Capital Improvement Program (CIP) Overview
City of Memphis · Shelby County · meeting of May 15, 2026 · Other
Open the original document More from City of Memphis
This document is no longer listed on City of Memphis's website. We kept the copy we read.
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
CIP Overview
FY27 Proposed Budget
FY27-31
Capital
Improvement
Plan
$18,060,000
City Engineering
4,200,000
Executive
38,178,800
Fire Services
106,133,204
General Services
70,072,960
Housing & Community Development
26,923,000
Information Technology
12,750,000
Library Services
76,989,000
Memphis Parks
47,882,762
Police Services
256,616,044
Public Works
675,103,092
CAPITAL PROJECTS FUND
84,515,000
Public Works Sewer
53,935,000
Public Works Storm Water
138,450,000
ENTERPRISE FUND
CITY ENGINEERING
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
City Engineering EN-TBD HSIP 150,000 150,000 150,000 150,000 150,000 750,000
City Engineering EN-TBD
Percent-for-Art
Program 400,000 400,000 400,000 400,000 400,000 2,000,000
City Engineering EN-TBD
Traffic Safety
Development 250,000 250,000 250,000 250,000 250,000 1,250,000
City Engineering EN-TBD
Traffic Calming
Devices 1,000,000 1,700,000 1,700,000 1,700,000 1,700,000 7,800,000
City Engineering EN-TBD
Traffic Signal
Improvements
(Union at
Lauderdale) 710,000 - - - - 710,000
City Engineering EN-TBD
Traffic Signals FF&E
(FY27) 550,000 - - - - 550,000
City Engineering EN-TBD
Neighborhood
Safety 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 5,000,000
CAPITAL PROJECTS
FUND 4,060,000 3,500,000 3,500,000 3,500,000 3,500,000 18,060,000
EXECUTIVE
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Executive GA01036
Capital Reserve
Animal Shelter 300,000 300,000 300,000 300,000 300,000 1,500,000
Executive GA-TBD Facility Additions - 2,700,000 - - - 2,700,000
CAPITAL PROJECTS
FUND 300,000 3,000,000 300,000 300,000 300,000 4,200,000
FIRE SERVICES
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Fire Services FS02032 EMA Sirens 173,800 170,000 170,000 170,000 170,000 853,800
Fire Services FS02033
Drill Tower
Improvements 3,000,000 3,000,000 - - 6,000,000
Fire Services FS04012
Personal Protective
Equipment 1,300,000 1,300,000 1,300,000 1,300,000 1,300,000 6,500,000
Fire Services FS25001 New Fire Station 28 6,000,000 2,125,000 8,125,000
Fire Services FS25002 Gender Separation 260,000 3,860,000 3,860,000 3,860,000 3,860,000 15,700,000
Fire Services FS25004
BRIC Grant - Project
52 1,000,000 - - - - 1,000,000
CAPITAL PROJECTS
FUND 2,733,800 14,330,000 10,455,000 5,330,000 5,330,000 38,178,800
GENERAL SERVICES
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
General Services GS-TBD FY27 CAQ Police 6,295,000 4,500,000 4,000,000 4,000,000 4,000,000 22,795,000
General Services GS-TBD FY27 CAQ Fire 3,070,253 5,000,000 5,000,000 5,000,000 5,000,000 23,070,253
General Services GS-TBD
FY27 CAQ Public
Works - Street
Maintenance 1,257,487 - - 250,000 500,000 2,007,487
General Services GS-TBD
FY27 CAQ Public
Works - ROW
Maintenenance 263,477 - 263,477
General Services GS-TBD
FY27 CAQ
Community
Enhancement -
Grounds Services 86,708 - 75,000 75,000 75,000 311,708
General Services GS-TBD
FY27 CAQ
Engineering 45,000 - 100,000 100,000 100,000 345,000
