Capital Projects
Greenville County · Greenville County · Budget documents
Open the original document More from Greenville County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
163
CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement Planning process.
This section of the document provides information on the multi-year capital improvement program, the
current program status, a summary of capital projects and a copy of the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent and
nonrecurring projects, which should be financed over a period of years. Greenville County has selected a
programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a
comprehensive evaluation of project planning, justification, coordination of needs, priorities and relationship
to budgeting policies. Therefore, the capital improvement budget is considered with budget decisions.
Capital improvement programming is a continuous process involving yearly adjust ments. The CIP includes
capital projects recommended for fiscal years 2022 through 2026. Each fiscal year’s capital budget is
submitted in conjunction with its respective operating budget. The CIP multi-year plan includes projects for
which funding is currently available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2020 January – June 2021
Departmental
program plans
prepared and capital
projects submitted to
CIP team.
November
CIP Team
Review
Requests
December
CIP Team reviews,
prioritizes and
recommends capital
program
January -April
County Council
adopts CIP and
capital budget
May - June
County Departments prepare
CIP requests
by December 22
Budget/Planning
Staff compile project
information
by December 31
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County
Administrator’s
Recommended
Budget
County of Greenville Budget Document
Fiscal Years 2022 and 2023
164
63.3%
25.1%
11.6%
Capital Projects by Fund
Capital Projects Infrastructure Stormwater Enterprise
$0
$20
$40
$60
$80
$100
$120
$140Millions
CURRENT PROGRAM STATUS
The FY2022-FY2026 Capital Improvement Program totals $239.055 million for projects in the areas of
technological improvements, equipment, facilities, parks and recreation, infrastructure, and stormwater. For
the current biennium budget, capital projects total $88.857 million for FY2022 and $93.302 million for FY2023.
Below are graphic comparisons of budgeted capital projects by fund and by type. The following page
provides a detailed listing of capital projects and financing summary. In the capital projects fund, facility
expenditures are by far the greatest percentage. Capital projects funded by the County’s enterprise funds
are specific to each respective fund.
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements. The majority
of improvements are for facility improvements. Other large areas are stormwater, which includes drainage
projects and specific task force projects, and infrastructure, which includes road paving.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
165
CIP FINANCING SUMMARY
FY2022-FY2026
County of Greenville Budget Document
Fiscal Years 2022 and 2023
166
Operating
Budget $35.362
$275.254 million
million
Capital
Budget
$89.298
million
Operating
Budget $36.184
$285.052 million
million
Capital
Budget
$93.765
million
Operating
Budget
92%
Capital
Budget
8%
Operating
Budget
91%
Capital
Budget
9%
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2022
The chart below shows the relationship between the operating budget and
capital expenditures for FY2022. Capital expenditures of $88.298 million
include capital projects of $21.857 million, a bond issue of $60.000 million, loan
proceeds of $7.000 million, and other capital items totaling $0.441 million. The
impact on the $275.254 million operating budget is $13.505 million, which is the
debt service for capital projects. There are no estimated operational costs for
new projects in FY2022. The $21.857 million for “pay-as-you-go” projects will
come from fund balances in each respective fund and/or special revenue.
Operating Impact $13.505 million for FY2022
Debt Service $13.505 million (Principal and Interest)
Operations and Maintenance $0 million
“Pay-as-you-go” - $21.857 million
Fiscal Year 2023
The chart below shows the relationship between the operating budget and
capital expenditures for FY2023. Capital expenditures of $93.765 million
include capital projects of $22.302 million, a bond issue of $64.000 million,
loan proceeds of $7.000 million, and other capital items totaling $0.463
million. The impact on the $285.052 million operating budget is $13.882
million, which is the debt service for capital projects. The remaining $ 22.302
million for “pay-as-you-go” projects will come from fund balances in each
respective funds and/or special revenue.
Operating Impact $13.882 million for FY2023
Debt Service $13.882 million (Principal and Interest)
Operations and Maintenance $0 million
“Pay-as-you-go” - $22.302 million
County of Greenville Budget Document
Fiscal Years 2022 and 2023
167
OPERATING
IMPACT DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating costs.
No Impact The project will cause no change in operating costs.
Negligible The impact will be very small; it will generate less than $10,000 per year in increased
operating expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating expenditures.
Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures.
High The impact will increase operating expenditures $100,001 or more.
