County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 185
COUNTY OF GREENVILLE
CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement Planning process.
This section of the document provides information on the multi-year capital improvement program, the current
program status, a summary of capital projects and a copy of the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent and
nonrecurring projects, which should be financed over a period of years. Greenville County has selected a
programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a
comprehensive evaluation of project planning, justification, coordination of needs, priorities and relationship to
budgeting policies. Therefore, the capital improvement budget is considered with budget decisions. Capital
improvement programming is a continuous process involving yearly adjustments. The CIP includes capital
projects recommended for fiscal years 2012 through 2016. Each fiscal year’s capital budget is submitted in
conjunction with its respective operating budget. The CIP multi-year plan includes projects for which funding is
currently available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2010 January – June 2011
Departmental
program plans
prepared and capital
projects submitted to
CIP team.
October - November
CIP Team
Review
Requests
December
CIP Team reviews,
prioritizes and
recommends capital
program
January -April
County Departments prepare
CIP requests
by November 30
Budget/Planning
Staff compile
project information
By December31
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County Council
adopts CIP and
capital budget
May - June
County
Administrator’s
Recommended
Budget
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 186
CURRENT PROGRAM STATUS
The FY2012-2016 Capital Improvement Program totals $69.382 million for projects in the areas of
technological improvements, equipment, facilities, infrastructure, solid waste, and stormwater. For the current
biennium budget, capital projects total $12.843 million for FY2012 and $15.002 million for FY2013.
Below are graphic comparisons of budgeted capital projects by fund and by type. The following page provides
a detailed listing of capital projects and financing summary. In the capital projects fund, infrastructure
expenditures are by far the greatest percentage. Capital projects funded by the County’s enterprise funds are
specific to each respective fund.
CAPITAL PROJECTS BY FUND
Capital Projects
Fund
57.67%
Stormwater
Enterprise Fund
35.53%
Solid Waste
Enterprise Fund
6.80%
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements. The majority of
improvements are for infrastructure improvements, which includes the County’s road program. Another large
area is stormwater, which includes drainage projects and specific task force projects.
$0
$5
$10
$15
$20
$25
$30
Millions
Tec
hnology
Equipment Fac
ilities
Infrastructur
e
Solid Waste
Stormw
ater
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 187
CIP FINANCING SUMMARY
FY2012-FY2016
2012 FY2013 FY2014 FY2015 FY2016 TOTAL
BUDGET BUDGET PROPOSED PROPOSED PROPOSED FUNDS
0.850$ 1.051$ 0.950$ 0.950$ 0.950$ 4.751$
0.100$ -$ 0.100$ -$ 0.100$ 0.300$
0.143$ 0.083$ 0.083$ 0.083$ - $ 0.392$
0.300$ 0.150$ 0.150$ 0.050$ - $ 0.650$
$ 1.284$ 1.283$ 1.083$ 1.050$ 6.094$
0.278$ 0.292$ 0.322$ 0.338$ - $ 1.230$
0.122$ -$ - $ - $ -$ 0.122$
- $ 0.200$ -$ - $ -$ 0.200$
0.400$ 0.492$ 0.322$ 0.338$ - $ 1.552$
0.080$ 0.070$ -$ - $ -$ 0.150$
0.200$ 0.200$ -$ - $ -$ 0.400$
0.115$ 0.241$ -$ - $ -$ 0.356$
0.250$ 2.000$ 0.250$ 2.000$ -$ 4.500$
0.250$ -$ - $ - $ -$ 0.250$
$ 2.511$ 0.250$ 2.000$ - $ 5.656$
4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
7.188$
FY
C
APITAL PROJECTS FUNDING SOURCE
COUNTY GOVERNMENT DEPARTMENTS
Technological Improvements
Information Technology Capital Projects Fund
GIS/Orthophotography Capital Projects Fund
EMS Communications Equipment Capital Projects Fund
MDT's - Sheriff's Office Capital Projects Fund
TOTAL 1.393
Equipment
Upgrade of Cardiac Monitors - EMS Capital Projects Fund
Safe Driving System - EMS Capital Projects Fund
Jet Vac Truck Addition - Public Works Capital Projects Fund
TOTAL
Facilities
Property & Evidence Storage Capital Projects Fund
Carpet Replacement Capital Projects Fund
Fire Alarm Upgrades Capital Projects Fund
Magistrate Office Consolidation Capital Projects Fund
Sh
elter for Sheriff Vehicles Capital Projects Fund
TOTAL 0.895
Infrastructure
Road Program Special Revenue Fund
TOTAL 4.500
CAPITAL PROJECTS FUND TOTAL
8.787$ 7.855$ 9.421$ 7.050 $ 40.302 $
SOLID WASTE ENTERPRISE FUND
Solid Waste
Bridge Connection between units Enterprise Fund
Leachate Pump Station Enterprise Fund
Stationary Compactor Enterprise Fund
Equipment Replacement Program Enterprise Fund
SOLID WASTE ENTERPRISE FUND TOTAL
-$ - $ -$ 0.250$ 1.200$ 1.450$
-$ 0.040$ 0.460$ -$ -$ 0.500$
-$ 0.170$ -$ - $ -$ 0.170$
0.350$ 0.700$ 0.850$ 0.350$ 0.300$ 2.550$
0.350$
0.910$ 1.310$ 0.600$ 1.500 $ 4.670 $
STORMWATER ENTERPRISE FUND
Neighborhood Drainage Projects Enterprise Fund
Flood Projects and Studies Enterprise Fund
STORMWATER ENTERPRISE FUND TOTAL
0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
4.705$ 4.705$ 4.000$ 4.000$ 4.000$ 21.410$
5.305$
5.305$ 4.600$ 4.600$ 4.600 $ 24.410 $
TOTAL FOR ALL CAPITAL PROJECTS 12.843$ 15.002$ 13.765$ 14.621$ 13.150 $ 69.382 $
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 188
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2012
Capital
Budget
8.41%
Operating
Budget
91.59%
The chart bel
ow shows the relationship between the operating budget and capital
expenditures for FY2012. Capital expenditures of $12.923 million include
capital projects of $12.843 million. The impact on the $139.794 million
operating budget is $9.569 million, which is the debt service for capital projects.
