CAPITAL BUDGET
ONE CHATTANOOGA
2024-2028
CITY OF CHATTANOOGA • MAYOR TIM KELLY
TABLEOFCONTENTS
● Capital ImprovementPlan…….………………….……… C‐1○ Governmental FundProjects............................................... C‐1○ EnterpriseFundProjects■ Wastewater………………………………………..................... C‐6■ Stormwater…………………………………........................... C‐10○ Capital ImprovementOrdinance………….......................... C‐13○ Fiscal Year2024Plan……..…………………..….......................... C‐15○ Five‐YearCapital ImprovementPlanResolution........ C‐23○ Fiscal Year2024thru2028Plan….………............................ C‐25○ BondResolution………………………………................................. C‐31
Introduction
The FY24-28 Capital Improvement Plan (CIP) is the City of Chattanooga’s five-year plan for
capital improvement throughout Chattanooga. The first year of the CIP is the fiscally constrained
budget, whereas the successive years are a roadmap for future action. Maintaining critical
infrastructure, investing in public safety, reimagining great outdoor spaces, delivering effective
services to all Chattanoogans, and more; this CIP continues the City’s investment in the goals
and strategies of the One Chattanooga strategic plan. The information below provides
summaries of the projects included in the FY24 capital budget. Funding sources for these
projects include reserve funds, general obligation bonds, grants, external funds, internal service
funds, and state loan funds.
General Government Projects
Better Government
Projects Funded: 8
T otal Funding: $5,947,000
% External Funding: 11%
City Hall Annex Renovation
Replacement of existing elevator and additional renovation at City Hall Annex
City Network Rebuild
Refresh of network infrastructure essential for City operations
Digital Infrastructure Investments
Citywide branding and website implementation
DRC Roof Replacement
Replacement of the Development Resource Center roof at the end of its useful life and
installation of solar array to reduce energy costs
Google Workspace Back-up
Email retention compliance update and expansion
Major Capital Maintenance Improvements Downtown Campus & Other Facilities
This funding will address major building system elements at City facilities identified in the
Facilities Assessment Evaluations, such as HVAC systems, roofing system replacements,
structural repairs, floor replacements, restroom rehabilitation, building code upgrades, and ADA
Compliance.
C-1
Security Compliance Tools
Cyber Security risk assessment and management network security tools
Wood Recycle Services Relocation
Grading, filling, installation of electrical infrastructure to support the relocation of the Brush and
Trash Operations to the New Wood Recycle Management Building
Economic Development
Projects Funded:
T otal Funding: $300,000
% External Funding: 0
Land Acquisition - Lead Abatement Program
Acquisition of property for storage related to EPA-funded lead abatement program
Education
Projects Funded: 1
T otal Funding: $100,000
% External Funding: 0
Ignite Discovery Capital Campaign
Year four of five year funding commitment to the Creative Discovery Museum’s capital campaign
to enhance visitors’ experience and ensure long term sustainability
Fleet
Projects Funded: 2
T otal Funding: $5,775,000
% External Funding: 0
Fleet Capital Infusion
Appropriate Fleet Program Reserve funds so that they may be used to replace vehicles
currently in the program that are at the end of their lease terms
Refuse Trucks
Purchase of new refuse trucks to replace existing trucks and expand refuse collection
Neighborhoods
Projects Funded: 7
T otal Funding: $2,300,000
% External Funding: 9%
C-2
CDBG Sidewalks
Construction of sidewalks in designated low‐ income neighborhoods where pedestrian travel is
necessary for many residents
Community Center Swimming Pool Repairs
Repairs to community center swimming pools
Hixson Community Center
Repair and remodeling of Hixson Community Center including the auditorium
Major Capital Maintenance Improvements Community Centers
This funding will address major building system elements at Community Centers identified in the
Facilities Assessment Evaluations, such as HVAC systems, roofing system replacements,
structural repairs, floor replacements, restroom rehabilitation, building code upgrades, and ADA
Compliance.
Plan of Services Obligations
Funds for pending obligations
Raccoon Mountain Water Service
Extension of water service to Raccoon Mountain
Washington Hills Community Center
Design for the Washington Hills Community Center
Outdoors
Projects Funded: 6
T otal Funding: $3,415,000
% External Funding: 0
Chattanooga Skatepark
Construction of the new Chattanooga Skatepark currently in design
Lynnbrook Park
Additional funding for Lynnbrook Park construction due to increased construction costs
Parks and Outdoors Plan Deferred Maintenance
Implementation of recommendations for Deferred Maintenance from the Parks and Outdoors
Plan
C-3
Parks and Outdoors Plan Recommended Master Plans
The Parks and Outdoors Plan recommends several major renovations plus New Parks,
Greenways, and Blueways. Master Plans are the first step towards implementation of the plan's
recommendations and include public engagement through schematic design to determine the
community-driven scope for each park identified.
Provence Park
Creation of a new City park to bring the City into compliance with T ennessee Department of
Environment and Conservation and National Park Service and to restore eligibility for Outdoor
Recreation Legacy Partnership and Land and Water Conservation funding.
Schoolyards Program
In coordination with the Trust for Public Land, expansion of park access through existing
schoolyards as identified in the Parks and Outdoors Plan
Public Safety
Projects Funded: 8
T otal Funding: $9,411,000
% External Funding: 19%
Apparatus Replacement Plan
The Chattanooga Fire Department's Apparatus Replacement Plan (ARP) strategically plans
toward the replacement of fire response apparatus. Of all of the vehicles used by the
department, these are the frontline workhorses of the department. Firefighters provide
exceptional service every hour of every day, and they could not do it without fire apparatus.
FY24 and future year funding will replace apparatus which are at the end of their useful life and
implement an ongoing replacement schedule.
Citywide Camera Refresh
The Department of T echnology Services maintains the support and functionality of the citywide
camera system including maintenance, damage, licensing and end-of-life replacement. This
funding will be used to maintain devices, refresh old equipment, and schedule new installations.
Fire Station Capital Maintenance
Fire station and building maintenance is vital to ensuring a healthy and operable place for
firefighters to work and live. This project will fund major maintenance projects, including HVAC
repair, roof repair, exhaust systems, security systems, and more.
Fire Training Tower Replacement
In partnership with the Hamilton County Office of Emergency Management and Homeland
Security, the Chattanooga Fire Department will demolish the old training tower, and design and
build a new replacement fire training tower to be used for skill-based training in various
disciplines for both fire cadets and current firefighters. The new tower will be a part of the
C-4
regional training facility for other departments, including all of the Hamilton County volunteer
agencies.
Law Enforcement Training Center
Design and construction of the new Law Enforcement Training Center to replace the existing
firing range and consolidate other training activities held in various temporary locations
Police Laptop Replacement
Replacement of outdated and inefficient CPD laptops
Station #15 Replacement
Additional funding toward the construction of the Station #15 Replacement due to increased
construction costs
Station #2 Apparatus
Apparatus, equipment, and additional costs for new Station #2
Roads and Bridges
Projects Funded: 10
T otal Funding: $36,330,440
% External Funding: 41%
Bridge Maintenance
The bridges program aims to fund necessary maintenance and rehabilitation to the city's
network of approximately 85 structures. This funding will be used for general maintenance work
to be performed by contracted crews, response to any emergencies that damage bridges, and
will be used to fund significant bridge capital projects.
