County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
111
COUNTY OF GREENVILLE
CAPITAL PROJECTS
Capital projects are submitted and approved through the multi-year Capital Improvement
Planning process. This section of the document provides information on the multi-year capital
improvement program, the current program status, a summary of capital projects and a copy of
the Capital Improvement Policies.
CAPITAL IMPROVEMENT PROGRAM
The County of Greenville’s Capital Improvement Program is designed to identify major, infrequent
and nonrecurring projects, which should be financed over a period of years. Greenville County
has selected a programming period of 5 years. The development of a Capital Improvement Plan
(CIP) involves a comprehensive evaluation of project planning, justification, coordination needs,
priorities and relationship to budgeting policies. Therefore, the capital improvement budget is
considered with budget decisions. Capital improvement programming is a continuous process
involving yearly adjustments. The CIP includes capital projects recommended for fiscal years
2004 through 2008. Each fiscal year’s capital budget is submitted in conjunction with its
respective operating budget. The CIP multi-year plan includes projects for which funding is
currently available and for which future funding is reasonably assured.
CAPITAL IMPROVEMENT PLANNING PROCESS
Shown below is a graphic depiction of the process followed for capital improvement planning.
July – December 2002 January – June 2003
Departmental
program plans
prepared and
capital projects
submitted to CIP
team.
July - November
CIP Team
Review
Requests
December
County Departments
prepare CIP requests
by October 30
Budget/Planning
Staff compile
project
information
By December31
CIP Team reviews,
prioritizes and
recommends
capital program
January -April
County Council
adopts CIP and
capital budget
May - June
5-Year CIP and Capital
Needs Assessment
Developed
by January 15
County
Administrator’s
Recommended
Budget
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
112
CURRENT PROGRAM STATUS
The FY2004-2008 Capital Improvement Program totals $106.783 million for projects in the areas
of public safety, technological improvements, facilities, infrastructure, solid waste, and
stormwater. For the current biennium budget, capital projects total $27.504 million for FY2004
and $37.539 million for FY2005. Below are graphic comparisons of budgeted capital projects by
fund and by type. The following page provides a detailed listing of capital projects and financing
summary. In the capital projects fund, infrastructure expenditures are by far the greatest
percentage. The County’s Road Program comprises the majority of the infrastructure items.
Capital projects funded by the County’s enterprise funds are specific to each respective fund.
CAPITA L PRO JECTS BY FU N D
Capital Projects
Fund
82. 04%
Stormwater
Enterprise Fund
2. 55%
Solid W aste
Enterprise Fund
15. 41%
CAPITAL PROJECTS BY TYPE
Following is a graphic comparison of the capital improvements plan by type of improvements.
The majority of improvements are for infrastructure improvements, which includes the County’s
road program and drainage/stormwater issues. Another large area is public safety improvements,
due to the expansion of the County’s Detention Center.
$0
$10
$20
$30
$40
$50
$60
Millions
Pu
blic Safety
Techn
ology
Faci
lities
Infrast
ruct
ure
Solid Wast
e
Stormw
ate
r
Ag
encies
TOTAL OPERATING OPERATING
CAPITAL PROJECTS FUND CURRENT FY04 FY05 FY06 FY07 FY08 FUNDS IMPACT IMPACT
FUNDING SOURCE APPROVED APPROVED PROPOSED PROPOSED PROPOSED FY2004-FY2008 FY2004 FY2005
COUNTY GOVERNMENT DEPARTMENTS
Public Safety Projects
Expansion of Criminal Records Division General Fund Transfer - $ - $ 0.279$ - $ - $ 0.279$ - $ - $
Forensics Technology General Fund Transfer - $ - $ 0.141$ - $ - $ 0.141$ - $ - $
Property and Evidence Processing Station General Fund Transfer - $ 0.150$ - $ - $ 0.150$
Detention Center Addition General Fund Transfer 6.000 $ 16.000 $ 1.430 $ - $ - $ 23.430$ - $ - $
TOTAL 6.000$ 16.000 $ 2.000 $ - $ - $ 24.000$ - $ - $
Technological Improvements
Information Technology GF Transfer/Special Revenue 1.085 $ 0.700 $ 0.500 $ - $ - $ 2.285$ - $ - $
Ortho Photography/Land Base General Fund Transfer - $ 0.300$ 0.200 $ - $ - $ 0.500$ - $ - $
TOTAL 1.085$ 1.000 $ 0.700 $ - $ - $ 2.785$ - $ - $
Facilities
HVAC Systems General Fund Transfer 0.074 $ - $ - $ - $ - $ 0.074$ (0.010) $ (0.010) $
Carpet Replacement General Fund Transfer 0.260 $ - $ - $ - $ 0.250$ 0.510 $ - $ - $
County Square Renovations General Fund Transfer 1.000 $ - $ - $ - $ - $ 1.000$ - $ - $
Parking Lot Renovations General Fund Transfer 0.088 $ 0.088 $ - $ - $ - $ 0.175$ - $ - $
Security Enhancements General Fund Transfer 0.200 $ 0.200 $ - $ - $ - $ 0.400$ - $ - $
Energy Projects (HVAC Controls) State ConserFund Program 0.298 $ - $ - $ - $ - $ 0.298$ (0.041) $ (0.041) $
TOTAL 1.919$ 0.288 $ - $ - $ 0.250$ 2.457 $ (0.051) $ (0.051) $
Infrastructure
Water Lines General Fund Transfer 0.500 $ 0.500 $ - $ - $ - $ 1.000$ - $ 0
Road Program RMF/SSRB/GOBond 9.650 $ 11.101 $ 12.589 $ 11.600 $ 11.601 $ 56.541 $ - $ - $
TOTAL 10.150$ 11.601 $ 12.589 $ 11.600 $ 11.601 $ 57.541 $ - $ - $
COUNTY GOVERNMENT SUBTOTAL 19.154 $ 28.889 $ 15.289 $ 11.600 $ 11.851 $ 86.783 $ (0.051) $ (0.051) $
OUTSIDE AGENCIES
The Matrix Business Park General Fund Transfer 0.500 $ 0.500 $ - $ - $ - $ 1.000$ - $ - $
AGENCIES SUBTOTAL 0.500$ 0.500 $ - $ - $ - $ 1.000$ - $ - $
CAPITAL PROJECTS FUND TOTAL 19.654 $ 29.389 $ 15.289 $ 11.600 $ 11.851 $ 87.783 $ (0.051) $ (0.051) $
SOLID WASTE ENTERPRISE FUND
Solid Waste
Landfill Solid Waste Fess/Millage 6.500 $ 6.800 $ 1.000 $ 1.000 $ 1.000 $ 16.300 $ - $ - $
SOLID WASTE ENTERPRISE FUND TOTAL 6.500 $ 6.800 $ 1.000 $ 1.000 $ 1.000 $ 16.300 $ - $ - $
STORMWATER ENTERPRISE FUND
Stormwater Task Force Projects Stormwater Fee 1.350 $ 1.350 $ - $ - $ - $ 2.700$ - $ - $
STORMWATER ENTERPRISE FUND TOTAL 1.350 $ 1.350 $ - $ - $ - $ 2.700$ - $ - $
TOTAL FOR ALL CAPITAL PROJECTS 27.504 $ 37.539 $ 16.289 $ 12.600 $ 12.851 $ 106.783 $ (0.051) $ (0.051) $
COUNTY OF GREENVILLE COMPREHENSIVE CAPITAL IMPROVEMENT PROGRAM
FINANCING SUMMARY (in Millions)
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
113
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
114
RELATIONSHIP BETWEEN OPERATING AND CAPITAL BUDGETS
Fiscal Year 2004
The chart below shows the relationship between the operating budget
and capital expenditures for FY2004. Capital expenditures of $29.802
million include capital projects of $27.504 million. The impact on the
$112.838 million operating budget is $2.799 million. This amount
includes $2.588 million in debt service for capital projects approved in
prior years, $224,614 in debt service for capital projects in FY2004,
$38,000 for loan payment for State ConserFund loan, and $51,000 in
estimated savings from operations related to new projects. The
remaining $21.857 million for “pay-as-you-go” projects will come
from fund balances in each of the respective funds and/or special
revenue.
