FY23 Proposed Capital Budget
City of Chattanooga · Hamilton County · Budget documents
Open the original document More from City of Chattanooga
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
ONE CHATTANOOGA
CAPITAL
BUDGET
2023-2027
CITY OF CHATTANOOGA
MAYOR TIM KELLY
TABLE OF CONTENTS
Capital Improvement Plan………………………….…………………. C‐1
Governmental Fund Projects…......................... C‐1
Enterprise Fund Projects
Interceptor Sewer System…………………….. C‐7
Water Quality……………………………………….. C‐10
Capital Improvement Ordinance……………………. C‐15
Fiscal Year 2023 Plan…………………………………..…. C‐17
Five‐Year Capital Improvement Plan Resolution C‐23
Fiscal Year 2023 thru 2027 Plan……………………… C‐25
Bond Resolution…………………………………………….. C‐31
IntroductionThe FY23-27 Capital Improvement Plan (CIP) is the City of Chattanooga’s five-year plan forcapital improvement throughout Chattanooga. The first year of the CIP is the fiscally constrainedbudget, whereas the successive years are a roadmap for future action. Repairing essentialinfrastructure, improving delivery of services for all Chattanoogans, expanding great communityspaces, and more; this CIP is a commitment to the goals and strategies of the One Chattanoogastrategic plan.The information below provides summariesof the projects included in theFY23 capital budget. Funding sources for these projectsinclude reserve funds, generalobligation bonds, grants, external funds, internal service funds, and state loan funds.
General Government Projects
Better GovernmentProjects Funded: 7Total Funding: $2,500,000% External Funding: 0%
City Facilities Capital Improvements and/or Campus ConsolidationSeveral of the City's facilities are past their usable life and/or require extensive capitalinvestment to ensure they are safe, efficient, and welcoming. A Major Facility Assessment Studyis being performed to evaluate existing facilities for the viability of rehabilitation, renovations,and/or recommendations for modernization and better cost efficient facilities, along with theirfunctionality and future uses.
City Hall Campus RenovationImprovements to City Hall work areas and public spaces
Cloud Software Service (SaaS)This funding will cover contracted annual spending for support of the City’s Cloud SoftwareService that is used by all departments.
City Network RebuildRefresh of essential IT hardware. The Department of Information Technology has set a policy ofreplacing hardware every 5 years to ensure that devices are supported by vendors and canhave the latest security patches installed to protect the City’s infrastructure.
City Wide Time ClockReplacement of time clocks citywide. The majority of the time clocks installed across the Cityare at end of life and must be supported for the foreseeable future.
C -1
End of Life Network Infrastructure UpgradeThis funding will be used to refresh and maintain the digital infrastructure of the City. Thisincludes COLO and disaster recovery servers and network devices that should be replacedevery three to five years. The current equipment is in its fifth year.
IT Security Compliance ToolsImplementation of citywide multi-factor authentication. 2-Factor Authentication / Multi-FactorAuthentication is required to secure the City’s network, applications, software and systemaccess from malware, vandalism and hacking situations.
Economic DevelopmentProjects Funded: 3Total Funding: $10,204,080% External Funding: 24%
Enterprise South Industrial Park (ESIP) Early Site PrepThis project will fund the City of Chattanooga's portion of site preparation. ESIP Sitepreparation is needed because companies in need of available land and space for potentialfacilities need to visit a site that’s fully prepared. Totaling nearly 110 acres in size, this additionalproperty could be home to the next automotive supplier or electric vehicle battery manufacturerthat has the potential to create hundreds - if not thousands - of new jobs that pay a living wage.
Riverfront Parking Lot EasementCity contribution to allow for deed restrictions to be lifted on City parcel for potentialredevelopment.
Tivoli Theatre and Performing Arts CenterFunding for historic renovation and rehabilitation of the 100-year-old Tivoli Theatre. Thisinvestment leverages more than $50 million from other sources.
EducationProjects Funded: 2Total Funding: $525,000% External Funding: 0
Head Start Capital ImprovementsHead Start facilities are in need of significant repairs, including roof repair and smaller repairs inmultiple facilities.
Ignite Discovery Capital CampaignYear three of five year funding commitment to the Creative Discovery Museum’s capitalcampaign to enhance visitors’ experience and ensure long term sustainability.
C -2
FleetProjects Funded: 1Total Funding: $4,500,000% External Funding: 0
Fleet Program PurchasesAppropriate Fleet Program Reserve funds so that they may be used to replace vehiclescurrently in the program that are at the end of their lease terms.
GreenwaysProjects Funded: 1Total Funding: $500,000% External Funding: 0
Alton Park ConnectorThe City of Chattanooga in partnership with the Trust for Public Land is constructing the AltonPark Connector that will transform rail-corridors in the Alton Park area of the city into recreationtrails to re-establish neighborhood connectivity. The complete project corridor extends from theintersection of Central Ave and E. 38th Street to the intersection of W 33rd St. and St. Elmo Avealongside Southside Community Park and W. 33rd St.
HousingProjects Funded: 1Total Funding: $33,000,000% External Funding: 0
Affordable Housing Trust FundThe City's commitment toward a total $100 million investment in affordable housing over thenext five years. See budget executive summary for more detail.
