County of Greenville Budget Document
Fiscal Years 2014 and 2015
9
County Administrator
Joseph Kernell
jkernell@greenvillecounty.org
(864) 467-7105
www.greenvillecounty.org
May 21, 2013
Dear Chairman Taylor and Members of County Council:
I am pleased to present Greenville County’s biennium budget for Fiscal Year 201 4 and Fiscal Year 2015. This
document provides the financial structure for the programs and services which Greenville County government
will be undertaking over the next two years. The budget provides the resources needed to ensure the delivery
of governmental services in a fiscally responsible manner. This budget is a continuation of the financially sound
practices Greenville County government has established and embraced.
BUDGET PROCESS
The two-year budget process will be similar to the process in prior years. Budget workshops are proposed to
review the budget with County Council. In order to comply with section 4 -9-140 of the State Code, a staggered
ordinance adoption process will be followed. As in previous years, the budget ordinances will be reviewed
concurrently. First reading is scheduled for May 21, 2013 and second reading for June 4, 2013. The public
hearing and third reading for the fiscal year 2014 budget is scheduled for June 18, 2013. The public hearing and
third reading for the fiscal year 2015 budget is scheduled for August 2013.
COUNTY FINANCIAL OVERVIEW
The preparation of the biennium budget was more challenging this year due to the continued condition of the
economy on the federal and state level. Most counties in South Carolina continue facing significant budgetary
challenges as a result of national and state economies. Although Greenville County is certainly not immune to
the resulting fiscal pressure, the County is positioned to deal with the impact of the economic uncertainty
because of solid fiscal planning, strong financial management, and conservative budgeting during the past
several years. Due to the current economic uncertainty, it is imperative to follow our established financial
policies and maintain sufficient fund balances which is reflected in the County’s General Fund Balance of $50
million.
Over the last few years, the County has been faced with responding to several revenue issues due to the
economic downturn in the country. Fees collected by areas related to property development, such as
building permits, subdivision reviews, and recording of deeds, have stabilized throughout the cur rent fiscal year.
The County also faced pressure responding to increases in health care costs; providing reasonable pay to
employees; escalating utility costs; and fluctuating fuel costs.
As a result of these issues, the staff has spent many hours reviewing current service levels and budgets, with an
emphasis on streamlining governmental services, reducing unnecessary expenses, and realigning resources. In
the current year, savings measures have been instituted and operating expenditures have been reduced.
Additional efforts to improve efficiency and reduce costs are being reviewed and will be implemented if feasible.
Due to the uncertainty of today’s economic environment at both the national and state level, Greenville
County’s budget reflects minimal increases in operating expenditures in the General Fund. The FY2014/FY2015
County of Greenville Budget Document
Fiscal Years 2014 and 2015
10
ADOPTED ADOPTED ADOPTED ADOPTED
BUDGET BUDGET BUDGET BUDGET
FY2012 FY2013 FY2013-2014 FY2014-2015
GENERAL FUND 128,191,849$ 131,646,023$ 140,195,909$ 144,814,151$
SPECIAL REVENUE FUNDS 27,834,921$ 27,429,119$ 44,372,415$ 44,466,951$
DEBT SERVICE FUND 19,593,692$ 17,731,154$ 18,501,715$ 18,233,772$
ENTERPRISE FUND 17,338,509$ 18,778,407$ 22,003,332$ 19,332,006$
TOTAL BUDGET 192,958,971$ 195,584,703$ 225,073,371$ 226,846,880$
Percent Change 15.08% 0.79%
biennium budget still allows us to provide and meet our current level of services that are of deserved
importance to the citizens of Greenville County.
MAJOR BUDGET INITIATIVES
The recommended budget seeks to maintain the Council’s priorities:
1. Public Safety: reduce crime; maintain a manageable jail population; reduce EMS response time
2. Infrastructure: reduce traffic congestion; establish a stormwater management system that allows for
growth
3. Fiscal Condition: maintain triple A bond ratings; maintain levels in quality of services
4. Public Transit: increase public transportation; provide for transit oriented economic development
5. Economic Development: increase workforce quality; increase number of jobs/high paying jobs
6. Comprehensive Planning: complete the comprehensive plan
7. Diversity in Employment
The budget provides the necessary resources to address the ongoing needs of our citizens and the delivery of
public services.
BUDGET IN BRIEF
Greenville County’s biennium budget for FY2014 and FY2015 totals $451,920,251. The FY2014 budget totals
$225,073,371 which is 15.08% greater than the FY2013 budget of $195,584,703. The FY2015 budget totals
$226,846,880 which is 0.79% greater than the FY2014 budget. The following chart provides an overview of the
County’s overall biennium budget for Fiscal Years 2014 and 2015 with comparison to the last biennium budget.
The County’s total budget includes the General Fund, selected Special Revenue Funds, Debt Service, and
Enterprise Funds.
