Call to Order and Determine Quorum
The Architectural Review Board meeting was called to order on June 3, 2026, at approximately 5:57
p.m. A quorum was established with four members present; Jason King, Gerald Meetze, and new
members Kevin Nickens and Phil Kumpf. Dan Powell was absent.
Statement of Freedom of Information Act Compliance
The meeting was held in compliance with the South Carolina Freedom of Information Act. Proper
notice was provided, and the agenda was made available to the public and was not amended within 24
hours of the meeting.
Public Comments related to agenda items
There were no public comments.
Approval of Minutes
October 2025 and May 2026 minutes were approved as submitted.
Elections
The Board held its annual election of officers. Jason was nominated and elected Chair, and Gerald was
nominated and elected Vice Chair. Both votes passed without opposition.
Board Terms
The Board briefly discussed member terms and noted that staff would resend the term information to
members for reference.
Lake Murray Tire
The Board reviewed the final architectural application for Lake Murray Tire, including a proposed 35-
by-50-foot rear addition related to the Columbia Avenue widening project. Staff noted the addition
would remain within setbacks, match the existing building color and metal material, and be minimally
visible from the roadway. Following discussion, a motion was made and seconded to approve the plans
as submitted. The motion passed without opposition.
306 Lexington Avenue
Solar Panels: The Board reviewed a request to revise the previously approved plans for 306 Lexington
Avenue to allow rooftop solar panels. Staff noted that the ordinance requires solar panels to be located
on roof slopes not visible from public rights-of-way and that the request required ARB approval. The
Board discussed visibility from Lexington Avenue, Clark Street, and Waters Street, as well as possible
impacts on future approvals. Following discussion, a motion was made and seconded to deny the
request based on visibility concerns and ordinance requirements. The motion passed without
opposition.
Staff Updates
Cola Rosa: Staff provided an update on the Cola Rosa project, noting that due to roadway changes,
DOT will include the Lexington Avenue sidewalk in its plans rather than requiring Cola Rosa to construct
it. Staff stated that Cola Rosa will revise its plans to reflect adjustments to the driveway entrance
related to the road expansion, and that the updated design will be provided once available.
Training Requirements: Staff reviewed ARB training requirements, noting that members are required
to complete three hours of training through the Municipal Association of South Carolina and may
complete additional hours if desired. Members were asked to submit certificates of completion for the
Town’s records.
Upcoming Projects: Staff noted that several confidential projects are in the early stages and have not
yet reached preliminary review. Staff also reported that a meeting with Hudson Ford is scheduled to
discuss revisions to its proposed redesign following prior ARB comments. The Board discussed the
project’s size, location in the interstate district, proposed siding materials, and the potential need to
consider future ordinance amendments regarding metal wall panels and approved exterior materials.
Next Meeting: The Board discussed the July 1 meeting date and noted that the meeting may be held if
pending projects or revised plans are ready for review; otherwise, cancellation may be considered.