County of Greenville Budget Document Fiscal Years 2024 and 2025 163 CAPITAL PROJECTS Capital projects are submitted and approved through the multi-year Capital Improvement Planning process. This section of the document provides information on the multi-year capital improvement program, the current program status, a summary of capital projects and a copy of the Capital Improvement Policies. CAPITAL IMPROVEMENT PROGRAM The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent and nonrecurring projects, which should be financed over a period of years. Greenville County has selected a programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a comprehensive evaluation of project planning, justification, coordination of needs, priorities and relationship to budgeting policies. Therefore, the capital improvement budget is considered with budget decisions. Capital improvement programming is a continuous process involving yearly adjust ments. The CIP includes capital projects recommended for fiscal years 2024 through 2028. Each fiscal year’s capital budget is submitted in conjunction with its respective operating budget. The CIP multi-year plan includes projects for which funding is currently available and for which future funding is reasonably assured. CAPITAL IMPROVEMENT PLANNING PROCESS Shown below is a graphic depiction of the process followed for capital improvement planning. July – December 2022 January – June 2023 Departmental program plans prepared and capital projects submitted to CIP team. November CIP Team Review Requests December CIP Team reviews, prioritizes and recommends capital program January -April County Council adopts CIP and capital budget May - June County Departments prepare CIP requests by December 9 Budget/Planning Staff compile project information by December 31 5-Year CIP and Capital Needs Assessment Developed by January 15 County Administrator’s Recommended Budget County of Greenville Budget Document Fiscal Years 2024 and 2025 164 31.0% 46.0% 23.0% Capital Projects by Fund Capital Projects Infrastructure Stormwater Enterprise $0 $10 $20 $30 $40 $50 $60 Millions CURRENT PROGRAM STATUS The FY2024-FY2028 Capital Improvement Program totals $118.217 million for projects in the areas of technological improvements, equipment, facilities, parks and recreation, infrastructure, and stormwater. For the current biennium budget, capital projects total $32.137 million for FY2024 and $29.686 million for FY2025. Below are graphic comparisons of budgeted capital projects by fund and by type. The following page provides a detailed listing of capital projects and financing summary. In the capital projects fund, facility expenditures are by far the greatest percentage. Capital projects funded by the County’s enterprise funds are specific to each respective fund. CAPITAL PROJECTS BY TYPE Following is a graphic comparison of the capital improvements plan by type of improvements. The majority of improvements are for facility improvements. Other large areas are stormwater, which includes drainage projects and specific task force projects, and infrastructure, which includes road paving. County of Greenville Budget Document Fiscal Years 2024 and 2025 165 FY2024 FY2025 FY2026 FY2027 FY2028 TOTAL CAPITAL PROJECTS ($000 omitted) FUNDING SOURCE BUDGET BUDGET PROPOSED PROPOSED PROPOSED FUNDS COUNTY GOVERNMENT DEPARTMENTS Technological Improvements Information Technology Capital Projects Fund 1.842$ 2.131$ 2.000$ 2.000$ 2.000$ 9.972$ GIS - Orthophotography and LIDAR Acquisition Capital Projects Fund - - 0.046 0.048 0.050 0.144 Register of Deeds Records Preservation Capital Projects Fund - - 0.500 0.500 0.500 1.500 TOTAL 1.842$ 2.131$ 2.546$ 2.548$ 2.550$ 11.616$ Facilities/Construction Projects Property Maintenance of Boilers Capital Projects Fund 0.150$ 0.100$ -$ -$ -$ 0.250$ Waterproofing of Juvenile Facility Capital Projects Fund 0.335 - - - - 0.335 Fire Alarm System Upgrade Detention Center Capital Projects Fund 0.160 - - - - 0.160 Replacement of Fill and Hot Water Basins Capital Projects Fund 0.110 - - - - 0.110 Floor Repairs for Animal Care Capital Projects Fund 0.162 0.261 - - - 0.423 Waterline Installation Capital Projects