CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement Planning process.
This section of the document provides information on the multi-year capital improvement program, the
current program status, a summary of capital projects and a copy of the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify ma jor, infrequent and
nonrecurring projects, which should be financed over a period of years. Greenville County has selected a
programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a
comprehensive evaluation of project planning, justification, coordination of needs, priorities and relationship
to budgeting policies. Therefore, the capital improvement budget is considered with budget decisions.
Capital improvement programming is a continuous process involving yearly adjust ments. The CIP includes
capital projects recommended for fiscal years 2020 through 2024. Each fiscal year’s capital budget is
submitted in conjunction with its respective operating budget. The CIP multi-year plan includes projects for
which funding is currently available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2018 January – June 2019
Departmental
program plans
prepared and capital
projects submitted to
CIP team.
November
CIP Team
Review
Requests
December
CIP Team reviews,
prioritizes and
recommends capital
program
January -April
County Council
adopts CIP and
capital budget
May - June
County Departments prepare
CIP requests
by December 22
Budget/Planning
Staff compile project
information
by December 31
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County
Administrator’s
Recommended
Budget
County of Greenville Budget Document
Fiscal Years 2020 and 2021
164
66.5%
26.0%
7.5%
Capital Projects by Fund
Capital Projects Infrastructure Stormwater Enterprise
$0
$20
$40
$60
$80
$100
$120
$140Millions
CURRENT PROGRAM STATUS
The FY2020-FY2024 Capital Improvement Program totals $230.828 million for projects in the areas of
technological improvements, equipment, facilities, parks and recreation, infrastructure, and stormwater. For
the current biennium budget, capital projects total $88.805 million for FY2020 and $90.244 million for
FY2021. Below are graphic comparisons of budgeted capital projects by fund and by type. The following page
provides a detailed listing of capital projects and financing summary. In the capital projects fund, facility
expenditures are by far the greatest percentage. Capital projects funded by the County’s enterprise funds
are specific to each respective fund.
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements. The majority
of improvements are for facility improvements. Other large areas are stormwater, which includes drainage
projects and specific task force projects, and infrastructure, which includes road paving.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
165
FY2020 FY2021 FY2022 FY2023 FY2024 TOTAL
CAPITAL PROJECTS ($000 omitted) FUNDING SOURCE BUDGET BUDGET PROPOSED PROPOSED PROPOSED FUNDS
COUNTY GOVERNMENT DEPARTMENTS
Technological Improvements
Information Technology C apital P r ojec ts Fund 1.800$ 1.800$ 1.500$ 1.500$ 1.500$ 8.100$
GIS - Orthophotography C apital P r ojec ts Fund 0.127 - - - - 0.127
GIS - LiDAR Ac quisition C apital P r ojec ts Fund - 0.046 0.047 0.048 0.049 0.190
Register of Deeds Rec or ds Digitization C apital P r ojec ts Fund 0.035 0.035 - - - 0.070
Probate Court Imaging C apital P r ojec ts Fund 0.035 0.035 0.035 - - 0.105
TOTAL 1.997$ 1.916$ 1.582$ 1.548$ 1.549$ 8.592$
Facilities/Construction Projects
Law Enforcement Ramp Replacement C apital P r ojec ts Fund -$ 0.150$ -$ -$ -$ 0.150$
HVAC Control Upgra de - LEC Compl e x C apital P r ojec ts Fund - - 0.300 - - 0.300
HVAC Units for Animal C ar e C apital P r ojec ts Fund 0.150 0.150 - - - 0.300
Sheriff - Training Center Upgrade Debt Service - Bond - 3.000 - - - 3.000
P ublic Wor ks New M aintenanc e Fac ility C apital P r ojec ts Fund - - 0.500 0.700 - 1.200
Univ ersity Ridge Dev elopment Project Debt Serv ice - Bond 60.000 60.000 - - - 120.000
TOTAL 60.150$ 63.300$ 0.800$ 0.700$ -$ 124.950$
Equipment
Vehicle Replacements/Additions Debt Serv ice - Lease 7.000$ 7.000$ -$ -$ -$ 14.000$
Public Works Equipment C apital P r ojec ts Fund 0.800 0.800 - - - 1.600
