Edgefield County Planning
Commission
County Council Chambers
February 12, 2026
Work Session 5:00 PM
Meeting 6:00 PM
The next Planning Commission Meeting is scheduled for March 12, 2026
Edgefield County Planning Commission
Work Session Agenda
County Council Chambers
February 12, 2026
5:00 PM
This agenda may be modified at any time prior to or during the meeting described herein.
The meeting may begin after the advertised start time if a reasonable adjustment to the
advertised start time is needed for any reason.
I. Call to Order
II. Guest Speakers
III. Old Business
a) Review “Restrictions on Land Disturbance Activity for Major Residential
Subdivisions” requested as an amendment to the Tree Preservation
Ordinance being presented to County Council for consideration.
b) Review corrections to proposed Data and Crypto Mining Centers
ordinance.
IV. New Business
a) Harmoni Towers AssetCo. LLC, is proposing the installation of a 315ft
guyed tower and associated antenna, located at the corner of Luke Bridge
Rd and Hyw 191 in Johnston. AT&T is looking to provide/enhance their
network and to provide improved cellular data and coverage.
Harmoni Towers AssetCo. LLC and AT&T are seeking a Conditional Use
Permit for the telecommunication Towers based on the criteria and the
general provisions outlined in Section 24-75- Communication Towers and
Antennas of the Edgefield County Ordinance.
3
V. Adjourn
To watch the Planning Commission Work Session live: Subscribe to our YouTube Account –
Edgefield County Government. You can be notified of upcoming live streams.
The next Planning Commission Meeting is scheduled for March 12, 2026. The Planning
Commission is scheduled to meet on the second Thursday of each month at 5:00 p.m. for a
work session and at 6:00 p.m. for the meeting at the Edgefield County Council Chambers,
located at 225 Jeter St., Edgefield, SC. These meetings are subject to cancellation or
change without prior notice. The public will be notified of any cancellation or change.
Individuals requiring special assistance or a sign interpreter to participate in the meeting are
asked to notify the Building & Planning Department 48 hours before the meeting at (803)
637-4073. Any questions regarding the Planning Commission should be directed to the
County’s Planner, April Morgan Amorgan@edgefieldcounty.sc.gov
4
Proposed Data and Crypto Mining Center Ordinance -
Draft
Recommended to first amend Section 24-31 (Land Use Table) to allow data centers in ID(Industrial)
zoned areas of Edgefield County and subject to certain conditional regulations.
Potential Conditional Use Regulations to be added to Chapter 24 in addition to being restricted to
Industrial areas only.
Defined Terms of Edgefield County
Closed loop system: A system that constantly reuses and recycles an initial load of water within its
operation, significantly reducing the draw on external water sources and minimizing wastewater
discharge. A closed loop system shall not use evaporative cooling, and may consist of methods including,
but not limited to, air-cooled (dry) cooling, rear door heat exchanger cooling, hybrid dry economizer
cooling, direct-to-chip cooling, or immersion cooling.
Data center: A physical room, building, or facility that houses infrastructure for building, running,
delivering, or transmitting technological applications and services, or for storing and managing the data
associated with those technological equipment, applications, or services.
Data Center, Campus: A data center campus shall include a singular development that has more than
one (1) data center with a total development area of a minimum of 500,000 square feet.
Load: The total power consumed by servers, storage, cooling, ventilation, generators, and other
networking devices that operate within a data center site.
Megawatt (MW): The unit of measurement for electricity that is equivalent to one million watts. This is
used to measure the total power consumption of data centers.
Substations: An electric system facility that converts higher voltages to lower voltages within or
separate from a data center to generate sufficient power at maximum efficiency; can operate
independently for dedicated site once directly connected to transmission line.