Hamilton Place Boulevard
This project will modify Hamilton Place Boulevard at the I-75/Hamilton Place Interchange to
accommodate revised traffic patterns from the Interchange Modification Project being designed
and implemented by TDOT .
Lake Resort Slope Repair
This project will construct a permanent repair to Lake Resort Dr. that experienced failure from
excessive rainfall in 2019.
Pavement Management
These funds are used for the City’s annual resurfacing contract. They are a critical part of
comprehensive pavement management that includes paving and preventative maintenance
techniques.
C-5
Public Works - Coronavirus Response and Relief
Use of Coronavirus Response and Relief Supplemental Appropriations Act funds for
transportation needs paused during the pandemic
Smart City Testbed Expansion
Expansion of Smart City testbed along McCallie Ave. and Bailey Ave.
Traffic Signal Infrastructure Maintenance
This funding will be used to maintain, refresh and upgrade the City of Chattanooga’s intersection
traffic signals, signal controls, software and technical maintenance. There are 380 intersections
in the City that are maintained by the Department of T echnology Services - Smart Cities
Division.
Walnut Street Bridge
Repair and rehabilitation of the Walnut Street bridge in downtown Chattanooga
Wilcox Blvd. Bridge
This project will replace the existing structurally deficient Wilcox Boulevard Bridge over the
DeButts Railyard. The replacement structure will include a multimodal path and support
development of a pedestrian connection from East Chattanooga to the Riverwalk.
Transit
Projects Funded: 1
T otal Funding: $1,634,830
% External Funding: 0
CARTA Vehicles & Equipment
This project is for the rehabilitation and maintenance of CARTA's intermodal facilities, vehicles,
and equipment. This funding is the local match of state and federal funds received directly by
CARTA.
Wastewater Projects
Projects Funded: 35
T otal Funding: $142,217,052
% External Funding: 12%
23rd St Pump Station Improvements
This project includes making capital improvements to the 23rd Street Pump Station within the
screening room, dry well, wet well, electrical room, and the site, in general.
C-6
Anaerobic Digester Rehab
Improvements to the overall digester process so the plant can reduce the volume of biosolids
produced, decrease chemical usage, and energy usage
Citico Force Main Replacement
This project includes rehabilitation of the 30” force main exiting the Citico pump station, located
on the south side of the T ennessee River near Citico Creek along Riverside Drive.
E2I2 SSO Abatement Program
This project is the overall E2I2 program, which includes the development of a feasibility study to
determine the size, location, and required infrastructure improvements needed to construct EQ
stations with 47 MGD of capacity in 3 strategic locations. This project is a cooperative,
cost-sharing undertaking with WWTA that will yield savings for tax and ratepayers in
Chattanooga and HCWWTA while providing the benefit of schedule extensions on certain
components of the City of Chattanooga's EPA Consent Decree.
Equipment Purchases
Purchase of necessary equipment including a mini trackhoe, a scissor lift, a portable light tower,
new Kubotas and dumpster replacements
Focused SSES and Rehab - Phase II
This project involves completing Sanitary Sewer Evaluation Studies (SSES) and the
rehabilitation of sanitary sewer pipes in twenty-four of Chattanooga's Sewersheds, as directed in
the Consent Decree. These repairs will help reduce sanitary sewer overflows in the Sewersheds
and will increase overall collection system capacity to the MBWWTP .
Highland Park Pump Station Improvements
This project includes improvements to the Highland Park wet weather Pump Station including
the full rehabilitation of the pump station, replacement of pumps with VFDs, replacement of all
electrical and MCC, new discharge piping, new safety grating, and wet well lining.
Influent Pump Station Improvements (IPS Screen Bypass)
This project includes the addition of a bypass system to allow for flow through the Influent Pump
Station (IPS) and to the MBEC process during blinding conditions of the IPS screen, as well as
the replacement of the bar screens.
ISS Capacity Improvements - Creekside Preserve
This project includes making unidentified capacity improvements across the collection system to
decrease SSOs.
Long Term Control Plan Upgrades
This project will result in an Additional Operational Plan for the Chattanooga Creek CSO
Outfalls, which will augment Chattanooga's current CSO control measures with additional
C-7
long-term controls that will ensure that discharges from these CSOs comply with State water
quality standards.
MBWWTP Electrical Upgrades (S&C Switches)
Switches are outdated and obsolete and need replacement prior to catastrophic failure or safety
issues arise during switching or operation
MBWWTP EQ - UNOX Piping Improvements
This project includes the design and construction of parallel conveyance piping and manifolds to
provide reliability from the EQ pump station to the UNOX basins. The piping includes various
lengths of 84-inch, 42-inch and 36-inch diameters. Also included is a flow-splitter structure with
actuated slide gates.
MBWWTP North Recycle Pump Station
Project involves the design and construction of a new recycle pump station at the MBWWTP
and moving drain piping effluent more efficiently to the discharge locations
MBWWTP Oxygen Plant Replacement
This project includes the replacement of the MBWWTP Oxygen Plant, which has reached its
end of life, and needs to be replaced to continue reliable MBWWTP operations.
MBWWTP Solids Process Optimization Implementation - Phase 4 (Digester/THP
Improvements)
The project consists of solids handling facilities including pre-thickening and cake storage, THP
and post-THP equipment provided by a vendor, steam generation/cooling, sludge blending, and
anaerobic digesters. This new process will allow for continued operations and will increase
performance in the solids handling process.
MBWWTP Wet Weather Treatment Upgrade
This project will design and build selected alternatives identified during the Wet Weather
Treatment Upgrade feasibility analysis.
New Biosolids Staging Area
Due to a reduction of available space for the current Biosolids staging area, a new area is
needed that is larger and is covered. This would help with over stockpiling out at farms and
decrease runoff concerns on the farms.
Office Space Expansion/Renovation
Evaluation of existing facilities and the potential need for additional space to accommodate staff.
Design of interior renovations in multiple structures or design of a proposed structure.
Program Management For Consent Decree
This project is the annual renewal of the scope and fee of program management services for the
implementation of the EPA CD program.
C-8
Pump Station Improvements - Hixson 2 (Bundle)
This project includes the bidding, construction administration, construction inspection and
construction costs associated with 4 pump stations previously designed
Sandswitch Road Point Repairs
Two extensive point repairs for Sandswitch Road
Sandswitch Road Sewer Lining
Sewer lining for Sandswitch Road
Sewer Bypass Pumps
Equipment needed for sewer line repair and maintenance
Sewer Line Extensions
Sewer line extensions to serve individual lots previously annexed and not currently served with
sewer
Shop Equipment and Tool Room
Replacement of aging shop equipment
Shop Storage and Organization
Improvement of shop storage and organization
Smart Sewer Implementation
Implementation of smart sewers will allow for improved operations by progressively installing
smart sensors at strategic locations of the system and real-time control based on the information
communicated by these sensors.
