Capital Projects
Greenville County · Greenville County · Budget documents
Open the original document More from Greenville County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
COUNTY OF GREENVILLE
CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement Planning process.
This section of the document provides information on the multi-year capital improvement program, the current
program status, a summary of capital projects and a copy of the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent and
nonrecurring projects, which should be financed over a period of years. Greenville County has selected a
programming period of 5 years. The development of a Capital Improvement Plan (CIP) involves a
comprehensive evaluation of project planning, justification, coordination needs, priorities and relationship to
budgeting policies. Therefore, the capital improvement budget is considered with budget decisions. Capital
improvement programming is a continuous process involving yearly adjustments. The CIP includes capital
projects recommended for fiscal years 2006 through 2010. Each fiscal year’s capital budget is submitted in
conjunction with its respective operating budget. The CIP multi-year plan includes projects for which funding is
currently available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2004 January – June 2005
Departmental
program plans
prepared and capital
projects submitted to
CIP team.
July - November
CIP Team
Review
Requests
December
CIP Team reviews,
prioritizes and
recommends capital
program
January -April
County Departments prepare
CIP requests
by October 30
Budget/Planning
Staff compile
project information
By December31
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County Council
adopts CIP and
capital budget
May - June
County
Administrator’s
Recommended
Budget
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
173
CURRENT PROGRAM STATUS
The FY2006-2010 Capital Improvement Program totals $82.457 million for projects in the areas of
technological improvements, facilities, infrastructure, solid waste, and stormwater. For the current biennium
budget, capital projects total $17.101 million for FY2006 and $16.624 million for FY2007. Below are
graphic comparisons of budgeted capital projects by fund and by type. The following page provides a detailed
listing of capital projects and financing summary. In the capital projects fund, infrastructure expenditures are by
far the greatest percentage. Capital projects funded by the County’s enterprise funds are specific to each
respective fund.
CAPITAL PROJECTS BY FUND
Capital Projects
Fund
82.78%
Stormwater
Enterprise Fund
15.30%
Solid Waste
Enterprise Fund
1.91%
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements. The majority of
improvements are for infrastructure improvements, which includes the County’s road program. Another large
area is stormwater, which includes drainage projects and specific task force projects.
$0
$10
$20
$30
$40
$50
$60
Millions
$70
Technolo
gy
Faciliti
es
Infrastructu
re
Solid
Waste
Storm
water
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
174
COUNTY OF GREENVILLE
COMPREHENSIVE CAPITAL IMPROVEMENT PROGRAM
FINANCING SUMMARY (in Millions)
TOTAL OPERATING OPERATING
CAPITAL PROJECTS CURRENT FY06 FY07 FY08 FY09 FY10 FUNDS IMPACT IMPACT
FUNDING SOURCE BUDGET BUDGET PROPOSED PROPOSED PROPOSED FY2006-FY2010 FY2006 FY2007
COUNTY GOVERNMENT DEPARTMENTS
Technological Improvements
Information Technology General Fund Transfer 1.900$ 1.700$ - $ - $ - $ 3.600$ -$ -$
Ortho Photography/Land Base General Fund Transfer 0.200$ 0.100$ - $ - $ 0.300$ 0.600$ -$ -$
TOTAL 2.100$ 1.800$ - $ - $ 0.300$ 4.200$ -$
Facilities
Carpet Replacement General Fund Transfer - $ - $ - $ - $ 0.260$ 0.260$ -$ -$
TOTAL - $ - $ - $ - $ 0.260$ 0.260$ -$
Infrastructure
Road Program RMF/GOBond 11.600$ 11.600$ 11.600$ 11.000$ 18.000$ 63.800$ -$ -$
TOTAL 11.600 $ 11.600 $ 11.600$ 11.000$ 18.000$ 63.800$ -$
CAPITAL PROJECTS FUND TOTAL 13.700 $ 13.400 $ 11.600$ 11.000$ 18.560$ 68.260$ -$ -$
SOLID WASTE ENTERPRISE FUND
Solid Waste
Landfill Solid Waste Fes/Millage 0.500$ 0.700$ - $ - $ - $ 1.200$ -$ -$
Enoree Convenience Center General Fund Transfer 0.377$ - $ - $ -$ - $ 0.377$ 0.183$ -$
SOLID WASTE ENTERPRISE FUND TOTAL 0.877$ 0.700$ - $ - $ - $ 1.577$ 0.183$ -$
STORMWATER ENTERPRISE FUND
Neighborhood Flood Projects Stormwater Fee 0.600$ 0.600$ 0.600$ 0.600$ 0.600$ 3.000$ -$ -$
Stormwater Task Force Projects Stormwater Fee 1.924$ 1.924$ 1.924$ 1.924$ 1.924$ 9.620$ -$ -$
STORMWATER ENTERPRISE FUND TOTAL 2.524$ 2.524$ 2.524$ 2.524$ 2.524$ 12.620$ -$ -$
TOTAL FOR ALL CAPITAL PROJECTS 17.101 $ 16.624 $ 14.124$ 13.524$ 21.084$ 82.457$ 0.183$ -$
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
175
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2006
The chart below shows the relationship between the operating budget and capital
expenditures for FY2006. Capital expenditures of $19.055 million include
capital projects of $17.101 million. The impact on the $126.630 million
operating budget is $6.850 million. This amount includes $6.667 million in
debt service for capital projects, $0.183 million in estimated operational costs
for new projects. The remaining $12.101 million for “pay-as-you-go” projects
will come from fund balances in each of the respective funds and/or special
revenue.
