.06>
Northbound Left Turn C (16.2) [<25] <0.21> D (34.1) [160] <0.7 6>
Northbound Right Turn A (9.4) [<25] <0.08> B (10.6) [<25] <0.23>
21: Palmetto Bay Rd & Bay Pines Rd (un -signalized)
Eastbound Left Turn No volumes observed F ($454) [ 48 ] <0.7 5>
Eastbound Right Turn C (21.7) [<25] <0.03> C (16.5) [<25] <0.04>
Northbound Left Turn C (19.4) [<25] <0.03> B (14.5) [<25] <0.06>
22: Palmetto Bay Rd & Point Comfort Rd/Arrow Rd (signal)
Overall Intersection B (17.1) C (26.9)
Eastbound Approach D (46.0) [171] <0.71> C (24.5) [102] <0.35>
Westbound Approach C (23.8) [73] <0.44> E (55.3) [#376] <0.94>
Northbound Approach A (9.7) [136] <0.37> C (21.7) [443] <0.86>
Southbound Approach B (15.2) [670] <0.73> C (24.3) [434] <0.88>
23: Palmetto Bay Rd & Genesta St (un -signalized)
Westbound Approach E ( 45.4 ) [<25] <0.13> F ( 14 6[28 ] <0.37>
Southbound Left Turn B (10.0) [<25] <0.0 3> C (16.8) [<25] <0.02>
24: Palmetto Bay Rd & Palmetto Business Park Rd (un-signalized)
Westbound Approach E (47.3) [<25] <0.13> F (114.3) [33] <0.37>
Southbound Left Turn B (10.1) [<25] <0.04> C (16.7) [<25] <0.02>
25: Palmetto Bay Rd & Bow Cir (un -signalized)
Westbound Left Turn D (27.7) [<25] <0.04> F (54.8) [<25] <0.14>
Westbound Right Turn B (11.6) [<25] <0.01> C (19.0) [<25] <0.04>
Southbound Left Turn B (10.3) [<25] <0.07> C (16.7) [<25] <0.04>
26: Palmetto Bay Rd & Archer Rd (un -signalized)
Westbound Left Turn D (29.0) [<25] <0.07> F (54.8) [<25] <0.14>
Westbound Right Turn B (11.7) [<25] <0.01> C (19.0) [<25] <0.04>
Southbound Left Turn B (10.5) [<25] <0.0 9> C (16.7) [<25] <0.04>
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection B (10.8) B (18.7)
Eastbound Approach C (33.2) [81] <0.31> D (51.4) [241] <0.82>
Westbound Approach D (48.8) [152] <0.69> C (30.4) [115] <0.50>
Northbound Approach B (10.9) [240] <0.37> B (19.0) [585] <0.72>
Southbound Approach A (4.6) [149] <0.69> A (7.3) [233] <0.66>
F-5
Page 143 of 234
P A G E | F-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [95 th Queue Length, ft] <v/c ratio>
AM Peak Hour PM Peak Hour
28: Palmetto Bay Rd & Dunnagans Alley (un -signalized)
Westbound Left Turn D (33.5) [<25] <0.09> F (55.4) [<25] <0.33>
Westbound Right Turn B (12.0) [<25] <0.02> C (20.0) [<25] <0.24>
Southbound Left Turn B (11.5) [<25] <0.2 2> B (14.6) [<25] <0.03>
29: Palmetto Bay Rd & William Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection F (56.0) F (60.3)
Eastbound Approach F (83.3) [375] <1.04> F (117.9) [550] <1.16 >
Westbound Approach D (26.1) [200] <0.79> F (92.4) [425] <1.08>
Northbound Approach C (16.4) [125] <0.6 6> F (78.2) [525] < 1.07 >
Southbound Approach F (134.4) [ 650 ] <1.2 4> F (94.3) [675] <1.13>
# – 95 th Percentile volume exceeds capacity
$ – Delay more than 300 seconds
m – Upstream metering is in effect
F-6
Page 144 of 234
P A G E | G-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
APPENDIX G: 2045 NO-BUILD TRAFFIC OPERATING CONDITI ONS (VISSIM)
Page 145 of 234
P A G E | G-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Table G-1. 2045 No-Build Operating Conditions (VISSIM)
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
1: Buckingham Plantation Dr & Bluffton Pkwy (signal)
Overall Intersection C (22.3) B (15.9)
Eastbound Approach C (26.6) [123] {700} B (18.5) [43] {241}
Westbound Approach B (14.0) [<25] {168} B (14.4) [32] {218}
Northbound Approach B (14.1) [<25] {68} B (14.5) [<25] {53}
Southbound Approach A (6.6) [<25] {56} A (8.5) [<25] {83}
2: Buckingham Plantation Dr/Moss Creek Dr & William Hilton Pkwy (signal)
Overall Intersection E (74.1) B (18.6)
Eastbound Approach F (146.0) [1628] {1658} B (16.6) [86] {567}
Westbound Approach B (14.1) [37] {302} B (18.4) [86] {474}
Northbound Approach C (26.4) [25] {186} D (39.3) [<25] {91}
Southbound Approach D (35.8) [<25] {88} C (24.4) [<25] {119}
3: Salt Marsh Dr/Moss Creek Village & William Hilton Pkwy (un -signalized)
Eastbound Left Turn F (54.8) [1075] {1304} C (18.8) [<25] {55}
Westbound Left Turn F (4,646.8) [142] {214} B (12.4) [<25] {45}
Northbound Approach B (12.3) [<25] {63} A (7.4) [<25] {62}
Southbound Approach D (29.4) [49] {107} A (8.1) [<25] {77}
4: Fording Island Rd Ext & William Hilton Pkwy (un -signalized)
Westbound Left Turn F (3,675.2) [85] {146} C (19.0) [<25] {34}
Northbound Approach F (3,448.2) [171] {189} C (18.4) [<25] {43}
5: Boat Landing Driveway/Wildlife Refuge Driveway & William Hilton Pkwy (un -signalized)
Eastbound Left Turn C (20.9) [902] {1658} D (26.6) [<25] {<25}
Westbound Left Turn No volumes observed C (21.4) [<25] {<25}