General Services GS-TBD
FY27 CAQ Memphis
Animal Shelter 95,000 95,000
General Services GS-TBD FY27 CAQ PARKS 50,000 - 100,000 300,000 300,000 750,000
General Services GS-TBD
FY27 CAQ GS - Prop
Maint 191,284 191,284
General Services GS-TBD
FY27 CAQ GS -
Grounds
Maintenance 49,000 - 50,000 50,000 35,000 184,000
General Services GS-TBD
FY27 CAQ GS - Fleet
Management 329,010 - 200,000 200,000 200,000 929,010
General Services GS-TBD
FY27 CAQ GS - City
Hall Ops 120,000 - 50,000 170,000
GENERAL SERVICES
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
General Services GS-TBD
FY27 CAQ
Community
Enhancement -
Public Service Corps 52,000 - 60,000 60,000 60,000 232,000
General Services GS-TBD FY27 CAQ Library 58,985 - 80,000 100,000 100,000 338,985
General Services GS24101
Roofing CIP Major
Modification Projects - 1,000,000 1,000,000
General Services GS24102
Electrical CIP Major
Modification Projects 1,000,000 3,000,000 3,000,000 3,000,000 3,000,000 13,000,000
General Services GS23103
Plumbing CIP Major
Modification Project 1,000,000 1,500,000 1,500,000 1,500,000 1,500,000 7,000,000
General Services GS24104
HVAC CIP Major
Modification Projects 700,000 1,400,000 1,400,000 1,400,000 1,400,000 6,300,000
General Services GS24105
Carpentry CIP Major
Modification Project 600,000 800,000 800,000 800,000 800,000 3,800,000
General Services GS22202 Operation City Hall 1,500,000 3,000,000 4,000,000 3,000,000 500,000 12,000,000
General Services GS01049
Coke: City of
Memphis Municipal
Complex 2 - 2,500,000 1,000,000 1,000,000 1,000,000 5,500,000
General Services GS20170
Public Safety
Building: 170 N Main 1,000,000 700,000 500,000 500,000 500,000 3,200,000
General Services GS24107
Emergency
Contingency:
Break/Fix 650,000 500,000 500,000 500,000 500,000 2,650,000
CAPITAL PROJECTS
FUND 18,413,204 23,900,000 22,415,000 21,835,000 19,570,000 106,133,204
HOUSING & COMMUNITY DEVELOPMENT
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Housing and
Community
Development CD01103
Hospitality Hub
North - 1,500,000 - - - 1,500,000
Housing and
Community
Development CD01104 Southwest Twin 13,672,960 11,000,000 - - - 24,672,960
Housing and
Community
Development CD01105
Raleigh Springs
Project - 6,500,000 6,500,000 - - 13,000,000
Housing and
Community
Development CD01106 Liberty Park Project - - 1,400,000 - - 1,400,000
Housing and
Community
Development CD01107
Fairgrounds
Redevelopment
Project - - 1,000,000 - - 1,000,000
Housing and
Community
Development CD-TBD
Middle Income
Housing
Infrastructure 1,000,000 6,000,000 6,000,000 6,000,000 5,000,000 24,000,000
Housing and
Community
Development CD-TBD South City Museum 500,000 2,000,000 2,000,000 4,500,000
CAPITAL PROJECTS
FUND 15,172,960 27,000,000 16,900,000 6,000,000 5,000,000 70,072,960
INFORMATION TECHNOLOGY
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Information
Technology IT01001
Desktop & App
Infrastruc/Optim 400,000 660,000 500,000 500,000 500,000 2,560,000
Information
Technology IT01002
Cyber Security
Infrastructure
Upgrades 480,000 500,000 500,000 500,000 500,000 2,480,000
Information
Technology IT01003
Operational Infra
Enhancements 650,000 650,000
Information
Technology IT01004
Implementation
