Planning Commission Meeting Packet Updated (PDF)
Town of Summerville · Berkeley County · meeting of Apr 20, 2026 · Agenda packets
Open the original document More from Town of Summerville
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
Town of Summerville
Planning Commission
April 20, 2026 - 4:00 PM
Town Hall, Council Chambers
The meeting will be live-streamed through the live-streaming link on the Town’s website: www.summervillesc.gov
For additional information regarding items on this agenda including any public hearings, please contact the Planning
Department at planning@summervillesc.gov or 843.851.4217. Applications and related documents for this meeting are
available for review at any time at www.summervillesc.gov/AgendaCenter.
I. APPROVAL OF MINUTES:
1. Approval of minutes from meeting on March 16, 2026
II. PUBLIC HEARINGS: (public hearing notice in Summerville Journal Scene on 3.18.26 and 4.1.26 and signs
posted on the property on 4.3.26)
1. Consideration of an updated Development Impact Fee Study and Capital Improvements Plan (CIP) and
revised Impact Fee Ordinance.
2. Request to rezone TMS# 154-06-02-001, located along Beverly Drive and totaling approximately 1.24 acres,
and owned by James Jamal Simpson from GR-5, General Residential (5 units/acre), to N-R, Neighborhood
Residential (Council District 6)
3. Request to rezone TMS#137-09-01-011, located at 727 Central Avenue, totaling approximately 0.23 acres,
and owned by Trilogy Properties of Summerville, LLC, from GR-5, General Residential (5 units/acre), to N-
B, Neighborhood Business (Council District 1)
4. Request to rezone TMS#137-07-16-001, located at 103 S. Magnolia Street, totaling approximately 0.34 acres,
and owned by David L. & Kimberly D. Garber, from GR-2 (2 units/acre), to N-MX, Neighborhood Mixed-
Use (Council District 2)
5. Petition by Glenn Segelken to annex Dorchester County TMS#137-00-00-003, approximately 62.27 acres,
located along Parsons Road.
Request to zone Dorchester County TMS#137-00-00-003, which is currently zoned TRM, Transitional
Residential District, in Dorchester County, as PUD, Planned Development District, upon annexation into the
Town of Summerville’s municipal limits. (Council District 1)
6. Request to rezone TMS#137-00-00-007, located at 710 Central Avenue, totaling approximately 10.31 acres,
and owned by Glenn Segelken, from AC, Agricultural Conservation, to PUD, Planned Development District
(Council District 1)
7. Petition by The Commissioners of Public Works of the Town of Summerville to annex Dorchester County
TMS#144-00-00-189, approximately 2.08 acres, located along the Berlin G. Myers Parkway.
Request to zoned Dorchester County TMS#144-00-00-189, which is currently zoned Other in Dorchester
County, as PL, Public Lands, upon annexation into the Town of Summerville’s municipal limits. (Council
District 5)
III. OLD BUSINESS:
IV. NEW BUSINESS:
1. New Street Names (as needed)
a. Droze Road Townhomes: Grace Hill Terrace, Valmere Grove Circle, and Corvella Park Circle
2. Consideration of an updated Development Impact Fee Study and Capital Improvements Plan (CIP) and
revised Impact Fee Ordinance.
3. Request to rezone TMS# 154-06-02-001, located along Beverly Drive and totaling approximately 1.24 acres,
and owned by James Jamal Simpson from GR-5, General Residential (5 units/acre), to N-R, Neighborhood
Residential (Council District 6)
4. Request to rezone TMS#137-09-01-011, located at 727 Central Avenue, totaling approximately 0.23 acres,
and owned by Trilogy Properties of Summerville, LLC, from GR-5, General Residential (5 units/acre), to N-
B, Neighborhood Business (Council District 1)
5. Request to rezone TMS#137-07-16-001, located at 103 S. Magnolia Street, totaling approximately 0.34 acres,
and owned by David L. & Kimberly D. Garber, from GR-2 (2 units/acre), to N-MX, Neighborhood Mixed-
Use (Council District 2)
6. Petition by Glenn Segelken to annex Dorchester County TMS#137-00-00-003, approximately 62.27 acres,
located along Parsons Road.
Request to zone Dorchester County TMS#137-00-00-003, which is currently zoned TRM, Transitional
Residential District, in Dorchester County, as PUD, Planned Development District, upon annexation into the
Town of Summerville’s municipal limits. (Council District 1)
7. Request to rezone TMS#137-00-00-007, located at 710 Central Avenue, totaling approximately 10.31 acres,
and owned by Glenn Segelken, from AC, Agricultural Conservation, to PUD, Planned Development District
(Council District 1)
8. Petition by The Commissioners of Public Works of the Town of Summerville to annex Dorchester County
TMS#144-00-00-189, approximately 2.08 acres, located along the Berlin G. Myers Parkway.
Request to zoned Dorchester County TMS#144-00-00-189, which is currently zoned Other in Dorchester
County, as PL, Public Lands, upon annexation into the Town of Summerville’s municipal limits. (Council
District 5)
V. MISCELLANEOUS:
1. Discussion about potential UDO amendments to address religious institutions
VI. ADJOURNMENT:
Posted April 14, 2026
DRAFT
The Town of Summerville Planning Commission Meeting
Minutes
March 16, 2026
This meeting of the Town of Summerville Planning Commission was held in Town Council Chambers and was
attended by Commission Members, Jim Reaves, Chairman; Kevin Carroll; Hart Weatherford; Shelley Macaluso;
Jill Weatherford; Trae McElheny; and Elaine Segelken. Staff in attendance included Jessi Shuler, AICP, Director
of Planning. The public was invited to attend in person, or they viewed the meeting via live-stream.
Jim Reaves, Chairman, called the meeting to order at 4:00 PM.
Oath of Office and Approval of Minutes:
Town Clerk Beth Messervy led Planning Commissioners Jill Weatherford and Trae McElheny in the Oath of
Office. The Chairman then asked if there were any edits or additions to the minutes from the meeting on February
23, 2026. Hearing none, the minutes were accepted as presented.
Public Hearings:
The first public hearing opened at 4:02 PM and was for the petition by Ambassadors of 1857 to annex TMS#
144-00-00-082, located at Luden Drive and King Charles Circle, and totaling approximately 4.26 acres.
Currently zoned TRM, Transitional Residential District, in Dorchester County and requested to be zoned MF-R,
Multi-family Residential, following annexation into the Town of Summerville’s municipal limits. (Council
District 5) Mr. Reaves introduced the item and asked if the applicant would like to present the request. Bill
Helmley stated that he is one of the founding members of Summerville Methodist Church, and he explained that
the Ambassadors of 1857 are doing business as Summerville Methodist Church. He noted he understands the
concerns about the MF-R zoning request for the annexation, and he provided two documents that he believes
distinguish the church’s zoning request from that of the apartment developer: their articles of incorporation,
which state that upon dissolution of the corporation, assets shall be distributed for one or more exempt purposes
within the median section 501 of the Internal Revenue Code, and Article 9 from their church constitution, which
states that in the event of the dissolution of the church, all assets and liabilities shall be distributed to one or
more organizations that are in agreement with the Church’s normative standards of Christian belief, the
normative standards of Wesleyan teaching, and are tax exempt under Section 501 of the Internal Revenue Code.
He emphasized that he does not believe that the church will fail, as their first service included about 150 people,
and now they have over 500 people attending in their temporary home. Mr. Helmley added that the church is
also financially sound. Ross Chellis, the Pastor of Summerville Methodist Church, explained that in discussions
with the neighborhood, the church has heard their concerns and wants to find a way of balance what is fair to
everyone. He stressed that the church intends to build their facilities on the property.
The following additional public comment was provided:
Thom Nolan of 106 King Charles Circle stated that he thinks it’s great that the church wants to build on the
property, but he asked if there was a way that the town could zone it institutional, as opposed to multifamily.
He does not oppose the church, but he just wants to ensure that what was already turned down under previous
ownership is not something that is going to be approved on the property in the future.
Frank Freeman of 108 King Charles Circle noted that he echoed Mr. Nolan’s comments.
Larry Collett of 311 Kenilworth Road stated that he is the president of the Newington Plantation Estates HOA
and is representing 549 homeowners. We wanted to welcome Summerville Methodist Church and respects and
supports their intended use of the property to build their sanctuary. He stressed that the neighborhood’s concern
is not with Summerville Methodist Church, as they really want them there, but with the outlier risk of the MF-R
DRAFT
zoning should the church not build. He explained that the neighborhood’s first and primary desire is for the
property to be granted a different, more appropriate residential zoning designation that matches the character of
the area, while still allowing the church to build. If MF-R must be granted, they would request a restrictive
covenant on the deed, which may be accomplished with the document that was already read, but they would
need a closer look. As an alternative to the restrictive covenant, the church offered the HOA first right of
refusal should they ever decide to sell the land in the future, but that was just brought up yesterday and needs to
be considered further.
Mark Bacher of 110 Hulton Lane noted that this exact same request was rejected unanimously by the Planning
Commission and later Town Council. Why is the request different with a local church as owner? He stated that
he does not oppose the church on that property, but he does have concerns that multifamily zoning is not needed
to build the church. The church says they intend to be there for 100 years, but they have refused deed
restrictions and said that zoning both properties to residential would be a bad business decision, so he does not
trust the church. He expressed concern that if the church’s plans change down the road, the property could
easily be flipped back to an apartment builder at a huge profit. The HOA won’t be able to afford first right of
refusal, and the documents previously read only address what would happen if the church were to dissolve. He
asked the Commission to please deny the request.
Gene Brislin of 209 King Charles Circle provided some history on the two properties that the church now owns,
including the larger piece that is already in Town and zoned MF-R. He noted that he did a survey of 22
churches in the Town and the average size campus is three acres, so it is curious that the front piece up for
annexation has become so important, as he has heard that the back piece has seven acres of highland. He
stressed that the risk of the church intentionally doing something is low, as he believes their intentions, but he is
worried about the unintentional consequences that you never know about. He emphasized that there is no
recourse for the neighborhood if the property is zoned MF-R, so their fail-safe is for it to be GR-5, which you
can still build a church within.
Tom Flatt of 105 Plantation Drive stated that they have heard the church wants a zoning that they don’t need,
but they haven’t heard why they are requesting that zoning, and he believes it is because they want to build
something multifamily. He is opposed to that. He also mentioned that the traffic through the neighborhood on
Sundays with people racing through the neighborhood would be a problem side effect. He can accept that, but
he wants to know why they want the multifamily zoning.
Jennie Sheadon-Sharing of 529 King Charles Circle stated that she has been a land planner for many years, and
she noted that it has been the practice in planning that churches are not good neighbors anymore. They are just
a culmination of land uses from homeless shelters to assisted living to events and weddings. She noted that a
majority of land use codes are now requiring churches to be on collectors, not neighborhood streets. She does
not feel that the church has been very forthcoming or trustworthy, and with 550 members, she is also concerned
about the number of meetings the church would have in one month, and they are going to be looking for more
and more members.
Ms. Shuler read additional comments provided in writing into the record, and those comments will be appended
to these minutes as part of the public hearing. Hearing no further public comment, this public hearing was
closed at 4:36 PM.
The second public hearing opened at 4:36 PM and was for a proposed amendment to the Summerville Unified
Development Ordinance (UDO), Chapter 3, Section 3.3 – Table of Permitted Uses and Section 3.4.5(E)(1)(a) -
Tobacco/Tobacco Alternative/CBD/CBD Alternatives Sales Store. Mr. Reaves introduced the item and asked
Ms. Shuler to provide a brief explanation. Ms. Shuler stated that this request was sent to them from Council,
DRAFT
and it would further limit where these types of stores would be allowed within town limits. Hearing no public
comment, this public hearing was closed at 4:37 PM.
The third public hearing opened at 4:37 PM and was for a proposed amendment to the Summerville Unified
Development Ordinance (UDO), Chapter 10, Section 10.7.2 – Temporary Freestanding Signs Erected During
An Election Season and Section 10.8.3 – Temporary Yard Signs. Mr. Reaves introduced the item and asked
Ms. Shuler to provide a brief explanation. Ms. Shuler stated that this request was also sent by Council. With
the change in the state law allowing for early voting two weeks in advance of the election date for everyone,
this amendment would avoid confusion by making it clear that election signs would be allowed 30 days in
advance of early voting. Hearing no public comment, this public hearing was closed at 4:38 PM.
Old Business
There were no items under Old Business.
New Business:
The first item under New Business was New Street Names. Ms. Shuler stated that they did not have any street
names.
The second item under New Business was the petition by Ambassadors of 1857 to annex TMS# 144-00-00-082,
located at Luden Drive and King Charles Circle, and totaling approximately 4.26 acres. Currently zoned TRM,
Transitional Residential District, in Dorchester County and requested to be zoned MF-R, Multi-family
Residential, following annexation into the Town of Summerville’s municipal limits. (Council District 5) Ms.
Weatherford recused herself from this agenda item as she represented the church in acquisition of the property
and continues to serve on the church’s Property Steering Committee. Mr. McElheny made a motion to
recommend approval, and Ms. Segelken made the second. Mr. Carroll noted that the only zoning district that
does not allow for a church is Public Lands, so he is having a hard time understanding the need for the MF-R
zoning. He stated that he believes that all the churches in the Historic District are built in residentially zoned
areas, and he doesn’t understand why the existing property within the Town is zoned MF-R, as a majority of it
is wetlands. He added that if the zoning request is for MF-R, he will have to vote against the annexation,
although he would love to see the church in that location. He isn’t comfortable with the possibility of what
could happen if the church doesn’t build there, which he believes would be a detriment to the neighborhood.
Ms. Segelken asked staff if there were any alternatives to residential zoning that the church could request, and
Ms. Shuler responded that Mr. Carroll was correct about the zoning districts in which churches are a permitted
use, but the Town does not have any non-residential zoning districts that do not also allow multifamily housing,
as the Town does not have an institutional zoning district, other than PL, which does not allow churches. Pastor
Chellis asked if he could try to answer Mr. Carroll’s questions. The Chairman allowed him to respond, and
Pastor Chellis explained that they are trying to match the existing zoning of the property that is already in the
Town limits so that they can combine the two properties and begin the permitting process in the most efficient
manner without devaluing the existing banknote that the church has on the property. Mr. Reaves summarized
his understanding of the request for the MF-R zoning as a means to be able to abandon the property line
between the two properties, as the Town does not allow for multiple zonings on one property. Mr. Weatherford
asked about the zoning on the adjacent properties in the Town, and Ms. Shuler responded that the properties are
zoned GR-5 and PL, and MF-R is adjacent and across Luden Drive. Following the discussion, Mr. Reaves
called for the question and the motion to recommend approval failed on a 3-3 vote with Hart Weatherford,
Kevin Carroll, and Shelley Macaluso voting in opposition.
The third item under New Business was the proposed amendment to the Summerville Unified Development
Ordinance (UDO), Chapter 3, Section 3.3 – Table of Permitted Uses and Section 3.4.5(E)(1)(a) -
Tobacco/Tobacco Alternative/CBD/CBD Alternatives Sales Store. Ms. Segelken made a motion to recommend
approval, and Mr. Carroll made the second. Mr. Carroll asked if this would grandfather existing stores, and Ms.
DRAFT
Shuler confirmed that existing locations would be allowed to remain in operation and would be considered a
legal nonconforming use in the D-MX and UC-MX zoning districts. Mr. Reaves explained that this only
applied to stores that met the definition in the UDO, and Ms. Shuler agreed and explained that the definition
addressed the percentage of display space and percentage of sales. Following the discussion, the Chairman
called for the question, and the motion passed unanimously.
The fourth item under New Business was the proposed amendment to the Summerville Unified Development
Ordinance (UDO), Chapter 10, Section 10.7.2 – Temporary Freestanding Signs Erected During An Election
Season and Section 10.8.3 – Temporary Yard Signs. Ms. Segelken made a motion to recommend approval, and
Mr. Carroll made the second. Mr. Carroll asked for confirmation that this would extend the sign allowance into
early voting. Ms. Shuler explained that staff interprets the current ordinance to allow the signs 30 days prior to
early voting, as it is called an election event in the existing ordinance, but this amendment would remove any
need for interpretation. Following the discussion, the Chairman called for the question, and the motion passed
unanimously.
Miscellaneous:
There were no items under Miscellaneous.
Adjourn
With no further business for the Commission, Mr. Weatherford made a motion to adjourn with Ms. Segelken
making the second. The motion carried and the meeting was adjourned at 4:55 PM.
Respectfully Submitted,
Date: __________________________
Jessi Shuler, AICP
Director of Planning
Approved: _________________________________________________
Jim Reaves, Chairman or Hart Weatherford, Vice Chairman
1
Jessi Shuler
From: Randy Sadler <rsadler17@gmail.com>
Sent: Monday, March 16, 2026 2:21 PM
To: Jessi Shuler
Subject: Zoning Parcel as MFR in Newington Plantation
SUMMERVILLE PLANNING DEPARTMENT,
I am surprised and concerned that the Town’s Planning department is already considering
another request to zone the parcel of land across from the elementary schools at King Charles Circle as
Multi-Family Residential.
Recently the neighborhood as well as the Planning Commission and the Town Council all agreed
that this parcel is not suitable for MFR zoning. Many reasons were given and the Town voted
overwhelmingly that MFR was inappropriate. It would be hypocritical to change positions now.
Apparently, for financial reasons, the church’s developer wants to artificially inflate the value of
this property as an MFR-suitable parcel, and it is not. It is suitable only for residential zoning.
Thank you,
RANDY SADLER, Long-time Newington Resident
14 Plantation Circle
Summerville, SC 29485
Email:
rsadler17@gmail.com
Could you please provide my comment to the Town’s Planning Commission.
You don't often get email from rsadler17@gmail.com. Learn why this is important
Caution: This email originated from outside of the organization. Please take care when clicking links
or opening attachments.
1
Jessi Shuler
From: erynn estep <erynnestep@gmail.com>
Sent: Monday, March 16, 2026 2:37 PM
To: Jessi Shuler
Subject: Today's meeting
Greetings Director of Planning Shuler,
I appreciate you taking the time to read this email and at this point in the process you may have heard so
much about this situation that it may sound like static. I value your time and my ability to be part of it.
I am writing to encourage you to NOT change the zoning for the Summerville Methodist church at
Newington to Multi-family (MFR), by refusing the zoning change altogether or enforcing deed restrictions
in the event of a sale of the property from the church. I would appreciate you taking a moment to
encourage others, town council, Mayor Touchberry and zoning administrators to consider the following.
1. Why does the church need MFR zoning?
They can already do anything they need/want to do without that zoning change-Jessi Schuler
has told them that. This is a greedy move, FOR A CHURCH, to try and change this, even if their
reason is a business one to help them navigate forward, they don’t need MFR to navigate. You
as a council member, know this. It is strictly being done as a shady, back door move, everyone
can see that and it is really disgraceful for a church to do such devious things. The church
does not need multi-family zoning to do church things. Period.
2. Zoning change will pull a fast one on us all.
We all know how Newington feels about a potential pile of apartments going into that
space, you’ll recall this past fall when this all started, the massive turnout that took place.
We as a neighborhood were so grateful for all of you, that saw through the greedy
developers plans, saw that they were not willing to work with us. We were truly
appreciative that you sided with us, the community members that voted for you to have
your space in the council. We are asking you to please keep the zoning as it is now, so that
if the church changes their mind, something shifts course, they cannot collect a huge sum
of money by a developer swooping in and do what you and I both know isn’t wanted or what
is right for this parcel of land.
3. Business moves: Why would it matter if both pieces of property have the same zoning if both
pieces are now owned by the same church who can do whatever they want without
restrictions
because they are a church? They want it changed so they can sell it.
The church can build whatever they want right now, by changing the zoning the church can
sell, take the money and run, and apartments go up.
You don't often get email from erynnestep@gmail.com. Learn why this is important
Caution: This email originated from outside of the organization. Please take care when clicking links
or opening attachments.
2
4. Why is MFR zoning bad for this space ? We do not need more apartments- I don’t think that is the
point to make for this argument but nonetheless, if rezoned to MFR, that could happen.
The church folk are simply telling us to rely on faith and have a little faith in them, but what
happens when the zoning changes, and the church sells and this nightmare becomes true?
Shame on the church for using faith and God in such a manner to guilt us into trusting them
but potentially to line their own pockets and collect on their deceit and greed.
IF zoned MFR, the domino effect will begin, little by little more trees and wetlands
disappear, the character of Summerville is already fading with the unhinged growth and
out of control developments.
As a resident and teacher in Newington, the changes that have occurred in the last year are
already overwhelming. The traffic through the neighborhood is getting scary- constant cut
throughs, speeding and increased noise this just from the opening of the BGM parkway
(also affiliated with the church – boy, does that raise some eyebrows). By changing the
zoning and allowing the MFR, the increase of students in our already OVERVCROWDED,
maxed out schools will be almost unbearable. The attendance lines being redrawn from
Sand Hill and Beech Hill have put Newington Elementary OVER capacity, crowded our
classrooms, made chaos across the board for our school, additional families are moving in
everyday and our numbers are increasing at an alarming rate with no slowi ng down in sight.
Multi-family housing going in across from the TWO elementary schools will have dire
consequences in our school setting. Please do not make this property zoned for Multi-
family.
5. The church is unwilling to cooperate and work with Newington. Just like the developers last fall,
we as a neighborhood, were proactive in reaching out to them. We have tried the
same with Summerville Methodist church, the church will not bend or compromise (deed
restrictions is another option) to meet us about our concerns, which is the biggest red flag
about all of this. As a neighborhood, we love the idea of church going in that space. We do not
understand why the church is insistent on changing the zoning when they do not need to
change it to do what they want to do as a church.
6. Deny the change, less work for everyone. If the zoning changes to MFR, that means more work for
everyone, more meetings, more input, more explanations, more complications and convolutions
for everyone and every project moving forward. By leaving the zoning as is, the church still gets
what they want, Newington plantation gets what they want, and the town of Summerville and city
council doesn’t have to hear from any of us anymore about this property. Why say yes to a zoning
change when it’s so easy to say no?
Please, please see this situation for what it is…a sneaky opportunity to disguise deception and greed with
good will and faith.
Please do not change the zoning for the church to Multi-Family at Newington Plantation.
I thank you kindly for your time and efforts in this matter. I am confident that you will make the right
choice and do the right thing for the voting citizens of Newington plantation, for the families attending
Newington and Flowertown schools and for all members of the Summerville community, please do not
allow the multi-family zoning for Summerville Methodist church.
~Erynn Estep
IMPACT FEE STUDY & CIP
STAFF REPORT
PLANNING COMMISSION
April 20, 2026
Request: Consideration of an updated Development Impact Fee Study and Capital
Improvements Plan (CIP) and revised Impact Fee Ordinance.
In February 2025, Town Council approved a resolution directing the Planning Commission to conduct
a review of and make recommendations for an amended capital improvements plan and a revised
impact fee ordinance, in accordance with the South Carolina Development Impact Fee Act, SC Code
of Laws Section 6-1-910. The Town contracted with TischlerBise, Inc. to complete an updated impact
fee study and CIP and a revised impact fee ordinance. Town Staff worked closely with TischlerBise,
Inc. throughout the process. A representative from TischlerBise, Inc. will be available during the
Planning Commission meeting via Zoom to briefly explain the process used and the proposed new
impact fee schedule and ordinance.