Fund 0.100 0.100 - - - 0.200 TOTAL 1.017$ 0.461$ -$ -$ -$ 1.478$ Equipment Vehicle Replacements/Additions Debt Service - Lease 7.000$ 7.000$ -$ -$ -$ 14.000$ Public Works Equipment Road Program Fund 0.750 0.750 - - - 1.500 EMS - Cardiac Monitors Capital Projects Fund 0.394 0.394 - - - 0.788 EMS - Communications Software/Technology Capital Projects Fund 0.160 - - - - 0.160 EMS - First Pass Capital Projects Fund 0.124 - - - - 0.124 TOTAL 8.428$ 8.144$ -$ -$ -$ 16.572$ Parks, Recreation, and Tourism Projects Parks Maintenance Facility at Pavilion Capital Projects Fund 1.100$ -$ -$ -$ -$ 1.100$ Picnic Shelter Replacement at Lakeside Park Capital Projects Fund 0.300 - - - - 0.300 Playground Replacement Capital Projects Fund 0.200 0.500 - - - 0.700 Slater Hall Rehabilitation Capital Projects Fund 0.150 1.200 1.350 Trail Maintenance Capital Projects Fund 1.000 1.000 - - - 2.000 Tennis Court and Athletic Field Lighting Capital Projects Fund 1.350 - - - - 1.350 TOTAL 4.100$ 2.700$ -$ -$ -$ 6.800$ CAPITAL PROJECTS FUND TOTAL 15.387$ 13.436$ 2.546$ 2.548$ 2.550$ 36.467$ SPECIAL REVENUE FUNDS Infrastructure Road Program Road Program Fund 11.000$ 11.000$ 11.000$ 11.000$ 11.000$ 55.000$ SPECIAL REVENUE FUNDS TOTAL 11.000$ 11.000$ 11.000$ 11.000$ 11.000$ 55.000$ STORMWATER ENTERPRISE FUND Repair of Augusta Grove SWM Pond River Enterprise Fund 0.500$ -$ -$ -$ -$ 0.500$ Neighborhood Drainage Projects Enterprise Fund 0.600 0.600 0.600 0.600 0.600 3.000 Flood Mitigation Program Enterprise Fund 2.350 2.350 2.350 2.350 2.350 11.750 Water Quality Retrofit/Stream Stabilization Enterprise Fund 2.300 2.300 2.300 2.300 2.300 11.500 STORMWATER ENTERPRISE FUND TOTAL 5.750$ 5.250$ 5.250$ 5.250$ 5.250$ 26.750$ TOTAL FOR ALL CAPITAL PROJECTS 32.137$ 29.686$ 18.796$ 18.798$ 18.800$ 118.217$ CIP FINANCING SUMMARY FY2024-FY2028 County of Greenville Budget Document Fiscal Years 2024 and 2025 166 Operating Budget $49.223 $359.246 million million Capital Budget $38.902 million Operating Budget $47.608 $371.750 million million Capital Budget $37.047 million Operating Budget 92% Capital Budget 8% Operating Budget 91% Capital Budget 9% RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS Fiscal Year 2024 The chart below shows the relationship between the operating budget and capital expenditures for FY2024. Capital expenditures of $38.902 million include capital projects of $25.004 million, loan proceeds of $7.000 million, and other capital items totaling $6.898 million. The impact on the $359.246 million operating budget is $24.218 million, which is the debt service for capital projects. There are no estimated operational costs for new projects in FY20 24. The $25.004 million for “pay-as-you-go” projects will come from fund balances in each respective fund and/or special revenue. Operating Impact $24.218 million for FY2024 Debt Service $24.218 million (Principal and Interest) Operations and Maintenance $0 million “Pay-as-you-go” - $25.004 million Fiscal Year 2025 The chart below shows the relationship between the operating budget and capital expenditures for FY2025. Capital expenditures of $37.047 million include capital projects of $23.044 million, loan proceeds of $7.000 million, and other capital items totaling $7.003 million. The impact on the $371.750 million operating budget is $24.563 million, which is the debt service for capital projects. The remaining $23.044 million for “pay-as-you-go” projects will come from fund balances in each respective funds and/or special revenue. Operating Impact $24.563 million for FY2025 Debt Service $24.563 million (Principal and Interest) Operations and Maintenance $0 million “Pay-as-you-go” - $23.044 million County of Greenville Budget Document Fiscal Years 2024 and 2025 167 OPERATING IMPACT DESCRIPTION Positive The project will either generate some revenue to offset expenses or reduce operating costs. No Impact The project will cause no change in operating costs. Negligible The impact will be very small; it will generate less than $10,000 per year in increased operating expenditures. Slight The impact will be between $10,001 and $50,000 in increased operating expenditures. Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures. High The impact will increase operating expenditures $100,001 or more. FUNDING SOURCE DESCRIPTION Transfers A major source of smaller capital projects is transfers from operating funds in the County. General Obligation Bonds General Obligation Bonds are used to finance a variety of public projects. Article X, Section 14 of the constitution of the State of South Carolina, 1895, as amended, provides that counties shall have the power to incur bonded indebtedness in such a manner and upon such terms and conditions as the General Assembly shall prescribe by general law. General obligation debt may be incurred only for public and corporate purpose in an amount not exceeding 8% of the assessed value of all taxable property of each county. Special Source Revenue Bonds The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties can issue Special Source Revenue Bonds for the purpose of building or acquiring infrastructure necessary to continue the economic development of a county. The portion of the CIP which provides for the building or acquiring of infrastructure necessary to continue the economic development of the County is included in the Infrastructure Bank and funded through Special Source Revenue Bonds. The County has pledged the County portion of the revenue stream from the multi-county parks, which includes fee-in-lieu-of-taxes (FILOT) revenues. Capital Projects Reserve Another source utilized in the CIP is the capital project reserve account. This account contains any unspent funds from previously completed capital projects. The County's Financial Policies allow the County Administrator to include recommendations in the budget to dispose of unspent capital project funds. Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem revenues or fees. The CIP utilizes a road maintenance fee of $25 per vehicle to fund a portion of the road program. Enterprise Fund Revenue For the County's two enterprise funds, Solid Waste and Stormwater, improvements are funded through each fund's respective revenue. OPERATING IMPACTS A project might have an operating budget impact if the project includes the need for additional staff, maintenance, or daily operational costs. The amount of operating budget impact for each project is referred to in the following terms: FUNDING SOURCES The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These sources include: transfers from other funds, general obligation bonds, special source revenue bonds, capital project reserve funds, pay-as-you-go basis either through ad valorem revenues or fees, and enterprise fund revenue. The chart below provides a description of funding sources. County of Greenville Budget Document Fiscal Years 2024 and 2025 168 PROJECT ITEMS FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT COST Information Technology 1.842$ 2.131$ 2.000$ 2.000$ 2.000$ 9.972$ GIS - Orthophotography and LiDAR - - 0.046 0.048 0.050 0.144 Register of Deeds Records Preservation - - 0.500 0.500 0.500 1.500 TOTAL PROJECT COST 1.842$ 2.131$ 2.546$ 2.548$ 2.550$ 11.616$ PROJECT FUNDING SOURCES FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT Capital Projects Fund 1.842$ 2.131$ 2.546$ 2.548$ 2.550$ 11.616$ TOTAL PROJECT FUNDING 1.842$ 2.131$ 2.546$ 2.548$ 2.550$ 11.616$ OPERATIONAL COSTS Operating Impact -$ -$ -$ -$ -$ -$ Cumulative Operating Impact - - - - - - CAPITAL IMPROVEMENT PROJECTS SUMMARY CAPITAL PROJECTS FUND The Capital Projects Fund is used to account for financial resources to be used for the acquisition or construction of major capital projects, other than those financed by proprietary funds. The FY20 24-FY2028 Capital Improvement Program includes a budget of $36.467 million for various capital projects in the areas of technological improvements, facility improvements, equipment, and parks and recreation projects. Each project is discussed in detail on the following pages. TECHNOLOGICAL IMPROVEMENTS No Impact on Operating Budget Description of Projects Technological improvements include funding for information technology, GIS, and Register of Deeds. Information technology projects include upgrading various information technology projects, such as software package