CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement Planning process. This
section of the document provides information on the multi-year capital improvement program, the current
program status, a summary of capital projects and a copy of the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent and
nonrecurring projects, which should be financed over a period of years. Greenville County has selected a
programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a comprehensive
evaluation of project planning, justification, coordination of needs, priorities and relationship to budgeting
policies. Therefore, the capital improvement budget is considered with budget decisions. Capital improvement
programming is a continuous process involving yearly adjustments. The CIP includes capital projects
recommended for fiscal years 2014 through 2018. Each fiscal year’s capital budget is submitted in conjuncti on
with its respective operating budget. The CIP multi-year plan includes projects for which funding is currently
available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2012 January – June 2013
Departmental
program plans
prepared and capital
projects submitted to
CIP team.
November
CIP Team
Review
Requests
December
CIP Team reviews,
prioritizes and
recommends capital
program
January -April
County Council
adopts CIP and
capital budget
May - June
County Departments prepare
CIP requests
by December 17
Budget/Planning
Staff compile project
information
by December31
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County
Administrator’s
Recommended
Budget
County of Greenville Budget Document
Fiscal Years 2014 and 2015
158
73%
3%
24%
Capital Projects by Fund
Capital Projects Stormwater Enterprise Solid Waste Enterprise
$0
$10
$20
$30
$40
$50
$60Millions
CURRENT PROGRAM STATUS
The FY2014-FY2018 Capital Improvement Program totals $119.388 million for projects in the areas of
technological improvements, equipment, facilities, infrastructure, solid waste, and stormwater. For the current
biennium budget, capital projects total $17.345 million for FY2014 and $42.743 million for FY2015. Below are
graphic comparisons of budgeted capital projects by fund and by type. The following page provides a detailed
listing of capital projects and financing summary. In the capital projects fund, facility expenditures are by far the
greatest percentage. Capital projects funded by the County’s enterprise funds are specific to each respective
fund.
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements. The majority of
improvements are for facility improvements. Other large areas are stormwater, which includes drainage projects
and specific task force projects, and infrastructure, which includes road paving.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
159
FY2014 FY2015 FY2016 FY2017 FY2018 TOTAL
CAPITAL PROJECTS ($000 omitted) FUNDING SOURCE BUDGET BUDGET PROPOSED PROPOSED PROPOSED FUNDS
COUNTY GOVERNMENT DEPARTMENTS
Technological Improvements
Information Technology C apital P r ojec ts Fund 1.000$ 1.000$ 1.000$ 1.000$ 1.000$ 5.000$
TOTAL 1.000$ 1.000$ 1.000$ 1.000$ 1.000$ 5.000$
Equipment
Voting M ac hines - Registr ation/Elec tion C apital P r ojec ts Fund 0.165$ 0.165$ -$ -$ -$ 0.330$
TOTAL 0.165$ 0.165$ -$ -$ -$ 0.330$
Facilities
Property & Ev idence Storage Renov ation C apital P r ojec ts Fund 0.070$ 0.050$ -$ -$ -$ 0.120$
Mobile Shelving for Records C apital P r ojec ts Fund 0.106$ 0.112$ -$ -$ -$ 0.218$
Detention C enter Security C apital P r ojec ts Fund 0.209$ -$ -$ -$ -$ 0.209$
Detention Center Slider Gate Upgrade C apital P r ojec ts Fund 0.120$ -$ -$ -$ -$ 0.120$
M agistr ate C onsolidation C apital P r ojec ts Fund 3.000$ -$ -$ -$ -$ 3.000$
Ar c hitec tur al Design/Building Bond Issue 1.200$ 30.000$ 20.000$ -$ -$ 51.200$
TOTAL 4.705$ 30.162$ 20.000$ -$ -$ 54.867$
Infrastructure
Roa d Progra m Special Revenue Fund 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
TOTAL 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
CAPITAL PROJECTS FUND TOTAL 10.370$ 35.827$ 27.000$ 7.000$ 7.000$ 87.197$
SOLID WASTE ENTERPRISE FUND
Solid Waste
Bridge Connection between units Enterprise Fund -$ 0.250$ 1.350$ -$ -$ 1.600$
Leac hate P ump Station Enterprise Fund 0.460$ -$ -$ -$ -$ 0.460$
Equipment Replacement Program Enterprise Fund 0.250$ 0.400$ 0.650$ 0.250$ 0.350$ 1.900$
SOLID WASTE ENTERPRISE FUND TOTAL 0.710$ 0.650$ 2.000$ 0.250$ 0.350$ 3.960$
STORMWATER ENTERPRISE FUND
Neighborhood Drainage Projects Enterprise Fund 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
Flood Projects and Studies Enterprise Fund 4.400$ 4.401$ 4.400$ 4.000$ 4.000$ 21.201$
NP DES Water Q uality Retr ofits Enterprise Fund 0.500$ 0.500$ 0.500$ 0.500$ 0.500$ 2.500$
C entr alized Elec tr onic P er mitting Enterprise Fund 0.765$ 0.765$ -$ -$ -$ 1.530$