i
Capital Improvement Plan and Development Impact Fee Study Prepared for: Town of Summerville, South Carolina April 15, 2026 Prepared by:
4701 Sangamore Road Suite S240 Bethesda, Maryland 20816 800.424.4318 www.tischlerbise.com
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
i
TischlerBise 4701 Sangamore Road Suite S240 Bethesda, Maryland 20816 800.424.4318 www.tischlerbise.com
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
ii
TABLE OF CONTENTS EXECUTIVE SUMMARY ......................................................................................................................... 1 SOUTH CAROLINA DEVELOPMENT IMPACT FEE ACT ............................................................................................ 1 CONCEPTUAL DEVELOPMENT IMPACT FEE CALCULATION ..................................................................................... 2 GENERAL METHODOLOGIES ............................................................................................................................ 2 Cost Recovery (Past Improvements) .................................................................................................................... 2 Incremental Expansion (Concurrent Improvements) ........................................................................................... 2 Plan-Based Fee (Future Improvements) .............................................................................................................. 3 Credits .................................................................................................................................................................. 3 PROPOSED FEE METHODS AND COST COMPONENTS ........................................................................................... 4 Figure 1: Proposed Fee Methods and Cost Components .................................................................................................... 4 PROPOSED DEVELOPMENT IMPACT FEE SCHEDULE ............................................................................................. 4 Figure 2: Maximum Supportable Development Impact Fees .............................................................................................. 5 Figure 3: Current Development Impact Fees ...................................................................................................................... 5 Figure 4: Difference between Current and Maximum Supportable Development Impact Fee .......................................... 6 PROJECTED DEMAND ..................................................................................................................................... 7 Figure 5: Town of Summerville Residential and Nonresidential Projections ...................................................................... 7 PARKS AND RECREATION DEVELOPMENT IMPACT FEE CALCULATIONS ................................................ 8 METHODOLOGY ............................................................................................................................................ 8 PARKS AND RECREATION BENEFIT AREA ............................................................................................................ 8 PARKS AND RECREATION FUNDING SOURCES ..................................................................................................... 8 SERVICE UNITS FOR PARK AND RECREATION ANALYSIS ......................................................................................... 9 Figure PR1: Residential Service Units .................................................................................................................................. 9 PARKS AND RECREATION LEVEL OF SERVICE AND COST ANALYSIS ........................................................................... 9 Park Land – Incremental Expansion ..................................................................................................................... 9 Figure PR2: Park Land Level of Service and Cost Allocation .............................................................................................. 10 Park Improvements – Incremental Expansion ................................................................................................... 11 Figure PR3: Park Improvement Level of Service and Cost Allocation ............................................................................... 11 Park Facilities – Incremental Expansion ............................................................................................................. 12 Figure PR4: Park Facilities Level of Service and Cost Allocation ....................................................................................... 12 Trails – Incremental Expansion .......................................................................................................................... 13 Figure PR5: Trails Level of Service and Cost Allocation ..................................................................................................... 13 Park Vehicles – Incremental Expansion ............................................................................................................. 14 Figure PR6: Park Vehicles Level of Service and Cost Allocation ........................................................................................ 14 PROJECTION OF PARKS AND RECREATION GROWTH-RELATED FACILITY NEEDS ....................................................... 15 Park Land ............................................................................................................................................................ 15 Figure PR7: Projected Demand for Park Land ................................................................................................................... 15 Park Improvements ............................................................................................................................................ 16 Figure PR8: Projected Demand for Park Improvements ................................................................................................... 16 Park Facilities ..................................................................................................................................................... 17
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
iii
Figure PR9: Projected Demand for Park Facilities ............................................................................................................. 17 Trails ................................................................................................................................................................... 18 Figure PR10: Projected Demand for Trails ........................................................................................................................ 18 Park Vehicles ...................................................................................................................................................... 19 Figure PR11: Projected Demand for Park Vehicles ........................................................................................................... 19 CREDITS .................................................................................................................................................... 19 MAXIMUM SUPPORTABLE PARKS AND RECREATION DEVELOPMENT IMPACT FEE ................................................... 19 Figure PR12: Maximum Supportable Parks and Recreation Development Impact Fee .................................................... 20 PROJECTED REVENUE FROM PARKS AND RECREATION DEVELOPMENT IMPACT FEE ................................................. 21 Figure PR13: Projected Revenue from the Parks and Recreation Development Impact Fee ............................................ 21 PUBLIC SAFETY DEVELOPMENT IMPACT FEE CALCULATIONS .............................................................. 22 METHODOLOGY .......................................................................................................................................... 22 PUBLIC SAFETY BENEFIT AREA ....................................................................................................................... 22 PUBLIC SAFETY FUNDING SOURCES ................................................................................................................ 22 SERVICE UNITS FOR PUBLIC SAFETY ................................................................................................................ 23 Figure P1: Residential Service Units .................................................................................................................................. 23 Figure P2: Nonresidential Service Units ............................................................................................................................ 24 PUBLIC SAFETY PROPORTIONATE SHARE FACTORS ............................................................................................ 24 Figure P3: Proportionate Share Factors ............................................................................................................................ 25 PUBLIC SAFETY SPACE LEVEL OF SERVICE AND COST ANALYSIS ............................................................................ 25 Public Safety Space – Plan-Based ....................................................................................................................... 25 Figure P4: Public Safety Space Planned Level of Service in 2040 ...................................................................................... 26 Figure P5: Public Safety Space Cost Allocation ................................................................................................................. 27 PUBLIC SAFETY PRINCIPAL PAYMENT CREDIT ................................................................................................... 28 Figure P5: Public Safety Principal Payment Credit ............................................................................................................ 28 MAXIMUM SUPPORTABLE PUBLIC SAFETY DEVELOPMENT IMPACT FEE ................................................................. 29 Figure P6: Maximum Supportable Public Safety Development Impact Fee ...................................................................... 29 PROJECTED REVENUE FROM PUBLIC SAFETY DEVELOPMENT IMPACT FEE .............................................................. 30 Figure P7: Projected Revenue from the Public Safety Development Impact Fee ............................................................. 30 FIRE DEVELOPMENT IMPACT FEE CALCULATIONS ............................................................................... 31 METHODOLOGY .......................................................................................................................................... 31 FIRE BENEFIT AREA ..................................................................................................................................... 31 FIRE FUNDING SOURCES ............................................................................................................................... 31 SERVICE UNITS FOR FIRE .............................................................................................................................. 32 Figure F1: Residential Service Units .................................................................................................................................. 32 Figure F2: Nonresidential Service Units ............................................................................................................................ 33 FIRE PROPORTIONATE SHARE FACTORS ........................................................................................................... 33 Figure F3: Proportionate Share Factors ............................................................................................................................ 34 FIRE FACILITIES LEVEL OF SERVICE AND COST ANALYSIS ...................................................................................... 34 Fire Station – Incremental Expansion ................................................................................................................ 34 Figure F4: Fire Station Level of Service and Cost Allocation Existing Level of Service ...................................................... 35
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
iv
Fire Apparatus – Incremental Expansion ........................................................................................................... 35 Figure F5: Fire Apparatus Level of Service and Cost Allocation Existing Level of Service ................................................. 36 PROJECTION OF FIRE GROWTH-RELATED INFRASTRUCTURE NEEDS ...................................................................... 37 Fire Station Space .............................................................................................................................................. 37 Figure F6: Projected Demand for Fire Stations ................................................................................................................. 37 Fire Apparatus .................................................................................................................................................... 38 Figure F7: Projected Demand for Fire Apparatus .............................................................................................................. 38 FIRE DEBT CREDIT ....................................................................................................................................... 39 Figure F8: Fire Debt Credit ................................................................................................................................................ 39 MAXIMUM SUPPORTABLE FIRE DEVELOPMENT IMPACT FEE ............................................................................... 40 Figure F9: Maximum Supportable Fire Development Impact Fee .................................................................................... 40 PROJECTED REVENUE FROM FIRE DEVELOPMENT IMPACT FEE ............................................................................ 41 Figure F10: Projected Revenue from the Fire Development Impact Fee .......................................................................... 41 CAPITAL IMPROVEMENT PLAN ........................................................................................................... 42 Figure CIP1: Parks and Recreation Capital Improvement Plan ......................................................................................... 42 Figure CIP2: Public Safety Capital Improvement Plan ....................................................................................................... 43 Figure CIP3: Fire Capital Improvement Plan ..................................................................................................................... 43 IMPLEMENTATION AND ADMINISTRATION ........................................................................................ 44 CREDITS AND REIMBURSEMENTS ................................................................................................................... 44 SERVICE AREA ............................................................................................................................................ 44 APPENDIX A: HOUSING AFFORDABILITY ANALYSIS ............................................................................. 45 Maximum Supportable Development Impact Fee ............................................................................................. 45 Figure A1. Maximum Supportable Development Impact Fee ........................................................................................... 45 Impact on Monthly Mortgage ............................................................................................................................ 45 Figure A2. Monthly Payment Sensitivity Analysis for a Single Family Unit ....................................................................... 45 APPENDIX B: LAND USE ASSUMPTIONS .............................................................................................. 47 SUMMARY OF GROWTH INDICATORS .............................................................................................................. 47 RESIDENTIAL DEVELOPMENT ......................................................................................................................... 48 Housing Unit Size ............................................................................................................................................... 48 Figure B1: Persons per Housing Unit ................................................................................................................................. 48 Residential Estimates ......................................................................................................................................... 49 Figure B2: Residential Estimates ....................................................................................................................................... 49 Residential Projections ....................................................................................................................................... 49 Figure B3: Residential Projections ..................................................................................................................................... 49 NONRESIDENTIAL DEVELOPMENT .................................................................................................................. 50 Nonresidential Demand Units ............................................................................................................................ 50 Figure B4: Nonresidential Demand Units .......................................................................................................................... 50 Nonresidential Estimates ................................................................................................................................... 51 Figure B5: Nonresidential Estimates ................................................................................................................................. 51 Nonresidential Projections ................................................................................................................................. 51
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
v
Figure B6: Nonresidential Projections ............................................................................................................................... 51 AVERAGE WEEKDAY VEHICLE TRIPS ................................................................................................................ 52 Nonresidential Demand Units ............................................................................................................................ 52 Figure B7: Nonresidential Demand Units .......................................................................................................................... 52 Trip Rate Adjustments ....................................................................................................................................... 53 Adjustment for Pass-By Trips ............................................................................................................................. 53 Average Weekday Vehicle Trips ......................................................................................................................... 53 Figure B8: Average Weekday Vehicle Trips (AWVT) by Development Type ..................................................................... 53 Figure B9: Nonresidential Vehicle Trips ............................................................................................................................ 53 DEVELOPMENT PROJECTIONS ........................................................................................................................ 54 Figure B10: Development Projections .............................................................................................................................. 54 Figure B11: Nonresidential Vehicle Trip Projections ......................................................................................................... 54 APPENDIX C: LAND USE DEFINITIONS ................................................................................................. 55 RESIDENTIAL DEVELOPMENT ......................................................................................................................... 55 NONRESIDENTIAL DEVELOPMENT .................................................................................................................. 56
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
1
EXECUTIVE SUMMARY The Town of Summerville, South Carolina retained TischlerBise to prepare a Capital Improvement Plan and Development Impact Fee Study. Development impact fees are collected from new construction at the time a building permit is issued and are one-time payments for new development’s proportionate share of the capital cost of infrastructure. The following study addresses the Town of Summerville’s Parks and Recreation facilities, Public Safety facilities, and Fire facilities. Development impact fees do have limitations and should not be regarded as the total solution for infrastructure funding. Rather, they are one component of a comprehensive funding strategy to ensure provision of adequate public facilities. Development impact fees may only be used for capital improvements or debt service for growth-related infrastructure. Under the South Carolina Development Impact Fee Act, fees may not be used for operations, maintenance, replacement of infrastructure, or correcting existing deficiencies. South Carolina Development Impact Fee Act The State of South Carolina grants the power for cities and counties to collect development impact fees on new development pursuant to the rules and regulations set forth in the South Carolina Development Impact Fee Act (Code of Laws of South Carolina, Section 6-1-910 et seq.). The process to create a local impact fee system begins with a resolution by the Town Council directing the Planning Commission to conduct an impact fee study and recommend a development impact fee ordinance for legislative action. Generally, a governmental entity must have an adopted comprehensive plan to enact development impact fees; however, certain provisions in State law allow counties, cities, and towns that have not adopted a comprehensive plan to impose development impact fees. Those jurisdictions must prepare a capital improvement plan as well as prepare an impact fee study that substantially complies with Section 6-1-960(B) of the Code of Laws of South Carolina. All counties, cities, and towns are also required to prepare a report that estimates the effect of development impact fees on the availability of affordable housing before imposing development impact fees on residential dwelling units. Based on the findings of the study, certain developments may be exempt from development impact fees when all or part of the project is determined to create affordable housing, and the exempt development’s proportionate share of system improvements is funded through a revenue source other than impact fees. A housing affordability analysis in support of the development impact fee study is published as a separate report. Eligible costs may include design, acquisition, engineering, and financing attributable to those improvements recommended in the local capital improvements plan that qualify for impact fee funding. Revenues collected by the county, city, or town may not be used for administrative or operating costs associated with imposing the impact fee. All revenues from development impact fees must be maintained in an interest-bearing account prior to expenditure on recommended improvements. Monies must be returned to the owner of record of the property for which the impact fee was collected if they are not spent within three years of the date, they are scheduled to be encumbered in the local capital improvements plan. All refunds to private landowners must include the pro rata portion of interest earned while on deposit in the impact fee account.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
2
The Town of Summerville is also responsible for preparing and publishing an annual report describing the amount of impact fees collected, appropriated, and spent during the preceding year. These updates must occur at least once every five years. Pursuant to the Act, the Town of Summerville will not be empowered to recommend additional projects eligible for impact fee funding or charge higher maximum allowable development impact fees until the Development Impact Fee study and capital improvement plan have been updated. Conceptual Development Impact Fee Calculation In contrast to project-level improvements, development impact fees fund growth-related infrastructure that will benefit multiple development projects, or the entire jurisdiction (referred to as system improvements). The first step is to determine an appropriate demand indicator for each infrastructure category. The demand indicator measures the number of demand units for each unit of development. For example, an appropriate indicator of the demand for park facilities is population growth, and the increase in population can be estimated from the average number of residents per housing unit. The second step in the development impact fee formula is to determine infrastructure units per demand unit, typically called level-of-service (LOS) standards. In keeping with the parks example, a common LOS standard is park acreage per resident. The third step in the development impact fee formula is the cost of various infrastructure units. To complete the parks example, this part of the formula would establish the cost per acreage for acquiring new park land. General Methodologies There are three general methods for calculating development impact fees. The choice of a particular method depends primarily on the timing of infrastructure construction (past, concurrent, or future) and service characteristics of the facility type being addressed. Each method has advantages and disadvantages in a particular situation and can be used simultaneously for different cost components. Reduced to its simplest terms, the process of calculating development impact fees involves two main steps: (1) determining the cost of development-related capital improvements and (2) allocating those costs equitably to various types of development. In practice, though, the calculation of development impact fees can become quite complicated because of the many variables involved in defining the relationship between development and the need for facilities within the designated service area. The following paragraphs discuss three basic methods for calculating development impact fees and how those methods can be applied. Cost Recovery (Past Improvements) The rationale for recoupment, often called cost recovery, is that new development is paying for its share of the useful life and remaining capacity of facilities already built, or land already purchased, from which new growth will benefit. This methodology is often used for utility systems that must provide adequate capacity before new development can take place. Incremental Expansion (Concurrent Improvements) The incremental expansion method documents current level-of-service (LOS) standards for each type of public facility, using both quantitative and qualitative measures. This approach ensures that there are no
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
3
existing infrastructure deficiencies or surplus capacity in infrastructure. New development is only paying its proportionate share for growth-related infrastructure. Revenue will be used to expand or provide additional facilities, as needed, to accommodate new development. An incremental expansion cost method is best suited for public facilities that will be expanded in regular increment to keep pace with development. Plan-Based Fee (Future Improvements) The plan-based method allocates costs for a specified set of improvements to a specified amount of development. Improvements are typically identified in a long-range facility plan, and development potential is identified by a land use plan. There are two options for determining the cost per demand unit: (1) total cost of a public facility can be divided by total demand units (average cost), or (2) the growth-share of the public facility cost can be divided by the net increase in demand units over the planning timeframe (marginal cost). Credits Regardless of the methodology, a consideration of “credits” is integral to the development of a legally defensible development impact fee methodology. There are two types of “credits” with specific characteristics, both of which should be addressed in development impact fee studies and ordinances. • First, a revenue credit might be necessary if there is a double payment situation and other revenues are contributing to the capital costs of infrastructure to be funded by development impact fees. This type of credit is integrated into the development impact fee calculation, thus reducing the fee amount. • Second, a site-specific credit or developer reimbursement might be necessary for dedication of land or construction of system improvements funded by development impact fees. This type of credit is addressed in the administration and implementation of the development impact fee program.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
4
Proposed Fee Methods and Cost Components Figure 1 summarizes the methods and cost allocation components used for each infrastructure category in the Town of Summerville’s development impact fee study. The development impact fees are based on the actual level of service. The Parks and Recreation components are allocated to only residential development based on population. The Public Safety and Fire component is allocated to residential and nonresidential development based on population and nonresidential vehicle trips, respectively. Figure 1: Proposed Fee Methods and Cost Components
Proposed Development Impact Fee Schedule As documented in this report, the Town of Summerville has complied with the South Carolina Development Impact Fee Act and applicable legal precedents. Development impact fees are proportionate and reasonably related to capital improvement demands of new development. Specific costs have been identified using local data and current dollars. This report documents the formulas and input variables used to calculate the development impact fees. The development impact fee methodologies also identify the extent to which new development is entitled to various types of credits to avoid potential double payment of growth-related capital costs. For residential development, proposed fees are assessed per housing unit by type of unit. The proposed residential fee categories include single family and multifamily units. Single family units include detached, attached (i.e., “townhouse”), and mobile home units. Multifamily units include duplexes, condominiums and apartments with two or more units. For nonresidential development, fees are assessed per 1,000 square feet of floor area. The proposed fee schedule for nonresidential development is designed to provide a reasonable development impact fee determination for broad property classes – commercial, office, industrial, and institutional. Figure 2 summarizes proposed development impact fees for new development in the Town of Summerville. The amounts shown are “maximum supportable” amounts based on the methodologies, levels of service, and costs for the capital improvements identified herein. The fees represent the highest amount feasible for each type of applicable development, which represent new growth’s fair share of the system improvement costs detailed in this report. The Town can adopt amounts that are lower than the maximum amounts shown; however, a reduction in fee revenue will necessitate an increase in other revenues, a decrease in planned capital expenditures, and/or a decrease in the Town’s level of service.
!"#$%F'$()'($*+
,%'*-.$I
0*$12)*+
3$*%
,.F'+
4*).1*$I
!")$*5*"'%6
789%"F2." :6%";<%F*= ,.F'+
366.)%'2."
:%$LF ?.@"@2=* AB3
:%$L+C%"=D+:%$L+
!59$.1*5*"'FD+:%$L+
N%)262'2*FD+?$%26FD+:%$LF+
F*G2)6*F
AB3 :.9(6%'2."
:(H62)+0%#*'I ?.@"@2=* AB3 AB3 :(H62)+0%#*'I+N%)262'2*F:.9(6%'2."D+A."$*FI+
F*G2)6*+?$29F
N2$* ?.@"@2=* AB3 N2$*+0'%'2."FD+N2$*+
399%$%'(F AB3 :.9(6%'2."D+A."$*FI+
F*G2)6*+?$29F
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
5
Figure 2: Maximum Supportable Development Impact Fees
Figure 3: Current Development Impact Fees
!"#$%"F'$()*+",")-./"F'
!"#$%F'()*"%+ ,-.I01 ,2.13I ,3.I24 012133
56%7"8()*"%+ ,2.391 ,3.111 ,4:1 042536
7-F8"#$%"F'$()*+",")-./"F'
;#<6=7>")% ,? ,0:2 ,-3I 0999
@A**F>B")% ,? ,-.934 ,2.3?: 0:2;65
CMM"BF'E'C7FF>'!F>G"BF ,? ,3.210 ,I9: 0<2;=6
;#=7"767"A#)% ,? ,3.:?3 ,4-4 062543
>""#*?"8*@F$'
>""#*."8*<2333*ABC(8"*>""'
D-'()
D-'()
+",")-./"F'*DN."
+",")-./"F'*DN."
?CF)$G*A(H"'N >$8"
?CF)$G*A(H"'N >$8"
?(8I#
?(8I#
!"#$%"F'$()*+",")-./"F'
!"#$%F'()*"%+ ,-.I0- ,1.I1I ,I02 012345
34%5"6()*"%+ ,1.I07 ,1.8-9 ,8:; 062178
9-F:"#$%"F'$()*+",")-./"F'
<#=4>5?")% ,: ,1.:01 ,;89 0;2<68
@A**F?B")% ,: ,1.I77 ,1.:I0 042747
CMM"BF'E'C5FF?'!F?G"BF ,: ,2.I09 ,1.;10 06238;
<#>5"545"A#)% ,: ,1.882 ,1.01: 0523=4
>""#*?":*@F$'
+",")-./"F'*AB." ?(:C# ?DN)$F*G(H"'B; >$:" A-'()
>""#*.":*;2===*GID(:"*>""'
+",")-./"F'*AB." ?(:C# ?DN)$F*G(H"'B; >$:" A-'()
1H'IFF'B4??F#5'34#"B"J)%'()B"%"5"F>')#='OL4"J*F#5'"*J)B5'MFF'">'4>F='"#'BA*J)?">A#'5A'5FF'#FM'N4O%"B'!)MF5+'
MFF
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
6
Figure 4: Difference between Current and Maximum Supportable Development Impact Fee
Furthermore, this report includes the Town of Summerville’s Capital Improvement Plan. In accordance with South Carolina Development Fee Act a municipality must have an adopted Capital Improvement Plan to collect impact fees. A note on rounding: Calculations throughout this report are based on an analysis conducted using Excel software. Most results are discussed in the report using one-, two-, and three-digit places, which represent rounded figures. However, the analysis itself uses figures carried to their ultimate decimal places; therefore, the sums and products generated in the analysis may not equal the sum or product if the reader replicates the calculation with the factors shown in the report (due to the rounding of figures shown, not in the analysis).
!"#$%"F'$()*+",")-./"F'
!"#$%F'()*"%+ ,-.II0 -1I2 -333 012133
45%6"7()*"%+ -889 ,-:I;0 -<3 40567
8-F9"#$%"F'$()*+",")-./"F'
=#>5?6@")% -9 ,-:3I0 ,-:290 405657
AB**F@C")% -9 -.MI31 -.M9;; 0:2553
EFF"CF'G'E6HF@'!F@I"CF -9 ,-.M<..0 ,-.M9;20 40:2;<57
=#?6"656"B#)% -9 ,-;I.0 ,-13.0 40=;:7
.J'OHF'C5@@F#6'45#"C"L)%'()C"%"6"F?')#>'MN5"L*F#6'"*L)C6'FFF'"?'5?F>'"#'CB*L)@"?B#'6B'6HF'#FO'P5Q%"C'!)FF6+'
FFF
>""#*."9*12???*@AB(9"*>""'
+",")-./"F'*CD." N(9F# NBG)$H*@(I"'D1 >$9" C-'()
>""#*N"9*JF$'
+",")-./"F'*CD." N(9F# NBG)$H*@(I"'D1 >$9" C-'()
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
7
Projected Demand Section 6-1-960 (B6) of the South Carolina Development Impact Fee Act requires: “the total number of service units necessitated by and attributable to new development within the service area, based on the land use assumptions and calculated in accordance with generally accepted engineering or planning criteria.” Based on the land use assumptions discussed in Appendix B, both residential and nonresidential development is expected to continue in the Town of Summerville over the next ten years. Figure 3 shows projected population, housing units, employment and nonresidential floor area over the next ten years. The Town of Summerville expects that in the next 10 years there will be an increase in 4,986 housing units. This is an annual increase of approximately 499 housing units per year. In total, the Town of Summerville is projected to increase by 9,829 residents of the next ten years, an increase of 18 percent from the base year. Nonresidential floor area growth is projected using CoStar construction forecasting, information from Town staff, and projected population growth. Employment growth is projected based on the nonresidential floor area growth and employee density factors from the Institute of Transportation Engineers. Over the next ten years, the Town is projected to add 1.5 million square feet of nonresidential floor area, a 15 percent increase from the base year. The commercial sector is projected to have the highest floor area growth. Figure 5: Town of Summerville Residential and Nonresidential Projections
!"!#!"!$!"!%!"!F!"'"!"'(!"'!!"''!"')!"'*!"'#
+,-.I0.,1( ! ' ) * # $ % F ("
!"#$%F'(") *+H---*+H.-/**H0/.*1H2*+*2H2-0*0H10-*.H12/1-H10/1/H2//13H21-14H03..H03.
5"$6()789)('6
23456.I7,8369 ($:)#"($:#*#($:%*#(%:"*F(%:!##(%:)$%(%:#F'(%:F(!(F:('#(F:'#)(F:*F$3H/41
;<6=3>?,8369 #:!#'#:*!)#:$F"$:"#!$:''%$:#!"$:F"$%:!""%:)F%%:%"'F:(('3H0*-
:"'F%85"$6()789)('634H2343+H/0-3+H1+13*H/3-3*H1-+31H-.231H1--32H//332H14*30H/1230H2-.+H.01
;<#%"=<>)'
@4A<-=13,6 (:*'F(:*#$(:*F*(:#!'(:#*!(:#%!(:$(!(:$)!(:$$'(:%")(:%'#3.2
BC88.1M3,6 #:#"$#:$(F#:%'!#:F)$$:"#)$:(%!$:'"!$:)!)$:*)$$:#$!$:$FF/H/.3
E??3M.IFIE=G.1I2.1H3M.*:*#"*:*F'*:#!**:#*F*:#F!*:$!#*:$#"*:$F**:%'"*:%#**:F""4+-
@4-=3=<=3C4,6 #:!"##:'''#:)#!#:*F'#:$!$#:%#!#:FFF$:('F$:!%($:)!*$:*$(/H41*
:"'F%8;<#%"=<>)'/.H./33-H3//3-H*/*3-H0333/H/4*3/H+*33/H22433H-..33H+4-33H21134H/-24H/.*
?")@>6A8B%""@8C@>F8DN/H---F
@4A<-=13,6 (:F%)!:"(*!:")$!:"$F!:(((!:())!:($$!:!((!:!)#!:!%(!:'(#443
BC88.1M3,6 ':$#)':%(%':%$!':F!$':F%'):")"):"F$):(*#):!(*):!$*):''**2/
E??3M.IFIE=G.1I2.1H3M.(:)'*(:))F(:)#)(:)$%(:)F'(:*"%(:*!'(:*'%(:**'(:*#F(:*%)/+.
@4-=3=<=3C4,6 !:#F*!:$'$!:$%"!:%!)!:%#%!:F()!:F#"':""#':"*)':("!':(*(+*1
:"'F%8?")@>6A8B%""@8C@>F.H020/-H-3-/-H/14/-H4-0/-H+*1/-H1-*/-H2*2/-H.////H-12//H331//H401/H*-0
(">0.,1I
@4M1.,-.G$<<>@H(%%>H8GI
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
8
PARKS AND RECREATION DEVELOPMENT IMPACT FEE CALCULATIONS Methodology Section 6-1-920(18h) of the South Carolina Development Impact Fee Act states that a development impact fee may be imposed on public facilities including: “…parks, libraries, and recreational facilities.” Section 6-1-960(B)(1) of the South Carolina Development Impact Fee Act requires: “a general description of all existing facilities and their existing deficiencies, within the service area or areas of the governmental entity, a reasonable estimate of all costs, and a plan to develop the funding resources, including existing sources of revenues, related to curing existing deficiencies including, but not limited to, the upgrading, updating, improving, expanding, or replacing of these facilities to meet existing needs and usage.” Section 6-1-960(B)(2) of the South Carolina Development Impact Fee Act requires: “an analysis of total capacity, the level of current usage, and commitments for usage of capacity of existing public facilities, which must be prepared by qualified a professional using generally accepted principles and professional standards.” It is assumed that only residential growth creates additional demand on Parks and Recreation facilities. Furthermore, the level of service for all infrastructure components is calculated at a Townwide basis. Residential development impact fees are calculated on a per capita basis, then converted to an appropriate amount for each type of housing unit based on persons per housing unit factors. Parks and Recreation Benefit Area Benefit areas are geographic areas in which the impact fees collected are earmarked to be spent. They are intended to ensure a reasonable benefit from the impact fee expenditures to the development that pays the fees by precluding, for example, a situation in which the fees collected from a development would be spent on facilities in the opposite end of the community that would be unlikely to benefit or be used by the fee-paying development. However, communities the size of Summerville are often treated as a single benefit district for the purpose of park and recreation impact fees. Additionally, Summerville provides a Townwide level of service, not varying levels of service to different areas. A single benefit area would continue to provide the Town with the maximum flexibility in the expenditure of impact fee funds, and to ensure that sufficient funds can be accumulated to fund significant improvements. Parks and Recreation Funding Sources Summerville has studied various ways of providing funding for Parks and Recreation facilities. The sources of revenue for Parks and Recreation are General Fund revenues, other taxes, sponsorships, grants or impact fees. In comparing an equitable allocation to the costs borne in the past and to be borne in the future, in comparison to the benefits already received and yet to be received, the Town has determined
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
9
that impact fees are the most equitable way of financing the growth-related Parks and Recreation facilities. Service Units for Park and Recreation Analysis Section 6-1-960(B)(4) of the South Carolina Development Impact Fee Act requires: “a definitive table establishing the specific service unit for each category of system improvements and an equivalency or conversion table establishing the ratio of a service unit to various types of land uses, including residential, commercial, agricultural, and industrial, as appropriate.” The “service unit” used for residential development is persons per housing unit (PPHU). This is a measure of, on average, the number of persons residing in each housing unit. As shown in Figure PR1, there are 2.56 persons per single family unit and 1.53 persons per multifamily unit. Factors have been calculated based on data provided by the U.S. Census Bureau’s 2023 ACS 5-year estimates (further discussed in Appendix B). Figure PR1: Residential Service Units
Parks and Recreation Level of Service and Cost Analysis Park Land – Incremental Expansion As shown in Figure PR2, the Town of Summerville has 276.3 acres of park land. This inventory excludes all parks that are owned and maintained by private developments (e.g., neighborhood parks). The Town plans to maintain current levels of service by incrementally expanding park land to serve new development. When the existing inventory of park land is compared to the existing residential population, the Town’s existing level of service is 0.0051 acres per person (276.3 acres X 100 percent residential share / 54,000 persons). Based on a survey of land for sale in and around the Town, this analysis uses a land acquisition cost of $100,000 per acre. For park land, the cost is $511.59 per person (0.0051 acres per person X $100,000 per acre).
!"#$%F'()*"%+ H-./
01%2"3()*"%+ 4-.5
4-'!FF'6)#7'89F':991*;2"<#9
=FLF%<;*F#2'?+;F @FA9<#9';FA'
B<19"#$'8#"24
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
10
Figure PR2: Park Land Level of Service and Cost Allocation
!"#$%FG(F)* +$%"#
+H-."- /01
2%)3*45-6F.7 809
!)(7 10J
;<="% L0?
;<($@F*#)*4AB<-%" L0?
C"##"* 80L
A<66"%DF.."4N%"#"%D" 1?09
F-@-=-* ?/0G
A-36F..4HFI="# G/0L
J"O()* J90L
L-MN%))M4O%-F. PJ01
HQRR 90L
A-<.4+."O-*I"% J0?
A@"G-%I J08
A<66"%DF.."4AM-("G-%M L0/
S-##-6-##-3 G08
!"#$% &'()*
R)#(4G"%4+$%" TPLLULLL
QOF#(F*=4+$%"# J8V09
H"#FI"*(F-.4A@-%" PLLP
JLJV4N)G<.-(F)* ?1ULLL
+$%"#4G"%4N"%#)* L0LL?P
+",#-./0-1/0,"2 3455)46
A)<%$"X4A<66"%DF.."4N-%M#4-*I4H"$%"-(F)*4!"G-%(6"*(
R)#(4+..)$-(F)*45-$()%#
H"#FI"*(F-.
Y"D".R)[RA"%DF$"4\YLA]4A(-*I-%I#
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
11
Park Improvements – Incremental Expansion As indicated in Figure PR3, Summerville currently provides 71 park improvements in its parks with an estimated value of $20,788,000 which results in a weighted average cost per improvement of $292,789 ($20,788,000 / 71 improvements). As is the case with park land, the Town plans to construct additional park improvements to serve future development. When the Town’s inventory of 71 park improvements is compared to current population, the Town’s existing level of service is 0.0013 improvements per person (71 improvements X 100 percent residential share / 54,000 persons). Using the weighted average cost per improvement of $292,789, the cost per demand unit is $384.96 per person (0.0013 improvements per person X $292,789 per improvement). Figure PR3: Park Improvement Level of Service and Cost Allocation
!"#$%FG(F)* +,G%)-","*(# .*F(I0)#( 1"G23$","*(I0)#(
45"2("%# 67 8699:999 86:799:999
;3K"=)# L 86?:999 8@?:999
A23BC%)D*E# F 8@?9:999 8L:G99:999
1"#(%)),# 6H 8L99:999 8L:G99:999
I"**F#I$)D%(# F 866?:999 8JH9:999
4G23#5IA3E 6 8??9:999 8??9:999
AF$O2"=322I0)D%( G 8?7:?99 8L@?:999
L3B3OIM3D*$5 6 8F9:999 8F9:999
N3#"=322O4)P(=322IQF"2E 7 87LF:999 8?:6GG:999
Q))(=322IPF"2E 6 87LF:999 87LF:999
4)$$"%IPF"2E L 87LF:999 8H:H6@:999
4O3("G3%O 6 8G99:999 8G99:999
N3#O"(=322I0)D%( H 866?:999 8HL9:999
!"G)(I1"*(32IQ3$F2F(B 6 86:999:999 86:999:999
!"#$% &' ()*)+&,* ()-+&,,+---
0)#(IG"%I+,G%)-","*( 8HJH:7FJ
RSF#(F*CI+,G%)-","*(# 76
1"#FE"*(F32I453%" 699T
H9HGIA)GD23(F)* ?@:999
+,G%)-","*(#IG"%IA"%#)* 9U996L
."/#01230423/"5 (6,78*9
4)D%$"VI4D,,"%-F22"IA3%O#I3*EI1"$%"3(F)*I!"G3%(,"*(
M"-"2P)PP4"%-F$"IXMY4RI4(3*E3%E#
1"#FE"*(F32
0)#(I[22)$3(F)*IQ3$()%#
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
12
Park Facilities – Incremental Expansion As shown in Figure PR4, the Town of Summerville has 23,129 square feet of park facilities. The Town plans to maintain current levels of service by incrementally expanding park facilities to serve new development. When the existing inventory of park facilities is compared to the existing residential population, the Town’s existing level of service is 0.4283 square feet per person (23,129 square feet X 100 percent residential share / 54,000 persons). Based on information from similar communities, this analysis uses a construction cost of $630 per square foot. For park facilities, the cost is $269.84 per person (0.4283 square feet per person X $630 per square foot). Figure PR4: Park Facilities Level of Service and Cost Allocation
!"#$%FG(F)* +,-.%"/0""(
1)22F*#/345.%4#/6)77-*F(8/6"*("% 9:;<<<
=.L.?.*/@AAF$" B;C<<
M.F*/E%"##F)G H;IB<
+=+J/6)*$"##F)*#/ 9;<CC
0%)*(/0))(F.22/6)*$"##F)*# 9;:9<
!"#$% &'()&*
6)#(/G"%/+,-.%"/0))( OLH<
3GF#(F*?/+,-.%"/0""( BH;9BC
1"#F4"*(F.2/+L.%" 9<<M
B<BL/E)G-2.(F)* N:;<<<
+,-.%"/0""(/G"%/E"%#)* <O:BPH
+",#-./0-1/0,"2 3&4*567
+)-%$"Q/+-77"%RF22"/E.%S#/.*4/1"$%".(F)*/!"G.%(7"*(
6)#(/T22)$.(F)*/0.$()%#
J"R"2U)AU+"%RF$"/VJ@+P/+(.*4.%4#
1"#F4"*(F.2
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
13
Trails – Incremental Expansion As shown in Figure PR5, the Town of Summerville has 13.8 miles of trails. The Town plans to maintain current levels of service by incrementally expanding its trails inventory to serve new development. When the existing inventory of trails is compared to the existing residential population, the Town’s existing level of service is 0.0003 miles per person (13.8 miles X 100 percent residential share / 54,000 persons). Based on the weighted replacement cost per mile, this analysis uses a construction cost of $1,004,066 per mile. For trails, the cost is $256.78 per person (0.0003 miles per person X $1,004,066 per mile). Figure PR5: Trails Level of Service and Cost Allocation
!"#$%F'(F)* +F,"# -)#(./"%.+F," 0)(1,.-)#(
231,"1./1%4 5678 9:;<=7:8 9L?=@A<
!)(B./1%4 56AL 9<;=;?: 9A8=;;:
CM"'1%N./1%4 56:@ 9@A=@<: 9:A=?@;
F1##1G1##1H.-)GGI*F(B./1%4 56?L 9::;=:57 9;?=?85
J%)H*.O1GF,B./1%4 56:? 98;=<AA 9L=;;5
L14M%))4.N1(I%".0%1F, 568L 9:@?=:A; 9::@=@A;
C1HGF,,.J%1*$M.0%1F, 86L5 9:=?@@=:A; 9<=?8;=;;:
2#M,"B.OFP"%./%"#"%P" A6L: 9:=:<5=5;; 9?=?;;=5AA
+F#$6.Q*'1P"N.0%1F,# A655 9;?A=L:5 9L87=8A:
!"#$% &'() *&+,,-+,.. *&'+)..+&/0
-)#(.'"%.+F," 9:=55;=588
RSF#(F*T.+F,"# :?6L
O"#FN"*(F1,.CM1%" :55U
A5A8./)'I,1(F)* 7;=555
+F,"#.'"%./"%#)* 56555?