Capital
Budget
16. 23%
Operating
Budget
83. 77%
Operating Impact $2.799 million for FY2004
Debt Service $2.850 million (Principal and Interest)
Operations and Maintenance ($.051) million
Operating
Budget $24.488
$112.838 million
million
Capital
Budget
$29.802
million
“Pay-as-you-go” - $21.587 million
Fiscal Year 2005
The chart below shows the relationship between the operating
budget and capital expenditures for FY2005. Capital expenditures of
$38.630 million include capital projects of $37.539 million. The
impact on the $121.752 million operating budget is $3.032 million.
That amount includes $3.045 million in debt service for capital
projects approved in prior years, $38,000 for loan payment of State
ConserFund loan, and $51,000 in estimated savings for operations
related to capital projects. The remaining $37.539 million for “pay-
as-you-go” projects will come from general fund balance and/or
special revenue.
Capital
Budget
24. 09%Operating
Budget
75. 91%
Operating Impact $3.032 million for FY2005
Debt Service $3.084 million (Principal and Interest)
Operations and Maintenance ($.051) million
Operating
Budget $40.571
$150.267 million
million
Capital
Budget
$44.721
million
“Pay-as-you-go” - $37.539 million
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
115
OPERATING IMPACTS
A project might have an operating budget impact if the project includes the need for additional
staff, maintenance, or daily operational costs. The amount of operating budget impact for each
project is referred to in the following terms:
OPERATING
IMPACT
DESCRIPTION
Positive The project will either generate some revenue to offset expenses or reduce operating
costs.
No Impact The project will cause no change in operating costs
Negligible The impact will be very small; it will generate less than $10,000 per year in increased
operating expenditures.
Slight The impact will be between $10,001 and $50,000 in increased operating
expenditures.
Moderate The impact will be between $50,001 and $100,000 in increased operating
expenditures.
High The impact will increase operating expenditures $100,001 or more.
FUNDING SOURCES
The Capital Improvement Program utilizes a variety of funding sources to fund capital projects.
These sources include: transfers from the County’s general operating fund, general obligation
bonds, special revenue, special source revenue bonds via the County’s Infrastructure Bank, pay-
as-you-go basis either through ad valorem revenues or fees, and enterprise fund revenue. The
chart below provides a description of funding sources.
FUNDING SOURCE DESCRIPTION
General Fund
Transfer
A major source of smaller capital projects is transfers from the County’s general
operating fund.
General Obligation
Bonds
General Obligation Bonds are used to finance a variety of public projects. Article X,
Section 14, of the constitution of the State of South Carolina, 1895, as amended,
provides that counties shall have the power to incur bonded indebtedness in such a
manner and upon such terms and conditions as the General Assembly shall
prescribe by general law. General obligation debt may be incurred only for public
and corporate purpose in an amount not exceeding 8% of the assessed value of all
taxable property of each county.
Special Revenue One source utilized in the current CIP program is special revenue received from the
sale of Grady Hipp Nursing Home and Greenville Retirement Center.
Special Revenue
Bonds
The South Carolina Code of Laws, Section 4-1-175 and 4-29-68 provides that
counties can issue Special Source Revenue Bonds for the purpose of building or
acquiring infrastructure necessary to continue the economic development of a
county. The portion of the CIP which provides for the building or acquiring of
infrastructure necessary to continue the economic development of the County is
included in the Infrastructure Bank and funded through Special Source Revenue
Bonds. The County has pledged the County portion of the revenue stream from the
multi-county parks, which includes fee-in-lieu-of-taxes (FILOT) revenues.
Pay-as-you-go
Basis
Another source utilized in the CIP is the pay-as-you-go basis either through ad
valorem revenues or fees. The CIP utilizes a road maintenance fee of $15 to fund a
portion of the road program.
State ConserFund
Program
This program provides the capability for SC counties to partner with the State to
borrow money with a low interest rate for the purpose of funding energy related
projects with demonstrated operational savings.
Enterprise Fund
Revenue
For the County’s two enterprise funds, Solid Waste and Stormwater, improvements
are funded through each fund’s respective revenue.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
116
CAPITAL IMPROVEMENT PROJECTS SUMMARY
CAPITAL PROJECTS FUND
The Capital Projects Fund is used to account for financial resources to be used for the acquisition
or construction of major capital projects, other than those financed by proprietary funds. The
FY2004-FY2008 Capital Improvement Program includes a budget of $105.783 million for various
capital projects in the areas of public safety, technological improvements, facility improvements,
and infrastructure improvements. Each project is discussed in detail on the following pages.
PUBLIC SAFETY PROJECTS $24,000,000
A total of $24.0 million is included in the Capital Improvement Program to fund the construction,
expansion, and renovation of law enforcement and public safety facilities. These projects include
the construction of an additional inmate-housing pod for the Detention Center and renovation of
law enforcement support areas.