EM S - LifeP ak M onitor s C apital P r ojec ts Fund 0.100 0.150 0.150 0.150 0.150 0.700
EM S - Str etc her and Stair C hair Replac ement C apital P r ojec ts Fund 0.100 0.150 0.150 0.150 - 0.550
TOTAL 8.000$ 8.100$ 0.300$ 0.300$ 0.150$ 16.850$
Parks, Recreation, and Tourism Projects
Shelter s, Bathr ooms, P ar k Renov ations C apital P r ojec ts Fund 0.600$ -$ -$ -$ -$ 0.600$
Conestee Stadium Renovations C apital P r ojec ts Fund 0.050 - - - - 0.050
Disc ov er y Island Water par k Slide/P lay Str uc tur e Replac ement C apital P r ojec ts Fund 0.450 - - - - 0.450
P av ilion Renov ation C apital P r ojec ts Fund 0.750 0.750 - - - 1.500
P leasant Ridge Renov ations C apital P r ojec ts Fund 0.100 - - - - 0.100
Swamp Rabbit - Repav ing of Tr ail C apital P r ojec ts Fund 0.100 0.100 - - - 0.200
Mt. Pleas ant Community Center Renovations C apital P r ojec ts Fund 0.150 - - - - 0.150
TOTAL 2.200$ 0.850$ -$ -$ -$ 3.050$
CAPITAL PROJECTS FUND TOTAL 72.347$ 74.166$ 2.682$ 2.548$ 1.699$ 153.442$
SPECIAL REVENUE FUNDS
Infrastructure
Roa d Progra m Road Program Fund 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
SPECIAL REVENUE FUNDS TOTAL 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
STORMWATER ENTERPRISE FUND
Equipment for Bridge Yard Enterprise Fund 0.380$ -$ -$ -$ -$ 0.380$
Neighborhood Drainage Projects Enterprise Fund 0.600 0.600 0.600 0.600 0.600 3.000
Flood M itigation P r ogr am Enterprise Fund 2.328 2.328 2.350 2.350 2.350 11.706
Water Q uality Retr ofit/Str eam Stabilization Enterprise Fund 1.150 1.150 - - - 2.300
STORMWATER ENTERPRISE FUND TOTAL 4.458$ 4.078$ 2.950$ 2.950$ 2.950$ 17.386$
TOTAL FOR ALL CAPITAL PROJECTS 88.805$ 90.244$ 17.632$ 17.498$ 16.649$ 230.828$
CIP FINANCING SUMMARY
FY2020-FY2024
County of Greenville Budget Document
Fiscal Years 2020 and 2021
166
Operating
Budget $35.448
$238.353 million
million
Capital
Budget
$89.244
million
Operating
Budget $48.934
$239.284 million
million
Capital
Budget
$87.617
million
Operating
Budget
92%
Capital
Budget
8%
Operating
Budget
91%
Capital
Budget
9%
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2020
The chart below shows the relationship between the operating budget and
capital expenditures for FY2020. Capital expenditures of $89.244 million
include capital projects of $21.719 million, a bond issue of $60.000 million, loan
proceeds of $7.000 million, and other capital items totaling $0.525 million. The
impact on the $238.353 million operating budget is $13.729 million, which is the
debt service for capital projects. There are no estimated operational costs for
new projects in FY2020. The $21.719 million for “pay-as-you-go” projects will
come from fund balances in each respective fund and/or special revenue.
Operating Impact $13.729 million for FY2020
Debt Service $13.729 million (Principal and Interest)
Operations and Maintenance $0 million
“Pay-as-you-go” - $21.719 million
Fiscal Year 2021
The chart below shows the relationship between the operating budget and
capital expenditures for FY2021. Capital expenditures of $87.617 million
include capital projects of $20.107 million, a bond issue of $60.000 million,
loan proceeds of $7.000 million, and other capital items totaling $0.510
million. The impact on the $239.284 million operating budget is $13.967
million, which is the debt service for capital projects. The remaining $ 34.967
million for “pay-as-you-go” projects will come from fund balances in each
respective funds and/or special revenue.
Operating Impact $13.967 million for FY2021
Debt Service $13.967 million (Principal and Interest)
Operations and Maintenance $0 million
“Pay-as-you-go” - $34.967 million
County of Greenville Budget Document
Fiscal Years 2020 and 2021
167
OPERATING
IMPACT DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating costs.
No Impact The project will cause no change in operating costs.
Negligible The impact will be very small; it will generate less than $10,000 per year in increased
operating expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating expenditures.
Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures.
High The impact will increase operating expenditures $100,001 or more.