1"2#345637562"8 *0/.(9)
C)I%$"V.CIGG"%PF,,"./1%4#.1*N.O"$%"1(F)*.!"'1%(G"*(
-)#(.2,,)$1(F)*.O1$()%#
P"P",X)YXC"%PF$".RPLC[.C(1*N1%N#
O"#FN"*(F1,
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
14
Park Vehicles – Incremental Expansion As indicated in Figure PR6, Summerville’s current parks vehicle inventory is 2 units with an estimated value of $230,000 which results in a weighted average cost per vehicle of $115,000 ($230,000 / 2 vehicles). The Town plans to purchase additional park vehicles to serve future development. When the Town’s inventory of 2 park vehicles is compared to current population, the Town’s existing level of service is 0.00004 vehicles per person (2 vehicles X 100 percent residential share / 54,000 persons). Using the weighted average cost per vehicle of $115,000, the cost per demand unit is $4.26 per person (0.00004 vehicles per person X $115,000 per improvement). Figure PR6: Park Vehicles Level of Service and Cost Allocation
!"#$%F'(F)* +),*( +)#(-."%-/*F( 0)(12-+)#(
31$45)" 6 7689:999 7689:999
3,$4"(-0%,$4 6 7699:999 7699:999
!"#$% & '(()*+++ '&,+*+++
0)(12-;"5F$2"# <
0)(12-+)#( 7<89:999
-".#/012/31456%1 '(()*+++
=LF#(F*?-;"5F$2"# <
@"#FA"*(F12-B51%" 699C
<9<D-.)',21(F)* EF:999
/*F(#-'"%-."%#)* 9G9999F
-".#/012/712."8 '9:&;
B),%$"H-B,II"%JF22"-.1%4#-1*A-@"$%"1(F)*-!"'1%(I"*(
O"J"2L)MLB"%JF$"-NOOBP-B(1*A1%A#
@"#FA"*(F12
+)#(-Q22)$1(F)*-R1$()%#
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
15
Projection of Parks and Recreation Growth-Related Facility Needs Section 6-1-960(B)(5) of the South Carolina Development Impact Fee Act requires: “a description of all system improvements and their costs necessitated by and attributable to new development in the service area, based on the approved land use assumptions, to provide a level of service not to exceed the level of service currently existing in the community or service area, unless a different or higher level of service is required by law, court order, or safety consideration.” Section 6-1-960(B)(7) of the South Carolina Development Impact Fee Act requires: “the projected demand for system improvements required by new service units projected over a reasonable period of time not to exceed twenty years.” Park Land Figure PR7 projects the growth-related demand for park land over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands 50.3 acres of park land (9,829 additional persons X 0.0051 acres per person) at a cost of $5 million (50.3 acres X $100,000 per acre). Figure PR7: Projected Demand for Park Land
!"#$%&G(%)* +,-*G."IG01I"
2324 567333 2849:
2328 567;3< 2=39;
232= 557=<; 2=594
232; 547856 2;396
23:3 58783= 2;592
23:< 5=74=3 :3392
23:2 5;748< :359:
23:: 4374=< :<396
23:6 4<78<< :<598
23:5 427843 :2<9<
23:4 4:7=2; :2495
!"#$%&'()%*+,* -.I0- 1"23
L5732=75:8G
?@."G,AGB%AI$-*IC1*CI" D"E"FG,AGG"IE)1"
H$IIGD$%& L<33733339335<01I"- ."IGH"I-,%
!"#$%&GA,IGH$IIGD$%&
J"$I H,.CF$*),% 01I"-
KI,L*MNO"F$*"&GPQ."%&)*CI"-
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
16
Park Improvements Figure PR8 projects the growth-related demand for park improvements over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands approximately 12.9 park improvements (9,829 additional persons X 0.0013 improvements per person) at a cost of $3.7 million (12.9 park improvements X $292,789 per improvement). Figure PR8: Projected Demand for Park Improvements
!"#$%&G(%)* +,-*G."IG(%)*
0102 345111 6781
0106 345917 6080
010: 335:79 6;84
0109 325634 6482
01;1 36561: 6389
01;7 3:52:1 6680
01;0 395267 6:83
01;; 2152:7 698:
01;4 275677 :787
01;3 205621 :083
01;2 2;5:09 :;89
!"#$%&'()%*+,* -.I0- !01-
<;56:;5:67G
="L"?G,@GA"IL)B"CD."G,@GE%@I$-*IFB*FI"
G$IHGE#.I,L"#"%*- <09056:918117;E#.I,L"#"%*- ."IGG"I-,%
!"#$%&G@,IGG$IHGE#.I,L"#"%*-
I"$I G,.F?$*),% E#.I,L"#"%*-
JI,K*LMN"?$*"&GOP."%&)*FI"-
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
17
Park Facilities Figure PR9 projects the growth-related demand for park facilities over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands approximately 4,210 square feet of park facilities (9,829 additional persons X 0.4283 square feet per person) at a cost of $2.67 million (4,210 square feet X $630 per square foot). Figure PR9: Projected Demand for Park Facilities
!"#$%FG(%)*+,-*G."IG012G3*2
4546 789555 4:9;4<
454= 789<5; 4:97;7
454L 779L;< 4:9<5L
454< 769=78 489:5<
45:5 7=9=5L 489=;=
45:; 7L96L5 479;:8
45:4 7<96=; 47977L
45:: 6596L; 479<<;
45:8 6;9=;; 4698:4
45:7 649=65 469LL;
45:6 6:9L4< 4=9::<
!"#$%&'()%*+,* -.I0- 1.0!"
?4967494<5G@I,A*BCD"E$*"FGFG."%F)*HI"-
?6:55284L:01H$I"G3""* ."IGI"I-,%
JK."G,LGM%LI$-*IHN*HI" O"P"EG,LG0"IP)N"
I$IQG3$N)E)*)"-
!"#$%FGL,IGI$IQG3$N)E)*)"-
R"$I I,.HE$*),% 01H$I"G3""*
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
18
Trails Figure PR10 projects the growth-related demand for trails over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands approximately 2.5 miles of trails (9,829 additional persons X 0.0003 miles per person) at a cost of approximately $2.5 million (2.5 miles X $1,004,066 per mile). Figure PR10: Projected Demand for Trails
!"#$%&G(%)* +,-*G."IG0)1"
2324 567333 89:;
232< 567=38 86:3
232; 557;8= 86:9
232= 547<56 86:5
2393 5<7<3; 86:;
2398 5;74;3 85:3
2392 5=74<8 85:9
2399 4374;8 85:5
2396 487<88 85:;
2395 427<43 84:8
2394 497;2= 84:9
!"#$%&'()%*+,* -.I0- 012
L275297=69G
?"$I @,.A1$*),% 0)1"-
BI,C*MEF"1$*"&GGH."%&)*AI"-
IJ."G,KGL%KI$-*IAM*AI" N"O"1G,KGP"IO)M"
II$)1- 3:33390)1"- ."IG@"I-,% L873367344
!"#$%&GK,IGII$)1-
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
19
Park Vehicles Figure PR11 projects the growth-related demand for park vehicles over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands approximately 0.4 park vehicles (9,829 additional persons X 0.00004 vehicles per person) at a cost of approximately $42,000 (0.4 units X $115,000 per unit). Figure PR11: Projected Demand for Park Vehicles
Credits As the Town has no outstanding debt on its Parks and Recreation facilities, a credit for future principal payments is not included. If elected officials make a legislative policy decision to fully fund growth-related costs from impact fees, there will be no potential double-payment from other revenue sources. Maximum Supportable Parks and Recreation Development Impact Fee The following figure lists the maximum supportable Parks and Recreation development impact fee for the Town of Summerville. Development impact fees for Parks and Recreation are only assessed on residential development and based on household size (i.e., persons per housing unit). Differentiating the fee by housing type allows the results to be more exact about the level of demand (persons per housing unit) a residential development will place on the current infrastructure based on level of service standards. For
!"#$%&G(%)* +,-*G."IG(%)*
0102 345111 061
0107 345819 061
010: 335:98 069
0108 325734 069
01;1 37571: 069
01;9 3:52:1 060
01;0 385279 060
01;; 2152:9 060
01;4 295799 06;
01;3 205721 06;
01;2 2;5:08 064
!"#$%&'()%*+,* -.I0- "12
<495:23G=I,L*?@A"B$*"&GCD."%&)*EI"-
!"#$%&GF,IGG$IHGI"?)JB"-
K"$I G,.EB$*),% (%)*-
G$IHGI"?)JB"- 1611114 (%)*- ."IGG"I-,% <9935111
LM."G,FGN%FI$-*IEJ*EI" O"P"BG,FGQ"IP)J"
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
20
residential development, the total cost per person is multiplied by the housing unit size to calculate the proposed fee. For example, there is a net cost per person of $1,427.43 and there is an average of 2.56 persons per single family housing unit, resulting in a fee of $3,654 per unit ($1,427.43 cost per person x 2.56 persons per unit). The fees represent the highest amount supportable for each type of development, which represents new growth’s fair share of the cost for capital facilities. The Town may adopt fees that are less than the amounts shown. However, a reduction in development impact fee revenue will necessitate an increase in other revenues, a decrease in planned capital expenditures, and/or a decrease in levels of service. Figure PR12: Maximum Supportable Parks and Recreation Development Impact Fee
!""#$%F'%("() $%*)#'"+#H"+*%(
!"#$%F"'( )*++,*-
!"#$%.I0#123I3'45 )678,-9
!"#$%:";<=<4<35 )L9-,78
?#"<=5 )L*9,@7
!"#$%A3B<;=35 )8,L9
-%)./ 012345637
8"*9:"()9./#;"<"/%'F"()
C<'M=3%:"I<=E L,*9 072=>3 )6F7*6 G)+--H
IJ=4<K:"I<=E +,*6 0421?3 )+F7*8 )66L
+,%C33%F"'(%M53%N55JI04<1'5
;"<"/%'F"()#-@'" H"+*%(*#'"+#
A%B*9(C#D(9)1
H+%'%*":
!""*
$B++"()#
!""* ;9EE"+"(F"
!""*#'"+#D(9)
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
21
Projected Revenue from Parks and Recreation Development Impact Fee Revenue from the Parks and Recreation development impact fee is estimated in Figure PR13 by applying the maximum supportable fees to the projected growth. As a result, projected fee revenue equals $14 million over the next ten years compared to projected expenditures of $14 million. Figure PR13: Projected Revenue from the Parks and Recreation Development Impact Fee
!"#$%FG(F)"*+H-.%-I0G(F)"* 1#%)2
3)"4G5)I6 789:;<98=LG 7:G 789:;<98=LG
3)"4G?@A"#B*@*I%. 7=9L<=9<LCG 7:G 7=9L<=9<LCG
3)"4GM)E-2-%-*. 7;9F8;9;G:G 7:G 7;9F8;9;G:G
1")-2. 7;98;=9GH=G 7:G 7;98;=9GH=G
3)"4GI*F-E2*. 7HC9<F8G 7:G 7HC9<F8G
!"#$% &'()*+*),*-. &*. &'()*+*),*-.
(-I02*GM)@-2J KL2%-MM)@-2J
7=9F8H 7;9C<H
A*"GLI-% A*"GLI-%
N.0GOI-% N.0GOI-%
P).* ;:;F CL9HF: F9;F=
Q*)"GC ;:;L CL9F8F F98;H
Q*)"G; ;:;< CL9<8F F9LG:
Q*)"G= ;:;G C<9:8G L9:F;
Q*)"GH ;:=: C<9;FF L9==<
Q*)"G8 ;:=C C<9HL< L9F;:
Q*)"GF ;:=; C<9FG= L9G:L
Q*)"GL ;:== C<9GC; <9;::
Q*)"G< ;:=H CG9C=F <9HG<
Q*)"GG ;:=8 CG9=FH <9<:=
Q*)"GC: ;:=F CG98GL G9CC=
;9C=F ;9<8:
&-)/*0)-+, &0)11+)--+
3"#R*E%*6GM**GS*B*IL* 7CH9:=:98:L
1#%)2G+HA*I6-%L"*. 7CH9:=:98:L
M**GT#@A#I*I%
Q*)"
C:MQ*)"G?IE"*).*
23"456#57.8595:;5
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
22
PUBLIC SAFETY DEVELOPMENT IMPACT FEE CALCULATIONS Methodology Section 6-1-920(18f) of the South Carolina Development Impact Fee Act states that a development impact fee may be imposed on public facilities including: “…public safety facilities, including law enforcement, fire, emergency medical and rescue, and street lighting facilities.” The Public Safety development impact fee includes the following component: • Police Space • Court Space • Fire Administrative Space A plan-based methodology is applied to the Public Safety building space analysis. Costs are allocated to both residential and nonresidential development using different demand indicators for each type of development. Section 6-1-960(B)(1) of the South Carolina Development Impact Fee Act requires: “a general description of all existing facilities and their existing deficiencies, within the service area or areas of the governmental entity, a reasonable estimate of all costs, and a plan to develop the funding resources, including existing sources of revenues, related to curing existing deficiencies including, but not limited to, the upgrading, updating, improving, expanding, or replacing of these facilities to meet existing needs and usage.” Section 6-1-960(B)(2) of the South Carolina Development Impact Fee Act requires: “an analysis of total capacity, the level of current usage, and commitments for usage of capacity of existing public facilities, which must be prepared by qualified a professional using generally accepted principles and professional standards.” Public Safety Benefit Area Police protection is provided from a central headquarters and by mobile units. While fire apparatus stationed in fixed locations primarily serves nearby areas, companies often respond to incidents in neighboring response areas as the need arises. In addition, certain facilities, such as central administrative and dispatch facilities, and court facilities have a system-wide function. Consequently, the entire Town may reasonably be designated as a single benefit area for public safety impact fees Public Safety Funding Sources Summerville has studied various ways of providing funding for Public Safety facilities. The sources of revenue for Public Safety are General Fund revenues, hospitality tax, grants or impact fees. In comparing an equitable allocation to the costs borne in the past and to be borne in the future, in comparison to the
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
23
benefits already received and yet to be received, the Town has determined that impact fees are the most equitable way of financing the growth-related Public Safety facilities. Service Units for Public Safety Section 6-1-960(B)(4) of the South Carolina Development Impact Fee Act requires: “a definitive table establishing the specific service unit for each category of system improvements and an equivalency or conversion table establishing the ratio of a service unit to various types of land uses, including residential, commercial, agricultural, and industrial, as appropriate.” The “service unit” used for residential development is persons per housing unit (PPHU). This is a measure of the average number of persons residing in each housing unit. As shown in Figure P1, there are 2.56 persons per single family unit and 1.53 persons per multifamily unit. Factors are calculated based on data provided by the U.S. Census Bureau’s 2023 ACS 5-year estimates (further discussed in Appendix B). Figure P1: Residential Service Units
TischlerBise recommends using nonresidential vehicle trips as the nonresidential “service unit” for Public Safety infrastructure. Average weekday vehicle trip ends for nonresidential development are from the 12th edition of the reference book, Trip Generation, published in 2025 by the Institute of Transportation Engineers. A “trip end” represents a vehicle either entering or exiting a development (as if a traffic counter were placed across a driveway). Trip ends for nonresidential development are calculated per thousand square feet. Trip generation rates are used for nonresidential development because vehicle trips are highest for retail/commercial developments, such as shopping centers, and lowest for industrial development. Office and institutional trip rates fall between the other two categories. This ranking of trip rates is consistent with the relative demand for Public Safety services from nonresidential development. Other possible nonresidential demand indicators, such as employment or floor area, will not accurately reflect the demand for service. For example, if employees per thousand square feet were used as the demand indicator, Public Safety development fees would be disproportionately high for office and institutional development because offices typically have more employees per 1,000 square feet than retail uses. If floor area were used as the demand indicator, Public Safety development fees would be disproportionately high for industrial development. For nonresidential land uses, the standard 50 percent adjustment is applied to office and industrial. A lower vehicle trip adjustment factor is used for commercial/retail and institutional because these types of development attracts vehicles as they pass-by on arterial and collector roads. For example, when someone stops at a convenience store on their way home from work, the convenience store is not their primary destination. Further detail on vehicle trip factors can be found in Appendix B.
!"#$%F'()*"%+ H-./
01%2"3()*"%+ 4-.5
4-'!FF'6)#7'89F':991*;2"<#9
=FLF%<;*F#2'?+;F @FA9<#9';FA'
B<19"#$'8#"24
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
24
Figure P2: Nonresidential Service Units
Public Safety Proportionate Share Factors Both residential and nonresidential developments increase the demand on Public Safety infrastructure. To calculate the proportional share between residential and nonresidential demand on Public Safety services and infrastructure, a functional population approach is used. Functional population is like what the U.S. Census Bureau calls "daytime population," by accounting for people living and working in a jurisdiction, but also considers commuting patterns and time spent at home and at nonresidential locations. The functional population approach allocates the cost of the facilities to residential and nonresidential development based on the activity of residents and workers in the Town through the 24 hours in a day. Residents that do not work are assigned 20 hours per day to residential development and 4 hours per day to nonresidential development (annualized averages). Residents that work in Summerville are assigned 14 hours to residential development and 10 hours to nonresidential development. Residents that work outside the Town are assigned 14 hours to residential development, the remaining 10 hours in the day are assumed to be spent outside of the Town working. Inflow commuters are assigned 10 hours to nonresidential development. Based on 2022 functional population data, residential development accounts for 74 percent of the functional population, while nonresidential development accounts for 26 percent.
!"#$%&'()* +,-. I.0 1,2.
34556'7()* +-,+8 ++0 19,.1
:;;(76<=<:&L6'<?6'@(76 A,2+ I.0 +,89
!"%&(&$&(4")* 1.,A. ++0 +,I+
1,<?66<B)"#<C%6<D%%$5E&(4"%
D@6')F6<G66H#)I
J6L(7*6<O'(E%L6@6*4E56"&<OIE6 D@F<GH#I<J6L<
O'(E<M"#%1
O'(E<N)&6<
D#O$%&56"&
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
25
Figure P3: Proportionate Share Factors
Public Safety Space Level of Service and Cost Analysis Section 6-1-960(B)(5) of the South Carolina Development Impact Fee Act requires: “a description of all system improvements and their costs necessitated by and attributable to new development in the service area, based on the approved land use assumptions, to provide a level of service not to exceed the level of service currently existing in the community or service area, unless a different or higher level of service is required by law, court order, or safety consideration.” Section 6-1-960(B)(7) of the South Carolina Development Impact Fee Act requires: “the projected demand for system improvements required by new service units projected over a reasonable period of time not to exceed twenty years.” Public Safety Space – Plan-Based The Town of Summerville plans to construct additional Public Safety space to continue to provide current levels of service to new development. As shown in Figure P5, the Town’s existing inventory includes 47,588 square feet of space. The Town plans on constructing a new Public Safety Complex to accommodate the expansion of the Courts, Police, and Fire Administrative functions. This expansion will increase the overall Public Safety space by 27,273 square feet. Conversations with staff indicate this space should be sufficient to serve businesses and residents of the Town through 2040. When the total square
!"#$%"&'$() !"#$%& '"()*%
'*+H-$.I*% 012345 6*H()7!$8 6*H()
9")I&"%.)J;*.J<*(=I%L ?@251@ ?1 03A2B?1
C#+-*8"&J9")I&"%.) ?32@4B
9")I&"%.)JC#+-*8"&JI%JMH##"(NI--" ?2F0? BA AB23?4
9")I&"%.)JC#+-*8"&J*H.)I&"JMH##"(NI--" ?125?F BA ?F12?1@
9")I&"%.I$-JMHG.*.$- 4@02@0A
!"#$%"&'$()*+,(-" ./0
12&-"#$%"&'$()
9")I&"%.)J;*.J<*(=I%L ?@251@ A B1@24?A
H*G)JI*J$."&JI%JMH##"(NI--" BF24B3
9")I&"%.)JC#+-*8"&JI%JMH##"(NI--" ?2F0? B1 ?F20?1
;*%O9")I&"%.J<*(="()JLM%N-*OJP*##H."()Q B@24@B B1 B@42@B1
;*%(")I&"%.I$-JMHG.*.$- 31A2F0A
12&-"#$%"&'$()*+,(-" 340
R*.$- B2B512@14
M*H(J"SJTUMUJP"%)H)JVH("$H2JP%RX"Y$+J@UBUBJR++-IJ$.I*%J$%&JIC6!JP(ILI%O!").I%$.I*%JC#+-*8#"%.JM.$.I).IJ)U
5"6(&%*7&$'#*$&*3833
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
26
footage is compared to the projected 2040 development base, the planned level of service is 0.8109 square feet per person (74,861 square feet X 74 percent residential share / 68,317 persons). For nonresidential development, the planned level of service is 0.2319 square feet per nonresidential vehicle trip (74,861 square feet X 26 percent nonresidential share / 83,921 nonresidential vehicle trips). Figure P4: Public Safety Space Planned Level of Service in 2040
Figure P4 shows the anticipated cost for the proposed Public Safety Complex, based on the engineered design plans prepared for the Town. The anticipated cost is $54.2 million, which results in a weighted average construction cost of $724 per square foot. Of that cost, $34.4 million is the cost to replace the existing Public Safety (47,588 square feet). The cost attributable to new development and the enhanced level of service is $19.7 million. The Town will issue a bond for the construction of this facility, and this will be the revenue source used to enhance the existing level of service, replace the existing space, as well as fund a small portion of the growth-related costs. A credit for future principal payments is included in the impact fee calculation, which will be discussed in a subsequent section. As shown in Figure P4, the cost per service unit is $1,020.58 per person and $339.76 per nonresidential vehicle trip.
!"#$%F'(%)*+,('%-""$ ./01
0203%)*+,('%-''$ 4/5166
7'$%7'8%)*+,('%-''$ 0/50/9
0242%)*+,('%-''$ /4563:
;<,=='L%)*+,('%-''$ /4563:
?'#@L'=$@,<%)A,(' /4B
0242%;"F+<,$@"= 3659:/
;+C<@D%),N'$F%)*+,('%-''$%F'(%;'(#"= 2G6:2H
7"=('#@L'=$@,<%)A,(' 03B
0242%7"=('#G%I'A@D<'%J(@F# 695H0:
)*+,('%-''$%F'(%I'A@D<'%J(@F 2G09:H
)"+(D'O%J"8=%"N%)+LL'(M@<<'%
7"=('#@L'=$@,<
?'#@L'=$@,<
N'M'<O"NO)'(M@D'%PNQ)R%)$,=L,(L#
!"#$%-,D$"(#
N'M'<O"NO)'(M@D'%PNQ)R%)$,=L,(L#
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
27
Figure P5: Public Safety Space Cost Allocation
Cost to Replace Current Facility $34,452,907 64%
Cost for New Development and Enhanced LOS $19,745,191 36%
$54,198,098 100%
Cost per Square Foot $724
Residential Share 74%
Increase in Population to 2040 14,317
Cost per Person $1,020.58
Nonresidential Share 26%
Increase in Nonres. Trips to 2040 15,110
Cost per Vehicle Trip $339.76
Source: Town of Summerville, based on engineered cost estimates.
Cost Allocation Factors
Nonresidential
Residential
Cost for new
Public Safety %
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
28
Public Safety Principal Payment Credit The Public Safety impact fee includes a credit for existing debt service. Summerville has bond financed the construction of the new Public Safety facility, which will use a combination of impact fees, Tax Increment Finance (TIF) District revenue, and hospitality tax. A credit is necessary since new development will pay the Public Safety impact fee and will also generate tax revenue used to repay debt service. Because the increase is square footage represents 36 percent of the project cost, only 36 percent of the debt principal is credited. As shown in Figure P5, the principal portion of new development’s share of existing debt service equals $27,355,000 over the next 20 years. To allocate the proportionate share of demand to residential and nonresidential development, this analysis uses proportionate share factors shown in Figure P3. Annual principal payments are divided by projected population and vehicle trips in each year to estimate the principal payment per person and vehicle trip. To account for the time value of money, annual principal payments per person and trip are discounted using a net present value formula based on an interest rate of 4.17 percent. The total net present value of future principal payments is $76.77 per person and $21.76 per nonresidential vehicle trip. Figure P5: Public Safety Principal Payment Credit
!"#$%FG(()%F*+,"($"-%F .I#"0I(1"%F +,"($"-%F23(,I#"0I(1"%F +,"($"-%F
4I%, +%56I(1 78%,I -I,*+I,#3( 78%,I -I,*9,"-
:;:< =>?>;@?;;; =A<B?C;; =:<D?AB: @N?B@D =@F>< =>;A?D:C B>?B<< =>FDD
:;A; =>?>N@?;;; =D><?D;; =A>;?A@N @B?B;C =@FAC =>;<?;DD B:?C:A =>F@;
:;A> =>?:A;?;;; =DD:?C;; =A:B?NB: @C?NC; =@F@C =>>@?>:C BA?CNA =>F@N
:;A: =>?:<;?;;; =DND?D;; =ADA?N@N @<?NB> =@FBN =>:;?BDD BD?<>C =>FN>
:;AA =>?A@@?;;; =DCB?C;; =AN;?<B: N;?NC> =@F<@ =>:N?C:C B@?<CB =>FNB
:;AD =>?DA;?;;; =@>D?C;; =AC;?<@: N>?B>> =NF>B =>AA?CDC BB?;BA =>FBD
:;A@ =>?D<@?;;; =@AC?:;; =A<C?:NC N:?BN; =NFA@ =>A<?<A: BC?>BA =>FB<
:;AN =>?@B;?;;; =@N@?:;; =D>C?:DC NA?C:< =NF@@ =>DN?<@: B<?:<; =>FC@
:;AB =>?N@@?;;; =@<@?C;; =DD;?C<: ND?<>< =NFB< =>@D?<;C C;?D:A =>F<A
:;AC =>?BD;?;;; =N:N?D;; =DNA?@AN NN?;A; =BF;: =>N:?CND C>?@B: =:F;;
:;A< =>?C:;?;;; =N@@?:;; =DCD?CDC NB?>NA =BF:: =>B;?A@: C:?BAC =:F;N
:;D; =>?<:;?;;; =N<>?:;; =@>>?DCC NC?A>B =BFD< =>B<?B>: CA?<:> =:F>D
:;D> =:?;:;?;;; =B:B?:;; =@AC?>:C N<?D<A =BFBD =>C<?;B: C@?>:; =:F::
:;D: =:?>:;?;;; =BNA?:;; =@ND?BNC B;?N<: =BF<< =><C?DA: CN?AAB =:FA;
:;DA =:?:A;?;;; =C;:?C;; =@<D?;B: B>?<>@ =CF:N =:;C?B:C CB?@B: =:FAC
:;DD =>?;:@?;;; =AN<?;;; =:BA?;N; BA?>N; =AFBA =<@?<D; CC?C:D =>F;C
:;D@ =>?;B;?;;; =AC@?:;; =:C@?;DC BD?DA; =AFCA =>;;?>@: <;?;<@ =>F>>
:;DN =>?>>@?;;; =D;>?D;; =:<B?;AN B@?B:D =AF<: =>;D?AND <>?ACD =>F>D
!"#$%&'()*++),,, &-)./().,,&()'.()*(' &00,1-' &')+2,)/'. &*01+'
G"#$3)(1*.%1I> DF>BH G"#$3)(1*.%1I> DF>BH
2I1*+,I#I(1*I%F)I&(21(( 2I1*+,I#I(1*I%F)I&'01(2
>J*K(1I,I#1*,%1I*%1*L8"$8*7)66I,M"FFI*8%#*,I$I(1F5*"##)I0*0IN1
+)NF"$*7%OI15*GIN1*7I,M"$I
+3-)F%1"3( 23(,I#"0I(1"%F*
II8"$FI*9,"-#
H*G11,"N)1%NFI*13*
2IL*P,3L18
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
29
Maximum Supportable Public Safety Development Impact Fee Figure P6 shows the maximum supportable Public Safety development impact fee for the Town of Summerville. Development impact fees for Public Safety facilities are assessed on residential and nonresidential development. Public Safety development impact fees are based on persons per housing unit for residential development and vehicle trips per 1,000 square feet for nonresidential development. Differentiating the fee by housing type allows the results to be proportional to the level of demand (persons per housing unit) a residential development will place on the current infrastructure based on level of service standards. For residential development, the total cost per person is multiplied by the household size to calculate the proposed fee. For nonresidential development, the total cost per nonresidential vehicle trip is multiplied by the trips per 1,000 square feet to calculate the proposed fee. The fees represent the highest amount supportable for each type of development, which represents new growth’s fair share of the cost for capital facilities. The Town may adopt fees that are less than the amounts shown. However, a reduction in development impact fee revenue will necessitate an increase in other revenues, a decrease in planned capital expenditures, and/or a decrease in levels of service. Figure P6: Maximum Supportable Public Safety Development Impact Fee
!""#$%F'%("() $%*)#'"+#H"+*%( $%*)#'"+#-+.'
!"#$%F'()*+,-'(.)F+ I01232456 I77849:
!;%<F%.)$'!)-=+<,'L;+?%, @I9:499A @I3049:A
-%)/0 1234567 1476588
9"*.:"()./0#;"<"0%'F"()
(%<B$+'C)=%$- 345: 1=>37? I01606 I586
M"$,%EC)=%$- 0457 17>333 I0187: @IF83A
@%(+"*.:"()./0#;"<"0%'F"()
G<?"H,;%)$ 0462 1AB= I01250 @IF98A
LI==+;F%)$ 03420 14>672 I016FF I01895
J**%F+'O'J,L+;'(+;M%F+ 7483 17>=3A I3165: @I01:00A
G<H,%,",%I<)$ 5475 17>B87 I01883 @I380A
04'(++'N)<?'OH+'PHH"=.,%I<H
;"<"0%'F"()#-C'"
!""*#'"+#D(.)
H"+*%(*#'"+#
N%F*.(G#D(.)7
H+%'%*":
!""*
$F++"()#
!""* ;.HH"+"(I"
!""*#'"+#7>888#JKF/+"#!"")
;"<"0%'F"()#-C'" L<"+/G"#MN:C#
O"P.I0"#-+.'*7
H+%'%*":
!""*
$F++"()#
!""* ;.HH"+"(I"
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
30
Projected Revenue from Public Safety Development Impact Fee Revenue from the Public Safety development impact fee is estimated in Figure P7 if the fee were implemented at the maximum supportable level and growth occurs as projected. Based on the growth projections and at the maximum development impact fee, projected fee revenue equals approximately $18.3 million over the next 14 years compared to projected expenditures of approximately $54.2 million. Figure P7: Projected Revenue from the Public Safety Development Impact Fee
!"#$%FG(F)"*+H-.%-I0G(F)"* 1#%)2
3452-6G()7*%8G(9)6* :;K=>;?=@ABG:>C=KKM=KM@:CN=;AK=MAKG
1#%)2 :;K=>;?=@ABG:>C=KKM=KM@G:CN=;AK=MAKG
(-I02*GF)G-28H42%-IF)G-28 JIO4.%"-)2 L#GG*"6-)2M77-6*GNGM%F*"JI.%-%4%-#I)2
:@=N;B :;=NNN :C?@ :>=K;A :;=@NC :;=?M;
9*"G4I-% 9*"G4I-% 9*"GO(F 9*"GO(F 9*"GO(F 9*"GO(F
P.0GQI-% P.0GQI-% O(F O(F O(F O(F
R).* @M@B ;?=NBM B=@B> ;=AKN >=?BN ;=N>C @=BAC
S*)"G;@M@? ;?=BCB B=C@N @=M;C >=K;K ;=NNA @=?>?