Modernization 4,000,000 2,250,000 250,000 250,000 250,000 7,000,000
Information
Technology IT01006
IT Improvement
Coverline 300,000 300,000 300,000 300,000 300,000 1,500,000
Information
Technology IT01009 Smart City Project - 3,183,250 3,183,250 3,183,250 3,183,250 12,733,000
CAPITAL PROJECTS
FUND 5,830,000 6,893,250 4,733,250 4,733,250 4,733,250 26,923,000
LIBRARY SERVICES
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Library Services LI01035
New Parkway Village
Library 1,250,000 6,500,000 7,750,000
Library Services LI01036
Library Improvement
Def Maint. 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 5,000,000
CAPITAL PROJECTS
FUND 2,250,000 7,500,000 1,000,000 1,000,000 1,000,000 12,750,000
MATA
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
MATA GA03001
MATA-Service
Vehicles - 250,000 200,000 200,000 200,000 850,000
MATA GA03022
MATA-Adv Public
Transp System - 200,000 200,000 200,000 200,000 800,000
MATA GA03023
MATA-
Operations/Maint
Facility - 1,890,893 1,871,429 3,762,322
MATA GA03029 Transit Amenities - 20,000 20,000 20,000 20,000 80,000
MATA GA03030
Fixed Route
Vehicles - 3,030,000 2,175,000 2,175,000 2,175,000 9,555,000
MATA GA03031 Paratransit Vehicles - 287,500 287,500 287,500 287,500 1,150,000
MATA GA03032 Bus Facility - 275,000 275,000 275,000 275,000 1,100,000
CAPITAL PROJECTS
FUND - 5,953,393 5,028,929 3,157,500 3,157,500 17,297,322
MEMPHIS PARKS
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Memphis Parks PK24107
Audubon Golf
Clubhouse 4,000,000 - - - - 4,000,000
Memphis Parks PK-TBD
Jesse Turner Park
Improvements 3,100,000 400,000 - - - 3,500,000
Memphis Parks PK-TBD
North Frayser
Community Center
Improvements 250,000 3,500,000 3,750,000
Memphis Parks PK-TBD
American Way Park
Improvements - 1,100,000 1,100,000
Memphis Parks PK-TBD
Lester Pool
Assessment & Design - 300,000 300,000
Memphis Parks PK-TBD
Pine Hill Golf Course
Netting 150,000 150,000
Memphis Parks PK-TBD
Community Center
Security - 600,000 600,000
Memphis Parks PK-TBD
Raleigh CC Design &
Renovation 250,000 1,100,000 1,100,000 - - 2,450,000
Memphis Parks PK-TBD
Indoor Aquatic Facility
Glenview 200,000 8,500,000 8,500,000 - - 17,200,000
Memphis Parks PK03004
Tennis Major
Maintenance - 200,000 200,000 200,000 200,000 800,000
Memphis Parks PK07127
Wolf River Greenway
Phase 5C/13 500,000 150,000 650,000
Memphis Parks PK09002
Zoo Major
Maintenance 250,000 250,000 250,000 250,000 250,000 1,250,000
Memphis Parks PK-TBD
Com Center
Replacement-
Douglass - 2,000,000 9,500,000 9,500,000 21,000,000
MEMPHIS PARKS
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Memphis Parks PK-TBD
Replacement Football
Field at Tobey - 600,000 3,500,000 4,100,000
Memphis Parks GA07002 MRPP Coverline 250,000 250,000 250,000 250,000 250,000 1,250,000
Memphis Parks PK12015
Parks Critical Needs
Cont. 500,000 500,000 500,000 500,000 500,000 2,500,000
Memphis Parks PK-TBD
Gooch Park-Multi-use
Sportsfield & Track 3,389,000 - 3,389,000
Memphis Parks GS01050
Levitt Shell
Improvements 750,000 - - - - 750,000
Memphis Parks PK-TBD
Ridgeway Community
Center Improvements - 500,000 1,250,000 6,500,000 - 8,250,000
CAPITAL PROJECTS
FUND 13,589,000 16,250,000 15,150,000 17,800,000 14,200,000 76,989,000