Northbound Approach F (426.9) [<25] {38} C (20.6) [<25] {47}
Southbound Approach No volumes observed C (17.5) [<25] {42}
6: Blue Heron Point Rd & William Hilton Pkwy (un -signalized)
Westbound Left Turn No volumes observed F (131.6) [<25] {<25}
Northbound Approach F (2,505.2) [214] {351} E (49.9) [<25] {74}
7: Crosstree Dr (Windmill Harbour) & William Hilton Pkwy (signal)
Overall Intersection A (9.5) B (13.4)
Eastbound Approach B (11.3) [433] {1093} B (10.6) [216] {1092}
Westbound Approach A (5.3) [26] {601} A (6.0) [86] {913}
G-2
Page 146 of 234
P A G E | G-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
Northbound Approach D (41.6) [<25] {138} F (237.4) [193] {326}
Southbound Approach A (9.8) [<25] {<25} A (0.0) [<25] {<25}
8: Jenkins Rd & William Hilton Pkwy (un -signalized)
Eastbound Left Turn B (14.4) [<25] {<25} D (32.0) [<25] {33}
Southbound Approach D (29.2) [<25] {47} E (43.5) [<25] {62}
9: Chamberlin Dr/Squire Pope Rd & William Hilton Pkwy (signal)
Overall Intersection C (26.8) E (70.7)
Eastbound Approach D (38.4) [361] {1332} B (13.9) [235] {1106}
Westbound Approach A (8.4) [55] {700} F (128.0) [1018] {1383}
Northbound Approach C (21.2) [<25] {42} E (67.4) [<25] {73}
Southbound Approach B (19.2) [<25] {189} F (80.3) [228] {693}
10: Old Wild Horse Rd & William Hilton Pkwy (un -signalized)
Southbound Approach A (1.4) [<25] {26} A (8.0) [<25] {29}
11: Spanish Wells Rd/Wild Horse Rd & William Hilton Pkwy (signal)
Overall Intersection C (30.3) F (328.8)
Eastbound Approach C (25.2) [169] {787} B (15.1) [98] {668}
Westbound Approach B (15.5) [80] {365} F (637.7) [896] {989}
Northbound Approach E (63.1) [122] {407} F (510.5) [1241] {1288}
Southbound Approach F (147.4) [192] {319} D (49.1) [51] {243}
12: Gumtree Rd & William Hilton Pkwy (signal)
Overall Intersection D (51.9) E (76.0)
Eastbound Approach D (43.1) [838] {1562} D (50.4) [254] {711}
Westbound Approach C (31.2) [128] {375} E (76.3) [1203] {1623}
Northbound Approach D (38.8) [166] {334} F (92.7) [280] {356}
Southbound Approach F (143.1) [1039] {1452} F (121.3) [657] {1380}
13: Jarvis Park Rd/Wilborn Rd & William Hilton Pkwy (signal)
Overall Intersection C (22.3) C (33.4)
Eastbound Approach B (17.7) [169] {962} B (12.6) [51] {552}
Westbound Approach C (21.5) [106] {673} D (42.5) [907] {1289}
Northbound Approach E (67.4) [42] {178} F (281.4) [153] {297}
Southbound Approach D (36.9) [65] {225} C (25.8) [32] {153}
14: Pembroke Dr/Museum St & William Hilton Pkwy (signal)
Overall Intersection C (22.1) E (55.1)
Eastbound Approach B (17.8) [227] {1081} B (18.9) [99] {679}
G-3
Page 147 of 234
P A G E | G-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
Westbound Approach B (19.5) [72] {553} D (54.5) [998] {1279}
Northbound Approach D (52.8) [71] {260} F (260.2) [397] {719}
Southbound Approach C (31.1) [<25] {87} D (43.2) [<25] {114}
15: Central Ave & William Hilton Pkwy (un -signalized)
Eastbound Left Turn B (13.4) [<25] {<25} C (21.6) [87] {146}
Westbound Left Turn C (22.4) [<25] {25} C (21.8) [<25] {<25}
Northbound Right Turn C (16.2) [<25] {29} B (12.6) [<25] {31}
Southbound Right Turn B (12.3) [<25] {44} F (2,448.4) [87] {171}
16: Hatton Pl/Merchant St & William Hilton Pkwy (un -signalized)
Northbound Right Turn A (8.1) [<25] {<25} A (6.9) [<25] {64}
Southbound Right Turn B (11.0) [<25] {36} F (1,211.0) [123] {244}
17: Indigo Run Dr/Whooping Crane Way & William Hilton Pkwy (signal)
Overall Intersection C (24.5) E (66.7)
Eastbound Approach B (19.7) [107] {764} C (34.5) [115] {636}
Westbound Approach B (17.3) [53] {371} E (75.8) [1341] {1658}
Northbound Approach E (55.2) [32] {110} E (76.4) [65] {265}
Southbound Approach D (47.7) [57] {203} F (126.4) [327] {1023}
18: Cross Island Pkwy SB Ramp/Gumtree Rd & Honey Horn Rd (un -signalized)
Eastbound Approach A (9.7) [<25] {45} B (12.1) [<25] {72}
19: Cross Island Pkwy SB Ramp & Marshland Rd (un -signalized)
Westbound Left Turn A (4.5) [<25] {62} A (2.4) [<25] {67}
Southbound Left Turn A (9.8) [<25] {53} B (11.1) [<25] {79}
Southbound Right Turn A (6.1) [<25] {86} A (7.9) [<25] {112}
20: Cross Island Pkwy NB Ramp & Marshland Rd (un -signalized)
Eastbound Left Turn A (1.6) [<25] {49} A (1.5) [<25] {<25}
Northbound Left Turn B (11.9) [<25] {77} D (27.8) [46] {252}
Northbound Right Turn A (6.0) [<25] {102} A (8.0) [62] {277}
21: Palmetto Bay Rd & Bay Pines Rd (un -signalized)
Eastbound Left Turn No volumes observed E (48.5) [<25] {35}
Eastbound Right Turn C (15.6) [<25] {<25} B (13.9) [<25] {32}