There are no estimated operational costs for new projects in FY2012. The
$12.243 million for “pay-as-you-go” projects will come from fund balances in
each of the respective funds.
Operating Impact $9.569 million for FY2012
Debt Service $9.569 million (Principal and Interest)
Operations and Maintenance $0 million
Operating
Budget $22.412
$139.794 million
million
Capital
Budget
$12.923
million
“Pay-as-you-go” - $12.843 million
Fiscal Year 2013
The chart below shows the relationship between the operating budget and
capital expenditures for FY2013. Capital expenditures of $20.304 million
include capital projects of $18.111 million. The impact on the $144.976
million operating budget is $10.123 million. The remaining $14.792 million
for “pay-as-you-go” projects will come from fund balances in each respective
funds and/or special revenue.
Capi tal
Budget
9.52%
Op e rati n g
Budget
90.48%
Operating Impact $8.806 million for FY2013
Debt Service $8.806 million (Principal and Interest)
Operations and Maintenance $0.000 million
Operating
Budget $23.598
$141.691 million
million
Capital
Budget
$15.082
million
“Pay-as-you-go” - $14.792 million
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 189
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional staff,
maintenance, or daily operational costs. The amount of operating budget impact for each project is referred to
in the following terms:
OPERATING
IMPACT
DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating costs.
No Impact The project will cause no change in operating costs
Negligible The impact will be very small; it will generate less than $10,000 per year in increased operating
expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating expenditures.
Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures.
High The impact will increase operating expenditures $100,001 or more.
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These sources
include: transfers from the County’s general operating fund, general obligation bonds, special source revenue
bonds via the County’s Infrastructure Bank, capital project reserve, pay-as-you-go basis either through ad
valorem revenues or fees, and enterprise fund revenue. The chart below provides a description of funding
sources.
FUNDING SOURCE DESCRIPTION
General Fund Transfer A major source of smaller capital projects is transfers from the County’s general operating fund.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X, Section 14,
of the constitution of the State of South Carolina, 1895, as amended, provides that counties
shall have the power to incur bonded indebtedness in such a manner and upon such terms and
conditions as the General Assembly shall prescribe by general law. General obligation debt may
be incurred only for public and corporate purpose in an amount not exceeding 8% of the
assessed value of all taxable property of each county.
Special Revenue Bonds The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties can
issue Special Source Revenue Bonds for the purpose of building or acquiring infrastructure
necessary to continue the economic development of a county. The portion of the CIP which
provides for the building or acquiring of infrastructure necessary to continue the economic
development of the County is included in the Infrastructure Bank and funded through Special
Source Revenue Bonds. The County has pledged the County portion of the revenue stream
from the multi-county parks, which includes fee-in-lieu-of-taxes (FILOT) revenues.
Capital Projects
Accounts
Another source utilized in the CIP is the capital project reserve account. This account contains
any unspent funds from previously completed capital projects. The County’s Financial Policies
allow the County Administrator to include recommendations in the budget to dispose of
unspent capital project funds.
Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem revenues
or fees. The CIP utilizes a road maintenance fee of $15 per vehicle to fund a portion of the
road program.
Enterprise Fund
Revenue
For the County’s two enterprise funds, Solid Waste and Stormwater, improvements are funded
through each fund’s respective revenue.
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 190
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition or
construction of major capital projects, other than those financed by proprietary funds. The FY2012-FY2016
Capital Improvement Program includes a budget of $40.218 million for various capital projects in the areas of
public safety, technological improvements, facility improvements, and infrastructure improvements. Each
project is discussed in detail on the following pages.