LibraryProjects Funded: 2Total Funding: $173,091% External Funding: 0
Library ADA Accessibility ImprovementsThis project will fund necessary accessibility improvements to all Library locations.
Library Security Network Switch ReplacementThis project funded replacement of network switches at the Chattanooga Public Librarylocations. Additional funding is required to cover a shortfall in anticipated federal funds.
C -3
NeighborhoodsProjects Funded: 5Total Funding: $2,649,670% External Funding: 8%
CDBG SidewalksConstruction of sidewalks in designated low ‐ income neighborhoods where pedestrian travel isnecessary for many residents.
City Buildings & Community Centers Major System ReplacementThis funding will address major building system elements at Community Centers and other Citybuildings, such as HVAC systems, roofing system replacements, structural repairs, floorreplacements, restroom rehabilitation, building code upgrades, ADA Compliance, etc.
Family Justice Center Facilities ProjectTo support the mission critical work of the FJC and its colocated partners, multiple facilityimprovements are needed to improve safety and quality of service to victims of domesticviolence, sexual assault, human trafficking, elder abuse and child abuse.
Public ArtFunding for new art in capital projects and/or maintenance of the existing public art collection.
SidewalksThis project installs new and repairs existing sidewalks across the City to allow safe mobility byany user and to help encourage active public space and engagement of commercial andresidential areas.
OutdoorsProjects Funded: 2Total Funding: $525,750% External Funding: 0
Parks ADA RepairsChattanooga Parks and Outdoors facilities play a huge role in the health, safety, wellness, andsense of inclusion of the Chattanooga public. This project elevates those responsibilities bycontinuing our work to repair ADA noncompliance issues in parks, and making improvements tocity facilities.
Provence ParkCreation of a new City park to bring the City into compliance with Tennessee Department ofEnvironment and Conservation and National Park Service and to restore eligibility for OutdoorRecreation Legacy Partnership and Land and Water Conservation funding.
C -4
Public SafetyProjects Funded: 9Total Funding: $17,050,000% External Funding: 22%
Apparatus Replacement PlanThe Chattanooga Fire Department's Apparatus Replacement Plan (ARP) strategically planstoward the replacement of fire response apparatus. Of all of the vehicles used by thedepartment, these are the frontline workhorses of the department. Our firefighters provideexceptional service every hour of every day, and they could not do it without fire apparatus.FY23 and future year funding will replace apparatus which are at the end of their useful life andimplement an ongoing replacement schedule.
Capital Maintenance and Repair ProjectsFire station and building maintenance is vital to ensuring a healthy and operable place forfirefighters to work and live. This project will fund four major maintenance projects: continuedreplacement of aging apparatus bay exhaust systems, HVAC replacement (Fire and PoliceTraining Center), roof replacement (Station 21), and a new program to install proximity cardentry systems at fire stations.
Citywide Security CamerasThe Department of Technology Services maintains the support and functionality of the citywidecamera system including maintenance, damage, licensing and end-of-life replacement. Thisfunding will be used to maintain devices, refresh old equipment, and schedule new installations.
CPD Equipment and RMSSecond installment to replace existing CPD systems and equipment.
Law Enforcement Training CenterDesign and construction of the new Law Enforcement Training Center to replace the existingfiring range and consolidate other training activities held in various temporary locations.
Police Service RenovationMajor renovation and improvement of the Police Service Center, including HVAC replacementand other major repairs.
Regional Training CenterTraining firefighters and police officers requires an academic understanding of emergencyresponse work. However, it is vital to move the academic theory into a hands-on model oftraining. This necessary model cannot occur without the facilities to provide those experiences.The requested funds will be added to the previously budgeted capital funds toward eitherupgrading the regional training facility through significant renovation or working in collaborationwith the Hamilton County Emergency Management Agency (HCEMA) to build a new trainingcenter.
C -5
Real-Time Intelligence Center (RTIC)Expansion of the Real-Time Intelligence Center, including site modifications, and the purchaseof new equipment.
Station #15 ReplacementThis Capital request is for additional funding toward the construction of the Station 15Replacement project due to increases in and volatility of construction costs.
RecreationProjects Funded: 2Total Funding: $650,000% External Funding: 0
Golf Course Renovations and MaintenanceChattanooga’s Municipal golf courses provide excellent recreational opportunities toChattanooga residents at an affordable price. This funding provides for resurfacing of cart pathsfor both Brainerd and Brown Acres.
Parks, Playgrounds, Field MaintenanceThe Department of Parks and Outdoors maintains and repairs the several public restrooms,pavilions, barns, and other building structures throughout the park system. DPO will continuereplacement of heavily worn and damaged playground equipment at many sites that are nearthe end of typical life, major repairs and other routine maintenance activities to make Sports andRecreational complexes attractive to visitors and safe for participants.
Roads and BridgesProjects Funded: 7Total Funding: $22,825,000% External Funding: 26%
Lake Resort Slope RepairThis project will construct a permanent repair to Lake Resort Dr. that experienced failure fromexcessive rainfall in 2019.
Main St. ExtensionThis project will fund the extension of Main Street from Riverfront Parkway to the TennesseeRiverwalk. The creation of this infrastructure will provide additional public access toChattanooga’s most valuable park, the Tennessee Riverwalk, returning privately-owned landback to the City of Chattanooga to protect public access in perpetuity.