S*)"G@@M@K ;?=KCB B=?AM @=MN? >=K?@ ;=NBN @=?KM
S*)"G>@M@A ;K=MCA ?=MB@ @=M?A >=A@? ;=N?K @=K@N
S*)"GN@M>M ;K=@BB ?=>>K @=;;; >=AK> ;=NA> @=KBK
S*)"GC@M>; ;K=N?K ?=B@M @=;NN N=MNM ;=CMK @=A;N
S*)"GB@M>@ ;K=BA> ?=AM? @=;?? N=MA? ;=C@> @=ABM
S*)"G?@M>> ;K=A;@ K=@MM @=@;; N=;CB ;=C>K >=MMB
S*)"GK@M>N ;A=;>B K=NAK @=@NB N=@;C ;=CC> >=MCN
S*)"GA@M>C ;A=>BN K=KM> @=@K; N=@?C ;=CBA >=;M@
S*)"G;M@M>B ;A=CA? A=;;> @=>;B N=>>C ;=CKN >=;C;
S*)"G;;@M>? ;A=K>N A=N@A @=>C@ N=>A? ;=BMM >=@MM
S*)"G;@@M>K @M=M?C A=?C; @=>KA N=NBM ;=B;B >=@C;
S*)"G;>@M>A @M=>@; ;M=M?A @=N@B N=C@> ;=B>@ >=>M@
S*)"G;N@MNM @M=C?@ ;M=N;N @=NBN N=CK? ;=BNK >=>CN
>=;;@ N=;C; N?A K@> @;> BCA
:?=C;K=N;A :C=AA>=A;A :@?N=>C; :>=;N>=>>M :@BC=BA@ :;=;@;=CKC
3"#T*6%*OGF**GU*V*I4* :;K=>;?=@AB
1#%)2G+H9*IO-%4"*. :CN=;AK=MAK
P#IIJG9)6%GF**G(F)"* :>C=KKM=KM@
@MIS*)"GJI6"*).*
3"#T*6%*OGU*V*I4*
F**GL#G9#I*I%
S*)"
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
31
FIRE DEVELOPMENT IMPACT FEE CALCULATIONS Methodology Section 6-1-920(18f) of the South Carolina Development Impact Fee Act states that a development impact fee may be imposed on public facilities including: “…public safety facilities, including law enforcement, fire, emergency medical and rescue, and street lighting facilities.” The Fire development impact fee includes the following component: • Fire Stations • Fire Apparatus An incremental expansion methodology is applied to the Fire station space and apparatus analysis. Costs are allocated to both residential and nonresidential development using different demand indicators for each type of development. Section 6-1-960(B)(1) of the South Carolina Development Impact Fee Act requires: “a general description of all existing facilities and their existing deficiencies, within the service area or areas of the governmental entity, a reasonable estimate of all costs, and a plan to develop the funding resources, including existing sources of revenues, related to curing existing deficiencies including, but not limited to, the upgrading, updating, improving, expanding, or replacing of these facilities to meet existing needs and usage.” Section 6-1-960(B)(2) of the South Carolina Development Impact Fee Act requires: “an analysis of total capacity, the level of current usage, and commitments for usage of capacity of existing public facilities, which must be prepared by qualified a professional using generally accepted principles and professional standards.” Fire Benefit Area Fire and emergency medical services are provided from multiple stations that include multiple pieces of apparatus. While fire apparatus stationed in fixed locations primarily serves nearby areas, companies often respond to incidents in neighboring response areas as the need arises. Consequently, the entire Town may reasonably be designated as a single benefit area for public safety impact fees Fire Funding Sources Summerville has studied various ways of providing funding for Fire facilities. The sources of revenue for Fire are General Fund revenues, grants or impact fees. In comparing an equitable allocation to the costs borne in the past and to be borne in the future, in comparison to the benefits already received and yet to be received, the Town has determined that impact fees are the most equitable way of financing the growth-related Fire facilities.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
32
Service Units for Fire Section 6-1-960(B)(4) of the South Carolina Development Impact Fee Act requires: “a definitive table establishing the specific service unit for each category of system improvements and an equivalency or conversion table establishing the ratio of a service unit to various types of land uses, including residential, commercial, agricultural, and industrial, as appropriate.” The “service unit” used for residential development is persons per housing unit (PPHU). This is a measure of the average number of persons residing in each housing unit. As shown in Figure F1, there are 2.56 persons per single family unit and 1.53 persons per multifamily unit. Factors are calculated based on data provided by the U.S. Census Bureau’s 2023 ACS 5-year estimates (further discussed in Appendix B). Figure F1: Residential Service Units
TischlerBise recommends using nonresidential vehicle trips as the nonresidential “service unit” for Fire infrastructure. Average weekday vehicle trip ends for nonresidential development are from the 12th edition of the reference book, Trip Generation, published in 2025 by the Institute of Transportation Engineers. A “trip end” represents a vehicle either entering or exiting a development (as if a traffic counter were placed across a driveway). Trip ends for nonresidential development are calculated per thousand square feet. Trip generation rates are used for nonresidential development because vehicle trips are highest for retail/commercial developments, such as shopping centers, and lowest for industrial development. Office and institutional trip rates fall between the other two categories. This ranking of trip rates is consistent with the relative demand for Fire services from nonresidential development. Other possible nonresidential demand indicators, such as employment or floor area, will not accurately reflect the demand for service. For example, if employees per thousand square feet were used as the demand indicator, Fire development fees would be disproportionately high for office and institutional development because offices typically have more employees per 1,000 square feet than retail uses. If floor area were used as the demand indicator, Fire development fees would be disproportionately high for industrial development. For nonresidential land uses, the standard 50 percent adjustment is applied to office and industrial. A lower vehicle trip adjustment factor is used for commercial/retail and institutional because these types of development attracts vehicles as they pass-by on arterial and collector roads. For example, when someone stops at a convenience store on their way home from work, the convenience store is not their primary destination. Further detail on vehicle trip factors can be found in Appendix B.
!"#$%F'()*"%+ H-./
01%2"3()*"%+ 4-.5
4-'!FF'6)#7'89F':991*;2"<#9
=FLF%<;*F#2'?+;F @FA9<#9';FA'
B<19"#$'8#"24
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
33
Figure F2: Nonresidential Service Units
Fire Proportionate Share Factors Both residential and nonresidential developments increase the demand on Fire infrastructure. To calculate the proportional share between residential and nonresidential demand on Fire services and infrastructure, a functional population approach is used. Functional population is like what the U.S. Census Bureau calls "daytime population," by accounting for people living and working in a jurisdiction, but also considers commuting patterns and time spent at home and at nonresidential locations. The functional population approach allocates the cost of the facilities to residential and nonresidential development based on the activity of residents and workers in the Town through the 24 hours in a day. Residents that do not work are assigned 20 hours per day to residential development and 4 hours per day to nonresidential development (annualized averages). Residents that work in Summerville are assigned 14 hours to residential development and 10 hours to nonresidential development. Residents that work outside the Town are assigned 14 hours to residential development, the remaining 10 hours in the day are assumed to be spent outside of the Town working. Inflow commuters are assigned 10 hours to nonresidential development. Based on 2022 functional population data, residential development accounts for 74 percent of the functional population, while nonresidential development accounts for 26 percent.
!"#$%&'()* +,-. I.0 1,2.
34556'7()* +-,+8 ++0 19,.1
:;;(76<=<:&L6'<?6'@(76 A,2+ I.0 +,89
!"%&(&$&(4")* 1.,A. ++0 +,I+
1,<?66<B)"#<C%6<D%%$5E&(4"%
D@6')F6<G66H#)I
J6L(7*6<O'(E%L6@6*4E56"&<OIE6 D@F<GH#I<J6L<
O'(E<M"#%1
O'(E<N)&6<
D#O$%&56"&
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
34
Figure F3: Proportionate Share Factors
Fire Facilities Level of Service and Cost Analysis Fire Station – Incremental Expansion The Town of Summerville plans to construct additional Fire station space to continue to provide current levels of service to new development. As shown in Figure F4 the Town’s existing inventory includes 34,841 square feet of space. Fire Station 1 is not included in this inventory as that square footage has already been accounted for in the Public Safety facilities component of the impact fee. To allocate the proportionate share of demand to residential and nonresidential development, this analysis uses the proportionate share factors outlined in Figure F3. Summerville’s existing level of service for residential development is 0.4775 square feet per person (34,841 square feet X 74 percent residential share / 54,000 persons). For nonresidential development, the existing LOS is 0.1316 square feet per vehicle trip (34,841 square feet X 26 percent nonresidential share / 63,909 vehicle trips). Based on engineered cost information obtained from the National Fire Protection Association, this analysis uses a construction cost estimate of $700 per square foot, which is a conservative estimate given it includes a land component and is less than the cost for the Town’s new Public Safety Complex. For Fire facilities, the cost per service unit is $334.22 per person (0.4775 square feet per person X $700 per square foot) and $92.15 per vehicle trip (0.1316 square feet per vehicle trip X $700 per square foot).
!"#$%"&'$() !"#$%& '"()*%
'*+H-$.I*% 012345 6*H()7!$8 6*H()
9")I&"%.)J;*.J<*(=I%L ?@251@ ?1 03A2B?1
C#+-*8"&J9")I&"%.) ?32@4B
9")I&"%.)JC#+-*8"&JI%JMH##"(NI--" ?2F0? BA AB23?4
9")I&"%.)JC#+-*8"&J*H.)I&"JMH##"(NI--" ?125?F BA ?F12?1@
9")I&"%.I$-JMHG.*.$- 4@02@0A
!"#$%"&'$()*+,(-" ./0
12&-"#$%"&'$()
9")I&"%.)J;*.J<*(=I%L ?@251@ A B1@24?A
H*G)JI*J$."&JI%JMH##"(NI--" BF24B3
9")I&"%.)JC#+-*8"&JI%JMH##"(NI--" ?2F0? B1 ?F20?1
;*%O9")I&"%.J<*(="()JLM%N-*OJP*##H."()Q B@24@B B1 B@42@B1
;*%(")I&"%.I$-JMHG.*.$- 31A2F0A
12&-"#$%"&'$()*+,(-" 340
R*.$- B2B512@14
M*H(J"SJTUMUJP"%)H)JVH("$H2JP%RX"Y$+J@UBUBJR++-IJ$.I*%J$%&JIC6!JP(ILI%O!").I%$.I*%JC#+-*8#"%.JM.$.I).IJ)U
5"6(&%*7&$'#*$&*3833
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
35
Figure F4: Fire Station Level of Service and Cost Allocation Existing Level of Service
Fire Apparatus – Incremental Expansion As indicated in Figure F5, Summerville currently has an inventory of 13 fire apparatus with an estimated value of $22,500,000 which results in a weighted average cost per apparatus of $1,730,769 ($22,500,000 / 13 apparatus). These apparatus costs are based on recent Town purchases and information obtained from inquiries regarding future purchases, as well as information from other Fire Departments in South Carolina. As is the case with fire facilities, the Town plans to purchase additional fire apparatus to serve future development. To allocate the proportionate share of demand to residential and nonresidential development, this analysis uses the proportionate share factors outlined in Figure F3. Summerville’s existing level of service for residential development is 0.0002 units per person (13 units X 74 percent residential share / 54,000 persons). For nonresidential development, the existing LOS is 0.0001 units per vehicle trip (13 units X 26 percent nonresidential share / 63,909 vehicle trips). For Fire facilities, the cost per service unit is $308.33 per person (0.0002 units per person X $1,730,769 per unit) and $91.54 per vehicle trip (0.0001 unit per vehicle trip X $1,730,769 per unit).
!"#$%F'(F)* +,-.%"/0""(
+(.(F)*/1 23245
+(.(F)*/5 63477
+(.(F)*/8 93294
+(.(F)*/2 9329:
+(.(F)*/9 :31;;
!"#$% &'()'*
<)#(/'"%/+,-.%"/0))( =677
L?F#(F*@/+,-.%"/0""( 583:8;
A"#FB"*(F.C/+D.%" 68N
1719/F)'-C.(F)* 283777
+,-.%"/0""(/'"%/F"%#)* 7G8662
+",#-./0-1/0,"2 3&&'455
H)*%"#FB"*(F.C/+D.%" 19N
1719/I"DF$C"/J%F'# 9:3:;;
+,-.%"/0""(/'"%/H)*%"#G/I"DF$C"/J%F' 7G;5;9
+",#-./0-6/789%/-!08. 3:54*;
+)-%$"O/+-LL"%MFCC"/0F%"/!"'.%(L"*(
<)#(/NCC)$.(F)*/0.$()%#
O"M"CP)QP+"%MF$"/ROS+T/+(.*B.%B#
A"#FB"*(F.C
H)*%"#FB"*(F.C
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
36
Figure F5: Fire Apparatus Level of Service and Cost Allocation Existing Level of Service
!"#$%F'(F)* +),*( +)#(-."%-/*F( 0)(12-+)#(
3*4F*" 56 758966866675986668666
:"%F12 ; 7<89668666 7=89668666
!"#$% &' (&)*'+)*,-(..)/++)+++
0)(12-L"?F$2"# 5;
0)(12-+)#( 7<<89668666
0"1#2345264789%4 (&)*'+)*,-
3@F#(F*4-L"?F$2"# 5;
A"#FB"*(F12-C?1%" =DN
<6<F-.)',21(F)* 9D8666
L"?F$2"#-'"%-."%#)* 6G666<
0"1#23452:451"; ('+<=''
H)*%"#FB"*(F12-C?1%" <FN
<6<F-L"?F$2"-0%F'# F;8I6I
L"?F$2"#-'"%-L"?F$2"-0%F' 6G6665
0"1#2345264789%42!583 (-&=/>
C),%$"J-C,OO"%LF22"-MF%"-!"'1%(O"*(
+)#(-:22)$1(F)*-M1$()%#
H)*%"#FB"*(F12
N"L"2O)POC"%LF$"-QNRCS-C(1*B1%B#
A"#FB"*(F12
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
37
Projection of Fire Growth-Related Infrastructure Needs Section 6-1-960(B)(5) of the South Carolina Development Impact Fee Act requires: “a description of all system improvements and their costs necessitated by and attributable to new development in the service area, based on the approved land use assumptions, to provide a level of service not to exceed the level of service currently existing in the community or service area, unless a different or higher level of service is required by law, court order, or safety consideration.” Section 6-1-960(B)(7) of the South Carolina Development Impact Fee Act requires: “the projected demand for system improvements required by new service units projected over a reasonable period of time not to exceed twenty years.” Fire Station Space Figure F6 projects the growth-related demand for Fire space over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands approximately 4,693 square feet of space (9,829 additional persons X 0.4775 square feet per person). With projected nonresidential vehicle trip growth of 9,650 vehicle trips, future nonresidential development demands approximately 1,380 square feet of space (9,650 additional vehicle trips X 0.1316 square feet per vehicle trip). The total cost of growth-related space is $4,250,770 (6,073 square feet X $700 per square foot). Figure F6: Projected Demand for Fire Stations
!"#$%FG(%)* +,-*G."IG01G2*
345667018$I"G2""* ."IG9"I-,%
34:;:<018$I"G2""* ."IG="L)?@"GAI).
B"-)F"%*)$@ C,%I"-)F"%*)$@ A,*$@
D3D< 75N333 <FNF:: D7N6FD GN37G ;5NF5:
D3D6 75NG3: <GN6GD D<ND:D GN:FF ;7N533
D3DF 77NF:G 63N6FF D<N<7: GN;:G ;7NG63
D3DG 7<N675 6:N6GG D6N3G6 GN57D ;<N75G
D3;3 76N63F 6DNFD; D6N77; GN7F6 ;6N:53
D3;: 7FN<F3 6;NF<; DFN3:6 GN6D5 ;6N65:
D3;D 7GN<6: 65NG:F DFN5G3 GNF<; ;FN;7;
D3;; <3N<F: 67NGF6 DFNG6D :3N33; ;FNG6<
D3;5 <:N6:: 66N36; DGN5<5 :3N:5< ;GN<:3
D3;7 <DN6<3 6FN:6; DGNG<7 :3NDG: 53ND7<
D3;< <;NFDG 6GNDG3 ;3N567 :3N5;F 53NG:5
!"#$%&'()%*+,* -.I0- !".12- 1.3-4 !.4I" 3."24
H;NDF7N3<7G HG<7N635G H5ND73N663G
!"#$%FGI,IG2)I"G0*$*),%-
AJ."G,IGK%II$-*I8?*8I" L"M"@G,IG0"IM)?"
2)I"G0*$*),%- H633
N"$I 9,.8@$*),% C,%I"-)F"%*)$@G
="L)?@"GAI).-
2)I"G0*$*),%G018$I"G2""*
OI,P*LQB"@$*"FGRS."%F)*8I"-
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
38
Fire Apparatus Figure F7 projects the growth-related demand for Fire apparatus over the next 10 years. Based on a projected population increase of 9,829 persons, future residential development demands approximately 1.8 units of apparatus (9,829 additional persons X 0.0002 units per person). With projected nonresidential vehicle trip growth of 9,650 vehicle trips, future nonresidential development demands approximately 0.5 units of apparatus (9,650 additional vehicle trips X 0.0001 units per vehicle trip). The total cost of growth-related apparatus is approximately $3.9 million (2.3 units X $1,730,769 per unit). Figure F7: Projected Demand for Fire Apparatus
!"#$%FG(%)* +,-*G."IG(%)*
0100023"4)56"- ."IG7"I-,%
0100083"4)56"- ."IG3"4)56"G9I).
:"-)F"%*)$6 ;,%I"-)F"%*)$6 9,*$6
202< =L?000 <@?A0A A1< @1L 8@10
202B =L?A08 <L?C8L A1C @1L 8@12
202C ==?C8A <=?B@8 A1A @1= 8@1L
202A =<?B=L <<?<<2 8018 @1= 8@1<
20@0 =B?B0C <B?<0< 801@ @1< 8@1A
20@8 =C?<C0 <C?=<@ 801= @1< 8L18
20@2 =A?<B8 <A?=@L 801< @1B 8L1@
20@@ <0?<C8 B0?=8A 801C @1B 8L1=
20@L <8?B88 B8?=8C 8810 @1C 8L1C
20@= <2?B<0 B2?=@2 8812 @1C 8=10
20@< <@?C2A B@?==A 881L @1A 8=1@
!"#$%&'()%*+,* -.I0- -.12" !3I "32 034
D@?0@0?<<=G DCC@?@2CG D@?A8@?AA@GNI,F*4G:"6$*"FGHI."%F)*JI"-
K"$I 7,.J6$*),% ;,%I"-)F"%*)$6G
3"4)56"G9I).-
3"4)56"-
9L."G,MGN%MI$-*IJ5*JI" O"P"6G,MGQ"IP)5"
R)I"GS..$I$*J- D8?B@0?B<A
!"#$%FGM,IGR)I"GS..$I$*J-
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
39
Fire Debt Credit The Fire impact fee includes a credit for existing debt service. Summerville has bond financed recent fire apparatus purchases. A credit is necessary since new development will pay the Fire impact fee and will also generate property tax revenue used to repay existing debt service. As shown in Figure F8, the principal portion of existing debt service equals $502,473 over the next 5 years. To allocate the proportionate share of demand to residential and nonresidential development, this analysis uses proportionate share factors shown in Figure F3. Annual principal payments are divided by projected population and vehicle trips in each year to estimate the principal payment per person and vehicle trip. To account for the time value of money, annual principal payments per person and trip are discounted using a net present value formula based on an interest rate of 2.00 percent. The total net present value of future principal payments is $6.16 per person and $1.84 per vehicle trip. Figure F8: Fire Debt Credit
!"#$%F'(()%F*+,"($"-%F.I#"0I(1"%F +,"($"-%F23(,I#"0I(1"%F +,"($"-%F
4I%, +%56I(1 78%,I -I,*+I,#3( 78%,I -I,*9,"-
:;:< =>;?:@< =AB?C<; AD?;;; =@N@; =:;?>A< <C?B;B =;NCC
:;:F =>@?AB< =<;?C>@ AD?B;@ =@N@; =:@?:@A <D?>@D =;NCC
:;:> =>:?BBB =<@?D@B AA?>@B =@N@; =:@?A>; <A?FC@ =;NCC
:;:B =>D?D:F =<:?DF< A<?FAD =@N@; =:@?BA@ <<?<<: =;NCC
:;C; =>A?>FB =<C?AA; AF?F;> =@N@; =::?C:B <F?<;< =;NCC
:;C@ =>F?CA< =<D?<DC A>?<>; =@N@; =::?F@C <>?A<C =;NCC
931%F =A;:?DFC =CF@?>C; !"#"$ =@C;?<DC !%#&'
G"#$3)(1*.%1I@ :N;;H G"#$3)(1*.%1I@ :N;;H
2I1*+,I#I(1*I%F)I !"#%" 2I1*+,I#I(1*I%F)I !%#()
@J*K(1I,I#1*,%1I*%1*L8"$8*7)66I,M"FFI*8%#*,I$I(1F5*"##)I0*0IN1
!",I*GIN1*7I,M"$I
+3-)F%1"3( 23(,I#"0I(1"%F*
II8"$FI*9,"-#
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
40
Maximum Supportable Fire Development Impact Fee Figure F9 shows the maximum supportable Fire development impact fee for the Town of Summerville. Development impact fees for Fire facilities are assessed on residential and nonresidential development. Fire development impact fees are based on persons per housing unit for residential development and vehicle trips per 1,000 square feet for nonresidential development. Differentiating the fee by housing type allows the results to be proportional to the level of demand (persons per housing unit) a residential development will place on the current infrastructure based on level of service standards. For residential development, the total cost per person is multiplied by the household size to calculate the proposed fee. For nonresidential development, the total cost per vehicle trip is multiplied by the trips per 1,000 square feet to calculate the proposed fee. The fees represent the highest amount supportable for each type of development, which represents new growth’s fair share of the cost for capital facilities. The Town may adopt fees that are less than the amounts shown. However, a reduction in development impact fee revenue will necessitate an increase in other revenues, a decrease in planned capital expenditures, and/or a decrease in levels of service. Figure F9: Maximum Supportable Fire Development Impact Fee
!""#$%F'%("() $%*)#'"+#H"+*%( $%*)#'"+#-+.'
!"#$%F'('")*+ ,--.I00 ,10I23
!"#$%455(#('6+ ,-78I-- ,83I70
!"#$%9$:'%;#$<"' =,LI2L? =,2I@2?
-%)/0 1232435 1678492
:"*.;"()./0#<"="0%'F"()
F"*AB$%!(C"BM 0I3L 16>2?5 ,830 ,@@@
E6B'"F!(C"BM 2I3- 1579 ,17@ ,L@
@%(+"*.;"()./0#<"="0%'F"()
G*<6+'#"(B 2I87 1362 ,@1L =,.87?
;)CC$#H"(B 20I72 1?>6A7 ,2I783 ,2I700
JOO"H$%L%J'M$#%F$#N"H$ -I10 12B7 ,2I@23 =,2I708?
G*+'"'6'")*(B 3I-3 1535 ,2I327 =,3@2?
2I%F$$%O(*<%P+$%4++6C5'")*+
<"="0%'F"()#-C'" H"+*%(*#'"+#
D%N*.(F#G(.)6
H+%'%*";
!""*
$N++"()#
!""*
<"="0%'F"()#-C'" H="+/F"#IJ;C#
K"L.M0"#-+.'*6
H+%'%*";
!""*
<.NN"+"(M"
!""*#'"+#G(.)
$N++"()#
!""* <.NN"+"(M"
!""*#'"+#6>AAA#OPN/+"#!"")
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
41
Projected Revenue from Fire Development Impact Fee Revenue from the Fire development impact fee is estimated in Figure F10 if the fee were implemented at the maximum supportable level and growth occurs as projected. Based on the growth projections and at the maximum development impact fee, projected fee revenue equals $8 million over the next ten years compared to projected expenditures of $8.1 million. Figure F10: Projected Revenue from the Fire Development Impact Fee
!"#$%FG(F)"*+H-.%-I0G(F)"*1#%)2
3-"*G(%)%-#I. 4567896::9G 494567896::9G
3-"*G;KK)")%=. 4>6?7@68A>G 494>6?7@68A>G
1#%)2 4A6@:76>8>G 49G4A6@:76>8>G
(-I02*G3)B-2CM=2%-E3)B-2C FIG=.%"-)2 H#BB*"I-)2 JOO-I*GLGFI.%-%=%-#I)2
4@6M7? 4?:5 4>@M 476@9: 4MA: 4?>?
K*"G=I-% K*"G=I-% K*"GN(3 K*"GN(3 K*"GN(3 K*"GN(3
O.0GPI-% O.0GPI-% N(3 N(3 N(3 N(3
Q).* 797M @:65M9 M67M> @6?A5 >6:M5 @65>8 76M?8
R*)"G@ 797: @:6M8M M6875 769@8 >6A@A @655? 76:>:
R*)"G7 797A @:6A8M M6:?9 7695: >6A:7 @65M5 76:A9
R*)"G> 797? @A698? :69M7 769:? >6?7: @65:A 76A75
R*)"G5 79>9 @A67MM :6>>A 76@@@ >6?A> @65?> 76AMA
R*)"G8 79>@ @A65:A :6M79 76@55 56959 @689A 76?@5
R*)"GM 79>7 @A6M?> :6?9: 76@:: 569?: @687> 76?M9
R*)"G: 79>> @A6?@7 A6799 767@@ 56@8M @68>A >699M
R*)"GA 79>5 @?6@>M A65?A 7675M 567@8 @688> >6985
R*)"G? 79>8 @?6>M5 A6A9> 767A@ 567:8 @68M? >6@97
R*)"G@979>M @?68?: ?6@@> 76>@M 56>>8 @68A5 >6@8@
76@>M 76A89 >>7 8:@ @5? 58M
4>65A96588 476::56:7: 4@956:>5 4@679>6>5?4@976M@A 457A6997
4A69?>6AA8
4A6@:76>8>
3**GH#BK#I*I%
R*)"
@9ER*)"GFII"*).*
S"#T*I%*GGU*V*I=*
S"#T*I%*GG3**GU*V*I=*
1#%)2G+HK*IG-%="*.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
42
CAPITAL IMPROVEMENT PLAN Section 6-1-930(A) of the South Carolina Development Impact Fee Act requires: “If a governmental entity has not adopted a comprehensive plan, but has adopted a capital improvements plan which substantially complies with the requirements of Section 6-1-960(B), then it may impose a development impact fee.” Section 6-1-960(B5) of the South Carolina Development Impact Fee Act requires: “a description of all system improvements and their costs necessitated by and attributable to new development in the service area, based on the approved land use assumptions, to provide a level of service not to exceed the level of service currently existing in the community or service area, unless a different or higher level of service is required by law, court order, or safety consideration.” Along with the impact fee analysis, this report represents the Town of Summerville’s Capital Improvement Plan. The Plan includes a list of 10-year growth-related capital facility needs for Parks and Recreation, Public Safety, and Fire. The 10-year facility needs list represents the additional capital improvements necessary to accommodate the projected growth at the levels of service established in the impact fee analysis. Further details about the levels of service and calculations can be found in their respective chapters. To respond to demand for Parks and Recreation facilities, the Town of Summerville plans to incrementally construct new park land, improvements, facilities, trails, and purchase additional vehicles. Figure CIP1 contains a list of impact fee eligible Parks and Recreation CIP projects the Town anticipates applying impact fee revenue for in the future. All these items provide Townwide benefit. Figure CIP1: Parks and Recreation Capital Improvement Plan
Project Estimated YearImpact Fee Eligible Cost
Skatepark 2027 $650,000
Gahagan Disc Golf Course 2027 $25,000
Azalea Park Community Building 2027 $1,500,000
Park Signage 2028-2031 $60,000
Summerville Preserve Education Center,
Ampitheater, & Amenities 2028 $4,000,000
Lift 2028 $130,000
Bucket Truck 2028 $125,000
Azalea Park Children's Garden Expansion 2028 $30,000
Sawmill Branch Trail paving & Ligthing 2029-2031 $3,000,000
Small Engine Shop Expansion 2029 TBD
Wassamassaw Court Lights 2029 $65,000
Azalea Park Children's Garden Expansion 2029 $30,000
Nexton office/Maintenance Building 2029 $350,000
Sports Complex 2029 $80,000,000
Gahagan Splash Pad 2030 $150,000
Bobcat 2031 $100,000
Total $90,215,000
Source: Summerville Parks and Recreation Department
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
43
To respond to demand for Public Safety facilities, the Town of Summerville is in the process of expanding their Public Safety facilities. Shown below in Figure CIP2 is the list of Public Safety impact fee eligible projects the Town anticipates in the future. All these items provide Townwide benefit. Figure CIP2: Public Safety Capital Improvement Plan
To respond to demand for Fire facilities, the Town of Summerville plans to incrementally construct new Fire facilities and purchase apparatus. Shown below in Figure CIP3 is the list of impact fee eligible CIP projects the Fire Department anticipates in the future. All these items provide Townwide benefit. Figure CIP3: Fire Capital Improvement Plan
!"#$%F' ()'*+,'%-.I%," 0+1,F'.2%%.(3*4*53%.
6#)'
!753*F.8,9%':.2,F*3*': ;<;= >?@AB?CA;D=
!"#$% &'()*'+),-.
8#7"F%E.F#GH.#9.87++%"I*33%
!"#$%F' ()'*+,'%-.I%," 0+1,F'.2%%.(3*4*53%.
6#)'
7%)F8%.9"8F: ;<;=>;<;? @ABC<<B<<<
D','*#E.? ;<;?>;<;C @FB<<<B<<<
(E4*E%.G<? ;<;?>;<;C @ABF<<B<<<
!"#$% &'()**(***
D#8"F%H.D8++%"I*33%.2*"%.J%1,"'+%E'
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
44
IMPLEMENTATION AND ADMINISTRATION Development impact fees should be periodically evaluated and updated to reflect recent data. TischlerBise recommends that the Town of Summerville adjust for inflation. If cost estimates or demand indicators change significantly, the Town should redo the fee calculations. Credits and Reimbursements A general requirement that is common to development impact fee methodologies is the evaluation of credits. A revenue credit may be necessary to avoid potential double payment situations arising from one-time development impact fees plus on-going payment of other revenues that may also fund growth-related capital improvements. The determination of revenue credits is dependent upon the development impact fee methodology used in the cost analysis and local government policies. Policies and procedures related to site-specific credits should be addressed in the resolution or ordinance that establishes the development impact fees. Project-level improvements, required as part of the development approval process, are not eligible for credits against development impact fees. If a developer constructs a system improvement included in the fee calculations, it will be necessary to either reimburse the developer or provide a credit against the fees due from that development. Service Area A development impact fee service area is a region in which a defined set of improvements provide benefit to an identifiable amount of new development. Within a service area, all new development of a type (single family, retail, etc.) is assessed at the same development impact fee rate. Land use assumptions and development impact fees are each defined in terms of this geography, so that capital facility demand, projects needed to meet that demand, and capital facility cost are all quantified in the same terms. Development impact fee revenue collected within a service area is required to be spent within that service area. Implementation of a large number of small service areas is problematic. Administration is complicated and, because funds collected within the service area must be spent within that area multiple service areas may make it impossible to accumulate sufficient revenue to fund any projects within the time allowed. As part of our analysis, the Parks and Recreation, Public Safety, Fire and Stormwater Impact Fees were determined to have one Townwide service area.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
45
APPENDIX A: HOUSING AFFORDABILITY ANALYSIS Section 6-1-930(2) of the South Carolina Development Impact Fee Act requires: “Before imposing a development impact fee on residential units, a governmental entity shall prepare a report which estimates the effect of recovering capital costs through impact fees on the availability of affordable housing within the political jurisdiction of the governmental entity.” In accordance with South Carolina Development Impact Fee Act, this chapter estimates the effects of imposing the maximum supportable development impact fees on the affordability of housing in Summerville. The analysis will examine the current housing expenses that burden an average household in the Town. Next, the maximum supportable development impact fee will be included in the cost burden analysis to identify the effect the proposed development impact fees will have on affordable housing. Maximum Supportable Development Impact Fee The development impact fees found in Figure A1 represent the highest amount supportable for housing units by housing type, which represents new growth’s fair share of the cost for capital facilities. The Town may adopt fees that are less than the amounts shown. However, a reduction in development impact fee revenue will necessitate an increase in other revenues, a decrease in planned capital expenditures, and/or a decrease in levels of service. The housing affordability analysis will assume a conservative condition for assessing the effect of the development impact fee on monthly mortgages in Summerville (i.e., the maximum supportable development impact fee amount). If the Town were to choose a lower development impact fee amount, the results presented in this section of the report would improve. Figure A1. Maximum Supportable Development Impact Fee
Impact on Monthly Mortgage The South Carolina Development Impact Fee Act requires preparation of a report that estimates the effect of imposing development impact fees on housing affordability in the jurisdiction. As shown in Figure A2, TischlerBise calculated the effect of the maximum allowable development impact fee on a monthly mortgage at different interest rates. For example, the proposed single-family development impact fee of $7,700 increases a mortgage with an interest rate of 2.5 percent by $30.42 per month, or 0.39%. For a mortgage with an interest rate of 8.0 percent, the cost is $56.50 per month, or 0.73%. Figure A2. Monthly Payment Sensitivity Analysis for a Single Family Unit
!"#$%"F'$()*+",")-./"F'
!"#$%F'()*"%+ ,-./01 ,2.13/ ,3./24 012133
56%7"8()*"%+ ,2.391 ,3.111 ,4:1 042536
7""#*8"9*:F$'
;-'()+",")-./"F'*;<." 8=>)$?*@(A"'< 7$9"8(9B#
!"#$%C'(F*"%+,-#".!/C#FM"1,2!/C#FM"1,P!/C#FM"1,4!/C#FM"1,5!/C#FM"1,S!/C#FM"1,7!/C#FM"1,U
!"#A%&%'(FF*+"IF-'.--LM1M22 LM1M22 LM1M22 LM1M22 LM1M22 LM1M22 LM1M22
3*"4'R-6%'T8-"69: ;2 ;2 ;2 ;2 ;2 ;2 ;2
Y4=-6-9='>"=-'T(44&"F: ?@A2B ;@22B C@22B A@22B a@22B M@22B b@22B
91#.:%+,;1<. =4>?5P =4P?57 =47?U7 =52?44 =57?27 =S2?P4 =S7?S>
91#.:%+,@F+*C#.,;F%/A%F."1#
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
46
Determining the effect of the impact fee amounts on multifamily rental rates is a little more difficult to determine. However, it is important to note that the multifamily impact fee amount is $95 less than the current impact fee amount. According to CoStar data, the average rent in Summerville is $1,692. Assuming 100% of the existing Town multifamily impact fee is passed on to the renter, the rent would decrease by almost 6%. Therefore, TischlerBise concludes the proposed impact fee amounts contained in the study will have a negligible effect on the availability of affordable housing in the Town of Summerville.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
47
APPENDIX B: LAND USE ASSUMPTIONS Section 6-1-960(B)(3) of the South Carolina Development Impact Fee Act requires: “a description of the land use assumptions.” Summary of Growth Indicators Key land use assumptions for the Summerville Impact Fee Study are population, housing units, employment, and nonresidential floor area. Based on Esri Business Analyst projections, TischlerBise projects Summerville to add approximately 499 housing units per year. For population, TischlerBise applies person per housing unit factors derived from American Community Survey 2019-2023 5-Year Estimates to housing unit projections. For nonresidential floor area, TischlerBise projects growth to be approximately 151,000 square feet per year using CoStar market analytics, information from Town staff, and projected population growth. These floor area projections are converted to jobs using employment density factors published in Trip Generation, Institute of Transportation Engineers, 12th Edition (2025). Complete development projections are summarized in Figure B10. These projections will be used to estimate impact fee revenue and to indicate the anticipated need for growth-related infrastructure. However, impact fee methodologies are designed to reduce sensitivity to development projections in the determination of the proportionate share fee amounts. If actual development is slower than projected, fee revenue will decline, but so will the need for growth-related infrastructure. In contrast, if development occurs faster than anticipated, fee revenue will increase, but Summerville will need to accelerate infrastructure improvements to keep pace with the actual rate of development. Over the next 10 years, development projections indicate an average increase of approximately 499 housing units per year and approximately 151,000 square feet of nonresidential development per year.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
48
Residential Development This section details current estimates and future projections of residential development including population and housing units. Housing Unit Size According to the U.S. Census Bureau, a household is a housing unit occupied by year-round residents. Impact fees often use per capita standards and persons per housing unit (PPHU) or persons per household (PPH) to derive proportionate share fee amounts. When PPHU is used in the fee calculations, infrastructure standards are derived using year-round population. When PPH is used in the fee calculations, the impact fee methodology assumes a higher percentage of housing units will be occupied, thus requiring seasonal or peak population to be used when deriving infrastructure standards. TischlerBise recommends Summerville impose impact fees for residential development according to the number of persons per housing unit. Occupancy calculations require data on population and the types of units by structure. The 2010 census did not obtain detailed information using a “long-form” questionnaire. Instead, the U.S. Census Bureau switched to a continuous monthly mailing of surveys, known as the American Community Survey (ACS), which has limitations due to sample-size constraints. For example, data on detached housing units are now combined with attached single units (commonly known as townhouses, which share a common sidewall, but are constructed on an individual parcel of land). For impact fees in Summerville, detached, stick-built units, attached units, and mobile homes are included in the “Single-Family” category. The “Multi-Family” category includes duplexes, structures with two or more units on an individual parcel of land, boats, RVs, and vans. Figure B1 shows the occupancy estimates for Summerville. Single-family units average 2.56 persons per housing unit and multi-family units average 1.53 persons per housing unit. Figure B1: Persons per Housing Unit
!"#$%F'()*"%+H-#".I0 102345HH 062445HHHHHHHHH 7850 052990HH !"#$ 3985: 780;:
<=%."'()*"%+H-#".I7
>2455HHHH 12566HHHHHHHHHHH 0849 62>5>HHHH %"#& 7581:7;83;:
?@.)% 6;2357HH 7;2560HHHHHHHHH 7815 772044HH !"!' 0;;8;: 38;;:
!@=ABFCH-8!8HMF#I=IHE=AF)=2H7;04'7;79HF*FA"B)#HM@**=#".+H!=AGF+H6'HF)AHII."*).FI
08HJ#B%=KFIHKF.)BLFK2H)..)BLFKHM"8F8H.@N#L@=IFIO2H)#KH*@P"%FHL@*FH=#".I8
78HJ#B%=KFIHKNF%%"#$IH"#HI.A=B.=AFIHN".LH.N@H@AH*@AFH=#".I8
Q@=I"#$
<"R
S)B)#B+H
T).FQ@=I"#$H?+UF VFAI@#IQ@=IFL@%KIVFAI@#IHUFAH
Q@=IFL@%K
Q@=I"#$H
-#".I
VFAI@#IHUFAH
Q@=I"#$H-#".