Northbound Left Turn B (12.8) [<25] {<25} A (7.8) [<25] {31}
22: Palmetto Bay Rd & Point Comfort Rd/Arrow Rd (signal)
Overall Intersection B (14.0) B (18.2)
Eastbound Approach C (30.2) [51] {187} C (29.0) [38] {164}
G-4
Page 148 of 234
P A G E | G-1
Independent Study of William Hilton Parkway Gateway Corridor
TRAFFIC AND SAFETY OPERATIONS REPORT
Intersection & Movements LOS (Delay, sec) [Average Queue Length, ft] {Max Queue, ft}
AM Peak Hour PM Peak Hour
Westbound Approach B (17.3) [<25] {108} C (28.2) [79] {337}
Northbound Approach B (12.4) [38] {311} B (15.5) [94] {596}
Southbound Approach B (11.6) [91] {737} B (16.3) [90] {601}
23: Palmetto Bay Rd & Genesta St (un -signalized)
Westbound Approach E (41.7) [<25] {57} D (25.4) [<25] {53}
Southbound Left Turn A (5.5) [37] {255} A (8.8) [<25] {<25}
24: Palmetto Bay Rd & Palmetto Business Park Rd (un -signalized)
Westbound Approach F (65.1) [<25] {75} C (21.0) [<25] {59}
Southbound Left Turn A (5.7) [35] {176} B (12.8) [<25] {<25}
25: Palmetto Bay Rd & Bow Cir (un -signalized)
Westbound Left Turn F (69.4) [46] {98} E (40.7) [<25] {48}
Westbound Right Turn A (9.1) [59] {131} B (13.1) [<25] {81}
Southbound Left Turn C (16.2) [551] {1040} B (14.1) [<25] {67}
26: Palmetto Bay Rd & Archer Rd (un -signalized)
Westbound Left Turn F (1,234.0) [40] {69} D (31.8) [<25] {34}
Westbound Right Turn B (11.6) [62] {105} B (11.5) [<25] {70}
Southbound Left Turn C (16.2) [228] {469} B (12.0) [<25] {28}
27: Palmetto Bay Rd & Target Rd (signal)
Overall Intersection C (26.9) B (18.6)
Eastbound Approach C (26.5) [<25] {105} D (37.6) [62] {250}
Westbound Approach C (34.2) [32] {157} C (26.1) [38] {144}
Northbound Approach B (12.5) [39] {235} B (15.4) [83] {522}
Southbound Approach C (33.5) [1209] {1511} B (15.6) [129] {820}
28: Palmetto Bay Rd & Dunnagans Alley (un -signalized)
Westbound Left Turn F (872.0) [62] {148} F (87.7) [<25] {97}
Westbound Right Turn E (36.3) [88] {182} B (13.0) [30] {132}
Southbound Left Turn C (20.8) [258] {513} B (13.1) [<25] {416}
29: Palmetto Bay Rd & William Hilton Pkwy (Sea Pines Circle, RAB)
Overall Intersection F (60.5) F (81.8)
Eastbound Approach F (314.7) [808] {838} F (168.2) [805] {838}
Westbound Approach B (14.3) [56] {434} F (200.4) [1645] {1658}
Northbound Approach A (4.2) [<25] {207} F (61.1) [534] {794}
Southbound Approach C (34.4) [297] {461} A (8.2) [88] {460}
G-5
Page 149 of 234
P A G E | H-1
APPENDIX H: FOUR LANE VIABILITY REVIEW TECHNICAL MEMORANDUM ; SEISMIC STUDY
REVIEW; CURSORY REVIEW OF SOUTHERN BYPASS
Page 150 of 234
MEMO
Huntington Tower, 201 W Springfield Avenue, Suite 1012
Champaign, Illinois 61820
PHONE: 217.673.7633
To: Town of Hilton Head, South Carolina
From: Lochmueller Group
Date: May 3, 2024
Subject: Independent Study of the William Hilton Parkway Gat eway Corridor
Four Lane Viability Review Technical Memorandum – T ask 1.3.3
Lochmueller Group (Lochmueller) is preparing an ind ependent study that evaluates congestion and
mobility challenges along the William Hilton Parkwa y Gateway Corridor. As part of this independent
study, Lochmueller evaluated the viability of sever al strategies in order to determine if they should be
included or excluded from further consideration as part of this project. These items include the viabi lity of
maintaining four lanes along William Hilton Parkway (US 278) between Windmill Harbour and Squire Pope
Road; the implementation of a second bridge; modifi cations to the existing mass transit system;
implementation of a new ferry system; and the imple mentation of a facility usage fee. It should be not ed
that an in-depth detailed analysis of any of these items was excluded from the scope of work.
The intention of this memorandum is to provide the Town of Hilton Head with Lochmueller’s professional
opinion regarding the feasibility of William Hilton Parkway being able to remain a four lane facility within
areas between Moss Creek Drive and Squire Pope Road , if one or more of these strategies were
implemented.
Viability of Maintaining Four Lanes Between
Windmill Harbour and Squire Pope Road
Lochmueller evaluated the viability of maintaining four lanes between Windmill Harbour and Squire Pope
Road. Currently, the intersection of Squire Pope Ro ad and US 278 experiences significant congestion,
specifically during the PM peak hour. The westbound approach has failing conditions and queues which
extend 2,500 feet from Squire Pope past Spanish Wells. This congestion is expected to be exacerbated by
2045 with the forecasted growth.
