Capital Projects
Greenville County · Greenville County · Budget documents
Open the original document More from Greenville County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
County of Greenville Budget Document
Fiscal Year 2026
167
CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement Planning process.
This section of the document provides information on the multi-year capital improvement program, the
current program status, a summary of capital projects and a copy of the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent and
nonrecurring projects, which should be financed over a period of years. Greenville County has selected a
programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a
comprehensive evaluation of project planning, justification, coordination of needs, priorities and relationship
to budgeting policies. Therefore, the capital improvement budget is considered with budget decisions.
Capital improvement programming is a continuous process involving yearly adjust ments. The CIP includes
capital projects recommended for fiscal years 2026 through 2030. Each fiscal year’s capital budget is
submitted in conjunction with its respective operating budget. The CIP multi-year plan includes projects for
which funding is currently available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2024 January – June 2025
Departmental
program plans
prepared and capital
projects submitted to
CIP team.
November
CIP Team
Review
Requests
December
CIP Team reviews,
prioritizes and
recommends capital
program
January -April
County Council
adopts CIP and
capital budget
May - June
County Departments prepare
CIP requests
by December 9
Budget/Planning
Staff compile project
information
by December 31
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County
Administrator’s
Recommended
Budget
County of Greenville Budget Document
Fiscal Year 2026
168
21.5%
64.0%
11.1%
3.3%
Capital Projects by Fund
Capital Projects Infrastructure Stormwater Enterprise Solid Waste
$0
$50
$100
$150
$200
$250Millions
CURRENT PROGRAM STATUS
The FY2026-FY2030 Capital Improvement Program totals $299.770 million for projects in the areas of
technological improvements, equipment, facilities, parks and recreation, infrastructure, stormwater, and
solid waste. For the current budget, capital projects total $71.883 million for FY2026. Below are graphic
comparisons of budgeted capital projects by fund and by type. The following page provides a detailed listing
of capital projects and financing summary. In the capital projects fund, facility expenditures are by far the
greatest percentage. Capital projects funded by the County’s enterprise funds are specific to each respective
fund.
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements. The majority
of improvements are for infrastructure improvements. Other major areas include stormwater, technology
improvements, and equipment replacement.
County of Greenville Budget Document
Fiscal Year 2026
169
FY2026 FY2027 FY2028 FY2029 FY2030 TOTAL
CAPITAL PROJECTS ($000 omitted) FUNDING SOURCE BUDGET PROPOSED PROPOSED PROPOSED PROPOSED FUNDS
COUNTY GOVERNMENT DEPARTMENTS
Technological Improvements
Information Technology
Capital Projects Fund 2.000$ 2.500$ 2.000$ 2.000$ 2.000$ 10.500$
GIS - Orthophotography and LIDAR Acquisition Capital Projects Fund 0.030 0.030 0.019 0.051 0.053 0.183
Register of Deeds Records Preservation Capital Projects Fund 0.150 0.650 0.300 0.300 0.300 1.700
GAMA Tax System Capital Projects Fund 2.678 - - - - 2.678
Body Cameras Capital Projects Fund 2.500 2.500 2.500 2.500 2.500 12.500
MDT Leaes Capital Projects Fund - 1.100 0.575 0.575 0.575 2.825
TOTAL 7.358$ 6.780$ 5.394$ 5.426$ 5.428$ 30.386$
Facilities/Construction Projects
Flooring Replacements Capital Projects Fund 0.150$ 0.150$ -$ -$ -$ 0.300$
Cooling Tower Rebuild LEC and Courthouse Capital Projects Fund 0.141 - - - - 0.141
Animal Care Roof Replacement Capital Projects Fund 0.190 - - - - 0.190
Central Records Roof Replacement Capital Projects Fund - 0.425 - - - 0.425
Oneal Maintenance Roof Replacement Capital Projects Fund - 0.335 - - - 0.335
Travelers Rest Maintenance Roof Replacement Capital Projects Fund - - 0.335 - - 0.335
Courthouse Expansion and Security Upgrades State Contribution 3.000 - - - - 3.000
TOTAL 3.481$ 0.910$ 0.335$ -$ -$ 4.726$
Equipment
Vehicle Replacements/Additions Debt Service - Lease 7.000$ 7.000$ -$ -$ -$ 14.000$
Public Works Equipment Road Program Fund 0.900 0.900 - - - 1.800
EMS - Stretcher replacement Capital Projects Fund 0.161 0.207 - - - 0.368
Interoperable Communications Radio Replacement Capital Projects Fund 2.000 2.000 2.100 - - 6.100