C -6
Pavement ManagementThese funds are used for the City’s annual resurfacing contract. They are a critical part ofcomprehensive pavement management that includes paving and preventative maintenancetechniques.
Standifer Gap Bridge ReplacementReplacement of the existing deficient and closed Standifer Gap Road bridge over Friar'sBranch, located between Glencroft Lane and Hickory Valley Road.
Traffic Signal Infrastructure MaintenanceThis funding will be used to maintain, refresh and upgrade the City of Chattanooga’s intersectiontraffic signals, signal controls, software and technical maintenance. There are 380 intersectionsin the City that are maintained by the Department of Technology Services - Smart CitiesDivision.
2021 CMAQ Traffic Signal Synchronization ProjectThis project will implement comprehensive traffic signal retiming citywide. It is completely fundedthrough a Federal Grant awarded in January of 2022.
Wilcox Blvd. BridgeThis project will replace the existing structurally deficient Wilcox Boulevard Bridge over theDeButts Railyard. The project is seeking one or more federal discretionary grants in addition topartnership with the Norfolk Southern Railway. The replacement structure will include amultimodal path and support development of a pedestrian connection from East Chattanooga tothe Riverwalk
TransitProjects Funded: 1Total Funding: $1,000,000% External Funding: 95%
North-South Multimodal Connectivity CorridorIn partnership with CARTA, install mobility hubs that include transit shelters, ADA accessibilityimprovements, lighting, and Bike Chattanooga Bicycle Transit System stations.
Interceptor Sewer System ProjectsProjects Funded: 22Total Funding: $97,000,000% External Funding: 0%
Chattanooga WW Consolidation StudyContingency funds allocated for the consolidation study.
C -7
Citico Pump Station ImprovementsContingency funds for capital improvements to the Citico Pump Station such as a New MotorControl Center, HVAC, Lighting, new pumps, motors and drives, wet well cleaned and coated,and other site improvements.
Contingency MBWWTP Improvements - General PurposeContingency funds allocated for MBWWTP improvement projects that have not been identifiedyet.
E2I2 SSO Abatement ProgramThis project is the overall E2I2 program, includes the development of a feasibility study todetermine the size, location, and required infrastructure improvements needed to construct EQstations with 47 MGD of capacity in 3 strategic locations. This project is a cooperative,cost-sharing undertaking with WWTA that will yield savings for tax and ratepayers inChattanooga and HCWWTA while providing the benefit of schedule extensions on certaincomponents of the City of Chattanooga's EPA Consent Decree.
Focused SSES and Rehab - Phase IIThis project involves completing Sanitary Sewer Evaluation Studies (SSES) and therehabilitation of sanitary sewer pipes in twenty-four of Chattanooga's Sewersheds, as directed inthe CD. These repairs will help reduce sanitary sewer overflows in the Sewersheds and willincrease overall collection system capacity to the MBWWTP.
Friars Branch Pump Station GrindersThe existing pump station has recently been upgraded but needs a new screening system toprevent rags and other debris from reaching and damaging the pumps. The City is requestingthe preliminary engineering, detailed design, bidding, construction administration and inspectionservices for a replacement pump station. The preliminary engineering phase will evaluatevarious options such as one or two grinders, or a bar screen and determine the mostcost-effective option
Highland Park Pump Station ImprovementsThis project includes improvements to the Highland Park wet weather Pump Station includingthe full rehabilitation of the pump station, replacement of pumps with VFDs, replacement of allelectrical and MCC, new discharge piping, new safety grating, and wet well lining.Implementation of CD Green Infra Projects in the CSSProject involves the implementation of the CD green infrastructure projects in the CSS.
MBWWTP EQ Blower ReplacementContingency funds for Equalization Basin and Blower Replacement Improvements. The goal ofthe project is to reduce annual power consumption from the Equalization Basin aeration systemand increase the available wet weather Equalization Basin capacity of the MBWWTP.
C -8
MBWWTP New Thickener PumpsThis project provides the necessary equipment required to maintain efficient and effective solidshandling, to ensure compliance with the City's NPDES permit for the MBWWTP.
MBWWTP North Recycle Pump StationProject involves the design and construction of a new recycle pump station at the MBWWTPand move drain piping effluent more efficiently to the discharge locations
MBWWTP Oxygen Plant ReplacementThis project includes the replacement of the MBWWTP Oxygen Plant, which has reached itsend of life, and needs to be replaced to continue reliable MBWWTP operations.
MBWWTP Solids Process Optimization Implementation - Phase 4 (Digester/THPImprovements)The project consists of solids handling facilities including pre-thickening and cake storage, THPand post-THP equipment provided by a vendor, steam generation/cooling, sludge blending, andanaerobic digesters. This new process will allow for continued operations and will increaseperformance in the solids handling process.
MBWWTP UNOX Electrical Upgrades (S&C Switches)Switches are outdated and obsolete Needs replacement prior to catastrophic failure or safetyissues arise during switching or operation
MBWWTP Vehicle Purchase and MaintainerAllows for continued reliable, efficient maintenance and operations
Program Management For Consent DecreeThis project is the annual renewal of the scope and fee of program management services for theimplementation of the EPA CD program.
Pump Station Generator 3This project involves the installation of emergency generator backup electrical power to selectedMBWWTP areas and pump stations to minimize the disrupted electrical service during poweroutages.