TOTAL
FY2012 FY2013 FY2014 FY2015 FY2016 FUNDS
CAPITAL PROJECTS BUDGET BUDGET PROP OSED PROPOSED PROPOSED FY2012-2016
Technological Improvements
Information Technology 0.850 $ 0.968 $ 0.950 $ 0.950 $ 0.950 $ 4.668 $
GIS/Orthophotography 0.100 $ - $ 0.100$ - $ 0.100$ 0.300 $
EMS Communications Equipment 0.143 $ 0.083 $ 0.083 $ 0.083 $ - $ 0.392$
MDT's - Sheriff's Office 0.300 $ 0.150 $ 0.150 $ 0.050 $ - $ 0.650$
TOTAL 1.393 $ 1.201 $ 1.283 $ 1.083 $ 1.050 $ 6.010 $
Eq
uipment
Upgrade of Cardiac Monitors - EMS 0.278$ 0.292$ 0.322$ 0.338$ -$ 1.230$
Safe Driving System - EMS 0.122$ -$ -$ -$ -$ 0.122$
Jet Vac Truck Addition - Public Works -$ 0.200$ -$ -$ -$ 0.200$
TOTAL 0.400$ 0.492$ 0.322$ 0.338$ -$ 1.552$
Facilities
Property & Evidence Storage 0.080$ 0.070$ -$ -$ -$ 0.150$
Carpet Replacement 0.200$ 0.200$ -$ -$ -$ 0.400$
Fire Alarm Upgrades 0.115$ 0.241$ -$ -$ -$ 0.356$
Magistrate Office Consolidation 0.250$ 2.000$ 0.250$ 2.000$ -$ 4.500$
Shelter for Sheriff Vehicles 0.250$ -$ -$ -$
-$ 0.250$
TOTAL 0.895 $ 2.511$ 0.250$ 2.000$ -$ 5.656$
Infrastructure
Road Program 4.500$ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
TOTAL 4.500 $ 4.500$ 6.000$ 6.000$ 6.000$ 27.000$
CAPITAL PROJECTS FUND TOTAL 7.188$ 8.704$ 7.855$ 9.421$ 7.050$ 40.218 $
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 191
TECHNOLOGICAL IMPROVEMENTS
PROJECT NAME: Information Technology
No Impact on Operating Budget
PROJECT DESCRIPTION
This
project entails implementing a comprehensive network system to
provide connectivity between and among users, upgrading the
County’s AS400 platform, installing network hardware and end-user
query reporting, and purchasing equipment for multiple county
departments. The implementation of the Information Technology
components will provide the County and its residents/customers with
a more advanced, user friendly, citizen centered service organization
through the addition, and replacement of equipment and software
which will heighten Greenville County’s technological abilities,
enhance existing service delivery, and provide for future growth in
technology.
PROJECT JUSTIFICATION
This project is consistent with the County Council’s desire to provide for the technological needs of the
County.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Information technology improvements are budgeted in a capital project fund and financed with funds from the
capital project reserve. The budget reflects the cost of purchasing the necessary equipment. No additional
operating costs are expected to be incurred.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Information Technology - $ 0.175$ 0.250$ 0.250$ 0.250$ 0.250 $ 1.175 $
Network - 0.240 0.313 0.350 0.350 0.350 1.603
Software - 0.380 0.350 0.350 0.350 0.350 1.780
Imaging 0.055 0.055 0.110
EMS System - -
Equipment 19.961 - - - 19.961
TOTAL PROJECT COST 19.961$ 0.850 $ 0.968$ 0.950$ 0.950$ 0.950 $ 24.629 $
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer 14.189$ - $ -$ -$ -$ - $ 14.189$
Capital Project Reserve Fund 1.172 0.850 0.968 0.950 0.950 0.950 5.840$
Special Revenue Fund 4.600 4.600$
TOTAL PROJECT FUNDING 19.961$ 0.850 $ 0.968$ 0.950$ 0.950$ 0.950 $ 24.629 $
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 192
TECHNOLOGICAL IMPROVEMENTS
PROJECT NAME: GIS/Orthophotography Land Base Updates
Negligible Impact on Operating Budget
PROJECT DESCRIPTION
This project in
volves the production of a standard series of maps with survey
control, aerial photography, analytic triangulation and digital and hardcopy
map production. These GIS land base updates began in FY2001 and
provide a mechanism for annual, incremental updates of aerial photography,
planimetric and topographic data within the county. Changes in planimetric
data such as building footprints, ponds, lakes, wetlands, streams, rivers,
dams, bridges, parks, airports, street center lines, edge of pavement lines,
and parking lots as well as changes in topography due to development will
be captured and incorporated into the GIS database. The digital
orthophotography database will be updated providing a current, accurate
picture of what exists on the ground.
PROJECT JUSTIFICATION
These GIS land base updates began in FY2001 and provide a mechanism
for annual, incremental updates of aerial photography, planimetric and topographic data within the county.
