Agenda
City of Isle of Palms · Charleston County · meeting of Jul 1, 2026 · Agenda packets
Open the original document More from City of Isle of Palms
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Special City Council Meeting
5:00 p.m., Wednesday, July 1, 2026
Council Chambers
1207 Palm Boulevard, Isle of Palms, SC
Agenda
1. Call to Order and acknowledgment that the press and the public were duly notified
of the meeting in accordance with the Freedom of Information Act.
2. Purpose – discussion and consideration of change order from the Bastion Group in
the amount of $151,337 to deconflict water and sewer lines along Waterway
Boulevard
3. Adjournment
Z:\27670\27670.0010\Documents\Construction\Change Orders\Change Order #2\Change Order No 2.docx CO–2
C O N S T R U C T I O N C O N T R A C T
C H A N G E O R D E R
www.thomasandhutton.com
Project: Waterway Blvd. Pathway Construction Contract: Contract I
Change Order Number: 2
Owner: City of Isle of Palms Date Issued: TBD
Contractor: The Bastion Group, LLC Engineer’s Project Number: 27670.0010
The Contract is changed as follows:
• Add 3 water line offsets to the construction cost (previously shown on the plans) and
adjust various unit cost as show on the attached spreadsheet.
Not valid until signed by the Owner, Engineer, and Contractor.
Adjustments in the Contract Sum:
The original Contract Amount was ............................................................................. $ 2,890,156.00
Net change by previously authorized Change Orders............................................ $ -49,23 7.00
The Contract Amount prior to this Change Order was ............................................ $ 2,840,919.00
The new Contract Amount will be ( increased ) (decreased) (unchanged)
by this Change Order in the amount of ........... .................................................. $ 151,337.50
The new Contract Amount including this Change Order will be .......................... $ 2,992,256.50
Adjustments in the Contract Time:
Original Substantial Completion Date ....................................................................... 07/21/2026
Sum of Previously Approved Increases and Decreases ...................... ( 56 ) days
Date of Substantial Completion prior to this Change Order ................................... 09/15/ 2026
The Contract Time will be (increased) (decreased) (unchanged) by (0 ) days
The date of Substantial Completion as a result of this Change Order therefore is 09/15/2026
E
NGINEER RECOMMENDATION
Richard Karkowski, PE, PH, D.WRE 06/26/2026
ENGINEER S IGNATURE D ATE
CONTRACTOR ACCEPTANCE
CONTRACTOR S IGNATURE D ATE
OWNER APPROVAL
Douglas Kerr
OWNER S IGNATURE D ATE
CONTINUATION SHEET AIA DOCUMENT G703
AIA Document G702, APPLICATION AND CERTIFICATION FOR PAYMENT, containing APPLICATION NO: 1
Contractor's signed certification is attached. APPLICATION DATE: 3/24/2026
In tabulations below, amounts are stated to the nearest dollar. BG PROJECT NO: 26.007
Use Column I on Contracts where variable retainage for line items may apply. Change Order Reduction IOP Waterway BLD
A B C D E F F F G H I J K L M N O
Budget DESCRIPTION OF WORK NO. Units Measure Unit Price March May June Unit Remainder SCHEDULED WORK COMPLETE MATERIALS TOTAL % BALANCE RETAINAGE
Line Item BID 1 2 3 VALUE FROM PREVIOUS THIS PERIOD PRESENTLY COMPLETED TO FINISH (IF VARIABLE