Pump Station Improvements - Hixson 2 (Bundle)This project includes the bidding, construction administration, construction inspection andconstruction costs associated with 4 pump stations previously designed
Riverview Park/CGCC Chronic SSO Elimination ProjectAdditional project funds for the Riverbank Stabilization at the Chattanooga Golf and CountryClub
C -9
South Chick Pump Station ImprovementsThis project includes making capital improvements to the South Chick. PS These improvementsare designed to improve the capacity, performance and reliability of the station and help toreduce sanitary sewer overflows in the area.
Tiftonia Pump Station #3 Safety UpgradeThis project includes safety and reliability improvements associated with converting the Tiftonia#2 PS from a canned pump station to a submersible pump station as well as the assessmentand rehabilitation or replacement of sewer force main in the basin
Winterview Pump Station and Basin ImprovementsThis project includes reliability and capacity improvements at the Winterview Pump Station aswell as the rehabilitation of sanitary sewer pipe in the basin. Improvements include potentialrehabilitation or replacement of pumps, valving, I&C/SCADA infrastructure, etc.
Water Quality ProjectsProjects Funded: 16Total Funding: $9,835,000% External Funding: 0%
2013 Briarwood CircleSeries of projects to reduce flooding in an 850-acre area.
Automated Flood Warning SystemAutomated flood warning system for flood prone streets around the City.
Dartmouth/Five Points Watershed SIPMulti-phase stormwater infrastructure replacement project. Rapid development in past years hascaused increased runoff potential in the area and taxed an undersized, aging system.
Drainage ProjectsVarious small drainage projects throughout the City.
Elder Mountain RoadEvaluate 23 existing cross drains between Isbill Rd and Elder Mountain gate house for integrityand adequacy due to apparent roadway failures at various locations
Floodplain ModelingProvide accurate, up-to-date information regarding flood levels, flood risk, and associatedhazards for areas with the City.
C -10
Heavy EquipmentNew equipment to replace existing and aging equipment.
Natural Resource Storage - Watkins StreetThe outdoor area at the DPO building on Watkins St. has been identified as the best location.This budget would provide for building/installation of the following: hoop house, tools storagebuilding, covered area for equipment, covered bays for materials storage, gutters and rainbarrels for stormwater control, potential fence repairs/upgrades, and potential repaving.
Provence Park 3332 Provence StreetProvide Water Quality elements for new Park.
Pumpkin Pie Lane (Pumpkin Pie @ West 57th)Repair and future replacement of bridge over stream.
Stormwater Asset Management PlanDevelopment of Stormwater Master Plan and Development of Stormwater Asset ManagementPlan.
Stream Buffer ConservationImplement a stream buffer program that benefits and improves streambank stabilization,erosion/sediment control, promotes habitat and wildlife along with reducing the impact fromfloods.
Stream Restoration/Various SitesReduce peak flow velocities which contribute to stream bank erosion, improving water qualitydownstream, restoring ecological habitat, and reducing peak flood stages.
TN Riverbank Stabilization ProjectSeries of projects for emergency stabilization of TN Riverbanks.
TMDL & Land ManagementTo preserve and enhance the quality of the physical environment with projects that meet theTMDL and WQ regulatory changes. These various projects will consist of planning, design, andconstruction to manage water quantity and improve water quality on City owned property.
USACE/FEMA Floodplain Culvert Replacement ProjectsCulvert replacement project to replace undersized culverts in FEMA mapped stream segmentsto 100 year conveyance capacity.
C -11
ORDINANC E NO. __________
AN ORDINANCE APPROPRIATING, AUTHORIZING OR
ALLOCATING FUNDS TO THE CAPITAL IMPROVEMENTS
BUDGET FOR THE FISCAL YEAR 2022-2023.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA,
TENNESSEE:
S
ECTION 1. That there be and is hereby appropriated, authorized, or allocated the
hereinafter set funds from the sources specified for the public purposes indicated of the Capital
Improvements Plan for the Fiscal Year Ending June 30, 2023:
SECTION 2. That there be and is hereby authorized the appropriation of all capital
donations, including partnership agreements not previously appropriated, to the projects and the capital
fund for which they are intended.
GENERAL GOVERNMENTAL FUNDS
C - 15
DRAFT
PROPRIETARY
CAPITAL FUNDS
BE IT FURT
HER ORDAINED, That this Ordinance shall take effect immediately from and after its
passage as provided by law.