FUNDING
SOURCE DESCRIPTION
Transfers A major source of smaller capital projects is transfers from operating funds in the County.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X, Section
14 of the constitution of the State of South Carolina, 1895, as amended, provides that
counties shall have the power to incur bonded indebtedness in such a manner and upon
such terms and conditions as the General Assembly shall prescribe by general law. General
obligation debt may be incurred only for public and corporate purpose in an amount not
exceeding 8% of the assessed value of all taxable property of each county.
Special Source
Revenue Bonds
The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties can
issue Special Source Revenue Bonds for the purpose of building or acquiring infrastructure
necessary to continue the economic development of a county. The portion of the CIP
which provides for the building or acquiring of infrastructure necessary to continue the
economic development of the County is included in the Infrastructure Bank and funded
through Special Source Revenue Bonds. The County has pledged the County portion of
the revenue stream from the multi-county parks, which includes fee-in-lieu-of-taxes
(FILOT) revenues.
Capital Projects
Reserve
Another source utilized in the CIP is the capital project reserve account. This account
contains any unspent funds from previously completed capital projects. The County's
Financial Policies allow the County Administrator to include recommendations in the
budget to dispose of unspent capital project funds.
Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem
revenues or fees. The CIP utilizes a road maintenance fee of $25 per vehicle to fund a
portion of the road program.
Enterprise Fund
Revenue
For the County's two enterprise funds, Solid Waste and Stormwater, improvements are
funded through each fund's respective revenue.
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional staff,
maintenance, or daily operational costs. The amount of operating budget impact for each project is referred
to in the following terms:
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These
sources include: transfers from other funds, general obligation bonds, special source revenue bonds, capital
project reserve funds, pay-as-you-go basis either though ad valorem revenues or fees, and enterprise fund
revenue. The chart below provides a description of funding sources.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
168
PROJECT ITEMS
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT COST
Information Technology 0.800$ 1.200$ 1.200$ 1.200$ 1.200$ 5.600$
Real Property GAMA System 0.271 0.875 0.875 - - 2.021
GIS - Orthophotography and LiDAR 0.040 0.040 0.040 0.040 - 0.160
Register of Deeds Digitization 0.035 0.035 - - - 0.070
Register of Deeds LMRS Replacement 0.120 0.130 - - - 0.250
Probate Court Imaging 0.035 0.035 - - - 0.070
TOTAL PROJECT COST 1.301$ 2.315$ 2.115$ 1.240$ 1.200$ 8.171$
PROJECT FUNDING SOURCES
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT
Capital Projects Fund 1.301$ 2.315$ 2.115$ 1.240$ 1.200$ 8.171$
TOTAL PROJECT FUNDING 1.301$ 2.315$ 2.115$ 1.240$ 1.200$ 8.171$
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition or
construction of major capital projects, other than those financed by proprietary funds. The FY2022-FY2026
Capital Improvement Program includes a budget of $151.231 million for various capital projects in the areas of
technological improvements, facility improvements, equipment, and parks and recreation projects . Each
project is discussed in detail on the following pages.
TECHNOLOGICAL IMPROVEMENTS
No Impact on Operating Budget
Description of Projects
Technological improvements include funding for information technology, GIS, Register of Deeds, and
Probate Court. Information technology projects include upgrading various information technology projects,
such as software package maintenance, AS400 maintenance, and new IT projects and upgrades. System
upgrades are needed for increased reliability, speed and security. Funding is also included for the Real
Property GAMA system, which involves the acquisition and installation of the GAMA system for Tax Service s.
GAMA integrates the CAMA (Computer Assisted Mass Appraisal System) with GIS so that appraisers can
combine spatial data with advanced analysis. This will result in more equitable and defensible valuations.
Funding is included for GIS acquisition of the annual LiDAR data from February 2022 through February 2024.
This data will primarily be used to determine where ground features have changed in Greenville County.