POLICE SERVICES
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Police Services PD04031
Axon Enterprise
Solution 11,000,000 11,000,000 11,000,000 33,000,000
Police Services PD04026
Helicopter
Maintenance 510,000 510,000
Police Services PD-TBD
New Request
Helicopter
Replacement (5-YR
Lease Purchase
est.) 2,250,000 2,250,000 1,500,000 1,500,000 7,500,000
Police Services PD04033
New Request Safety
Equipment
Purchase/Replacem
ent 1,400,000 2,672,762 1,400,000 1,400,000 6,872,762
CAPITAL PROJECTS
FUND 12,910,000 15,922,762 14,650,000 2,900,000 1,500,000 47,882,762
PUBLIC WORKS
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Public Works PW01025 Winchester/Perkins 4,000,000 4,000,000
Public Works PW01056
Holmes-Millbranch
to East 3,000,000 5,000,000 5,000,000 13,000,000
Public Works PW01087
Holmes Rd/S
3rd/Horn Lake 3,000,000 5,000,000 5,000,000 13,000,000
Public Works PW01179
Holmes Road East
Malone-Lamar 2,500,000 25,000,000 27,500,000
Public Works PW01255
Chelsea Avenue
Greenline 1,500,000 1,500,000
Public Works PW01256 Overton Park Trail 200,000 - 200,000
Public Works PW01284
Shelby - Paul
Lowery to Weaver 500,000 5,000,000 10,000,000 15,000,000 15,000,000 45,500,000
Public Works PW02015
Holmes St. Br over
CSX RR 16,044 16,044
Public Works PW-TBD STBG Resurfacing - 500,000 500,000 500,000 500,000 2,000,000
Public Works PW17301
American Way
Bridge Repairs - 2,000,000 2,000,000
Public Works PW17302
Fire S&L Bldg -
Seismic Repair - 4,500,000 4,500,000
Public Works PW18401
Wolf River
Greenway Phase 15 900,000 900,000
Public Works PW-TBD
Asphalt Paving
Neighborhood
(Expense Recovery) 6,500,000 6,500,000 6,500,000 6,500,000 6,500,000 32,500,000
Public Works PW-TBD
Asphalt Paving
Streets Group 1 6,750,000 8,250,000 9,250,000 11,750,000 11,750,000 47,750,000
PUBLIC WORKS
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Public Works PW-TBD
Asphalt Paving Streets
Group 2 6,750,000 8,250,000 9,250,000 11,750,000 11,750,000 47,750,000
Public Works PW-TBD
NEW PW-TBD
Sidewalks - 500,000 500,000 500,000 500,000 2,000,000
Public Works PW-TBD
Grant Assistance
Sidewalk/Cost Share - 500,000 - - - 500,000
Public Works PW-TBD ADA Curb Ramp - 1,000,000 1,000,000 1,000,000 1,000,000 4,000,000
Public Works PW-TBD Bridge Repairs - 1,600,000 800,000 800,000 800,000 4,000,000
Public Works PW-TBD
Asphalt Plant
Rehabilitation 3,000,000 - - - - 3,000,000
Public Works PW-TBD
Street Maintenance
Security 300,000 - - - - 300,000
Public Works PW-TBD
Street Maintenance
Wash Bay 500,000 - - - - 500,000
Public Works PW-TBD
Street Maintenance
Master Plan 200,000 - - - - 200,000
CAPITAL PROJECTS
FUND 31,116,044 42,600,000 77,300,000 57,800,000 47,800,000 256,616,044
PUBLIC WORKS - SEWER
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Public Works Sewer SW04009
Stiles Plant
Modification - - - - 5,000,000 5,000,000
Public Works Sewer SW04011
Stiles WWTF
Biosolids Upgrades 10,000,000 - - 30,000,000 - 40,000,000
Public Works Sewer SW05001
Sewer Assessment
and Rehab - - 20,000,000 - - 20,000,000
Public Works Sewer SW05005 TDEC ARP Sewer 5,000,000 - - - - 5,000,000
Public Works Sewer SW24204
Sewer Annual CIPP
2025 2,200,000 2,200,000 - - - 4,400,000
Public Works Sewer SW-TBD
559 North Front St. -