The General Fund operating and capital budget for the two-year period of FY2014 and FY2015 totals
$285,010,060. The General Fund operating budget for FY2014 (including salaries, operating, contractual and
capital line items) totals $140,195,909. This represents an increase of $8,549,886 or 6.49% from the FY2013
budget. The General Fund operating budget for FY2015 (including salaries, operating, contractual, and capital
line items) totals $144,814,151. This represents an increase of $4,618,242 or 3.29% as compared to the FY2014
budget. The increase is attributed to salary increases, moderate increases for health insurance, and the addition
of public safety positions.
Revenue Assumptions
Ad Valorem Taxes- The County’s base property valuation is estimated to be $2.01 billion, reflecting a growth in
the base of about 3% over the prior year. In Fiscal Year 2014, three-tenths of one mil will be transferred from
the Solid Waste enterprise fund to the General Fund. Also, one-tenth of one mil will be transferred from COPs
debt service fund to General Obligation Bond debt service fund. This transfer will be accomplished due to
reduction in the debt service obligations in the Certificates of Participation. Over 55 % of Greenville County’s
budgeted revenue is derived from local ad valorem property taxes.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
11
Expenditure Highlights
The County’s expenditures are divided across several major service areas. The total County budget is projected
to increase by 15.08%, with the General Fund increasing by 6.49%. Noteworthy changes to expenditures include:
• Sheriff’s Office – Goal 1: Public Safety
Funding is included in the biennium budget for additional deputy positions. The budget adds six positions for
FY2014 and six positions for FY2015 to respond to the increased volume of calls.
• Coroner’s Office – Goal 1: Public Safety
Funding is included in the biennium budget to upgrade a part-time deputy coroner position to full-time. Funding
is also included to add one administrative position.
• Emergency Medical Services - Goal 1: Public Safety
Funding is included in the biennium budget for two communication specialist positions. The budget also includes
funds for additional medical supplies and increases in contractual obligations.
• Detention Center - Goal 1: Public Safety
Funding is included in the biennium budget for additional detention offi cer positions. The budget adds six
positions for FY2014 and four positions for FY2015.
• Forensics/Records - Goal 1: Public Safety
Funding is included in the biennium budget for two additional positions for the Forensic Division and one
additional position for the Records Division.
• Stormwater - Goal 2: Infrastructure
The budget includes funding for neighborhood drainage improvement projects in the amount of $600,000 in
each year of the two year biennium budget. In addition, $4.4 million has been appropriated in each year for
funding flood projects as part of the flood hazard mitigation program. Funds are also includes for NPDES wa ter
quality retrofits and to implement a centralized electronic permitting process. Funding will be provided from the
current stormwater utility fee.
• Road Program - Goal 2: Infrastructure
In the road program, a total of $9 million is programmed for the biennium -- $4.5 million for each year. Funds
are included for road paving, sidewalks, bridge replacements, road improvements, and traffic calming. The
County’s local government revenue sharing program with municipalities is proposed to continue at the cur rent
level of $700,000 annually.
• Planning and Code Compliance - Goal 2: Infrastructure
Funding is included in the biennium budget for two additional inspector positions and one permit technician
position. These positions are funded by increases in construction permit revenue.
• Maintenance of Current Operating Expenditures – Goal 3: Fiscal Condition
As part of the budget development process, staff conducted a line item review of departmental operations and
service delivery. Through this review, it was determined that a majority of operating expenditures could be held
at current levels for the biennium. In addition, many departments reduced certain line items for the biennium.
Increases for fuel, vehicle, and utility costs were included in the budget as these areas have increased
substantially throughout the current biennium. Any other increases in operating expenditures are a result of the
inclusion of expansion packages for enhanced services.
• Employee Benefits – Goal 3: Fiscal Condition
The budget includes funding for health and dental insurance to keep pace with the rising cost of health care. A
moderate increase for health and dental insurance rates has been projected for both years of the biennium.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
12
• Salary Adjustment of 3.0% - Goal 3: Fiscal Condition
The proposed budget anticipates an average 3.0% increase for both years of the biennium. These salary
adjustments reflect the County’s commitment to pay for performance of our employees, our most valuable
resource.
• Vehicle Replacement - Goal 3: Fiscal Condition
The budget includes funding to continue vehicle replacements for both fiscal years. A total of $ 2,000,000 of
vehicles and equipment is scheduled in both years of the biennium utilizing the master lease program.
• Grants - Goal 3: Fiscal Condition
Funding for matching grants in the amount of $200,000 for each of the fiscal years is included in the budget.
• Capital Projects - Goal 3: Fiscal Condition
A total of $10.370 million for FY2014 and $35.827 million for FY2015 is included in the Capital Improvement
Program to support technological enhancements, equipment replacement, and facility improvements.
• Economic Development Funding - Goal 5: Economic Development
The proposed budget includes $2,223,547 for the biennium to be appropriated for the County’s economic
development programs. This includes $321,000 for the Upstate Alliance for the two-year budget. The remaining
funds are allocated to the Greenville Area Development Corporation (GADC) for the biennium.