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
49
Residential Estimates For 2025, Esri business analyst estimates indicate that there are 53,677 persons living in 23,441 housing units Townwide. Housing units are allocated between Single and Multifamily based on the housing unit mix shown in Figure B1. In order to develop an estimate for the 2026 base year the Esri population and housing unit growth between 2020 and 2025 was first calculated. These growth rates were then applied to the 2025 population and housing unit estimates. Summerville’s 2026 residential development base includes 54,000 persons living in 23,723 housing units. Figure B2: Residential Estimates
Residential Projections Population and housing unit projections are used to illustrate the possible future pace of service demands, revenues, and expenditures. To the extent these factors change, the projected need for infrastructure will also change. If development occurs at a more rapid rate than projected, the demand for infrastructure will increase at a corresponding rate. If development occurs at a slower rate than is projected, the demand for infrastructure will also decrease. In order to project housing unit growth this analysis uses a growth rate calculated from Esri Business analyst housing unit projections from 2025-2030. Based on these projections, Summerville can expect 4,986 additional housing units over the next 10 years. Information on approved developments provided by town staff indicates that 43% of future housing units are anticipated to be single family, and 57% will be multifamily. For this study, the analysis assumes the occupancy factors shown in Figure B1 will remain constant. Converting projected housing units to population, based on the PPHU factors in Figure B1, results in a 10-year population increase of 9,829 persons. Figure B3: Residential Projections
!"!" !"!# !"!$
%F'()*(F+
!"#$%&'(") *+H-.+ */H.00 *1H---
2"$3()456)('3
,-./0()1F2-03 4$5!46 475!#8 4756$"
9:0;-<1F2-03 #5=4$ $54== $5!$8
7"'&% ++H-/- +/H118 +/H0+/
9$::;<=(%%;H59>
!"!# !"!$ !"!% !"!F !"'" !"'( !"'#
)*+,-.,*I ( ! ' 0 1 ("
!"#$%&'(") *+H--- *+H.-/ **H0/. *1H2*+ *2H2-0 *0H10- 13H04. .H04.
5"$6()789)('6
23456,-7*8369 ($:0#" ($:#1# ($:%1# (%:"1F (%:!## (%:0$% (F:1F$ 4H/31
;<6=3>7*8369 #:!#' #:1!0 #:$F" $:"#! $:''% $:#!" F:((' 4H0*-
:"'&% 43H243 4+H/0- 4+H1+1 4*H/4- 4*H1-+ 41H-.2 40H2-. +H.01
(">.,*I-
?4@I,*+,;$<<=>?(%%=H8;@
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
50
Nonresidential Development This section details current estimates and future projections of nonresidential development including jobs and nonresidential floor area. Nonresidential Demand Units In Figure B4, gray shading indicates the nonresidential development prototypes used by TischlerBise to derive employment densities and average weekday vehicle trip ends. For nonresidential development, TischlerBise uses data published in Trip Generation, Institute of Transportation Engineers, 12th Edition (2025). The prototype for industrial development is Light Industrial (ITE 110) which generates 3.60 average weekday vehicle trip ends per 1,000 square feet of floor area and has 1,117 square feet of floor area per employee. Institutional development uses Hospital (ITE 610) and generates 10.70 average weekday vehicle trip ends per 1,000 square feet of floor area and has 334 square feet of floor area per employee. For office & other services development, the proxy is General Office (ITE 710); it generates 7.83 average weekday vehicle trip ends per 1,000 square feet of floor area and has 439 square feet of floor area per employee. The prototype for commercial development is Shopping Center (ITE 820) which generates 36.39 average weekday vehicle trips per 1,000 square feet of floor area and has 479 square feet of floor area per employee. Figure B4: Nonresidential Demand Units
!"# $%FG()*+,-.I)0-"123-#()4*+,-.I)0-"123-#()4#F3560%%4-7%189:G1%-;%%<
=6)% L(2< 7%1-$%FG()-L(2<? 7%1-#F3560%%? $%FG()-L(2<7%1-#F3560%%
!!"#$%FG()*+H-G.$I0 !1"""(23(4G 567" 86"9 "6:" !1!!;
!5")*+H-G.$I0(<I.= !1"""(23(4G 967L 56:5 "67L !1877
!8"?I*H@IAGH.$*% !1"""(23(4G 869; 967; !67" 79B
!B"CI.MFNH-$*% !1"""(23(4G !65L B6"B "69; 517B:
9B8F--$-GM+(#$G$*% !1"""(23(4G 86!: 8698 "6:: !1"!9
59"?NGM0 .NNH 565B 9B6!; "6!5 IJF
B7BOIL(MI.M !1"""(23(4G 5:65" !:65" 96"8 8:!
7!"NN-O$GI0 !1"""(23(4G !"6;" 56B; 56"" 558
79"IH.-$*%(NNHM PM+ 56"7 565! "6:9 IJF
;!"QM*M.I0(R@@$AM(SIG%(-$TMU!1"""(23(4G ;6L5 5688 969L 85:
;9"?M+$AI0VOM*GI0(R@@$AM!1"""(23(4G 586"5 !!6;L 96L: 587
;5"QNGM.*HM*G(R@@$AM !1"""(23(4G 996B: ;68B 56"5 55"
;;"PH-$*M--(<I.= !1"""(23(4G :6:; B689 !6L8 B88
L9"2FNOO$*%(MM*GM.(SIG%(-$TMU!1"""(23(4G 5765: !;689 96": 8;:
!6(X.$O(QM*M.IG$N*1()*-G$GHGM(N@(X.I*-ON.GIG$N*(Y*%$*MM.-1(!9GF(Y+$G$N*(S9"9BU6
@G()-L4%-A16:3
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
51
Nonresidential Estimates TischlerBise uses the term jobs to refer to employment by place of work. Shown below in Figure B5, Esri Business Analyst estimates employment equal to 19,912 jobs. According to public record data from CoStar there is 9.88 million square feet of nonresidential floor area in Summerville. Figure B5: Nonresidential Estimates
Nonresidential Projections To project industrial, commercial, and office floor area this analysis uses construction forecasts from CoStar analytics for Summerville, which is adjusted according to information on approved developments provided by Town staff. Due to the nature of institutional development, it is assumed that floor area growth will mirror population growth. Floor area was then converted to employment using square feet per employment factors from ITE. The 10-year projected increase includes approximately 1,508,000 additional square feet of nonresidential development and 3,195 additional jobs. Figure B6: Nonresidential Projections
!"!# $%F'%()*+, !"!#*-.)I01)%2 $%F'%()*+,
3+4.5 6+)17*3+4. 87++F*9F%1! 6+)17*87++F*9F%1
J(2;.)FI17 !"#$% <= !"%&'"'() !"=
>+00%F'I17 ("(*) ??= $")('"$'( ?<=
@,,I'%*A*@)B%F*C%FDI'% #"#(* !<= !"'$'"%'& 5N=
J(.)I);)I+(17 ("+*( ?5= +"(%'"#(% !F=
6+)17 !%"%!+ 5""= %"&)&"$$* 5""=
5G*-.FI*H;.I(%..*9(17I.)*@(7I(%J*H;.I(%..*C;001FIJ*!"!NG
!G*>+C)1F*$;47I'*O%'+F2*L1)1G
M+(F%.I2%()I17
>1)%N+FI
!"!# !"!$ !"!% !"!& !"'" !"'( !"'#
)*+,-.,*I ( ! ' 0 1 ("
!"#$%F"'()
2345+6I7*8 (91'& (91#$ (91&1 (9#!' (9#1! (9#%! (9%'# *+,
:;<<,I=7*8 #9#"$ #9$(& #9%'! #9&0$ $9"#0 $9(%! $9$&& -.-+*
>??7=,-@->6A,I-B,IC7=,+ 191#" 191&' 19#!1 19#1& 19#&! 19$!# 19&"" /01
23+676567;3*8 #9!"# #9''' #90#! #91&' #9$!$ #9%#! $91$( -./23
4%)5$ -+.+-* *1.*-- *1.3-3*1.6***-.-/3*-.03**/.-1, /.-+3
7%(8'9:;'():5$<=><?)<@A-.111B
2345+6I7*8 (9&%0 !9"(1 !9"0$ !9"$& !9((( !9(00 !9'(# //*
:;<<,I=7*8 '9$#0 '9%(% '9%$! '9&!$ '9&%' 09"0" 09''1 3,-
>??7=,-@->6A,I-B,IC7=,+ (90'1 (900& (90#0 (90$% (90&' (91"% (91%0 -0+
23+676567;3*8 !9#&1 !9$'$ !9$%" !9%!0 !9%#% !9&(0 '9(1( 032
4%)5$ +.6,6 -1.1*1 -1.-2/-1./16-1.032-1.213--./62 -.316
=C""'8D:$$'.<=N ("D.,*I-
23=I,*+,
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
52
Average Weekday Vehicle Trips Summerville will use average weekday vehicle trips (AWVT) for nonresidential Public Safety and Fire Impact Fees. Components used to determine average weekday vehicle trips include trip generation rates and adjustments for pass-by trips. Nonresidential Demand Units In Figure B7, gray shading indicates the nonresidential development prototypes used by TischlerBise to derive average weekday vehicle trip ends. For nonresidential vehicle trips, TischlerBise uses data published in Trip Generation, Institute of Transportation Engineers, 12th Edition (2025). The prototype for industrial development is Light Industrial (ITE 110) which generates 3.60 average weekday vehicle trip ends per 1,000 square feet of floor area. Institutional development uses Hospital (ITE 610) and generates 10.70 average weekday vehicle trip ends per 1,000 square feet of floor area. For office & other services development, the proxy is General Office (ITE 710); it generates 7.83 average weekday vehicle trip ends per 1,000 square feet of floor area. The prototype for commercial development is Shopping Center (ITE 820) which generates 36.39 average weekday vehicle trips per 1,000 square feet of floor area. Figure B7: Nonresidential Demand Units
!"# $%FG()*+,-.I)0-"123-#()4*+,-.I)0-"123-#()4#F3560%%4-7%189:G1%-;%%<
=6)% L(2< 7%1-$%FG()-L(2<? 7%1-#F3560%%? $%FG()-L(2<7%1-#F3560%%
!!"#$%FG()*+H-G.$I0 !1"""(23(4G 567" 86"9 "6:" !1!!;
!5")*+H-G.$I0(<I.= !1"""(23(4G 967L 56:5 "67L !1877
!8"?I*H@IAGH.$*% !1"""(23(4G 869; 967; !67" 79B
!B"CI.MFNH-$*% !1"""(23(4G !65L B6"B "69; 517B:
9B8F--$-GM+(#$G$*% !1"""(23(4G 86!: 8698 "6:: !1"!9
59"?NGM0 .NNH 565B 9B6!; "6!5 IJF
B7BOIL(MI.M !1"""(23(4G 5:65" !:65" 96"8 8:!
7!"NN-O$GI0 !1"""(23(4G !"6;" 56B; 56"" 558
79"IH.-$*%(NNHM PM+ 56"7 565! "6:9 IJF
;!"QM*M.I0(R@@$AM(SIG%(-$TMU!1"""(23(4G ;6L5 5688 969L 85:
;9"?M+$AI0VOM*GI0(R@@$AM!1"""(23(4G 586"5 !!6;L 96L: 587
;5"QNGM.*HM*G(R@@$AM !1"""(23(4G 996B: ;68B 56"5 55"
;;"PH-$*M--(<I.= !1"""(23(4G :6:; B689 !6L8 B88
L9"2FNOO$*%(MM*GM.(SIG%(-$TMU!1"""(23(4G 5765: !;689 96": 8;:
!6(X.$O(QM*M.IG$N*1()*-G$GHGM(N@(X.I*-ON.GIG$N*(Y*%$*MM.-1(!9GF(Y+$G$N*(S9"9BU6
@G()-L4%-A16:3
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
53
Trip Rate Adjustments To calculate impact fees, trip generation rates require an adjustment factor to avoid double counting each trip at both the origin and destination points. Therefore, the basic trip adjustment factor is 50 percent. As discussed further below, the impact fee methodology includes additional adjustments to make the fees proportionate to the infrastructure demand for particular types of development. Adjustment for Pass-By Trips For commercial and institutional development, the trip adjustment factor is less than 50 percent since these types of development attract vehicles as they pass by on arterial and collector roads. For example, when someone stops at a convenience store on the way home from work, the convenience store is not the primary destination. For an average shopping center, ITE data indicate 34 percent of the vehicles that enter are passing by on their way to another primary destination. The remaining 66 percent of attraction trips have the commercial site as their primary destination. Since attraction trips are half of all trips, the trip adjustment factor is 66 percent multiplied by 50 percent – approximately 33 percent of trip ends. Average Weekday Vehicle Trips Shown in Figure B8 are the demand indicators for nonresidential land uses related to average weekday vehicle trips (AWVT) generated per 1,000 square feet of floor area. To calculate average weekday vehicle trips, multiply average weekday vehicle trip ends by the trip rate adjustment factor. For example, the industrial demand unit of 1.80 average weekday vehicle trips per 1,000 square feet of floor area is the sum of 3.60 average weekday vehicle trip ends per 1,000 square feet of floor area multiplied by a trip rate adjustment factor of 50 percent. Figure B9 includes nonresidential vehicle trips in the 2026 base year. Figure B8: Average Weekday Vehicle Trips (AWVT) by Development Type
Figure B9: Nonresidential Vehicle Trips
!"#$%&'()* +,-. I.0 1,2.
34556'7()* +-,+8 ++0 19,.1
:;;(76<=<:&L6'<?6'@(76 A,2+ I.0 +,89
!"%&(&$&(4")* 1.,A. ++0 +,I+
1,<?66<B)"#<C%6<D%%$5E&(4"%
D@6')F6<G66H#)I
J6L(7*6<O'(E%L6@6*4E56"&<OIE6 D@F<GH#I<J6L<
O'(E<M"#%1
O'(E<N)&6<
D#O$%&56"&
!"#"$%F'"() !"# *+, -#.I01234 +56F 7879 7879
+4F" :(6) ;%2" K+, -2=>?)'"()!"#I:(6)?K"@I+56F?
*(2>?)563$ ABC DE8 FG98 H8I DJOLE FJHM7
;%''"5N63$ ABC L78 F9GFO FFI FJM9E EHJ78H
OPP6N"IQIO)@"5IB"5#6N"? ABC MD8 MGLF H8I DJEFH HJ9DL
*(?)6)>)6%(3$ ABC H9H D8GM8 FFI 7J9OH OJHDH
+%)3$ 9FJO8O
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
54
Development Projections Provided below are summaries of development projections used in the Impact Fee Study. Development projections are used to illustrate a possible future pace of demand for infrastructure and cash flows resulting from revenues and expenditures associated with those demands. Figure B10: Development Projections
Figure B11: Nonresidential Vehicle Trip Projections
!"!# !"!$ !"!% !"!F !"'" !"'( !"'! !"'' !"') !"'* !"'#
+,-.I0.,1 ( ! ' ) * # $ % F ("
!"#$%F'(") *+H---*+H.-/**H0/.*1H2*+*2H2-0*0H10-*.H12/1-H10/1/H2//13H21-14H03. .H03.
5"$6()789)('6
23456.I7,8369 ($:)#"($:#*#($:%*#(%:"*F(%:!##(%:)$%(%:#F'(%:F(!(F:('#(F:'#)(F:*F$ 3H/41
;<6=3>?,8369 #:!#' #:*!) #:$F" $:"#! $:''% $:#!" $:F"$ %:!"" %:)F% %:%"' F:((' 3H0*-
:"'F%85"$6()789)('6 34H2343+H/0-3+H1+13*H/3-3*H1-+31H-.231H1--32H//332H14*30H/1230H2-. +H.01
;<#%"=<>)'
@4A<-=13,6 (:*'F (:*#$ (:*F* (:#!' (:#*! (:#%! (:$(! (:$)! (:$$' (:%") (:%'# 3.2
BC88.1M3,6 #:#"$ #:$(F #:%'! #:F)$ $:"#) $:(%! $:'"! $:)!) $:*)$ $:#$! $:$FF /H/.3
E??3M.IFIE=G.1I2.1H3M. *:*#" *:*F' *:#!* *:#*F *:#F! *:$!# *:$#" *:$F* *:%'" *:%#* *:F"" 4+-
@4-=3=<=3C4,6 #:!"# #:''' #:)#! #:*F' #:$!$ #:%#! #:FFF $:('F $:!%( $:)!* $:*$( /H41*
:"'F%8;<#%"=<>)' /.H./33-H3//3-H*/*3-H0333/H/4*3/H+*33/H22433H-..33H+4-33H21134H/-2 4H/.*
?")@>6A8B%""@8C@>F8DN/H---F
@4A<-=13,6 (:F%) !:"(* !:")$ !:"$F !:((( !:()) !:($$ !:!(( !:!)# !:!%( !:'(# 443
BC88.1M3,6 ':$#) ':%(% ':%$! ':F!$ ':F%' ):")" ):"F$ ):(*# ):!(* ):!$* ):''* *2/
E??3M.IFIE=G.1I2.1H3M. (:)'* (:))F (:)#) (:)$% (:)F' (:*"% (:*!' (:*'% (:**' (:*#F (:*%) /+.
@4-=3=<=3C4,6 !:#F* !:$'$ !:$%" !:%!) !:%#% !:F() !:F#" ':""# ':"*) ':("! ':(*( +*1
:"'F%8?")@>6A8B%""@8C@>F.H020/-H-3-/-H/14/-H4-0/-H+*1/-H1-*/-H2*2/-H.////H-12//H331//H401 /H*-0
(">0.,1I
@4M1.,-.G$<<>@H(%%>H8GI
!"#$ % F ' ( ) * + , - %. %.I0$"1
F.F* F.F+ F.F, F.F- F.'. F.'% F.'F F.'' F.'( F.') F.'* 2341$"#$
2356#718"9:;K= %>-,( F>.%) F>.(+ F>.+- F>%%% F>%(( F>%++ F>F%% F>F(* F>F,% F>'%* ''F
?@AA$148"9:;K= '>+*( '>,%, '>,+F '>-F+ '>-,' (>.(. (>.-+ (>%)* (>F%) (>F+) (>'') )+%
BCC84$:D:B7E$1:K$1F84$#:;K=%>(') %>((- %>(*( %>(+, %>(-' %>)., %>)F' %>)', %>))' %>)*- %>),( %(-
23#787678@3"9:;K= F>*-) F>+'+ F>+,. F>,F( F>,*, F>-%( F>-*. '>..* '>.)( '>%.F '>%)% ()*
2356#718"9:G18H# '>)+F '>*F, '>*,( '>+(F '>,.. '>,)- '>-%- '>-,. (>.(F (>%.) (>%*- )-+
?@AA$148"9:G18H# ()>F.)()>,(,(*>)..(+>%*F(+>,''(,>)%'(->F.'(->-.').>*%')%>''')F>.*' *>,),
BCC84$:D:B7E$1:K$1F84$#:G18H#)>*%, )>*+( )>+'. )>+,+ )>,() )>-.' )>-*F *>.F% *>.,% *>%(F *>F.' ),)
23#787678@3"9:G18H# ->)%) ->**( ->,%+ ->-+%%.>%F,%.>F,,%.>().%.>*%)%.>+,F%.>-)F%%>%F( %>*%.
!"#$%&'(%#)'*+,-$'.& /01232/41564/71806//1//9/81/3//517/0/21704831762861765891709801772 21/73
K6AA$1F899$>:K?
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
55 55
APPENDIX C: LAND USE DEFINITIONS Residential Development As discussed below, residential development categories are based on data from the U.S. Census Bureau, American Community Survey. The Town of Summerville will collect development fees from all new residential units. One-time development fees are determined by site capacity (i.e., number of residential units). Single Family: 1. Single family detached is a one-unit structure detached from any other house, that is, with open space on all four sides. Such structures are considered detached even if they have an adjoining shed or garage. A one-family house that contains a business is considered detached as long as the building has open space on all four sides. 2. Single family attached (townhouse) is a one-unit structure that has one or more walls extending from ground to roof separating it from adjoining structures. In row houses (sometimes called townhouses), double houses, or houses attached to nonresidential structures, each house is a separate, attached structure if the dividing or common wall goes from ground to roof. 3. Mobile home includes both occupied and vacant mobile homes, to which no permanent rooms have been added, are counted in this category. Mobile homes used only for business purposes or for extra sleeping space and mobile homes for sale on a dealer's lot, at the factory, or in storage are not counted in the housing inventory. Multifamily: 1. 2+ units (duplexes and apartments) are units in structures containing two or more housing units, further categorized as units in structures with “2, 3 or 4, 5 to 9, 10 to 19, 20 to 49, and 50 or more apartments.” 2. Boat, RV, Van, Etc. includes any living quarters occupied as a housing unit that does not fit the other categories (e.g., houseboats, railroad cars, campers, and vans). Recreational vehicles, boats, vans, railroad cars, and the like are included only if they are occupied as a current place of residence.
Capital Improvement Plan and Development Impact Fee Study Town of Summerville, South Carolina
56 56
Nonresidential Development The proposed general nonresidential development categories (defined below) can be used for all new construction within the Town of Summerville. Nonresidential development categories represent general groups of land uses that share similar average weekday vehicle trip generation rates and employment densities (i.e., jobs per thousand square feet of floor area). Retail: Establishments primarily selling merchandise, eating/drinking places, and entertainment uses. By way of example, Retail includes shopping centers, supermarkets, pharmacies, restaurants, bars, nightclubs, automobile dealerships, and movie theaters, hotels, and motels. Office/Service: Establishments providing management, administrative, professional, or business services; By way of example, Office/Service includes banks, business offices, headquarter buildings, business parks, and research and development centers. Industrial: Establishments primarily engaged in the production, transportation, or storage of goods. By way of example, Industrial includes manufacturing plants, distribution warehouses, trucking companies, utility substations, power generation facilities, and telecommunications buildings. Institutional: Establishments providing management, administrative, professional, or business services; By way of example, Institutional includes assisted living facilities, nursing homes, hospitals, medical offices, veterinarian clinics, schools, universities, churches, daycare facilities, government buildings, and prisons.
- CODE OF ORDINANCES
Chapter 20 - PLANNING AND DEVELOPMENT
ARTICLE IV. DEVELOPMENT IMPACT FEES
Summerville, South Carolina, Code of Ordinances Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 1 of 20
ARTICLE IV. DEVELOPMENT IMPACT FEES1
REVISED, APRIL 16, 2026
Sec. 20-101. Title.
This article shall be referred to as the "Development Impact Fee Ordinance for the Town of Summerville".
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-102. Authority.
This article is adopted pursuant to and in compliance with the authority of the South Carolina Development
Impact Fee Act, S.C. Code 1976, § 6-1-9 (the "Act"), and is to be interpreted in accordance with such Act , or as it
may be amended in the future.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-103. Findings.
The Summerville Town Council hereby declares that:
(1) Adequate park and recreation facilities, fire protection, and municipalpublic safety facilities and
services, and transportation system are vital and necessary to the health, safety, welfare, and
prosperity of the town and its citizens. Substantial growth and new construction is taking place within
the town and is anticipated to continue. This growth creates substantial need for new infra structure
capacity. Meeting these needs is very costly; however, failure to do so will result in an inadequate
system of facilities and equipment to accommodate anticipated demand. This would make the town a
less desirable place to live and do business and be detrimental to the health, safety, welfare, and
prosperity of the town and its citizens.
(2) To the extent that future growth and new construction in the town place demands on park and
recreation facilities, fire protection, or municipalpublic safety facilities and services, or the
transportation system those demands and needs should be met by shifting a portion of the capital cost
for providing new capacity to serve new development, which creates, in whole or in part, these
demands and needs.
(3) By Resolution adopted on September 9, 2021_________________ __, 2026, the town council directed
the planning commission to conduct the necessary review and develop a revised development impact
fee ordinance in accordance with the requirements of the Act.
1Editor's note(s)—Ord. No. 10-0802, adopted Oct. 13, 2010, amended art IV in its entirety to read as herein set out.
Former art. IV §§ 20-101—20-108, pertained to similar subject matter and derived from: Ord. No. 02 -1202,
arts. II—IX, adopted Jan 8, 2003.
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 2 of 20
(4) The planning commission recommended to town council an updated revised Town of Summerville
Capital Improvements Planimpact fee study, including capital improvements plan, with projects eligible
for impact fee funding, dated November 20, 2021; and the Town of Summerville Impact Fee Update
dated January 2022, each of which have been adopted by the town council as modified, on February
10, 2022 and March 10, 2022, respectively__________________ __, 2026, to be upheld as part of this
revised Development Impact Fee Ordinance dated March 10, 2022____________________ __, 2026.
(5) This Ordinance is enacted to implement the recommendations of the Town of Summerville impact fee
study update Impact Fee Study Update as prepared for the planning horizon year of 20326 and endorse
the newly revised Town of Summerville Capital Improvements Plancapital improvements plan.
(6) The impact fees prescribed in this article are equitable, do not impose an unfair or disproportionate
burden on developers and new construction, and are in the best interests of the general welfare of
Summerville and its citizens.
(7) New facilities or equipment eligible for development impact fee funding will benefit all new
development or redevelopment in town limits. Therefore, it is appropriate to treat the entire town as
one service area for calculating, collecting, and spending development impact fees.
(8) This article provides the procedures for timely processing of applications for determination of
appropriate development impact fees applicable to all development inside town limits subject to the
impact fees and for the timely processing of applications for individual assessment of development
impact fees, credits, or reimbursements allowed or paid.
(9) The maximum allowable park and recreation impact fee determined in the Town of Summerville
Impact Fee Update has been reduced by zero percent for the General Development Impact Fee
Schedule summarized in Exhibit A of this article, setting the fees at 100 p ercent of the maximum
amount to provide a reasonable fee for residential investment and to ensure that the impact fees
collected do not exceed the cost to provide capital facilities and equipment that accommodate new
development.
(10) The maximum allowable fire protection impact fee determined in the Town of Summerville Impact Fee
Update has been reduced by zero percent for the General Development Impact Fee Schedule
summarized in Exhibit A of this article, setting the fees at 100 percent of the maximum amount to
provide a reasonable fee for residential and non-residential investments and to ensure that the impact
fees collected do not exceed the cost to provide capital facilities and equipment that accommodate
new development.
(11) The maximum allowable municipal facilities and services impact fee determined in the Town of
Summerville Impact Fee Update has been reduced by zero percent for the General Development
Impact Fee Schedule summarized in Exhibit A of this article, setting the fees at 100 percent of the
maximum amount to provide a reasonable fee for residential and non -residential investments and to
ensure that the impact fees collected do not exceed the cost to provide capital facilities and equipment
that accommodate new development.
(912) Property for which a valid building permit has been issued prior to the effective date of this article shall
not be subject to the new or updated development impact fees.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 3, 3-10-2022; Ord. No. 23-0601, § 2, 7-13-2023)
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 3 of 20
Sec. 20-104. Definitions.
The following definitions apply within this article consistent with the provisions set forth in the South
Carolina Development Impact Fee Act, or as it may be amended in the future. Where terms are not defined, the
definitions used in the Town of Summerville Code of Laws shall apply.
Affordable housing. Housing that is affordable to families whose incomes do not exceed 80 percent of the
median income for the service zone established for the Town of Summerville.
Building permit. A permit issued by the town permitting the construction of a building or structure within
town limits.
Capital improvement. Improvements with a useful life of five years or more, by new construction or other
action, which increase the service capacity of the public facility. Public facilities for the purpose of this article
include park and recreation facilities, fire protection, and municipalpublic safety facilities and services, and
transportation and include the costs components identified in the impact fee study update .
Capital improvements plan (CIP). A multi-year planning tool, included in and incorporated into the impact fee
study update, used to identify capital projects and coordinate financing and implementation. The plan also
identifies capital improvements for which development impact fees may be used as a funding source.
