Quarterly Capital Projects Workshop — Agenda Packet
City of Beaufort · Beaufort County · General · meeting of May 19, 2026 · Agenda packets
Open the original document More from City of Beaufort
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
1
Join from PC, Mac, iPad, or Android:
https://us02web.zoom.us/j/89782739090?pwd=Pav52huoww0T4myCFLKA3CjrZRVEPE.1
Passcode:521976 +16469313860 Webinar ID: 897 8273 9090
City of Beaufort
1911 Boundary Street
Beaufort Municipal Complex
Beaufort, South Carolina 29902
(843) 525-7070
City Council Quarterly Capital Projects Workshop - Amended Agenda
May 19, 2026
Statement of Media Notification
"In accordance with South Carolina Code of Laws, 1976, Section 30-4-80(d), as amended, all
local media was duly notified of the time, date, place and agenda of this meeting."
Quarterly Capital Projects Workshop - Amended - Planning Conference Room - 5:00 PM
Please note, this meeting will be broadcast via zoom and live-streamed on YouTube. You
can view the meeting at the City's page; City Beaufort SC
I. Call to Order - Philip Cromer, Mayor
II. Discussion
A. Quarterly Capital Improvements Program (CIP) Update
III. Executive Session
A. Pursuant to Title 30, Chapter 4, Section 70 (a)(2) of the South Carolina Code of
Law: Receipt of legal advice where the legal advice relates to a pending, threatened,
or potential claim or other matters covered by the attorney-client privilege -
Discussion of obligations pursuant to remaining TIF II Special Tax Allocation Fund
Revenues
IV. Adjourn
Page 1 of 29
City of Beaufort
Department Request for City Council Agenda Item
To: City Council Date: 05/14/2026
From: Eric Claussen , Assistant City Manager
Item Name: Quarterly Capital Improvements Program (CIP) Update
Meeting Date: May 19, 2026
Department: City Managers Office
Background Information:
Introduction:
Assistant City Manager, Eric Claussen and David Gregory, Capital Improvements Program
Coordinator, will be providing an update on current and completed Capital Projects.
Background:
Legal Authority:
Staff Recommendation:
Placed on Agenda For:
Attachments:
1. 2nd Quarter Capital Improvements Update (May 2026)
Page 2 of 29
CAPITAL IMPROVEMENT
QUARTERLY UPDATE
MAY 19, 2026
Presented By
Eric Claussen and David Gregory
Page 3 of 29
Capital Project Presentation
• Projects Completed
• Projects Under Construction
• Projects Fully Designed/Advertised
• Projects that are Unfunded or Partially Funded
Page 4 of 29
Projects Completed
1. Washington Street Park
2. West Street Ramp
3. Waterfront Park Fence
4. Marina Day Dock (Dinghy Dock)
Page 5 of 29
Washington Street
Park Phase II
Description
The project includes a new pavilion, playground
equipment, benches, and sod.
Funding
Parks and Tourism Fund: $528,000
Consultant Contractor
Davis and Floyd Beaufort Construction
Page 6 of 29
Washington Street
Park Phase II
Highlights
The park has a long history serving the
African American community in the
Northwest Quadrant, for music, events, and
recreation.
Washington Street Park hosted a Taste of
Community event as a part of the Taste of
Beaufort on May 2
Official Opening and Ribbon Cutting is
scheduled for May 20th at 10am
Page 7 of 29
West Street
Ramp
Description
Replaced the two-step walkway with a ramp that
supports pedestrians and limited vehicles, matching
existing pavers.
Schedule
Completed March 2026
Funding
Parks and Tourism Fund: $12,536
Contractor
The Greenery
Page 8 of 29
Waterfront
Fence
Description
Replaced the chain link fence with decorative
aluminum fence.
Schedule
Completed April 2026
Funding
Parks and Tourism Fund: $27,660
Contractor
Graybar Fence Co.
Page 9 of 29
Marina Day
Dock
Description
The downtown public day dock sustained irreparable
damage during Hurricane Helene. Scope of work
will furnish and install new floating dock
Schedule
SCDES permit was issued in April 2026
Completed May 2026
Funding
Parks and Tourism Fund: $286,125
Consultant Contractor
McSweeny Engineers O’Quinn Marine
Page 10 of 29
Projects Under Construction
1. King Street Stormwater - The Point Drainage
2. Charles & Craven Street Stormwater
3. Carnegie Library Roof Replacement
4. Waterfront Park Day Dock
Page 11 of 29
King Street
Stormwater - The
Point Drainage
Description
The project includes upgrading the drainage network
on King Street between Hamilton and West Streets
Current Schedule
Construction started December 2025
Completion estimate July 2026
Funding
SCIIP Grants: $9,460,299
ARPA Fund: $727,827
Consultant Contractor
Davis and Floyd JH Hiers
Page 12 of 29
King Street
Stormwater - The
Point Drainage
Highlights
Installation and testing of new BJWSA
waterlines from Hamilton Street to Pinckney
Street have been completed.
J.H. Hiers is nearing completion of the main
storm drain connection beneath Carteret
Street.
