ECONOMIC PLANNING & DEVELOPMENT COMMITTEE MEETING
FEBRUARY 3, 2025, 6PM
CITY HALL - COUNCIL CHAMBERS
5 E. BUTLER ROAD
4th commitee mee�ng
Commitee Members present: Ta� Matney (Chair), Mark Steenback and Jason Kraeling
Others present: City Administrator Seth Duncan
1. Call to Order- Chairman Matney
2. Public Comment- None
3. Reading and Approval of Minutes
a. Economic Development Commitee Minutes January 6, 2025
Mo�on: Councilman Steenback made a mo�on to approve the minutes with Councilman
Kraeling seconding.
Vote: The vote was unanimous (3-0).
4. Reports or Communica�ons from City Officers
a. City Administrator Seth Duncan
Mr. Duncan reported the City has released a branding RFP that will be closing the middle
of February. He also men�oned the Planning Commission will begin working with
Benchmark Consul�ng on the comprehensive plan.
b. Cultural Center Floor- Mathew Fleahman
Mr. Fleahman advised Commitee the theater floor in the Cultural Center is sagging. A
structural engineer was called in to look and reported several joists are roten. A bid was
sent out and a contractor will come in and make the joist repairs as well as install a new
sub-floor. The project will cost $76,000 and will begin in April.
5. Unfinished Business- There is no unfinished business.
6. New Business
a. Amphitheater Stage Cover
Project Manager Gina McAtee introduced this item. In September 2024, the
amphitheater stage was hit by a falling tree during Hurricane Helene, destroying the stage
cover and damaging the fascia of the stage. Staff released a Request for Proposals (RFP) to
solicit bids for a steel structure that will support rigging, incorporate basic overhead
ligh�ng, and have beter long-term durability.
Hogan Construc�on Group, LLC provided a comprehensive response to the City’s RFP for a
new stage cover. The proposed stage completely covers the exis�ng stage, locates the
columns outside the exis�ng stage pla�orm, and preserves site lines from the sea�ng area
to the performers on stage. It also includes basic ligh�ng above the stage and will support
an op�onal truss system as desired. The structure includes painted steel columns, arched
beams, purlins, and secondary framing with stained tongue and grove decking, and
painted standing seam metal roof. The structure comes with a 35-year warranty on the
finish and 20-year water�ghtness warranty. Hogan an�cipates a comple�on date of 12
weeks a�er engagement.
Mo�on: Councilman Kraeling made a mo�on to send this item to Council with a
recommenda�on of approval as well as a recommenda�on to award the bid to Hogan
Construc�on. Councilman Steenback seconded the mo�on.
Vote: The vote was unanimous (3-0).
7. Public Comment- None
8. Commitee Concerns- None
9. Adjournment- Chairman Matney adjourned the mee�ng at 7:03 p.m.
Respec�ully Submited,
Cindy Miller