Travel times were calculated using VISSIM, which is a microsimulation tool that accurately replicates
individual vehicles and their interactions within c omplex traffic streams, such as interchanges, freew ays,
and expressway corridors with signalized intersecti ons. A robust amount of data and field observations
were conducted to calibrate VISSIM to reproduce fie ld conditions.
The travel time results are provided in Table 1. As shown, it currently takes approximately 19 minute s to
travel along US 278 between Moss Creek Drive and Indig o Run Drive during the AM peak hour, and it
takes approximately 21 minutes to travel along US 278 b etween Indigo Run Drive and Moss Creek Drive
during the PM peak hour today.
US 278 between Moss Creek Drive and Indigo Run Drive i s approximately 8.2 miles. Based on the travel
times, the existing average speed along this corridor is 26 miles per hour (mph) during the AM peak hour
and 23 mph during the PM peak hour. This is well belo w the posted speed limits of 45 mph and 55 mph
along the corridor.
Page 151 of 234
May 3, 2024
Page 2
These travel times are expected to increase by appr oximately 36% during the AM peak hour and by
approximately 23% during the PM peak hour in the year 2045 with the anticipated background growth. It
is evident based on the travel times that the exist ing four-lane section already struggles to accommod ate
the 2023 traffic volumes, and the 2045 forecasted traffic v olumes would be expected to significantly
deteriorate operating conditions along the corridor .
TABLE 1. VISSIM 2023 EXISTING AND 2045 NO BUILD TRAVEL TIME RESULTS
Corridor
2023 Existing
Simulated travel
time (secs)
2045 No Build
Simulated travel
time (secs)
% Difference
AM PM AM PM AM PM
William Hilton Parkway between
Moss Creek and Indigo Run
EB 1157 619 1579 642 36.47% 3.72%
WB 572 1252 584 1544 2.10% 23.32%
A preliminary analysis was completed in an effort t o determine how much the 2023 existing and 2045 no
build traffic volumes would need to be reduced in o rder for the existing four-lane section to operate
acceptably. It was determined that the 2023 existing tr affic volumes would need to be reduced by
approximately 30% for the current four-lane configura tion to operate acceptably. Furthermore, based on
an annual growth rate of 0.56%, the 2045 traffic volumes w ould need to be reduced by approximately
40% for the current four-lane configuration to operat e acceptably.
Implementation of a Second Bridge
Lochmueller was asked to evaluate the implementatio n of a second bridge and/or point of access onto
Hilton Head Island from the mainland. It is Lochmue ller’s understanding that a second bridge or point of
access has been discussed locally to address conges tion along US 278. A new bridge could take up to
twenty years to come to fruition once all studies, planning, environmental, design, and construction i s
complete.
While there are clear benefits to providing a secon d bridge, such as redundancy, the operating conditi ons
along US 278 are already congested today. As previousl y stated, the 2023 existing traffic volumes would
need to be reduced by approximately 30% and the 2045 tr affic volumes would need to be reduced by
approximately 40% for the current four-lane configura tion to operate acceptably. Given the congestion
already experienced along this corridor today and t he time it would take to construct a second bridge, it is
our opinion that a six-lane section of US 278 onto Hil ton Head Island is needed independently of a second
bridge.
Modifications to Existing Transit System
Lochmueller evaluated whether modifications to the existing mass transit system and its services, or t he
implementation of a new mass transit system, could provide enough benefit to maintain the needed
levels of efficiency and operations of a four-lane section between Windmill Harbour and Squire Pope
Road.
Page 152 of 234
May 3, 2024
Page 3
Based on data provided by the Lowcountry Regional T ransportation Authority (LRTA), transit service in the
region has been on the decline. It should be noted that the transit service does show signs of rebound ing;
however, it remains to be seen what the new normal or equilibrium state may mean and if this is
sustainable and long lasting for passenger volumes as transit agencies struggle with driver shortages,
funding gaps and other operational challenges.
The following ridership data was provided from the LRTA:
• The Palmetto Breeze commuter bus’s yearly unlinked trips peaked in 2019 at 196,978
• Trips declined to 129,160 in 2021 (post pandemic)
• Trips increased by 4.45% to 134,916 in 2022 according to the Federal Transit Administration
(FTA) National Transit Database (NTD) data
The transit service in the region is fragmented by service area and type (commuter/worker,
worker/tourist) and serves different markets with l imited coordination. According to the LRTA, they
currently have 72,963 yearly unlinked trips or 201 unlinke d trips daily across all the routes that serve
Hilton Head, with 363 service days and one AM and PM t rip respectively. The Breeze Trolley, a seasonal
service had 34,600 unlinked trips (2023) across 143 service d ays or 242 trips per day with 18 daily runs
Sunday to Thursday and 20 runs on Friday and Saturday . The trolley runs April through Labor Day from 1
PM to 10 PM daily, with extended service to 11 PM Frida y and Saturday.
There is an on-demand van service countywide with t rips to Hilton Head. However, the ridership is
unknown, and a 24 hour prior reservation is needed to make a trip. The is also a Beach Parking shuttle
which operates 47 days per year from 10 AM to 4:30 PM on Friday, Saturday, Sunday and holidays from
Memorial Day to Labor Day, with 3,980 riders (2023).
The fixed route Breeze transit option, as currently structured, only largely addresses the employment side
to/from the island, and the trolley partially addre sses trips of visitors, residents and likely some workers
once they are on the island. The Breeze service doe s provide long distance routes. The on-island troll ey is
seasonal and has limited service hours. Overall, th ere is little coordination between the transit serv ice
types (commuter bus and trolley/shuttle), and there is service gap from Labor Day to April when the
trolley does not currently run.