Register of Deeds digitization projects will allow for the digitization and indexing of all d eeds and plats and
will ensure the preservation and online availability of nearly 450,000 permanent land records. The Land
Management Records System (LMRS) Replacement project will allow for upgrading the software used for
land records management. Current software was not designed for Windows 10. Probate Court imaging will
allow for the imaging of probate records that are “permanent records” under South Carolina law. Imaging of
these records will still allow access to all records and keep all permanent reco rds secure and in good order.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Information technology improvements are budgeted in a capital project fund and financed with funds
transferred from the Infrastructure Bank. The budget reflects the cost of purchasing necessary equipment
and/or contractual costs. There will be no operating budget impact due to any of these projects.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
169
PROJECT ITEMS
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL PROJECT
COST
Courthouse Fire Alarm System 0.150$ -$ -$ -$ -$ 0.150$
Courthouse Automation System 0.110 - - - - 0.110
Security Equipment Replacement (Clerk of Court) 0.100 0.100 0.200 - - 0.400
Waterline Installation 0.100 0.100 - - - 0.200
Pendleton Street Renovations (Sheriff) 0.075 - - - - 0.075
Training Center Target System (Sheriff) 0.150 0.150 0.300
Magistrate Office Consolidation - 4.000 - - - 4.000
University Ridge Development Project 60.000 60.000 - - - 120.000
TOTAL PROJECT COST 60.685$ 64.350$ 0.200$ -$ -$ 125.235$
PROJECT FUNDING SOURCES
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.685$ 0.350$ 0.200$ . -$ 1.235$
Bond Issue 60.000 64.000 - - - 124.000
TOTAL PROJECT FUNDING 60.685$ 64.350$ 0.200$ -$ -$ 125.235$
FACILITIES/CONSTRUCTION PROJECTS
High Impact on Operating Budget
Description of Projects
Facility/Construction projects include funding for renovations and new construction. Renovations include the
replacement of the existing obsolete fire alarm system at the Greenville County Courthouse. The original
panel was installed in 1997 and replacement parts are no longer manufacture d. Renovations also include the
installation of an automation system at the Greenville County Courthouse for heating and air controls and
mechanical equipment. The manufacturer no longer supports the current software. There will also be
replacement of the current security video surveillance equipment, card access system, and the control board
in the Security office command center at the Greenville County Courthouse. The curr ent system is over
twenty years old and is systematically failing and beyond repair. These projects also include funding for
waterline installation. This project involves continued funding for the County’s water installation project.
Renovations also include funding for the renovation of Pendleton Street and replacement of the Sheriff’s
Office training center target system. The property of 1200 Pendleton Street was renovated into office space
for Sheriff’s Office investigators previously located in leased space on Woodruff Road and County Square.
New construction projects include the consolidation of magistrate offices and the development for County
properties.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Facility/construction projects are budgeted in a capital project fund. Renovation projects are financed with
funds transferred from the Infrastructure Bank. New construction projects will be financed with bond issues.
Operating costs will include the debt service for the bond issue.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
170
PROJECT ITEMS
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT COST
Vehicle Replacements/Additions $ 7.000 $ 7.000 $ - $ - $ - $ 14.000
Public Works Equipment 0.750 0.750 - - - 1.500
EMS Power Loads 0.200 0.200 0.206 - - 0.606
EMS Stairchairs and Stretchers 0.140 0.140
EMS Cardiac Monitors 0.069 0.150 0.185 - - 0.404
TOTAL PROJECT COST 8.159$ 8.100$ 0.391$ -$ -$ 16.650$
PROJECT FUNDING SOURCES
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT
FUNDING
Capital Lease 7.000$ 7.000$ -$ -$ -$ 14.000$
Capital Projects Fund 1.159 1.100 0.391 - - 2.650
TOTAL PROJECT FUNDING 8.159$ 8.100$ 0.391$ -$ -$ 16.650$
EQUIPMENT
Moderate Impact on Operating Budget
Description of Projects
Equipment projects include vehicle/heavy equipment replacement and additions and the replacement of
EMS equipment. Various vehicles and equipment will be replaced and/or added as needed through the
County’s master lease program. Vehicle/equipment additions include heavy equipment for Public Works
offices, marked patrol cars, and other vehicles as needed. The EMS Division will implement the Stryker
Power LOAD system which is a new technology that facilitates a hands-free and lift-free mechanism for
loading and unloading patients on stretchers into and out of ambulances. The system focuses on reducing
injuries and the costs associated with them. EMS will replace fourteen stair chairs and add five stretchers for
the EMS department. Also, EMS will replace LifePak cardiac monitors. These replacements will allow the
department to keep up with software updates and scheduled maintenance.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized,
benefit to the county and citizens)
Vehicle/equipment replacements and additions projects are
budgeted in a capital project fund and financed with a capital
lease. EMS projects are budgeted in a capital project fund
and financed with a transfer from the Infrastructure Bank.