Capital
Budget
13.08%
Operating
Budget
86.92%
Operating Impact $6.850 million for FY2006
Debt Service $6.667 million (Principal and Interest)
Operations and Maintenance $0.183 million
Operating
Budget $18.951
$126.630 million
million
Capital
Budget
$19.055
million
“Pay-as-you-go” - $12.101 million
Fiscal Year 2007
The chart below shows the relationship between the operating budget and
capital expenditures for FY2007. Capital expenditures of $17.535 million
include capital projects of $16.624 million. The impact on the $116.005
million operating budget is $6.924 million, which is the debt service for
capital projects. The remaining $10.342 million for “pay-as-you-go” projects
will come from fund balances in each respective funds and/or special revenue.
Capital
Budget
13.13%
Operating
Budget
86.87%
Operating Impact $6.924 million for FY2007
Debt Service $6.924 million (Principal and Interest)
Operations and Maintenance $0 million
Operating
Budget $17.266
$116.005 million
million
Capital
Budget
$17.535
million
“Pay-as-you-go” - $10.342 million
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
176
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional staff,
maintenance, or daily operational costs. The amount of operating budget impact for each project is referred to
in the following terms:
OPERATING
IMPACT
DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating costs
No Impact The project will cause no change in operating costs
Negligible The impact will be very small; it will generate less than $10,000 per year in increased operating
expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating expenditures
Moderate The impact will be between $50,001 and $100,000 in increased operating expenditures
High The impact will increase operating expenditures $100,001 or more
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects. These sources
include: transfers from the County’s general operating fund, general obligation bonds, special source revenue
bonds via the County’s Infrastructure Bank, pay-as-you-go basis either through ad valorem revenues or fees,
and enterprise fund revenue. The chart below provides a description of funding sources.
FUNDING SOURCE DESCRIPTION
General Fund Transfer A major source of smaller capital projects is transfers from the County’s general operating fund.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X, Section 14,
of the constitution of the State of South Carolina, 1895, as amended, provides that counties
shall have the power to incur bonded indebtedness in such a manner and upon such terms and
conditions as the General Assembly shall prescribe by general law. General obligation debt may
be incurred only for public and corporate purpose in an amount not exceeding 8% of the
assessed value of all taxable property of each county.
Special Revenue Bonds The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that counties can
issue Special Source Revenue Bonds for the purpose of building or acquiring infrastructure
necessary to continue the economic development of a county. The portion of the CIP which
provides for the building or acquiring of infrastructure necessary to continue the economic
development of the County is included in the Infrastructure Bank and funded through Special
Source Revenue Bonds. The County has pledged the County portion of the revenue stream
from the multi-county parks, which includes fee-in-lieu-of-taxes (FILOT) revenues.
Pay-as-you-go Basis Another source utilized in the CIP is the pay-as-you-go basis either through ad valorem revenues
or fees. The CIP utilizes a road maintenance fee of $15 per vehicle to fund a portion of the
road program.