PASSED _____________________, 2022
__________________________________________
CHAIRPERSON
APPROVED_______ DISAPPROVED _________
DATE: ______________________________, 2022
__________________________________________
MAYOR
C - 16
DRAFT
City of Chattanooga
Capital Budget Summary by Department
Fiscal Year 2023
Summary Schedule (Capital)
Proposed FY23 External Sources Reserves Operations GO Bonds SRF WIFIA EconDev
Other City
Sources Total
General Governmental 96,102,591 13,002,591 33,000,000 2,500,000 30,000,000 8,250,000 9,350,000 96,102,591
General Government 10,533,171 2,893,091 - 1,405,000 2,435,080 3,800,000 10,533,171
Economic Development 38,019,000 2,409,500 33,000,000 2,609,500 38,019,000
Fire Department 8,300,000 8,300,000 8,300,000
Parks & Outdoors 1,175,750 1,175,750 1,175,750
Police Department 8,600,000 3,750,000 600,000 4,250,000 8,600,000
Public Works 29,049,670 3,950,000 70,000 17,450,000 2,029,670 5,550,000 29,049,670
Early Learning 425,000 425,000 425,000
Enterprise 106,835,000 27,635,000 32,200,000 (30,000,000) 10,000,000 67,000,000 106,835,000
Interceptor Sewer System 97,000,000 24,500,000 25,500,000 (30,000,000) 10,000,000 67,000,000 97,000,000
Water Quality 9,835,000 3,135,000 6,700,000 9,835,000
Total All Funds 202,937,591 13,002,591 60,635,000 34,700,000 - 10,000,000 67,000,000 8,250,000 9,350,000 202,937,591
C - 17
C - 18
City of Chattanooga
Capital Budget Summary by Project
Fiscal Year 2023
**The initials "A.O." and "A.S.F." as appear in this section shall have the same meaning as described in Section 5a of the Operating Budget Ordinance 13xxx
Departments Proposed FY23 External Reserves Operations Bonds SRF WIFIA
Economic
Development Other City Total
General Governmental 96,102,591 13,002,591 33,000,000 2,500,000 30,000,000 8,250,000 9,350,000 96,102,591
General Government 10,533,171 2,893,091 - 1,405,000 2,435,080 3,800,000 10,533,171
Chattanooga Public Library 173,091 (131,909) 105,000 400,000 (200,000) 173,091
Library Security Network Switch Replacement (26,909) (131,909) 105,000 (26,909)
Library ADA Accessibility Improvements 200,000 400,000 (200,000) 200,000
Information Technology 4,525,000 3,025,000 1,300,000 200,000 4,525,000
2021 CMAQ Traffic Signal Synchronization Project 3,025,000 3,025,000 3,025,000
City Network Rebuild 400,000 400,000 400,000
City Wide Time Clock 150,000 150,000 150,000
Citywide Security Cameras 150,000 150,000 150,000
Cloud Software Service (SaaS) 200,000 200,000 200,000
End of Life Network Infrastructure Upgrade 300,000 300,000 300,000
IT Security Compliance Tools 100,000 100,000 100,000
Traffic Signal Infrastructure Maintenance 200,000 200,000 200,000
Finance 735,080 735,080 735,080
City Hall Campus Improvements 350,000 350,000 350,000
Riverfront Property Lot Easement 385,080 385,080 385,080
Tivoli Foundation (A.O.) 5,000,000 1,000,000 4,000,000 5,000,000
Tivoli Theatre and Performing Arts Center (A.O.) 5,000,000 1,000,000 4,000,000 5,000,000
Creative Discovery Museum (A.O.) 100,000 - 100,000 100,000
Ignite Discovery Capital Campaign (A.O.) 100,000
- 100,000 100,000
Economic Development 38,019,000 2,409,500 33,000,000 2,609,500 38,019,000
Economic Development 38,019,000 2,409,500 33,000,000 2,609,500 38,019,000
ESIP Early Site Prep 4,819,000 2,409,500 2,409,500 4,819,000
Public Art 200,000 200,000 200,000
Affordable Housing Trust Fund (A.O.) 33,000,000 33,000,000 33,000,000
Fire Department 8,300,000 8,300,000 8,300,000
Fire Department 8,300,000 8,300,000 8,300,000
Apparatus Replacement Plan 6,000,000 6,000,000 6,000,000
Capital Maintenance and Repair Projects 500,000 500,000 500,000
Regional Training Center 300,000 300,000 300,000
Station #15 Replacement 1,500,000 1,500,000 1,500,000
Parks & Outdoors 1,175,750 1,175,750 1,175,750
Parks & Outdoors 1,175,750 1,175,750 1,175,750
Provence Park 225,750 225,750 225,750
Parks ADA Repairs 300,000 300,000 300,000
Parks, Playgrounds, Field Maintenance 300,000 300,000 300,000
Golf Course Renovations and Maintenance 350,000 350,000 350,000
Police Department 8,600,000 3,750,000 600,000 4,250,000 8,600,000
Chattanooga Police Department 8,600,000 3,750,000 600,000 4,250,000 8,600,000
CPD Equipment and RMS 300,000 300,000 300,000
Law Enforcement Training Center 7,500,000 3,750,000 3,750,000 7,500,000
Police Service Renovation 500,000 500,000 500,000
RTIC 300,000 300,000 300,000
Public Works 29,049,670 3,950,000 70,000 17,450,000 2,029,670 5,550,000 29,049,670