This is an ongoing project consistent with the priorities and goals of County Council.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Geographic information system improvements are budgeted in a capital project fund and financed with capital
project reserve. The budget reflects funding of $300,000 for the five-year CIP planning period for updating
the GIS land base. Hardware and software contract costs will increase approximately $5,000 beginning in
FY2014 and will have a minimal impact on the operating budget.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Hardware/Software System Upgrade - $ 0.025$ - $ 0.025$ -$ 0.025$ 0.075 $
OrthoPhotography Update - 0.075 - 0.075 - 0.075 0.225
Equipment 2.900 - - - 2.900
TOTAL PROJECT COST 2.900$ 0.100 $ - $ 0.100$ -$ 0.100$ 3.200 $
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer 2.900$ - $ - $ -$ -$ - $ 2.900$
Capital Project Account 0.100 - 0.100 - 0.100 0.300
TOTAL PROJECT FUNDING 2.900$ 0.100 $ - $ 0.100$ -$ 0.100$ 3.200 $
OPERATIONAL COSTS
Operating Impact -$ - $ 0.005$ 0.010$ 0.010 $ 0.025 $
Cumulative Operating Impact -$ - $ 0.005$ 0.015$ 0.025 $ 0.045 $
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 193
TECHNOLOGICAL IMPROVEMENTS
PROJECT NAME: EMS Communications Equipment
Slight Impact on Operating Budget
PROJECT DESCRIPTION
This project proposes the replacement of portable and fixed radios as a requirement to the FCCs mandate
regarding the reallocation/reconfiguration of radio frequencies (narrow-banding) and the addition of radio
access at the supervisor’s console in the EMS Communications Center. The FCC distributed a mandate in June
2010 that all public safety and commercial radio licenses operating in UHF (421-512 MHz) and VHF (150-
174 MHz) bands must transition to narrowband operation by January 1, 2013. These portable radios are
essential tools to EMS operations by keeping crews in constant contact with the EMS communications center
and staff.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority Area I: Public Safety which provides for the
implementation of a high performance EMS program.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Acquisition of the EMS Communications Equipment is budgeted in a capital project fund and financed with
funds from the capital projects reserve. The budget reflects funding of $392,000 for the five-year CIP
planning period for acquiring the equipment. After the initial expense of equipment acquisition and installation,
recurring maintenance costs will be in proportion to the replacement or upgraded maintenance expenses.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
PROPOSED
FY2013
PROPOSED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Equipment -$ 0.143$ 0.083$ 0.083$ 0.083$ - $ 0.392$
Other - - - - - - -
- - - - -
- - - - -
TOTAL PROJECT COST -$ 0.143$ 0.083$ 0.083$ 0.083$ - $ 0.392$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer - $ -$ -$ -$ -$ - $ -$
Capital Project Account 0.143 0.083 0.083 0.083 0.392
-
TOTAL PROJECT FUNDING -$ 0.143$ 0.083$ 0.083$ 0.083$ - $ 0.392$
OPERATIONAL COSTS
Operating Impact 0.040$ 0.002$ 0.002$ 0.002$ 0.003 $ 0.049 $
Cumulative Operating Impact 0.040$ 0.042$ 0.044$ 0.046$ 0.049 $ 0.221 $
FTEs Added - - - - - -
.
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 194
TECHNOLOGICAL IMPROVEMENTS
PROJECT NAME: Replacement of Mobile Data Terminals for Sheriff’s Office
No Impact on Operating Budget
PROJECT DESCRIPTION
This project proposes the replacement over several years of the mobile data terminals utilized in Sheriff’s Office
vehicles. Current equipment within the patrol vehicles is breaking frequently and replacement parts are no
longer readily available. Replacement of this equipment is critical to maintain functional efficiency.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority Area I: Public Safety. The mobile data terminals will
assist in providing a safe community for citizens.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Acquisition of the mobile data terminals for the Sheriff’s Office is budgeted in a capital project fund and
financed with funds from the capital projects reserve. The budget reflects funding of $650,000 for the five-
year CIP planning period for acquiring the equipment. After the initial expense of equipment acquisition and
installation, recurring maintenance costs will be absorbed within the current operating budget; consequently,
there is no additional impact on the operating budget.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
PROPOSED
FY2013
PROPOSED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Equipment -$ 0.300$ 0.150$ 0.150$ 0.050$ - $ 0.650$
Other - - - - - - -
TOTAL PROJECT COST -$ 0.300$ 0.150$ 0.150$ 0.050$ - $ 0.650$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer - $ - $ -$ -$ -$ - $ -$
Capital Project Account - 0.300 0.150 0.150 0.050 - 0.650
TOTAL PROJECT FUNDING -$ 0.300$ 0.150$ 0.150$ 0.050$ - $ 0.650$
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 195
EQUIPMENT
PROJECT NAME: Upgrade of Cardiac Monitors – EMS
Negligible Impact on Operating Budget
PROJECT DESCRIPTION
This project proposes the methodical purchase of 40 monitor-defibrillators
over the span of four years due to
the age and excessive use of the current
units, the pending availability of maintenance and parts supported by the
manufacturer for the current units, and a mandated upgrade in monitoring
capability by DHEC. These units are essential tools used by paramedics to
assess the cardiac condition of the majority of patients treated annually. The