Enterprise Fund
Revenue
For the County’s two enterprise funds, Solid Waste and Stormwater, improvements are funded
through each fund’s respective revenue.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
177
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition or
construction of major capital projects, other than those financed by proprietary funds. The FY2006-FY2010
Capital Improvement Program includes a budget of $68.26 million for various capital projects in the areas of
public safety, technological improvements, facility improvements, and infrastructure improvements. Each
project is discussed in detail on the following pages.
TECHNOLOGICAL IMPROVEMENTS $4,200,000
A total of $4.2 million is programmed for technological improvements in the FY2006 – FY2010 Capital
Improvement Program. These projects include the Greenville County Information Technology Plan and the
Geographical Information System. These projects are described in more detail below.
INFORMATION TECHNOLOGY
No Impact on Operating Budget
PROJECT NAME: Information Technology LOCATION: Various
PROJECT DESCRIPTION
This project entails implementing a comprehensive network system to provide connectivity between and among
users, upgrading the County’s AS400 platform, installing network hardware and end-user query reporting, and
purchasing equipment for multiple county departments. The implementation of the Information Technology
components will provide the County and its residents/customers with a more advanced, user friendly, citizen
centered service organization through the addition, and replacement of equipment and software which will
heighten Greenville County’s technological abilities, enhance existing service delivery, and provide for future
growth in technology.
FY06 FY07 FY08 FY09 FY10 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Purchase of Equipment 1.900$ 1.700$ -$ -$ -$ 3.600$
Total Expenditures 1.900$ 1.700$ -$ -$ -$ 3.600$
General Fund Transfer 1.900$ 1.700$ -$ -$ -$ 3.600$
Total Funding 1.900$ 1.700$ -$ -$ -$ 3.600$
Personnel Services -$ - $ -$ -$ -$ -$
Operating Expenses - - - - - -
Contractual Services - - - - - -
Total Operating Costs -$ -$ -$ -$ -$ -$
OPERATING BUDGET IMPACT (No Impact)
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Information technology improvements are budgeted in a capital project fund and financed with a transfer from
the General Fund in both years of the biennium budget. The budget reflects the cost of purchasing the
necessary equipment. No additional operating costs are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
178
GIS-ORTHO PHOTOGRAPHY/LAND BASE UPDATES
No Impact on Operating Budget
PROJECT NAME: GIS – Ortho Photography/Land Base Updates LOCATION: Various
PROJECT DESCRIPTION
This project involves the production of a standard series of maps with survey control, aerial photography,
analytic triangulation and digital and hardcopy map production. These GIS land base updates began in FY2001
and provide a mechanism for annual, incremental updates of aerial photography, planimetric and topographic
data within the county. Changes in planimetric data such as building footprints, ponds, lakes, wetlands, streams,
rivers, dams, bridges, parks, airports, street center lines, edge of pavement lines, and parking lots as well as
changes in topography due to development will be captured and incorporated into the GIS database. The
digital orthophotography database will be updated providing a current, accurate picture of what exists on the
ground.
FY06 FY07 FY08 FY09 FY10 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Purchase of Equipment 0.200$ 0.100$ -$ -$ 0.300$ 0.600 $
Total Expenditures 0.200$ 0.100$ -$ -$ 0.300$ 0.600 $
General Fund Transfer 0.200$ 0.100$ -$ -$ 0.300$ 0.600 $
Total Funding 0.200$ 0.100$ -$ -$ 0.300$ 0.600 $
Personnel Services -$ -$ -$ -$ -$ -$
Operating Expenses - - - - - -
Contractual Services - - - - - -
Total Operating Costs -$ -$ -$ -$ -$ -$
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Geographic information system improvements are budgeted in a capital project fund and financed with a
general fund transfer. The budget reflects funding of $600,000 for the five-year CIP planning period for
updating the GIS land base. No additional operating costs are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
179
FACILITY PROJECTS $260,000
A total of $260,000 is programmed for facility upgrades for County owned facilities. These projects are
described in more detail below.
CARPET REPLACEMENT
No Impact on Operating Budget
PROJECT NAME: Carpet Replacement LOCATION: Various
PROJECT DESCRIPTION
This project involves replacement of interior floor coverings of Greenville County facilities. Carpet replacement
recommendations are based on age and condition of carpet and facility usage. This project will allow the
County to maintain appearance, safety standards, and ensure product availability in the most economical
manner.
