Slides
City of Isle of Palms · Charleston County · meeting of Jan 13, 2026 · Agendas
Open the original document More from City of Isle of Palms
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
City Council Workshop/
Planning Session
13 January 2026
City of Isle of Palms
City Hall Council Chambers
Agenda
• Opening Remarks by Mayor Pounds
• Strategic Plan Review
• Current Projects Update
• New Initiatives
• Threats to IOP
• Legislative Opportunities
• Beach Funding Options
• Miscellaneous
• Adjournment
• Five-minute comfort breaks at the top of each
hour
2
Strategic Plan Review
• Extant through 2027
• Discussion on efficacy/
relevance of current plan
• Discussion on drafting a new
plan
• Thought Drivers:
• What’s the same since 2022?
• What’s different since 2022?
• What’s on the horizon?
• Do we envision any fundamental
changes needed?
• How do we assess our priorities
and goals?
3
Current Projects Review
• Projects Extant Through 2026
• Beach Restoration
• Waterway Flood Mitigation
• Drainage Palm Blvd
• Marina Dredging
• Marina Parking
• Underground Power
4
New Initiatives Discussion
5
Threats to the City
• Thought Drivers:
• Revenue
• Expenses
• Projects
• State & Federal initiatives/
mandates
• Economic downturn
• Catastrophic weather events
• What else?
6
Legislative Opportunities
7
• Thought Drivers:
• Funding flexibility
• Grants
• Special Tax District(s)
• BCM regulatory flexibility
• Earmarks
• Lobbyist discussions
City of Isle of Palms Beach Restoration Project 2026
Cost Estimates, Revenue and Funding Scenarios
High Level Fund Balance and Revenue Impact Assessment
As of 1/2/2026 - For Discussion Only
Beach Restoration Macro Look
8
High Level Cost Estimate Per CY Sand - Beach Nourishment FY26/27
A rea CY Sand Percentage Amount
Estimated Cost for South/Breach Inlet Per CY Sand 563,200 32% $10,342,243
Estimated Cost for North/Wild Dunes Per CY Sand 1,196,800 68% $21,977,265
Total Funding Required for Beach Nourishment 1,760,000 100% $32,319,508
City of Isle of Palms Beach Restoration Project 2026
Cost Estimates, Revenue and Funding Scenarios
High Level Fund Balance and Revenue Impact Assessment
As of 1/2/2026 - For Discussion Only
*If SCPRT grant is not awarded an additional $1.5M will be required
Beach Restoration Funding Sources
9
Funding Sources:
WDCA $11,647,951
Grants-SCPRT* $1,524,000
City's Available Beach Preservation Fund $8,661,082
Funding Gap - Requirement From Other Funds/Sources $10,486,476
City of Isle of Palms Beach Restoration Project 2026
Cost Estimates, Revenue and Funding Scenarios
High Level Fund Balance and Revenue Impact Assessment
As of 1/2/2026 - For Discussion Only
Costs & Revenue Impact
10
Summary:
High Level Cost Estimate Per CY Sand - Beach Nourishment FY26/27
Estimated Cost for South/Breach Inlet $10,342,243
Estimated Cost for North/Wild Dunes $21,977,265
Total Funding Required for Beach Nourishment $32,319,508
Funding Sources:
WDCA Funding - North/WD $11,647,951
Grants- South /Breach Inlet, other State/Federal Funding $1,524,000
City's Available Beach Preservation Fee Fund $8,661,082
City's Excess (Deficit) - Required From Other Funds/Sources ($10,486,476)
Total City's Funding Required From Fund Balances $19,147,557
IOP Revenue Impact
Annual Interest Income Impact - Current LGIP Rates ($782,005)
.8 M
5.2 M
4.6 M
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Hospitality T ax Fund M unicipal A ccommodations Fee Fund State A ccommodations T ax Fund
A mount ($)
FUNDING FROM OTHER SOURCES
Gap Sourcing & Impacted Funds
City of Isle of Palms Beach Restoration Project 2026
Cost Estimates, Revenue and Funding Scenarios
High Level Fund Balance and Revenue Impact Assessment
As of 1/2/2026 - For Discussion Only
Potential Funding Sources:
Funding Gap - Requirement From Other Funds/Sources $10,486,476
Hospitality Tax Fund $750,000
Municipal Accommodations Fee Fund $5,200,000
State Accommodations Tax Fund $4,550,000
Total Other Funds/Sources $10,500,000
11
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31GENERAL FUND
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31
CAPITAL PROJECTS FUND
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31
TOURISM FUNDS
MUNI & STATE ATAX + HOSPITALITY TAX
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
12
Historical and Forecasted Ending Fund Balances (1/2)
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31
MUNICIPAL ATAX FUND
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31
STATE ACCOMODATIONS FUND
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31
HOSPITALITY FUND
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
500,000
4,500,000
8,500,000
12,500,000
16,500,000
20,500,000
24,500,000
Actual
FY22
Actual
FY23
Actual
FY24
Actual
FY25
Budget
FY26
Forcast
FY27
Forcast
FY28
Forcast
FY29
Forcast
FY30
Forcast
FY31
BEACH PRESERVATION FEE FUND
Fund Balance Revenue + Transfers In Expenditures + Transfers Out
13
Historical and Forecasted Ending Fund Balances (2/2)
BEACH RESTORATION PROJECT FUNDING
Wild Dunes Only Wild Dunes & Breach Inlet
2008 % of Total 2018 % of Total 2026 % of Total
IOP Portion -WD Public 1,900,000 20% 2,832,000 21% 8,832,933 27%
Private Contributions 5,926,000 63% 5,240,000 39% 11,679,095 36%
Charleston County 900,000 10% - 0% - 0%
State of South Carolina* 671,000 7% 3,614,000 27% 1,524,000 5%
FEMA - 0% 1,895,000 14% - 0%
Breach Inlet - 0% - 0% 10,283,480 32%
9,397,000 100% 13,581,000 100% 32,319,508 100%
Note: The total collections from the private stakeholders in 2008 was $7,108,000. Funds not
used in the 2008 offshore project were used for a smaller focused erosion project in 2012 with
approximately $240,000 remaining that is included in the 2018 Stakeholder estimate of $5,240,000.
2008 and 2018 Beach Restoration projects did not include Breach Inlet.
*SCPRT grant has not been awarded as 1/8/2026.
Cost Sharing Factors – 2008 to Present
City of Isle of Palms Beach Restoration Project 2026
Cost Estimates, Revenue and Funding Scenarios
High Level Fund Balance and Revenue Impact Assessment
As of 1/2/2026 - For Discussion Only
16
Cost Sharing Scenarios
Pre-Decisional Planning Document Only
*Scenario 5 is only scenario that includes soft cost.
City
Contribution
%
Miscellaneous
17
Adjournment
18
Source: City of Isle of Palms website. First collected Oct 13, 2026.