As we bring to a close yet another budget development process, it has been a pleasure to work with the County
Council to allocate the public resources in accomplishing the County’s goals. Also, it is a privilege serving with
the professionals that make up the entire County organization as we strive to provide the level of services
needed and desired by our citizens. I sincerely appreciate the commitment of our staff in serving our citizens
and conducting the County’s business.
Sincerely,
Joseph M. Kernell
County Administrator
County of Greenville Budget Document
Fiscal Years 2014 and 2015
13
LONG-TERM GOALS AND PRIORITIES
Consistent with the County’s financial policies of providing a financially stable fiscal plan, budget development
directives from County Council called for streamlining the government focus. This secti on outlines seven long-
term goals that have shaped budgetary decisions for the upcoming biennium.
♦ Public Safety
♦ Infrastructure
♦ Fiscal Condition
♦ Public Transit
♦ Economic Development
♦ Comprehensive Planning
♦ Employment Diversity
PRIORITY AREA I: PUBLIC SAFETY
Provide a safe community for citizens
Maintain manageable Detention Center population. Facilitate coordination between magistrates and jail
regarding bond hearings and review alternatives to incarceration to reduce length of stay for inmates.
Reduce EMS Response Time. Provide for the implementation of the high performance EMS program to achieve a
ninetieth percentile response time and overall response time of 12 minutes and 30 seconds or less.
Reduce Crime. Provide funding to support public safety functions that address crime and the effects of drug and
gang activity within our community.
PRIORITY AREA II: INFRASTRUCTURE
Establish adequate funding and management systems to provide for County infrastructure
Provide for roads/infrastructure needs. Support infrastructure to meet the community’s growth. Develop an
effective road network for the county to reduce traffic congestion.
Provide for Stormwater Management System. Provide funding for drainage projects and stormwater system
that allows for growth.
PRIORITY AREA III: FISCAL CONDITION
Operate within a fiscally responsible framework
Maintain Triple A Bond Ratings. Provide for long-term fiscal viability and fiscal management of fund balance
reserves through operating efficiencies, cost savings, and revenue enhancement.
Maintain Levels in Quality Services. Review services provided by County Departments, their current level, any
mandated levels, and opportunities for streamlining.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
14
PRIORITY AREA IV: PUBLIC TRANSIT
Rethink public transportation to encourage ridership; reduce
traffic congestion and improve air quality
Provide for Transit Oriented Economic Development. Consider public transportation availability when planning
for economic development to assist with ingress/egress of the workforce.
Increase Public Transportation. Continue to financially support the operations of the Greenville Transit
Authority/Greenlink and the development of a community wide transit vision and master plan with other
community based groups.
PRIORITY AREA V: ECONOMIC DEVELOPMENT
Improve economic development climate within County to promote long term
financial stability and provide a livable community for citizens
Increase Quality of the Workforce. Create and encourage public/private partnerships with county offices, local
and state educational institutions, and private and non-profit organizations to meet the training needs of
today’s workforce and targeted industries.
Increase Number of Jobs/High Paying Jobs. Improve the quality of life of every Greenville County citizen by
facilitating investment and job growth from new and existing companies and small businesses.
PRIORITY AREA VI: COMPREHENSIVE PLANNING
Prepare for the future ever mindful of the changing dynamics of growth
Complete Comprehensive Plan. Facilitate the comprehensive planning process for the County utilizing the
involvement of the stakeholders including citizens, school district, utilities, recreation district, fire districts and
municipalities. Coordinate implementation of comprehensive plan and infrastructure improvements with
appropriate entities.
PRIORITY AREA VII: EMPLOYMENT DIVERSITY
Value and respect diversity in experience and perspectives, take advantage
of the backgrounds and abilities that employees provide, and
promote greater diversity in positions of supervision and leadership
County of Greenville Budget Document
Fiscal Years 2014 and 2015
15
Maintain manageable
Detenti on Center
population
Public Safety,
Law Enforcement,
Judicial Se rvice s
Provi de a
safe communi ty
for citize ns
Reduce
EMS
response ti me
County Administration,
Public Safety
Reduce
cri me
Law Enforcement
Servi ces
Provide for County
infrastructure to meet
community's needs
Devel op effecti ve
road network and provide
for stormwater
management
County Council and
Administration,
Community Development
& Planning
Operate within
fiscally re sponsible
framework
Maintain Triple A
Bond Ratings and levels of
quality se rvice
County Administration, All
Departments/Offi ces
Provide for
public transit
Increase public
transportation and improve
air quality
County Council,
County Administration
Improve
economi c devel opment
clim ate
Increase quality of
workforce and number of
jobs
County Council and
A dm inistration, Gre e nville
Area Devel opment
Provi de
comprehensive planning
for growth
Compl ete
Comprehensi ve Pl an
County Council and
Administration, Planning
Promote
empl oyment
dive rsity
Prom ote dive rsity in
position of supervision and
l eadershi p
A ll
Departments
LINKING LONG- AND SHORT-TERM GOALS
County of Greenville Budget Document
Fiscal Years 2014 and 2015
16
THIS PAGE INTENTIONALLY LEFT BLANK