EMS Division proposes acquiring the Physiocontrol LP15 as the monitor-
defibrillator due to the required integration of the EKG and diagnostic data in
the current patient care reporting system, and the transfer of data to the hospital systems through proprietary
data ports specific to the Physiocontrol platform.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority Area I: Public Safety which provides for the
implementation of a high performance EMS program.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Upgrade of the EMS Cardiac Monitors is budgeted in a capital project fund and financed with funds from the
capital projects reserve. The budget reflects funding of $1,230,000 for the five-year CIP planning period for
acquiring the equipment. After the initial expense of equipment acquisition and installation, recurring
maintenance costs will be in proportion to the number of Lifepack 15s acquired.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
PROPOSED
FY2013
PROPOSED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Equipment -$ 0.278$ 0.292$ 0.322$ 0.338$ - $ 1.230$
Other - - - - - - -
TOTAL PROJECT COST -$ 0.278$ 0.292$ 0.322$ 0.338$ - $ 1.230$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer - $ -$ -$ -$ -$ - $ -$
- 0.278Capital Project Account 0.292 0.322 0.338 - 1.230
TOTAL PROJECT FUNDING -$ 0.278$ 0.292$ 0.322$ 0.338$ - $ 1.230$
OPERATIONAL COSTS
Operating Impact 0.040$ 0.002$ 0.002$ 0.002$ - $ 0.046$
Cumulative Operating Impact 0.040$ 0.042$ 0.044$ 0.046$ - $ 0.172$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 196
EQUIPMENT
PROJECT NAME: Safe Driving System – EMS
Negligible Impact on Operating Budget
PROJECT DESCRIPTION
This project will allow for the installation of the Safe Force Driving System on all EMS vehicles. Safe Force
Driving System is a multi-component hardware/software package that monitors and records the vehicle
performance and driver characteristics, and provides immediate visual and audible feedback to the driver when
pre-established driving conditions are exceeded or violated. The system documents conditions in real time,
providing accurate performance conditions while the vehicle is in operation for use by EMS. It also provides
Fleet Management with information in evaluating maintenance needs and quality improvement driving training.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority Area I: Public Safety which provides for the
implementation of a high performance EMS program.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Acquisition of the Safe Driving System for EMS is budgeted in a capital project fund and financed with funds
from the capital projects reserve. The budget reflects funding of $122,000 for the five-year CIP planning
period for acquiring the equipment. After the initial expense of equipment acquisition and installation,
recurring maintenance costs will be charged each year.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
PROPOSED
FY2013
PROPOSED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Equipment -$ 0.122$ -$ -$ -$ - $ 0.122$
Other - - - - - - -
TOTAL PROJECT COST -$ 0.122$ -$ -$ -$ - $ 0.122$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer - $ -$ -$ -$ -$ - $ -$
Capital Project Account - 0.122 - - - - 0.122
TOTAL PROJECT FUNDING -$ 0.122$ -$ -$ -$ - $ 0.122$
OPERATIONAL COSTS
Operating Impact 0.004$ -$ 0.001$ 0.003$ - $ 0.008$
Cumulative Operating Impact 0.004$ 0.004$ 0.005$ 0.008$ - $ 0.021$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 197
EQUIPMENT
PROJECT NAME: Jet-Vac Truck Addition – Public Works
No Impact on Operating Budget
PROJECT DESCRIPTION
The addition
of a new Jet-Vac truck will allow the Public
Works Department to have one truck in the Northern
area and one in the Southern area of the County for use
to remove blockages from drainage structures. This will
assist in alleviating potential flooding or backups due to
blockages and allow the County to have at least one
truck operational at all times.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority
Area II: Infrastructure which requires the County
establish adequate funding and management system to provide for the County’s infrastructure.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Acquisition of the Jet Vac Truck for the Public Works Department is budgeted in a capital project fund and
financed with funds from the capital projects reserve. The budget reflects funding of $200,000 for the five-
year CIP planning period for acquiring the equipment. There are no other impacts to the operating budget.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
PROPOSED
FY2013
PROPOSED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Equipment - $ -$ 0.200$ -$ -$ - $ 0.200$
Other - - - - - - -
TOTAL PROJECT COST -$ -$ 0.200$ -$ -$ - $ 0.200$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer -$ -$ -$ -$ -$ - $ -$
Capital Project Account - - 0.200 - - - 0.200
TOTAL PROJECT FUNDING -$ -$ 0.200$ -$ -$ - $ 0.200$
OPERATIONAL COSTS
Operating Impact - $ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 198
FACILITY PROJECTS
PROJECT NAME: Property and Evidence Storage Upgrade/Renovations
Negligible Impact on Operating Budget
PROJE
CT DESCRIPTION
This project proposes the renovation of existing storage spaces
assigned to Property and Evidence; removal of older dilapidated
wood shelving and the installation of fire-proof units. It is
anticipated that the utilization of high density mobile storage
systems will most likely double the linear footage of the property
rooms and will allow Property and Evidence to reduce its floor
space requirements in half.