Based upon Lochmueller’s evaluations, it appears tr ansit across all services currently only provides a
fraction of the total regional trip making to and f rom, and on, the island. In the future, transit would need
to be more robust in terms of service span (number of trips daily and days per year of service) and
coordinated to be most effective, with some sort of travel time advantage and way to address the last
mile distribution once passengers are on the island .
As described in the preceding sections of this memo randum, the 2023 existing traffic volumes would need
to be reduced by approximately 30% and the 2045 traffic volumes would need to be reduced by
approximately 40% for the current 4-lane configuratio n to operate acceptably. By comparison, in 2021,
the transit mode share was less than 1% in the regi on
1 , and would therefore have to grow exponentially
to be effective enough to reduce the need for six l anes along US 278 in the area under study.
1 https://datausa.io/profile/geo/hilton-head-island- bluffton-towns-beaufort-city-puma-sc#housing
Page 153 of 234
May 3, 2024
Page 4
Therefore, it is Lochmueller’s opinion that even if significant modifications were made to the existin g
Palmetto Breeze transit system, it would be highly unlikely these modifications alone could account fo r
enough trips and the mode share percentage needed t o sufficiently reduce the number of trips across th e
US 278 bridges, such that a four-lane facility could b e maintained.
Ferry System/Facility Usage Fee
In addition to expanding the existing mass transit system, Lochmueller evaluated whether the
implementation of a new ferry system or the impleme ntation of a facility usage fee, also commonly
known as congestion pricing, would provide enough b enefit to maintain the existing four-lane section
across the US 278 bridges and/or between Windmill Har bour and Squire Pope Road.
In regard to the implementation of a new ferry system, it is our understanding that during the
development of the 2045 Lowcountry Area Transportation Study (LATS) Long Range Transportation Plan
(LRTP), long-term transit considerations were discu ssed with the public and stakeholders. One of these
considerations included implementing high-speed fer ry services between Hilton Head Island and Beaufort
or Port Royal to the north, and Savannah or Tybee I sland to the south.
It should be noted, however, that no formal studies have been initiated by the LATS Policy Committee o r
other governing bodies to determine the feasibility of implementing and/or maintaining a high-speed
ferry system to/from Hilton Head Island. Therefore, it is reasonable to assume that a high speed ferry
system to/from Hilton Head Island would not be full y operational within the next ten to fifteen years.
If/when a new ferry system is implemented, it is highly unlikely the resulting reduction in traffic wo uld
allow for a four-lane section to be maintained alon g US 278 across the bridges and/or between Windmill
Harbour and Squire Pope Road (e.g., 30% reduction in 2023 traffic or 40% reduction in traffic by 2045),
given that the existing Palmetto Breeze transit system accounts for less than 1% of the region’s transi t
mode share today.
In regard to the implementation of a facility usage fee, it is our understanding that laws within the State
of South Carolina only allow tolls/fees to be imple mented on new roads within the State system. As suc h,
implementing facility usage fees on any of the existing roadways that are within the William Hilton
Parkway Gateway Corridor Study area would be prohib ited. It should be noted that, even if a facility usage
fee could be implemented, the fee would largely imp act commuters, not tourists, who enter and exit the
island for work, as the majority of traffic during the AM and PM peak hours is a result of commuter tr affic.
Therefore, even if a facility usage fee could be implemented, it is highly unlikely the resulting redu ction in
traffic would allow for a four-lane section to be maintained along US 278 across the bridges and/or
between Windmill Harbour and Squire Pope Road (e.g. , e.g., 30% reduction in 2023 traffic or 40%
reduction in traffic by 2045).
Page 154 of 234
May 3, 2024
Page 5
Conclusions
Lochmueller evaluated the viability of maintaining four lanes along William Hilton Parkway (US 278)
between Windmill Harbour and Squire Pope Road; the implementation of a second bridge; modifications
to the existing mass transit system; implementation of a new ferry system; and the implementation of a
facility usage fee. These evaluations were completed by Lochmueller to determine feasibility of
maintaining a four lane section along William Hilto n Parkway between Moss Creek Drive and Squire Pope
Road, if one or more of these strategies were imple mented.
As noted in this technical memorandum, the existing traffic volumes already create significant congest ion
along US 278, and the congestion is expected to be ex acerbated by 2045 with the forecasted background
growth. Based on a preliminary analysis, the existi ng traffic volumes would need to be reduced by
approximately 30%, and the 2045 traffic volumes would ne ed to be reduced by approximately 40%, in
order for a four-lane section to operate acceptably .
Based on Lochmueller’s evaluations, it was conclude d that it would be highly unlikely that modificatio ns
to the existing transit system alone could account for enough trips and the mode share percentage
needed to sufficiently reduce the number of trips a cross the US 278 bridges, such that a four-lane facil ity
could be maintained, given that the current transit mode share within the region is less than 1%, and
would therefore have to increase exponentially to r each the target goal. In addition, neither the
implementation of a new ferry system, nor the imple mentation of a facility usage fee (if there were a legal
way to implement said fee), would be able to signif icantly reduce the number of vehicles along US 278
within the study area to allow for a four-lane section to be maintained.
In order for the existing four-lane section to operate acceptably, the total reduction in vehicles fro m mass
transit, a new ferry system, and the implementation of a facility usage fee would need to be between 30 -
40%. While implementing the aforementioned types of t ransportation strategies would help slow future
traffic growth on US 278, it is Lochmueller’s opinion that even if all of these strategies are implement ed,
the reduction in vehicles would not reach 30%. Furth ermore, these strategies would not address the
structural issues associated with the existing brid ges over Mackay Creek and Skull Creek. Consequently , it
is Lochmueller’s opinion that these strategies shou ld not be considered as viable alternatives to be u sed
individually and/or collectively to solely address traffic congestion and mobility related concerns al ong US
278 within the project study area, that could allow a four-lane section to be maintained along US 278
within the study area.
