Roads and Bridges Ad Hoc Committee Meeting — Agenda Packet
Pickens County · Pickens County · Pickens County Council · meeting of Feb 9, 2026 · Agenda packets
Open the original document More from Pickens County
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
222 MCDANIEL AVENUE, B-1 ∙ PICKENS, SC 29671 ∙ 864.898.5856 ∙ WWW.CO.PICKENS.SC.US
COUNCIL MEMBERS
ALEX SAITTA, CHAIRMAN
CHRIS LOLLIS, VICE CHAIRMAN
DALE HOLLOWAY, VICE CHAIR PRO-TEM
C. CLAIBORNE LINVILL
SCOTT LANG
CHRIS BOWERS
COUNTY ADMINISTRATOR
KEN ROPER
CLERK TO COUNCIL
MEAGAN NATIONS
PICKENS COUNTY COUNCIL ROADS AND BRIDGES AD-HOC
COMMITTEE MEETING
MONDAY, FEBRUARY 9, 2026
3:30 PM
CONFERENCE ROOM, ROADS AND BRIDGES BUILDING
186-A COUNTY FARM ROAD, PICKENS, SC 29671
THIS MEETING IS BEING HELD TO CONFORM WITH THE SOUTH CAROLINA FREEDOM OF INFORMATION ACT AND COUNCIL'S ORGANIZATIONAL RULES. THE
PUBLIC HAS BEEN NOTIFIED OF THE DATE, TIME AND PLACE OF THE MEETING. PUBLIC NOTICE AND THE AGENDA WAS PLACED ON THE COUNTY WEBSITE
AND THE BULLETIN BOARD AT THE COUNTY ADMINISTRATION BUILDING AT LEAST 24 HOURS PRIOR TO THE START OF THE MEETING.
1. WELCOME AND CALL TO ORDER:
INVOCATION:
PLEDGE OF ALLEGIANCE:
Chairman Alex Saitta
Vice Chairman Chris Lollis
Vice Chairman Chris Lollis
2. ROADS AND BRIDGES AD-HOC MEETING ITEMS:
a) SELECTION OF CHAIRMAN
b) ROAD FUNDING AND PAVING PRIORITIES
c) OVERVIEW ON OPERATIONS AND CAPITAL BUDGET
3. ADJOURN
Page 1 of 4
Road Funding:
What is the millage rate and how much revenue will it generate for 2026-27?
The millage rate for the Road Maintenance Fund is 5.0 mils and will generate $4,445,645 for FY
2027. This does not include growth from this past year. We expect to have these numbers by the
end of the month.
CFund money expected for 2026-27?
For a normal fiscal year, we collect about $200,000 on average per month for a total of
$2,400,000. During the year the State will sometimes have additional funding and they will pass it
along to Counties based on population of each county.
Out of that $2.4M that PCTC receives each year, as of July 2023, $750K goes towards SC 183 each
year as part of Pickens County’s match for a 20-yr commitment. This is considered as the portion
of allotment that has to go towards State roads. If we receive additional funding throughout the
year, 25% of said additional funding has to go towards State roads. Also, out of the $2.4M, PCTC
reserves $350K for future unknown projects / change orders. Due to the SC 183 commitment and
the reserved $350K, the County portion typically ends up being about $1.3M. Also, this $1.3M is
only if other municipalities don’t show up to request funding for road projects.
Any other sources of road revenue?
No other sources of revenue for roads.
What are the current balances of these accounts: 1) Road fee balance, 2) Road maintenance balance, 3)
Road reserve balance. How much is roads payable — the amount we committed to but have not yet paid.
February 05th 2026
Road Fee Fund – Approximately $100,000 which is earmarked for the completion of the Rocky Bottom
Road Culvert.
Road Maintenance Fund - $7,953,756
committed but have not paid yet $1,059,174
Road Reserve Fund - $6,962,325
committed but have not paid yet $3,172,817
Page 2 of 4
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(PCTC Funds) Available Funds
MILE CREEK RD 4.13 67.526 SIX MILE & PICKENS Preservation (Major) - PATCHING (6") & OVERLAY (2") $1,353,419.28 2026 $1,300,000.00
TOTAL: 4.13 $1,353,419.28 $1,300,000.00
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(Road
Maintenance)
Available Funds
FERGUSON RD 1.01 31.500 PICKENS Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $368,770.42 2026
JIM HUNT RD 1.26 54.600 EASLEY Rehabilitation (Minor) - MILL - RESURFACE (2"-4") $593,423.99 2026
GRIFFIN RD 1.05 38.500 EASLEY Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $383,375.19 2026
BREAZEALE RD 1.02 58.444 LIBERTY Preservation (Major) - PATCHING (6") & OVERLAY (2") $427,335.22 2026
FISH CAMP RD 0.65 70.400 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $262,456.13 2026
ROANOKE RD 1.98 74.714 LIBERTY Preservation (Major) - PATCHING (6") & OVERLAY (2") $799,481.76 2026
Culvert Replacement Projects $400,000.00 2026
TOTAL: 6.97 $3,234,842.71 $3,408,169.86
TOTAL FOR 2026 11.10 INCLUSIVE OF $400K FOR CULVERT PROJECTS, NO ROAD RESERVE FUNDS $4,588,261.99 2026 $4,708,169.86
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(PCTC Funds) Available Funds