Public Works 29,049,670 3,950,000 70,000 17,450,000 2,029,670 5,550,000 29,049,670
Alton Park Connector 500,000 500,000 500,000
City Buildings & Community Centers Major System
Replacement 1,000,000 1,000,000 1,000,000
City Facilities Capital Improvements and/or Campus
Consolidation 1,000,000 1,000,000 1,000,000
Family Justice Center Facilities Project 125,000 125,000 125,000
Fleet Program Purchases 4,500,000 4,500,000 4,500,000
Lake Resort Slope Repair 3,100,000 1,600,000 1,500,000 3,100,000
Main Street Extension 4,500,000 4,500,000 4,500,000
Pavement Management 10,000,000 8,950,000 1,050,000 10,000,000
Sidewalks 1,124,670 70,000 1,054,670 1,124,670
Standifer Gap Bridge Replacement 500,000 500,000 500,000
C - 19
City of Chattanooga
Capital Budget Summary by Project
Fiscal Year 2023
Departments Proposed FY23 External Reserves Operations Bonds SRF WIFIA
Economic
Development Other City Total
Wilcox Blvd Bridge 1,500,000 1,200,000 300,000 1,500,000
CDGB Sidewalks 200,000 200,000 200,000
North-South Multimodal Connectivity Corridor 1,000,000 950,000 50,000 1,000,000
Early Learning 425,000 425,000 425,000
Early Learning 425,000 425,000 425,000
Head Start Capital Repairs 425,000 425,000 425,000
Enterprise 106,835,000 27,635,000 32,200,000 (30,000,000) 10,000,000 67,000,000 106,835,000
Interceptor Sewer System 97,000,000 24,500,000 25,500,000 (30,000,000) 10,000,000 67,000,000 97,000,000
PW-ISS 97,000,000 24,500,000 25,500,000 (30,000,000) 10,000,000 67,000,000 97,000,000
Chattanooga WW Consolidation Study 500,000 500,000 500,000
Citico Pump Station Improvements 4,000,000 4,000,000 4,000,000
Contingency MBWWTP Improvements - General Purpose 2,000,000 2,000,000 2,000,000
E2I2 SSO Abatement Program 60,000,000 15,000,000 45,000,000 60,000,000
Focused SSES and Rehab - Phase II 8,000,000 8,000,000 8,000,000
MBWWTP EQ Blower Replacement 750,000 750,000 750,000
MBWWTP Oxygen Plant Replacement 12,000,000 12,000,000 12,000,000
MBWWTP Solids Process Optimization Implementation - Phase 20,000,000 10,000,000 10,000,000 20,000,000
Program Management For Consent Decree 3,400,000 3,400,000 3,400,000
Pump Station Generator 3 750,000 750,000 750,000
Winterview Pump Station and Basin Improvements 500,000 500,000 500,000
MBWWTP New Thickener Pumps 400,000 400,000 400,000
E2I2 SSO Abatement Program - East Ridge (20,000,000) (20,000,000) (20,000,000)
E2I2 SSO Abatement Program - Lee Hwy (5,000,000) (5,000,000) (5,000,000)
E2I2 SSO Abatement Program - Red Bank (5,000,000) (5,000,000) (5,000,000)
Tiftonia Pump Station #3 Safety Upgrade 500,000 500,000 500,000
South Chick Pump Station Improvements 1,500,000 1,500,000 1,500,000
Riverview Park/CGCC Chronic SSO Elimination Project 500,000 500,000 500,000
Pump Station Improvements - Hixson 2 (Bundle) 6,500,000 6,500,000 6,500,000
MBWWTP Vehicle Purchase and Maintainer 1,350,000 1,350,000 1,350,000
MBWWTP North Recycle Pump Station 1,000,000 1,000,000 1,000,000
MBWWTP Electrical Improvements (S&C Switches) 500,000 500,000 500,000
Implementation of CD Green Infra Projects in the CSS 500,000 500,000 500,000
Highland Park Pump Station Improvements 2,000,000 2,000,000 2,000,000
Friars Branch Pump Station Grinders 350,000 350,000 350,000
Water Quality 9,835,000 3,135,000 6,700,000 9,835,000
Public Works - Water Quality 9,835,000 3,135,000 6,700,000 9,835,000
2013 Briarwood Circle 1,000,000 1,000,000 1,000,000
Automated Flood Warning System 350,000 350,000 350,000
Dartmouth/Five Points Watershed SIP 2,750,000 2,750,000 2,750,000
Drainage Projects 500,000 500,000 500,000
Elder Mountain Road 890,000 890,000 890,000
Floodplain Modeling 200,000 200,000 200,000
Heavy Equipment 570,000 570,000 570,000
Natural Resource Storage - Watkins Street 75,000 75,000 75,000
Provence Park 3332 Provence Street 250,000 250,000 250,000
Pumpkin Pie Lane (Pumpkin Pie @ West 57th) 50,000 50,000 50,000
Stormwater Asset Management Plan 1,000,000 1,000,000 1,000,000
Stream Buffer Conservation 200,000 200,000 200,000
TMDL & Land Management 500,000 500,000 500,000
TN Riverbank Stabilization Project 1,000,000 1,000,000 1,000,000
USACE/FEMA Floodplain Culvert Replacement Projects 250,000 250,000 250,000
Stream Restoration/Various Sites 250,000 250,000 250,000
Grand Total 202,937,591 13,002,591 60,635,000 34,700,000 - 10,000,000 67,000,000 8,250,000 9,350,000 202,937,591
C - 20
City Of Chattanooga
Other City and External Sources by Project
Fiscal Year 2023
Department