APPLICATIONS STORED AND STORED RATE)
(NOT IN TO DATE
I OR J) (I+J+K)
General
1 Mobilization 1 LS 100000.00 100000 0 0 0 100,000.00$ 100,000.00$ -$ 100,000.00$ 100% -$ 10,000.00$
2 Construction Staking 1 LS 20000.00 12000 8000 0 0 20,000.00$ 20,000.00$ -$ 20,000.00$ 100% -$ 2,000.00$
3 Traffic Control 1 LS 18000.00 6000 6000 0 6000 18,000.00$ 12,000.00$ -$ 12,000.00$ 67% 6,000.00$ 1,200.00$
4 Erosion Conrol 1 LS 78500.00 16000 16000 16000 30500 78,500.00$ 32,000.00$ 16,000.00$ 48,000.00$ 61% 30,500.00$ 4,800.00$
5 As-Built Construction Plans 1 LS 12000.00 0 0 0 12000 12,000.00$ -$ -$ -$ 0% 12,000.00$ -$
Earthwork 0
6 Selected Clearing and Grubbing 2.400 AC 7650.00 0.15 0.50 0.50 1.25 18,360.00$ 4,972.50$ 3,825.00$ 8,797.50$ 48% 9,562.50$ 879.75$
7 Milling Existing Asphalt Pavement 1770 SY 11.55 0 0 0 1770 20,443.50$ -$ -$ -$ 0% 20,443.50$ -$
8 Removal & Disposal of Existing Pavement 6685 SY 11.65 0 2312 1500 2873 77,880.25$ 26,934.80$ 17,475.00$ 44,409.80$ 57% 33,470.45$ 4,440.98$
9 Removal & Disposal of Existing Concrete 600 SY 20.15 0 0 0 600 12,090.00$ -$ -$ -$ 0% 12,090.00$ -$
10 Controlled Fill - Borrow Material 750 CY 49.95 0 0 250 500 37,462.50$ -$ 12,487.50$ 12,487.50$ 33% 24,975.00$ 1,248.75$
11 Grading 11400 SY 5.95 730 3265 3000 4405 67,830.00$ 23,770.25$ 17,850.00$ 41,620.25$ 61% 26,209.75$ 4,162.03$
Roadway and Pathway 0
12 Graded Aggregate Base Course (8" Rooads and Driveways) 2191 SY 45.00 0 0 120 2071 98,595.00$ -$ 5,400.00$ 5,400.00$ 5% 93,195.00$ 540.00$
13 Graded Aggregate Base Course(4" for Pathway) 7715 SY 22.65 0 2700 1500 3515 174,744.75$ 61,155.00$ 33,975.00$ 95,130.00$ 54% 79,614.75$ 9,513.00$
14 Hot Mix Asphalt Intermmediate Course Type B 244 TON 223.00 0 0 0 244 54,412.00$ -$ -$ -$ 0% 54,412.00$ -$
15 Hot Mix Asphalt Surface Course Type B 1145 TON 223.00 0 0 500 645 255,335.00$ -$ 111,500.00$ 111,500.00$ 44% 143,835.00$ 11,150.00$
16 Concrete Curb and Gutter (1'-6") Vertical Face 367 LF 72.00 0 92 0 275 26,424.00$ 6,624.00$ -$ 6,624.00$ 25% 19,800.00$ 662.40$
17 Detectable Warning Surface 385 SF 54.00 0 0 0 385 20,790.00$ -$ -$ -$ 0% 20,790.00$ -$
18 Concrete Driveway (6") 550 SY 113.00 0 0 0 550 62,150.00$ -$ -$ -$ 0% 62,150.00$ -$
19 Gravel Drive 220 SY 40.80 0 0 0 220 8,976.00$ -$ -$ -$ 0% 8,976.00$ -$
Striping 0
20 4" White Solid Lines (Pvt. Edge Lines) Thermo 90 MIL 870 LF 3.00 0 0 0 3 2,610.00$ -$ -$ -$ 0% 2,610.00$ -$
21 24" White Solid Lines (Stop/Diagonal Lines) Thermo 125 MIL 100 LF 17.70 0 0 0 18 1,770.00$ -$ -$ -$ 0% 1,770.00$ -$
22 8" White Solid Lines (Crosswalk) Epoxy Paint Slow Cure 540 LF 5.00 0 0 0 5 2,700.00$ -$ -$ -$ 0% 2,700.00$ -$
23 4" Yellow Solid Lines (Pvt. Edge No Passing Zone) Thermo 90 MIL1410 LF 3.00 0 0 0 3 4,230.00$ -$ -$ -$ 0% 4,230.00$ -$
24 Reset Sign 45 EA 142.00 0 0 0 142 6,390.00$ -$ -$ -$ 0% 6,390.00$ -$
Drainage 0 -$
25 15" RC Pipe 151 LF 142.00 139 0 0 12 21,442.00$ 19,738.00$ -$ 19,738.00$ 92% 1,704.00$ 1,973.80$
26 18" RC Pipe 1558 LF 158.00 58 98 333 1069 246,164.00$ 24,648.00$ 52,614.00$ 11,995.00$ 89,257.00$ 36% 156,907.00$ 8,925.70$
27 Junction Box 2 EA 5750.00 2 11,500.00$ -$ -$ -$ 0% 11,500.00$ -$
28 Manhole 7 EA 5750.00 1 1 0 5 11,500.00$ 11,500.00$ -$ 11,500.00$ 100% -$ 1,150.00$
29 Catch Basin - Type 9 4 EA 5750.00 4 23,000.00$ -$ -$ -$ 0% 23,000.00$ -$
