Public Works Committee minutes february 2021
City of Mauldin · Greenville County · meeting of Mar 5, 2021 · Minutes
Open the original document More from City of Mauldin
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Minutes
Public Works Committee
February 1, 2021
3rd committee meeting
Committee Members present: Jason Kraeling (Chair), Carol King, Michael Reynolds
Others present: Public Works Director Matt Fleahman via Zoom, City Administrator Brandon Madden
1. Call to Order- Chairman Kraeling
2. Public Comment- None
3. Reading and Approval of Minutes
a. Public Works Committee Meeting: January 4, 2021
Action: Councilman Reynolds made a motion to approve the minutes with Chairman Kraeling
seconding. Councilwoman King was not present at January’s meeting and did not vote.
Vote: The vote was unanimous (2-0).
4. Reports or Communications from City Officers
a. Public Works Director Matt Fleahman
i. Budget Review
The budget has 43% remaining. All divisions are under budget and doing extremely well.
Councilman Reynolds asked about the capital budget. All the equipment is ordered. The
department is waiting on the leaf vac and trash truck.
ii. Department of Transportation Cleaning State Roads
A work order has been submitted to DOT to clean the intersection of Laurens Road and East
Butler Road as per the request of Councilwoman Kuzniar. They have not cleaned the
Intersection yet. Mr. Fleahman will contact them again.
iii. Road Paving List Update
Bids were received for the GLDTC 574.01 Municipal Match Resurfacing Program on January 18,
2021. King Asphalt was the low bidder. The contract will be awarded to King Asphalt on
February 2nd after the expiration of the 15-day protest period. After analysis of the contract bid
pricing, it was determined that seven additional roads could be added to the contract for the
City of Mauldin. Also, after adding the additional roads, there was approximately $70k that is
available for removal and replacement of existing extruded curbing. Staff will provide a list of
the roads that have curbing to the GLDTC. Chairman Kraeling asked if the roads will be listed on
our website. Mr. Madden answered yes.
Councilman Reynolds asked when King Asphalt might begin. Mr. Fleahman said they are
meeting at County Square to talk about everything and will relay the message back to Council
when he has dates for paving. Councilman Reynolds said he wants to make sure the utilities are
contacted to make sure they do not have scheduled maintenance. Mr. Fleahman said he sent
the list to Greenville Water.
Chairman Kraeling asked if there would be signage showing this is the City of Mauldin’s paving
program and it is a good use of our citizens’ taxpayer dollars. Mr. Madden said yes.
5. Unfinished Business- There is no unfinished business.
6. New Business
a. Playground and Shelter Lighting- Councilperson Black presented a request to staff to explore
options for adding lighting to the playground and shelter area located on City Center Dr. so that
events in the evening (e.g., Beachin Fridays) where people gather at shelters have adequate
lighting. Staff requested a quote for the work that would be needed to install the additional lighting
The quoted cost is for 2 options at $8,407.42 and $11,620.50. This is an unbudgeted expense.
Chairman Kraeling asked if there was a time frame. Mr. Fleahman said it would take 3-4 days to
complete. Chairman Kraeling said there are kids that play on the playground after dark and he is in
favor of this from a safety standpoint. Councilwoman King thanked Councilman Black for
requesting this be put on the agenda. She is in favor of this as well and it just makes sense. Her
recommendation is to incorporate it in the upcoming budget. She does not like to do things outside
of the budget if possible. With Covid, there are not a lot of activities going on in the evening.
Chairman Kraeling asked about the electrical issues we have. Mr. Fleahman said historically, the
electrical work done at the cultural center has been direct bury of electrical lines. The practice
causes shortages. Right now, the area is very well lit up and all lights currently work except for two
poles. Chairman Kraeling asked if a temporary floodlight could be put back there to get some light
now. Mr. Fleahman answered yes. There are enough mains in the breaker box. He does agree
with budgetary concerns but did note that there are a lot of events coming up in the Spring. There
is a potential for having several events with no playground lighting.
Mr. Madden said there has been some cost savings on several of our capital projects, and he could
check with the Finance Director to see if this could be budgeted in the current budget.
Councilwoman King said it isn’t a lot of money, but she is a stickler about going outside of the
budget. Councilman Reynolds said if we could do what needs to be done all at once,
instead of piecemeal, that would be his preference.
Mr. Fleahman said we are addressing some other lighting issues at other parks. Councilman
Reynolds asked if we want kids on the playground when it is dark. Chairman Kraeling said they
would jump the fence. They are kids. Chairman Kraeling said he is also concerned about older kids
going there to hang out. They may be less likely to hang out if there are lights. We have had some
issues with vandalism. Councilwoman King said she is thinking about Beachin’ Fridays. It does get
dark before the band finishes. Councilman Reynolds said he would like Mr. Madden to talk with the
Finance Director to see if there is some extra money to use out of the current budget.
Councilwoman King thanked Mr. Fleahman for his comment that the cultural center is as bright as
He has ever seen it. She rode through there a couple of months ago and a couple of lights were out,
and a few days later they were back on again.
Mr. Madden will talk to the Finance Director. If there is money available, this item can be brought
back to committee next month.
b. Cely Construction Contract
Last month Council awarded the construction contract to Cely Constructions for the PW facility
renovations. The contract is now being brought to committee for vetting. The Construction
Manager at Risk will come back to Council if the price goes over the budgeted amount of $200,000.
City Administrator Madden said Cely understands where we are, the time frame, the reasons for
the project, and the budget.
Action: Councilwoman King made a motion to send this item to Council. Councilman Reynolds
seconded the motion.
Councilman Reynolds asked if the City Attorney has vetted the contract. Mr. Madden answered
yes.
Vote: The vote was unanimous (3-0).
7. Public Comment
Joel Ann Chandler asked about the lighting for the basketball goals at the Senior Center. There are a
lot of people that go out there at night and there is no lighting. Chairman Kraeling asked Mr.
Madden to evaluate that.
Councilwoman King asked if the field lights were on timers. Mr. Fleahman answered yes and they
can also be controlled by cell phones.
8. Committee Concerns
Councilwoman King asked about the brush and limb pickup and excess being dumped behind Jenkins
Street. She asked what the plan is to get that moved. Mr. Fleahman said we have a contract and
they are hauling stuff away almost every day. We are currently in discussions with Republic to
take our leaves. If we can get that done, the volume will be significantly reduced. Henson’s in
Simpsonville goes through periods where they have too much volume or their equipment breaks.
Joel Ann Chandler said the City could look into a commercial chipper.