TOTAL 10.061$ 10.107$ 2.100$ -$ -$ 22.268$
Parks, Recreation, and Tourism Projects
Road Paving and Sidewalk - Southside, Northside Parks Capital Projects Fund 1.700$ 1.500$ -$ -$ -$ 3.200$
Court Lighting - Southside, Northside, Lakeside Parks Capital Projects Fund 0.700 0.500 - - - 1.200
Playground Replacements Capital Projects Fund - 0.200 - - - 0.200
Park Master Plan - Oakland Plantation and Lakeside Capital Projects Fund - 0.300 0.300
Trail Extension and Improvement Capital Projects Fund 0.750 - - - - 0.750
Herdklotz Park - Turf Soccer Field Capital Projects Fund 1.400 - - - - 1.400
TOTAL 4.550$ 2.500$ -$ -$ -$ 7.050$
CAPITAL PROJECTS FUND TOTAL 25.450$ 20.297$ 7.829$ 5.426$ 5.428$ 64.430$
SPECIAL REVENUE FUNDS
Infrastructure
Road Program Road Program Fund 36.258$ 39.494$ 38.095$ 38.093$ 40.000$ 191.940$
SPECIAL REVENUE FUNDS TOTAL 36.258$ 39.494$ 38.095$ 38.093$ 40.000$ 191.940$
STORMWATER ENTERPRISE FUND
Neighborhood Drainage Projects Enterprise Fund 0.600 0.600 0.600 0.600 0.600 3.000
Flood Mitigation Program Enterprise Fund 2.350 2.350 2.350 2.350 2.350 11.750
Water Quality Retrofit/Stream Stabilization Enterprise Fund 2.525 4.050 4.025 4.025 4.025 18.650
STORMWATER ENTERPRISE FUND TOTAL 5.475$ 7.000$ 6.975$ 6.975$ 6.975$ 33.400$
SOLID WASTE ENTERPRISE FUND
Twin Chimneys Landfill Cell Construction Unit VI, Cell V Bond Proceeds 3.300 4.300 - - - 7.600
Equipment Replacement Bond Proceeds 1.400 1.000 - - - 2.400
SOLID WASTE ENTERPRISE FUND TOTAL 4.700$ 5.300$ -$ -$ -$ 10.000$
TOTAL FOR ALL CAPITAL PROJECTS 71.883$ 72.091$ 52.899$ 50.494$ 52.403$ 299.770$
CIP FINANCING SUMMARY
FY2026-FY2030
County of Greenville Budget Document
Fiscal Year 2026
170
Operating
Budget $87.329
$485.057 million
million
Capital
Budget
$73.733
million
Operating
Budget
87% Capital
Budget
13%
OPERATING
IMPACT DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating costs.
No Impact The project will cause no change in operating costs.
Negligible The impact will be very small; it will generate less than $10,000 per year in increased
operating expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating expenditures.
Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures.
High The impact will increase operating expenditures $100,001 or more.
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2026
The chart below shows the relationship between the operating budget and capital expenditures for FY20 26.
Capital expenditures of $73.733 million include capital projects of $60.183 million, loan proceeds of $7.000
million, a bond issue for Solid Waste of $4.7 million, and other capital items totaling $ 1.849 million. The
impact on the $485.057 million operating budget is $27.146 million, which is the debt service for capital
projects. There are no estimated operational costs for new projects in FY20 26. The $60.183 million for “pay-
as-you-go” projects will come from fund balances in each respective fund and/or special revenue.
Operating Impact $27.146 million for FY2026
Debt Service $27.146 million (Principal and Interest)
Operations and Maintenance $0 million
“Pay-as-you-go” - $60.183 million
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional staff,
maintenance, or daily operational costs. The amount of operating budget impact for each project is referred
to in the following terms:
County of Greenville Budget Document
Fiscal Year 2026
171
FUNDING
SOURCE DESCRIPTION
Transfers A major source of smaller capital projects is transfers from operating funds in the County.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X, Section
14 of the constitution of the State of South Carolina, 1895, as amended, provides that
counties shall have the power to incur bonded indebtedness in such a manner and upon
such terms and conditions as the General Assembly shall prescribe by general law. General
obligation debt may be incurred only for public and corporate purpose in an amount not
exceeding 8% of the assessed value of all taxable property of each county.
Special Source
Revenue Bonds
The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties can
issue Special Source Revenue Bonds for the purpose of building or acquiring infrastructure
necessary to continue the economic development of a county. The portion of the CIP
which provides for the building or acquiring of infrastructure necessary to continue the
economic development of the County is included in the Infrastructure Bank and funded
through Special Source Revenue Bonds. The County has pledged the County portion of
the revenue stream from the multi-county parks, which includes fee-in-lieu-of-taxes
(FILOT) revenues.