FY06 FY07 FY08 FY09 FY10 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Renovations -$ - $ -$ -$ 0.260$ 0.260$
Total Expenditures -$ - $ -$ -$ 0.260$ 0.260$
General Fund Transfer -$ - $ -$ -$ 0.260$ 0.260$
Total Funding -$ - $ -$ -$ 0.260$ 0.260$
Personnel Services -$ -$ -$ -$ -$ -$
Operating Expenses - - - - - -
Contractual Services - - - - - -
Total Operating Costs -$ - $ -$ -$ -$ -$
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The replacement of the carpet at Greenville County facilities is budgeted in a capital project fund and financed
with a general fund transfer. No additional operating costs are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
180
INFRASTRUCTURE IMPROVEMENTS $63,800,000
A total of $63.8 million is programmed for infrastructure improvements for the FY2006 – FY2010 Capital
Improvement Program. These projects include the County’s road program, which is described in more detail
below.
ROAD PROGRAM
No Impact on Operating Budget
PROJECT NAME: Road Program LOCATION: Various
PROJECT DESCRIPTION
Road improvements include rehabilitation and/or reconstruction of “worst roads” first on a countywide basis.
Planned projects are to be consistent with: (1) division and Council approved programs to reduce risk to public
safety; (2) improvements on deteriorating road structures; and (3) Council approved Prescription for Progress
Plan. The road program also includes bridge replacements, a traffic program, and a contribution for local
municipality road programs.
FY06 FY07 FY08 FY09 FY10 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Paving Program 5.530$ 5.530$ 5.530$ 5.325$ 7.650$ 29.565$
Construction Projects 2.415 2.445 2.450 2.350 4.750 14.410
Bridges 0.755 0.810 0.745 0.650 1.500 4.460
Traffic & Safety Projects 0.225 0.225 0.225 0.225 0.650 1.550
Local Municipalities/Limited Partnerships 0.750 0.750 0.750 0.750 0.750 3.750
Cosulting Fees 1.925 1.840 1.900 1.700 2.700 10.065
Total Expenditures 11.600$ 11.600$ 11.600$ 11.000$ 18.000$ 63.800$
General Obligation Bonds 5.000$ 10.000$ -$ 5.000$ -$ 20.000$
Road Maintenance Fee 4.248 1.600 4.676 4.904 5.200 20.628
Other Sources/Fund Balance 2.352 - 6.924 1.096 12.800 23.172
Total Funding 11.600$ 11.600$ 11.600$ 11.000$ 18.000$ 63.800$
Personnel Services -$ -$ -$ -$ -$ -$
Operating Expenses - - - - - -
Contractual Services - - - - - -
Total Operating Costs -$ -$ -$ -$ -$ -$
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for the road program is included in the capital projects fund and is financed through several
instruments, such as General Obligation Bonds, Road Maintenance Fee, and other sources, including fund
balance, interest and contributions from the Infrastructure Bank. This project provides a direct benefit to
citizens through road and bridge improvements. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
181
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within these funds are
accounted for in the appropriate proprietary enterprise fund. The FY2006-FY2010 Capital Improvement
Program includes a budget of $14.197 million for various capital projects in the areas of solid waste and
stormwater. Each project is discussed in detail on the following pages.
SOLID WASTE ENTERPRISE FUND $1,577,000
The FY2006-FY20010 Capital Improvement Program includes a budget of $1.577 million for various capital
projects in the solid waste enterprise fund, such as landfill improvements and the renovation of the Enoree
Convenience Center.
LANDFILL
No Impact on Operating Budget
PROJECT NAME: Landfill LOCATION: Anderson Ridge Road
PROJECT DESCRIPTION
The Enterprise Fund accounts for operations of the County’s waste disposal, recycling, and landfill. Revenues
are derived from three major source categories: tipping fees, property taxes, and other. Capital projects for the
landfill include continued landfill development at the Southern Greenville County Landfill to ensure waste
disposal capacity, equipment replacement for efficient operations, and maintenance of inactive landfills.