FUNDING
SOURCE DESCRIPTION
Transfers A major source of smaller capital projects is transfers from operating funds in the County.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X, Section
14 of the constitution of the State of South Carolina, 1895, as amended, provides that
counties shall have the power to incur bonded indebtedness in such a manner and upon
such terms and conditions as the General Assembly shall prescribe by general law. General
obligation debt may be incurred only for public and corporate purpose in an amount not
exceeding 8% of the assessed value of all taxable property of each county.
Special Source
Revenue Bonds
The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties can
issue Special Source Revenue Bonds for the purpose of building or acquiring infrastructure
necessary to continue the economic development of a county. The portion of the CIP
which provides for the building or acquiring of infrastructure necessary to continue the
economic development of the County is included in the Infrastructure Bank and funded
through Special Source Revenue Bonds. The County has pledged the County portion of
the revenue stream from the multi-county parks, which includes fee-in-lieu-of-taxes
(FILOT) revenues.
Capital Projects
Reserve
Another source utilized in the CIP is the capital project reserve account. This account
contains any unspent funds from previously completed capital projects. The County's
Financial Policies allow the County Administrator to include recommendations in the
budget to dispose of unspent capital project funds.
Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem
revenues or fees. The CIP utilizes a road maintenance fee of $25 per vehicle to fund a
portion of the road program.
Enterprise Fund
Revenue
For the County's two enterprise funds, Solid Waste and Stormwater, improvements are
funded through each fund's respective revenue.
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional staff,
maintenance, or daily operational costs. The amount of operating budget impact for each project is referred
to in the following terms:
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These
sources include: transfers from other funds, general obligation bonds, special source revenue bonds, capital
project reserve funds, pay-as-you-go basis either though ad valorem revenues or fees, and enterprise fund
revenue. The chart below provides a description of funding sources.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
168
PROJECT ITEMS
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT COST
Information Technology 1.800$ 1.800$ 1.500$ 1.500$ 1.500$ 8.100$
GIS - Orthophotography 0.127 - - - - 0.127
GIS - LiDAR Acquisition - 0.046 0.047 0.048 0.049 0.190
Register of Deeds Digitization 0.035 0.035 - - - 0.070
Probate Court Imaging 0.035 0.035 0.035 - - 0.105
TOTAL PROJECT COST 1.997$ 1.916$ 1.582$ 1.548$ 1.549$ 8.592$
PROJECT FUNDING SOURCES
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT
Capital Projects Fund 1.997$ 1.916$ 1.582$ 1.548$ 1.549$ 8.592$
TOTAL PROJECT FUNDING 1.997$ 1.916$ 1.582$ 1.548$ 1.549$ 8.592$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition or
construction of major capital projects, other than those financed by proprietary funds. The FY2020-FY2024
Capital Improvement Program includes a budget of $153.442 million for various capital projects in the areas
of technological improvements, facility improvements, equipment, and parks and recreation projects. Each
project is discussed in detail on the following pages.
TECHNOLOGICAL IMPROVEMENTS
No Impact on Operating Budget
Description of Projects
Technological Improvements include funding for information technology, GIS , Register of Deeds, and
Probate Court. Information technology projects include upgrading various information technology projects,
such as software package maintenance, AS400 maintenance, and new IT projects and upgrades. System
upgrades are needed for increased reliability, speed and security. Funding is also included for GIS
Orthophotography and Elevation Contours Upgrade and LIDAR acquisition. These project s involve the
acquisition of countywide, digital orthophotography with a ground resolution of six inches per pixel and
countywide elevation contours at an interval of four feet. In addition, the annual Light Detection and
Training (LiDAR) elevation data from February 2021 through February 2024 will be acquired to determine
where ground features have changed in Greenville County. Register of Deeds digitization project will allow
for the digitization and indexing of all deeds and plats and will ensure the preservation and online availability
of nearly 450,000 permanent land records. Probate Court imaging will allow for imaging permanent records
and allow access to all records. All of these technological projects are consistent with the County Council’s
