KNOX COUNTY
TENNESSEE
Adopted
FIVE-YEAR
CAPITAL
IMPROVEMENT
PLAN
For fiscal years
2011-2015
Michael R. Ragsdale
Knox County Mayor
TABLE OF CONTENTS
CAPITAL IMPROVEMENT PLAN
FY 2011 – FY 2015
Capital Improvement Plan Policy ----------------------------------------------- 1
Adopted Projects Summary ------------------------------------------------------ 2
Sources and Uses of Funds------------------------------------------------------- 3
Countywide Projects -------------------------------------------------------------- 4
Public Libraries -------------------------------------------------------------------- 5
Parks and Recreation-------------------------------------------------------------- 6
Building Improvements/Major Maintenance ---------------------------------- 7
Engineering and Public Works -------------------------------------------------- 8
Knox County Schools------------------------------------------------------------- 9
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
CAPITAL IMPROVEMENT PLAN POLICY
Knox County has established a set of policies that cover the process of preparing the
Capital Improvement Plan. Below are the major factors involved in the process:
A. Construction projects and capital purchases that generally cost in the aggregate more
than $100,000 and/or have a useful life of greater than seven years will be included in
the Capital Improvement Plan. Furniture, fixtures and equipment purchased for major
additions or renovations will be included in the plan; all other regular maintenance
and capital purchases less than $100,000 will be included in the operating budget.
B. The purpose of the Capital Improvement Plan is to plan, schedule, and anticipate
financing for capital projects for the next five years.
C. Department Heads and Elected Official s will prepare the project proposals and
present the requests to the Finance Depart ment. The Public Building Authority will
assist with the calculation of project cost s and schedules. The project proposals from
the Knox County School System will be forw arded to the Finance Department once
the Knox County School Board adopts its request. Operating costs associated with the
project must be provided by the department or elected official and are not included in
the Capital Improvement Plan.
D. The Knox County Finance Department and County Mayor will review the project
requests and make recommendations to the County Commission. The final plan
recommended by the County Mayor include s the financing of the projects
recommended. Financing for the capital budget will come from General Obligation
Bonds and other sources. If a specific cu rrent revenue source is identified for a
project, then that funding is included in the plan.
E. Budget appropriations for projects included in the first year of the approved Capital
Improvement Plan, for which financing is planned for the upcoming fiscal year, are
required to be approved by the County Co mmission. Budgetary approval for projects
planned for the subsequent years, for which the financing is planned in those future
years, is generally not obtained during the fi rst year of the Capital Improvement Plan
and is subject to revision in subsequent years’ Capital Improvement Plans as the
expected capital needs, and anticipated av ailability of the related financing, may
change in response to future economic conditions and other circumstances.
1
FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
Countywide Projects 3,576,949 $ 776,949 $ 776,949 $ 776,949 $ - $ 5,907,796$
Public Libraries 100,000 100,000 100,000 100,000 - 400,000
Parks and Recreation 150,000 150,000 150,000 150,000 - 600,000
Building Improvements/Major Maintenance 926,308 1,482,614 652,990 500,000 - 3,561,912
Engineering and Public Works
Highways 1,000,000 1,000,000 1,000,000 1,000,000 - 4,000,000
Solid Waste - - - - - -
Stormwater Management - - - - - -
Total Engineering and Public Works 1,000,000 1,000,000 1,000,000 1,000,000 - 4,000,000
Knox County Schools -- School Debt 10,000,000 23,100,000 20,000,000 - - 53,100,000
Total of All Projects 15,753,257 $ 26,609,563 $ 22,679,939 $ 2,526,949 $ - $ 67,569,708$
Adopted
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
ADOPTED PROJECTS SUMMARY
2
FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
Adopted 15,753,257 $ 26,609,563 $ 22,679,939 $ 2,526,949 $ - $ 67,569,708$
Expected Adjustment for Carter
Elementary Project 2,000,000 3,000,000 - - - 5,000,000
Adjustment for Cash Flow/Project
Schedule - (6,000,000) - 6,000,000 - -
Bonds to Be Issued for Projects
Approved in Prior Years - 20,000,000 9,000,000 8,000,000 - 37,000,000
Total Uses of Funds 17,753,257 $ 43,609,563 $ 31,679,939 $ 16,526,949 $ - $ 109,569,708$
FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
General Obligation Bonds:
Issued for New Projects 17,000,000 $ 27,000,000 $ 20,000,000 $ 15,000,000 $ - $ 79,000,000$
Refunding of BANs 30,000,000 - - 15,000,000 10,000,000 55,000,000
Bond Anticipation Notes (BANs):
Notes Issued - 15,000,000 10,000,000 - - 25,000,000
Notes Repaid (30,000,000) - - (15,000,000) (10,000,000) (55,000,000)
Other Funding
Funds Reappropriated from
Completed Projects (A) 753,257 1,609,563 1,679,939 1,526,949 - 5,569,708
Total Other Funding 753,257 1,609,563 1,679,939 1,526,949 - 5,569,708
Total Sources of Funds 17,753,257 $ 43,609,563 $ 31,679,939 $ 16,526,949 $ - $ 109,569,708$
(A) Projects will be appropriated from existing appropriations for already closed projects and for additional projects to be closed at 6/30/10.