FY06 FY07 FY08 FY09 FY10 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Landfill Development 0.500$ 0.700$ -$ -$ -$ 1.200$
Total Expenditures 0.500$ 0.700$ -$ -$ -$ 1.200$
Enterprise Fund Revenue 0.500$ 0.700$ -$ -$ -$ 1.200$
Total Funding 0.500$ 0.700$ -$ -$ -$ 1.200$
Personnel Services -$ -$ -$ -$ -$ -$
Operating Expenses - - - - - -
Contractual Services - - - - - -
Total Operating Costs -$ - $ -$ -$ -$ - $
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the Solid Waste Enterprise Fund and is funded through revenue received
for that fund. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
182
ENOREE CONVENIENCE CENTER
High Impact on Operating Budget
PROJECT NAME: Enoree Convenience Center LOCATION: Anderson Ridge Road
PROJECT DESCRIPTION
This capital project will allow for continued citizen disposal of waste after the Enoree Landfill closes in 2006.
The convenience center will receive residential waste and banned materials. Currently, approximately 450-650
vehicles/week use the Enoree Landfill as a convenience center. This project will help to reduce roadside or
illegal dumping in the Enoree Landfill area.
FY06 FY07 FY08 FY09 FY10 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Planning and Design 0.040$ -$ -$ -$ -$ 0.040$
Site Improvement 0.047 - - - - 0.047
Construction 0.120 - - - - 0.120
Purchase of Equipment 0.130 - - - - 0.130
Administration 0.005 - - - - 0.005
Contingency 0.035 - - - - 0.035
Total Expenditures 0.377$ -$ -$ -$ -$ 0.377$
General Fund Transfer 0.377$ -$ -$ -$ -$ 0.377$
Total Funding 0.377$ -$ -$ -$ -$ 0.377$
Personnel Services 0.065$ -$ - $ - $ - $ 0.065$
Operating Expenses 0.091 - - - - 0.091
Contractual Services 0.027 - - - - 0.027
Total Operating Costs 0.183$ -$ -$ -$ -$ 0.183$
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is provided for by a transfer from the General Fund to the Solid Waste Enterprise Fund
in the amount of $377,000 for FY2006. The annual operating impact of this project is anticipated to be
approximately $183,000, which includes funding for temporary personnel and other operational costs of the
Convenience Center.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
183
STORMWATER ENTERPRISE FUND $12,620,000
The FY2006-FY2010 Capital Improvement Program includes a budget of $12.620 million for capital projects
in the Stormwater Enterprise Fund.
STORMWATER PROJECTS
No Impact on Operating Budget
PROJECT NAME: Stormwater Projects LOCATION: Various
PROJECT DESCRIPTION
The project includes funding for neighborhood drainage improvement projects and flood projects and/or
studies.
FY06 FY07 FY08 FY09 FY10 TOTAL
PROPOSED PROPOSED PROPOSED PROPOSED PROPOSED
Neighborhood Flood Projects -$ -$ 0.600$ 0.600$ 0.600$ 1.800$
Yorkshire Drive 0.175 - - - - 0.175
Ila Street 0.180 - - - - 0.180
Vedado Lane 0.245 - - - - 0.245
4th Street - 0.265 - - - 0.265
Greyleaf Court - 0.150 - - - 0.150
Old Dunham Bridge Road - 0.125 - - - 0.125
Hammet Street study - 0.025 - - - 0.025
Satterfield/East Caroline Study - 0.035 - - - 0.035
Task Force Projects - - 1.924 1.924 1.924 5.772
Brushy Creek Study 0.300 - - - - 0.300
Lake Fairfield Recommendations 1.624 1.924 - - - 3.548
Total Expenditures 2.524$ 2.524$ 2.524$ 2.524$ 2.524$ 12.620$
Enterprise Fund Revenue 2.524$ 2.524$ 2.524$ 2.524$ 2.524$ 12.620$
Total Funding 2.524$ 2.524$ 2.524$ 2.524$ 2.524$ 12.620$
Personnel Services -$ -$ -$ -$ -$ - $
Operating Expenses - - - - - -
Contractual Services - - - - - -
Total Operating Costs -$ -$ -$ -$ -$ - $
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
FY2006-2010 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the Stormwater Enterprise Fund and is funded through revenue received
for that fund. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
184
CAPITAL IMPROVEMENT POLICIES
POLICY It is the policy of Greenville County government to develop, maintain, and revise
when necessary, a continuing Capital Improvement Program. The goal of the program
is to provide the infrastructure, i.e., streets, bridges, etc.; and physical plant required
by the County to respond to needs and demands of the citizens in the manner that
makes the best use of the limited monies available and is consistent with the various
legal requirements and policies of the County.