30 Drop Inlet (24" x 36") 22 EA 5750.00 5 5 3 9 126,500.00$ 57,500.00$ 17,250.00$ 42,585.00$ 117,335.00$ 93% 9,165.00$ 11,733.50$
31 Check Valve (15" In-Line) - Installation Only 1 EA 700.00 1 700.00$ -$ -$ -$ 0% 700.00$ -$
32 Check Valve (18" In-Line) - Installation Only 4 EA 700.00 4 2,800.00$ -$ -$ -$ 0% 2,800.00$ -$
33 Check Valve (24" In-Line) - Installation Only 1 EA 700.00 1 700.00$ -$ -$ -$ 0% 700.00$ -$
Water and Sewer Relocations 0 -$
34 Waterway Blvd. near 22nd Ave. – 12” WM horiz. offset 1 LS 179500.00 -150000 29500 0 29,500.00$ 29,500.00$ -$ 29,500.00$ 100% -$ 2,950.00$
35 23rd Ave. near Waterway Blvd – 8” WM vert. offset 1 LS 117250.00 117250 0 117,250.00$ 117,250.00$ -$ 117,250.00$ 100% -$ 11,725.00$
36 23rd Ave. near Waterway Blvd – 8” FM vert. offset with ARV 1 LS 117250.00 -5650 111600 0 111,600.00$ 111,600.00$ -$ 111,600.00$ 100% -$ 11,160.00$
37 3107 Waterway Blvd. – 8” FM horz. offset 1 LS 95200.00 95200 0 95,200.00$ -$ 95,200.00$ 95,200.00$ 100% -$ 9,520.00$
38 Waterway Blvd. near 32nd Ave. – 8” FM vert. offset with ARV1 LS 117250.00 -5150 0 112100 -$ -$ -$ -$ #DIV/0! -$ -$
39 3605 Waterway Blvd. – 8” FM vert. offset with ARV 1 LS 137250.00 -5150 132100 -$ -$ -$ -$ #DIV/0! -$ -$
40 4001 Waterway Blvd. – 8” FM vert. offset with ARV 1 LS 137250.00 5150 142400 136,687.50$ -$ -$ -$ 0% 136,687.50$ -$
41 Water Service Relocations/Replacements 6 EA 4950.00 6 29,700.00$ -$ -$ -$ 0% 29,700.00$ -$
42 Adjust Sewer Manhole Ring & Cover with Concrete Collar 17 EA 1250.00 3 17 21,250.00$ -$ 3,750.00$ 3,750.00$ 18% 17,500.00$ 375.00$
43 8" Sewer in 16" Steel Casing 58 LF 1785.00 58 103,530.00$ -$ -$ -$ 0% 103,530.00$ -$
Miscellaneous 0
44 Sodding 7 MSY 12800.00 12800 92,800.00$ -$ -$ -$ 0% 92,800.00$ -$
45 CMU Wall - Fire Station 313 LF 238.00 238 74,494.00$ -$ -$ -$ 0% 74,494.00$ -$
Owner Controlled Allowance 0
46 Miscellaneous 1 LS 75000.00 75000 -$ -$ -$ -$ #DIV/0! -$ -$
Change Order #1 Additional Line Items 0
Survey Revisions 1 LS 6000.00 6000 6000 6,000.00$ 6,000.00$ 6,000.00$ 100% -$ 600.00$
Testing 1 LS 18496.00 18496 0 18,496.00$ -$ -$ 0% 18,496.00$ -$
12" Watermain in Swale 1 LS 6000.00 6000 0 6,000.00$ 6,000.00$ 6,000.00$ 100% -$ 600.00$
Sewer Lateral in 12" Steel Casing 10 LF 500.00 500 5,000.00$ -$ -$ 0% 5,000.00$ -$
Permit Delays Management and Overhead 7 WKS 5000.00 0 35,000.00$ 35,000.00$ 35,000.00$ 100% -$ 3,500.00$
Structure Adjustments 1 LS 1000.00 1000 0 1,000.00$ 1,000.00$ 1,000.00$ 100% -$ 100.00$
Field Coordination Delays (incorrect utility locates, etc.) 12 LS 500.00 6000 0 6,000.00$ 6,000.00$ 6,000.00$ 100% -$ 600.00$
Revision Printing Costs 1 LS 500.00 5000 0 500.00$ 500.00$ 500.00$ 100% -$ 50.00$
Change Order #2 Additional Line Items 0
3102 Waterway Blvd 12" WM Vertical and Horizontal Offset 1 LS 179500.00 0 179500 0 179,500.00$ -$ -$ -$ 0% 179,500.00$ -$
32nd Ave. near Waterway Blvd – 8” WM vert. offset 1 LS 117250.00 0 117250 0 117,250.00$ -$ -$ -$ 0% 117,250.00$ -$
3200 Waterway Blvd 12" WM Verticall Offset 1 LS 179500.00 179500 0 179,500.00$ -$ -$ -$ 0% 179,500.00$ -$
Asphalt Price increase (14 and 15) 1 LS 9029.00 9029 0 -$
GRAND TOTALS 2,992,256.50$ 713,692.55$ 387,326.50$ 54,580.00$ 1,155,599.05$ 39% 1,836,657.45$ 115,559.91$
AIA DOCUMENT G703 · CONTINUATION SHEET FOR G702 · 1992 EDITION · AIA · © 1992
THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE, N.W. WASHINGTON, D.C. 20006-5292 l G703-1992
1
Douglas Kerr
From: Karkowski, Rick <karkowski.r@tandh.com>
Sent: Friday, June 26, 2026 10:47 AM
To: Douglas Kerr
Cc: Valenzuela, Maria; Robert Asero; Sean Kuester
Subject: Waterway Blvd. Change Order 2 discussion and justification
Douglas,
As you are aware, a potentially significant issue has developed concerning the project. However, we believe that
we have identified a path forward that will minimize the impact of the issue and allow the project to be completed
successfully.
The issue had originated with a discrepancy between the project’s plans and bid tabulation. Three (3) waterline
oƯsets were included on the plans but inadvertently not included in the project’s bid tabulation. A waterline oƯset
is a construction activity necessary to adjust the horizontal and/or vertical alignment of an existing waterline to
accommodate the installation of proposed infrastructure (in this case, drainage pipes and inlets proposed to
improve drainage and limit flooding along Waterway Blvd.). Because they were not listed in the bid tabulation,
prospective bidders (including the successful bidder/contractor) did not include the cost for these 3 oƯsets in
their bids for this work.
This issue was identified early in the project, and eƯorts have been ongoing to develop a plan to address the
situation. In April, the 3 water line oƯset issue was identified prior to a minor change order (Change Order 1) being
coordinated with the contractor. At that time, a change order was being prepared to address minor design
changes to avoid construction near a large oak tree and also incorporate minor design changes related to other
water and sewer work. CO1 resulted in a credit of $49,237 to the project. Due to the need to ensure work
continued on the project, CO1 was completed without addressing the 3 water line oƯsets.
At the time of the execution of CO1, T&H had requested the contractor provide pricing for the 3 water line oƯsets
so T&H, in coordination with City staƯ, could assess the impact of this cost and potentially adjust the project to
limit the financial impact of the additional work, and a second change order could be issued before this work
would be completed. However, the contractor proceeded with the 3 water line oƯsets and afterwards provided a
change order (CO 2) request of approximately $427,000. T&H, in coordination with City staƯ, immediately
contacted the contractor to discuss this request and communicated that an alternative would need to be
identified to lower (and preferably eliminate) this significant increase in project cost. T&H and City staƯ met
numerous times with the contractor and discussed various alternatives to the situation. The alternatives included:
lower pricing from the contractor for work completed, redesign of the project to minimize costs (including utilizing
conflict boxes for utility conflicts), elimination of certain work from the contracts, utilizing alternative sub-
contractors, the contractor self-performing some of the work planned to be sub-contracted, and other
alternatives. A complicating factor is that work on IOPW&S infrastructure must be completed by an IOPW&S pre-
qualified subconsultant. This limits the potential pool of sub-consultants and potentially aƯects pricing.