STORMWATER ENTERPRISE FUND TOTAL 6.265$ 6.266$ 5.500$ 5.100$ 5.100$ 28.231$
TOTAL FOR ALL CAPITAL PROJECTS 17.345$ 42.743$ 34.500$ 12.350$ 12.450$ 119.388$
CIP FINANCING SUMMARY
FY2014-FY2018
County of Greenville Budget Document
Fiscal Years 2014 and 2015
160
Operating
Budget
91%
Capital
Budget
9%
Operating
Budget $24.953
$154.889 million
million
Capital
Budget
$17.679
million
Operating
Budget $21.482
$153.521 million
million
Capital
Budget
$12.743
million
Operating
Budget
92%
Capital
Budget
8%
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2014
The chart below shows the relationship between the operating budget and capital
expenditures for FY2014. Capital expenditures of $17.679 million include capital
projects of $16.145 million and a bond issue of $1.2 million. The impact on the
$154.889 million operating budget is $8.808 million, which is the debt service for
capital projects. There are no estimated operational costs for new projects in
FY2014. The $16.145 million for “pay-as-you-go” projects will come from fund
balances in each of the respective funds.
Operating Impact $8.808 million for FY2014
Debt Service $8.808 million (Principal and Interest)
Operations and Maintenance $0 million
“Pay-as-you-go” - $16.145 million
Fiscal Year 2015
The chart below shows the relationship between the operating budget and
capital expenditures for FY2015. Capital expenditures of $42.979 million include
capital projects of $12.743 million and a bond issue of $30.000 million. The
impact on the $153.521 million operating budget is $8.739 million. The
remaining $12.743 million for “pay-as-you-go” projects will come from fund
balances in each respective funds and/or special revenue.
Operating Impact $8.739 million for FY2015
Debt Service $8.739 million (Principal and Interest)
Operations and Maintenance $0.000 million
“Pay-as-you-go” - $12.743 million
County of Greenville Budget Document
Fiscal Years 2014 and 2015
161
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional staff,
maintenance, or daily operational costs. The amount of operating budget impact for each project is referred to
in the following terms:
OPERATING
IMPACT
DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating costs.
No Impact The project will cause no change in operating costs
Negligible The impact will be very small; it will generate less than $10,000 per year in increased
operating expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating expenditures.
Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures.
High The impact will increase operating expenditures $100,001 or more.
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These sources
include: transfers from the County’s general operating fund, general obligation bonds, special source revenue
bonds via the County’s Infrastructure Bank, capital project reserve, pay-as-you-go basis either through ad
valorem revenues or fees, and enterprise fund revenue. The chart below provides a description of funding
sources.
FUNDING SOURCE DESCRIPTION
General Fund
Transfer
A major source of smaller capital projects is transfers from the County’s general
operating fund.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X,
Section 14, of the constitution of the State of South Carolina, 1895, as amended,
provides that counties shall have the power to incur bonded indebtedness in such a
manner and upon such terms and conditions as the General Assembly shall prescribe by
general law. General obligation debt may be incurred only for public and corporate
purpose in an amount not exceeding 8% of the assessed value of all taxable property of
each county.
Special Revenue
Bonds
The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties
can issue Special Source Revenue Bonds for the purpose of building or acquiring
infrastructure necessary to continue the economic development of a county. The
portion of the CIP which provides for the building or acquiring of infrastructure
necessary to continue the economic development of the County is included in the
Infrastructure Bank and funded through Special Source Revenue Bonds. The County has
pledged the County portion of the revenue stream from the multi-county parks, which
includes fee-in-lieu-of-taxes (FILOT) revenues.
Capital Projects
Accounts
Another source utilized in the CIP is the capital project reserve account. This account
contains any unspent funds from previously completed capital projects. The County’s
Financial Policies allow the County Administrator to include recommendations in the
budget to dispose of unspent capital project funds.
Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem
revenues or fees. The CIP utilizes a road maintenance fee of $15 per vehicle to fund a
portion of the road program.