maintenance, AS400 maintenance, and new IT projects and upgrades. System upgrades are needed for increased reliability, speed and security. Funding is also proposed in future years for the GIS acquisition of LiDAR data for the Geographic Information System. This data is used to determine where ground features have changed in Greenville County. Funds are also proposed in future years for the Register of Deeds preservation project. This project will allow for the restoration and preservation of approximately 1,000 historical land record indexes and deed documents. All of these documents are considered permanent by South Carolina statute. Impact on Operating Budget (Discussion of recurring costs, savings that will be realized, benefit to the county and citizens ) Information technology improvements are budgeted in a capital project fund and financed with funds transferred from the General Fund. The budget reflects the cost of purchasing necessary equipment and/or contractual costs. There will be no operating budget impact due to any of these projects. County of Greenville Budget Document Fiscal Years 2024 and 2025 169 PROJECT ITEMS FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT COST Property Maintenance of Boilers 0.150$ 0.100$ -$ -$ -$ 0.250$ Waterproofing of Juvenile Detention Facility 0.335 - - - - 0.335 Fire Alarm System Upgrade Detention Center 0.160 - - - - 0.160 Replacement of Fill and Hot Water Basins 0.110 - - - - 0.110 Floor Repairs Animal Care Services 0.162 0.261 0.423 Waterline Installation 0.100 0.100 - - - 0.200 TOTAL PROJECT COST 1.017$ 0.461$ -$ -$ -$ 1.478$ PROJECT FUNDING SOURCES FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT FUNDING Capital Projects Fund 1.017$ 0.461$ -$ -$ -$ 1.478$ TOTAL PROJECT FUNDING 1.017$ 0.461$ -$ -$ -$ 1.478$ OPERATIONAL COSTS Operating Impact -$ -$ -$ -$ -$ -$ FACILITIES/CONSTRUCTION PROJECTS No Impact on Operating Budget Description of Projects Facility/Construction projects include funding for renovations and maintenance of facilities. These projects include the maintenance of the Raypak boiler units that are located in the Greenville County Detention Center. These units provide hot water to the entire facility for the workers and inmates. Other maintenance projects include the waterproofing of the Juvenile Detention Facility. The back wall and two side walls around the basketball gym are below grade and deteriorating due to moisture penetrating the block masonry. Another maintenance project involves the replacement of existing obsolete fire alarm systems that parts are no longer available to be acquired. The existing panel is no longer supported through tech support. Projects also include the replacement of the “fill” components and the hot water basins of the two cooling towers at the Greenville County Detention Center. These towers allow water to circulate through and back to the chillers to provide cooling in the Center. Funding is also provided for the County’s water installation project. In addition to these maintenance projects, the flooring at Animal Care Services will be replaced in the animal intake and animal adoption buildings. The floor repairs encompass 24,000 square feet of flooring and 2,700 linear feet of cover base. The project will include demolition and removal of existing floor coverings, moisture testing, floor preparation, and installation of a new protect-all flooring system. The new flooring includes rapid chemical weld on all seams, flash cove up walls 6" and capped with stainless steel bar. All drains in floor will be surrounded with a stainless steel drain ring. Protect All flooring is a durable, long - lasting, waterproof, slip, scratch, puncture, chemical, mildew, and bacteria resistant flooring system. Impact on Operating Budget (Discussion of recurring costs, savings that will be realized, benefit to the county and citizens ) Facility/Construction projects are budgeted in a capital project fund. These projects are financed with funds transferred from the General Fund. There will be no additional impact to the operating budget due to any of these projects. County of Greenville Budget Document Fiscal Years 2024 and 2025 170 