EXPANSION OF CRIMINAL RECORDS DIVISION
No Impact on Operating Budget
PROJECT NAME: Expansion of Criminal Records LOCATION: 20 McGee Street
PROJECT DESCRIPTION
The Criminal Records unit currently manages all criminal records generated by the Greenville
County Sheriff’s Office, the Greenville Police Department, EMS records and related billing
processes and all property seized by the Sheriff’s Office and Greenville Police Department. Record
storage space and data entry space for clerks has not increased since 1976. Currently, during a
typical month, approximately 8,000+ reports are received ranging from a single page to large
files containing multiple pages. This project involves the relocation of the Criminal Records
function to the 1994 Detention facility and would allow the opportunity for some future growth.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROV ED PROPOSED PROPOSED PROPOSED
Planning and Design 0.070 0.070
Construction 0 .209 0.209
Total Expenditures - - 0.209 - - 0.279
General Fund Transfer 0.279 0.279
Total Funding - - 0.279 - - 0.279
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL FUNDING SCHEDULE (IN M ILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
FY2004- 20 08 C APITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIO NS)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The renovation of the Criminal Records area is budgeted in a capital projects fund and is being
financed with a general fund transfer to capital projects in conjunction with the Detention Center
addition project. No impact on the operating budget is anticipated. Benefits of this project
include: custodial consolidation of all department records, adequate space for operations of the
Division, and enhanced security for the Division.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
117
FORENSIC TECHNOLOGY
No Impact on Operating Budget
PROJECT NAME: Forensic Technology LOCATION: 20 McGee Street
PROJECT DESCRIPTION
This project involves the replacement of three Livescan 3000N workstations. The Livescan devices
are biometric fingerprint imaging devices utilizing computer processing to capture, store, and
transmit fingerprint data in FBI NIST format. This system provides an inkless method of obtaining
fingerprints and then electronically transmits these images and data information to SLED for
criminal history purposes. The system has been redesigned and now allows the ability to capture
palm prints. Currently, palm prints requested on an individual must be obtained in ink, which is
time consuming, messy and requires extra space for a fingerprint stand. The automatic capturing
of palm prints would ensure that high quality impressions are obtained. The most important
element of the devices is that it allows for the ability to search against stored data.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Purchase of Equipment 0.141 0.141
Total Expenditures - - 0.141 - - 0.141
General Fund Transfer 0.141 0.141
Total Funding - - 0.141 - - 0.141
Personnel Services -
Operating Expenses -
Contractual Services -
Total Operating Costs - - - - - -
CAPITAL FUNDIN G SCHEDULE (IN M ILLIO NS)
OPERATIN G BUDGET IM PACT (No Impact)
FY2004- 2008 C APITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The replacement of this forensic technology is budgeted in the capital projects fund and is being
financed with a general fund transfer to capital projects in conjunction with the Detention Center
addition project. No impact on the operating budget is anticipated. This project will provide for
the replacement of aged equipment and allow for faster processing time by reducing errors and
time involved in capturing fingerprint and palm print information.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
118
PROPERTY AND EVIDENCE PROCESSING STATION
No Impact on Operating Budget
PROJECT NAME: Property and Evidence Processing Station LOCATION: 20 McGee Street
PROJECT DESCRIPTION
The Property and Evidence function is a part of the Criminal Records Division. Property and
Evidence stores all physical evidence seized/obtained by the Sheriff’s Office and the Greenville
Police Department. This project involves the development of a processing station in the
temporary morgue located in the parking lot of the Law Enforcement Center. This temporary
facility can be modified to create a drying space with appropriate ventilation for harmful and
annoying odors. Portions of the same facility can be modified and enhanced with security
measures to store repulsive items of evidence.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Construction 0.150 0.150
Total Expenditures - - 0.150 - - 0.150
General Fund Transfer 0.150 0.150
Total Funding - - 0.150 - - 0.150
Personnel Services -
Operating Expenses -
Contractual Services -
Total Operating Costs - - - - - -
FY2004- 2008 C APITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDIN G SCHEDULE (IN M ILLIO NS)
OPERATIN G BUDGET IM PACT (No Impact)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The creation of a property and evidence processing station for biohazard contaminated evidence
is budgeted in the capital projects fund and is being financed with a general fund transfer to
capital projects in conjunction with the Detention Center addition project. No impact on the
operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
119
DETENTION CENTER ADDITION
Impact on Operating Budget – High >$100,001
PROJECT NAME: Detention Center Addition LOCATION: 20 McGee Street
PROJECT DESCRIPTION
This project involves the construction of a separate multiple custody building located adjacent to
the current Detention Center. This project would increase the capacity of the facility to 1591
rated beds, an increase of 672 beds. The current facility is operating at 125% of its rated bed
capacity for general population adult inmates. This addition will be accommodated in the form of
new construction and minor renovations to the existing facility.
FY 04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Planning and Design 1.678 1.678
Site Improvement 0.048 0.048
Construction 17.292 17. 29 2
Purchase of Equipment 1.497 1.497
Administration 0.50 0 0.500
Contingency 1.500 1.500
Ot her 0.915 0.915
Total Expenditures - 1.678 21.752 - - 23.430
General Fund Transfer 6.000 16.000 1.43 0 23. 43 0
Total Funding 6.000 16.000 1.430 - - 23.430
Personnel Services 0.226 0.831 1.391 2.448
Operating Expenses 0.349 0.524 0.549 1.421
Contractual Services 0.022 - - 0.022
Total Operating Costs - - 0.597 1.355 1.939 3.891
General Fund 0.597 1.355 1.939 3.891
Total Funding - - 0.597 1.355 1.939 3.891
CAPITAL FUNDIN G SCHEDULE (IN M ILLIO NS)
OPERATING BUDGET IMPACT (High > $10 0,001)
OPERATIN G FUNDIN G SCHEDULE (IN MILLIO NS)
FY2004- 2008 C APITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The Detention Center addition is budgeted in a capital project fund and is being financed as a
pay-as-you-go project with transfers from the general fund balance. The budget reflects the
design and construction of the addition. The project has a high impact on the operating budget.
Operating costs are expected to be $597,000 beginning in FY2006. This will provide for six full-
time equivalent positions to begin the transition and phase-in of the addition. The full impact on
the operating budget will be seen in FY2007, resulting in operational increases of $1,355,000 for
salaries, utilities, and other related operational costs.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
120
TECHNOLOGICAL IMPROVEMENTS $2,785,000
A total of $2.785 million is programmed for technological improvements in the FY2004 – FY2008
Capital Improvement Program. These projects include the Greenville County Information
Technology Plan and the Geographical Information System. These projects are described in more
detail below.