Enterprise Fund
Revenue
For the County’s two enterprise funds, Solid Waste and Stormwater, improv ements are
funded through each fund’s respective revenue.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
162
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Information Technology 1.000$ 1.000$ 1.000$ 1.000$ 1.000$ 5.000$
TOTAL PROJECT COST 1.000$ 1.000$ 1.000$ 1.000$ 1.000$ 5.000$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 1.000$ 1.000$ 1.000$ 1.000$ 1.000$ 5.000$
TOTAL PROJECT FUNDING 1.000$ 1.000$ 1.000$ 1.000$ 1.000$ 5.000$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition or construction
of major capital projects, other than those financed by proprietary funds. The FY201 4-FY2018 Capital
Improvement Program includes a budget of $87.197 million for various capital projects in the areas of public
safety, technological improvements, facility improvements, and inf rastructure improvements. Each project is
discussed in detail on the following pages.
TECHNOLOGICAL IMPROVEMENTS
Project Name: INFORMATION TECHNOLOGY
No Operating Budget Impact
Project Description
This project entails upgrading various sections of the County’s
information technology infrastructure, and replacing physical network
wiring. System upgrades are needed for increased reliability, speed and
security.
Project Justification
This project is consistent with the County Council’s desire to provide for
the technological needs of the County.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to
the county and citizens)
Information technology improvements are budgeted in a capital
project fund and financed with funds from the capital project reserve. The budget reflects the cost or purchasing
necessary equipment and/or contractual costs. No additional operating costs are expected to be incurred
County of Greenville Budget Document
Fiscal Years 2014 and 2015
163
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Voting Machine s for Re gistration/Ele c 0.165$ 0.165$ -$ -$ -$ 0.330$
TOTAL PROJECT COST 0.165$ 0.165$ -$ -$ -$ 0.330$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.165$ 0.165$ -$ -$ -$ 0.330$
TOTAL PROJECT FUNDING 0.165$ 0.165$ -$ -$ -$ 0.330$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
EQUIPMENT
Project Name: VOTING MACHINES
No Impact on Operating Budget
Project Description
This project will allow for the acquisition of 150 voting machines over the biennium
period of FY2014/FY2015. .
Project Justification
South Carolina Code of Laws (7-13-1680) requires counties to provide at least one
voting machine for every 250 registered voters in each precinct. Greenville County's
growth has placed the county government in the position of not being able to meet
that standard. For Greenville County to meet the legal minimum, a total of 150
more voting machines are needed. Refurbished voting machines are being quoted
at $2,200.00 each. Recent situations in Richland County have put all election offices under public review. This
purchase (over the next two budgets) will bring Greenville County into compliance .
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The acquisition of voting machines for the Registration and Election Office is budgeted in a capital project fund
and financed with funds from the capital project reserve. The budget reflects the cost of purchasing necessary
equipment. No additional operating costs are expected to be incurred.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
164
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Property & Evi dence Storage 0.070$ 0.050$ -$ -$ -$ 0.120$
TOTAL PROJECT COST 0.070$ 0.050$ -$ -$ -$ 0.120$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.070$ 0.050$ -$ -$ -$ 0.120$
TOTAL PROJECT FUNDING 0.070$ 0.050$ -$ -$ -$ 0.120$
OPERATIONAL COSTS
Operating Impact 0.020$ 0.020$ -$ -$ -$ 0.040$
Cumulative Operating Impact 0.020$ 0.020$ -$ -$ -$ 0.040$
FACILITIES
Project Name: PROPERTY AND EVIDENCE STORAGE RENOVATION
Slight Impact on Operating Budget
Project Description
This project will complete the renovation of existing storage spaces assigned
to Property and Evidence. Renovation of the storage areas will provide the
opportunity to work toward the goal of having a full inventory. Funding will
also be used to conduct a systematic review process to remove
evidence/property designated/authorized for release/destruction and bar
code items for storage.