Certificate of occupancy. A certificate allowing the occupancy or use of a building and certifying that the
structure or use has been constructed or will be used in compliance with the Town of Summerville Code of Laws
and all other applicable regulations.
Credits. Impact fee deductions allowed to a fee payor for eligible off-site capital improvements funded by the
fee payor.
Developer. An individual, corporation, partnership, or other legal entity undertaking new development.
Development. Construction or installation of a new building or structure, or a change in use of an existing
building or structure, any of which creates additional demand and need for public facilities (i.e., parks and
recreation, fire protection, or municipalpublic safety facilities and services, or transportation). A building or
structure shall include, but not be limited to, modular buildings and manufactured housing. Development does not
include alterations made to existing single-family homes.
Development impact fee. A financial payment made by a developer to a local government for funding certain
off-site capital improvements identified to accommodate future growth. Development impact fees are collected by
the town for park and recreation facilities, fire protection, and municipalpublic safety facilities and services, and
transportation.
Fee payor. A developer that pays or is required to pay a development impact fee.
Fire protection impact fee. A payment of money imposed as a condition of approval to pay a proportionate
share of the cost for capital improvements to the fire protection system identified to serve new development.
Municipal facilities and services impact fee. A payment of money imposed as a condition of approval to pay a
proportionate share of the cost for improvements to the municipal facilities and services system identified to serve
new development.
General impact fee schedule. The schedule of impact fee amounts, by public facility category and land use
and set forth in Fee Schedule 1 of this article.
Impact fee study update. The Capital Improvement Plan and Development Impact Fee Study, prepared by
TischlerBise, dated ______________ ____, 2026.
Off-site improvements. Capital improvements located outside of the boundaries of a development that are
required to serve the development's demands and needs.
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 4 of 20
Park and recreation impact fee. A payment of money imposed as a condition of approval to pay a
proportionate share of the cost for capital improvements to the park and recreation system identified to serve
new development.
Public facilities. Improvements to and/or construction of capital improvements identified in the impact fee
study update Town of Summerville Capital Improvements Plan and the Town of Summerville Impact Fee Update as
described in Article V hereof. Public facilities for the purpose of this article include park and recreation facilities,
fire protection, and municipalpublic safety facilities and services.
Public safety facilities and services impact fee. A payment of money imposed as a condition of approval to
pay a proportionate share of the cost for capital improvements to the public safety facilities and services system
identified to serve new development.
Square feet (s.f.). As referred to in Fee Schedule 1Exhibit A (attached to Ord. No. 10-0802 and kept on file
with the town), means the sum (in square feet) of the area of each floor level, including cellars, basements,
mezzanines, penthouses, corridors, lobbies, stores and offices, that are within the principal outside faces of
exterior walls, not including architectural setbacks or projections. Included are all areas that have floor surfaces
with clear standing head room (measured six-foot, six inches minimum) regardless of their use. If a ground level
area of a building, or part thereof, within the principal outside faces of the exterior walls is not enclosed, this
square footage definition considers it part of the overall square footage for the building. However, unroofed areas
and unenclosed roofed-over spaces, except those contained within the principle outside faces of exterior walls,
should be excluded from the area measurement. The area of any parking garage within a building shall not be
included in the area measurement.
System improvement. A capital improvement to a public facility which is designed to provide service to a
service area.
System improvement cost. The costs incurred for construction and reconstruction of system improvements,
including design, acquisition, engineering, and other costs attributable to the improvements, and also including the
costs of providing additional public facilities needed to serve new growth and development. System improvement
costs do not include:
(1) Construction, acquisition, or expansion of public facilities other than capital improvements eligible for
impact fee funding that are identified in the Town of Summerville Capital Improvements Plancapital
improvements plan;
(2) Repair, operation, or maintenance of existing or new capital improvements;
(3) Upgrading, updating, expanding, or replacing existing capital improvements to serve existing
development in order to meet stricter safety, efficiency, environmental, or regulatory standards;
(4) Upgrading, updating, expanding, or replacing existing capital improvements to provide better service
to existing development;
(5) Administrative and operating costs of the governmental entity; or
(6) Principle Principal payments and interest or other finance charges on bonds or other indebtedness
except financial obligations issued by or on behalf of the governmental entity to finance capital
improvements eligible for impact fee funding that are identified in the Town of Summerville Capital
Improvements Plancapital improvements plan.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 4, 3-10-2022)
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 5 of 20
Sec. 20-105. Supporting documentation.
(a) This article is based upon the conclusions, and recommendations, and capital improvements plan presented
in the impact fee study update, Town of Summerville Impact Fee Update and Town of Summerville Capital
Improvements Plan prepared consistent with the provisions set forth in the Act and adopted by town council
on March 10 _______________ ___, 2026and February 10, 2022 respectively. Both The impact fee study
update documents are is on file in the town planning department and are is incorporated into this article by
reference.
(b) All development impact fees collected pursuant to this article shall be used to implement any or all of the
public facilities deemed eligible for impact fee funding identified in the Town of Summerville Capital
Improvements Plancapital improvements plan as prioritized therein.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 5, 3-10-2022)
Sec. 20-106. Jurisdiction.
A development impact fee shall apply to all new development or redevelopment located within town limits.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-107. Application and exemptions.
The provisions of this article shall apply to all new development or redevelopment within town limits for
which a building permit or development approval is required except for the following:
(1) Rebuilding the same amount of floor space of a structure that was destroyed by fire or other natural
catastrophe;
(2) Remodeling or repairing a structure with the same land use that does not result in an increase in the
number of service units or place new demand on park and recreation facilities, fire protection, or
municipalpublic safety facilities and services, or transportation system;
(3) Replacing a residential unit, including a manufactured home, with another residential unit on the same
lot, if the amount of traffic generated by the new residential unit does not increase;
(4) Placing a construction trailer or temporary office on a lot during the period of construction on the same
lot;
(5) Construction of an addition to a residential structure that does not increase the amount of traffic
generated by the same land use;
(6) Adding uses that are typically accessory to residential uses, such as a tennis court or a clubhouse,
unless it is demonstrated clearly that the use creates new demand for park and recreation facilities, fire
protection, or municipalpublic safety facilities and services, or the transportation system; and
(7) All or part of a particular development project if:
a. The project is determined to create affordable housing; and
b. The exempt development's proportionate share of system improvements is funded through a
revenue source other than development impact fees.
(Ord. No. 10-0802, 10-13-2010)
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 6 of 20
Sec. 20-108. Provisions for affordable housing.
Because all or part of any particular development project may be exempt from development impact fees for
affordable housing, the following sets forth the administrative standards for determining what constitutes
affordable housing and the procedures for exemption from one or more development impact fees:
(1) Median family income. Affordable housing is based upon 80 percent of the median family income for
residents living within the Town of Summerville. Median family income shall be determined once a
year utilizing the following procedure:
a. The most recently available figures from the U.S. Census Bureau American Community Survey will
serve as the base year for this evaluation;
b. Each subsequent year will be adjusted once annually thereafter during January of the calendar
year based upon the previous year's published Consumer Price Index (CPI) increase, until the next
U.S. Census Bureau data set is published and this procedure is replicated.
(2) Maximum expenditure. The maximum expenditure for housing costs shall correspond to the Fannie
Mae Foundation Mortgage Calculator multiplier of 30 percent of gross family income as used in the
Housing Affordability Analysis, included as Appendix A of the impact fee study update in Support of an
Impact Fee Study Update in Summerville. Affordable housing based upon 80 percent of median family
income is:
a. Multifamily rental dwelling units of which the gross monthly rent cost does not exceed 30
percent of 80 percent of the gross median family monthly income.
b. Fee simple ownership dwelling units of which the cost of homeownership for the dwelling unit do
not exceed 30 percent of 80 percent of the gross median family monthly income as reflected in
the sales price using the Fannie Mae Foundation Mortgage Calculator (or comparable
methodology) assuming a 15 percent down payment and a specified interest rate. The specified
interest rate shall be determined by selecting the lowest 30-year fixed mortgage rate reported by
area lending institutions as of the first week of January for any given year and shall remain so for
the balance of the year.
(3) Procedures for exemption from development impact fees.
a. A developer seeking exemption from one or more development impact fees for the construction
of affordable multifamily rental dwelling units must identify the alternate source of funds for the
impact fee and, unless the alternate source is from town resources, post a financial guarantee
suitable to the town prior to the issuance of a building permit. The amount of the financial
guarantee shall reflect the amount of development impact fees due for all affordable housing
units as if they were not affordable housing units. No certificate of occupancy for any of the units
may be issued until the impact fees for the affordable housing units have been paid by the
alternate source or from the proceeds of the financial guarantee.
If the alternate source of funds for impact fees is from town resources, prior to issuance of the
certificate of occupancy by the town, the developer shall record an agreement approved by the
town restricting the monthly rental cost of each affordable hous ing unit for a period of six years.
Upon delivery of the recorded rent control agreement, the certificate of occupancy shall be
issued.
b. A developer seeking exemption from one or more development impact fees for construction of a
fee simple ownership dwelling unit shall identify the alternate source of funds for the impact fees
and, unless the alternate source is from town resources, post a financial guarantee suitable to
the town prior to the issuance of a building permit. The amount of the financial guarantee shall
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 7 of 20
reflect the amount of development impact fees due for all affordable housing units as if they
were not affordable housing units. No certificate of occupancy may be issued for the affordable
housing dwellings until the impact fees have been paid by the alternate source or from the
proceeds of the financial guarantee.
If the alternate source of funds for impact fees is from town resources, prior to the issuance of a
certificate of occupancy by the town, the developer shall file with the town a closing statement
for the dwelling unit indicating an arm's length sales price no greater than that allowed for
affordable housing at the time of final sale and a recorded covenant, approved by the town,
restricting the sales price of the dwelling, for a period of six years, to the original sales price,
adjusted annually for inflation.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-109. Determination of fees and independent impact fee calculations.
(a) General provisions.
(1) The town building department shall determine and collect all development impact fees administered
within town limits.
(2) Upon the effective date of this article, or related revisions to this article, development impact fees shall
be charged to new development or redevelopment in accordance with the procedures set forth in this
article, or relevant revisions thereto, in accordance with Fee Schedule 1 below. The fees to be collected
for a development will be determined at the time of application for a building permit. If the
development is one that does not require a building permit, the impact fee for the development will be
determined at the time of development approval. No building permit or development approval shall be
issued for any development requiring the payment of development impact fees until the fees have
been remitted to the town building department, or in the case of affordable housing, the appropriate
financial guarantees have been filed with the town administrator. Payment of such fees shall not
relieve the developer from obligations to comply with any other applicable Town ordinance,
regulation, or requirement including, but not limited to, the Unified Development Ordinance (UDO) of
the Town of Summerville Code of Laws prior to receiving a certificate of occupancy.
Fee Schedule 1
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 8 of 20
(3) All monies paid by the fee payor pursuant to this article shall be identified as development impact fees
and promptly deposited in the appropriate development impact fee trust fund described under section
20-110 of this article.
(4) For the purpose of calculating development impact fees, the land use types assumed in the General
Development Impact Fee Fee Schedule 1 of this article section (i.e., Exhibit A)shall be defined in
accordance with the definitions contained in Appendix C of the impact fee study update, based on the
U.S. Census Bureau, American Community Survey, for purposes of determining residential uses, and
the Institute of Transportation Engineers' Trip Generation Manual, Tenth Twelfth Edition, consistent
with the impact fee study update, for purpose of determining nonres idential uses(see Town of
Summerville Impact Fee Update, Appendix B).
(5) Payment of development impact fees according to the general development impact fee schedule (i.e.,
Exhibit A, attached to Ord. No. 22-0201 and kept on file with the town), or independent impact fee
calculation study accepted by town council, shall constitute full and complete payment of the new
development's proportionate share of public facilities costs.
(6) A developer may negotiate and contract with the town to provide facilities or services in lieu of
payment of development impact fees in accordance with S.C. Code 1976, § 6 -1-1050 of the Act.
(b) Park and recreation impact fee formula. Park and recreation impact fees collected within town limits shall be
in accordance with the following formula:
Impact Fee = (NNDU) × (P/HH) × (COST) × (TDR)
Where:
NNDU = The number of net new dwelling units generated by the proposed development.
P/HH = Average person per household estimate published by the U.S. Census Bureau for various dwelling unit
categories (see Town of Summerville Impact Fee Update, Appendix B).
COST = The cost per capita for providing improvements to park and recreation facilities is based on information
presented in the Town of Summerville Impact Fee Update adopted by town council on March 10, 2022. The
cost per capita is $1,324.13.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of the maximum allowable
park and recreation impact fee determined in the Town of Summerville Impact Fee Update.
(c) Determining park and recreation impact fees. The amount of park and recreation impact fees attributable to
a specific development shall be determined through the following process:
(1) Verify the type and number of new residential dwelling units for which the building permit is being sought;
(2) Determine whether any of the proposed residential dwelling units qualify for a discount on park and
recreation impact fees as "affordable housing" and, if so, the number and type of such units;
(3) Determine the applicable residential dwelling unit category set forth in Exhibit A, attached to Ord. No. 22 -
0201 and kept on file with the town (as applicable); and
(4) Multiply the discounted development impact fee rate for the residential dwelling unit category by the
number of net new units within the development and the average persons per household estimate.
(bd) Independent park and recreation impact fee calculations. In the event that a fee payor or town staff contend
that the land use for which the building permit is being sought is not within those land uses identified in
general impact fee scheduleExhibit A, (attached to Ord. No. 22-0201 and kept on file with the town) or if the
fee payor contends that the general impact fee schedule Exhibit A, (attached to Ord. No. 22-0201 and kept
on file with the town) calculations are not accurate for its intended use, then the town building official, or its
designee, shall make a determination as to the most comparable land use category to assume for calculating
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 9 of 20
park and recreation impact fees. If the fee payor disagrees with the determination of the town building
official or if the town otherwise deems it appropriate, an independent impact fee calculation may be
performed to quantify the fair share of system improvement costs attrib utable to the development.
Preparation of an independent impact fee calculation will immediately halt the building permit application
process until such time that the necessary calculation is deemed complete by the town building officia l. If an
independent calculation is requested, it must accompany the building permit application and be prepared in
accordance with the following provisions:
(1) Independent calculations for the determination of park and recreation impact fees must be performed
by a certified professional planner or other duly qualified and licensed professional approved by the
town building official.
(2) The independent calculation shall be subject to review and approval by the town building official, or its
designee.
(3) The town building official shall either approve or provide in writing the reasons for disapproval of the
independent calculation study within 30 days of its submittal for review.
(4) Prior to commencing the study, the developer's professional consultant and the town building official,
or its designee, shall agree upon the relevant factors and values that will be utilized in the independent
calculation of impact fees and to confirm the professional’s proposed methodology and formulas to be
used in the calculation are consistent with those in the impact fee study update .
(5) The maximum allowable park and recreation impact fee determined in the Town of Summerville Impact
Fee Update shall be 100 percent for the purposes of completing an independent impact fee calculation,
setting the fees at 100 percent of the maximum amount.
(6) The independent impact fee calculation shall be based on the following formula:
Impact Fee = (NNDU) × (P/HH) × (COST) × (TOR)
Where:
NNDU = The number of net new dwelling units generated by the proposed development.
P/HH = Average person per household estimate approved by the town building official.
COST = The cost per capita for providing improvements to park and recreation facilities is based on
information presented in the Town of Summerville Impact Fee Update adopted by town council on
March 10, 2022. The cost per capita is $1,324.13.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of the maximum
allowable park and recreation impact fee determined in the Town of Summerville Impact Fee Update.
(7) For properties in which DRB or BAR approval is required, the current impact fee rates adopted March
10, 2022 shall remain effective if DRB or BAR preliminary approval has been granted and building
permits are issued within 18 months of the date of adoption of this amended section. For properties in
which DRB or BAR approval is not required, the current impact fee rates adopted March 10, 2022, shall
remain effective for the current phase of development if a complete MS4 permit or EPSC permit
submittal has been received, and building permits are issued within 36 months of the date of adoption
of this amended section.
(e) Fire protection impact fee formula. Fire protection impact fees collected within town limits shall be in
accordance with one of the following formulas:
(1) Residential development:
Impact Fee = (NNDU) × (P/HH) × (COST) × (TDR)
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 10 of 20
Where:
NNDU = The number of net new dwelling units generated by the proposed development.
P/HH = Average person per household estimate published by the U.S. Census Bureau for various
dwelling unit categories (see Town of Summerville Impact Fee Update, Appendix B).
COST = The cost per capita for providing fire protection services is based on information
presented in the Town of Summerville Impact Fee Update adopted by town council on March 10,
2022. The cost per capita is $289.69.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of the
maximum allowable fire protection impact fee determined in the Town of Summerville Impact
Fee Update.
(2) Nonresidential development.
Impact Fee = (NNSF) × (ESR) × (COST) × (TDR)
Where:
NNSF = The amount of net new square footage generated by the proposed development.
ESR = Average employee space ratio developed using information published in the Institute of
Transportation Engineers Trip Generation, Tenth Edition (see Town of Summerville Impact Fee
Update, Appendix B).
COST = The cost per employee for providing fire protection services is based on information
presented in the Town of Summerville Impact Fee Update adopted by town council on March 10,
2022. The cost per capita is $488.56.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of the
maximum allowable fire protection impact fee determined in the Town of Summerville Impact
Fee Update.
(f) Determining fire protection impact fees. The amount of fire protection impact fees attributable to a specific
development shall be determined through the following process:
(1) Verify the type and number of new residential dwelling units or the type and intensity of new
nonresidential square footage or other land use measuring criteria for which the building permit is
being sought;
(2) For residential development, determine whether any of the proposed residential dwelling units qualify
for a discount on fire protection impact fees as "affordable housing" and, if so, the number and type of
such units;
(3) Determine the applicable land use type and impact fee per unit set forth in Exhibit A, (attached to Ord.
No. 22-0201 and kept on file with the town) (as applicable); and
(4) Multiply the discounted development impact fee rate for the specified land use category by the
number of net new units or net new square footage within the development (as applicable) and the
average persons per household or employee space ratio estimate (as applicable).
(g) Independent fire protection impact fee calculation. In the event that a fee payor or town staff contend that
the land use for which the building permit is being sought is not within those land uses identified in Exhibit A,
(attached to Ord. No. 22-0201 and kept on file with the town) or if the fee payor contends that the Exhibit A
(attached to Ord. No. 22-0201 and kept on file with the town) calculations are not accurate for its intended
use, then the town building official, or its designee, shall make a determination as to the most comparable
land use category to assume for calculating fire protection impact fees. If the fee payor disagrees with the
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 11 of 20
determination of the town building official or if the town otherwise deems it appropriate, an independent
impact fee calculation may be performed to quantify the fair share of system improvement costs attributable
to the development. Preparation of an independent impact fee calculation will immediately halt the building
permit application process until such time that the necessary calculation is deemed complete by the town
building official. If an independent calculation is requested, it must accompany the building permit
application and be prepared in accordance with the following provisions:
(1) Independent calculations for the determination of fire protection impact fees must be performed by a
certified professional planner or other duly qualified and licensed professional approved by the town
building official.
(2) The independent calculation shall be subject to review and approval by the town building official, or its
designee.
(3) The town building official shall either approve or provide in writing the reasons for disapproval of the
independent calculation study within 30 days of its submittal for review.
(4) Prior to commencing the study, the developer's professional consultant and the town building official,
or its designee, shall agree upon the relevant factors and values that will be utilized in the independent
calculation of impact fees.
(5) The maximum allowable fire protection impact fee determined in the Town of Summerville Impact Fee
Update shall be reduced by zero percent for the purposes of completing an independent impact fee
calculation, setting the fees at 100 percent of the maximum amount.
(6) The independent impact fee calculation shall be based on one of the following formulas:
a. Residential development:
Impact Fee= (NNDU) × (P/HH) × (COST) × (TDR)
Where:
NNDU = The number of net new dwelling units generated by the proposed development.
P/HH = Average person per household estimate published by the US Census Bureau for
various dwelling unit categories (see Town of Summerville Impact Fee Update, Appendix B).
COST = The cost per capita for providing fire protection services is based on information
presented in the Town of Summerville Impact Fee Update adopted by town council on
March 10, 2022. The cost per capita is $289.69.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of
the maximum allowable fire protection impact fee determined in the Town of Summerville
Impact Fee Update.
b. Nonresidential development:
Impact fee = (NNSF) × (ESR) × (COST) × (TDR)
Where:
NNSF = The amount of net new square footage generated by the proposed development.
ESR = Average employee space ratio developed using information published in the Institute
of Transportation Engineers Trip Generation, Tenth Edition (see Town of Summerville
Impact Fee Update, Appendix B).
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 12 of 20
COST = The cost per employee for providing fire protection services is based on information
presented in the Town of Summerville Impact Fee Update adopted by town council on
March 10, 2022. The cost per capita is $488.56.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of
the maximum allowable fire protection impact fee determined in the Town of Summerville
Impact Fee Update.
(h) Municipal facilities and services impact fee formula. Municipal facilities and services impact fees collected
within town limits shall be in accordance with one of the following formulas:
(1) Residential development:
Impact fee = (NNDU) × (P/HH) × (COST) × (TDR)
Where:
NNDU = The number of net new dwelling units generated by the proposed development.
P/HH = Average person per household estimate published by the U.S. Census Bureau for various
dwelling unit categories (see Town of Summerville Impact Fee Update, Appendix B).
COST = The cost per capita for providing municipal facilities and services is based on information
presented in the Town of Summerville Impact Fee Update adopted by town council on March 10,
2022. The cost per capita is $618.45.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of the
maximum allowable municipal facilities and services impact fee determined in the Town of
Summerville Impact Fee Update.
(2) Nonresidential development:
Impact fee = (NNSF) × (ESR) × (COST) × (TDR)
Where:
NNSF = The amount of net new square footage generated by the proposed development.
ESR = Average employee space ratio developed using information published in the Institute of
Transportation Engineers Trip Generation, Tenth Edition (see Town of Summerville Impact Fee
Update, Appendix B).
COST = The cost per employee for providing municipal facilities and services is based on
information presented in the Town of Summerville Impact Fee Update adopted by town council
on March 10, 2022. The cost per capita is $644.59.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of the
maximum allowable municipal facilities and services impact fee determined in the Town of
Summerville Impact Fee Update.
(i) Determining municipal facilities and services impact fees. The amount of municipal facilities and services
impact fees attributable to a specific development shall be determined through the following process:
(1) Verify the type and number of new residential dwelling units or the type and intensity of new
nonresidential square footage or other land use measuring criteria for which the building permit is
being sought;
(2) For residential development, determine whether any of the proposed residential dwelling units qualify
for a discount on fire protection impact fees as "affordable housing" and, if so, the number and type of
such units;
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 13 of 20
(3) Determine the applicable land use type and impact fee per unit set forth in Exhibit A, (attached to Ord.
No. 22-0201 and kept on file with the town) (as applicable); and
(4) Multiply the discounted development impact fee rate for the specified land use category by the
number of net new units or net new square footage within the development (as applicable) and the
average persons per household or employee space ratio estimate (as applicable).
(j) Independent municipal facilities and services impact fee calculation. In the event that a fee payor or town
staff contend that the land use for which the building permit is being sought is not within those land uses
identified in Exhibit A, (attached to Ord. No. 22-0201 and kept on file with the town) or if the fee payor
contends that the Exhibit A (attached to Ord. No. 22-0201 and kept on file with the town) calculations are
not accurate for its intended use, then the town building official, or its des ignee, shall make a determination
as to the most comparable land use category to assume for calculating fire protection impact fees. If the fee
payor disagrees with the determination of the town building official or if the town otherwise deems it
appropriate, an independent impact fee calculation may be performed to quantify the fair share of system
improvement costs attributable to the development. Preparation of an independent impact fee calculation
will immediately halt the building permit application process until such time that the necessary calculation is
deemed complete by the town building official. If an independent calculation is requested, it must
accompany the building permit application and be prepared in accordance with the following provisions :
(1) Independent calculations for the determination of municipal facilities and services impact fees must be
performed by a certified professional planner or other duly qualified and licensed professional
approved by the town building official.
(2) The independent calculation shall be subject to review and approval by the town building official, or its
designee.
(3) The town building official shall either approve or provide in writing the reasons for disapproval of the
independent calculation study within 30 days of its submittal for review.
(4) Prior to commencing the study, the developer's professional consultant and the town building official,
or its designee, shall agree upon the relevant factors and values that will be utilized in the independent
calculation of impact fees.
(5) The maximum allowable municipal facilities and services impact fee determined in the Town of
Summerville Impact Fee Update shall be reduced by zero percent for the purposes of completing an
independent impact fee calculation, setting the fees at 100 percent of the maximum amount.
(6) The independent impact fee calculation shall be based on one of the following formulas:
a. Residential development:
Impact fee = (NNDU) × (P/HH) × (COST) × (TDR)
Where:
NNDU = The number of net new dwelling units generated by the proposed development.
P/HH = Average person per household estimate published by the U.S. Census Bureau for
various dwelling unit categories (see Town of Summerville Impact Fee Update, Appendix B).
COST = The cost per capita for providing municipal facilities and services is based on
information presented in the Town of Summerville Impact Fee Update adopted by town
council on March 10, 2022. The cost per capita is $618.45.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of
the maximum allowable municipal facilities and services impact fee determined in the
Town of Summerville Impact Fee Update.
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 14 of 20
b. Nonresidential development:
Impact fee = (NNSF) × (ESR) × (COST) × (TDR)
Where:
NNSF = The amount of net new square footage generated by the proposed development.
ESR = Average employee space ratio developed using information published in the Institute
of Transportation Engineers Trip Generation, Tenth Edition (see Town of Summerville
Impact Fee Update, Appendix B).
COST = The cost per employee for providing municipal facilities and services is based on
information presented in the Town of Summerville Impact Fee Update adopted by town
council on March 10, 2022. The cost per capita is $644.59.
TDR = For the purpose of this calculation, it is town council policy to charge 100 percent of
the maximum allowable municipal facilities and services impact fee determined in the
Town of Summerville Impact Fee Update.
(ck) Special cases. The town building department shall take the following special cases into account when
calculating development impact fees for a building permit application:
(1) When an application for a building permit has been made that contains two or more land uses in any
combination, including two or more land uses within a single building or structure, the total
development impact fee assessment shall be the sum of the fees due for each land usethe products, as
calculated determined above, for each land use unless an independent impact fee calculation is
performed, and approved for use by the Town Building Official, or its designee, consistent with
subsections (b) (d), (g), or (j) (as applicable) of this articlesection.
(2) In the case of a change, redevelopment, or modification of a land use which requires a building permit,
and which is not exempted from development impact fees under section 20 -107 of this article, the
impact fee calculation shall be based upon the net increase in new or proposed land use as compared
to the existing or previous land use.
(3) In the case of a demolition or termination of an existing use or structure, development impact fees for
future redevelopment shall be based upon the net increase in development impact fees for the new or
proposed land use as compared to the existing actual active previous land use since its original
occupancy. Credit for the prior use shall not be transferable to another location.
(4) In the case of relocating an existing land use, development impact fees shall be assessed to the
relocated use at its new location. Future redevelopment of the old location from which the use was
removed will receive a credit against development impact fees assessed equal to the impact fees that
would have been assessed against the relocated use. Credits shall not be transferable to the new
location.
(5) Before a building permit application may become eligible for the provisions set forth in subparagraphs
(k)(2) through (4) of this section, a developer shall provide reasonably sufficient evidence that a
previous land use had been actively maintained on the site within 12 months of the date of application
for a building permit. Such evidence may include proof of utility records, records for the use sought to
be shown, or other documentation.
(6) Any claim of existing or previous use must be made no later than the time for application of a building
permit. Any claim made after such time shall be deemed invalid.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 6, 3-10-2022; Ord. No. 23-0601, § 3, 7-13-2023)
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 15 of 20
Sec. 20-110. Impact fee trust funds.
(a) Development impact fees collected pursuant to this article shall be kept separate from other revenue of the
town. There shall be one trust fund established for each development impact fee category depicted in Fee
Schedule 1Exhibit A, (attached to Ord. No. 22-0201 and kept on file with the town); park and recreation, fire
protection, and municipalpublic safety facilities and services, and transportation. All development impact
fees collected shall be properly identified by property address noted on the approved building permit and by
the appropriate trust account.
(b) Any funds on deposit not immediately necessary for expenditure shall be maintained in an interest -bearing
account prior to expenditure on recommended projects. Interest earned on development impact fees in
deposit must be considered revenue to the trust fund account for which income is earned and must be
subject to all restrictions placed on the use of development impact fees pursuant to this article.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 7, 3-10-2022)
Sec. 20-111. Limitation on expenditures of funds collected.
(a) Eligible system improvement costs. Funds from development impact fee trust accounts shall be expended
only for the public facilities and system improvements identified as eligible for impact fee funding in the
Town of Summerville Capital Improvements Plancapital improvements plan, incorporated herein by
reference, consistent with the impact fee study update. No funds shall be used for administrative or
operating costs associated with imposing any of the development impact fees. Eligible components of a
public facility may include, but are not limited to the following:
(1) Design and construction plan preparation;
(2) Right-of-way acquisition;
(3) Construction of new through lanes and/or turn lanes;
(4) Construction of new bridges;
(5) Construction of new drainage facilities associated with roadway improvements;
(6) Purchase and installation of traffic signalization;
(7) Construction of new curbs, medians, and shoulders;
(8) Relocating utilities to accommodate new road construction; and
(9) Principle payments, interest and other finance charges on bonds or other indebtedness issued by or on
behalf of the town for financing any or all public facilities.
(b) Rationale Nexus Test. The town finance director, or its designee, shall make an annual report to the town
council and publish this report for access by the general citizenry showing where development impact fees
have been collected and what projects have been funded with these revenues. The council shall consider this
report and whether the fees are being spent for the benefit of new development within town limits. If the
council determines that this is not the case, then it shall adjust the Town of Sum merville Capital
Improvements Plancapital improvements plan and other projected capital expenditures to correct the
condition.
(c) Expenditure of funds. Development impact fee funds shall be expended in the order in which they were
collected. The disbursal of such funds shall require approval of the town council, upon recommendation of
the town administrator or its designee.
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 16 of 20
(d) Reimbursement. Impact fee funds not obligated for expenditure within three years of the date that they are
scheduled to be expended in the Town of Summerville Capital Improvements Plancapital improvements plan
shall be returned, with actual interest earned, to the record owner of the property for which the fees were
collected, on a first-in, first-out basis.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-112. Credits/reimbursements.
(a) General provisions.
(1) A developer shall be entitled to a credit against development impact fees assessed pursuant to this
article for town-approved monetary or in-kind contributions toward some or all of the public facilities
included in the Town of Summerville Capital Improvements Plancapital improvements plan that are
eligible for impact fee funding.
(2) Development impact fees shall not be imposed on a fee payor or developer who has entered into an
agreement with the town for certain contribution, payment, construction, or dedication of land up to
the cash value of the specific improvements identified within the agreement. Any difference between
total development impact fees due for the development and the cash value of the executed agreement
remain eligible for collection pursuant to the rules and requirements of this article.
(3) A fee payor shall be reimbursed for contributions of land or facilities that exceed his proportionate
share of the cost of public facilities when such excess contribution is made at the request of the town.
(b) Application for credit agreement.
(1) The determination of the amount of any credit shall be undertaken through submission of an
application for credit agreement, which shall be submitted through the town building department for
review by the town building official, or its designee.