PURPOSE To set forth a process for capital improvement planning and programming,
administering, and implementing, and reporting.
DEFINITIONS
Capital The County’s Capital Improvement Program is a five-year plan for the making of
Improvement capital expendit ures to be incurred each year to meet the County’s identified capital
Program needs. It sets forth each project which the County is to undertake by fiscal year, and
outlines those resources needed or estimated to finance the projected expenditures.
Annual Capital The County’s capital budget is th e designated year within the five-year
Budget Capital Improvement Program approved by the County Council and is included as a
part of the County’s adopted budget.
Capital Project A capital project results in a permanent addition to the County’s assets. This is
accomplished by acquisition of property, new construction, or rehabilitation,
reconstruction, or renovation of an existing facility to a ‘like new’ condition which
extends its useful life or increases its usefulness or capacity. Capital projects are large-
scale endeavors in cost, in size, and in benefit to the county. They involve
nonrecurring expenditures or capital outlays from a variety of specifically identified
funding sources and do not duplicate maintenance activities in the operating budget.
Capital projects typically have a service life in excess of the life of the bond issues used
to finance them – typically from fifteen to twenty years. The purchase of vehicles is
not considered a capital project.
Unused Bond Unspent monies paid to the County by the purchaser or underwriter for an issue of
Proceeds county bonds and interest earned on those monies, intended for use to finance the
project or purpose for which the bonds were issued.
Unspent Capital Unspent capital project funds are th ose resources other than bond proceeds that
Project Funds have been received but are not spen t in completing the capital project as planned.
CAPITAL The continuing capital improvement planning and programming process is designed
IMPROVEMENT to yield four products on an annual basis: an annual capital budget, a three-year
PLANNING & funding program, a five-year CIP, and projects for future consideration. The
PROGRAMMING planning and programming process requires the active participation of the following
groups, entities, and agencies: citizens, County Council, Planning Commission,
County Administrator’s Office, Finance Department and Office of Management and
Budget, Public Services and Facilities Department, other departments of the county
involved in providing physical facilities, and as appropriate, representatives from cities
incorporated within Greenville County.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
185
Planning and The overall process of capital improvement planning and programming is in two
Programming phases: Phase I – five-year capital program development for separate functional
Process areas and Phase 2 – review of department proposals and development of countywide
capital program update. As the annual operating budget is developed, the
departments, the Office of Management and Budget and the County Administrator’s
Office will examine the five-year capital program and its impact on the operating
budget.
Phase 1 Each line department of the County is responsible for biennially developing a
departmental five-year capital improvement program. The building blocks of any CIP
program are the individual projects. For each project requested, regardless of funding
source, the departments are to provide the following information: community need
for or purpose of the project, specific description or definition of project scope,
priority ranking, fiscal impact, proposed financing schedule for each project, health
and safety effects, environmental and social effects, distribution effects and general
location, effects on inter-jurisdictional relationship, and advantages from relation to
other capital project proposals.
It is the responsibility of the other operating units, as named below, to take steps to
ensure that all essential information required by the Departments is available to the
Departments on a timely basis.
Overall policy direction for Capital Improvement Programs is provided by the
County Council and disseminated by the County Administrator’s Office.
Administrative policies and procedures are implemented by the County
Administrator.
The Public Works Division, working with Purchasing, is responsible for
providing five-year program project cost estimates and more refined budget
cost estimates.
The Public Buildings Division, working with Purchasing, is responsible for
developing an estimate of the operating and maintenance budget impact of
new, improved or expanded County facilities.
It is the responsibility of the Planning Commission to convey information on
the County’s Comprehensive Plan, including its policies and elements, facility
plans, development and population trends, and annexations.
The Office of Management and Budget is responsible for providing current
financial and budget information, respectively, affecting the short and long-
term funding of all capital projects.
Phase 2 The first level of review of departmental proposals is accomplished simultaneously and
independently by the Office of Management and Budget and the Planning
Commission. The Planning Commission reviews the priority projects listing of the
department and relates the projects and priorities to the Comprehensive Plan. The
Office of Management and Budget works within the priorities proposed by the
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
186
departments and develops financing strategies and identifies funding limitations for the
program proposals of the departments.