The remaining unexpended appropriations from the closed projects will be transferred to these future projects; therefore,
no new appropriations will be required.
Uses of Funds
Sources of Funds
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
SOURCES AND USES OF FUNDS
3
Description FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
General Project Management 576,949 $ 576,949 $ 576,949 $ 576,949 $ - $ 2,307,796$
Energy Management Equipment 2,400,000 - - - - 2,400,000
Debt Issuance Costs (See Note Below) 400,000 - - - - 400,000
City/County Improvements and Development 200,000 200,000 200,000 200,000 - 800,000
Total Countywide Projects 3,576,949 $ 776,949 $ 776,949 $ 776,949 $ - $ 5,907,796$
Note: The costs of debt issuance are included only for FY 2011, as only FY 2011 will be appropriated based on this capital plan.
Adopted
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
COUNTYWIDE PROJECTS
4
Description FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
Lawson McGhee / Facilities Upgrades 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ 400,000$
Total Public Libraries 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ 400,000$
Adopted
CAPITAL IMPROVEMENT PLAN
PUBLIC LIBRARIES
FY 2011 THROUGH FY 2015
5
Description FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
Parks Facilities Upgrades 100,000 $ 100,000 $ 100,000 $ 100,000 $ - $ 400,000$
Greenways 50,000 50,000 50,000 50,000 - 200,000
Total Parks and Recreation 150,000 $ 150,000 $ 150,000 $ 150,000 $ - $ 600,000$
Adopted
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
PARKS AND RECREATION
6
Description FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
City / County Building (CCB) 160,000 $ 749,000 $ 342,000 $ 285,000 $ - $ 1,536,000$
Less: City Contribution toward CCB (48,192) (225,599) (103,010) (85,000) - (461,801)
Net County Funding for CCB 111,808 523,401 238,990 200,000 - 1,074,199
Andrew Johnson Building 52,500 285,000 130,000 50,000 - 517,500
Dwight Kessel Garage 30,000 29,213 60,000 - - 119,213
Juvenile Justice 250,000 - 62,000 50,000 - 362,000
Health Department 100,000 - - 50,000 - 150,000
Libraries 280,000 645,000 122,000 100,000 - 1,147,000
Senior Centers - - - 50,000 - 50,000
Fairview Technology Center 102,000 - 40,000 - - 142,000
Total Building Improvements/
Major Maintenance 926,308 $ 1,482,614 $ 652,990 $ 500,000 $ - $ 3,561,912$
Adopted
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
BUILDING IMPROVEMENTS/MAJOR MAINTENANCE
7
Description FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
CMAQ 50,000 $ 50,000 $ 50,000 $ 50,000 $ - $ 200,000$
Geometric Improvements 200,000 200,000 200,000 200,000 - 800,000
General Road Improvements 750,000 750,000 750,000 750,000 - 3,000,000
Total Engineering and Public Works 1,000,000 $ 1,000,000 $ 1,000,000 $ 1,000,000 $ - $ 4,000,000$
Adopted
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
ENGINEERING AND PUBLIC WORKS
8
Description FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 Total
Physical Plant Upgrades 5,000,000 $ 5,000,000 $ 5,000,000 $ - $ - $ 15,000,000$
Roofing and HVAC Replacements 3,200,000 3,000,000 3,150,000 - - 9,350,000
Carter Campus Renovations/Additions (See note below) - - - - - -
New Southwest Elementary 800,000 12,500,000 5,000,000 - - 18,300,000
1,000,000 2,600,000 6,850,000 - - 10,450,000
Total School Projects (See note below) 10,000,000 $ 23,100,000 $ 20,000,000 $ - $ - $ 53,100,000$
Note: The County initially had planned for a $5 million ($2 million in 2011 and $3 million in 2012) renovation at Carter Elemen tary.
The Knox County Commission did not fund this project, and alternatives to the planned renovations are being investigated.
The County plans to amend the Capital Improvement Plan once a final determination is approved.
A provision has been made for this expected change in the overall plan to restore the planned $5 million.
Other Projects
Adopted
CAPITAL IMPROVEMENT PLAN
FY 2011 THROUGH FY 2015
KNOX COUNTY SCHOOLS
9
Source: Knox County website. First collected Nov 4, 2026.