Recommended
Other City Sources
Fleet Mgt Fund
(6504) Hotel/Motel
Library
Reserves
State Street
Aid Ops
(2050)
State Street
Aid Reserves
IDB TIF
Loan
Recommended
External Sources
Surface
Transportation
Block Grant (STBG)
Multimodal
Access Grant CDGB
Hamilton
County
Congestion
Mitigation and Air
Quality
Improvement
(CMAQ)
Federal
Communications
Commission
(FCC)
General Government 3,800,000 4,000,000 (200,000) 2,893,091 3,025,000 (131,909)
Police - 3,750,000 3,750,000
Public Works 5,550,000 4,500,000 1,050,000 3,950,000 2,800,000 950,000 200,000
Economic Development - 2,409,500 2,409,500
Total Govt Funds 9,350,000 4,500,000 4,000,000 (200,000) - 1,050,000 - 13,002,591 2,800,000 950,000 200,000 6,159,500 3,025,000 (131,909)
Total All Funds 9,350,000 4,500,000 4,000,000 (200,000) - 1,050,000 - 13,002,591 2,800,000 950,000 200,000 6,159,500 3,025,000 (131,909)
General Government 3,800,000 2,893,091
Library ADA Accessibility Improvements (200,000) (200,000) -
Library Security Network Switch
Replacement - (131,909) (131,909)
2021 CMAQ Traffic Signal
Synchronization Project - 3,025,000 3,025,000
Tivoli Theatre 4,000,000 4,000,000 -
-
Public Works 5,550,000 7,700,000
Fleet Program Purchases 4,500,000 4,500,000 -
Pavement Management 1,050,000 1,050,000 -
CDBG Sidewalks - 200,000 200,000
Lake Resort Slope Repair - 1,600,000 1,600,000
North-South Multimodal Connectivity
Corridor - 950,000 950,000
Law Enforcement Training Cente
r - 3,750,000 3,750,000
Wilcox Blvd. Bridge - 1,200,000 1,200,000
Economic Development - 2,409,500
ESIP Early Site Prep - 2,409,500 2,409,500
Total Projects 9,350,000 - - - - - - 13,002,591 2,800,000 950,000 200,000 6,159,500 3,025,000 (131,909)
External Funding SourcesOther City Sources
C - 21
C - 22
RESOLUTION NO. __________
A RESOLUTION ADOPTING A FIVE-YEAR CAPITAL
IMPROVEMENT PLAN FOR FISCAL YEARS 2023-2027,
SUBJECT TO FUTURE REVISION; A COPY OF WHICH IS
ATTACHED HERETO AND MADE A PART HEREOF BY
REFERENCE.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA,
TENNESSEE, That there be and is hereby adopted a five-year Capi tal Improvement Plan for
Fiscal Years 2023-2027 for the City of Chattanooga, subject to future revisions; a copy of which
is attached hereto and made a part hereof by reference.
ADOPTED: ______________________, 2022
C - 23
DRAFT
C - 24
City of Chattanooga
FY23-27 Capital Budget Summary by Department
Department Proposed FY23 Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 5 Year Total
General Governmental 96,102,591 81,739,000 90,510,000 93,610,000 68,260,000 430,221,591
City Planning 1,000,000 1,000,000 1,000,000 1,000,000 4,000,000
Economic Development 38,019,000 1,760,000 860,000 760,000 760,000 42,159,000
Fire Department 8,300,000 5,100,000 3,100,000 6,500,000 7,000,000 30,000,000
General Government 10,533,171 3,700,000 3,850,000 1,250,000 1,250,000 20,583,171
Parks & Outdoors 1,175,750 7,100,000 6,925,000 7,125,000 8,125,000 30,450,750
Police Department 8,600,000 9,500,000 - 3,500,000 - 21,600,000
Public Works 29,049,670 53,579,000 74,775,000 73,475,000 50,125,000 281,003,670
Early Learning 425,000 425,000
Enterprise 106,835,000 115,038,600 99,930,253 96,103,268 60,846,663 478,753,784
Interceptor Sewer System 97,000,000 103,721,000 88,616,000 82,404,000 52,640,000 424,381,000
Water Quality 9,835,000 11,317,600 11,314,253 13,699,268 8,206,663 54,372,784
Grand Total 202,937,591 196,777,600 190,440,253 189,713,268 129,106,663 908,975,375
C - 25
C - 26
City of Chattanooga
FY23-27 Capital Budget Summary by Project
Department Proposed FY23 Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 5 Year Total
General Governmental 96,102,591 81,739,000 90,510,000 93,610,000 68,260,000 430,221,591
General Government 10,533,171 3,700,000 3,850,000 1,250,000 1,250,000 20,583,171
Chattanooga Public Library 173,091 2,200,000 2,500,000 4,873,091
Library Local History Facility and Service Improvements 1,000,000 1,000,000
Library Security Network Switch Replacement (26,909) (26,909)
Library ADA Accessibility Improvements 200,000 1,200,000 2,500,000 3,900,000
Creative Discovery Museum 100,000 100,000 100,000 300,000
Ignite Discovery Capital Campaign 100,000 100,000 100,000 300,000
Information Technology 4,525,000 1,400,000 1,250,000 1,250,000 1,250,000 9,675,000
2021 CMAQ Traffic Signal Synchronization Project 3,025,000 3,025,000
City Network Rebuild 400,000 400,000
City Wide Time Clock 150,000 150,000