The second level of the review utilizes a Capital Improvements Team, which is hereby
established. The team is chaired by the Deputy County Administrator. The team shall
include the Director of General Services, the Planning Commission and the OMB
Manager. The team shall prepare a five-year CIP and submit to the County
Administrator the proposal no later than November 15 of each year. The County
Administrator shall propose a CIP to the County Council after having concluded an
initial budgetary review and comprehensive plan consistency review with the Planning
Commission.
The County Administrator’s proposed five-year Capital Improvement Program is to
be submitted to the County Council on or by the first council meeting in February of
each year.
CAPITAL The Capital Improvement Program administration and implementation process is
IMPROVEMENT designed to efficiently transform plans and programs to usable public facilities.
PROGRAM Specific objectives of the process are to implement projects at minimum cost and in
ADMINISTRATION & minimum time. The process begins with the annual adoption of the capital budget.
IMPLEMENTATION
The administration and implementation process requires the active participation of the
following groups, entities, and agencies: County Council, County Administrator’s
Office, Office of Management and Budget, Planning Commission and the Engineering
and Purchasing Division, and each department of the County involved in providing
physical facilities, maintenance and services.
Administration & The Capital Improvement Program ad ministration and implementation process can be
Implementation identified as having five phases: project initiation by department, project design,
Process contract bidding, project construction, and project closeout.
Responsibilities The following process description is ne cessarily general. It is intended to set forth the
responsibilities, functions, and required internal procedures for administering and
implementing capital projects. It should be recognized that there are other
requirements and procedures that are directed by outside agencies. They are primarily
associated with federal aid programs which have varying procedure requirements. This
directive will govern unless outside agency requirements dictate otherwise and, in such
instances, variations from this directive will be permitted only with County
Administrator approval.
Phase 1 Each Department is responsible for initiating those projects within its jurisdiction. The
Project Initiation purpose of the initiation process is to ver ify that conditions existing at the time of
approval still exist, that conditions of approval have been met, and that organizational
readiness and project analysis has been reviewed under current conditions. In general,
the order of project initiation will be consistent with the priority listing in the
approved program. The following steps are required in this phase:
The Department prepares scope of project, designated project director, and
submits capital improvement project memorandum, with scope of project
attached to initiate project. The following information should be attached to
the initiation request: request for a new project number, project cost
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
187
estimate, synopsis of project funding, project cash flow, project calendar,
capital budget authorization, and verification of any special (non-current
revenue) funding.
OMB verifies funding and advises the General Services Director who shall
establish sufficient revenue and expenditure accounts, making transfers as
appropriated, and forwards documents to the County Engineer for
evaluation. Projects shall be expended from authorized funds, using most
restrictive revenue first, as appropriated. Each reviewing department should
process initiation forms within three working days of receipt.
Architects and engineers evaluate scope and determine adequacy of budget
estimate. Other requirements such as land acquisition also reviewed at this
time.
Capital Improvement Team either recommends project approval or refers
back for additional work based on reports from initiating departments, OMB,
and the Engineering staff.
Approval by the County Administrator or designee is necessary to authorize
proceeding with project.
Phase 2 Unless specific exception is made in Phase 1 project initiation, the Engineering staff is
The Design responsible for executing the design phase. The County may award professional
services design and inspection contracts to outside architects and engineers for capital
improvement projects.
Throughout the design phase, consultants are required to maintain liaison with the
appropriate County departments to assure functional acceptability and that operating
and maintenance considerations are fully considered. The Engineering staff will ensure
proper coordination in this regard. The project design will be subject to acceptance by
the professional Engineering staff and the operating Department.
The Building Maintenance Division will refine earlier estimates of the operating and
maintenance budget impact of new or expanded County facilities during the design
phase. The projected operating and maintenance budget impact shall include, but is
not limited to, estimates of the increased costs for custodial and maintenance
requirements, utilities, and staffing needs for a period of each of five consecutive fiscal
years.