(2) The application for credit agreement shall include the following information:
a. The following documentation must be provided if the proposed application involves a credit for
any cash contribution:
1. A certified copy of the development approval in which the contribution was agreed; and
2. Proof of payment (if already made); or
3. Proposed method of payment (if not already made).
b. The following documentation must be provided if the proposed application involves credit for
dedication of land:
1. A drawing and legal description of the land;
2. The appraised fair market value of the land at the date a building permit application is
sought for the traffic generating land use(s), prepared by a professional real estate
appraiser who is a member of the member appraisal institute (MAL) or who is a me mber of
senior residential appraisers (SRA), and if applicable; and
3. A certified copy of the development permit in which the land was agreed to be dedicated
(if applicable).
c. The following documentation must be provided if the proposed application involves credit for
construction:
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 17 of 20
1. The proposed construction documents of the specific construction project prepared and
certified by a duly qualified and licensed engineer in the State of South Carolina;
2. The projected costs for the suggested improvements, which shall be based on local
information for similar improvements, along with the construction schedule for the
completion of said improvements. Such estimated cost shall include construction or
reconstruction of the project, the cost of labor and materials, the cost of all lands,
property, rights, easements, and franchises acquired, financing charges, interest prior to
and during construction and for one year after completion of construction, costs of plans
and specifications, surveys of estimates of costs and revenues, costs of professional
services, and all of the expenses necessary or incidental to determining the feasibility or
practicability of such construction or reconstruction.
(3) Within 14 days of receipt of the proposed application for credit agreement, the town building official,
or its designee, shall determine if the application is complete. If it is determined that the proposed
agreement is not complete, the town building official shall send written notification to the applicant
outlining the deficiencies. The town building official shall take no further action on the proposed
application for credit agreement until all such deficiencies have been corrected or otherwise sett led.
(4) Once the town building official determines that the proposed application for credit agreement is
complete, it shall be reviewed within 30 days by a committee of designated staff composed of the
town administrator, director of planning, town building official, and town engineer (known as the
credit review committee).
(5) If the application for credit agreement is approved by the credit review committee, a credit agreement
shall be prepared and signed by the applicant and the town administrator. It shall specifically outline
the contribution, payment, construction, or land dedication, the time by which it shall be complete,
dedicated, or paid, and any extensions thereof, and the dollar credit the applicant shall receive for the
contribution, payment, or construction against development impact fees. The agreement may also
include provisions for rescinding the credit and issuing stop work orders if the dedication and/or work
and/or construction are not timely accomplished.
(6) A fee payor affected by the decision of the credit review committee regarding credits may appeal such
decision pursuant to subsection 20-114(1) of this article.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 8, 3-10-2022)
Sec. 20-113. Penalties.
Town council shall have the following remedies, which may be exercised individually or collectively, for
collecting development impact fees. The failure to pursue any remedy at any time shall not be deemed as a waiver
of town rights to pursue any remedy at such other time as may be deemed appropriate:
(1) Interest and penalties. The town may, at its discretion, add to the amount of calculated development
impact fees due prior to award of a certificate of occupancy, reasonable interest and penalties for
nonpayment or late payment of required funds. Penalties for unpaid development impact fees shall be
administered consistent with section 1-8 in the Town of Summerville Code of Laws, which declares
violation as a misdemeanor and, upon conviction thereof, an offender shall be liable to a fine of not
more than $500.00, or imprisoned not to exceed 30 days, or both. Each day of violation shall be
deemed a separate offense.
(2) Withholding certificate of occupancy. The town may withhold a certificate of occupancy until full and
complete payment has been made by the developer of development impact fees due for the
development.
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 18 of 20
(3) Withholding utility service. The town may withhold the provision of utility services to a development
until the required development impact fees have been paid in full.
(4) Lien. The town may impose a lien on the developer's property for failure of the developer to pay
required development impact fees in full.
(5) Other. The town may pursue the collection of the development impact fees, including interest, by way
of civil process in the Court of Common Pleas for Dorchester County.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-114. Appeal process.
A developer shall have the following rights for appeal of development impact fees imposed by the town on
their development pursuant only to this article:
(1) Administrative appeal.
a. A developer may file an administrative appeal with the town administrator regarding the
payment of development impact fees, independent calculation of impact fees or credits or
reimbursements by filing a written notice of appeal. Said notice shall be filed within 30 days of
the decision sought to be appealed. The filing of an appeal will immediately halt the building
permit application process, unless the developer posts a bond or submits an irrevocable letter of
credit for the full amount of the development impact fees as calculated by the town to be due.
All notices of appeal shall include a full explanation of the reasons for the appeal, specifying the
grounds therefore, and containing any documentation that the developer desires to be
considered. The appeal shall contain the name and address of the developer filing the appeal and
shall state their capacity to act as a representative or agent if they are not the owner of the
property to which impact fees or credits pertain.
b. Within 30 days following receipt of the written notice of appeal, the town administrator will
review the appellant's written report, supporting documentation and departmental staff reports.
The 30-day review period may be extended if additional information is needed from the
appellant in order to render a decision. Upon completion of the administrative review, the town
administrator will provide a written response to the appellant constituting a final administrative
determination.
c. Any person desiring to appeal the final administrative determination of the town administrator
regarding payment of development impact fees or credits shall file a written notice of appeal to
the town council. Said notice of appeal to town council shall be filed with the clerk of town
council within 15 days following receipt of the final administrative determination. Receipt shall
be construed to have occurred when the final administrative decision is deposited in the United
States Mail postage prepaid to the person whose name and address is identified in the original
notice of appeal.
d. The town clerk of council will schedule all impact fee appeals for the first town council meeting
following ten days from receipt of the written notice of appeal to the town council.
Postponements of the town council appeal date may be granted by the town administrator if
they are requested in writing at least ten days in advance of the scheduled town council meeting
date.
e. When an appeal is scheduled for oral presentation before the town council, the appellant and
town staff shall each be given ten minutes at the oral argument to present the appeal and to
discuss the submitted written record.
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 19 of 20
(2) Payment under protest. A fee payer may pay development impact fees under protest. Payment under
protest does not preclude the developer from filing an administrative appeal, nor is the fee payer
estopped from receiving a refund of an amount considered to have been collected ill egally. A fee
payor, at his option, may also post a bond or submit an irrevocable letter of credit for the amount of
development impact fees due instead of making a cash payment under protest, pending the outcome
of an appeal.
(3) Mediation. Town council shall provide for mediation by a qualified independent party, upon voluntary
agreement by both the developer and the town, to address a disagreement related to development
impact fees calculated by the town. Neither a request for, nor partici pation in, mediation shall preclude
a fee payor from pursuing other developer rights or remedies otherwise available by law.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-115. Refunds.
(a) General provisions. Funds not obligated for expenditure within three years of the date that they are
scheduled to be expended in the Town of Summerville Capital Improvements Plancapital improvements plan
shall be refunded to the record owner of property for which the impact fees were paid, with actual interest
earned, on a first-in, first-out basis. For the purpose of determining whether fees have been spent or
encumbered, the first money placed in a trust fund account shall be deemed to the first money taken out of
that account when withdrawals have been made.
(b) Refund process.
(1) The owner of property eligible for a refund of one or more development impact fee payments shall
submit to the town building official a notarized sworn statement that the person is the current owner
of the property for which a refund is due, a certified copy of the latest recorded deed, and a copy of
the most recent ad valorem tax bill for the property.
(2) When a right to a refund exists, the town shall send a refund to the current owner of record within 90
days after it is determined by town council that a refund is due.
(3) All refunds shall include the pro rata portion of the interest earned while on deposit in the specific
development impact fee trust account.
(4) A record owner of property for which one or more development impact fee refunds are due has
standing to sue for such refund pursuant to Section 6-1-1020(D) of the Act, if there has not been a
good-faith effort towards a timely payment of a refund pursuant to subsection (b)(2) of this section.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-116. Review.
(a) Town council shall be responsible for preparing and publishing an annual report describing the amount of
development impact fees collected, appropriated, and spent during the preceding fiscal year , consistent with
the impact fee study update and the Act.
(b) Planning commission shall be responsible for a holistic review and update of the Town of Summerville Capital
Improvements Plancapital improvements plan, Town of Summerville iImpact fFee study uUpdate, and the
Development Impact Fee Ordinance for the Town of Summerville in the same manner and on the same
review cycle as the Town of Summerville Comprehensive Plan.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 9, 3-10-2022)
Created: 2026-01-12 08:06:21 [EST]
(Supp. No. 18, Update 2)
Page 20 of 20
Sec. 20-117. Termination of development impact fee.
Development impact fees for the Town of Summerville shall be terminated within 15 years after the effective
date of this section, or when sufficient fees have been collected to fund all of the projects eligible for development
impact fee funding that are identified in the Town of Summerville Capital Improvements Plancapital improvements
plan, whichever shall first occur, unless:
(1) Town council adopts a revised Town of Summerville impact fee study Impact Fee Update update or
amends the Town of Summerville Capital Improvements Plancapital improvements plan for a
subsequent amount of time; or
(2) Town council adopts an updated Development Impact Fee Ordinance for the Town of Summerville
pursuant to the substantive and procedural requirements set forth in the South Carolina Development
Impact Fee Act, as amended.
(Ord. No. 10-0802, 10-13-2010; Ord. No. 22-0201, § 10, 3-10-2022)
Sec. 20-118. Liberal construction.
The provisions of this article shall be liberally construed to effectively carry out its purpose in the interest of
further promoting and protecting public health, safety, welfare and convenience.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-119. Severability.
(a) If any section, subsection, sentence, clause, phrase or portion of this article is, for any reason, held invalid or
unconstitutional by any court, such section, subsection, sentence, clause, phrase or portion of this article
shall be deemed to be a separate, distinct, and independent provision and such holding shall not affect the
validity of the remaining provisions of this article, nor impair or nullify the remainder of these provisions
which shall continue in full force and effect.
(b) If the application of any provision of this article to any new development is declared to be invalid by a
decision of any court, the intent of the town council is that such decision shall be limited only to the specific
new development expressly involved in the controversy, action, or proceeding in which such decision of
invalidity was rendered. Such decision shall not affect, impair, or nullify this article as a whole or the
application of any provision of this article to any other new development.
(Ord. No. 10-0802, 10-13-2010)
Sec. 20-120. Effective date.
This article shall become effective upon adoption by the Summerville Town Council.
(Ord. No. 10-0802, 10-13-2010)
Secs. 20-121—20-150. Reserved.
RESOLUTION
A RESOLUTION RECOMMENDING THE TOWN OF SUMMERVILLE TOWN COUNCIL TO APPROVE THE
CAPITAL IMPROVEMENTS PLAN (CIP) AND A REVISED IMPACT FEE ORDINANCE, IN ACCORDANCE
WITH, THE SOUTH CAROLINA DEVELOPMENT FEE ACT, S.C. CODE OF LAWS § 6-1-910, ET SEQ. (THE
DEVELOPMENT IMPACT FEE ACT):
WHEREAS, by the Summerville Town Council Resolution adopted February 13, 2025, the Summerville Planning
Commission was directed to review and make recommendations for an amended Capital Improvements Plan and a revised
impact fee ordinance; and,
WHEREAS, the Town of Summerville desires to review the Capital Improvements Plan and revise the Impact Fee Ordinance
within the Town of Summerville for the primary purpose of funding capital projects and improvements; and,
WHEREAS, in order to review and make recommendations for an amended Capital Improvements Plan and revised Impact
Fee Ordinance, the Town of Summerville Town Council as required, directed the Town of Summerville Planning Commission
to review and make recommendations for an amended Capital Improvements Plan and revised Impact Fee Ordinance,
pursuant to S. C. Code of Law § 6-1-910, (1976, as amended); and
WHEREAS, the South Carolina Development Impact Fee Act requires that the Planning Commission prepare a
recommendation to the City Council in regard to a capital improvements plan and impact fees by service unit; and
WHEREAS, the Town directed staff to employ a consultant to conduct a study to develop updated impact fee amounts and a
capital improvements plan; and
WHEREAS, the Town Planning staff did contract with TischlerBise, a Land Use and Economics Firm with decades of
experience in developing impact fee studies in South Carolina and around the country; and
WHEREAS, TischlerBise also has prepared a report which estimates the effect of recovering capital costs through impact
fees on the availability of affordable housing within the political jurisdiction of the Town, as required by the Development
Impact Fee Act; and
WHEREAS, the Planning Commission has accepted the study and affordable housing report from TischlerBise, including a
capital improvement plan, and has developed a revised and updated ordinance in support of the update capital improvement
plan, land use assumptions, and the impact fee calculations update; and
NOW, THEREFORE, BE IT RESOLVED by Town of Summerville Planning Commission, in a meeting duly assembled,
makes the recommendation for the Summerville Town Council to approve the proposed amended Capital Improvements Plan
and impact fee study update, dated April 15, 2026 and revised Impact Fee Ordinance consistent therewith.
DONE this 20th day of April, 2026.
SUMMERVILLE, SOUTH CAROLINA
__
Jim Reaves, Chairman, Planning Commission; or,
Hart Weatherford, Vice Chairman, Planning Commission
ATTEST:
Jessi Shuler, AICP
Director of Planning
2
ANNEXATION & ZONING
STAFF REPORT
PLANNING COMMISSION
April 20, 2026
Owner: James Jamal Simpson
Applicant: Tashya Norman
TMS#s: 154-06-02-001
Location: Beverly Drive
Description: one lot, approximately 1.24 acres
Request: Rezoning to N-R
The property owners are requesting for the above-referenced parcel to be rezoned from the current
zoning of GR-5 to N-R.
This property is included in the Town’s ‘ Mixed Residential ’ area as identified within the
Summerville: Our Town, Our Future Comprehensive Plan as well as on the accompanying Future
Land Use Map, which includes both detached and attached single -family properties to allow for
flexible and denser development in proximity to the Town’s major roadways . Development along
these roadways should be consistent in design and character throughout. Attached residences can
include townhouse or duplex residential properties. This property also falls within the Infill area in the
growth strategy included in the Land & Development element of the Comp Plan. The Infill growth
area supports the development of vacant properties and redevelopment of underutilized properties
already served by infrastructure within established areas of the Town. The Housing and
Neighborhoods element of the Comp Plan also states that the Town should focus new development at
infill locations within existing neighborhoods to prevent the unnecessary extension of infrastructure
and services, and promote missing middle housing options (duplexes, triplexes, multiplexes, courtyard
apartments, and townhouses) on infill parcels within single -family neighborhoods, as well as
throughout Summerville to increase density and maintain neighborhood character.
The property was previously owned by Summerville CPW and was sold to Mr. Simpson in 2023. The
property was a part of the original Jamison Terrace subdivision, shown as Lot 30 in Block 10 on the
subdivision plat recorded on March 22, 1977. As stated on that plat, the property is subject to the
recorded protective covenants of the subdivision. Staff’s understanding is that the applicant is
proposing to build a quadraplex on the property; however, the protective covenants could present a
challenge to this proposal as they only allow for single-family detached homes and do not allow for
subdivision of the lots to create any new lots.
While the proposed use of the property appears to be in line with the goals of the Comprehensive Plan,
the zoning request for N-R zoning would allow for development that is in violation of the protective
covenants of the Jamison Terrace subdivision, and there is no N-R zoning anywhere in the vicinity of
the property. The property owner can seek to be released from the covenants, but that is a legal
process that may take some time to be completed. Staff recommends that the property owner pursue
the process to be released from the covenants prior to moving forward with the rezoning request.
EagleRidgeRd
Bill Park Dr
Hunters WoodDr
Iris St
Creek BendDr
BeverlyDr
Barbara Dr
SandraLn
Vickie St
EvaDr
Glenda Vw
SoniaDr
Rezoning Exhibit - TMS#154-02-06-001 - GR-5 to N-R
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, © OpenStreetMap
contributors, and the GIS User Community
Road Centerlines
ROAD- Dorchester County
ROAD- Town of Summerville
Summerville Parcels
PUD
GR-5
PL
Dorchester Parcels
4/13/2026
0 0.04 0.080.02 mi
0 0.07 0.130.03 km
1:3,010
Eagle Ridge Rd
EagleRidgeRd
Beverly Dr
Bill Park Dr
Hunters Wood
Dr
BeverlyDr
Iris St
Cre ek Bend Dr
BeverlyDr
Barbara Dr
SandraLn
Vickie St
EvaDr
Glenda Vw
SoniaDr
Rezoning Aerial Exhibit - TMS# 154-02-06-001 - GR-5 to N-R
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, (c) OpenStreetMap
contributors, and the GIS User Community, Source: Esri, USDA FSA,
Road Centerlines
ROAD- Dorchester County
ROAD- Town of Summerville
Dorchester Parcels
4/13/2026
0 0.04 0.080.02 mi
0 0.07 0.130.03 km
1:3,010
3
REZONING
STAFF REPORT
PLANNING COMMISSION
April 20, 2026
Owner: Trilogy Properties of Summerville
Applicant: Natasha Robinson
TMS#: 137-09-01-011
Location: 727 Central Avenue
Description: one property, approximately 0.37 acres
Request: Rezoning to N-B, Neighborhood Business, from GR-5, General Residential (5
units/acre)
The applicant is requesting the above-referenced parcel be rezoned from GR-5 to N-B. No reason was
detailed in the rezoning application.
This property is included in the Town’s ‘Mixed Residential’ District within the Summerville: Our
Town, Our Future Comprehensive Plan as well as on the accompanying Future Land Use Map. The
Mixed Residential designation includes both detached and attached single-family properties with a
density between 5-12 units per acre.
This is the last property fronting Central Ave. on the south side of the road from the 700 block through
the 900 block that is not zoned for either neighborhood or general business use (733 Central Ave. was
rezoned to N-B in 2023 and 801 Central and the property behind it in 2024). The property to the rear
of this property is still zoned for residential use, so a 30-foot vegetated buffer will be required along
that property line if a change of use to commercial is permitted, but otherwise the adjacent property is
zoned N-B to the west and PUD (apartments) to the east. The property currently has a residential
structure that is being used as a duplex, which would be a nonconforming use under the current GR-5
zoning district.
Although the proposed zoning does not meet the Town’s Future Land Use Plan, given the surrounding
zoning and the location of the property, the zoning of N-B is recommended for approval, as long as
this property, if redeveloped is done in full conformance with the UDO standards and is compatible
with the residential properties behind it. In addition, the rezoning to N-B would bring the existing
duplex use into conformance, as a duplex is a permitted use in that zoning district.
ParkwoodDrive
Flud
Street
Germantown Road
PineWatersLane
EthelmaeLane
AtlanticStreet
Central Avenue
Central Avenue
Germantown Road
Rezoning Exhibit - TMS# 137-09-01-011 - GR-5 to N-B
Sources: Map data © OpenStreetMap contributors, Microsoft, Esri
Community Maps contributors, Map layer by Esri
Road Centerlines
ROAD- Private
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
ROAD-TOS under developer warranty
Summerville Parcels
PUD
GR-5
N-R
MF-R
N-B
AC
Dorchester Parcels
4/13/2026
0 0.04 0.080.02 mi
0 0.07 0.130.03 km
1:3,010
Parkw
ood
Dr
Flud
St
Germantown Rd
Atlantic
St
EthelM
ae
Ln
Central Ave
Central Ave
Charlie
Ln
Germantown Rd
Rezoning Exhibit Aerial - TMS# 137-09-01-011 - GR-5 to N-B
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, (c) OpenStreetMap
contributors, and the GIS User Community, Source: Esri, USDA FSA,
Road Centerlines
ROAD- Private
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
ROAD-TOS under developer warranty
Dorchester Parcels
4/13/2026
0 0.04 0.080.02 mi
0 0.07 0.130.03 km
1:3,010
4
REZONING
STAFF REPORT
PLANNING COMMISSION
April 20, 2026
Owner: David L. & Kimberly D. Garber
Applicant: Charpia & Hammes, LLC
TMS#: 137-07-16-001
Location: 103 S. Magnolia St.
Description: one property, approximately 0.34 acres
Request: Rezoning to N-MX, Neighborhood Mixed-Use from GR-2, General Residential (2
units/acre)
The applicant is requesting for the above-referenced parcel to be rezoned from the current zoning of
GR-2 to N-MX. The following reasoning is stated on the application:
We own a small business (law practice) and would like to run that small business at this location.
This property is included in the Town’s ‘Single -Family Detached’ area as identified within the
Summerville: Our Town, Our Future Comprehensive Plan as well as on the accompanying Future
Land Use Map, which includes detached single -family uses with a typical density of 2 -5 units per
acre.
This block is all zoned GR-2, as is the block across E. Richardson Ave. The properties directly across
S. Magnolia St. are zoned N-MX. There are properties on the next block further down E. Richardson
that are zoned N -MX as well. The intention of the N -MX zoning was to buffer the more intense D -
MX uses from the residential properties in the GR-2 zoning district. A request to rezone the opposite
corner of the block to D-MX was denied by Town Council at their meeting on April 9th.
The proposed rezoning is outside of the area identified in the Comp Plan for Neighborhood Mixed-
Use or Downtown Transition. Staff is concerned about the N-MX zoning and the potential precedent
it could set for rezoning of the entire block and does not recommend approval based on the current
Comprehensive Plan.
Southern Railroad
S
Magnolia
St
E Doty Ave
E Luke Ave
The Icehouse
The James F.
Dean
Community
Theater
Frothy Beard
Off World
Brewery
Shelbourne
Law
Fleet Feet
AdaLease
Property
Management
Inc.
Mod Beauty
Salon
One Coast
Design
Lafond Law
Firm
O. Paul Culver,
III, DMD
Salley Wealth
Advisors
Group, LLC
S
Gum
St
E Luke St
E Luke Ave
Rezoning Exhibit - TMS# 137-07-16-001 - GR-2 to N-MX
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, © OpenStreetMap
contributors, and the GIS User Community
Road Centerlines
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
Summerville Parcels
GR-5
GR-2
D-MX
N-MX
Dorchester Parcels
4/13/2026
0 0.02 0.040.01 mi
0 0.03 0.060.01 km
1:1,505
Rezoning Exhibit - TMS# 137-07-16-001 - GR-2 to N-MX
Microsoft, Vantor
Road Centerlines
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
Dorchester Parcels
4/13/2026
0 0.02 0.040.01 mi
0 0.03 0.060.01 km
1:1,505
5
ANNEXATION & ZONING/REZONING
STAFF REPORT
PLANNING COMMISSION
April 20, 2026
Owner: Glenn G. Segelken
Applicant: SeamonWhiteside
TMS#: 137-00-00-003 and -007
Location: Parsons Rd. and 710 Central Ave.
Description: Two properties, approximately 72.58 acres total
Request: Annexation and zoning to PUD (TMS#137-00-00-003), Rezoning to PUD (TMS#137-
00-00-007)
The owner/applicant petitioned for a portion of the above-referenced parcels to be annexed and zoned
(TMS#137-00-00-003) and rezoned (TMS#137-00-00-007) PUD, Planned Development District. The
property for annexation is currently zoned TRM, Transitional Residential District, in Dorchester
County, and the property for rezoning is currently zoned AC, Agricultural Conservation, in the Town.
As the PUD is proposed to include both of these property, these agenda items will be considered
together in this staff report.
These properties are included in the Town’s ‘ Neighborhood Mixed Use’ area as identified within the
Summerville: Our Town, Our Future Comprehensive Plan as well as on the accompanying Future
Land Use Map, which “ is intended to encourage the integration of commercial and a variety of
residential land uses within easy walking distance of each other. Commercial uses should include
residentially scaled businesses, such as sales of consumer goods, health and personal care,
professional services, offices, restaurants, and religious institutions. Residential land uses such as,
townhomes, rowhouses, duplexes, live-work units, single-family housing and accessory dwelling units
are encouraged. Medium -to-high residential densities are recommended.” These properties also fall
in the Infill and Town Edges areas in the growth strategy included in the Land & Development
element of the Comp Plan. The Infill and Town Edges growth areas both support development of
vacant properties and redevelopment of underutilized properties within existing infrastructure service
boundaries. This property is also identified as a priority annexation area in the Community Facilities
and Infrastructure Element.
The PUD includes a mix of residential and commercial uses. The annexation and proposed uses are in
line with the Town’s Comprehensive Plan, and staff supports the overall annexation ; however, staff
has a few issues that they would like to see addressed before recommending final approval:
1. The inclusion of Gas Stations as a permitted use does not appear to be in line with the
intention of the Neighborhood Mixed Use are a description in the Comp Plan or the N -MX
zoning within the UDO. The stated intent is “to encourage the integration of commercial and
a variety of residential land uses within easy walking distance of each other,” and gas
stations, as an auto-oriented use are not compatible with this intent.
2. Preliminary townhome elevations must be included prior to final approval of the PUD.
3. Further discussion is needed with Engineering staff regarding the proposed final plat language
proposed in the PUD.
4. The percentage of improved open space and unimproved open space should both be based on
the total site acreage.
5. Buffers between the PUD and adjacent development need to be clarified. An exhibit detailing
required buffer widths and vegetation should be provided.
6. The location of stands of pine trees planted for timbering proposed to be removed without
mitigation (timbered) should be shown on an exhibit and it should be notated that best
management timbering practices will be utilized.
6
7. The require d letters of coordination must be provided prior to final PUD approval. It is
staff’s understanding that Summerville CPW will be the water and sewer provider, as
Dorchester County Water & Sewer will be releasing their sewer service area to SCPW. This
will require approval from Dorchester County Council , and once completed , the PUD
document must be updated accordingly.
8. The conceptual master plan for the proposed PUD needs to provide more detail including
proposed roadways, buffers, and any proposed stub-outs to adjacent properties.
9. The Traffic Impact Analysis (TIA) i s currently in process. The final TIA must be completed
and included in the PUD document prior to PUD approval.
STATE OF SOUTH CAROLINA )
) P E T I T I O N F O R A N N E X A T I O N
C O U N T Y O F )
TO THE HONORABLE MAYOR AND TOWN COUNCIL OF SUMMERVILLE
WHEREAS, SECTION 5-3-150 (3) C ode of laws of South Carolina provides for the annexation of an
area or property which is contiguous to a Town by filing with the municipal governing body a petition signed
by all persons owning real estate in the area requesting annexation, and
WHEREAS, the undersigned are a ll persons owning real estate in the area requesting annexation, and
WHEREAS, the area requesting a nnexation is described as follows, to wit:
S A I D P R O P E R T Y , l o c a t e d a t ( a p p r o x i m a t e l y a c r e s ) to be annexed
is identified by the C ounty Assessor’s Office as Property Identification Number:
T M S # t o i n c l u d e , i f necessary to establish contiguity, any road,
waterway, easement, railroad track, marshland or utility line that intervenes between this property and the
municipal limits of the Town of Summerville.
NOW, THEREFORE, the undersigned petition the Town Council of Summerville to annex the above described
area into the municipal limits of the Town of Summerville.
Dated this day of , 2018.
FREEHOLDERS (OWNERS) SIGNED DATE OF SIGNATURE
( S i g n a t u r e ) ( D a t e )
(Print Name)
( S i g n a t u r e )
( D a t e )
(Print Name)
DORCHESTER
62
CENTRAL AVE, PARSONS RD
DORCHESTER
137-00-00-003
3/24/2026
Glenn G Segelken
March, 2026
24
Parsons
Rd
King Mountain Dr
Canvasback Dr
Poconos Ct
W
oodduck Dr
Parsons
Rd
Pintail Dr
Canvasback Dr
Drake
Ct
W
oodduck
D
r
BriarwoodLn
Parsons Rd
Willis Ln
Quinby St
Scott Ct
Atlantic
St
Charlie
LnFlud
St Colleton Ave
Atlantic
St
EthelM
ae
Ln
Central Ave
Annexation & Zoning/Rezoning Exhibit - Green Fields PUD
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, © OpenStreetMap
contributors, and the GIS User Community
Road Centerlines
ROAD- Dorchester County
ROAD- Private
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
Summerville Parcels
PUD
GR-5
GR-2
N-R
G-B
N-B
AC
Dorchester Parcels
4/13/2026
0 0.09 0.170.04 mi
0 0.1 0.20.05 km
1:6,019
Parsons
Rd
Canvasback Dr
Poconos Ct
W
oodduck Dr
Parsons
Rd
Pintail Dr
Canvasback Dr
Drake
Ct
W
oodduck
Dr
BriarwoodLn
Parsons Rd
Willis Ln
Quinby St
Scott Ct
Atlantic
St
Central Ave
Flud
St Colleton Ave
Atlantic
St
EthelM
ae
Ln
Central Ave
Cent ral Ave
Annexation & Zoning/Rezoning Exhibit Aerial - Green Fields PUD
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, (c) OpenStreetMap
contributors, and the GIS User Community, Source: Esri, USDA FSA,
Road Centerlines
ROAD- Dorchester County
ROAD- Private
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
Dorchester Parcels
4/13/2026
0 0.09 0.170.04 mi
0 0.1 0.20.05 km
1:6,019
GREEN FIELDS
MIXED USED DEVELOPMENT
DESIGNED BY:
SeamonWhiteside
501 Wando Park Boulevard, Suite 200
Mt. Pleasant, SC 29464
(843) 884-1667
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
Table of Contents
Section 1: General Description of the Proposed Proj ect
Section 2: Land Uses and Intensities
Section 3: Development Criteria
Section 4: Open Space
Section 5: Tree Regulations
Section 6: Traffic, Streets, and Parking
Section 7: Storm Water Management
Section 8: Letters of Coordination
Section 9: Development Schedule
Section 10: Exhibits
1. Survey
2. Municipal Plan
3. Conceptual Master Plan
4. Traffic Study
5. Conceptual Drainage Master Plan
6. N-MX Zoning Criteria
7. Preliminary Townhome Elevations
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 1: GENERAL DESCRIPTION OF THE PROPOSED PROJECT
This project is two tracts, including 62 acres in Dorchester County and 10 acres in the Town of
Summerville. The primary uses are currently agricultural with a pine tree farm and horse
stables.
Primary frontage is along Parsons Avenue, across from the Summit, and Central Avenue, west
of the Summerville Estates retirement community. There is also frontage along Atlantic Street,
Maude Avenue, and Third Street. The project shares a property line with various residential lots.
The TMS numbers and acreage for the property are:
1. 137-00-00-003 62.31 Acres Segelken Family Limit ed Partnership
2. 137-00-00-007 10.27 Acres Segelken Family Limit ed Partnership
The property owners are requesting annexation of a portion of the Dorchester County parcel
and Planned Unit Development (PUD) zoning for the overall acreage in accordance with Section
2.10 of the Town of Summerville Unified Development Ordinance (UDO) to allow a mixture of
land uses including single family detached, single family attached, and Neighborhood
Commercial.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 2: LAND USES AND INTENSITIES
The family intends to continue to enjoy the land for some time in the same manner and uses
they have for generations. This PUD would preserve those rights as long as the family
continues to own the land. Any portion of land retained by the seller and not designated for
commercial use will have the below listed rights.
The existing uses on the family land are currently:
• Farming and all uses incidental to farming, raisin g livestock, boarding horses, equipment
storage, fueling and repair
• Hunting, although the discharging of firearms will no longer be permitted
• Timbering operations
• Burning of fallen trees and debris
• RV, tractor, boat and storage
• Boarding of horses and livestock including but not limited to pigs, hens, and roosters
The maximum single-family intensity and minimum neighborhood commercial area are as
follows:
Land Use Anticipated Area Maximum Intensity
Single-Family 66.68 Acres 350 Units
Land Use Anticipated Area Minimum Area
Neighborhood Commercial 5.90 Acres 2.00 Acres
Allowable land uses
A. Single Family Residential Zone
(Residential uses currently allowed in the Town of Summerville, or currently under use
on the property.)
• All residential uses will follow N-MX zoning.
• Parks, playgrounds, clubhouses, amenity centers, s chools, swim clubs and
cemeteries
• Churches
• Home occupations
• Model homes & sales office
• Accessory dwelling units
B. Neighborhood Commercial Zone
(All those uses listed above plus the following)
• All uses currently allowed in the Town under N-MX zoning
• Gas Stations
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
• Hotels, Extended Stay with no room limit
• Veterinary Services
• Alcohol Beverage Sales Stores
• Bars & Taverns
• Entertainment – Indoor
• Continuing Care Retirement Facilities (Skilled Car e, Assisted Living, or Nursing
Home units that do not have full kitchens do not count towards residential density)
• Nurseries and garden centers
• Bus Rapid Transit Stops (BRT’s)
The Planning Department shall review the project as building permits are requested to
ensure that the proposed uses are compatible with those defined within the PUD.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 3: DEVELOPMENT CRITERIA
3.1 CONFIGURATION AND BUILDING PLACEMENT
Lot configuration and building placement shall follow UDO Section 2.5 N-MX standards at the
time of PUD approval (see Section 10 Exhibit 6) with the following exceptions:
1. The attached garage setback must be equal to or behind the front facade. Attached
garages along frontage shall be allowed. Parking shall be allowed in front of the garage.