Crews are working nights and Saturdays
Water line is being renewed at King and
Scott Street
Page 13 of 29
Charles & Craven
Street Stormwater
Description
This SCOR-managed project is to upgrade stormwater
infrastructure on Charles Street from Craven Street to the Harbor,
including portions of Craven Street and North Street
Current Schedule
Construction started November 2025
Completion estimate December 2026
Funding
ASIP-funded : $10,708,149
Consultant Contractor
McCormick Taylor/Davis Floyd Gulf Stream
Page 14 of 29
Charles & Craven
Street Stormwater
Highlights
Gulf Stream has installed:
53 sections of 72” RCP pipe
37 sections of 60” RCP pipe
The diameter of pipe being installed for this
project include: 72”, 60”, 36”, 18”, & 15”
Gulf Stream has mobilized a crew to the
Waterfront Park (Contemplative Garden) for
connection to the existing outfall
Page 15 of 29
Carnegie Library
Improvements
Description
Project to include roof repairs, gutters and
downspouts, soffit and eave repair, engineering
services and interior repairs.
Current Schedule
Construction started Mar 2026
Completion estimate May 2026
Funding
Parks and Tourism Fund: $200,000
Consultant Contractor
Meadows Architecture Luna Roofing
Page 16 of 29
Carnegie Library
Improvements
Highlights
Construction on the main building commenced
in April 2026
Installation of the dormers, trim boards, and
new copper gutters is complete
New tile is being installed on the roof with the
old tile being kept for future maintenance
Page 17 of 29
Waterfront Park
“Day Dock”
Improvements
Description
The work includes installing a new platform and
gangways that do not rest on the structurally deficient
promenade.
Schedule
RFP issued March 2026
SCDES permits approved May 2026
Completion estimate June 2026
Funding
Parks and Tourism Fund - $325,000
Consultant Contractor
McSweeny Engineers O’Quinn Marine
Page 18 of 29
Projects Fully Designed/Advertised
1. Arsenal Walls & Windows Rehabilitation
2. Duke Street - Streetscape & Drainage
3. Bayard Street Stormwater - The Point Drainage
4. Southside Park - Dog Park Upgrades
5. City Hall & PD Headquarters Re-Roofing
6. Pigeon Point Drainage Study
Page 19 of 29
Arsenal Walls &
Windows
Rehabilitation
Description
The Arsenal, originally constructed in 1795-1798. Project was
originally identified in 2018 when one portion of the walls was to
be repaired, and it was determined that the roof would need to be
fixed before the remaining walls and windows could be repaired.
Schedule
RFP anticipated to be issued in May 2026
Funding
State Accommodations Tax Fund:
Arsenal Walls Rehabilitation: $268,639
Arsenal Windows: $200,000
Consultant Contractor
Meadors Architecture TBD
Page 20 of 29
Duke Street -
Streetscape &
Drainage
Description
Streetscape and Drainage Improvements from
Ribaut Road to Bladen Street
Schedule
Bids opened on May 15, 2026
Construction anticipated to start in July 2026
Funding
ARPA Fund: $625,000
General Fund: $375,000
Consultant Contractor
Davis and Floyd TBD
Page 21 of 29
Bayard Street
Stormwater - The
Point Drainage
Description
Project area includes the drainage infrastructure that historically
served the Bayard Street, Duke Street, New Street, and East
Street
Schedule
USACE & SCDOT permits received in April 2026
Construction anticipated to start in September 2026
Funding
Stormwater Fund- $398,061 Grant Fund- $707,664
Consultant Contractor
Davis and Floyd TBD
Page 22 of 29
Southside Park -
Dog Park Upgrades
Description
The next phase of Southside Park will focus on
upgrades to the Dog Park
Schedule
Design anticipated to be complete by August 2026
Funding
Park and Tourism Bond: $275,000
Consultant Contractor
Davis and Floyd TBD
Page 23 of 29
City Hall & PD
Headquarters Re-
Roofing
Description
The project includes the removal and replacement of the solar
panel systems and replacement of roofing at the City Hall and
PD Headquarters
Schedule
Bids opened on April 30, 2026
Recommendation to City Council in June 2026
Funding
TIF II Fund: $700,000
Contractor
TBD
Page 24 of 29
Pigeon Point
Drainage Study
Description
A study has started to determine the stormwater
improvements in the Pigeon Point neighborhood.
Schedule
City Council approved contract in March 2026
Funding
Stormwater Fund: $54,000
Grant Fund: $162,000
Consultant
Davis and Floyd
Page 25 of 29
Projects Unfunded/Partially Funded
1. Henry C. Chambers Waterfront Park
(Preserving the Promenade)
2. 1st South Carolina Volunteer Park
3. Pigeon Point Boat Landing Improvements
Page 26 of 29
Henry C. Chambers
Waterfront Park
(Preserving the
Promenade)
Description
The project is moving to the next phase to begin design for the
replacement of the promenade.
Schedule
Public Meeting/ Webpage launch April 2026
RFQ for design anticipated in June 2026
Partial Funding
Parks and Tourism Bond: $925,000
Consultant
TBD
Page 27 of 29
1st South Carolina
Volunteer Park
Description
A new passive park located on Boundary St. to commemorate the
1st South Carolina Volunteer Infantry composed primarily of formerly
enslaved Gullah Geechee men.
Schedule
Design contract awarded in December 2025
Final design is anticipated in September 2026
Partial Funding
TIF II Fund: $250,000
Consultant
Davis and Floyd
Page 28 of 29
Pigeon Point Boat
Landing
Improvements
Description
Pigeon Point Boat Landing project consists of a new
dock, a new single launch boat ramp, a raised parking
area, and underground stormwater detention
Schedule
Awaiting approval from SCDES, BCM, and Army Corp
Funding
TBD
Consultant
Davis and Floyd
Page 29 of 29