DALTON RD 1.12 59.000 MARIETTA Rehabilitation (Minor) - PATCHING (6") & OVERLAY (2") $527,487.99 2027
MONTAGUE DR 0.76 44.000 EASLEY Rehabilitation (Minor) - PATCHING (6") & OVERLAY (2") $477,148.49 2027
LAKEVIEW DR 0.98 54.167 PICKENS Preservation (Major) - PATCHING (6") & OVERLAY (2") $321,150.34 2027
TOTAL: 2.86 $1,325,786.82 $1,300,000.00
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(Road
Maintenance)
Available Funds
FARMERS HILL RD 0.87 29.333 LIBERTY Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $317,653.73 2027
HIGHLAND RD 1.19 57.083 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $560,455.99 2027
GIBSON RD 1.42 62.000 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $573,365.71 2027
HILLCREST DR 0.46 38.000 PICKENS Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $167,954.84
DAN ROSS RD 1.61 54.600 EASLEY Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $674,519.32 2027
CAMP CREEK RD 1.63 79.000 CENTRAL Preservation (Major) - PATCHING (6") & OVERLAY (2") $658,159.23 2027
Culvert Replacement Projects $400,000.00 2027
TOTAL: 7.18 $3,352,108.82 $3,476,333.26
TOTAL FOR 2027 10.04 INCLUSIVE OF $400K FOR CULVERT PROJECTS, NO ROAD RESERVE FUNDS $4,677,895.64 2027 $4,776,333.26
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(PCTC Funds) Available Funds
$3,408,169.86
$1,300,000.00
$3,476,333.26
"BALANCED APPROACH" PAVING PRESERVATION PROGRAM - FY 2026 - FY 2029
Page 3 of 4
HOYT ANDERSON RD 0.91 57.000 PICKENS Rehabilitation (Minor) - MILL - RESURFACE (2"-4") $400,312.55 2028
ADAMS RD 1.03 68.333 PICKENS Preservation (Major) - PATCHING (6") & OVERLAY (2") $415,892.03 2028
STEPHENS RD 0.92 66.000 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $408,624.01 2028
TOTAL: 2.86 $1,224,828.59 $1,300,000.00
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(Road
Maintenance)
Available Funds
MOUNTAIN VIEW CHURCH RD 1.16 72.333 SIX MILE & PICKENS Preservation (Major) - PATCHING (6") & OVERLAY (2") $468,383.26 2028
FLEETWOOD CT 0.09 45.000 LIBERTY Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $30,748.37 2028
BRIDWELL CT 0.13 13.000 SIX MILE Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $47,465.50 2028
FLEETWOOD DR 0.24 34.000 LIBERTY Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $87,628.61 2028
LONG CREEK DR 0.38 35.000 EASLEY Rehabilitation (Major)/Reconstruction - FULL-DEPTH RECLAMATION (FDR) $138,745.31 2028
PINE GROVE CHURCH RD 4.46 69.444 SUNSET Preservation (Major) - PATCHING (6") & OVERLAY (2") $1,800,852.86 2028
CREST DR 0.74 88.286 EASLEY Preservation (Minor) - PATCHING (6") & OVERLAY (2") $297,584.21 2028
Culvert Replacement Projects $400,000.00 2028
TOTAL: 7.20 $3,271,408.12 $3,545,859.92
TOTAL FOR 2028 10.06 INCLUSIVE OF $400K FOR CULVERT PROJECTS, NO ROAD RESERVE FUNDS $4,496,236.70 2028 $4,845,859.92
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(PCTC Funds) Available Funds
CROSS ROADS CHURCH RD 0.88 73.667 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $355,325.23 2029
HERITAGE RD 1.42 64.000 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $573,365.71 2029
QUAIL HAVEN DR 0.88 73.625 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $355,325.23 2029
TOTAL: 3.18 $1,284,016.16 $1,300,000.00
Street Name
Sum of
Length
(mi)
Average of
PCI Communel Treatment Type Estimated Repair
Cost
Repair Year
(Road
Maintenance)
Available Funds
WINDHAM LN 0.82 65.400 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $331,098.51 2029
OLD SALUDA DAM RD 1.54 62.571 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $621,819.15 2029
MOSSIE SMITH RD 1.10 71.750 EASLEY Preservation (Major) - PATCHING (6") & OVERLAY (2") $444,156.53 2029
BRANDY LN 1.55 72.500 PICKENS Preservation (Major) - PATCHING (6") & OVERLAY (2") $625,856.94 2029
GILLESPIE RD 1.03 77.000 LIBERTY Preservation (Major) - PATCHING (6") & OVERLAY (2") $415,892.03 2029
WINDY HILL RD 1.73 70.000 CENTRAL Preservation (Major) - PATCHING (6") & OVERLAY (2") $698,537.10 2029
Culvert Replacement Projects $400,000.00
TOTAL: 7.77 $3,537,360.25 $3,616,777.12
TOTAL FOR 2029 10.95 INCLUSIVE OF $400K FOR CULVERT PROJECTS $4,821,376.41 2029 $4,916,777.12
TOTAL FY 2026 - FY 2029 COUNTY PROGRAM 42.15 INCLUSIVE OF FUNDS FOR CULVERT PROJECTS $18,583,770.75 $19,247,140.16
$3,545,859.92
$1,300,000.00
$3,616,777.12
$1,300,000.00
Page 4 of 4
Source: Pickens County website. First collected Oct 15, 2026.