In regard to implementing a second bridge and/or po int of access onto Hilton Head Island from the
mainland, while it is acknowledged there are clear benefits to providing a second bridge (e.g., redund ancy
during natural disasters), Lochmueller’s evaluation s show that operating conditions along US 278 are
already congested today. Given the congestion that is already experienced along this corridor today, t he
amount of traffic that would need to be removed fro m the existing traffic stream to be able to maintai n
four lanes across the bridge (i.e., 30% reduction in 2023 traffic or 40% reduction in traffic by 2045), and
the time it would take to construct a second bridge , it is our opinion that a six-lane section of US 278 onto
Hilton Head Island is needed independently of a sec ond bridge.
Page 155 of 234
MEMO
Huntington Tower, 201 W Springfield Avenue, Suite 1012
Champaign, Illinois 61820
PHONE: 217.673.7633
To: Town of Hilton Head Island, South Carolina
From: Lochmueller Group
Date: May 31, 2024
Subject: Independent Study of the William Hilton Parkway Gat eway Corridor
SCDOT Seismic Study Review Findings – Task 1.8
During the May 8, 2024, William Hilton Parkway Gateway C orridor Independent Review Advisory
Committee meeting, Lochmueller provided findings re lated Lochmueller’s cursory, high-level review the
US 278 Bridge Seismic Study prepared by the South Caro lina Department of Transportation (SCDOT) in
April of 2020. Lochmueller was asked to perform this cursory, high-level review of SCDOT’s Seismic Study
to offer a professional opinion regarding the feasi bility of seismically retrofitting and structurally
rehabilitating the existing US 278 bridges to allow fo r six travel lanes (three eastbound lanes and three
westbound lanes), rather than constructing the new six-lane bridge proposed by SCDOT. A copy of the
Seismic Study Review related slides that were prese nted during the 5/8 Committee meeting are attached
to this memorandum as Appendix A .
The SCDOT Seismic Study included an evaluation of o ptions to retrofit, widen, or replace the existing US
278 bridges onto Hilton Head Island, and provided info rmation to SCDOT to implement best replacement
strategies, as well as detailed Life Cycle Cost Ana lysis (LCCA) results, considering three Options:
• Option #1 – Construct a new eastbound bridge over Mackay Cre ek & Skull Creek; widen the
existing westbound bridge over Mackay Creek; and mo dify the existing Skull Creek bridges for
westbound movements.
• Option #2 – Construct a new eastbound bridge over Mackay Cre ek & Skull Creek; replace the
existing westbound bridge over Mackay Creek; and mo dify the existing Skull Creek bridges for
westbound movements.
• Option #3 – Construct a new six-lane bridge between Bluffton and Hilton Head Island, and then
remove all existing bridges across Mackay Creek and Skull Creek.
A copy of the LLCA prepared by SCDOT’s Design team is shown below:
Page 156 of 234
May 31, 2024
Page 2
It should be noted that Lochmueller’s efforts in re viewing the Seismic Study prepared by SCDOT were
limited to a cursory review of the SCDOT Design Tea m’s structural analysis related assumptions and
findings; LLCA results; their noted benefits/risks with Options 1/2/3; and if these efforts by SCDOT’s
Design Team appeared to following standard engineer ing practices. Lochmueller’s efforts did not inclu de
any detailed evaluations of the SCDOT Design Team’s design calculations or software modeling
inputs/results; any considerations for alternative Options to consider for inclusion in the Seismic St udy;
any roadway, bridge, or environmental design/review services; or coordination with SCDOT, their Design
Team, Beaufort County, Town of Hilton Head, and/or any other governing Agency or design consultant
associated with the US 278 project.
Key observations from Lochmueller’s review of the SCDOT Seismic Study are summarized below. Please
refer to Appendix A for additional information:
• The SCDOT Design Team’s structural analysis finding s; LCCA results; and noted benefits/risks with
Options 1/2/3 appear valid and appear to follow standa rd engineering practices.
• The LCCA results do not account for costs that woul d be required to improve seismic conditions
for Options 1 & 2. Therefore, true costs associated with Options 1 & 2 would be significantly
higher to implement, than what is shown in the LCCA table above.
• Options 1 & 2 would take approximately 2 years longer to construct vs Option 3. The
rehabilitated structures would still need to be rep laced at some point, and time required to do so
is not accounted for in this table.
• Existing bridge structures would be approximately 50 years old after improvements made by
Options 1 or 2, with rehab efforts likely to extend life of existing structures by approximately 25
to 35 years. By comparison, typical design life for Option 3 newly constructed bridges
approximately 75 to 100 years.
• Options 1 & 2 being pursued for use solely as tempora ry condition would require more than
$130M to construct initially (using 2020 costs), and these costs do not account for needed
Functional Evaluation Earthquake (FEE) seismic desi gn improvements. Depending upon when
remaining structures were replaced, the future/user /maintenance costs req’d over that time
would assuredly lead to higher overall cost than bu ilding new at outset.
• Options 1 & 2 would put maintenance/replacement sched ules of the structures on varying
timeframes, which would cause additional user disru ptions in the future.
• Existing structures under Options 1 & 2 would never m eet Safety Evaluation Earthquake (SEE)
seismic design requirements. New structures can be built to meet SEE seismic design
requirements.
• In summary, Lochmueller does not recommend rehabili tation and/or retrofit options being
pursued for this project, in lieu of constructing a new six-lane bridge connecting Bluffton and
Hilton Head Island.
Page 157 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Objective: Perform cursory, high-level review of seismic study and offer
professional opinion regarding feasibility of seismic retrofit & structural rehab
existing bridges vs. constructing new bridge
o PDF copy of SCDOT approved US 278 Bridge Seismic Study (dated April 2020) provided to
Lochmueller on 4/15/24.
o Study included evaluation of options to retrofit, widen, or replace the existing US 278 bridges
onto HHI, and provided information to SCDOT to implement best replacement strategy, as well
as detailed Life Cycle Costs Analysis (LCCA) results, considering following three Options:
Option #1 – Construct new EB bridge over Mackay Creek & Skull Creek; widen existing
WB bridge over Mackay Creek; modify existing Skull Creek bridges for WB movements.