Square footage, data centers: The square footage of a data center shall include the total square footage
of each floor in the data center development, the square footage of any supporting uses, and the square
footage of any additional exterior equipment, such as substations, electrical yards, mechanical yards,
and any other exposed equipment, located within property boundaries
Crypto Mining A crypto mining center (or farm) is a specialized, industrial-scale facility containing a large
number of high-powered computers—usually Application-Specific Integrated Circuits (ASICs) or
powerful GPUs—dedicated solely to validating blockchain transactions and generating new
cryptocurrency units, such as Bitcoin. These centers operate 24/7, requiring significant, constant
5
electricity for processing and intense cooling systems. Its purpose is primarily to solve complex
cryptographic algorithms (Proof of Work) to earn cryptocurrency rewards.
A. Permitted location
1. Data centers shall only be permitted in ID (Industrial Zoned) areas and shall be
specifically forbidden in un-zoned portions of the unincorporated areas of the
County.
2. No Data Center shall be permitted within 1000 feet of a single or multi-family
residence.
3. Data centers and Campus data centers shall provide a 20-foot-wide landscaped
buffer. It shall be located around the data center development, and may be within
the 100-foot transitional buffer. A minimum of one canopy tree shall be planted
for every 30 feet of property frontage if the subject site abuts publicly accessible
right-of-way or non-industrially zoned properties. These improvements may be
located within the required 100-foot transitional buffer described in (Sec. 27-
4.2.64 (B)5) if applicable
4. Distance shall be measured from the edge of any building, substation, drive,
street, parking lot, structure or improvement to the nearest property line.
B. Architectural and landscaping design requirements
1. Where visible from a publicly accessible road or right-of-way, a Medium, Major, or
Campus data center shall have a minimum of thirty (30) percent of the width of the
front façade of any buildings at the ground level consist of fenestration. Decorative
windows, architecturally glazed windows and painted or applied decorative murals
shall be permitted to count towards fenestration requirements after ten percent (10%).
a) A mural shall be classified as a very large image, such as a painting, applied
directly to a wall. Murals are signs that promote public art and shall not used for
advertising.
2. A minimum of ten percent (10%) of the width of side and rear facades shall
incorporate decorative windows or architecturally glazed windows.
3. The following materials shall not be utilized on the building façade: aluminum
siding; corrugated steel; vinyl siding; plywood; pressed wood products; synthetic
stucco; or unfinished concrete block.
6
4. All data centers shall have unified landscape and architectural elements.
C. Operation requirements.
1. Substations, electrical yards, mechanical yards, and any other exposed equipment
shall not be located between the building and a publicly accessible road or right-
of-way and shall be screened from any adjacent publicly accessible street, private
street, trail, or park.
2. All lighting other than street and pedestrian scale lighting shall have “Dark Sky”
design. There shall be no spillover from the fixture onto surrounding properties,
including the street. All lights and poles shall have a permanent black finish.
3. All cooling and ventilation equipment within property boundaries shall operate
on a closed-loop system.
4. All cooling, ventilation, and other external equipment used to operate the facility
shall not be located between building and publicly accessible rights-of-way,
unless located on the rooftop of any data center development or building within
property boundaries.
5. Substations associated with the operation of a data centers shall be subject to the
following requirements:
a) The substation shall be at least fifty (50) feet from the public right-of-way.
b) The substation shall be screened with a minimum eight (8) foot tall wall from
any adjoining property or publicly accessible street.
c) The substation shall not involve the storage of vehicles or service equipment.
Generator Maintenance requirements.
1. Any generators on the property shall comply with U.S. Environmental
Protection Agency (EPA) New Source Performance Standards (NSPS) of at least
Tier 4 emission standards.
a) Testing for these generators shall not exceed 10 hours per month.
b) Testing for these generators shall only occur between the hours of 9:00
a.m. and 5:00 p.m.
c) Generators shall be enclosed by a sound attenuation for noise reduction
and to reduce pollution.
2. Except for generator testing or commissioning activities, generator use is
limited to backup/emergency use only.