INFORMATION TECHNOLOGY
No Impact on Operating Budget
PROJECT NAME: Information Technology LOCATION: Various
PROJECT DESCRIPTION
This project entails implementing a comprehensive network system to provide connectivity
between and among users, upgrading the County’s AS400 platform, installing network hardware
and end-user query reporting, purchasing imaging systems and equipment for multiple county
departments. The implementation of the Information Technology components will provide the
County and its residents/customers with a more advanced, user friendly, citizen centered service
organization through the addition, and replacement of equipment and software which will
heighten Greenville County’s technological abilities, enhance existing service delivery, and
provide for future growth in technology.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Purchase of Equipment 1.085 0.700 0.500 2.285
Total Expenditures 1.085 0.700 0.500 - - 2.285
General Fund Transfer 0.700 0.500 1.200
Special Revenue 1.085 - 1.085
Total Funding 1.085 0.700 0.500 - - 2.285
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE ( IN MILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
FY2004- 2008 C APITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Information technology improvements are budgeted in a capital project fund and financed with a
transfer from special revenue in FY2004 and a general fund transfer in FY2005 and FY2006. The
budget reflects the cost of purchasing the necessary equipment. No additional operating costs
are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
121
GIS-ORTHO PHOTOGRAPHY/LAND BASE UPDATES
No Impact on Operating Budget
PROJECT NAME: GIS – Ortho Photography/Land Base Updates LOCATION: Various
PROJECT DESCRIPTION
This project involves the production of a standard series of maps with survey control, aerial
photography, analytic triangulation and digital and hardcopy map production. These GIS land
base updates began in FY2001 and provide a mechanism for annual, incremental updates of
aerial photography, planimetric and topographic data within the county. Changes in planimetric
data such as building footprints, ponds, lakes, wetlands, streams, rivers, dams, bridges, parks,
airports, street center lines, edge of pavement lines, and parking lots as well as changes in
topography due to development will be captured and incorporated into the GIS database. The
digital orthophotography database will be updated providing a current, accurate picture what
exists on the ground.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROV ED PROPOSED PROPOSED PROPOSED
Purchase of Equipment 0.300 0.200 0.500
Total Expenditures - 0.300 0.20 0 - - 0.500
General Fund Transfer 0.300 0.200 0.500
Total Funding - 0.300 0.20 0 - - 0.500
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
FY2004 -2008 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Geographic information system improvements are budgeted in a capital project fund and
financed with a general fund transfer. The budget reflects funding of $500,000 for the five-year
CIP planning period for updating the GIS land base. No additional operating costs are expected to
be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
122
FACILITY PROJECTS $2,457,000
A total of $2.457 million is programmed for facility construction and upgrades for County owned
facilities. Projects include facility enhancements for County Square, including parking lot
renovations, energy projects, and security enhancements. These projects are described in more
detail below.
UPGRADE OF HVAC SYSTEMS
Impact on Operating Budget – Positive
PROJECT NAME: HV/AC System Upgrades LOCATION: Health Department
PROJECT DESCRIPTION
This project involves upgrading the HVAC systems at the Health Department. This facility is
currently being heated with 50+-year-old converted oil fired boilers (converted from coal to #2
fuel oil). These units are very inefficient and have borderline safety issues. New updated
equipment with better energy rating will reduce energy cost, operational and maintenance costs.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROV ED PROPOSED PROPOSED PROPOSED
Purchase of Equipment 0.074 0.074
Total Expenditures 0.074 - - - - 0.074
General Fund Transfer 0.074 0.074
Total Funding 0.074 - - - - 0.074
Personnel Services -
Operating Expenses (0 .010) (0.010) (0. 011) (0.011) (0.011) (0.053)
Contractual Services -
Total O perating Costs (0 .010) (0.010) (0. 011 ) (0. 01 1) (0.011) (0.053)
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATIN G BUDGET IM PACT (Positive)
FY2004-2008 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The replacement of the chiller at the Greenville County Health Department, one of Greenville
County’s facilities, is budgeted in a capital project fund and financed with a general fund transfer.
The budget reflects the cost of purchasing the equipment. Replacement of this outdated
equipment will provide a positive impact on the operating budget. Savings of $10,000 within the
operating budget for FY2004 and FY2005 are expected to be realized because of this project.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
123
CARPET REPLACEMENT
No Impact on Operating Budget
PROJECT NAME: Carpet Replacement LOCATION: County Square
PROJECT DESCRIPTION
This project involves the last phase of replacement of interior floor coverings of Greenville County
Square, one of Greenville County’s facilities. Greenville County Square, which houses the County’s
administrative and general government offices, is scheduled for carpet replacement in FY2004.