Option #2 – Construct new EB bridge over Mackay Creek & Skull Creek; replace existing
WB bridge over Mackay; modify existing Skull Creek bridges for WB movements.
Option #3 – Construct new 6-lane bridge; remove all existing bridges
APPENDIX A
PAGE 1 OF 15
Page 158 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• With each Option, a new EB bridge will be constructed
o Designed to SCDOT standards to withstand seismic events
o Serve as a “lifeline” bridge in case of significant seismic event for Options 1 or 2
• Assumed Construction Sequence
o Options #1 or #2 :
New EB structure constructed wide enough to accommodate 4-Lanes, 2-Way traffic in
temporary condition & 6-Lanes in permanent condition.
All traffic moved to new EB structure, while demolition / seismic retrofits / structural
repairs & replacements take place on existing structures.
Traffic then moved in to final positions
If necessary, traffic can be returned to the 4-Lanes, 2-Way traffic pattern on EB structure
o Option #3 :
Entire new 6-Lane structure can constructed with traffic retained in existing patterns
APPENDIX A
PAGE 2 OF 15
Page 159 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
APPENDIX A
PAGE 3 OF 15
Page 160 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
APPENDIX A
PAGE 4 OF 15
Page 161 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
APPENDIX A
PAGE 5 OF 15
Page 162 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
APPENDIX A
PAGE 6 OF 15
Page 163 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
APPENDIX A
PAGE 7 OF 15
Page 164 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Assumptions/Findings Noted by SCDOT Design Team:
o All existing bridges designed and constructed prior to SCDOT’s implementation of seismic
analysis and detailing. Therefore, all existing bridges are considered inadequate when
compared to today’s seismic design standards .
o In order to model existing structures, SCDOT design team assumed minimum level of seismic
retrofits would be performed. Design team did not determine if existing structures could
withstand any seismic event without minimum retrofits being performed.
o SCDOT design team intended to evaluate the bridges for two seismic events as required by
SCDOT Seismic Design Specifications (SDS):
Functional Evaluation Earthquake (FEE) = lower magnitude earthquake event that has higher
chance of occurrence during life of the bridge.
Safety Evaluation Earthquake (SEE) = higher magnitude earthquake event that has lower
chance of occurrence during life of the bridge.
NOTE: US 278 Bridges assigned highest SCDOT SDS classification rating OC 1; therefore, must
meet FEE design thresholds at a minimum
APPENDIX A
PAGE 8 OF 15
Page 165 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Assumptions/Findings Noted by SCDOT Design Team (cont.):
o It was determined that soils around and below the existing bridge foundations and roadway
approaches can liquefy at ground accelerations just above the FEE event:
This liquefaction could cause bridges/roadways to settle, slide or collapse during and/or
after seismic event.
Design team recognized that mitigation for liquefaction (i.e., add’l foundations, deep soil
mixing, etc.) would likely exceed costs for new construction, and would greatly increase
environmental disturbance.
Design team therefore elected to limit structural improvements through seismic retrofits
to FEE level, w/ SCDOT concurrence.
New bridges can be constructed to meet SEE requirements; existing bridges only will be
able to attain FEE requirements at best.
APPENDIX A
PAGE 9 OF 15
Page 166 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Assumptions/Findings Noted by SCDOT Design Team (cont.):
o SCDOT Design team prepared LCCA, for Options 1/2/3, as shown below.
Costs are in 2020 dollars, assume annual inflation of 2% for future costs.
Construction costs developed from historical data, as well as correspondence w/ local
Contractors. Widening existing structures over water ~1.5 to 2 times more expensive than
new construction.
User Costs developed from SCDOT provided data, based on cost/lane/day.
Maintenance costs based on existing bridge details and assumed new bridges.
NOTE: LCCA costs only reflect rehabilitation related costs (e.g., widening, maintenance,
cosmetic improvements), and do not include retrofit related costs (e.g., seismic related
improvements). Therefore, true costs to attain FEE standards for Options 1 & 2 would be
significantly higher than those shown in the table below .
APPENDIX A
PAGE 10 OF 15
Page 167 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Assumptions/Findings Noted by SCDOT Design Team (cont.):
o SCDOT Design team evaluated benefits & risks of Options 1/2/3
APPENDIX A
PAGE 12 OF 15
Page 168 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Assumptions/Findings Noted by SCDOT Design Team (cont.):
o SCDOT Design team evaluated benefits & risks of Options 1/2/3 (cont.)
APPENDIX A
PAGE 13 OF 15
Page 169 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Observations by Lochmueller Group:
o SCDOT Design Team’s structural analysis findings; LCCA results; and noted benefits/risks
associated with Options 1/2/3 appear valid and appear to follow standard engineering practices.
o LCCA results do not account for costs that would be required to improve seismic conditions for
Options 1 & 2. Therefore, true costs associated with Options 1 & 2 would be significantly
higher to implement, than what is shown in the LCCA table above .
o Options 1 & 2 would take ~ 2 years longer to construct vs Option 3. The rehabilitated structures
would still need to be replaced at some point, and time required to do so is not accounted for
in this table.
APPENDIX A
PAGE 14 OF 15
Page 170 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Observations by Lochmueller Group (cont.):
o Existing bridge structures would be ~50 years old after improvements made by Options 1 or 2,
with rehab efforts likely to extend life of existing structures by ~25 to 35 years. By comparison,
typical design life for Option 3 newly constructed bridges ~ 75 to 100 years .
o Options 1 & 2 being pursued for use solely as temporary condition would require >$130M to
construct initially (using 2020 costs), and these costs do not account for needed FEE
improvements . Depending upon when remaining structures were replaced, the
future/user/maintenance costs req’d over that time would assuredly lead to higher overall cost
than building new at outset.
