PUBLIC WORKS COMMITTEE MEETING, September 22, 2026
CONFERENCE ROOM 1, 5:30 pm
Present: Alderman Mark Skidmore (Chairman), Alderman Eddie Roberson (Vice-Chairman)
Absent: Alderman Michael Martin, Mayor Jaime Clary
Others Present: Alderman Jeffrey Sasse, Alderman Mark Burgdorf, Alderman Terri Goodwin, Alderman
Don Ward, COO Jesse Eckenroth, Public Works Director Stephen Winzenread, Garrett Kidd
Called to order at 5:31 pm
Acceptance of Agenda
No objection to agenda - ordered
Motion to Approve July 28. 2026 , Public Works Committee meeting minutes
Motion: Alderman Roberson
Second: Alderman Skidmore
Vote: Approved unanimously
Citizens Comments
None
Ordinances and Resolutions
1. Reading of Ordinance 2026-13, An ordinance amending Hendersonville Municipal Code, Title 1
General Administration, Chapter 6, Standing Committees, 1-603, Regular Meetings; Changing
times for Public Works Committees.
An amendment was proposed to strike the language in Section One beginning with "However,
the above starting times will not be effective until July 1, 2021. Until then, the current starting
times for the committee shall remain unchanged."
Motion to amend Ordinance 2026-13 by striking the above-referenced language.
Motion: Alderman Roberson
Second: Alderman Skidmore
Vote: Approved unanimously
Motion to adopt amended Ordinance 2026-13.
Motion: Alderman Roberson
Second: Alderman Skidmore
Vote: Approved unanimously
Other Agenda Items
2. Trash Collection Update
Staff provided a two-month trash collection update covering July 20th through September 11th,
2026. Missed collections remained relatively low, with 147 total misses and a daily high of 18.
Staff also reported that customer lists are reviewed and updated at least monthly, with
information verified against City records.
3. Drainage follow-up near Trucord Dr. and Vulco Drive (verbal update)
Staff reported that crews have been working through the drainage system from the bottom
upward to prevent downstream issues. At the corner of Trucord Drive and Vulco Drive, crews
identified overgrown areas and drainage components requiring cleaning. Work has also included
areas extending toward Robin Hood, including relining a pipe, cleaning the southernmost Robin
Hood culvert, and removing obstructions. Staff stated that these issues contributed to flooding
concerns near 107 Trucord Drive.
4. Eagle View Project (verbal update)
Staff reported that the Eagle View Project is under construction, with work beginning September
10th, 2026. The contractor is proceeding with a three-sided culvert. The committee discussed
the status of the related lawsuit and project funding. Staff reported that approximately $30,000
in stormwater surety funds is proposed to be applied to the project through a budget
amendment. Staff also noted that surety calculations have been updated to reflect increased
construction costs.
5. Drakes Creek and Stop 30 Intersection Project (verbal update)
• HUD Waterline Relocation Update
The waterline relocation has been completed. Some paving work was also completed as
night work south of the intersection.
• Permit Updates
The Army Corps permit is provisionally approved, pending issuance of the required TDEC
permit. TDEC's permitting process included two 30-day notice periods. The second notice
period, concerning the purchase of mitigation credits for relocating the stream along Stop
30 Road, ended September 18th, 2026. Staff anticipated receiving the TDEC permit within
approximately three to four weeks. The project cannot be advertised for bids until the
required permits are obtained. The consultant is completing the bid package, which will also
require TOOT approval because the project is a Local Programs project.
• R/W Acquisition
Staff reported that the order of possession was issued August 3rd, 2026, and right-of-way
acquisition is complete. The City is awaiting a certification letter from TDOT confirming
completion of the right-of-way process. The committee discussed the potential impact of
construction near the cemetery. Staff stated that the acquired area is a relatively small sliver
and that no impact to grave sites is anticipated. If an unexpected issue were encountered
during construction, work would be paused while the situation was assessed. The
committee also discussed project funding through the Greater Nashville Regional Council
(GNRC), with GNRC providing 80% of the funding and the City providing 20%. Staff agreed to
verify the status of the City's 20% budgeted share.
6. Light Synchronization Project (verbal update)
Staff reported that radar detection equipment has been ordered and is expected to arrive by
mid-October. The contractor is currently testing existing conduits and preparing for installation.
The committee discussed the system's ability to improve vehicle detection and provide traffic
data for signal timing adjustments. Staff clarified that the equipment uses radar and is not a
camera or a real-time automatic signal adjustment system.
7. LED Streetlight Conversion Project (verbal update)
Staff reported that the LED streetlight conversion project is approximately 93% complete. A
total of 2,197 of the 2,370 lights included in the project have been converted. The committee
discussed anticipated energy savings. Staff stated that savings had been projected as part of the
proposal and that the City's budget had been adjusted in anticipation of those savings.
The committee also discussed the previously approved trial of solar-powered streetlights on
Bonita. Staff reported that the city had been working to obtain three comparable bids from
vendors. Three bids had been obtained, but staff still needed to evaluate whether the proposed
solution was the appropriate option to proceed with. Staff explained that the solar streetlights
must meet street-lighting standards and that visual appearance was also being considered.
8. Other Business
Alderman Sasse discussed a sidewalk trip hazard in Mansker Farms. Staff recommended using
the city app to submit service requests. Alderman Burgdorf requested an update on the
proposed cable railing for the greenway boardwalk. Staff reported that the railing would require
structural modifications and cost more than $250,000. The committee discussed alternatives
when the existing wood railing requires replacement. The committee discussed a request for a
flashing crosswalk at Walton Ferry Road and Luna Lane. Staff stated that the traffic engineer
would review the location and determine whether it meets the criteria for a rectangular rapid
flashing beacon (RRFB). The committee also discussed decorative street signs being installed in
the Westlake area.
Motion to Adjourn
Motion: Alderman Roberson
Second: Alderman Skidmore
Vote: Approved unanimously
Adjourned at 6:23 pm