Sewer 490,000 - - - - 490,000
Public Works Sewer SW-TBD Cane Creek CIPP 5,250,000 - - - - 5,250,000
Public Works Sewer SW-TBD
54" Loos. Sewer
Relocation 1,875,000 - - - - 1,875,000
Public Works Sewer SW-TBD
TE Maxson Raw
Sewage Pumps 1,000,000 - - - - 1,000,000
Public Works Sewer SW-TBD
Gayoso PS Electrical
Upgrades - Sewer 500,000 - - - - 500,000
Public Works Sewer SW-TBD
Berryhill Road
Unsewered Area 1,000,000 - - - - 1,000,000
ENTERPRISE FUND 27,315,000 2,200,000 20,000,000 30,000,000 5,000,000 84,515,000
PUBLIC WORKS – STORM WATER
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Public Works Storm
Water ST02001 Design-ST Coverline 1,000,000 1,000,000 1,000,000 3,000,000
Public Works Storm
Water ST02013
Stormwater Program
Mgr 7,000,000 - - - - 7,000,000
Public Works Storm
Water ST02029 Frisco Ave Detention 6,000,000 - - - - 6,000,000
Public Works Storm
Water ST02037
Ash/Omar Robinson
Drop Structure 1,000,000 - - - - 1,000,000
Public Works Storm
Water ST03231
Citywide ST Rehab
FY24-26 1,500,000 - - - - 1,500,000
Public Works Storm
Water ST-TBD Curb and Gutter 500,000 - - - - 500,000
Public Works Storm
Water ST03239 Storm Water CIP 2025 550,000 - - - - 550,000
Public Works Storm
Water ST03244
Whitehaven Gardens
CCL 3,000,000 - - - - 3,000,000
Public Works Storm
Water ST-TBD Rain Gauge Network 100,000 - - - - 100,000
Public Works Storm
Water ST02035
QA/QC Drainage MP
Study 100,000 - - - - 100,000
Public Works Storm
Water ST-TBD DMP - Point Church 500,000 - - - - 500,000
PUBLIC WORKS – STORM WATER
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Public Works Storm
Water ST02033
DMP Madison
Heights-Lick Creek 500,000 - - - - 500,000
Public Works Storm
Water ST02034 DMP Ten-Mile 500,000 - - - - 500,000
Public Works Storm
Water ST-TBD
Trash Wheel @
Nonconnah 120,000 - - - - 120,000
Public Works Storm
Water ST-TBD
Trash Wheel @ Wolf
River 120,000 - - - - 120,000
Public Works Storm
Water ST-TBD
Southwest Twin -
Stormwater Detention 235,000 - - - - 235,000
Public Works Storm
Water ST-TBD Harrison CCL R&R 5,500,000 - - - - 5,500,000
Public Works Storm
Water ST03246
Chickamauga Drain
Improvements 1,220,000 - - - - 1,220,000
Public Works Storm
Water ST03241 2700 Summer Viaduct 650,000 - - - - 650,000
Public Works Storm
Water ST-TBD
Peach/Evergreen
Drain Improvements 6,500,000 - - - - 6,500,000
Public Works Storm
Water ST-TBD
Evergreen Drain Re-
Route 4,500,000 - - - - 4,500,000
Public Works Storm
Water ST-TBD
Tchulahoma/Bluebon
net Drain
Improvements 150,000 - - - - 150,000
PUBLIC WORKS – STORM WATER
Division Project Number Project Name FY2027 FY2028 FY2029 FY2030 FY2031 Total
Public Works Storm
Water ST-TBD
University Circle
Drain Improvements 800,000 - - - - 800,000
Public Works Storm
Water ST-TBD
Wanda St. Drain
Improvements 600,000 - - - - 600,000
Public Works Storm
Water ST-TBD
MSQ2 Project
Easements 300,000 - - - - 300,000
Public Works Storm
Water ST-TBD
559 North Front St. -
Storm Water 490,000 - - - - 490,000
Public Works Storm
Water ST03242
Gayoso PS Electrical
Upgrades - Storm
Water 6,000,000 - - - - 6,000,000
ENTERPRISE FUND 49,935,000 500,000 1,500,000 500,000 1,500,000 53,935,000
Source: City of Memphis website. First collected Oct 27, 2026.