D. Application requirements.
1. All applications for a data center shall, in addition to any other application
requirements of this code, provide the following information:
a) Applicants shall provide a letter of intent from the relevant utility provider(s),
confirming that preliminary coordination has occurred and that service to the
proposed facility is technically feasible subject to final engineering review.
b) Noise Impact Assessment: A Noise Impact Assessment shall be required as
part of the permitting process for any proposed data center development and
assessed at a distance of 500 feet from the data center development. The Noise
Impact Assessment shall:
7
i. Define the scope of the assessment, including the geographic area, the
noise sources to be studied, and the specific objectives of the assessment
for the proposed development.
ii. Measure pre-operation ambient noise, or the existing background noise
before any server equipment is installed, and provide acoustic mitigation
strategies if noise level is proposed to exceed 60 dB during any hours of
the day or night once equipment for data center development is in
operation.
c) Water Consumption and Sustainability Plan: A Water Consumption and
Sustainability Plan shall address conservation and scarcity, outlining the total
water requirement of the data center, including cooling needs, and any strategies
to reduce or mitigate excessive water usage. The plan shall demonstrate that the
water usage shall not significantly strain the County’s water supply.
d) Energy Consumption and Sustainability Plan: An Energy Consumption Sustainability
Plan shall contain the estimated energy load before construction and the daily
operational load once constructed. This assessment shall outline:
i. Estimates of peak electricity demand and strategies for mitigating
strain on local power infrastructure
ii. Proposed improvements or alternatives to minimize the need for
additional transmission lines and the designated power provider
iii. The use of sustainable alternatives for on-site water or power
generation, such as solar panels, rooftop cisterns, small-scale wind
turbines, or other renewable energy sources which shall offset at least
10% of total power or water usage.
iv. A decommissioning plan, in the event data infrastructure is not sold or
transferred, for recycling all on-site electronic infrastructure through
certified recyclers that follow Responsible Recycling (R2) Standard
for Electronics Recyclers and/or e-Stewards® Standard for
Responsible Recycling and Reuse of Electronic Equipment. An
approved decommissioning plan shall be provided to the Planning
Director for county records.
e. Transmission Line Impact Assessment: A Transmission Line Impact Assessment shall
identify the need for new or upgraded transmission lines to meet the data center’s
electricity requirements. This assessment shall include the potential environmental
impact on public land, including tree removal from county-owned land and rights-of-
way. This plan shall also include information on the planned substation’s location and
shall show the screening mechanism(s), which shall include a minimum of an eight (8)
foot tall decorative brick wall if potentially visible by the public.
8
f. Before final approval by Edgefield County all stormwater and environmental approvals
from the South Carolina Department of Environmental Services will have to be
submitted to the Planning Director.
2. Additional Information: Any additional information requested by Edgefield County’s Planning
Department shall be submitted before the application is deemed complete.
3. The owner and/or operator is required to submit an annual compliance report that details
any changes to and continuation of all assessments submitted with an application
demonstrating compliance and monitoring of all applications requirements and conditions of
zoning to the County’s Planning Director no later than the first of January of each year.
4. The burden of showing compliance with supplemental requirements and/or conditions of
zoning is on the applicant and/or owner of the property or use.
A. Decommissioning
Upon the decommissioning of a Data or Crypto Mining Center, a detailed, documented
approval from any and all applicable regulatory authority, shall be provided to the
Edgefield County Planning Director for review and county record.
9
Memorandum
To: Edgefield County Planning Commission
From: April Morgan, Edgefield County Planner
Date: February 12, 2026
Re: Land Development Application (Telecommunication Tower)
Applicant: Harmoni Towers AssetCo. LLC
Property Owner: Stone Mountain Property Holdings LLC
Property Address:
(or) Location: Corner of Luke Bridge & Highway 191
Parcel ID: 192-00-00-072-000
Property Size: 4.32 acre
Zoning: UN-Zoned
Proposed Use: Commercial
Sewer/Septic: NA
Water: NA
Land Development Description
Harmoni Towers AssetCo. LLC, is proposing the installation of a 315ft guyed tower
and associated antenna and equipment. AT&T is looking to provide/enhance their
network and to provide improved cellular data and coverage. Harmoni Towers
AssetCo. LLC. and AT&T are seeking a Conditional Use Permit for the
telecommunication Towers based on the criteria and the general provisions outlined
in Section 24-75- Communication Towers and Antennas of the Edgefield County
Ordinance (SEE BELOW).