PROJECT JUSTIFICATION
This project is consistent with the requirements of CALEA
(Commission for Accreditation of Law Enforcement Agencies).
CALEA standards mandate that a property and evidence section
should provide for the security and control of seized, recovered,
and evidentiary property as well as abandoned, lost, or found
property.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Renovation of the Property and Evidence section of the Forensic Division is budgeted in a capital project fund
and financed with funds from the capital projects reserve. The budget reflects funding of $150,000 for the
five-year CIP planning period for acquiring the equipment. The project will require funding for temporary
personnel while the renovations are being complete so that the property and evidence can be relocated in a
timely manner.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Renovation - 0.080 0.070 - - - 0.150
TOTAL PROJECT COST -$ 0.080$ 0.070$ -$ -$ - $ 0.150$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer -$ -$ -$ -$ -$ - $ -$
Capital Project Reserve Fund - 0.080 0.070 - - - 0.150
-
TOTAL PROJECT FUNDING -$ 0.080$ 0.070$ -$ -$ - $ 0.150$
OPERATIONAL COSTS
Operating Impact 0.020 $ -$ -$ -$ - $ 0.020$
Cumulative Operating Impact 0.020$ 0.020$ -$ -$ - $ 0.040$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 199
FACILITY PROJECTS
PROJECT NAME: Carpet Replacement
No Impact on Operating Budget
PROJECT DESCRIPTION
This project proposes the second phase of a multi-phase program to replace carpet at the Courthouse and
Family Court facilities. These floor coverings were installed in 1997 and 2002 and are subject to heavy traffic
and are showing patterns of wear.
PROJECT JUSTIFICATION
This project is consistent with County Council’s desire to provide a safe, workable, environment for County
employees. Carpet replacement is necessary to replace worn areas that, if delayed, could become torn and
frayed resulting in accidents for employees and citizens.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The carpet replacement project at Greenville County facilities is budgeted in a capital project fund and
financed with funds from the capital project reserve. No additional operating costs are expected to be incurred.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Renovation 0.250 0.200 0.200 - - - 0.650
TOTAL PROJECT COST 0.250$ 0.200 $ 0.200$ -$ -$ - $ 0.650$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer 0.250$ - $ -$ -$ -$ - $ 0.250$
Capital Project Reserve Fund - 0.200 0.200 - - - 0.400
-
TOTAL PROJECT FUNDING 0.250$ 0.200 $ 0.200$ -$ -$ - $ 0.650$
OPERATIONAL COSTS
Operating Impact - $ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 200
FACILITY PROJECTS
PROJECT NAME: Fire Alarm Upgrades
No Impact on Operating Budget
PROJECT DESCRIPTION
This project proposes change out of existing obsolete and antiquated fire alarm systems that are noncompliant
with current codes. Replacement panels are not accessible, as they are not longer manufactured. The system
change out would make the components specific to a location point opposed to general areas. The notification
devices (fire horns) would be replaced and installed throughout the facility instead of mostly general areas.
PROJECT JUSTIFICATION
This project is consistent with County Council’s desire to provide a safe, workable, environment for County
employees. Fire alarm upgrades are necessary to replace existing alarms that are obsolete and antiquated.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The fire alarm upgrade project at Greenville County facilities is budgeted in a capital project fund and financed
with funds from the capital project reserve. No additional operating costs are expected to be incurred.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Equipment -$ 0.115$ 0.241$ -$ -$ - $ 0.356$
-
TOTAL PROJECT COST -$ 0.115$ 0.241$ -$ -$ - $ 0.356$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
General Fund Transfer -$ -$ -$ -$ -$ - $ -$
Capital Project Reserve Fund - 0.115 0.241 - - - 0.356
-
TOTAL PROJECT FUNDING -$ 0.115$ 0.241$ -$ -$ - $ 0.356$
OPERATIONAL COSTS
Operating Impact - $ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 201
FACILITY PROJECTS
PROJECT NAME: Magistrate Office Consolidation
Positive Impact on Operating Budget
PROJE
CT DESCRIPTION
This project proposes the implementation of a multi-phased project to
consolidate magistrate offices based on population in each consolidated jury
area. Fiscal Years 2012 – 2015 would involve the construction of two of
these consolidated offices.
PROJECT JUSTIFICATION
This project is consistent with the Administration’s proposal to provide
magistrate services in consolidated jury areas.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county
and citizens)
The Magistrate Office Consolidation project is budgeted in a capital project fund and financed with funds from
the capital project reserve. There will also be operating savings achieved once the offices are consolidated,
thereby producing a positive impact on the operating budget.