PROJECT ITEMS FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT COST Vehicle Replacements/Additions $ 7.000 $ 7.000 $ - $ - $ - $ 14.000 Public Works Equipment 0.750 0.750 - - - 1.500 EMS Cardiac Monitors 0.394 0.394 - - - 0.788 EMS Communications Software 0.160 - - - - 0.160 EMS First Pass 0.124 - - - - 0.124 TOTAL PROJECT COST 8.428$ 8.144$ -$ -$ -$ 16.572$ PROJECT FUNDING SOURCES FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT FUNDING Capital Lease 7.000$ 7.000$ -$ -$ -$ 14.000$ Capital Projects Fund 1.428 1.144 - - - 2.572 TOTAL PROJECT FUNDING 8.428$ 8.144$ -$ -$ -$ 16.572$ OPERATIONAL COSTS Operating Impact 0.765$ 1.400$ 1.400$ 0.765$ 0.190$ 4.520$ EQUIPMENT Moderate Impact on Operating Budget Description of Projects Equipment projects include vehicle/heavy equipment replacement and additions and the replacement of EMS equipment. Various vehicles and equipment will be replaced and/or added as needed through the County’s master lease program. Vehicle/equipment additions include heavy equipment for Public Works office marked patrol cars, and other vehicles as needed. The EMS Division will acquire cardiac monitors and technology equipment. Eighteen LIFEPAK 15 cardiac monitors/defibrillator units will be purchased. This is used to monitor cardiac waveforms, heart rates, conduction disturbances, identify life-threatening rhythms and heart damage, perform and transmit 12-lead electrocardiograms, measure vital signs, provide external cardiac pacing, and perform cardioversion or defibrillation. EMS will also acquire the Auto EMS and FIRE Dispatch and single agency modifications to CAD. The Auto EMS & FIRE Dispatch program utilizes the computer-aided dispatch (CAD) system to instantly alert emergency resources and multiple agencies/departments simultaneously and accurately so as to reduce the time to initiate a dispatch. This improves EMS and fire personnel safety by ensuring appropriate and important incident information is provided. This project will also provide for CAD modifications made by the Central Square system to support auto dispatching and unit-based projects, as well as improving dispatch time and accuracy. In addition, EMS will implement the First Pass Technology. FirstPass is a well-known clinical quality measurement and protocol monitoring tool designed to alert users of deviations in expected treatments to protocols. FirstPass bundles of care provide information that allows for comprehensive system and indivi dual provider review in order to illustrate a much broader insight to the system of performance and care. Impact on Operating Budget (Discussion of recurring costs, savings that will be realized, benefit to the county and citizens ) Vehicle/equipment replacements and addition projects are budgeted in a capital project fund and fin anced with a capital lease. EMS projects are budgeted in a capital project fund and financed with a transfer from the General Fund. Operating costs will include the debt service for the capital lease. County of Greenville Budget Document Fiscal Years 2024 and 2025 171 PROJECT ITEMS FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT COST Parks Maintenance Facility at Pavilion 1.100$ -$ -$ -$ -$ 1.100$ Picnic Shelter Renovations 0.300 - - - - 0.300 Playground Replacement 0.200 0.500 - - - 0.700 Slater Hall Rehabilitation 0.150 1.200 - - - 1.350 Trail Maintenance 1.000 1.000 - - - 2.000 Tennis Court and Athletic Field Lighting 1.350 - - - - 1.350 TOTAL PROJECT COST 4.100$ 2.700$ -$ -$ -$ 6.800$ PROJECT FUNDING SOURCES FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT FUNDING Capital Projects Fund 4.100$ 2.700$ -$ -$ -$ 6.800$ TOTAL PROJECT FUNDING 4.100$ 2.700$ -$ -$ -$ 6.800$ OPERATIONAL COSTS Operating Impact -$ -$ -$ -$ Cumulative Operating Impact - - - - - - PARKS, RECREATION, AND TOURISM PROJECTS No Impact on Operating Budget Description of Projects Projects for the Parks, Recreation, and Tourism Department include construction of a new central regions maintenance facility at the Pavilion, replacement of picnic shelter at Lakeside Park, replacement of playground equipment at various parks, rehabilitations of Slater Hall Community Center, trail