_08312026-4099
Town of Mount Pleasant · Charleston County · meeting of Aug 31, 2026 · Minutes
Open the original document More from Town of Mount Pleasant
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Bids and Purchases Committee
Monday, August 31, 2026
Municipal Complex, Council Chambers
100 Ann Edwards Lane, Mount Pleasant, SC 29464
Minutes
Click here to listen to recording
PowerPoint Presentation
1. Call To Order
Council Member Daniel Brownstein called the meeting to order at 8:00
AM, noting it was Committee Day, Monday, August 31, 2026. A moment
of silent reflection was observed before proceeding. Council Members
Mike Tinkey and Alex Crosby were also present.
2. Approval Of Minutes From August 3, 2026, Meeting
The minutes from the August 3, 2026, meeting were presented for
approval without discussion.
Motion to approve the minutes of August 3, 2026, meeting was made by
Council Member Mike Tinkey and seconded by Council Member Alex
Crosby. The motion carried 3-0.
3. Public Comment
Council Member Brownstein invited public comments. No members of
the public came forward, and the committee proceeded to the next
agenda item.
4. Award Of A Design Contract For Updating The 2023 Safety
Action Plan
Chief Financial Officer, Tammy Harness presented the item, providing
background on the Town's Target Zero resolution, adopted in March
2023, which committed the Town to substantially eliminating all traffic-
related deaths and serious injuries on its roadway network. She noted
that the Town's first Safety Action Plan was adopted in June 2023 and
subsequently enabled the Town to secure a Fiscal Year 2023 Safe
Streets and Roads for All (SS4A) implementation grant. The proposed
contract with Kimberly Horn would update that plan and position the
Town to pursue future grant funding opportunities.
Ms. Harness outlined the nine elements of the scope of services: project
management and coordination, data collection, goal setting, planning
structure, policy and process review, safety analysis, engagement and
collaboration, strategy and project selections, and a final report. The
update is expected to take approximately 18 months to complete.
Staff Engineer, Sophie Holmes addressed questions from the committee
regarding what was new in this update compared to the 2023 plan. She
identified two primary additions: a review of existing policies and
recommendations for updates aligned with federal Safe Streets and
Roads for all grant requirements, and a more proactive safety analysis
using new data resources. Among the new data tools, she highlighted
analysis products developed by the Berkeley-Charleston-Dorchester
Council of Governments (BCD COG) as part of their regional safety
action plan, as well as a product called "Replica," which leverages
datasets such as hard-braking and near-miss data to enable more
forward-looking analysis.
Council Member Tinkey commended the Town for the thoroughness of
the 2023 plan and its ambitious goals and expressed interest in which
prior countermeasures had proven most effective. Ms. Holmes indicated
that this analysis would be incorporated into the current update as part
of the work scope. Council Member Alex Crosby noted that she had
intended to ask about the new data sources included in the update and
acknowledged that Ms. Holmes had already addressed this topic in her
presentation. Council Member Brownstein highlighted that the 2023
Safety Action Plan had directly facilitated approximately $16 million in
grant funding for safety improvements and underscored the importance
of maintaining the Town's competitive positioning for future grant rounds.
Motion to award the design contract for updating the 2023 Safety Action
Plan to Kimberly Horn in the amount of $154,700.00 was made by Council
Member Tinkey and seconded by Council Member Crosby . The motion
carried 3-0.
5. Award Of A Contract For Electrical Renovations To Joe Gawrych
Baseball Complex / Sloan Park
Ms. Harness presented this item, explaining that the Town had solicited
bids from qualified contractors for electrical upgrades to the field lighting
at the Joe Gawrych Baseball Complex and Sloan Park, located behind
Whitesides Elementary School. The scope of work encompasses all
labor, materials, equipment, and supervision required for electrical
renovations and the installation of a new turnkey LED sports lighting
system for the baseball fields and batting cages, including demolition,
installation, testing, and commissioning. The construction window is
limited to 45 calendar days after receipt of equipment, with all work to be
completed between December 15, 2026, and February 1, 2027.