Capital Projects
Reserve
Another source utilized in the CIP is the capital project reserve account. This account
contains any unspent funds from previously completed capital projects. The County's
Financial Policies allow the County Administrator to include recommendations in the
budget to dispose of unspent capital project funds.
Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem
revenues or fees. The CIP utilizes a road maintenance fee of $25 per vehicle to fund a
portion of the road program.
Enterprise Fund
Revenue
For the County's two enterprise funds, Solid Waste and Stormwater, improvements are
funded through each fund's respective revenue.
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These
sources include: transfers from other funds, general obligation bonds, special source revenue bonds, capital
project reserve funds, pay-as-you-go basis either through ad valorem revenues or fees, and enterprise fund
revenue. The chart below provides a description of funding sources.
County of Greenville Budget Document
Fiscal Year 2026
172
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT COST
Information Technology 2.000$ 2.500$ 2.000$ 2.000$ 2.000$ 10.500$
GIS - Orthophotography and LiDAR Acquisition 0.030 0.030 0.019 0.051 0.053 0.183
Register of Deeds Records Preservation 0.150 0.650 0.300 0.300 0.300 1.700
GAMA Tax System 2.678 - - - - 2.678
Body Cameras 2.500 2.500 2.500 2.500 2.500 12.500
MDT Leases - 1.100 0.575 0.575 0.575 2.825
TOTAL PROJECT COST 7.358$ 6.780$ 5.394$ 5.426$ 5.428$ 30.386$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT
Capital Projects Fund 7.358$ 6.780$ 5.394$ 5.426$ 5.428$ 30.386$
TOTAL PROJECT FUNDING 7.358$ 6.780$ 5.394$ 5.426$ 5.428$ 30.386$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition or
construction of major capital projects, other than those financed by proprietary funds. The FY20 26-FY2030
Capital Improvement Program includes a budget of $64.430 million for various capital projects in the areas of
technological improvements, facility improvements, equipment, and parks and recreation projects. Each
project is discussed in detail on the following pages.
TECHNOLOGICAL IMPROVEMENTS
No Impact on Operating Budget
Description of Projects
Technological improvements include funding for information technology, GIS, Tax
Services, Register of Deeds, and the Sheriff’s Office. Information technology
projects include upgrading various information technology projects, such as
software package maintenance, AS400 maintenance, and new IT projects and
upgrades. System upgrades are needed for increased reliability, speed and security.
Funding is also proposed for the GIS acquisition of LiDAR data for the Geographic
Information System. This data is used to determine where ground features have
changed in Greenville County. Funds are also proposed for the Register of Deeds
preservation project. This project will allow for the restoration and preservation of
approximately 1,000 historical land record indexes and deed documents. All of
these documents are considered permanent by South Carolina statute. The budget includes funds for the
GAMA Tax System, which involves the conversion of two appraisal software products into one for more
efficiency and consistency. Funding is also included for the Sheriff’s Office to acquire body -worn and dash
cameras. These cameras provide reliable visual and audio evidence to verify events, document statements,
and increase transparency with the community. Funding is included in future years for the payment of the
annual leases for the mobile data terminals for the Sheriff’s Office as well.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Information technology improvements are budgeted in a capital project fund and financed with funds
transferred from the Infrastructure Bank. The budget reflects the cost of purchasing necessary equipment
and/or contractual costs. There will be no operating budget impact due to any of these projects.