This County facility has not replaced the carpet in 15 years. Standards for commercial facilities
indicate replacement of floor coverings every 8-10 years. Carpet replacement recommendations
are based on age and condition of carpet and facility usage. This project will allow the County to
maintain appearance, safety standards and ensure product availability in the most economical
manner.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROV ED PROPOSED PROPOSED PROPOSED
Renovations 0.260 0.250 0.510
Total Expenditures 0.260 - - - 0.250 0.510
General Fund Transfer 0.260 0.250 0.510
Total Funding 0.260 - - - 0.250 0.510
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE (IN M ILLIONS)
OPERATING BUDGET IM PACT ( No Impact)
FY2004- 2008 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The replacement of the carpet at Greenville County Square is budgeted in a capital project fund
and financed with a general fund transfer. The budget reflects the cost of this renovation. No
additional operating costs are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
124
COUNTY SQUARE RENOVATIONS
No Impact on Operating Budget
PROJECT NAME: County Square Renovations LOCATION: County Square
PROJECT DESCRIPTION
Greenville County Square is a 350,000 square foot facility currently housing County offices and
departments. Approximately 10% of the space is leased to state and federal agencies and other
groups. The facility has been at the maximum occupancy level since 1996. In September 2001,
Craig, Gaulden and Davis, Inc., conducted a feasibility study for the facility to determine how to
more effectively utilize the building. An evaluation of the existing facility, conducted by means of
a physical survey an departmental and management interviews, revealed that the functions and
size of some departments make them unsuited for occupancy at County Square, and other
departments have requirements and space needs that make their current locations within County
Square less than ideal. A conceptual master plan was developed indicating recommendations for
department relocation. A phasing sequence was provided showing the order in which these
relocations and moves might occur with the least disruption to County operations.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Construction 1.000 1.000
Total Expenditures 1.000 - - - - 1.000
General Fund Transfer 1.00 0 1.000
Total Funding 1.000 - - - - 1.000
Personnel Services -
Operating Expenses -
Contractual Services -
Total Operating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE ( IN M ILLIONS)
CAPITAL FUNDING SCHEDULE ( IN M ILLIONS)
OPERATIN G BUDGET IM PACT ( No Impact)
FY2004- 2008 C APITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The renovation of County Square is budgeted in a capital project fund and financed with a general
fund transfer. The budget reflects the cost of this renovation for Phase II. No additional operating
costs are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
125
PARKING LOT RENOVATIONS
No Impact on Operating Budget
PROJECT NAME: Parking Lot Renovations LOCATIONS: County Square, Law
Enforcement Center, Health Department
PROJECT DESCRIPTION
This project provides for renovations to the parking lots of the following County facilities: County
Square, Law Enforcement Center, and the Health Department. The parking lots are 26 to 50 years
old for these facilities and are experiencing fatigue and failure in many areas. Many years of
traffic, tree roots, foot traffic, and renovation projects have contributed to these problems. Some
injuries and claims for damage have been associated with damaged areas of parking lots.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Construction 0.088 0.088 0.175
Total Expenditures 0.08 8 0.088 - - - 0.175
General Fund Transfer 0.088 0.088 0.175
Total Funding 0.08 8 0.088 - - - 0.175
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
FY200 4-200 8 CAPITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The request for funding renovations to the parking lots of County facilities is appropriated over a
two-year period for fiscal years 2004 and 2005. Funding ($87,500 for each fiscal year) is
budgeted in a capital project fund and financed with a general fund transfer. No additional
operating costs are expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
126
SECURITY ENHANCEMENTS
No Impact on Operating Budget
PROJECT NAME: Security Enhancements LOCATION: County Square, Courthouse
PROJECT DESCRIPTION
Security audits have been conducted for two County facilities: County Square and the Courthouse
(General Sessions Court). The audits were conducted by DLR Group/Enwright and Associates to
determine the vulnerability to certain types of threats. These threats include but are not limited
to bodily harm of employees and staff, theft, bombing, and biohazard attacks. The audits were
intended to serve as a guideline for security enhancement. They do not contain
recommendations for providing the maximum amount of security, but contain recommendations
for enhancing security while keeping costs, convenience, and accessibility in mind. For both
facilities, recommendations were made concerning perimeter security, entry security, and interior
security.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Purchase of Eqiupment 0.200 0.200 0.400
Total Expenditures 0.20 0 0.200 - - - 0.400
General Fund Transfer 0.200 0.200 0.400
Total Funding 0.20 0 0.200 - - - 0.400
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
FY200 4-200 8 CAPITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
The request for funding security enhancements for County Square and the Courthouse is
appropriated over a two-year period for fiscal years 2004 and 2005. Funding is budgeted in a
capital project fund and financed with a general fund transfer. No additional operating costs are
expected to be incurred.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
127
ENERGY PROJECTS (HV/AC CONTROLS)
Impact on Operating Budget – Positive
PROJECT NAME: Energy Projects (HVAC Controls) LOCATIONS: County Square, Law
Enforcement Center
PROJECT DESCRIPTION
This project involves the implementation of energy-related projects. The project includes lighting
retrofits for the Detention Center at the Law Enforcement Center facility. The project also includes
upgrading the DDC Control System, installing pulse tap on main meter, ductwork/mechanical
systems changes to correct hot spot/cold spot locations for the County Square facility.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Purchase of Eqiupment 0.298 0.298
Total Expenditures 0.298 - - - - 0.298
State ConserFund Program 0.298 0.29 8
Total Funding 0.298 - - - - 0.298
Personnel Services -
Operating Expenses (0.041) (0.041) (0.042) (0.042) (0.042) (0.208)
Contractual Services -
Total O perating Costs (0.041) (0.041) (0.042) (0.042) (0.042) (0.208)
FY2004- 2008 C APITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN MILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for these energy projects is included in the capital projects fund and is financed through
the State ConserFund Program administered by the South Carolina Energy Office. Greenville
County is a partner with the South Carolina Energy Office and thereby qualifies to borrow money
at a low interest rate for energy projects. The State has allocated a total of $297,670 to complete
these projects. Savings of $41,000 within the operating budget for FY2004 and FY2005 are
expected to be realized because of this project.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
128
INFRASTRUCTURE IMPROVEMENTS $57,41,000
A total of $57.541 million is programmed for infrastructure improvements for the FY2004 –
FY2008 Capital Improvement Program. These projects include the County’s road program, which
is described in more detail below.
ROAD PROGRAM
No Impact on Operating Budget
PROJECT NAME: Road Program LOCATION: Various
PROJECT DESCRIPTION
Road improvements include rehabilitation and/or reconstruction of “worst roads” first on a
countywide basis. Planned projects are to be consistent with: (1) division and Council approved
programs to reduce risk to public safety; (2) improvements on deteriorating road structures; and
(3) Council approved Prescription for Progress Plan. The road program also includes bridge
replacements, a traffic program, and a contribution for local municipality road programs.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROV ED PROPOSED PROPOSED PROPOSED
Planning and Design 0.312 0.150 0.622 0.150 0.550 1.784
Site A cquisition 0.150 0.476 0.164 0.815 0.165 1.770
Paving Program 5.262 5.084 6.719 3.708 4.851 25.624
Road and Inspection 0.900 2.671 2.139 4.052 2.975 12.737
Bridge 0.62 6 0.320 0.520 0.450 0.610 2.526
Traffic 0.450 0.450 0.450 0.450 0.450 2.250
Local M unicipalities 0.700 0.700 0.700 0.700 0.700 3.500
Program Management 1.250 1.250 1.275 1.275 1.300 6.350
Total Expenditures 9.650 11.101 12. 589 11. 600 11 .601 56. 54 1
Special Source Revenue Bonds 8.000 - - - 8.000
General O bligation Bonds - - 5.000 10.250 - 15.250
Road Maintenance Fee 1.650 6.111 6.106 1.350 5.972 21.189
Other Sources/ Fund Balance 4.990 1.483 - 5.629 12.102
Total Funding 9.650 11.101 12. 589 11. 600 11 .601 56. 54 1
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDIN G SCHEDULE (IN M ILLIO NS)
OPERATING BUDGET IMPACT (No Impact)
FY20 04- 2008 C APITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for the road program is included in the capital projects fund and is financed through
several instruments, such as Special Source Revenue Bonds, General Obligation Bonds, Road
Maintenance Fee, and other sources. This project provides a direct benefit to citizens through
road and bridge improvements. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
129
WATERLINES
No Impact on Operating Budget
PROJECT NAME: Water Lines LOCATION: Various
PROJECT DESCRIPTION
This project involves the installation of city water lines for the southern portion of Greenville
County. This project was included as an amendment by Council to the Capital Improvement
Program.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROV ED PROPOSED PROPOSED PROPOSED
Construction 0.500 0.500 - - - 1.000
Total Expenditures 0.500 0.500 - - - 1.000
General Fund Transfer 0.500 0.500 - - - 1.000
Total Funding 0.500 0.500 - - - 1.000
Personnel Services -
Operating Expenses -
Contractual Services -
Total Operating Costs - - - - - -
FY200 4-2008 CAPITAL IMPROVEMENT PROGRAM
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE ( IN M ILLIONS)
OPERATIN G BUDGET IMPACT (No Impact)
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the capital projects fund and is financed through a general
transfer to the capital projects fund. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
130
AGENCY REQUESTS $1,000,000
Funds programmed for agency requests for the FY2004 – FY2008 Capital Improvement Program
total $1.00 million. This includes one project for infrastructure improvements for the Matrix
Business Park.