Software Upgrades
Upgrades to Cityworks and pipe coding software
South Chick Pump Station Improvements
This project includes making capital improvements to the South Chick PS. These improvements
are designed to improve the capacity, performance and reliability of the station and help to
reduce sanitary sewer overflows in the area.
Training Center Expansion
Expansion of training center to accommodate larger group meetings and hands-on technical
training
Vehicle Purchases
Purchase of new CCTV truck, maintainer, and other vehicles for all Wastewater divisions
C-9
Warehouse Racking
Warehouse racking and shelving was not included in the warehouse project budget and is
needed to replace current racking to equip the new warehouse space.
Wet Weather Storage Phase 4 - South Chic PS
This project is a major component of the ISS plan to reduce system overflows and stay within
compliance of the EPA mandated Chattanooga Consent Decree Program.
Wet Weather Storage Phase 6 - Hixson PS #1
This project is a major component of the ISS plan to reduce system overflows and stay within
compliance of the EPA mandated Chattanooga Consent Decree Program
Wilcox Blvd Chronic SSO
This project includes making unidentified capacity improvements across the collection system to
decrease SSOs
Stormwater Projects
Projects Funded: 17
T otal Funding: $11,042,500
% External Funding: 0
3469 Brainerd Rd.
Design and construction of a new storm drainage separation line across Brainerd Rd.
Automated Flood Warning System
Automated flood warning system for flood prone streets around the City
Briarwood Circle
Identification of various problem areas caused by flooding and improvements to City
infrastructure to alleviate the impacts to neighboring properties
Broad Street - MLK to Aquarium Way
Design and construction of a new storm drainage separation line along Broad Street
Dartmouth/Five Points Watershed SIP
Multi-phase stormwater infrastructure replacement project. Rapid development in past years has
caused increased runoff potential in the area and taxed an undersized, aging system.
Drainage Projects
Design and construction of various locations across the City to address localized flooding
C-10
Floodplain Modeling
Provide accurate, up-to-date information regarding flood levels, flood risk and associated
hazards for areas within the City of Chattanooga in conformance with current FEMA standards
Green Infrastructure SOV Bank
Implement numerous innovative projects to mitigate existing stormwater impacts to watersheds,
streams, and rivers
Heavy Equipment
New equipment to replace existing and aging equipment for continued service on water quality
projects
On-Call Landscape Design
These services will provide landscape designs on blanket contract for green infrastructure and
water quality projects
Stormwater Asset Management Plan
Creation of a Stormwater Asset Management Plan and Master Plan. Proactive efforts to assess
existing stormwater infrastructure and prioritize rehab, replacement or installation of
infrastructure to continue to provide a high level of service
Stream Buffer Conservation
Implement a stream buffer program that benefits and improves streambank stabilization,
erosion/sediment control, promotes habitat and wildlife along with reducing the impact from
floods
Stream Restoration/Various Sites
Reduce peak flow velocities which contribute to stream bank erosion, improving water quality
downstream, restoring ecological habitat, and reducing peak flood stages
TN Riverbank Stabilization Project
Series of projects to provide emergency stabilization along the TN Riverbanks
USACE/FEMA Floodplain Culvert Replacement Projects
Culvert replacement project to replace undersized culverts in FEMA mapped stream segments
to 100 year conveyance capacity
WQ TMDL & Land Management
T o preserve and enhance the quality of the physical environment with projects that meet the
TMDL and WQ regulatory changes. These various projects will consist of planning, design, and
construction to manage water quantity and improve water quality on City owned property.
WQ Vehicles
Purchase of City vehicles not currently in the Fleet replacement program
C-11
C-12
ORDINANCE NO. __________
AN ORDINANCE APPROPRIA TING, AUTHORIZING OR
ALLOCA TING FUNDS TO THE CAPITAL IMPROVEMENTS BUDGET
FOR THE FISCAL YEAR 2023-2024.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CHA TTANOOGA,
TENNESSEE:
SECTION 1. That there be and is hereby appropriated, authorized, or allocated the hereinafter set
funds from the sources specified for the public purposes indicated of the Capital Improvements Plan for
the Fiscal Y ear Ending June 30, 2024:
SECTION 2. That there be and is hereby authorized the appropriation of all capital donations,
including partnership agreements not previously appropriated, to the projects and the capital fund for
which they are intended.
GENERAL GOVERNMENTAL FUNDS
FROM General Obligation Bonds $ 15,000,000
General Fund Reserves 10,000,000
General Fund Reserves Cleanup (12,700,000)
American Rescue Plan Funds 12,700,000
Operations 2,500,000
Economic Development Fund 7,750,000
Hotel Motel Tax Fund (2070) 4,500,000
State Street Aid (2050) 1,000,000
Fleet Management Fund (6504) 4,500,000
Coronavirus Response and Relief Supplemental Appropriation 2,488,558
Community Development Block Grant (CDBG) 200,000
Federal Appropriation 6,600,000
Hamilton County 912,830
Hamilton County Office of Emergency Management 1,500,000
Surface Transportation Block Grant (STBG) 8,261,882
TO General Government and Supported Agencies $ 4,672,830
Department of Community Development 400,000
Department of Police 950,000
Department of Fire 8,300,000
Department of Public Works 47,175,440
Department of Parks and Outdoors 3,415,000
Department of Economic Development 300,000
TOTAL GENERAL GOVERNMENTAL FUNDS $ 65,213,270 $ 65,213,270
DRAFT
C-13
PROPRIETARY CAPITAL FUNDS
FROM State Revolving Loan Fund /WIFIA (ISS) $ 71,700,000
Wastewater Operations (Fund 6010) 27,048,646
Wastewater Reserves (Fund 6010) 26,801,354
Stormwater Fund Operations (Fund 6030) 6,478,626
Stormwater Fund Reserves(Fund 6030) 4,563,874
Tennessee Department of Environment and Conservation
American Rescue Plan Grant 16,667,052
TO Wastewater Fund $ 142,217,052
Stormwater Fund 11,042,500
TOTAL PROPRIETARY CAPITAL FUNDS $ 153,259,552 $ 153,259,552
TOTAL CAPITAL BUDGET $ 218,472,822 $ 218,472,822
BE IT FURTHER ORDAINED, That this Ordinance shall take effect immediately from and after
its passage as provided by law.