desire to provide for the technological needs of the County.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens )
Information technology improvements are budgeted in a capital project fund and financed with funds
transferred from the Infrastructure Bank. The budget reflects the cost of purchasing necessary equipment
and/or contractual costs. There will be a no operating budget impact due to any of these projects.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
169
PROJECT ITEMS
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL PROJECT
COST
Law Enforcement Ramp Replacement -$ 0.150$ -$ -$ -$ 0.150$
HVAC Controls Upgrade - LEC Complex - - 0.300 - - 0.300
HVAC Units for Animal Care 0.150 0.150 - - - 0.300
Training Center Upgrade - 3.000 - - - 3.000
PW Maintenance Facility - - 0.500 0.700 - 1.200
University Ridge Development Project 60.000 60.000 - - - 120.000
TOTAL PROJECT COST 60.150$ 63.300$ 0.800$ 0.700$ -$ 124.950$
PROJECT FUNDING SOURCES
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.150$ 0.300$ 0.800$ 0.700$ -$ 1.950$
Bond Issue 60.000 63.000 - - - 123.000
TOTAL PROJECT FUNDING 60.150$ 63.300$ 0.800$ 0.700$ -$ 124.950$
OPERATIONAL COSTS
Operating Impact -$ -$ 0.900$ 0.900$ 0.900$ 2.700$
FACILITIES/CONSTRUCTION PROJECTS
High Impact on Operating Budget
Description of Projects
Facility/Construction projects include funding for renovations and new construction. Renovations include the
replacement of the ramp at the Law Enforcement Center. The ramp is a wood and cement structure that has
been in place for 30 years and is need of replacing. Renovations also include installing automated controls
for the HVAC equipment at the Law Enforcement Center complex. The Law Enforcement Center currently
does not have any control system in place. The installation of a control system will result in energy savings.
HVAC units will also be installed at the Animal Care facility. The requested funds wil l pay for two HVAC units
and their installation into D12 and D15 dog kennels at the Animal Care adoption center. New construction
projects include the construction of a new Training Center facility for the Sheriff’s Office. Also,
A new maintenance facility for the Public Works Department will be constructed within the five year period.
There will also be a new development project for County properties, to include a new County facility.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Facility/construction projects are budgeted in a capital project fund. Renovation projects are financed with
funds transferred from the Infrastructure Bank. New construction projects will be financed with a bond
issue. Operating costs will include the debt service for the bond issue. Operating costs have not yet been
determined as the project has not yet been discussed and approved by County Council. There will be
additional operational costs beginning in FY2022 for the new Public Works maintenance facility. These costs
will include additional personnel and supplies/maintenance costs.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
170
PROJECT ITEMS
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT COST
Vehicle Replacements/Additions $ 7.000 $ 7.000 $ - $ - $ - $ 14.000
Public Works Equipment 0.800 0.800 - - - 1.600
EMS Life Pak Monitors 0.100 0.150 0.150 0.150 0.150 0.700
EMS Stretcher and Stair Chair Repl 0.100 0.150 0.150 0.150 - 0.550
TOTAL PROJECT COST 8.000$ 8.100$ 0.300$ 0.300$ 0.150$ 16.850$
PROJECT FUNDING SOURCES
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT
FUNDING
Capital Lease 7.000$ 7.000$ -$ -$ -$ 14.000$
Capital Projects Fund 1.000 1.100 0.300 0.300 0.150 2.850
TOTAL PROJECT FUNDING 8.000$ 8.100$ 0.300$ 0.300$ 0.150$ 16.850$
OPERATIONAL COSTS
Operating Impact -$ 0.080$ 0.160$ 0.180$ 0.200$ 0.620$
EQUIPMENT
Moderate Impact on Operating Budget
Description of Projects
Equipment projects include vehicle/heavy equipment replacements and additions and the replacement of
EMS equipment. Various vehicles and equipment will be replaced and/or added as needed through the
County’s master lease program. Vehicles/equipment additions include heavy equipment for Public Wor ks
offices, marked patrol cars, and other vehicles as needed. The EMS Division will replace LifePak cardiac
monitors over the next five years. The Physio-Control LifePak is used to monitor a patient’s cardiac activity
(heart rate and rhythm), perform a 12 lead EKG, perform pacing functions to stabilize a heart rhythm and
perform cardioversion or defibrillate a patient’s heart when it is in legal rhythm. The EMS Division will also
replace stretcher and stair-chairs for the EMS vehicles.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized,
benefit to the county and citizens)
Vehicle/equipment replacements and additions project is
budgeted in a capital project fund and is financed with a
capital lease. Cardiac monitor replacement project is