maintenance, and tennis court and athletic field lighting. Impact on Operating Budget (Discussion of recurring costs, savings that will be realized, benefit to the county and citizens) Parks, Recreation, and Tourism capital projects are budgeted in a capital project fund. Projects will be funded through a transfer from the Parks, Recreation, and Tourism special revenue fund. No additional impact on the operating budget is anticipated. County of Greenville Budget Document Fiscal Years 2024 and 2025 172 PROJECT ITEMS FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT COST Road Program 11.000$ 11.000$ 11.000$ 11.000$ 11.000$ 55.000$ TOTAL PROJECT COST 11.000$ 11.000$ 11.000$ 11.000$ 11.000$ 55.000$ PROJECT FUNDING SOURCES FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED O PROJECT FUNDING Special Revenue Fund - Road Fee 11.000$ 11.000$ 11.000$ 11.000$ 11.000$ 55.000$ TOTAL PROJECT FUNDING 11.000$ 11.000$ 11.000$ 11.000$ 11.000$ 55.000$ OPERATIONAL COSTS Operating Impact -$ -$ -$ -$ -$ -$ Cumulative Operating Impact - - - - - - CAPITAL IMPROVEMENTS PROJECTS SUMMARY SPECIAL REVENUE FUNDS The Road Program Special Revenue Fund is used to finance capital infrastructure improvements. The FY2024-FY2028 Capital Improvement Program includes a budget of $55.00 million for infrastructure capital projects. INFRASTRUCTURE IMPROVEMENTS No Impact on Operating Budget Description of Projects Road improvements include rehabilitation and/or reconstruction of “worst roads” first on a countywide basis. Planned projects are consistent with Council approved programs to reduce risk to public safety and to improve deteriorating road structures. The road program also includes a contribution for local municipality road programs. Impact on Operating Budget (Discussion of recurring costs, savings that will be realized, benefit to the county and citizens) Funding for the road program is included in the capital projects fund and is financed through road maintenance fees. This project provides direct benefit to citizens through road and bridge improvements. No additional impact on the operating budget is anticipated. County of Greenville Budget Document Fiscal Years 2024 and 2025 173 PROJECT ITEMS FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT COST Neighborhood Drainage Projects 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$ Repair of Augusta Grove SWM Pond 0.500 - - - - 0.500 Flood Mitigation Program 2.350 2.350 2.350 2.350 2.350 11.750 Water Quality Retrofits/Stream Stable 2.300 2.300 2.300 2.300 2.300 11.500 TOTAL PROJECT COST 5.750$ 5.250$ 5.250$ 5.250$ 5.250$ 26.750$ PROJECT FUNDING SOURCES FY2024 BUDGET FY2025 BUDGET FY2026 PROPOSED FY2027 PROPOSED FY2028 PROPOSED TOTAL PROJECT FUNDING Enterprise Fund Revenue 5.750$ 5.250$ 5.250$ 5.250$ 5.250$ 26.750$ TOTAL PROJECT FUNDING 5.750$ 5.250$ 5.250$ 5.250$ 5.250$ 26.750$ OPERATIONAL COSTS Operating Impact -$ -$ -$ -$ -$ -$ Cumulative Operating Impact - - - - - - CAPITAL IMPROVEMENTS PROJECTS SUMMARY PROPRIETARY FUNDS The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within these funds are accounted for in the appropriate proprietary enterprise fund. The FY20 24-FY2028 Capital Improvement Program includes a budget of $26.750 million for various capital projects in the area of stormwater. STORMWATER ENTERPRISE FUND Description of Projects Capital projects for Stormwater include funding for neighborhood drainage projects, repair of structures at the August Grove SWM Pond River, NPDES/water quality retrofit projects, and flood mitigation program. These projects are consistent with County Council’s goals for infrastructure which provide for funding to resolve drainage problems and for stormwater flood project. Impact on Operating Budget (Discussion of recurring costs, savings that will be realized, benefit to the county and citizens ) Funding for these projects is included in the Stomwater Enterprise Fund and funded through revenue received in that fund. No additional impact on the operating budget is anticipated. County of Greenville Budget Document Fiscal Years 2024 and 2025 174 THIS PAGE INTENTIONALLY LEFT BLANK

Source: Greenville County website. First collected Oct 13, 2026.