Compliance with County Land Development Ordinances
• Permitted Use in Zoning District -Conditionally Permitted
• Application process for Land Development -Completed
10
Compliance with County Comprehensive Plan
Rural Agricultural
Farming / General Development,
Large Lot Single Family Residential,
Light Industrial
Commercial uses
Heavy industry,
Small Lot
Residential
Approval by Other Regulatory Entities
• DHEC Storm Water / Sediment Control Pending
• DHEC Waste Water Control NA
11
• ECWSA Tap Approval NA
• Electric Utility Pending
• SCDOT Encroachment Pending
Communication Tower Ordinance
Article III. – Conditional Use
The regulations contained in this article are intended to minimize the impact and improve the
siting of uses, buildings, and projects whose design and/or operational characteristics could
adversely affect surrounding property and environmental conditions. To this end, standards and
criteria over and above those set forth elsewhere in this chapter are imposed herein on all
conditional uses listed on table 1 in
Sec. 24-75. - Communication towers and antennas.
(a) Telecommunication facilities should be located so as to minimize adverse, aesthetic and
visual impacts on the land, property, buildings, and other facilities where wireless
communication devices are considered. New telecommunications facilities, towers, or antennas
shall adhere to the following regulations.
(b) Prior to approval of any application for a permit for a new telecommunication facility a
public hearing shall be held by the county planning commission, notice which shall be published
in the county no less than ten calendar days prior to the hearing. Also ten days prior to the public
hearing this notice will be given to all landowners within 500 feet of the property.
(c) After the public hearing and formal consideration of the application, the county planning
commission may determine in writing the approval, approval with conditions, or denial of a
permit. The planning commission can deny the location and placement of a telecommunication
facility if it is a substantial detriment to the surrounding area.
(d) Definitions:
Applicant means any wireless service provider or agent submitting an application for a permit for
a telecommunications facility.
Fall zone means the maximum area (the furthest distance from the tower base) in which a
telecommunications facility will collapse in the event of a failure, usually less than the total
height of the structure. This zone must be defined by a professional civil or structural engineer
licensed in the state.
FCC means the Federal Communications Commission, or its duly designated and authorized
successor agency.
Height means, when referring to a tower or other structure, the distance measured from the pre-
existing grade level to the highest point on the tower or structure, even if said highest point is an
antenna or lightning protection device.
12
Telecommunications means the transmission and/or reception of audio, video, data, and other
information by wire, radio frequency, light, and other electronic or electromagnetic systems.
Tower means any structure designed primarily to support an antenna for receiving and/or
transmitting a wireless signal. A "freestanding tower" shall mean a monopole or self-supporting
tower. A "guyed tower" shall mean a tower supported and stabilized through the use of guy
wires.
(e)
(1) All new towers shall be designed to accommodate additional antennas equal in number to the
applicant's present and future requirements.
(2) All applicable safety code requirements shall be met.
(3) Towers or antennas shall not be painted or illuminated unless otherwise required by state or
federal regulations.
(4) No tower shall be located in any wetlands.
(5) No tower or antenna shall be located within 1,000 feet of an existing tower or antenna, unless
the applicant certifies that the existing tower does not meet the applicant's structural
specifications and applicant's technical design requirements, or that a collocation agreement
could not be obtained.
(6) Towers or antennas shall be exempt from the maximum height requirements of this chapter,
except as provided for in section 24-203
.