THE MATRIX BUSINESS PARK
No Impact on Operating Budget
PROJECT NAME: Matrix Business Park LOCATION: Highway 25
PROJECT DESCRIPTION
This project involves the development of approximately 1,800 acres adjacent to Route 25 and the
Southern Connector into a mixed use business, industrial, technology park. Funding is provided
by the County for the construction of the backbone roads. The remainder of funding is from
other sources such as C funds, GRATs, Tea 2, etc. Funding for FY2002 – FY2005 will provide
essential infrastructure on public roads in the Matrix Business Park. This includes road design
and construction, utilities, stormwater/drainage, engineering and related activities.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Construction 0.500 0.500 1.000
Total Expenditures 0.50 0 0.50 0 - - - 1.000
General Fund Transfer 0.500 0.500 1.000
Total Funding 0.50 0 0.50 0 - - - 1.000
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE (IN M ILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
FY2004 -2008 C APITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the capital projects fund and is funded through a transfer
from the General Fund. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
131
CAPITAL IMPROVEMENTS PROJECTS SUMMARY
PROPRIETARY FUNDS
The County operates two enterprise funds: Solid Waste and Stormwater. Capital projects within
those funds are accounted for in the appropriate proprietary enterprise fund. The FY2004-
FY2008 Capital Improvement Program includes a budget of $19.000 million for various capital
projects in the areas of solid waste and stormwater. Each project is discussed in detail on the
following pages.
SOLID WASTE ENTERPRISE FUND $16,300,000
The FY2004-FY2008 Capital Improvement Program includes a budget of $16.300 million for
various capital projects in the solid waste enterprise fund, such as landfill improvements,
acquisition of equipment.
LANDFILL
No Impact on Operating Budget
PROJECT NAME: Landfill LOCATION: Anderson Ridge Road
PROJECT DESCRIPTION
The Enterprise Fund accounts for operations of the County’s waste disposal, recycling, and
landfill. Revenues are derived from three major source categories: tipping fees, property taxes,
and other. Capital projects for the landfill include continued cell construction at the Enoree
Landfill to ensure waste disposal capacity, equipment replacement for efficient operations, and
maintenance of inactive landfills.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Cell Construction 6.500 6.800 1.000 1.000 1.000 16.300
Equipment Replacement
Inactive Landfill Postclosure
Enoree Closure
Landfill Permitting
Landfill Development 0.600
Total Expenditures 6.50 0 6.800 1.000 1.000 1.000 16.300
Enterprise Fund Revenue 6.500 6.800 1.000 1.000 1.000 16. 300
Total Funding 6.50 0 6.800 1.000 1.000 1.000 16.300
Personnel Services -
Operating Expenses -
Contractual Services -
Total O perating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE (IN M ILLIONS)
OPERATIN G BUDGET IM PACT (No Impact)
FY20 04- 20 08 C APITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the Solid Waste Enterprise Fund and is funded through
revenue received for that fund. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
132
STORMWATER ENTERPRISE FUND $2,700,000
The FY2004-FY2008 Capital Improvement Program includes a budget of $2.700 million for
capital projects in the Stormwater Enterprise Fund.
STORMWATER TASK FORCE PROJECTS
No Impact on Operating Budget
PROJECT NAME: Stormwater Task Force Projects LOCATION: Various
PROJECT DESCRIPTION
The Drainage Program includes funding for the “425” drainage projects. The following projects
are anticipated to be completed during the five-year CIP: Fairmont and Clearfield (FY2004),
Merrifield Park (FY2005). Funding is also included for Corp of Engineer flood studies.
FY04 FY05 FY06 FY07 FY08 TOTAL
APPROVED APPROVED PROPOSED PROPOSED PROPOSED
Task Force Projects 0.600 0.600 - - - 1.200
Other Project 0.750 0.750 1.500
Total Expenditures 1.350 1.350 - - - 2.700
Enterprise Fund Revenue 1.350 1.350 - - - 2.700
Total Funding 1.350 1.350 - - - 2.700
Personnel Services -
Operating Expenses -
Contractual Services -
Total Operating Costs - - - - - -
CAPITAL EXPENDITURE SCHEDULE (IN M ILLIONS)
CAPITAL FUNDING SCHEDULE (IN MILLIONS)
OPERATING BUDGET IMPACT (No Impact)
FY2004- 2008 CAPITAL IMPROVEMENT PROGRAM
IMPACT ON OPERATING BUDGET
(Discussion of recurring costs, savings that will be realized, benefit to the county and citizens)
Funding for this project is included in the Stormwater Enterprise Fund and is funded through
revenue received for that fund. No additional impact on the operating budget is anticipated.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
133
CAPITAL IMPROVEMENT POLICIES
POLICY It is the policy of Greenville County government to develop, maintain, and
revise when necessary, a continuing Capital Improvement Program. The
goal of the program is to provide the infrastructure, i.e., streets, bridges,
etc.; and physical plant required by the County to respond to needs and
demands of the citizens in the manner that makes the best use of the
limited monies available and is consistent with the various legal
requirements and policies of the County.