2. Minimum front yard when parking is provided in r ear of fee simple townhouses shall be
10 feet.
3. Minimum front yard when parking is provided in t he front for single family shall be 20
feet.
4. Driveway curb cuts shall be a maximum of 3’ from the next adjoining property line.
5. A model home court consisting of up to four (4) model homes and an associated
temporary parking lot may be constructed within the project. Such model homes are
permitted to deviate from typical lot configuration and placement standards as needed to
support marketing and sales activities.
3.2 GENERAL REQUIREMENTS FOR LOTS
1. Corner lots will require only one front setback. Front setback shall apply to the shorter
property line and side setback shall apply to the longer property line.
2. Accessory structures are permitted in the rear a nd side yards only with indicated minimum
setbacks from the side and rear property lines or ingress/egress easements, whichever is
greater.
3. Building heights are measured to the eave of str ucture. The maximum building height in
Neighborhood Commercial areas shall be 55’. Building height for single-family residential
shall be limited to 3 stories.
4. Maximum block length requirements are void where the site layout is constrained by
property or environmental factors. Maximum block le ngth may be extended to 800’ with
either a traffic calming device on the adjacent roadway or a mid-block path.
5. Subdivision of lots shall be allowed off private roads and alleys where the lots are fronting
open space. There shall be no maximum.
3.3 ARCHITECTURAL REQUIREMENTS FOR TOWNHOMES
Townhomes shall not require DRB approval so long as they conform to the below set of
requirements. Preliminary elevations have been incl uded in the PUD documents. Any deviation
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
from the elevations will require approval from Town of Summerville Staff.
1. Townhomes shall utilize pitched roofs and roof o verhangs
2. Quality material and facade detailing shall exte nd to all facades which are visible or
are expected to be visible from a public or private street and other public spaces,
and/or from primary vehicular access points or parking areas.
3. Different materials on different exterior elevations are allowed on the same structure
so long as those materials maintain the architectural unity and integrity of the entire
structure (i.e., there may be brick and wood on the same building).
4. No more than four colors complementary to each othe r will be allowed on the
building.
5. Piecemeal embellishment and frequent changes in mat erial and color shall be
avoided.
6. Multiple materials on the same roof line are genera lly discouraged. Shingled and
aluminum roof on the same house are allowed.
7. The following materials shall not be allowed as siding; sheet plywood, concrete block
(CMU), unfinished poured concrete block, and plastic or metal not closely resembling
painted wood clapboard.
8. All buildings other than garages should be designed to include varied relief to provide
interest and variety.
9. Wall Materials:
1. Building walls will be fiber cement board such a s “Hardie-Plank” siding, 50-year
siding product, wood, termite resistant.
2. Visible foundation walls should be finished in o ne of the following materials:
Brick, Stucco, finished or painted concrete.
3. Chimneys: Chimneys should be finished with appro ved building wall materials.
4. Downspouts and Gutters: Downspouts and gutters a re to be galvanized steel,
aluminum, nonglossed stainless steel or copper. Dow nspouts and gutters are
to match in materials and finish.
5. Day-glo, luminescent, iridescent, neon or simila r types of color finishes are
prohibited.
6. Mirrored glass with a reflectivity of 20% or mor e and spandrel is prohibited.
10. Windows:
1. Windows should not be flush with exterior wall t reatments. Windows should be
provided with an architectural surround at the jambs, header and sill.
2. In general, clear glazing is preferred, but atti c windows may utilize blackout
glazing to hide framing.
3. Except for round windows, picture windows, accen t windows, and transoms,
windows and door openings should be taller than the y are wide. Supersliders
are permitted in the rear of homes.
4. Exterior Shutters shall be allowed on all residential buildings if the shutters cover
the full window.
11. Roofs:
1. Skylights must be flat to the pitch of the roof and should not be located on any
sloped roof facing the primary frontage.
2. Roof penetrations shall be hidden or painted to match the color of the roof.
12. Attached Garages and Accessory Structures:
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
1. Attached garages, detached garages and other acc essory structures, shall be
subordinate in height, footprint, and proportion to the primary structure on the
site, and shall be compatible with the principal st ructure in terms of roof form,
materials, and color.
13. Entrances:
1. Building Entrances to Face Street or Public Open Space: All townhome
buildings should face the street or designated publ ic space (e.g., common
courtyard, plaza, or green) and have a pedestrian p athway connecting the
principal entry to the street. All buildings with s hared entrances should be
oriented so that the primary entrance(s) faces the street.
2. Raised Entry Required: The finished ground floor elevation for units within 18
feet of a sidewalk shall be 18 inches above the ave rage adjacent sidewalk
grade, or 2 feet above the adjacent street grade where no sidewalk is present.
3. Buildings must be designed to provide varied rel ief through the use of porches,
balconies, shutters, projected dormers, variation in roof lines, or decorative caps
on chimneys.
4. Zero-Step Entry: For residential buildings in de velopments designed for
residents aged 55 and older, at least one zero-step entry should be provided
from the fronting sidewalk or pedestrian pathway fr om the side or rear to the
interior of the house. Each unit should have a sepa rate outdoor entrance that
includes a porch, stoop, courtyard or similar element which provides a transition
from the public sidewalk to the private space within the building or unit.
5. Secondary Entries Permitted: Individual units an d tenant spaces on the ground
floor may have separate entrances to the public sid ewalk, but units on upper
floors must be accessed through a common entrance on the ground floor.
6. Corner Lot/Entry: In the case of corner lots, th e primary entrance(s) should face
the street from which the building derives its street address.
14. Facade Transparency:
1. Building elevations that face the street should have at least 20% of the wall area
consisting of windows and/or doors. Mirrored glass with a reflectivity of 20% or
more is prohibited.
15. Cornice and Expression Lines:
1. Cornices and other similar elements are required to delineate the tops of
facades. Expression lines are required to delineate the divisions between the
first floor and upper floors.
3.4 FLEXIBILITY OF USES OF TRACTS
The Development Plan and acreage must maintain flexibility to accommodate specific soil
conditions, environmental concerns, physical constraints, market conditions, design
parameters, and changing trends and strategies in planning and development. Accordingly,
the exact location of boundary lines between tracts, the location and size of land uses
indicated within the planned areas, and the preliminary design concepts for the tracts and
uses described in this PUD shall be subject to change as phases of the Development Plan
are submitted for final review over the life of the Project; provided, however, that the allowed
land uses described in this Ordinance shall be strictly adhered to.
3.5 CURRENT REGULATIONS
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
The Default Regulations shall be the Town of Summerville’s Zoning Ordinance in effect at the
date of PUD approval. Should this PUD not specifically address certain zoning or
development standards, it will be subject to the Default Regulations (UDO).
3.6 SUBDIVISION PLAN REVIEW AND APPROVAL
Preliminary plans and final plats for each phase of the development shall be submitted for
review and approval by the appropriate Summerville authority pursuant to the provisions of
the Default Regulations. The following modifications have been incorporated into this PUD:
• Final Plats (with conditions) recording the dedica ted roadways and adjacent
development parcels for all uses are allowed when construction of roadways and
related infrastructure are not complete. For these Final Plats to be approved, an
acceptable performance bond amount of 150% of the remaining roadway
infrastructure (base course, asphalt, curb, underdrain only), street tree, sidewalk, and
open space improvement costs (at the time of plat recording) must be submitted to
and approved by the Town of Summerville. No Certificate of Occupancy shall be
issued for any building on adjacent development tracts until the roadway items
covered by the bond are completed, inspected and approved by the Town of
Summerville and a maintenance bond is issued to the Town, and Permits to Operate
the associated water and sewer systems are issued by SCDES, if applicable.
• Single-family attached product (townhomes) shall n ot require DRB review and
approval such that the architectural requirements defined within this PUD are met.
Commercial development will still require DRB review and approval.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 4: OPEN SPACE
4.1 OPEN SPACE
The intent of open space within this project is to:
• Provide park space that provides pedestrian and ga thering opportunities
• Preserve significant hardwood forested tree lines and grand trees
• Conserve areas which are inappropriate for develop ment because they contain
wetlands or wetland buffers
4.2 IMPROVED OPEN SPACE
Minimally, five percent (5%) of the total site acreage shall be devoted to improved open space.
Developable areas shall be defined as the total highland minus wetlands and required buffers.
Improved open space can include:
• Wetland buffers with trails
• New storm water ponds (if amenitized with pathways , boardwalks, piers, or landings,
etc.)
• Amenity centers, playgrounds, sports courts, commu nity gathering areas
• Landscape buffers with trails, boardwalks, paths, or other similar uses
Improved Park Spaces will be provided through neighborhood parks, squares and greens,
amenity centers, or playgrounds. These parks shall not be confined to one area but should
blend throughout the development.
These areas shall be landscaped or natural and may include benches, bike racks, other site
furnishings and shall serve as gathering areas for both the residential neighborhood and
neighborhood commercial areas. Designs of these areas shall be submitted to Town staff for
approval and compliance with this PUD.
4.3 UNIMPROVED OPEN SPACE
Minimally, five percent (5%) of the developable areas shall be devoted to unimproved open
space. Unimproved open space will be provided through existing wetlands, wetland buffers,
natural property line buffers, or preserved natural areas.
4.4 WETLAND AND WATERCOURSE BUFFERS
Wetland buffers shall have an average depth of 25’ with a minimum depth of 10’ and shall
otherwise default to the Summerville code.
Buffers on existing drainage ditches that are deemed jurisdictional by the determination of the
U.S. Army Corps of Engineers may be reduced to 10’ on each side of the top of bank such that
the following conditions are met:
1. The buffers are planted with (80) 3-gallon nativ e grasses per 100 linear feet
2. The buffers are planted with (6) native understo ry trees per 100 linear feet
3. The buffers are planted with (3) native canopy t rees per 100 linear feet
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
4.5 INTERNAL BUFFERS
Internal buffers shall be required between commercial parking lots and adjacent rights-of-ways
or residential areas and shall meet the following requirements:
• Evergreen hedges and canopy trees at (3) per 100 l inear feet.
• Evergreen hedges shall be maintained at 3’ minimum height.
• Required hedges and canopy trees shall be provided on the commercial lot
where commercial use borders residential use.
4.6 MAINTENANCE OF PARKS AND OPEN SPACE
Unless accepted for dedication or otherwise agreed to by the Town of Summerville, another unit
of government, or a private non-profit land conservancy, the cost and responsibility of
maintaining Park or Open Space and any associated facilities shall be the responsibility of the
HOA.
Natural features may be maintained in their natural condition or may be modified to improve
their appearance, functionality, or overall condition, pending the approval of Town of
Summerville Staff. Permitted modifications may include:
• Reforestation
• Woodland management
• Pasture or cropland management
• Buffer area landscaping
• Stream bank protection
• Wetlands management
• Removal of invasive species
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 5: TREE REGULATIONS
5.1 TREE PROTECTION
A tree survey has been completed locating all trees 16” and larger and a ¼ acre sample area
representing trees 6” and larger. Prior to development of Neighborhood Commercial areas, a tree
survey shall be conducted to locate all trees 8” or greater except for Sweet Gums or invasive trees
which are exempt.
Reasonable efforts during the planning process shal l be made to site structures around existing
Grand Trees.
Existing Grand Trees must be evaluated by a certifi ed arborist or registered landscape architect
in coordination with the Town arborist, prior to su bmitting Construction Documents and shall be
graded as follows: A – excellent; B - good; C – average; D – below average; or F – poor.
Trees to be removed are subject to the following mitigation guidelines:
Grade A & B – 100% mitigation of caliper inches removed
Grade C, D & F – no mitigation required
Mitigation trees shall be 2 ½” minimum caliper and of a species approved by the Town Arborist.
Exact locations of mitigation trees are subject to approval by town staff prior to installation.
Suitable areas may include public green spaces, rights of way, buffers, on lots, recreational
areas, etc.
Mitigation for residential areas will be calculated per phase but may be satisfied over the course
of the full residential project buildout such that the total residential mitigation is met.
Agricultural pine trees may be removed without miti gation. Any tree listed on the State of South
Carolina’s invasive species list (as published by the South Carolina Forestry Commission and/or
South Carolina Exotic Pest Plant Council) as either Severe Threat, Significant Threat, or
Emerging Threat may be removed without mitigation b ut will require approval from the Town of
Summerville.
Grand trees designated to be saved may be impacted by encroachment into their Protected Zone
by impervious surfaces up to 25% and/or grading by up to 33.3%. The Protected Zone is defined
as a circle of one foot in radius for every inch of caliper or a sum of calipers for multi-trunk trees.
Applications to remove or impact Grand Trees must i nclude a Site Plan prepared by a
Professional Engineer or a licensed Landscape Architect. The plans must identify the trees to be
removed and the trees to be retained. Grand Trees shall be color coded according to their Grade
as follows: A=Green, B=Blue, C=Yellow, D=Orange, and F= Red with circles coinciding with their
Protected Zone. The plan shall be accompanied by a general statement of hardship addressing
each A, B, and C tree individually and include an arborist care plan.
All trees, regardless of size, proposed to be remov ed can be approved at a Town staff planning
level and are not required to apply to the Town’s tree board.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
Areas already planted for timbering purposes, typic ally Pine stands, do not require protection or
mitigation.
Clearing plans will be per phase and may include th e clearing of all lot areas with initial mass
clearing operations.
5.2 STREET TREES & RESIDENTIAL LANDSCAPING
Street Trees shall be planted along both sides of all public streets and shall have an average
spacing of 40’.
Street trees shall be 2 ½” minimum caliper and of a species approved by the Town Arborist.
Street trees will be allowed to count towards mitigation.
If street trees are planted within the right of way between the curb and the sidewalk, the planter
strip shall be a minimum of five (5) feet wide for understory trees and seven (7) feet wide for
canopy trees. The tree will be planted near the center of the landscape strip, and no root barrier
is required.
The developer and/or subsequent HOA are responsible for the maintenance, trimming, and
replacement of all street trees. Trees in the public right of way and those on private property
which encroach into the public right of way above a public sidewalk must be maintained so that
the lowest limbs are a minimum of 7 feet above the grade of the sidewalk and street to create
an unobstructed movement zone for pedestrians.
Sidewalks shall be a minimum of 5’ width.
Developers shall coordinate the locations of streetlights with street trees to avoid conflicts.
Street trees shall be at least 15’ from streetlights and stop signs.
At road intersections, Canopy and understory trees shall be located a minimum of 25 feet from
the edge of travelway of the intersecting road (edge of pavement) to the center of the tree trunk.
Proper sight distance shall be observed.
Each single-family home shall have at least 1 tree planted anywhere on the lot. Town homes
shall have 1 tree per every two units. Trees shall be 2 ½” minimum caliper, to be planted on the
lot or adjacent right of way. If trees cannot be feasibly planted on a residential lot or within the
right of way adjacent to the lot, they may be planted in open space as approved by the Planning
Director or designee. Canopy trees planted on lots may count towards mitigation.
Canopy trees shall be planted at least 10’ from drainage and utility structures, measured to the
center of the tree trunk.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 6: TRAFFIC, STREETS AND PARKING
6.1 TRAFFIC STUDY
A traffic study has been requested via the Town’s Traffic Study Ordinance. Town staff can
provide the traffic study, or it will be included as an attachment to this document once finalized.
Supplemental traffic studies can be provided to outline and allow for required improvements
associated with the development of the site to be phased in accordance with the traffic counts
that necessitate each improvement.
6.2 STREETS
Primary vehicular access is planned to be on Parsons Road and Central Avenue. The exact
size and number of access points shall be determined by the traffic study and as allowed by
SCDOT.
There will be vehicular and pedestrian interconnectivity between the residential and
Neighborhood Commercial land uses.
Construction routes for different phases shall be allowed per approved construction documents.
Typical residential roadway section shall be a minimum of 8” of graded aggregate base course
and 1.5" intermediate asphalt course and 1.5" asphalt surface course. Increases to minimums
shall be allowed as specified by geotechnical engineer.
6.3 PARKING
Town of Summerville requirements for parking shall be met with the following exceptions:
• In Neighborhood Commercial areas, parking may be p rovided within 600’ of the site that
it serves and may include on-street parking such that it is only counted once.
• In Neighborhood Commercial areas, when an individu al block or lot within its boundaries
has more than one use, shared parking may be considered to satisfy minimum parking
requirements as approved by Town staff.
• Required parking for designated outdoor spaces and amenity areas outside of right-of-
way areas may be unpaved or non-hard surfaced utilizing slag, gravel, ROC, grasscrete
or similar pervious material, subject to site plan approval. Parking improvements within
right-of-way shall be paved or other hard surface type material (asphalt, concrete, etc.)
acceptable to the Town Engineer.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 7: STORM WATER MANAGEMENT
Runoff from developed property will be routed through detention pond systems prior to its
ultimate outfall. These ponds will be designed to limit post-development runoff to be lower than
pre-development rates. Temporary ditches, which will be maintained by the developer, may be
utilized.
Storm water within the tract will be routed by a combination of grassed swales, underground
piping, and overland flow into a series of ponds to be detained temporarily or permanently
before exiting the development. Detention areas will be appropriately landscaped and stabilized
in accordance with applicable regulations.
Storm water management will be designed and implemented in accordance with the Town of
Summerville’s development standards as well as the requirements of the South Carolina
Department of Environmental Services – Office of Ocean and Coastal Resource Management.
Storm water Best Management Practices (BMPs), Low Impact Development (LIDs), and other
accepted measures may be implemented to reduce post-development runoff rates and improve
storm water quality.
Upon completion and approval, the drainage system, except for ponds and LID practices, will be
dedicated to and maintained by the Town of Summerville.
A conceptual master drainage plan is provided in the appendix.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 8: LETTERS OF COORDINATION
The following list of letters of coordination or service letters will be submitted in the future prior
to the approval of any subsequent development plans for any portion of the PUD.
Sanitary Sewer System Dorchester County Water an d Sewer Department
and Summerville CPW
Domestic Water System Summerville CPW
Electric Dominion
Communications To be determined
Schools Dorchester District 2
All utilities will be installed underground. All underground utilities will be coordinated with the
applicable utility providers for review and approval, as needed, prior to installation within the
neighborhood.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 9: DEVELOPMENT SCHEDULE
A. Phases of Construction and Development
Green Fields will have a build-out program which could last over 10 years. The timing of
development will be very much affected by the health of the national and local economies,
as well as the demand for various housing types and other needs for the region. It is
extremely difficult, if not impossible, to accurately project timing of future phases of
development and parcel demand. The following estimates are based on information
believed to be reasonable at this time. The estimates are subject to change, from time to
time, based on market conditions, the supply of competing properties within the region, and
other factors not in control of the property owner.
B. 2026-2036
During the initial phase of development, the construction of infrastructure will begin on the
residential portion of the property. During this ten-year period, single family lot development
will occur. Roads will connect Green Fields to Parsons Road and Central Avenue. Various
amenities will be built within the single-family area and will be expanded from time to time to
accommodate and link future phases of development. Single family development during this
period should be in the range of 40-80 lots per year. It’s also reasonable to assume that
Neighborhood Commercial development could occur.
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
SECTION 10: EXHIBITS
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 1 – SURVEY
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 2 – MUNICIPAL PLAN
NOTE: THIS PLAN IS CONCEPTUAL IN NATURE AND SUBJECT TO CHANGE. ALL ACREAGES ARE APPROXIMATE.
P:\ACAD-D-3\10146\Landscape\Exhibits\24-10-05 Master Plan Graphic\Source Files\Master Plan Graphic.indd
MUNICIPAL BOUNDARY PLAN
GREEN FIELDS
SUMMERVILLE, SC
10/10/2024
DORCHESTER COUNTY
TMS# 137-00-00-003
(62 Acres)
TOWN OF
SUMMERVILLE
TMS# 137-00-00-007
(10 Acres)
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 3 – CONCEPTUAL MASTER PLAN
NOTE: THIS PLAN IS CONCEPTUAL IN NATURE AND SUBJECT TO CHANGE. ALL ACREAGES ARE APPROXIMATE.
“P:\ACAD-D-3\10146\Landscape\Exhibits\2026-02-23 Updated Exhibits for PUD\Master Plan Graphic.indd”
GREEN FIELDS
SUMMERVILLE, SC
02/23/2026
CONCEPTUAL MASTER PLAN
S
I
N
G
L
E
F
A
M
I
L
Y
SINGLE FAMILY
RESIDENTIAL
(61.1 Acres)
NEIGHBORHOOD
COMMERCIAL
(3.4 Acres)
NEIGHBORHOOD
COMMERCIAL
(2.5 Acres)
ANTICIPATED
USE TBD
(6 Acres)
N
E
I
G
H
B
O
R
H
O
O
D
C
O
M
M
E
R
C
I
A
L
PARSONS ROAD
PARSONS ROAD
CENTRAL AVENUE
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 4 – TRAFFIC STUDY
TRAFFIC IMPACT ANALYSIS
IS UNERGOING UPDATES,
UPDATED VERSION WILL BE
PROVIDED UPON RECEIPT
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 5 – CONCEPTUAL DRAINAGE MASTER PLAN
image
CONCEPTUAL STORMWATERDETENTION POND, TYP.
CONCEPTUAL ROADRIGHT-OF-WAY, TYP.DRAINAGE OUTFALL LOCATION
TMS #137-00-00-003SEGELKEN FAMILY LIMITED PARTNERSHIP
PARSONS ROAD
CENTRAL AVENUE
GREEN FIELDS TRACT PROJECT LIMITSLEGEND
EXISTING WETLANDCONCEPTUAL STORMWATER DETENTION PONDCONCEPTUAL STORMWATER PIPEDRAINAGE FLOW ARROW
NOTES:1.THIS PLAN IS CONCEPTUAL IN NATURE. THE SIZE AND LOCATION OF THE DETENTIONPONDS SHOWN ON THE EXHIBIT ARE APPROXIMATED. A DETAILED ENGINEERING ANALYSISWILL BE PERFORMED AT A LATER DATE TO DETERMINE THE ACTUAL SIZE, LOCATION, ANDDIMENSIONS OF THE DETENTION SYSTEM.2.THE USE OF UNDERGROUND DETENTION SYSTEMS AND/OR LOW IMPACT DEVELOPMENTPRACTICES MAY ALSO BE UTILIZED TO LIMIT POST-DEVELOPMENT RUNOFF RATES.3.ALL DRAINAGE FACILITIES MUST BE DESIGNED TO MEET APPLICABLE TOWN AND STATEREQUIREMENTS.
NOTE: THIS PLAN IS CONCEPTUAL IN NATURE AND SUBJECT TO CHANGE DRAWING IS NOT TO SCALE.
PLOTTED:3/24/2026 3:57 PM, BY Daniel Farrell P:\ACAD-D5-12700\13076\CAD Files\Exhibits\2026-03-24 Drainage Exhibit\Conceptual Drainage Exhibit.dwg
GREEN FIELDS TRACTCONCEPTUAL DRAINAGE EXHIBITSUMMERVILLE, SOUTH CAROLINAMARCH 24, 2026 SEWN
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 6 – N-MX ZONING CRITERIA
10
Summerville, SC UDO Adopted October 10, 2019 Last Amended January 15, 2026
2 Districts I 2.4 Mixed-Use Districts
2.4 MIXED-USE DISTRICTS
2.4.1 NEIGHBORHOOD RESIDENTIAL (N-R)
The Neighborhood Residential District is
established to accommodate a wide variety
of housing types in close walking or biking
proximity to Summerville’s mixed-use
centers.
2.4.2 NEIGHBORHOOD MIXED-USE (N-MX)
The purpose of the Neighborhood Mixed-
use district is to encourage diverse housing
and residentially-scaled professional services,
offices, small shops, limited lodging, and
restaurants directly adjacent to or in easy
walking distance of neighborhoods.
12
Summerville, SC UDO Adopted October 10, 2019 Last Amended January 15, 2026
2 Districts I 2.5 Mixed-Use District Standards
2.5 MIXED-USE DISTRICT STANDARDS
DISTRICT N-R N-MX D-MX UC-MX
Replaces Previous Districts R-3 / R-5 B-1 / some B-2 CBD/B-3 B-3 (redevelopment
areas)
1. DEVELOPMENT
A. Maximum Density N/A N/A N/A N/A
B. Required Open Space/Park Space
(Note 1) 5%/5% 5%/5% 2% if 5 acres or more 2% if 5 acres or more
C. Perimeter Buffer None unless adjacent to
existing GR-2 & GR-5
None unless adjacent to
existing GR-2 & GR-5
None unless adjacent to
existing GR-2 & GR-5
None unless adjacent to
existing GR-2 & GR-5
2. LOT CONFIGURATION
A. Lot Size N/A N/A N/A N/A
B. Maximum Lot Coverage (Note 2 & 9) 50% of lot area 80% of lot area 100% 100%
C. Frontage Buildout N/A 35% min 35% min N/A
D. Lot Width at Front Setback 15 ft N/A N/A N/A
3. PRIMARY BUILDING PLACEMENT (NOTE 3)
A. Front Setback 10 ft min 0 ft min 0 ft min 0 ft min
N/A N/A N/A N/A
B. Side Setback - Corner 10 ft min 0 ft min 0 ft min 0 ft min
N/A N/A N/A N/A
C. Side Setback - Interior
0 feet or 10 ft min
between detached
buildings
0 feet or 10 ft min
between detached
buildings
N/A N/A
D. Rear Setback (Note 4) 20 ft min 5 ft min 5 ft min 5 ft min
E. Rear Setback from Alley (Note 5) 3 ft 0 ft 5 ft 5 ft
F. Attached Garage Setback (from front
facade) (Note 4 & 6)
5 ft min behind primary
façade (detached homes
only - not permitted
otherwise)
Attached garages along
frontage are prohibited
Attached garages along
frontage are prohibited
Attached garages along
frontage are prohibited
4. ACCESSORY BUILDING PLACEMENT (NOTE 4)
A. Side Setback - Corner 5 ft min 3 ft min 2 ft min 2 ft min
B. Side Setback - Interior 5 ft min 5 ft min 0 ft min 0 ft min
C. Rear Setback (Note 4) 5 ft min 5 ft min 3 ft min 3 ft min
D. Rear Setback from Alley (Note 4) 3 ft min 3 ft min 3 ft min 3 ft min
Note 1: See also Open Space Standards in Chapter 6
Note 2: Lot coverage may also be subject to Stormwater Regulations (See Town Code - Chapter 22 )
Note 3: Building and fire codes may also apply
Note 4: In addition to the setback requirements listed above, garage doors which face a public right-of-way, except for rear alleys, must be set back a minimum
of 20 ft from that right-of-way.
Note 5: Garage doors shall be a minimum of 15 feet from alley centerline. Setbacks may be increased to accommodate parking outside of the garage.
Note 6: Also see Accessory Uses & Structures in Section 3.5
Note 7: The height of the accessory building may not exceed the principal structure except where the principal structure is a single story, a two-story
accessory structure is permitted located in the rear yard only.
Note 8: Also see General Street Design Requirements in Section 5.7.1.A
Note 9: For townhomes, lot coverage will be calculated for the entire site if the site is part of a larger plan requiring stormwater permitting.
13
Summerville, SC UDO
2 Districts I 2.5 Mixed-Use District Standards
Adopted October 10, 2019 Last Amended January 15, 2026
DISTRICT N-R N-MX D-MX UC-MX
Replaces Previous Districts R-3 / R-5 B-1 / some B-2 CBD/B-3 B-3 (redevelopment
areas)
E. Detached Garage Door Setback (from
front facade) (Note 6)
15 from centerline of the
alley
15 from centerline of the
alley
Must be located behind primary building and accessed
via alley or side street
5. BUILDING HEIGHT
A. Primary Building Height 36 feet max 40 feet max 55 feet max
55 feet (may be waived
through Design Review if
site is north of Hwy 78 and
does not front Hwy 78)
B. Accessory Building Height (Note 7) 20 feet max 20 feet max 20 feet 30 feet
6. PARKING LOCATION (NOTE 8)
A. Zone 1 (Front Yard) Restricted to detached
homes only N/A N/A N/A
B. Zone 2 (Side Yard) N/A
C. Zone 3 (Rear Yard)
D. Unrestricted N/A N/A N/A N/A
EXAMPLE: PARKING LOCATION
EXAMPLE: TYPICAL MIXED-USE BLOCK
public-right-of-way
ZONE 2
(side yard)
Note: a 0-foot requirement allows
for continuous parking areas across
property boundaries
ZONE 1
(front yard)
Note: a 0-foot requirement brings the building
frontage up to the public-right-of-way
ZONE 3
(rear yard)
Note: a 0-foot requirement allows
for continuous parking areas across
property boundaries
ZONE 1
(front yard)
ZONE 2
(side yard)
ZONE 3
(rear yard)
Green Fields
SeamonWhiteside
Project No. 13076
03/25/2026
EXHIBIT 7 – PRELIMINARY TOWNHOME ELEVATIONS
TRAFFIC IMPACT ANALYSIS
IS UNERGOING UPDATES,
UPDATED VERSION WILL BE
PROVIDED UPON RECEIPT
PRELIMINARY TOWNHOME
ELEVATIONS ARE PENDING
AND WILL BE PROVIDED
WITH A FUTURE SUBMITTAL
7
ANNEXATION & ZONING
STAFF REPORT
PLANNING COMMISSION
April 20, 2026
Owner & Applicant: The Commissioners of Public Works of the Town of Summerville (SCPW)
TMS#: 144-00-00-189
Location: Berlin G. Myers Parkway
Description: approximately 2.08 acres
Request: Annexation and zoning to PL
The owner/applicant petitioned for the above-referenced parcel to be annexed and zoned PL, Public
Lands. The property is currently zoned Other in Dorchester County.
This property is included in the Town’s ‘Utility’ area as identified within the Summerville: Our Town,
Our Future Comprehensive Plan as well as on the accompanying Future Land Use Map. The property
is a part of the larger SCPW complex fronting Orangeburg Rd. and Greenwave Blvd., and it houses
their largest pump station. It was recently brought to SCPW’s attention that the property is not within
the Town limits, so they have requested annexation.
This request is in conformance with the Comprehensive P lan, and staff rec ommends approval of the
annexation and zoning request of PL.
Orangeburg
Rd
Sawm
illBranch
17
Greenwave Blvd
Orangeburg
Rd
Berlin G Myers Pkwy
Sawmill Branch
King
Charles
Cir
Berlin
G
MyersPkwy
Annexation Exhibit - TMS# 144-00-00-189 - PL
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, © OpenStreetMap
contributors, and the GIS User Community
Road Centerlines
ROAD- Dorchester County
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
Summerville Parcels
PUD
GR-5
MF-R
G-B
PL
N-B
Dorchester Parcels
4/13/2026
0 0.09 0.170.04 mi
0 0.1 0.20.05 km
1:6,019
Orangeburg
Rd
Saw
m
illBranch
17
Greenwave Blvd
Orangeburg
Rd
Orangeburg
Rd
Berlin G Myers Pkwy
Berlin
G
Myers
Pkwy
Sawmill Branch
King
C
harles
Cir
Berlin
G
MyersPkwy
Annexation Exhibit Aerial - TMS# 144-00-00-189 - PL
Sources: Esri, TomTom, Garmin, FAO, NOAA, USGS, (c) OpenStreetMap
contributors, and the GIS User Community, Source: Esri, USDA FSA,
Road Centerlines
ROAD- Dorchester County
ROAD- SCDOT-Dorchester County
ROAD- Town of Summerville
Dorchester Parcels
4/13/2026
0 0.09 0.170.04 mi
0 0.1 0.20.05 km
1:6,019