(7) Towers or antennas shall be located such that adequate setbacks are provided on all sides to
prevent the tower's fall zone from encroaching onto adjoining properties. Should this fall zone
encroach onto another property, a recorded easement may be prepared and signed by the adjacent
property owner to ensure that no structure will be built within the fall zone.
(8) Signage on communication towers and/or antennas.
a. No advertising of any type may be attached to a communication tower; however, a
communication tower and/or antennas may be placed upon an outdoor advertising sign provided
the height of the sign is increased not more than 20 feet.
b. The placement of a communication tower and/or antennas upon an outdoor advertising sign
shall not change the principal nature or classification.
c. A sign no larger than four square feet shall be placed in a visible location identifying the
owner and operator of each antenna as well as their emergency phone number(s).
13
(9) Communication towers shall be removed at the operator's expense within 120 days of the
date such tower ceases to be used for its intended purpose.
(10) Permit requirements for the erection or replacement of a tower or antenna shall be
accompanied by the following:
a. One copy of engineered stamped typical specifications for proposed structures and antenna,
including description of design characteristics and material.
b. An engineered stamped site plan drawn to scale showing property boundaries, tower location,
tower height, guy wires and anchors, existing structures, fall zone (as determined by a structural
engineer, licensed and certified in South Carolina), photographs or elevation drawings depicting
typical design of proposed structures, parking, fences, landscape plan, and existing land uses on
adjacent property; [site plan not required if antenna is to be mounted on an approved existing
structure].
c. A current map or update of an existing map on file, showing locations of applicant's antenna,
facilities, existing towers, and proposed towers which are reflected in public records, serving any
property.
d. Identification of the owners of all antenna and equipment to be located on the site. Allow
Edgefield County to share the wireless telecommunications facility for emergency services and
government use at no cost.
e. Written authorization from the site owner for the application.
f. Evidence that a valid FCC license for the proposed activity has been issued.
g. The applicant shall furnish a visual impact assessment, which shall include digital pictorial
representations of "before and after" views from key roads, residential, commercial or other
locations where the site is visible to a large number of individuals. The applicant shall provide a
map showing the locations of where the digital pictures were taken and the distance from the
proposed structure.
h. A written agreement to remove the tower and/or antenna within 120 days after cessation of
use.
i. A certificate from a registered engineer that the proposed facility will contain only equipment
meeting FCC rules, together with written indemnification of the county and proof of liability
insurance or financial ability to respond to claims up to $1,000,000.00 in the aggregate which
may arise from operation of the facility during its life, at no cost to the county.
j. The applicant shall demonstrate and provide in writing and/or by drawing how it shall
effectively screen from view the base and all related equipment and structures of the proposed
wireless facility.
14
k. A report from a structural engineer registered in South Carolina showing the tower antenna
capacity by type and number, a certification that the tower is designed to withstand winds in
accordance with ANSI/EIA/TIA 222 standards and a determination of the fall zone.
l. A written agreement to allow other users to co-locate on the tower and documentation that the
tower will be designed to allow it.
(11) The provisions of this section shall not apply to amateur radio, citizens band radio, or
television reception towers, masts and/or antennas.
(12) All telecommunication facilities and antennas shall be located, fenced or otherwise secured
in a manner that prevents unauthorized access.
(13) The holder of a permit issued under this section shall comply with all applicable state and
federal laws, regulations and rules pertaining to the wireless telecommunications facility for
which the permit was issued.
Planning Commission Action
Planning Commission shall review the preliminary plat. After final discussions, the
item will be put to a vote to determine the Planning Commission’s recommendation
of approval or denial of the preliminary plat.
15
Land Development Area
Aerial: (Image, Streets, Property red outline)
16
Land Development Property
17
Land Development Preliminary Plan
18
19
Restrictions on Land Disturbing Activity for Major Residential Subdivisions
(a) Major Residential Subdivision developments should be adapted to the natural contours of
the land.