PURPOSE To set forth a process for capital improvement planning and programming,
administering, and implementing, and reporting.
DEFINITIONS
Capital The County’s Capital Improvement Program is a five-year plan for the
Improvement making of capital expenditures to be incurred each year to meet the
Program County’s identified capital needs. It sets forth each project which the
County is to undertake by fiscal year, and outlines those resources needed
or estimated to finance the projected expenditures.
Annual Capital The County’s annual capital budget is the designated year within the five-
Budget year Capital Improvement Program approved by the County Council and is
included as a part of the County’s annual adopted budget.
Capital Project A capital project results in a permanent addition to the County’s assets.
This is accomplished by acquisition of property, new construction, or
rehabilitation, reconstruction, or renovation of an existing facility to a ‘like
new’ condition which extends its useful life or increases its usefulness or
capacity. Capital projects are large-scale endeavors in cost, in size, and in
benefit to the county. They involve nonrecurring expenditures or capital
outlays from a variety of specifically identified funding sources and do not
duplicate maintenance activities in the operating budget. Capital projects
typically have a service life in excess of the life of the bond issues used to
finance them – typically from fifteen to twenty years. The purchase of
vehicles is not considered a capital project.
Unused Bond Unspent monies paid to the County by the purchaser or underwriter for an
Proceeds issue of county bonds and interest earned on those monies, intended for
use to finance the project or purpose for which the bonds were issued.
Unspent Capital Unspent capital project funds are those resources other than bond
Project Funds proceeds that have been received but are not spent in completing the
capital project as planned.
CAPITAL The continuing capital improvement planning and programming process is
IMPROVEMENT designed to yield four products on an annual basis: an annual capital
PLANNING & budget, a three-year funding program, a five-year CIP, and projects for
PROGRAMMING future consideration. The planning and programming process requires the
active participation of the following groups, entities, and agencies: citizens,
County Council, Planning Commission, County Administrator’s Office,
Finance Department and Office of Management and Budget, Public Services
and Facilities Department, other departments of the county involved in
providing physical facilities, and as appropriate, representatives from cities
incorporated within Greenville County.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
134
Planning and The overall process of capital improvement planning and programming is
Programming in two phases: Phase I – five-year capital program development for
Process separate functional areas and Phase 2 – review of department proposals
and development of countywide capital program update. As the annual
operating budget is developed, the departments, the Office of Management
and Budget and the County Administrator’s Office will examine the five-
year capital program and its impact on the operating budget.
Phase 1 Each line department of the County is responsible for biennually
developing a departmental five-year capital improvement program. The
building blocks of any CIP program are the individual projects. For each
project requested, regardless of funding source, the departments are to
provide the following information: community need for or purpose of the
project, specific description or definition of project scope, priority ranking,
fiscal impact, proposed financing schedule for each project, health and
safety effects, environmental and social effects, distribution effects and
general location, effects on inter-jurisdictional relationship, and
advantages from relation to other capital project proposals.
It is the responsibility of the other operating units, as named below, to take
steps to ensure that all essential information required by the Departments
is available to the Departments on a timely basis.
Overall policy direction for Capital Improvement Programs is
provided by the County Council and disseminated by the County
Administrator’s Office.
Administrative policies and procedures are implemented by the
County Administrator.
The Public Works Division, working with Purchasing, is responsible
for providing five-year program project cost estimates and more
refined budget cost estimates.
The Public Buildings Division, working with Purchasing, is
responsible for developing an estimate of the operating and
maintenance budget impact of new, improved or expanded County
facilities.
It is the responsibility of the Planning Commission to convey
information on the County’s Comprehensive Plan, including its
policies and elements, facility plans, development and population
trends, and annexations.
The Office of Management and Budget is responsible for providing
current financial and budget information, respectively, affecting the
short and long-term funding of all capital projects.
Phase 2 The first level of review of departmental proposals is accomplished
simultaneously and independently by the Office of Management and Budget
and the Planning Commission. The Planning Commission reviews the
priority projects listing of the department and relates the projects and
priorities to the Comprehensive Plan. The Office of Management and
Budget works within the priorities proposed by the
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
135
departments and develops financing strategies and identifies funding limitations
for the program proposals of the departments.
The second level of the review utilizes a Capital Improvements Team, which
is hereby established. The team is chaired by the Deputy County
Administrator. The team shall include the Director of General Services, the
Planning Commission and the OMB Manager. The team shall prepare a five-
year CIP and submit to the County Administrator the proposal no later than
November 15 of each year. The County Administrator shall propose a CIP to
the County Council after having concluded an initial budgetary review and
comprehensive plan consistency review with the Planning Commission.
The County Administrator’s proposed five-year Capital Improvement
Program is to be submitted to the County Council on or by the first council
meeting in February of each year.
CAPITAL The Capital Improvement Program administration and implementation
IMPROVEMENT process is designed to efficiently transform plans and programs to usable
PROGRAM public facilities. Specific objectives of the process are to implement
ADMINISTRATION & projects at minimum cost and in minimum time. The process begins with
IMPLEMENTATION the annual adoption of the capital budget.
The administration and implementation process requires the active
participation of the following groups, entities, and agencies: County
Council, County Administrator’s Office, Office of Management and Budget,
Planning Commission and the Engineering and Purchasing Division, and
each department of the County involved in providing physical facilities,
maintenance and services.
Administration & The Capital Improvement Program administration and implementation
Implementation process can be identified as having five phases: project initiation by
Process department, project design, contract bidding, project construction, and
project closeout.
Responsibilities The following process description is necessarily general. It is intended to
set forth the responsibilities, functions, and required internal procedures
for administering and implementing capital projects. It should be
recognized that there are other requirements and procedures that are
directed by outside agencies. They are primarily associated with federal aid
programs which have varying procedure requirements. This directive will
govern unless outside agency requirements dictate otherwise and, in such
instances, variations from this directive will be permitted only with County
Administrator approval.
Phase 1 Each Department is responsible for initiating those projects within its
Project Initiation jurisdiction. The purpose of the initiation process is to verify that
conditions existing at the time of approval still exist, that conditions of
approval have been met, and that organizational readiness and project
analysis has been reviewed under current conditions. In general, the order
of project initiation will be consistent with the priority listing in the
approved program. The following steps are required in this phase:
The Department prepares scope of project, designated project
director, and submits capital improvement project memorandum,
with scope of project attached to initiate project. The following
information should be attached to the initiation request: request
f or a new p roje ct number, pr oje ct cost
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
136
estimate, synopsis of project funding, project cash flow, project calendar,
capital budget authorization, and verification of any special (non-current
revenue) funding.