Recently, the contractor presented an amended change order (CO 2) request that significantly reduced the
potential financial impact to the project. The revised change order request would result in a contract increase of
approximately $102,100. This change order request includes a reduction in pricing for some work previously
completed, elimination of an asphalt escalation fee, and using an alternative (IOPW&S-approved) subconsultant
to complete the remaining water and sewer infrastructure work (at a lower cost than included in the bid). T&H
believes this is a fair solution to the project and recommends the City approve the change order (CO2). This work
2
is critical to the success of the project and necessary to attain the project's goals of providing tidal protection and
drainage improvements to the project area.
There are potential financial mitigation measures that can be taken to limit (and potentially eliminate) the increase
in project cost caused by this change order (CO2). These include:
1. Limiting the placement of sod during the restoration phase of the project. The project currently includes
7,250 SY of sod ($92,800 ) to be used in restoring areas disturbed by construction. This amount could be
reduced to only include critical areas (residential yards, right-of-way immediately adjacent residential
yards, etc.). Alternative restoration measures (seeding/mulching, hydro-seeding, mulching, etc.) could be
used in non-critical areas (critical/non-critical areas coordinated closely with City staƯ). The exact project
savings are unknown at this time, but are estimated to range from $60,000 up to the full sodding amount
($92,800).
2. Limit the replacement of certain driveways along the new pathway. The project had not included the
replacement of decorative/paver driveways along the pathway alignment due to the challenge of restoring
them to their original condition. The project generally included replacing all other asphalt and concrete
driveways along the pathway. A study of the condition of the existing driveways has been conducted to
assess the potential of retaining certain driveways that are in good condition. The pathway’s proposed
grading would be adjusted to be flush with the existing driveways if they were retained. The function of the
pathway, as a multi-use trail or flood barrier, would not be compromised by this change. The exact
savings to the contract are unknown at this time, but an early estimate (if fully implemented) could result in
savings of nearly $57,000.
3. Delay (and potentially modify) the work east of 41st Avenue. This work could be removed from the current
contract and completed during phase 3 of the Waterway Blvd. flood mitigation project. The work east of
41st Avenue included a knee-high wall along the back property line behind the City’s fire station (on City
property) and minor modifications to the Dewees Island Ferry Parking driveway (landscape berms and
minor grading to raise the driveway approximately 18 inches) on property owned by the Dewees Island
POA. T&H and City staƯ had been attempting to gain permission from the Dewees POA for the work on their
property. This coordination included assisting the POA in investigating the raising of their entire parking lot
to the target protection elevation (elev. 7.0 ft. NAVD88), which would have provided the necessary
protection for this portion of the project, as well as protect parked cars in the Dewees Island Ferry Parking
lot. The cost for this parking lot work (on private property) would have been borne by the POA, but could
have been partially oƯset by the amount planned for the work in this area (approximately $39,000).
However, the cost of raising the entire parking lot was not feasible for the POA. The POA subsequently
informed the City that they did not want to allow the originally planned work on their property. However,
conversations continue with the POA as to the potential for completing this work, but the timing may not
fall within the current contract.
I recommend the City to approve CO2 as currently proposed (project cost increase of $102,100) and instruct City
staƯ, T&H, and the contractor to work collaboratively to implement the 3 cost-saving measures listed above. I
believe the current contract could be completed for the original awarded contract budget ($2,890,156). This
approach would provide the most flexibility in completing the project and ensure the project is completed within
the City’s originally awarded budget. This would be achieved by limiting the installation of sod and not replacing
certain driveways (and possibly eliminating the work east of 41st Avenue). This would result in lower quantities for
these items being used than included in the current contract, which would be addressed by a subsequent CO that
would reduce the quantities of these line items (and the project contract cost) at the conclusion of the project.
Please let me know if you have any questions about this.
Sincerely,
Rick
3
RICK KARKOWSKI, PE, PH, D.WRE | Principal/Water Resources Manager
THOMAS & HUTTON
p 843-725-5280 m 843-708-1509
e karkowski.r@tandh.com
a 682 Johnnie Dodds Blvd.; Suite 100 | Mt. Pleasant, SC 29464
vCard | Website | LinkedIn | Facebook | Instagram | YouTube
Stay connected with Thomas & Hutton. Sign up for our newsletter.
PRIVILEGED AND CONFIDENTIAL: This electronic message and any attachments are confidential property of Thomas &
Hutton. The information is intended only for the use of the person to whom it is addressed. Any other interception, copying,
accessing, or disclosure of this message is prohibited. If you have received this message in error, please immediately notify
Thomas & Hutton and purge the message received. Do not forward this message without permission.