County of Greenville Budget Document
Fiscal Year 2026
173
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL PROJECT
COST
Flooring Replacements 0.150$ 0.150$ -$ -$ -$ 0.300$
Cooling Tower Rebuild LEC and Courthouse 0.141 - - - - 0.141
Animal Care Roof Replacement 0.190 - - - - 0.190
Central Records Roof Replacement - 0.425 - - - 0.425
Oneal Maintenance Roof Replacement - 0.335 - - - 0.335
Travelers Rest Maintenance Roof Replacement - - 0.335 - - 0.335
Courthouse Expansion and Security Upgrades 3.000 - - - - 3.000
TOTAL PROJECT COST 3.481$ 0.910$ 0.335$ -$ -$ 4.726$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.481$ 0.910$ 0.335$ -$ -$ 1.726$
State Contribution 3.000 - - - - 3.000
TOTAL PROJECT FUNDING 3.481$ 0.910$ 0.335$ -$ -$ 4.726$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
FACILITIES/CONSTRUCTION PROJECTS
No Impact on Operating Budget
Description of Projects
Facility/Construction projects include funding for renovations and maintenance of facilities. These projects
include flooring replacements at various County facilities, including the Courthouse, Law Enforcement
Center, and Detention Center. Carpet and tile will be replaced in offices and common space. Another
projects involves the rebuilding the cooling towers at the Courthouse and the Law Enforcement Center in
order to provide improved circulation throughout the tower and facilitate the operation of the ch illers at
these facilities. Funds are also included for the replacement of existing roof at the Animal Care facility, which
is over 22 years old. The current roof has experienced leaks and become dangerous to perform work on
them. The budget includes funds for the replacement of the roof at the Central Records facility. This facility
houses a majority of the County archived records. The current roof has been in place since 1994. Roof
replacements for other facilities are programmed in the next five years. R oofs will be replaced at the
Travelers Rest Maintenance Facility and the Oneal Maintenance Facility. The current roof at the Travelers
Rest facility was installed in 1990. Roof consultants recommend full replacement of the low slope and steep
slope roof. The Oneal building is close to 100 years old and the roof is in a constant state of disrepair. The
budget also includes funds for a courthouse expansion and security upgrades. The project involves the
expansion of judicial offices at the County Courthouse, as well as security upgrades. These upgrades will
include modern security cameras and monitoring equipment, updated key card access, perimeter protective
barriers and secure parking solutions, as well as a new command center control board.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Facility/Construction projects are budgeted in a capital project fund. These projects are financed with funds
transferred from the Infrastructure Bank and with contributions from the State of South Carolina for the
courthouse expansion.
County of Greenville Budget Document
Fiscal Year 2026
174
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT COST
Vehicle Replacements/Additions $ 7.000 $ 7.000 $ - $ - $ - $ 14.000
Public Works Equipment 0.900 0.900 - - - 1.800
EMS - Stretcher Replacement 0.161 0.207 - - - 0.368
Radio Replacement 2.000 2.000 2.100 - - 6.100
TOTAL PROJECT COST 10.061$ 10.107$ 2.100$ -$ -$ 22.268$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT
FUNDING
Capital Lease 7.000$ 7.000$ -$ -$ -$ 14.000$
Capital Projects Fund 3.061 3.107 2.100 - - 8.268
TOTAL PROJECT FUNDING 10.061$ 10.107$ 2.100$ -$ -$ 22.268$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
EQUIPMENT
Moderate Impact on Operating Budget
Description of Projects
Equipment projects include vehicle/heavy equipment replacement and additions , the replacement of EMS
equipment, and radio replacement. Various vehicles and equipment will be replaced and/or added as needed
through the County’s master lease program. Vehicle/equipment additions
include heavy equipment for Public Works office marked patrol cars, and
other vehicles as needed.
Funds are also included for the replacement of sixteen stretchers for EMS
over a two-year period. Stretchers have a lifespan of seven years.
Replacement is recommended as these stretchers have reached the lifespan
and the physical nature is in disrepair and poses a risk to patient care.
The budget also includes the replacement of legacy radios due to South Carolina’s transition to TDMA (Time
Division Multiple Access). Transition to TDMA allows for additional talk paths and increases the capacity of
the system. Approximately 75% of the radios are for the Sheriff’s Office. The remaining 25% are for other
County departments, including EMS, Emergency Management, Special Operations, Forensics, and the
Coroner’s Office.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Vehicle/equipment replacements and addition projects are budgeted in a capital project fund and fin anced
with a capital lease. EMS equipment replacement and radio replacement are budgeted in a capital project
fund and financed with a transfer from the Infrastructure Bank . Operating costs will include the debt service
for the capital lease.