Project Justification
This project is consistent with the requirements of CALEA (Commission for
Accreditation of Law Enforcement Agencies). CALEA standards mandate that
a property and evidence section should provide for the security and control
of seized, recovered, and evidentiary property as well as abandoned, lost, or
found property.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Renovation of the Property and Evidence section of the Forensic Division is budgeted in a capital project fund
and financed with funds from the capital projects reserve. The budget reflects funding of $ 120,000 for the five-
year CIP planning period. The project will require funding for temporary personnel while the renovat ions are
being complete so that the property and evidence can be relocated in a timely manner.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
165
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Mobile Shelving for Records 0.106$ 0.112$ -$ -$ -$ 0.218$
TOTAL PROJECT COST 0.106$ 0.112$ -$ -$ -$ 0.218$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.106$ 0.112$ -$ -$ -$ 0.218$
TOTAL PROJECT FUNDING 0.106$ 0.112$ -$ -$ -$ 0.218$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
FACILITIES
Project Name: MOBILE SHELVING FOR RECORDS
No Impact on Operating Budget
Project Description
This project will provide a mobile shelving system to newly
acquired storage space at Central Records. The mobile system
provides 12,200 storage spaces for boxes. The system will consist
of three separate mobile units that can be installed during the
biennium. During the first year of the biennium budget, this project
will provide the installation of the first and largest mobile unit that
will accommodate the relocation of 6,736 stored boxes from the
South storage facility to the Central Main storage area, plus
provide an additional 2,100 spaces. During the second year of the
biennium budget, two additional mobile units will provide 2,280
spaces to accommodate future growth in the County.
Project Justification
The Greenville County Archives Records Center oversees the management of stored records generated by
County departments who desire a centralized storage facility for inactive and archival records. The South
Carolina Code of Laws mandates that local governments manage their public record documents an d data. This
project will allow centralization of the record retention process and will provide space for future growth.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The Mobile Shelving for Records project is budgeted in a capital project fund and financed with funds from the
capital projects reserve. The budget reflects funding of $218,000 for the five-year CIP planning period. No
additional operating costs are expected to be incurred.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
166
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Detenti on Center Securi ty 0.209$ -$ -$ -$ -$ 0.209$
TOTAL PROJECT COST 0.209$ -$ -$ -$ -$ 0.209$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.209$ -$ -$ -$ -$ 0.209$
TOTAL PROJECT FUNDING 0.209$ -$ -$ -$ -$ 0.209$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
FACILITIES
Project Name: DETENTION CENTER SECURITY
No Impact on Operating Budget
Project Description
This project will provide for the upgrade of the Detention Center control
room. In 2012, Com-Tec Security upgraded the audio portion of the
system by replacing the Com-Tec amplifiers. This project will complete
the upgrade by putting in place the remaining hardware portion of the
system.
Project Justification
This project is consistent with County Council’s goal of providing
adequate public safety. South Carolina Minimum Standards for Local
Detention Facilities required all facilities to have a two-way intercom
system for emergency communications.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and
citizens)
The Detention Center Security System project is budgeted in a capital project fund and
financed with funds from the capital projects reserve. The budget reflects funding of
$209,000 for the five-year CIP planning period. No additional operating costs are expected to be incurred.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
167
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Detenti on Center Sl i der Gate Upgrade 0.120$ -$ -$ -$ -$ 0.120$
TOTAL PROJECT COST 0.120$ -$ -$ -$ -$ 0.120$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 0.120$ -$ -$ -$ -$ 0.120$
TOTAL PROJECT FUNDING 0.120$ -$ -$ -$ -$ 0.120$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
FACILITIES
Project Name: DETENTION CENTER SLIDER GATE UPGRADE
No Impact on Operating Budget
Project Description
This project will provide for the replacement of 12 slider gates of obsolete mechanical components upgrading
with current hardware by the manufacturer. Current gates are expensive to maintain and repair.
Project Justification
This project is consistent with County Council’s goal of providing adequate public safety. This project will provide
for reliable operations of gates in the Detention facility.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The Detention Center Slider Gate Upgrade project is budgeted in a capital project fund and financed with funds
from the capital projects reserve. The budget reflects funding of $120,000 for the five-year CIP planning period.
No additional operating costs are expected to be incurred.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
168
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Magistrate Consolidation 3.000$ -$ -$ -$ -$ 3.000$
TOTAL PROJECT COST 3.000$ -$ -$ -$ -$ 3.000$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Capital Projects Fund 3.000$ -$ -$ -$ -$ 3.000$
TOTAL PROJECT FUNDING 3.000$ -$ -$ -$ -$ 3.000$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
FACILITIES
Project Name: MAGISTRATE OFFICE CONSOLIDATION
Positive Impact on Operating Budget
Project Description
This project proposes the implementation of a multi-phased project to
consolidate magistrate offices based on population in each consolidated
jury area. Fiscal Year 2014 would involve the construction of one
consolidated office.
Project Justification
This project is consistent with the Administration’s proposal to provide
magistrate services in consolidated jury areas.