PASSED _____________________, 2023
__________________________________________
CHAIRPERSON
APPROVED_______ DISAPPROVED _________
DA TE: ______________________________, 2023
__________________________________________
MAYOR
DRAFT
C-14
City of Chattanooga
Capital Budget Summary by Department
Fiscal Year 2024
Summary Schedule (Capital)
Proposed FY24
External
Sources Reserves Operations Bonds SRF WIFIA
Economic
Development
Other City
Sources Total
General Governmental 65,213,270 17,474,712 -2,700,000 2,500,000 15,000,000 - - 7,750,000 25,188,558 65,213,270
General Government 4,672,830 1,600,000 2,617,830 - - - - 455,000 - 4,672,830
Community Development 400,000 - 400,000 - - - - - - 400,000
Police Department 950,000 275,000 675,000 - - - - - - 950,000
Fire Department 8,300,000 1,500,000 800,000 - 6,000,000 - - - - 8,300,000
Public Works 47,175,440 14,099,712 5,207,170 2,500,000 9,000,000 - - 3,880,000 12,488,558 47,175,440
Parks and Outdoors 3,415,000 - - - - - - 3,415,000 - 3,415,000
Economic Development 300,000 - -12,400,000 - - - - - 12,700,000 300,000
Enterprise 153,259,552 16,667,052 31,365,228 33,527,272 - 46,700,000 25,000,000 - - 153,259,552
Wastewater 142,217,052 16,667,052 26,801,354 27,048,646 - 46,700,000 25,000,000 - - 142,217,052
Stormwater 11,042,500 - 4,563,874 6,478,626 - - - - - 11,042,500
Total All Funds 218,472,822 34,141,764 28,665,228 36,027,272 15,000,000 46,700,000 25,000,000 7,750,000 25,188,558 218,472,822
C-15
C-16
City of Chattanooga
Capital Budget Summary by Project
Fiscal Year 2024
Proposed FY24
External
Sources Reserves Operations Bonds SRF WIFIA
Economic
Development
Other City
Sources Total
General Governmental 65,213,270 17,474,712 -2,700,000 2,500,000 15,000,000 - - 7,750,000 25,188,558 65,213,270
General Government 4,672,830 1,600,000 2,617,830 - - - - 455,000 - 4,672,830
Technology Services 2,938,000 1,600,000 983,000 - - - - 355,000 - 2,938,000
City Network Rebuild 400,000 - 400,000 - - - - - - 400,000
Citywide Camera Refresh 161,000 - 161,000 - - - - - - 161,000
Digital Infrastructure Investments 77,000 - 77,000 - - - - - - 77,000
Google Workspace Back-up 200,000 - 200,000 - - - - - - 200,000
Security Compliance Tools 100,000 - 100,000 - - - - - - 100,000
Smart City Testbed Expansion 1,850,000 1,600,000 45,000 - - - - 205,000 - 1,850,000
Traffic Signal Infrastructure Maintenance 150,000 - - - - - - 150,000 - 150,000
Chattanooga Area Regional Transportation Authority 1,634,830 - 1,634,830 - - - - - - 1,634,830
CARTA Vehicles & Equipment 1,634,830 - 1,634,830 - - - - - - 1,634,830
Creative Discovery Museum (A.O.) 100,000 - - - - - - 100,000 - 100,000
Ignite Discovery Capital Campaign (A.O.) 100,000 - - - - - - 100,000 - 100,000
Community Development 400,000 - 400,000 - - - - - - 400,000
Community Development 400,000 - 400,000 - - - - - - 400,000
Hixson Community Center 150,000 - 150,000 - - - - - - 150,000
Washington Hills Community Center 250,000 - 250,000 - - - - - - 250,000
Police Department 950,000 275,000 675,000 - - - - - - 950,000
Police Department 950,000 275,000 675,000 - - - - - - 950,000
Law Enforcement Training Center 550,000 275,000 275,000 - - - - - - 550,000
Police Laptop Replacement 400,000 - 400,000 - - - - - - 400,000
Fire Department 8,300,000 1,500,000 800,000 - 6,000,000 - - - - 8,300,000
Fire Department 8,300,000 1,500,000 800,000 - 6,000,000 - - - - 8,300,000
Apparatus Replacement Plan 2,500,000 - - - 2,500,000 - - - - 2,500,000
Fire Station Capital Maintenance 400,000 - 400,000 - - - - - - 400,000
Fire Training Tower Replacement 3,000,000 1,500,000 - - 1,500,000 - - - - 3,000,000
Station #15 Replacement 400,000 - 400,000 - - - - - - 400,000
Station #2 Apparatus 2,000,000 - - - 2,000,000 - - - - 2,000,000
Public Works 47,175,440 14,099,712 5,207,170 2,500,000 9,000,000 - - 3,880,000 12,488,558 47,175,440
Public Works 47,175,440 14,099,712 5,207,170 2,500,000 9,000,000 - - 3,880,000 12,488,558 47,175,440
Bridge Maintenance 250,000 - - - - - - 250,000 - 250,000
CDBG Sidewalks 200,000 200,000 - - - - - - - 200,000
City Hall Annex Renovation 1,370,000 - 870,000 - 500,000 - - - - 1,370,000
Community Center Swimming Pool Repairs 200,000 - - - - - - 200,000 - 200,000
DRC Roof Replacement 1,900,000 637,830 1,262,170 - - - - - - 1,900,000
Fleet Capital Infusion 4,500,000 - - - - - - - 4,500,000 4,500,000
Hamilton Place Boulevard 1,500,000 - - - - - - 1,500,000 - 1,500,000
Lake Resort Slope Repair 400,000 - 400,000 - - - - - - 400,000
Major Capital Maintenance Improvements Community Centers 1,000,000 - - - 1,000,000 - - - - 1,000,000
Major Capital Maintenance Improvements Downtown Campus & Other Facilities 1,000,000 - - - 1,000,000 - - - - 1,000,000
Pavement Management 10,000,000 - - 2,500,000 6,500,000 - - - 1,000,000 10,000,000
Plan of Services Obligations 250,000 - 250,000 - - - - - - 250,000
Public Works - Coronavirus Response and Relief 2,488,558 - - - - - - - 2,488,558 2,488,558
Raccoon Mountain Water Service 250,000 - 250,000 - - - - - - 250,000
Refuse Trucks 1,275,000 - 1,275,000 - - - - - - 1,275,000
Walnut Street Bridge 18,061,882 13,261,882 - - - - - 300,000 4,500,000 18,061,882
Wilcox Blvd Bridge 1,630,000 - - - - - - 1,630,000 - 1,630,000
C-17
City of Chattanooga
Capital Budget Summary by Project
Fiscal Year 2024
Proposed FY24
External
Sources Reserves Operations Bonds SRF WIFIA
Economic
Development
Other City
Sources Total
Wood Recycle Services Relocation 900,000 - 900,000 - - - - - - 900,000
Parks and Outdoors 3,415,000 - - - - - - 3,415,000 - 3,415,000
Parks and Outdoors 3,415,000 - - - - - - 3,415,000 - 3,415,000
Chattanooga Skatepark 1,000,000 - - - - - - 1,000,000 - 1,000,000
Lynnbrook Park 115,000 - - - - - - 115,000 - 115,000
Parks and Outdoors Plan Deferred Maintenance 400,000 - - - - - - 400,000 - 400,000
Parks and Outdoors Plan Recommended Master Plans 400,000 - - - - - - 400,000 - 400,000