APPENDIX A
PAGE 15 OF 15
Page 171 of 234
SCDOT Seismic Study Review Findings (Task 1.8)
• Key Observations by Lochmueller Group (cont.):
o Options 1 & 2 would put maintenance/replacement schedules of the structures on varying
timeframes, which would cause additional user disruptions in the future .
o Existing structures under Options 1 & 2 would never meet SEE seismic design requirements .
New structures can be built to meet SEE seismic design requirements.
o In summary, Lochmueller does not recommend rehabilitation and/or retrofit options be pursued.
Page 172 of 234
MEMO
Huntington Tower, 201 W Springfield Avenue, Suite 1012
Champaign, Illinois 61820
PHONE: 217.673.7633
To: Town of Hilton Head Island, South Carolina
From: Lochmueller Group
Date: May 13, 2024
Subject: Independent Study of the William Hilton Parkway Gat eway Corridor
Response to Advisory Committee Desire to Fully Evaluate Southern Bypass Alternative
During the May 8, 2024, William Hilton Parkway Gateway C orridor Independent Review Advisory
Committee meeting, Lochmueller provided cursory, hi gh-level observations related to traffic, geometric ,
ROW, and environmental challenges associated with t he “Southern Bypass” alternative that has been
brought up by citizens and/or Committee members. T he primary purpose for sharing this information
with the Committee and others in attendance was to provide reasoning as to why Lochmueller did not
include this Southern Bypass alternative as one of the four alternatives that were thoroughly evaluate d as
a part of our independent study. A copy of the Sou thern Bypass related slides that were presented dur ing
the 5/8 Committee meeting are attached to this memora ndum as Appendix A .
As specified during the May 8 Committee meeting, Loc hmueller has been clear that our professional
opinion is that any iteration of a new terrain rout e along the south side of US 278 is not feasible due to
the many sensitive resources that would be impacted . However, the May 8 Committee meeting included
a passing voice vote that seemingly puts Lochmuelle r in the position of having to evaluate an alternat e
concept that still has considerable identified flaw s and only perpetuates a fallacious motive by some
members of the Committee. We contend that further e xploration and detailed evaluation of such a
concept only serves as an exercise in futility and would not expend the Town’s money prudently, as the
results will remain unchanged. Additionally, we can predict with certainty that South Carolina Departm ent
of Transportation (SCDOT) and the Federal Highway A dministration (FHWA) will outright reject such a
concept, regardless of its location south of US 278, b ecause such a premise fails to regard the basic NEP A
principles applied to projects of avoid, minimize, and mitigate. If the Town expands our scope to prov ide
an in-depth analysis regarding the viability of a s outhern bypass alternative, we want to be certain t he
following is clear:
1) The FHWA and SCDOT will not accept any version of a route that extends on new terrain creating
more direct impacts to the Stoney TCP and other Sec tion 4(f) resources.
2) Recommending the inclusion of the southern bypass a s part of SCDOTs recommended preferred
alternative has grave implications associated with the trajectory of the level of NEPA document
being prepared, if adopted by SCDOT. Currently, SCD OT is preparing an Environmental
Assessment (EA) for the project. An EA is prepared for projects where it is unknown whether
there are clear significant impacts to the natural or human environment, and typically culminates
with FHWA issuing a Finding of No Significant Impac t (FONSI). The FONSI is FHWA’s decision
document for the project that acknowledges the absence of any significant impacts to the
natural or human environment. However, at any point during the development of an EA, FHWA
can elevate the level of environmental documentatio n to an Environmental Impact Statement
Page 173 of 234
May 13, 2024
Page 2
(EIS) if they foresee the potential for significant impacts. EIS-level projects conclude with FHWA
issuing a Record of Decision (ROD), which is their acceptance of the preferred alternative and
identification of all mitigation measures to offset the significant impacts. If FHWA elevates this
project to an EIS, it is likely to require at least an additional two years to reach a ROD. Some of
this time is attributed to necessary backsteps in t he process to make the transition to the higher
level of document, but a majority of it resides wit h time needed to update / complete the
essential technical analyses that would be prompted by such an action in this case. A summary of
some major actions associated with the elevation to an EIS for this project is listed below.
• Publication of a Notice of Intent (NOI) in the Fede ral Register
• Scoping meeting with resource agencies
• Update alternatives analysis
• Update noise analysis
• Update environmental justice analysis / additional outreach
• Update ecological surveys and supplemental coordina tion with agencies
• Updating Section 106 process to reflect adverse effec ts to previously reviewed
resources (Stoney TCP) and new cultural resources ( Honey Horn Plantation)
• Amend the Section 106 Memorandum of Agreement (MOA) to account for mitigation
measures for new adverse effects
• Completion of an Individual Section 4(f) Evaluation for Stoney TCP, Park at 152 William
Hilton Parkway, and Honey Horn Plantation)
• Prepare a Draft EIS
• Prepare for and conduct another public hearing
• Prepare Final EIS / ROD
This is not intended to be an exclusive list of tasks needed for the transition to an EIS but
provides some insight on the breadth in task detail that will be required for such an endeavor.
Elevation to an EIS would also likely make the proj ect subject to the July 2020 regulations
promulgated by the Council on Environmental Quality (CEQ) regarding Update to the Regulations
Implementing the Procedural Provisions of the Natio nal Environmental Policy Act. Specifically,
Section 1501.10(b)(2) of 40 CFR which mandates the complet ion of EISs within two years
measured from NOI to ROD.
3) The requested analysis, if authorized by Town Counc il, is a deviation from our agreed upon scope
of work and will require additional funds. We have taken the liberty of outlining some cost
estimates to complete a full evaluation of the sout hern bypass to the same level as the other
four alternatives approved by the Committee. Plea
Text truncated. Open the original for the full document.
Source: Town of Hilton Head Island website. First collected Nov 14, 2026.