Transportation, Streets, Garage Committee — Agenda
City of Clarksville · Montgomery County · Transportation, Streets, Garage Committee · meeting of Feb 11, 2025 · Agendas
Open the original document More from City of Clarksville
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
AGENDA
Please silence all cell phones.
1. Call to Order
2. Attendance
3. Approval of Minutes: January Meeting
4. Department Reports a) Transit Report - Mike Ringgenberg
CTS had 42,316 riders in January = 38,313 riders on Fixed route buses including 7,047
Senior
riders
rode
for
free
and
4,003
riders
rode
on
Paratransit.
CTS financial report for December - will be provided during the meeting.
CTS just received notice that we will receive a $4.5M State Grant in July to help purchase
land
for
our
new
Transit
Center
and
$1.2M
State
Grant
in
July
for
new
vehicle
scheduling
software,
vehicle
cameras
and
bus
radios.
b) Street Report
Department Report - Orville Sykes
We completed 289 work orders in January.
Capital Project Update - Chris Cowan
c) Garage Report
Department Report - Bill Lee
The total number of work orders for January was 380. The total number of work order
hours
was
650.80.
Total
parts
cost
was
$44,396.09.
Total
tire
cost
was
$8,700.32.
At
last
delivery
on
1-27-25
unleaded
was
$2.25
per
gallon,
an
increase
of
7%
from
$2.10
on
12-20-24.
At
last
delivery
on
1-23-25
diesel
was
$2.57
per
gallon,
an
increase
of
6.6%
from
$2.41
on
12-30-24.
5. Committee Action Required (none)
6. City Council Action
7. Old Business
8. New Business
Public Comment (allows 3 persons; 5 minutes each)
9. Adjournment
Transportation, Streets, Garage Committee
January 14, 2025 MINUTES
Tuesday, January 14th at 3:30 pm City Hall, 4th Floor, Large Conference Room Members Present: Wanda Smith, Chairperson Tim Chandler, Councilman Jimmy Brown, Councilman Keri Lovato, Councilperson Carlos Peters, Councilman Members Absent: None Transit Michael Ringgenberg, Director Randie Cilk, Administrative Support Street David Smith, Director Orville Sykes, Equipment Operations Manager Bonny Blyzes, Administrative Support Supervisor Garage Bill Lee, Director Stacey Burney, Administrative Support Technician Internal Audit Stephanie Fox
CALL TO ORDER:
January 14, 2025 at 3:30 p.m…Transportation, Street & Garage Committee (TSG) meeting was
called
to
order
by
Chairperson
Wanda
Smith.
The
members
in
attendance
were
Tim
Chandler,
Jimmy
Brown,
Keri
Lovato
and
Carlos
Peters.
There
were
no
members
absent.
Chair Smith made a motion to entertain the minutes as printed. The motion was seconded by
Brown.
All
were
in
favor
and
none
opposed.
TRANSPORTATION
Departmental Report - MIke Ringgenberg
CTS had 41,222 riders for January 2025 = 37,389 riders on Fixed route buses including
6,723
Senior
riders
that
rode
for
free
and
3,833
riders
on
Paratransit.
As of November 2024 the year-to-date (YTD) revenues were under budget $4,475.85. The YTD
expenses
were
under
budget
$274,
565.62.
The
combined
net
YTD
under
budget
was
$279,041.47.
COMMITTEE ACTION REQUIRED:
No action required
CITY COUNCIL ACTION REQUIRED:
No action required
STREET DEPARTMENT
Departmental Report:
DEPARTMENTAL REPORT - Orville Sykes We closed 311 work orders in the month of December. Capital Project Update - David Smith Spring Creek Parkway - Phase 1 - should be completed soon and opening up, as we’ll be
installing
the
signal
as
soon
as
possible.
The
contract
for
the
paving
near
the
round-about
was
terminated
and
The
Street
Department
employees
completed
that
project
in
house.
The
next
phase
of
the
round-about
project
will
be
completed
during
CMCSS
spring
break
to
alleviate
traffic
disruption
during
construction.
Sidewalk projects: Peachers Mill is complete, the Crossland Avenue project is 90% complete and
the
Ringold
Road
project
should
begin
in
a
couple
weeks
as
we
just
had
a
pre-con
meeting
this
week.
Committee Action Required:
No action required
CITY COUNCIL ACTION REQUIRED:
No action required
GARAGE DEPARTMENT
Departmental Report: Bill Lee
CITY GARAGE REPORT:
For December, the total number of work orders was 345. The total number of work order hours
was
720.05.
Total
parts
cost
was
$56,883.06.
Total
tire
cost
was
$5,871.22.
At
last
delivery
on
12-20-24
unleaded
was
$2.10
per
gallon,
a
decrease
of
2.8%
from
$2.16
on
11-25-24.
At
last
delivery
on
12-30-24
diesel
was
$2.41
per
gallon,
an
increase
of
0.4%
from
$2.40
on
11-26-24.
COMMITTEE ACTION REQUIRED:
No action required
CITY COUNCIL ACTION REQUIRED:
No action required
NEW BUSINESS:
None.
OLD BUSINESS:
None.
PUBLIC COMMENTS:
None.
Adjournment:
A motion to adjourn was made by Chairperson Smith and seconded by Councilperson Chandler.
The
meeting
was
adjourned
without
objection
at
3:48
pm.
Chairperson Date
Street Department Report
Capital Project update
● Starting on Ringgold Rd sidewalk during Spring Break (March) ● Traffic Signal at Spring Creek Parkway to be fully operational this week ● Construction beginning soon for Phase 2 of Rossview Road and Dunbar Cave
Realignment
● Bid opening for Spring Creek Pkwy Phase 2 in March