Provence Park 1,300,000 - - - - - - 1,300,000 - 1,300,000
Schoolyards Program 200,000 - - - - - - 200,000 - 200,000
Economic Development 300,000 - -12,400,000 - - - - - 12,700,000 300,000
Economic Development 300,000 - -12,400,000 - - - - - 12,700,000 300,000
Affordable Housing Trust Fund - - (12,700,000) - - - - - 12,700,000 -
Land Acquisition - Lead Abatement Program 300,000 - 300,000 - - - - - - 300,000
Enterprise 153,259,552 16,667,052 31,365,228 33,527,272 - 46,700,000 25,000,000 - - 153,259,552
Wastewater 142,217,052 16,667,052 26,801,354 27,048,646 - 46,700,000 25,000,000 - - 142,217,052
Wastewater 142,217,052 16,667,052 26,801,354 27,048,646 - 46,700,000 25,000,000 - - 142,217,052
23rd St Pump Station Improvements 1,100,000 - 1,100,000 - - - - - - 1,100,000
Anaerobic Digester Rehab 1,000,000 - 1,000,000 - - - - - - 1,000,000
Citico Force Main Replacement - - - 10,000,000 - -10,000,000 - - - -
E2I2 SSO Abatement Program 10,000,000 - - - - - 10,000,000 - - 10,000,000
Equipment Purchases 206,500 - 206,500 - - - - - - 206,500
Focused SSES and Rehab - Phase II 8,500,000 - - 8,500,000 - - - - - 8,500,000
Highland Park Pump Station Improvements 2,100,000 - 2,100,000 - - - - - - 2,100,000
Influent Pump Station Improvements (IPS Screen Bypass) 1,500,000 - 1,500,000 - - - - - - 1,500,000
ISS Capacity Improvements - Creekside Preserve 1,000,000 - - 1,000,000 - - - - - 1,000,000
Long Term Control Plan Upgrades 700,000 - 700,000 - - - - - - 700,000
MBWWTP Electrical Upgrades (S&C Switches) 2,000,000 - 2,000,000 - - - - - - 2,000,000
MBWWTP EQ - UNOX Piping Improvements 1,700,000 - - - - 1,700,000 - - - 1,700,000
MBWWTP North Recycle Pump Station 2,500,000 - 2,500,000 - - - - - - 2,500,000
MBWWTP Oxygen Plant Replacement 10,000,000 - - - - 10,000,000 - - - 10,000,000
MBWWTP Solids Process Optimization Implementation - Phase 4 (Digester/THP Improvements)20,000,000 - - - - 10,000,000 10,000,000 - - 20,000,000
MBWWTP Wet Weather Treatment Upgrade 15,000,000 - - - - 10,000,000 5,000,000 - - 15,000,000
New Biosolids Staging Area 900,000 - 900,000 - - - - - - 900,000
Office Space Expansion/Renovation 1,000,000 - 1,000,000 - - - - - - 1,000,000
Program Management For Consent Decree Implementation 2,600,000 - 2,600,000 - - - - - - 2,600,000
Pump Station Improvements - Hixson 2 (Bundle) 6,500,000 - - 6,500,000 - - - - - 6,500,000
Sandswitch Road Point Repairs 625,000 - 625,000 - - - - - - 625,000
Sandswitch Road Sewer Lining 2,500,000 - 2,500,000 - - - - - - 2,500,000
Sewer Bypass Pumps 145,000 - 145,000 - - - - - - 145,000
Sewer Line Extensions 575,000 - 76,354 498,646 - - - - - 575,000
Shop Equipment and Tool Room 250,000 - 250,000 - - - - - - 250,000
Shop Storage and Organization 50,000 - - 50,000 - - - - - 50,000
Smart Sewer Implementation 350,000 - 350,000 - - - - - - 350,000
Software Upgrades 195,000 - 195,000 - - - - - - 195,000
South Chick Pump Station Improvements 5,000,000 - 5,000,000 - - - - - - 5,000,000
Training Center Expansion 500,000 - 500,000 - - - - - - 500,000
Vehicle Purchases 1,053,500 - 1,053,500 - - - - - - 1,053,500
C-18
City of Chattanooga
Capital Budget Summary by Project
Fiscal Year 2024
Proposed FY24
External
Sources Reserves Operations Bonds SRF WIFIA
Economic
Development
Other City
Sources Total
Warehouse Racking 500,000 - 500,000 - - - - - - 500,000
Wet Weather Storage Phase 4 - South Chic PS 25,000,000 - - - - 25,000,000 - - - 25,000,000
Wet Weather Storage Phase 6 - Hixson PS #1 16,667,052 16,667,052 - - - - - - - 16,667,052
Wilcox Blvd Chronic SSO 500,000 - - 500,000 - - - - - 500,000
Stormwater 11,042,500 - 4,563,874 6,478,626 - - - - - 11,042,500
Public Works - Stormwater 11,042,500 - 4,563,874 6,478,626 - - - - - 11,042,500
3469 Brainerd Rd 1,000,000 - - 1,000,000 - - - - - 1,000,000
Automated Flood Warning System 360,000 - - 360,000 - - - - - 360,000
Briarwood Circle 1,030,000 - - 1,030,000 - - - - - 1,030,000
Broad Street - MLK to Aquarium Way 350,000 - - 350,000 - - - - - 350,000
Dartmouth/Five Points Watershed SIP 2,000,000 - - 2,000,000 - - - - - 2,000,000
Drainage Projects 500,000 - - 500,000 - - - - - 500,000
Floodplain Modeling 250,000 - 250,000 - - - - - - 250,000
Green Infrastructure SOV Bank 100,000 - 100,000 - - - - - - 100,000
Heavy Equipment 485,000 - 485,000 - - - - - - 485,000
On-Call Landscape Design 250,000 - 250,000 - - - - - - 250,000
Stormwater Asset Management Plan 1,545,000 - 1,545,000 - - - - - - 1,545,000
Stream Buffer Conservation 250,000 - 250,000 - - - - - - 250,000
Stream Restoration/Various Sites 312,500 - 312,500 - - - - - - 312,500
TN Riverbank Stabilization 1,030,000 - - 1,030,000 - - - - - 1,030,000
USACE/FEMA Floodplain Culvert Replacement Projects 880,000 - 671,374 208,626 - - - - - 880,000
WQ TMDL & Land Management 550,000 - 550,000 - - - - - - 550,000
WQ Vehicles 150,000 - 150,000 - - - - - - 150,000
Total All Funds 218,472,822 34,141,764 28,665,228 36,027,272 15,000,000 46,700,000 25,000,000 7,750,000 25,188,558 218,472,822
C-19
C-20
City of Chattanooga
Other City and External Sources by Project
Fiscal Year 2024
Other City Sources External Funding Sources
Recommended
Other City Sources
American
Rescue Plan
Funds
Coronavirus
Response and
Relief
Supplemental
Appropriation
Fleet Mgt Fund
(6504) Hotel/Motel
State Street Aid
Reserves
Recommended
External
Sources CDBG
Federal
Appropriation
Hamilton
County
Hamilton
County Office of
Emergency
Management
Surface
Transportation
Block Grant
TDEC American
Rescue Plan
Grant
General Government - - - - - - 1,600,000 - 1,600,000 - - - -
Police Department - - - - - - 275,000 - - 275,000 - - -
Fire Department - - - - - - 1,500,000 - - - 1,500,000 - -
Public Works 12,488,558 - 2,488,558 4,500,000 4,500,000 1,000,000 14,099,712 200,000 5,000,000 637,830 - 8,261,882 -
Economic Development 12,700,000 12,700,000 - - - - - - - - - - -