County of Greenville Budget Document
Fiscal Year 2026
175
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT COST
Road Paving and Sidewalk Replacement 1.700$ 1.500$ -$ -$ -$ 3.200$
Court Lighting Replacement 0.700 0.500 - - - 1.200
Playground Replacements - 0.200 - - - 0.200
Park Master Plan for Oakland Plantation and Lakeside - 0.300 - - - 0.300
Trail Extension and Improvements 0.750 - - - - 0.750
Herdklotz Park Turf Soccer Fields 1.400 - - - - 1.400
TOTAL PROJECT COST 4.550$ 2.500$ -$ -$ -$ 7.050$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT
FUNDING
Capital Projects Fund 4.550$ 2.500$ -$ -$ -$ 7.050$
TOTAL PROJECT FUNDING 4.550$ 2.500$ -$ -$ -$ 7.050$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
PARKS, RECREATION, AND TOURISM PROJECTS
No Impact on Operating Budget
Description of Projects
Projects for the Parks, Recreation, and Tourism Department include repaving of roadways, parking lots and
sidewalks at Southside and Northside parks; replacement of court lighting systems at Southside and
Northside tennis/pickleball courts and Lakeside basketball courts; replacement of existing playground
equipment at Pittman Park; development of master plan and construction documents for Oakland
Plantation development and Lakeside Park renovations; expansion of current trail system from Verdae
Boulevard to Millennium Boulevard at CU-ICAR and replacement of small bridge near Willard Street; and turf
for soccer field at Herdklotz Park.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Parks, Recreation, and Tourism capital projects are budgeted in a capital project fund. Projects will be
funded through a transfer from the Parks, Recreation, and Tourism special revenue fund. No additional
impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Year 2026
176
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT COST
Road Program 36.258$ 39.494$ 38.095$ 38.093$ 40.000$ 191.940$
TOTAL PROJECT COST 36.258$ 39.494$ 38.095$ 38.093$ 40.000$ 191.940$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
PROJECT
FUNDING
Special Revenue Fund - Road Program 36.258$ 39.494$ 38.095$ 38.093$ 40.000$ 191.940$
TOTAL PROJECT FUNDING 36.258$ 39.494$ 38.095$ 38.093$ 40.000$ 191.940$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
SPECIAL REVENUE FUNDS
The Road Program Special Revenue Fund is used to finance capital infrastructure improvements. The
FY2026-FY2030 Capital Improvement Program includes a budget of $191.940 million for infrastructure capital
projects.
INFRASTRUCTURE IMPROVEMENTS
No Impact on Operating Budget
Description of Projects
Road improvements include rehabilitation and/or reconstruction of “worst roads” first on a countywide
basis. Planned projects are consistent with Council approved programs to reduce risk to public safety and to
improve deteriorating road structures. The road program also includes a contribution for local municipality
road programs.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Funding for the road program is included in the capital projects fund and is financed through road
maintenance fees, a transfer from the Infrastructure Bank, and Road Program fund balances. This project
provides direct benefit to citizens through road and bridge improvements. No additional impact on the
operating budget is anticipated.
County of Greenville Budget Document
Fiscal Year 2026
177
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL PROJECT
COST
Neighborhood Drainage Projects 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
Flood Mitigation Program 2.350 2.350 2.350 2.350 2.350 11.750
Water Quality Retrofits/Stream Stable 2.525 4.050 4.025 4.025 4.025 18.650
TOTAL PROJECT COST 5.475$ 7.000$ 6.975$ 6.975$ 6.975$ 33.400$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL PROJECT
FUNDING
Enterprise Fund Revenue 5.475$ 7.000$ 6.975$ 6.975$ 6.975$ 33.400$
TOTAL PROJECT FUNDING 5.475$ 7.000$ 6.975$ 6.975$ 6.975$ 33.400$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within these funds
are accounted for in the appropriate proprietary enterprise fund. The FY20 26-FY2030 Capital Improvement
Program includes a budget of $33.400 million for various capital projects in the area of Stormwater. The
Program includes a budget of $10.000 million for projects in the area of Solid Waste.
STORMWATER ENTERPRISE FUND
No Impact on Operating Budget
Description of Projects
Capital projects for Stormwater include funding for neighborhood drainage projects, repair of structures at
the August Grove SWM Pond River, NPDES/water quality retrofit projects, and flood mitigation program.
These projects are consistent with County Council’s goals for infrastructure which provide for funding to
resolve drainage problems and for stormwater flood project.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Funding for these projects is included in the stormwater enterprise fund and is funded through revenue
received in that fund. No additional impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Year 2026
178
PROJECT ITEMS
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT COST
Twin Chimneys Landfill Cell Construction 3.300$ 4.300$ -$ 7.600$
Equipment Replacement 1.400 1.000 - 2.400
TOTAL PROJECT COST 4.700$ 5.300$ -$ -$ -$ 10.000$
PROJECT FUNDING SOURCES
FY2026
BUDGET
FY2027
PROPOSED
FY2028
PROPOSED
FY2029
PROPOSED
FY2030
PROPOSED
TOTAL
PROJECT
FUNDING
Bond Proceeds 4.700$ 5.300$ -$ -$ -$ 10.000$
TOTAL PROJECT FUNDING 4.700$ 5.300$ -$ -$ -$ 10.000$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
SOLID WASTE ENTERPRISE FUND
No Impact on Operating Budget
Description of Projects
Capital projects for Solid Waste include funding for landfill cell construction and heavy equipment
replacement.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Funding for the road program is included in the solid waste enterprise fund and is anticipate to be funded
through a bond issue. No additional impact on the operating budget is anticipated.