Operating costs will include the debt service for the capital
lease.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
171
PROJECT ITEMS
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT COST
Bridge Stabilization (Campbell's Covered Br) 0.325$ -$ -$ -$ -$ 0.325$
Shelter Renovations - 0.150 - - - 0.150
Playground Replacements 0.250 0.250 - - - 0.500
Trail Maintenance 0.100 0.100 - - - 0.200
TOTAL PROJECT COST 0.675$ 0.500$ -$ -$ -$ 1.175$
PROJECT FUNDING SOURCES
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT
FUNDING
Capital Projects Fund 0.675$ 0.500$ -$ -$ -$ 1.175$
TOTAL PROJECT FUNDING 0.675$ 0.500$ -$ -$ -$ 1.175$
PARKS, RECREATION, AND TOURISM PROJECTS
No Impact on Operating Budget
Description of Projects
Projects for the Parks, Recreation, and Tourism
Department include the bridge stabilization and
rehabilitation for the Campbell Covered Bridge, various
shelter renovations, playground replacements and
maintenance of the Swamp Rabbit Trail.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized,
benefit to the county and citizens)
Parks, Recreation, and Tourism capital projects are
budgeted in a capital project fund. Projects will be funded through a transfer from the Parks, Recreation,
and Tourism special revenue fund. No additional impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
172
PROJECT ITEMS
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL
PROJECT COST
Road Program 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
TOTAL PROJECT COST 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
PROJECT FUNDING SOURCES
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
O
PROJECT
FUNDING
Special Revenue Fund - Road Fee 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
TOTAL PROJECT FUNDING 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
SPECIAL REVENUE FUNDS
The Road Program Special Revenue Fund is used to finance capital infrastructure improvements. The FY20 22-
FY2026 Capital Improvement Program includes a budget of $60.00 million for infrastructure capital projects.
INFRASTRUCTURE IMPROVEMENTS
No Impact on Operating Budget
Description of Projects
Road improvements include rehabilitation and/or reconstruction of “worst roads” first on a countywide
basis. Planned projects are consistent with Council approved programs to reduce risk to public safety and to
improve deteriorating road structures. The road program also
includes a contribution for local municipality road programs.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to
the county and citizens)
Funding for the road program is included in the capital projects and is
financed through road maintenance fees. This project provides direct
benefit to citizens through road and bridge improvements. No
additional impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
173
PROJECT ITEMS
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL PROJECT
COST
Neighborhood Drainage Projects 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
Large Bridge Replacements 0.175 0.175 - - - 0.350
Flood Mitigation Program 2.350 2.350 2.350 2.350 2.350 11.750
Water Quality Retrofits/Stream Stable 2.912 2.912 2.300 2.300 2.300 12.724
TOTAL PROJECT COST 6.037$ 6.037$ 5.250$ 5.250$ 5.250$ 27.824$
PROJECT FUNDING SOURCES
FY2022
BUDGET
FY2023
BUDGET
FY2024
PROPOSED
FY2025
PROPOSED
FY2026
PROPOSED
TOTAL PROJECT
FUNDING
Enterprise Fund Revenue 6.037$ 6.037$ 5.250$ 5.250$ 5.250$ 27.824$
TOTAL PROJECT FUNDING 6.037$ 6.037$ 5.250$ 5.250$ 5.250$ 27.824$
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within these funds
are accounted for in the appropriate proprietary enterprise fund. The FY20 22-FY2026 Capital Improvement
Program includes a budget of $27.824 million for various capital projects in the area of stormwater.
STORMWATER ENTERPRISE FUND
No Impact on Operating Budget
Description of Projects
Capital projects for Stormwater include funding for neighborhood drainage projects, NPDES/water quality
retrofit projects, flood mitigation program, and large bridge replacements. These projects are consistent
with County Council’s goals for infrastructure which provide for funding to resolve drainage problems and
for stormwater flood project.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized,
benefit to the county and citizens)
Funding for these projects is included in the Stormwater
Enterprise Fund and funded through revenue received in that
fund. No additional impact on the operating budget is
anticipated.
County of Greenville Budget Document
Fiscal Years 2022 and 2023
174
THIS PAGE INTENTIONALLY LEFT BLANK