Total General Governmental Funds 25,188,558 12,700,000 2,488,558 4,500,000 4,500,000 1,000,000 17,474,712 200,000 6,600,000 912,830 1,500,000 8,261,882 -
Wastewater - - - - - - 16,667,052 - - - - - 16,667,052
Total Enterprise Funds - - - - - - 16,667,052 - - - - - 16,667,052
Total All Funds 25,188,558 12,700,000 2,488,558 4,500,000 4,500,000 1,000,000 34,141,764 200,000 6,600,000 912,830 1,500,000 8,261,882 16,667,052
General Government - - - - - - 1,600,000 - 1,600,000 - - - -
Smart City Testbed Expansion - - - - - - 1,600,000 - 1,600,000 - - - -
Police Department - - - - - - 275,000 - - 275,000 - - -
Law Enforcement Training Center - - - - - - 275,000 - - 275,000 - - -
Fire Department - - - - - - 1,500,000 - - - 1,500,000 - -
Fire Training Tower Replacement - - - - - - 1,500,000 - - - 1,500,000 - -
Public Works 12,488,558 - 2,488,558 4,500,000 4,500,000 1,000,000 14,099,712 200,000 5,000,000 637,830 - 8,261,882 -
CDBG Sidewalks - - - - - - 200,000 200,000 - - - - -
DRC Roof Replacement - - - - - - 637,830 - - 637,830 - - -
Fleet Capital Infusion 4,500,000 - - 4,500,000 - - - - - - - - -
Pavement Management 1,000,000 - - - - 1,000,000 - - - - - - -
Public Works - Coronavirus Response and Relief 2,488,558 - 2,488,558 - - - - - - - - - -
Walnut Street Bridge 4,500,000 - - - 4,500,000 - 13,261,882 - 5,000,000 - - 8,261,882 -
Economic Development 12,700,000 12,700,000 - - - - - - - - - - -
Affordable Housing Trust Fund 12,700,000 12,700,000 - - - - - - - - - - -
Total General Governmental Funds 25,188,558 12,700,000 2,488,558 4,500,000 4,500,000 1,000,000 17,474,712 200,000 6,600,000 912,830 1,500,000 8,261,882 -
Wastewater - - - - - - 16,667,052 - - - - - 16,667,052
Wet Weather Storage Phase 6 - Hixson PS #1 - - - - - - 16,667,052 - - - - - 16,667,052
Total Enterprise Funds - - - - - - 16,667,052 - - - - - 16,667,052
Total All Projects 25,188,558 12,700,000 2,488,558 4,500,000 4,500,000 1,000,000 34,141,764 200,000 6,600,000 912,830 1,500,000 8,261,882 16,667,052
C-21
C-22
RESOLUTION NO. __________
A RESOLUTION ADOPTING A FIVE-YEAR CAPITAL
IMPROVEMENT PLAN FOR FISCAL YEARS 2024-2028, SUBJECT TO
FUTURE REVISION; A COPY OF WHICH IS A TTACHED HERETO
AND MADE A PART HEREOF BY REFERENCE.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHA TTANOOGA,
TENNESSEE, That there be and is hereby adopted a five-year Capital Improvement Plan for Fiscal Y ears
2024-2028 for the City of Chattanooga, subject to future revisions; a copy of which is attached hereto and
made a part hereof by reference.
ADOPTED: ______________________, 2023
DRAFT
C-23
C-24
City of Chattanooga
FY24-28 Capital Budget Summary by Department
Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 Proposed FY28 5 Year Total
General Governmental 65,213,270 72,970,700 68,200,000 61,750,000 49,700,000 317,833,970
General Government 4,672,830 2,600,000 1,200,000 1,200,000 1,200,000 10,872,830
Community Development 400,000 - - - - 400,000
Police Department 950,000 5,600,000 6,900,000 6,550,000 3,100,000 23,100,000
Fire Department 8,300,000 6,150,700 5,900,000 5,900,000 5,800,000 32,050,700
Public Works 47,175,440 52,170,000 50,300,000 46,000,000 37,500,000 233,145,440
Parks and Outdoors 3,415,000 6,450,000 3,900,000 2,100,000 2,100,000 17,965,000
Economic Development 300,000 - - - - 300,000
Enterprise 153,259,552 123,688,000 98,355,625 52,438,031 41,605,527 469,346,735
Wastewater 142,217,052 109,575,000 84,500,000 43,800,000 33,300,000 413,392,052
Stormwater 11,042,500 14,113,000 13,855,625 8,638,031 8,305,527 55,954,683
Total All Funds 218,472,822 196,658,700 166,555,625 114,188,031 91,305,527 787,180,705
C-25
C-26
City of Chattanooga
FY24-28 Capital Budget Summary by Project
Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 Proposed FY28 5 Year Total
General Governmental 65,213,270 72,970,700 68,200,000 61,750,000 49,700,000 317,833,970
General Government 4,672,830 2,600,000 1,200,000 1,200,000 1,200,000 10,872,830
Technology Services 2,938,000 1,000,000 800,000 800,000 800,000 6,338,000
City Network Rebuild 400,000 400,000 400,000 400,000 400,000 2,000,000
Citywide Camera Refresh 161,000 200,000 200,000 200,000 200,000 961,000
Digital Infrastructure Investments 77,000 - - - - 77,000
Google Workspace Back-up 200,000 200,000 - - - 400,000
Security Compliance Tools 100,000 - - - - 100,000
Smart City Testbed Expansion 1,850,000 - - - - 1,850,000
Traffic Signal Infrastructure Maintenance 150,000 200,000 200,000 200,000 200,000 950,000
Traffic Signal Upgrades - 100,000 100,000 100,000 100,000 400,000
Chattanooga Area Regional Transportation Authority 1,634,830 1,500,000 400,000 400,000 400,000 4,334,830
CARTA Vehicles & Equipment 1,634,830 1,500,000 400,000 400,000 400,000 4,334,830
Creative Discovery Museum (A.O.) 100,000 100,000 - - - 200,000
Ignite Discovery Capital Campaign (A.O.) 100,000 100,000 - - - 200,000
Community Development 400,000 - - - - 400,000
Community Development 400,000 - - - - 400,000
Hixson Community Center 150,000 - - - - 150,000
Washington Hills Community Center 250,000 - - - - 250,000
Police Department 950,000 5,600,000 6,900,000 6,550,000 3,100,000 23,100,000
Police Department 950,000 5,600,000 6,900,000 6,550,000 3,100,000 23,100,000
Law Enforcement Training Center 550,000 4,750,000 6,050,000 6,050,000 2,600,000 20,000,000
Police Laptop Replacement 400,000 350,000 350,000 - - 1,100,000
Police Service Renovation - 500,000 500,000 500,000 500,000 2,000,000
Fire Department 8,300,000 6,150,700 5,900,000 5,900,000 5,800,000 32,050,700
Fire Department 8,300,000 6,150,700 5,900,000 5,900,000 5,800,000 32,050,700
Apparatus Replacement Plan 2,500,000 4,400,000 4,400,000 1,500,000 1,500,000 14,300,000
Fire Equipment Capital Maintenance - 500,000 500,000 500,000 500,000 2,000,000
Fire Station Capital Maintenance 400,000 500,000 500,000 500,000 500,000 2,400,000
Fire Training Tower Replacement 3,000,000 - - - - 3,000,000
Regional Training Center - 500,000 500,000 3,400,000 3,300,000 7,700,000