Phase 3 Upon the completion of the design phase, reporting of deviations between project
Contract Bidding budget and cost estimates resulting from design phase and authorization by the
County Administrator to proceed, the Engineering staff will forward plans and
specifications to the Director of General Services, Purchasing and the operating
Department Director for processing of the construction contract. The following steps
are required in the bidding process: issuance of notice of call for bids; conduct pre-bid
conference with prospective bidders, where appropriate; authorize written agenda to
contract documents as required; receipt and public opening of bids; refer bids to
Engineering and Purchasing staff and the operating department for evaluation and
recommendation; verify contractor’s ability to obtain bond and insurance documents
and compliance with purchase procedures; award of contract in accordance County
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
188
purchasing policies and procedures; approval as to form by the County Attorney
(public improvement contracts require the approval of County Council. Requests for
Council action must be submitted to OMB 8-10 working days before the Council
meeting. OMB is responsible for review and submittal to the County Administrator
for inclusion on Council agenda no later than 5 working days prior to Council
meeting.); execution of contract; approval by the County Administrator or designee;
and notify contractor, County representative responsible for administering the
contract, and operating Department that contract documents are completed.
Phase 4 Upon completion of Phase 3, the County representative designated in the contract to
Project Consultation/ administer the work and perform inspection will: (1) conduct a pre-construction
Construction conference (utilizing the checklist) to coordinate the construction with utility and
traffic requirements and to provide Purchasing the opportunity to explain equal
employment opportunity provisions, local and federal and the procedures for change
orders and process payments; (2) establish a date for commencement of the work
and issue a notice to proceed; (3) coordinate the inspection functions of the
consultant; (4) actively pursue the progress of the work, performing timely
inspections and processing progress payments as required; (4) where needed,
recommend and initiate change orders to the contract; (5) authorize field change
orders to the contract not to exceed $5,000 or 10% of the original contract price,
whichever is smaller and make recommendations to Purchasing for change orders in
excess of these amounts; (6) handle emergency field change orders; (7) conduct final
inspection of the project with the contractor, consultant and operating department
where appropriate; (8) ensure corrective action on all deficiencies; and (9) issue
certificate of completion and process final payment documents.
Phase 5 Upon completion of the construction phase and within 90 days of final contractor
Project Close-Out payment, the initiating Department will enter final costs, completion dates,
identification of unspent funds, and other pertinent information on projects close-out
form, sign the certificate of completion and return the original form to the General
Services Department. Departments shall be responsible to reconcile any differences
between project closeout detail and the County’s financial and CIP tracking system.
The General Services Department will verify the funding information, then shall close
out appropriate project accounts within fifteen days of receipt of notice verifying the
amount of unspent bond proceeds and/or unspent capital project funds.
Phase 6 After project closeout, total revenues should equal total expenses. There should be
Project Final no further charges to the project account.
REVISIONS IN OMB will be responsible for the coordination of the preparation and submission of
CAPITAL PROGRAMS reports, setting out revisions that are recommended, and the current status of the
AND CAPITAL capital projects. All proposed capital project changes shall be submitted through OMB
PROJECTS for the approval of the County Administrator.
Departments shall endeavor to implement without change their approved
capital program and the projects therein. However, it is recognized that, for a
variety of reasons, changes are necessary and, therefore, procedures to
accommodate changes are established herein.
No capital project shall be undertaken unless it is included in the capital
budget or is approved by County Council.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
189
No capital project shall be deleted from the capital budget unless approved
by the Council or notice given to Council.
In no case shall projects incur a funding deficit without approval of the
County Council.
The underlying principles governing the handling of proposed capital program
and capital project changes are to ensure consistency with County Council
policy direction, available budget capacity, and the achievement of the
overall functional objectives of the Department, as embodied in the adopted
CIP, and to ensure that changes are handled in a visible manner with all
appropriate entities involved.
All changes to capital programs and projects shall be reported to the County
Council on a quarterly basis.
PROJECT In October, January, April, and July, the OMB will assemble a Capital Improvements
REPORTING Project Status Report for distribution to the Council through the Quarterly Operating
PROCEDURE Report.
Status of Previously Each October and November, the Departments are scheduled to brief the Capital
Approved or Carried Improv ements Team on the status of that Department’s then existing capital program
Forward Projects budget and individual projects. This status briefing is especially useful in identifying
those projects that have fallen behind schedule and, thus, may need to be included,
although not originally planned, in a subsequent year’s budget.
The presence of carried forward projects could place the County in the awkward
position of having to use scarce budget capacity twice; once in the initial budget year
and then again in the subsequent period. The result is a needless use of legal budget
capacity and, therefore, carry forward projects are to be discouraged. Each
department will monitor project implementation closely.
County of Greenville
Operating and Capital Budget
Fiscal Years 2006 and 2007
190
Source: Greenville County website. First collected Oct 13, 2026.