OMB verifies funding and advises the General Services Director who
shall establish sufficient revenue and expenditure accounts, making
transfers as appropriated, and forwards documents to the County
Engineer for evaluation. Projects shall be expended from authorized
funds, using most restrictive revenue first, as appropriated. Each
reviewing department should process initiation forms within three
working days of receipt.
Architects and engineers evaluate scope and determine adequacy of
budget estimate. Other requirements such as land acquisition also
reviewed at this time.
Capital Improvement Team either recommends project approval or
refers back for additional work based on reports from initiating
departments, OMB, and the Engineering staff.
Approval by the County Administrator or designee is necessary to
authorize proceeding with project.
Phase 2 Unless specific exception is made in Phase 1 project initiation, the
The Design Engineering staff is responsible for executing the design phase. The
County may award professional services design and inspection contracts to
outside architects and engineers for capital improvement projects.
Throughout the design phase, consultants are required to maintain liaison
with the appropriate County departments to assure functional acceptability
and that operating and maintenance considerations are fully considered.
The Engineering staff will ensure proper coordination in this regard. The
project design will be subject to acceptance by the professional
Engineering staff and the operating Department.
The Building Maintenance Division will refine earlier estimates of the
operating and maintenance budget impact of new or expanded County
facilities during the design phase. The projected operating and
maintenance budget impact shall include, but is not limited to, estimates of
the increased costs for custodial and maintenance requirements, utilities,
and staffing needs for a period of each of five consecutive fiscal years.
Phase 3 Upon the completion of the design phase, reporting of deviations between
Contract Bidding project budget and cost estimates resulting from design phase and
authorization by the County Administrator to proceed, the Engineering
staff will forward plans and specifications to the Director of General
Services, Purchasing and the operating Department Director for processing
of the construction contract. The following steps are required in the
bidding process: issuance of notice of call for bids; conduct pre-bid
conference with prospective bidders, where appropriate; authorize written
agenda to contract documents as required; receipt and public opening of
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
137
bids; refer bids to Engineering and Purchasing staff and the operating
department for evaluation and recommendation; verify contractor’s ability
to obtain bond and insurance documents and compliance with purchase
procedures; award of contract in accordance County purchasing policies
and procedures; approval as to form by the County Attorney (public
improvement contracts require the approval of County Council. Requests
for Council action must be submitted to OMB 8-10 working days before the
Council meeting. OMB is responsible for review and submittal to the
County Administrator for inclusion on Council agenda no later than 5
working days prior to Council meeting.); execution of contract; approval by
the County Administrator or designee; and notify contractor, County
representative responsible for administering the contract, and operating
Department that contract documents are completed.
j
Phase 4 Upon completion of Phase 3, the County representative designated in the
Pro ect Consultation/ contract toadminister the work and perform inspection will: (1) conduct a
Construction pre-construction conference (utilizing the checklist) to coordinate the
construction with utility and traffic requirements and to provide Purchasing
the opportunity to explain equal employment opportunity provisions, local
and federal and the procedures for change orders and process payments;
(2) establish a date for commencement of the work and issue a notice to
proceed; (3) coordinate the inspection functions of the consultant; (4)
actively pursue the progress of the work, performing timely inspections
and processing progress payments as required; (4) where needed,
recommend and initiate change orders to the contract; (5) authorize field
change orders to the contract not to exceed $5,000 or 10% of the original
contract price, whichever is smaller and make recommendations to
Purchasing for change orders in excess of these amounts; (6) handle
emergency field change orders; (7) conduct final inspection of the project
with the contractor, consultant and operating department where
appropriate; (8) ensure corrective action on all deficiencies; and (9) issue
certificate of completion and process final payment documents.
Phase 5 Upon completion of the construction phase and within 90 days of final
Project Close-Out contractor payment, the initiating Department will enter final costs,
completion dates, identification of unspent funds, and other pertinent
information on projects close-out form, sign the certificate of completion
and return the original form to the General Services Department.
Departments shall be responsible to reconcile any differences between
project closeout detail and the County’s financial and CIP tracking system.
The General Services Department will verify the funding information, then
shall close out appropriate project accounts within fifteen days of receipt of
notice verifying the amount of unspent bond proceeds and/or unspent
capital project funds.
Phase 6 After project closeout, total revenues should equal total expenses. There
Project Final should be no further charges to the project account.
REVISIONS IN OMB will be responsible for the coordination of the preparation and
CAPITAL PROGRAMS submission of reports, setting out revisions that are recommended, and
AND CAPITAL the current status of the capital projects. All proposed capital project
PROJECTS changes shall be submitted through OMB for the approval of the County
Administrator.
County of Greenville
Operating and Capital Budget
Fiscal Years 2004 and 2005
138
Departments shall endeavor to implement without change their
approved capital program and the projects therein. However, it is
recognized that, for a variety of reasons, changes are necessary
and, therefore, procedures to accommodate changes are
established herein.
No capital project shall be undertaken unless it is included in the
capital budget or is approved by County Council.
No capital project shall be deleted from the capital budget unless
approved by the Council or notice given to Council.
In no case shall projects incur a funding deficit without approval of
the County Council.
The underlying principles governing the handling of proposed
capital program and capital project changes are to ensure
consistency with County Council policy direction, available budget
capacity, and the achievement of the overall functional objectives of
the Department, as embodied in the adopted CIP, and to ensure
that changes are handled in a visible manner with all appropriate
entities involved.
All changes to capital programs and projects shall be reported to
the County Council on a quarterly basis.
PROJECT In October, January, April, and July, the OMB will assemble a Capital
REPORTING Improvements Project Status Report for distribution to the Council through
PROCEDURE the Quarterly Operating Report.
Status of Previously Each October and November , the Departments are scheduled to brief the
Approved or Carried Capital Improvements Team on the status of that Department’s then
Forward Projects existing capital program bu dget and individual projects. This status
briefing is especially useful in identifying those projects that have fallen
behind schedule and, thus, may need to be included, although not
originally planned, in a subsequent year’s budget.
The presence of carried forward projects could place the County in the
awkward position of having to use scarce budget capacity twice; once in
the initial budget year and then again in the subsequent period. The result
is a needless use of legal budget capacity and, therefore, carry forward
projects are to be discouraged. Each department will monitor project
implementation closely.