TOTAL
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
PROJECT
CO
ST
Planning and Design -$ 0.100$ -$ 0.100$ -$ - $ 0.200$
Site Acquisition Costs - 0.150 - 0.150 - - 0.300
Construction - - 2.000 - 2.000 - 4.000
TOTAL PROJECT COST -$ 0.250$ 2.000$ 0.250$ 2.000$ - $ 4.500$
TOTAL
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
PROJECT
FU
NDING
General Fund Transfe -$ -$ r -$ -$ -$ - $ -$
Capital Project Reserve Fund - 0.250 2.000 0.250 2.000 - 4.500
-
TOTAL PROJECT FUNDING -$ 0.250$ 2.000$ 0.250$ 2.000$ - $ 4.500$
OPERATIONAL COSTS
Operating Impact - $ -$ (0.100)$ -$ - $ (0.100)$
Cumulative Operating Impact -$ -$ (0.100)$ (0.100)$ (0.100) $ (0.300) $
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 202
FACILITY PROJECTS
PROJECT NAME: Shelter for Sheriff’s Vehicles
Positive Impact on Operating Budget
PROJECT DESCRIPTION
This project proposed the construction of a building approximately 90’ wide by 48’ deep to be used as a
parking facility for special purpose vehicles. Due to lack of a shelter, many special purpose vehicles have
experienced leaks and other weather damage requiring extensive repairs. Secure storage will increase the
likelihood that these vehicles will be available to respond to emergencies.
PROJECT JUSTIFICATION
This project will provide secure storage of the County’s assets and will increase the likelihood that these special
purpose vehicles will be available to respond to emergencies.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The Shelter for Sheriff’s Vehicles project if budgeted in a capital project fund and financed with funds from the
capital project reserve accounts. The building will provide savings on vehicle maintenance and will have a
positive impact on the operating budget.
TOTAL
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
PROJECT
COST
C
onstruction -$ 0.250$ -$ -$ -$ - $ 0.250$
TOTAL PROJECT COST -$ 0.250$ -$ -$ -$ - $ 0.250$
TOTAL
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
PROJECT
FUN
DING
General Fund Transfer -$ -$ -$ -$ -$ - $ -$
Capital Project Reserve Fund - 0.250 - - - - 0.250
-
TOTAL PROJECT FUNDING -$ 0.250$ -$ -$ -$ - $ 0.250$
OPERATIONAL COSTS
Operating Impact (0.020)$ -$ -$ -$ - $ (0.020)$
Cumulative Operating Impact (0.020)$ (0.020)$ (0.020)$ (0.020)$ (0.020) $ (0.100) $
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 203
INFRASTRUCTURE IMPROVEMENTS
PROJECT NAME: Road Program
No Impact on Operating Budget
PROJE
CT DESCRIPTION
Road improvements include rehabilitation and/or reconstruction of
“worst roads” first on a countywide basis. Planned projects are to be
consistent with: (1) division and Council approved programs to
reduce risk to public safety; and (2) improvements on deteriorating
road structures. The road program also includes bridge replacements,
a traffic program, and a contribution for local municipality road
programs.
PROJECT JUSTIFICATION
This project is consistent with Council Priority I:
Infrastructure which requires that the County provide for
roads and infrastructure needs.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized,
benefit to the county and citizens)
Funding for the road program is included in the capital
projects fund and is financed through road maintenance
fees. This project provides a direct benefit to citizens
through road and bridge improvements. No additional
impact on the operating budget is anticipated.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Paving Program 65.362 $ 3.800 $ 3.800$ 5.300$ 5.300$ 5.300 $ 88.862 $
Construction Projects 29.554 - - - - - 29.554
Bridges 6.981 - - - - - 6.981
Traffic & Safety Projects 4.210 - - - - - 4.210
Local Municipalities 5.760 0.700 0.700 0.700 0.700 0.700 9.260
Limited Partnerships 0.690 - - - - - 0.690
Consulting Fees 15.244 - - - - - 15.244
TOTAL PROJECT COST 127.801$ 4.500 $ 4.500$ 6.000$ 6.000$ 6.000 $ 154.801$
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
General Obligation Bonds 38.000 $ - $ -$ -$ 38.000$
Road Maintenance Fees 43.175 4.500 4.500 6.000 6.000 6.000 70.175
General Fund Transfer - - - - - - -
Special Source Revenue Bonds 19.750 19.750
Other Sources/Fund Balance 26.876 - - - - - 26.876
TOTAL PROJECT FUNDING 127.801$ 4.500 $ 4.500$ 6.000$ 6.000$ 6.000 $ 154.801$
OPERATIONAL COSTS
Operating Impact - $ -$ -$ -$ -$ -$
Cumulative Operating Impact -$ -$ -$ -$ -$ -$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 204
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within these funds are
accounted for in the appropriate proprietary enterprise fund. The FY2012-FY2016 Capital Improvement
Program includes a budget of $29.08 million for various capital projects in the areas of solid waste and
stormwater. Each project is discussed in detail on the following pages.