Station #15 Replacement 400,000 250,700 - - - 650,700
Station #2 Apparatus 2,000,000 - - - - 2,000,000
Public Works 47,175,440 52,170,000 50,300,000 46,000,000 37,500,000 233,145,440
Public Works 47,175,440 52,170,000 50,300,000 46,000,000 37,500,000 233,145,440
3rd Street & 4th Street Corridor - - - 5,000,000 - 5,000,000
Alton Park Connector - 2,500,000 2,500,000 - - 5,000,000
Bridge Maintenance 250,000 2,050,000 1,500,000 1,500,000 1,500,000 6,800,000
Broad Street Re-design - 2,500,000 2,500,000 2,500,000 2,500,000 10,000,000
C-27
City of Chattanooga
FY24-28 Capital Budget Summary by Project
Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 Proposed FY28 5 Year Total
CDBG Sidewalks 200,000 - - - - 200,000
Central Ave. Extension - - 10,500,000 - - 10,500,000
City Hall Annex Renovation 1,370,000 3,000,000 2,000,000 - - 6,370,000
Community Center Swimming Pool Repairs 200,000 - - - - 200,000
DRC Roof Replacement 1,900,000 - - - - 1,900,000
East Lake Connections - - - 500,000 - 500,000
Fleet Capital Infusion 4,500,000 - - - - 4,500,000
Goodwin Rd. - - 800,000 3,000,000 - 3,800,000
Hamilton Place Boulevard 1,500,000 1,000,000 - - - 2,500,000
Hwy 58 Bicycle and Pedestrian Facilities Phase 2 - 1,100,000 2,500,000 - - 3,600,000
Lake Resort Slope Repair 400,000 - - - - 400,000
Major Capital Maintenance Improvements Community Centers 1,000,000 1,000,000 3,000,000 3,000,000 3,000,000 11,000,000
Major Capital Maintenance Improvements Downtown Campus & Other Facilities 1,000,000 1,500,000 3,000,000 3,000,000 3,000,000 11,500,000
Manufacturers Rd./Hamm Gateway - 1,400,000 - - - 1,400,000
Pavement Management 10,000,000 10,000,000 10,000,000 10,000,000 10,000,000 50,000,000
Plan of Services Obligations 250,000 5,200,000 - - - 5,450,000
Public Works - Coronavirus Response and Relief 2,488,558 - - - - 2,488,558
Raccoon Mountain Water Service 250,000 - - - - 250,000
Refuse Trucks 1,275,000 - - - - 1,275,000
Roadway Rebuilding - 5,000,000 5,000,000 5,000,000 5,000,000 20,000,000
Shallowford Rd. - 800,000 2,000,000 10,000,000 10,000,000 22,800,000
Sidewalks - 2,000,000 2,000,000 2,000,000 2,000,000 8,000,000
Slope Management - 500,000 500,000 500,000 500,000 2,000,000
Walnut Street Bridge 18,061,882 2,250,000 - - - 20,311,882
Wilcox Blvd Bridge 1,630,000 10,370,000 2,500,000 - - 14,500,000
Wood Recycle Services Relocation 900,000 - - - - 900,000
Parks and Outdoors 3,415,000 6,450,000 3,900,000 2,100,000 2,100,000 17,965,000
Parks and Outdoors 3,415,000 6,450,000 3,900,000 2,100,000 2,100,000 17,965,000
Chattanooga Skatepark 1,000,000 2,000,000 - - - 3,000,000
Golf Course Renovations and Maintenance - 1,750,000 1,500,000 500,000 500,000 4,250,000
Lynnbrook Park 115,000 - - - - 115,000
Parks ADA Repairs - 300,000 300,000 300,000 300,000 1,200,000
Parks and Outdoors Plan Deferred Maintenance 400,000 500,000 500,000 500,000 500,000 2,400,000
Parks and Outdoors Plan Recommended Master Plans 400,000 500,000 500,000 500,000 500,000 2,400,000
Provence Park 1,300,000 300,000 - - - 1,600,000
Schoolyards Program 200,000 - - - - 200,000
Softball Facility Improvements - 800,000 800,000 - - 1,600,000
Trail and Greenway Capital Maintenance - 300,000 300,000 300,000 300,000 1,200,000
C-28
City of Chattanooga
FY24-28 Capital Budget Summary by Project
Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 Proposed FY28 5 Year Total
Economic Development 300,000 - - - - 300,000
Economic Development 300,000 - - - - 300,000
Affordable Housing Trust Fund - - - - - -
Land Acquisition - Lead Abatement Program 300,000 - - - - 300,000
Enterprise 153,259,552 123,688,000 98,355,625 52,438,031 41,605,527 469,346,735
Wastewater 142,217,052 109,575,000 84,500,000 43,800,000 33,300,000 413,392,052
Wastewater 142,217,052 109,575,000 84,500,000 43,800,000 33,300,000 413,392,052
23rd St Pump Station Improvements 1,100,000 - - - - 1,100,000
Anaerobic Digester Rehab 1,000,000 4,000,000 - - - 5,000,000
Citico Force Main Replacement - 5,000,000 - - - 5,000,000
Contingency - Plans and Studies - - - 300,000 300,000 600,000
Contingency MBWWTP Improvements - 2,000,000 2,000,000 5,000,000 5,000,000 14,000,000
E2I2 SSO Abatement Program 10,000,000 - - - - 10,000,000
Equipment Purchases 206,500 - - - - 206,500
Focused SSES and Rehab - Phase II 8,500,000 9,000,000 9,000,000 10,000,000 10,000,000 46,500,000
Highland Park Pump Station Improvements 2,100,000 - - - - 2,100,000
Hixson Pump Station #3 Safety Upgrades - - 500,000 2,500,000 - 3,000,000
Influent Pump Station Improvements (IPS Screen Bypass) 1,500,000 - - - - 1,500,000
ISS Capacity Improvements - Creekside Preserve 1,000,000 3,000,000 3,000,000 5,000,000 5,000,000 17,000,000
Long Term Control Plan Upgrades 700,000 - - - - 700,000
MBWWTP Electrical Upgrades (S&C Switches) 2,000,000 - - - - 2,000,000
MBWWTP EQ - UNOX Piping Improvements 1,700,000 - - - - 1,700,000
MBWWTP North Recycle Pump Station 2,500,000 5,000,000 - - - 7,500,000
MBWWTP Oxygen Plant Replacement 10,000,000 - - - - 10,000,000
MBWWTP Solids Process Optimization Implementation - Phase 4 (Digester/THP Improvements) 20,000,000 20,000,000 18,000,000 - - 58,000,000
MBWWTP Water Use and Reuse Implementation - 4,500,000 - - - 4,500,000
MBWWTP Wet Weather Treatment Upgrade 15,000,000 30,000,000 35,000,000 - - 80,000,000
New Biosolids Staging Area 900,000 - - - - 900,000
Office Space Expansion/Renovation 1,000,000 - - - - 1,000,000
Program Management For Consent Decree Implementation 2,600,000 2,600,000 3,000,000 3,000,000 3,000,000 14,200,000
Pump Station Improvements - 19th St PS - 500,000 3,000,000 - - 3,500,000
Pump Station Improvements - Big Ridge #1 - - 500,000 4,000,000 - 4,500,000
Pump Station Improvements - Big Ridge #12 and others - - - 10,000,000 10,000,000 20,000,000
Pump Station Improvements - Boy Scout Rd - - 500,000 2,500,000 - 3,000,000
Pump Station Improvements - Hixson 2 (Bundle) 6,500,000 - - - - 6,500,000