(b) Mass grading of Large residential subdivisions should be limited to road right-of-way,
public utility easements, stormwater detention / retention facilities, and no more than 5
concurrent lots.
(c) Cut and fill slopes shall be no steeper than 2 feet long to 1 foot vertical. This shall also
apply to detention / retention ponds.
(d) Topsoil stripped during construction must be stockpiled and reapplied to disturbed areas
during final grading and prior to final grassing.
(e) Developments other than single family residential. Multi-family, commercial and
industrial developments normally require a much flatter topography than single family
residential. Therefore, portions of non-single family residential developments may be
mass graded in order to meet the requirements of the project. However, the design shall
be as compatible with the existing topography and attempt to leave as much natural
vegetation in place as practical.
Definitions:
Mass Grading: Land disturbance including earth moving over a large area which results in an
alteration of the natural contours of the land.
Major Residential Subdivision:
Topsoil Preservation: Stockpiling stripped topsoil onsite to be reapplied at final grading and prior to
revegetation of the site.
20
Edgefield County Planning Commission
Meeting Agenda
County Council Chambers
February 12, 2026
6:00 PM
This agenda may be modified at any time prior to or during the meeting described herein. A vote may be held on
all agenda items. The meeting may begin after the advertised start time if a reasonable adjustment to the
advertised start time is needed for any reason.
VI. Call to Order
VII. Invocation
VIII. Pledge of Allegiance
IX. Approval of Agenda
A. Approval of February 12, 2026 Meeting Agenda
X. Approval of Minutes
A. Approval of December 11, 2025 Work Session Meeting Minutes
B. Approval of December 11, 2025 Meeting Minutes
C. Approval of January 8, 2026 Work Session Minutes
XI. Reports
Staff Reports
XII. Guest Speakers
XIII. Public Hearing
Chairman: James Burt – Dist. I Members: Dustin Doolittle – Dist. II
Vice-Chairman: Lisa Whitaker- Dist. III Karlene Butler– Dist. IV
At Large: Autumn Eubanks
At Large: Tracy Walsh
21
This portion of the Planning Commission's regular Meeting allows for comments from citizens
regarding Public Hearing items on the Agenda during the regular meeting. Citizens may sign up to
speak on these matters. Interested citizens may sign up to speak on a list maintained by the
County Planner before the meeting. Each citizen shall be eligible to speak for a maximum of 5
minutes. All citizens wishing to speak during the public hearing shall be subject to recognition by
the presiding officer and shall address the presiding officer directly. Written comments may be
submitted to the County Planner before the meeting, which will be read during the Public Hearing
Comment Section.
XIV. Old Business
a) Vote and final discussion regarding the request to add “Restrictions on
Land Disturbance Activity for Major Residential Subdivisions” as an
amendment to the Tree Preservation Ordinance being presented to
County Council for consideration.
b) Vote and final discussion on a recommended Data & Crypto Mining
ordinance.
XV. New Business
c) Vote and final discussion regarding the preliminary approval of
Harmoni Towers AssetCo. LLC, proposed installation of a 315ft guyed
tower to be located off of Lick Fork Road in Edgefield (parcel ID #073-
00-00-010-000).
XVI. Adjournment
The next Planning Commission Meeting is scheduled for March 12, 2026. The Planning Commission is scheduled to
meet on the second Thursday of each month at 5:00 p.m. for a work session meeting and at 6:00 p.m. for the
regular meeting at the Edgefield County Council Chambers located at 225 Jeter St., Edgefield, SC. These meetings
are subject to cancellation or change without prior notice. The public will be notified of any cancellation or change.
Individuals requiring special assistance or a sign interpreter to participate in the meeti ng are asked to notify the
Building & Planning Department 48 hours before the meeting at (803) 637- 4073. Any questions regarding the
Planning Commission should be directed to the County’s Planner, April Morgan, at
amorgan@edgefieldcounty.sc.gov
22