TOTAL
FY2012 FY2013 FY2014 FY2015 FY2016 FUNDS
CAPITAL PROJECTS BUDGET BUDGET PROPOSED PROPOSED PROPOSED FY2012-2016
SOLID WASTE ENTERPRISE FUND
Bridge Connection Between Units -$ -$ -$ 0.250$ 1.200$ 1.450$
Leachate Pump Station -$ 0.040$ 0.460$ -$ -$ 0.500$
Stationary Compactor -$ 0.170$ -$ -$ -$ 0.170$
Equipment Replacement Program 0.350$ 0.700$ 0.850$ 0.350$ 0.300$ 2.550$
SOLID WASTE ENTERPRISE FUND TOTAL 0.350$ 0.910$ 1.310$ 0.600$ 1.500$ 4.670 $
STORMWATER ENTERPRISE FUND
Neighborhood Drainage Projects 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$
Flood Projects and Studies 4.705$ 4.705$ 4.000$ 4.000$ 4.000$ 21.410$
STORMWATER ENTERPRISE FUND TOTAL 5.305$ 5.305$ 4.600$ 4.600$ 4.600$ 24.410 $
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 205
SOLID WASTE PROJECTS
Negligible Impact on Operating Budget
PROJECT DESCRIPTION
The Solid Waste Enterprise Fund accounts for
operations of
the County’s waste disposal,
recycling, and landfill. Revenues are derived
from three major source categories: tipping fees,
property taxes, and other. Capital projects for
the landfill include (1) the construction of a
bridge connecting the access roads between Unit
One and Unit Four at the Twin Chimneys
Landfill; (2) the construction of a pump station
for leachate removal from the northern
collection area within Cell V of Unit one at the
Twin Chimneys Landfill; (3) the replacement of
the stationary compactor at the O’Neal Convenience Center; and (4) the continued replacement of heavy
equipment used in the transport and disposal of municipal solid waste.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority II: Infrastructure, which encompasses providing adequate
funding for landfill capital needs.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the Solid Waste Enterprise Fund and is funded through revenue received
for that fund. No additional impact on the operating budget is anticipated.
SOLID WASTE ENTERPRISE FUND
PROJECTS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Bridge Connection Between Units - $ -$ -$ -$ 0.250$ 1.200 $ 1.450 $
Leachate Pump Station - - 0.040 0.460 - - 0.500
Stationary Compactor - - 0.170 - - - 0.170
Equipment Replacement Program - 0.350 0.700 0.850 0.350 0.300 2.550
TOTAL PROJECT COST -$ 0.350$ 0.910$ 1.310$ 0.600$ 1.500 $ 4.670 $
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
Enterprise Fund Revenue - $ 0.350$ 0.910$ 1.310$ 0.600$ 1.500 $ 4.670 $
TOTAL PROJECT FUNDING -$ 0.350$ 0.910$ 1.310$ 0.600$ 1.500 $ 4.670 $
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - - - -
County of Greenville
Operating and Capital Budget
Fiscal Years 2012 and 2013 206
STORMWATER PROJECTS
No Impact on Operating Budget
PROJECT DESCRIPTION
The projects for stormwater include fundi
ng for
neighborhood drainage improvement projects and flood
projects and/or studies.
PROJECT JUSTIFICATION
This project is consistent with County Council Priority II:
Infrastructure, which provides for funding to resolve
drainage problems and for stormwater flood projects.
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the Stormwater Enterprise Fund and is funded through revenue received
for that fund. No additional impact on the operating budget is anticipated.
PROJECT ITEMS
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
COST
Improvements - Neighborhood Flood 5.520$ 0.600 $ 0.600$ 0.600$ 0.600$ 0.600 $ 8.520 $
Improvements - Flood Studies 28.308 4.705 4.705 4.000 4.000 4.000 49.718
Management 6.000 - - - - - 6.000
TOTAL PROJECT COST 39.828$ 5.305 $ 5.305$ 4.600$ 4.600$ 4.600 $ 64.238 $
PROJECT FUNDING SOURCES
FUNDING
TO-DATE
FY2012
APPROVED
FY2013
APPROVED
FY2014
PROPOSED
FY2015
PROPOSED
FY2016
PROPOSED
TOTAL
PROJECT
FUNDING
Enterprise Fund Revenue 39.822 $ 5.305 $ 5.305$ 4.600$ 4.600$ 4.600 $ 64.232 $
TOTAL PROJECT FUNDING 39.822$ 5.305 $ 5.305$ 4.600$ 4.600$ 4.600 $ 64.232 $
OPERATIONAL COSTS
Operating Impact -$ -$ -$ -$ - $ -$
Cumulative Operating Impact -$ -$ -$ -$ - $ -$
FTEs Added - - - - - -