Sandswitch Road Point Repairs 625,000 625,000 - - - 1,250,000
Sandswitch Road Sewer Lining 2,500,000 2,350,000 - - - 4,850,000
C-29
City of Chattanooga
FY24-28 Capital Budget Summary by Project
Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 Proposed FY28 5 Year Total
Sanitary Sewers for Annexed Areas - 4,500,000 4,000,000 - - 8,500,000
Sewer Bypass Pumps 145,000 - - - - 145,000
Sewer Line Extensions 575,000 - - - - 575,000
Shop Equipment and Tool Room 250,000 - - - - 250,000
Shop Storage and Organization 50,000 - - - - 50,000
Smart Sewer Implementation 350,000 500,000 1,000,000 1,500,000 - 3,350,000
Software Upgrades 195,000 - - - - 195,000
South Chick Pump Station Improvements 5,000,000 10,000,000 - - - 15,000,000
Tiftonia Pump Station #1 Safety Upgrade - - 5,000,000 - - 5,000,000
Tiftonia Pump Station #3 Safety Upgrade - 2,500,000 - - - 2,500,000
Training Center Expansion 500,000 1,000,000 - - - 1,500,000
Vehicle Purchases 1,053,500 - - - - 1,053,500
Warehouse Racking 500,000 - - - - 500,000
Wet Weather Storage Phase 4 - South Chic PS 25,000,000 - - - - 25,000,000
Wet Weather Storage Phase 6 - Hixson PS #1 16,667,052 - - - - 16,667,052
Wilcox Blvd Chronic SSO 500,000 2,500,000 - - - 3,000,000
Stormwater 11,042,500 14,113,000 13,855,625 8,638,031 8,305,527 55,954,683
Public Works - Stormwater 11,042,500 14,113,000 13,855,625 8,638,031 8,305,527 55,954,683
3469 Brainerd Rd 1,000,000 1,000,000 - - - 2,000,000
Automated Flood Warning System 360,000 375,000 375,000 385,000 400,000 1,895,000
Briarwood Circle 1,030,000 1,050,000 1,100,000 1,125,500 1,200,000 5,505,500
Broad Street - MLK to Aquarium Way 350,000 350,000 350,000 - - 1,050,000
Central Ave Ext Separation - 3,683,000 4,620,000 1,030,000 - 9,333,000
Dartmouth/Five Points Watershed SIP 2,000,000 2,060,000 2,200,000 - - 6,260,000
Drainage Projects 500,000 500,000 500,000 500,000 500,000 2,500,000
Floodplain Modeling 250,000 312,500 375,000 450,000 540,000 1,927,500
Green Infrastructure SOV Bank 100,000 125,000 162,500 227,500 318,500 933,500
Heavy Equipment 485,000 635,000 635,000 775,000 650,000 3,180,000
On-Call Landscape Design 250,000 325,000 422,500 528,125 660,150 2,185,775
Stormwater Asset Management Plan 1,545,000 1,030,000 - - - 2,575,000
Stream Buffer Conservation 250,000 325,000 390,000 487,500 585,000 2,037,500
Stream Restoration/Various Sites 312,500 375,000 450,000 540,000 648,000 2,325,500
TN Riverbank Stabilization 1,030,000 1,100,000 1,250,000 1,400,000 1,500,000 6,280,000
USACE/FEMA Floodplain Culvert Replacement Projects 880,000 262,500 275,625 289,406 303,877 2,011,408
WQ TMDL & Land Management 550,000 605,000 750,000 900,000 1,000,000 3,805,000
WQ Vehicles 150,000 - - - - 150,000
Total 218,472,822 196,658,700 166,555,625 114,188,031 91,305,527 787,180,705
C-30
RESOLUTION NO. _____________
A RESOLUTION INDICATING INTENT OF THE CITY OF CHATTANOOGA ,
TENNESSEE, TO ISSUE ITS BONDS OR OTHER OBLIGATION OF
INDEBTEDNESS RELATING TO PUBLIC WORKS PROJECTS OF THE CITY
WITH THE PROCEEDS OF BONDS OR OTHER DEBT OBLIGATIONS TO BE
ISSUED BY THE CITY OF CHATTANOOGA, TENNESSEE.
WHEREAS, the City Council of the City of Chattanooga, Tennessee (the "City") has determined
that it is necessary and advisable for the City to issue bonds, notes and/or loans for the purpose of financing,
in whole or in part, (i) constructing, improving, repairing, renovating and equipping of public buildings,
city hall , fire department buildings, parks and recreation facil ities, (ii) the acquisition of equipment,
including vehicles, for City purposes ; (iii) constructing and improving roads, streets, bridges , sidewalks,
culverts, plazas and highways; and (iv) payment of legal, fiscal, administrative, architectural and
engineering costs incident to all of the foregoing (collectively, the "Projects"); and
WHEREAS, the City expects to incur certain expenses in connection with undertaking such
Projects; and
WHEREAS, the City Council of the City desires to state its intentions with respect to the
reimbursement of such expenditures in accordance with the requirements of the regulations applicable
thereto promulgated by the United States Department of Treasury; and
NOW, THEREFORE, BE RESOLVED by the City Council of the City of Chattanooga, Tennessee
as follows:
Section 1 . The City hereby states that it reasonably expects to reimburse itself for certain
expenditures to be made by the City in connection with the undertaking of the Projects.
Section 2. The maximum principal amount of bonds or other indebtedness expected to be issued
for the purpose of reimbursing the City for expenditures in connection with the Projects is $15,500,000.
The bonds or other indebtedness expected to be issued to finance the Projects are expected to be general
obligations of the City.
Section 3. This resolution shall be placed in the minutes of the City Council and shall be made
available for inspection by the general public.
Section 4. The City's statement of intent in this resolution to reimburse itself for the expenditures
described herein is consistent with the budgetary and financial circumstances of the City as of the date of
this resolution.
Section 5. This resolution constitutes a declaration of official intent under Treas. Reg. § 1.150-2.
Section 6. The adoption of this resolution shall not in any event require the City to carry out any
Projects referenced herein. Any notes or other indebtedness of the City to be issued to finance any of the
Projects referenced herein shall only be issued after compliance by the City with all requirements of law.
Section 7. All resolutions or parts of resolutions in conflict herewith are hereby repealed, and this
resolution shall be in immediate effect from and after its adoption.
DRAFT
C-31
Section 8. This resolution shall take effect immediately.
ADOPTED: June ______, 2023.
35804002.2
DRAFT
C-32