Three bids were received, and Camp Electric Company, Inc., was
determined to be the lowest responsive and responsible bidder.
Council Member Tinkey raised the issue of light spillage into adjacent
residential properties, referencing previous concerns experienced at
other Town facilities such as James B. Edwards, where newly installed
lights lacked adequate shielding. Sarah Mittermeier, Deputy Director of
Public Services, responded that LED lighting systems are engineered to
produce less light spillage than traditional systems, and that the new
installation should therefore represent an improvement for neighboring
communities. Council Member Tinkey requested that staff proactively
verify that shielding is adequate before installation is finalized, and Ms.
Mittermeier acknowledged the concern.
Motion to award the contract for electrical renovations to Joe Gawrych
Baseball Complex / Sloan Park to Camp Electric Company, Inc. in the
amount of $349,000.00 was made by Council Member Alex Crosby and
seconded by Council Member Mike Tinkey. The motion carried 3-0.
6. Award Of A Contract For Cured In Place Pipe Lining On Patty
Lane
Ms. Harness presented this item, noting that the Bids and Purchases
Committee had previously approved on-call agreements with contractors
for stormwater repair and rehabilitation services. This project involves
lining 500 linear feet of 48-inch concrete pipe in the I’on neighborhood
on Patty Lane, where multiple joint failures have been documented and
have begun to cause surface issues with the roadway. All work is
required to be completed by January 31, 2027.
Staff identified James White Construction LLC as the appropriate
contractor utilizing established unit pricing under their on-call agreement
with the Town.
Council Member Tinkey inquired about community notification and
anticipated traffic disruption. Frankie Pettit, Asset Manager for Public
Services, confirmed that the Town has existing contacts with the
homeowner’s association and will communicate proactively with
residents prior to mobilization. He noted that cured-in-place pipe lining is
significantly less disruptive than full pipe replacement, as it involves
shooting a liner from one end of the pipe to the other without excavation.
Council Member Brownstein asked for clarification on the lining process,
and Mr. Pettit confirmed that once the liner is in place, flow performance
would improve. Mr. Pettit also indicated that projects of this nature, when
they proceed smoothly, can typically be completed in approximately two
weeks.
Motion to award the contract for cured in place pipe lining on Patty Lane
to James White Construction, LLC in the amount of $293,380.05 was
made by Council Member Alex Crosby and seconded by Council Member
Mike Tinkey. The motion carried 3-0.
7. Award Of A Contract For Cured In Place Pipe Lining On 940
Casseque Province
Ms. Harness presented this item, which also falls under the Town's
previously established on-call stormwater repair and rehabilitation
agreements. The project involves lining 480 linear feet of 18-inch metal
pipe at 940 Casseque Province in the Snee Farm neighborhood, where
one segment of pipe has experienced a collapse near the roadway. All
work must be completed by January 31, 2027.
Staff identified James White Construction, LLC as the appropriate
contractor utilizing established unit pricing under their on-call agreement
with the Town.
Council Member Tinkey asked about the anticipated start date and
project duration for this project and requested that Mr. Pettit address the
same questions about the Patty Lane project discussed under the
previous agenda item. Mr. Pettit indicated that both projects are
expected to commence in late fall or early winter, and that each project,
if it proceeds without complications, would take approximately two
weeks to complete.
Motion to approve the contract for cured in place pipe lining on 940
Casseque Province to James White Construction, LLC in the amount of
$106,049.21 was made by Council Member Alex Crosby and seconded
by Council Member Mike Tinkey. The motion carried 3-0.
8. Adjourn
There being no further business before the committee, Council Member
Brownstein adjourned the Bids and Purchases Committee meeting at
8:14 AM.
Respectfully submitted by,
Katie Wagner
August 31, 2026
Source: Town of Mount Pleasant website. First collected Oct 13, 2026.