1
Minutes
EPD Committee
Monday, September 14, 2020
6:00 p.m.
1st meeting
Meeting Location: City Hall Upstairs Conference Room
Members: Chairman Taft Matney, Committee members Diane Kuzniar
and Jason Kraeling. Community and Development Director Van
Broad and City Administrator Brandon Madden were also present .
1. Call to Order Chairman Taft Matney
2. Public Comment- None
3. Reading and Approval of Minutes
a. EPD Committee Meeting: July 6, 2020
b. Action: Councilwoman Kuzniar made a motion to approve the minutes with
Councilman Kraeling seconding.
Vote: The vote was unanimous (3-0).
4. Reports or Communications from City Officers
a. Department Reports
Community Development Director Van Broad
Budget Review- The budget looks good. There
should be some significant economic development
announcements soon.
Grant Funding Phase II & III Lobby- This is a report, but Council does need to act on a portion of
this. In the original 2009 conceptual drawing and design of the auditorium renovation, there
was a plan for the lobby. Following parts of this plan will allow for:
1. Better use of the entrance
2. Easier access to the auditorium
3. Multiple entry points for the auditorium
4. Less interruption during a performance
5. New rentable options
2
Currently, when theater productions and invited traveling productions perform at the center,
audiences’ line up in the hallway for access. This creates bottleneck entry into the main door of
the auditorium. This door is right beside the stage and entry and exiting during productions for
bathroom and other necessities makes viewing for audience members challenging. With the
help of John DeRieux of Momentum construction, staff set out to configure the best and most
practical use of an expanded lobby and plaza. People will be able to gather in a plaza when
the cultural center has events.
The new Lobby will contain:
1. Handicap accessible bathrooms
2. Warming kitchen
3. Loading patio for catering
4. New egress and ingress into the Lobby and Auditorium
5. New Plaza as an extension of the lobby waiting area will also serve as:
a. Reception leasing space
b. Extended area for patrons to relax
c. Overflow crowds
d. Entertaining venue for small productions and private gatherings
In the current budget, the lobby renovation is part of the Council approved 10-year Capital
Improvement Program (CIP). With enough funding to commit to the Phase I portion of the
lobby, staff plans to seek additional partners for phase II and III by submitting a grant requests
to SCPRT for funding in the amount of $200K. These grants will be matched by the funding
included in the City’s CIP. Additionally, staff will seek private donations for opportunities to
name portions of the lobby and other areas in the center.
Phase II will contain most of what is noted in the new lobby plan and phase III will contain:
1. Complete fix of all window repairs
2. Renovate and relocate bathrooms beside auditorium
3. New ticket booth
4. Repair any and all ceiling drywall maintenance
5. Finish and complete sheetrock and painting green room
6. New awnings over front windows and others and lighting
An RFQ, (request for qualifications) will be submitted in order to solicit a CMAR (construction
Manager at Risk) to complete phase II and phase III of the lobby renovation. The Construction
Manager at Risk (CMAR) is a delivery method which entails a commitment by the Construction
Manager (CM) to deliver the project within a Guaranteed Maximum Price.
Preliminary Pricing:
1. Phase II - $388K
2. Phase III - $120K
3. Contingency Awnings and lighting - $50K
4. Total all projects - $558
3
The probability of completion and success of this project is based on the following:
1. Success and completion of Auditorium renovation under budget
2. Success of grant funding from previous projects
3. Solicitation by SCPRT to request funding for the next phase
A grant from SCPRT for this project will be discussed in the Finance Committee meeting tonight.
The recommendation is to revise the plan to a plaza plan, which staff believes is a better use.
Councilwoman Kuzniar asked about a timeline. Mr. Broad answered Phase 1 funding is in place
and work can start soon. He would like to get the other funding started for the other work.
5. Unfinished Business- None
6. New Business Chairman Taft Matney
Action: Councilwoman Kuzniar made a motion to move into executive session for all the
matters stated below. Councilman Kraeling seconded the motion.
Vote: The vote was unanimous (3-0).
a. Motion to enter into Executive Session for a personnel matter as allowed by State
Statute Section 30-4-70 a (1)
b. Motion to enter into Executive Session for consideration of an economic matter
related to Project Bosa and Project Legacy as allowed by State Statute Section
30-4-70 (a)(5)
c. Possible action on items discussed in executive session
Chairman Matney reconvened the meeting. Councilwoman Kuzniar reported no action
or votes were taken.
Action: Councilwoman Kuzniar made a motion to forward an agreement for Project Bosa
to Council. Councilman Kraeling seconded the motion.
Vote: The vote was unanimous (3-0).
7. Public Comment- None
8. Committee Concerns
Chairman Matney commented that he had received some public comment and he was
concerned as well on the progress that was being made on one of the resolutions passed
in July. He has received a status report and feels more comfortable now with what the City
is currently working on. Council is taking this issue very seriously.
9. Adjourn- Chairman Matney adjourned the meeting.
Respectfully Submitted
Cindy Miller
Municipal Clerk
4