Impact on operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the
county and citizens)
The Magistrate Office Consolidation project is budgeted in a capital project
fund and financed with funds from the capital project reserve. There will
also be operating savings achieved once the offices are consolidated,
thereby producing a positive impact on the operating budget.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
169
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Road Program 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
TOTAL PROJECT COST 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Special Revenue Fund - Road Fee 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
TOTAL PROJECT FUNDING 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
INFRASTRUCTURE IMPROVEMENTS
Project Name: ROAD PROGRAM
No Impact on Operating Budget
Project Description
Road improvements include rehabilitation and/or
reconstruction of “worst roads” first on a countywide basis.
Project Justification
Planned projects are consistent with Council approved
programs to reduce risk to public safety and to improve
deteriorating road structures. The road program also includes a
contribution for local municipality road programs
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized,
benefit to the county and citizens)
Funding for the road program is included in the capital projects fund and is financed through road maintenance
fees. This project provides a direct benefit to citizens through road and bridge improvements. No additional
impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
170
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Bridge - Connecting Unit 1 to Unit 4 -$ 0.250$ 1.350$ 1.600$
Leachate Pump Stati on 0.460$ -$ -$ 0.460$
Equipment Replacement Program 0.250$ 0.400$ 0.650$ 0.250$ 0.350$ 1.900$
TOTAL PROJECT COST 0.710$ 0.650$ 2.000$ 0.250$ 0.350$ 3.960$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Enterprise Fund Revenue 0.710$ 0.650$ 2.000$ 0.250$ 0.350$ 3.960$
TOTAL PROJECT FUNDING 0.710$ 0.650$ 2.000$ 0.250$ 0.350$ 3.960$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater . Capital projects within these funds are
accounted for in the appropriate proprietary enterprise fund. The FY2014-FY2018 Capital Improvement
Program includes a budget of $32.191 million for various capital projects in the areas of solid waste and
stormwater. Proposed projects are discussed below.
SOLID WASTE ENTERPRISE FUND
Project Name: SOLID WASTE PROJECTS
No Impact on Operating Budget
Project Description
The Solid Waste Enterprise Fund accounts for operations
of the County’s waste disposal, recycling, and landfill.
Capital projects for the Solid Waste Division include the
continued replacement of heavy equipment used in the
transport and disposal of municipal solid waste; a pump
station for leachate removal from the northern collection
area within Cell V of Unit One of the landfill, and the
construction of a bridge to connect the access roads
between Unit One and Unit Four.
Project Justification
These projects are consistent with County Council’s goals for infrastructure which encompass providing
adequate funding for landfill capital needs.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for these projects are included in the Solid Waste Enterprise Fund and funded through revenue
received for that fund. No additional impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
171
PROJECT ITEMS
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
COST
Neighborhood Drainage Projects 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
Flood Projects and Studies 4.400$ 4.401$ 4.400$ 4.000$ 4.000$ 21.201$
NPDES Water Quality Retrofits 0.500$ 0.500$ 0.500$ 0.500$ 0.500$ 2.500$
Ce ntralize d Ele ctronic Pe rm itting 0.765$ 0.765$ -$ -$ -$ 1.530$
TOTAL PROJECT COST 6.265$ 6.266$ 5.500$ 5.100$ 5.100$ 28.231$
PROJECT FUNDING SOURCES
FY2014
BUDGET
FY2015
BUDGET
FY2016
PROPOSED
FY2017
PROPOSED
FY2018
PROPOSED
TOTAL PROJECT
FUNDING
Enterprise Fund Revenue 6.265$ 6.266$ 5.500$ 5.100$ 5.100$ 28.231$
TOTAL PROJECT FUNDING 6.265$ 6.266$ 5.500$ 5.100$ 5.100$ 28.231$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ -$ -$
Cumulative Operating Impact - - - - - -
STORMWATER ENTERPRISE FUND
Project Name: STORMWATER PROJECTS
No Impact on Operating Budget
Project Description
The projects for Stormwater include funding for
neighborhood drainage improvement projects and flood
studies and/or projects. Funds are also included for
NPDES water quality retrofits, which will identify, by
priority, watersheds, best practices to manage
stormwater in order to meet in-stream water quality
goals. Funds are included for implementing a centralized
electronic permitting process bringing all divisions
involved in the land development process into a shared
network of electronic data.
Project Justification
These projects are consistent with County Council’s goals for infrastructure which provide for funding to resolve
drainage problems and for stormwater flood projects.
Impact on Operating Budget
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for these projects are included in the Stormwater Enterprise Fund and funded through revenue
received for that fund. No additional impact on the operating budget is anticipated.
County of Greenville Budget Document
Fiscal Years 2014 and 2015
172
THIS PAGE INTENTIONALLY LEFT BLANK
Source: Greenville County website. First collected Oct 13, 2026.