budgeted in a capital project fund and is financed with a
transfer from the Infrastructure Bank. Operating costs will
include the debt service for the capital lease.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
171
PROJECT ITEMS
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT COST
Shelters, Bathroom, Park Renovations 0.600$ -$ -$ -$ -$ 0.600$
Conestee Stadium Renovations 0.050 - - - - 0.050
Discovery Island Waterpark Slide Replacement 0.450 - - - - 0.450
Pavilion Renovatons 0.750 0.750 - - - 1.500
Pleasant Ridge Renovations 0.100 - - - - 0.100
Swamp Rabbit Repaving 0.100 0.100 - - - 0.200
Mt. Pleasant Community Center Renovations 0.150 - - 0.150
TOTAL PROJECT COST 2.200$ 0.850$ -$ -$ -$ 3.050$
PROJECT FUNDING SOURCES
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT
FUNDING
Capital Projects Fund 2.200$ 0.850$ -$ -$ -$ 3.050$
TOTAL PROJECT FUNDING 2.200$ 0.850$ -$ -$ -$ 3.050$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
PARKS, RECREATION, AND TOURISM PROJECTS
No Impact on Operating Budget
Description of Projects
Projects for the Parks, Recreation, and Tourism Department
include maintenance for park shelter renovations and
enhancements/maintenance at several park facilities, sign
replacements, parking lot re-stripings, park shelter renovations
and enhancements/maintenance at several park facilities.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit
to the county and citizens)
Parks, Recreation and Tourism capital projects are budgeted in a capital project fund. Projects will be funded
through a transfer from the Parks, Recreation, and Tourism special revenue fund. No additional impact on
the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
172
PROJECT ITEMS
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL
PROJECT COST
Road Program 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
TOTAL PROJECT COST 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
PROJECT FUNDING SOURCES
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
O
PROJECT
FUNDING
Special Revenue Fund - Road Fee 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
TOTAL PROJECT FUNDING 12.000$ 12.000$ 12.000$ 12.000$ 12.000$ 60.000$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
SPECIAL REVENUE FUNDS
The Road Program Special Revenue Fund is used to finance capital infrastructure improvements. The
FY2020-FY2024 Capital Improvement Program includes a budget of $60.000 million for various infrastructure
capital projects.
INFRASTRUCTURE IMPROVEMENTS
No Impact on Operating Budget
Description of Projects
Road improvements include rehabilitation and/or reconstruction of “worst roads” first on a countywide
basis. Planned projects are consistent with Council approved
programs to reduce risk to public safety and to improve
deteriorating road structures. The road program also includes a
contribution for local municipality road programs.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to
the county and citizens)
Funding for the road program is included in the capital projects
fund and is financed through road maintenance fees. This project
provides a direct benefit to citizens through road and bridge
improvements. No additional impact on the operating budget is
anticipated.
County of Greenville Budget Document
Fiscal Years 2020 and 2021
173
PROJECT ITEMS
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL PROJECT
COST
Neighborhood Drainage Projects 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
Equipment for Bridge Yard 0.380 - - - - 0.380
Flood Mitigation Program 2.328 2.328 2.350 2.350 2.350 11.706
Water Quality Retrofits/Stream Stable 1.150 1.150 - - - 2.300
TOTAL PROJECT COST 4.458$ 4.078$ 2.950$ 2.950$ 2.950$ 17.386$
PROJECT FUNDING SOURCES
FY2020
BUDGET
FY2021
BUDGET
FY2022
PROPOSED
FY2023
PROPOSED
FY2024
PROPOSED
TOTAL PROJECT
FUNDING
Enterprise Fund Revenue 4.458$ 4.078$ 2.950$ 2.950$ 2.950$ 17.386$
TOTAL PROJECT FUNDING 4.458$ 4.078$ 2.950$ 2.950$ 2.950$ 17.386$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within these funds
are accounted for in the appropriate proprietary enterprise fund. The FY20 20-FY2024 Capital Improvement
Program includes a budget of $17.386 million for various capital projects in the area of stormwater.
STORMWATER ENTERPRISE FUND
No Impact on Operating Budget
Description of Projects
Capital projects for Stormwater include funding for neighborhood drainage projects, NPDES/water quality
retrofit projects, and flood studies. These projects are consistent
with County Council’s goals for infrastructure which provide for
funding to resolve drainage problems and for stormwater flood
projects.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to
the county and citizens)
Funding for these projects are included in the Stormwater Enterprise
Fund and funded through revenue received for that fund. No
additional impact on the operating budget is anticipated.