Citywide Security Cameras 150,000 250,000 250,000 250,000 250,000 1,150,000
Cloud Software Service (SaaS) 200,000 200,000
End of Life Network Infrastructure Upgrade 300,000 300,000
Firewall Upgrade 150,000 150,000
IT Security Compliance Tools 100,000 100,000
Traffic Signal Infrastructure Maintenance 200,000 1,000,000 1,000,000 1,000,000 1,000,000 4,200,000
Tivoli Foundation 5,000,000 5,000,000
Tivoli Theatre and Performing Arts Center 5,000,000 5,000,000
Finance 735,080 735,080
Riverfront Property 385,080 385,080
City Hall Campus Improvements 350,000 350,000
City Planning 1,000,000 1,000,000 1,000,000 1,000,000 4,000,000
City Planning 1,000,000 1,000,000 1,000,000 1,000,000 4,000,000
Neighborhood Equity Fund 1,000,000 1,000,000 1,000,000 1,000,000 4,000,000
Economic Development 38,019,000 1,760,000 860,000 760,000 760,000 42,159,000
Economic Development 38,019,000 1,760,000 860,000 760,000 760,000 42,159,000
Brainerd Tech Program 760,000 760,000 760,000 760,000 3,040,000
Chattanooga Land Bank Authority 1,000,000 100,000 1,100,000
ESIP Early Site Prep 4,819,000 4,819,000
Affordable Housing Trust Fund 33,000,000 33,000,000
Public Art 200,000 200,000
Fire Department 8,300,000 5,100,000 3,100,000 6,500,000 7,000,000 30,000,000
Fire Department 8,300,000 5,100,000 3,100,000 6,500,000 7,000,000 30,000,000
Apparatus Replacement Plan 6,000,000 3,500,000 1,500,000 1,500,000 1,500,000 14,000,000
Capital Maintenance and Repair Projects 500,000 500,000 500,000 500,000 500,000 2,500,000
Fire Equipment Capital Maintenance 500,000 500,000 500,000 500,000 2,000,000
Regional Training Center 300,000 600,000 600,000 4,000,000 4,500,000 10,000,000
Station #15 Replace 1,500,000 1,500,000
Parks & Outdoors 1,175,750 7,100,000 6,925,000 7,125,000 8,125,000 30,450,750
Parks & Outdoors 1,175,750 7,100,000 6,925,000 7,125,000 8,125,000 30,450,750
Avondale Playground 250,000 250,000
Natural Resources Management 300,000 350,000 350,000 350,000 1,350,000
Parks and Outdoors Plan Recommendation Implementation 1,000,000 2,000,000 3,000,000 4,000,000 10,000,000
Provence Park 225,750 1,000,000 1,225,750
Softball Facility Improvements 800,000 800,000 - - 1,600,000
Sport Court & Fitness Maintenance 500,000 500,000 500,000 500,000 2,000,000
Trail and Greenway Capital Maintenance 275,000 275,000 275,000 275,000 1,100,000
C - 27
City of Chattanooga
FY23-27 Capital Budget Summary by Project
Department Proposed FY23 Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 5 Year Total
Trail Branding Implementation 150,000 150,000 150,000 150,000 600,000
Parks ADA Repairs 300,000 300,000 300,000 300,000 300,000 1,500,000
Parks, Playgrounds, Field Maintenance 300,000 500,000 500,000 500,000 500,000 2,300,000
Golf Course Renovations and Maintenance 350,000 1,750,000 1,750,000 1,750,000 1,750,000 7,350,000
Golf Course Capital Equipment 275,000 300,000 300,000 300,000 1,175,000
Police Department 8,600,000 9,500,000 - 3,500,000 - 21,600,000
Chattanooga Police Department 8,600,000 9,500,000 - 3,500,000 - 21,600,000
CPD Equipment and RMS 300,000 300,000
Law Enforcement Training Center 7,500,000 9,500,000 - 3,500,000 - 20,500,000
Police Service Renovation 500,000 500,000
RTIC 300,000 300,000
Public Works 29,049,670 53,579,000 74,775,000 73,475,000 50,125,000 281,003,670
Public Works 29,049,670 53,579,000 74,775,000 73,475,000 50,125,000 281,003,670
26th Street Complete Street Project 1,000,000 1,000,000
3rd Street & 4th Street Corridor 1,000,000 2,000,000 - - 3,000,000
Alton Park Connector 500,000 2,500,000 2,500,000 5,500,000
Bike Chattanooga Maintenance and Expansion 100,000 100,000 100,000 100,000 400,000
Bridges 2,000,000 2,000,000 2,000,000
2,000,000 8,000,000
Central Ave Extension - - 6,550,000 5,000,000 11,550,000
City Buildings & Community Centers Major System Replacement 1,000,000 2,000,000 2,000,000 2,000,000 2,000,000 9,000,000
City Facilities Capital Improvements and/or Campus Consolidation 1,000,000 2,000,000 2,000,000 2,000,000 2,000,000 9,000,000
East Lake Connections 75,000 2,000,000 2,000,000 2,000,000 6,075,000
Family Justice Center Facilities Project 125,000 125,000
Fleet Program Purchases 4,500,000 5,000,000 5,000,000 5,000,000 5,000,000 24,500,000
Goodwin Road - 1,000,000 - 10,000,000 11,000,000
Hamilton Place Boulevard 6,879,000 6,879,000
Lake Resort Slope Repair 3,100,000 3,100,000
Main Street Extension 4,500,000 4,500,000
Midtown Pathway 1,000,000 1,000,000 1,000,000 - 3,000,000
N Chickamauga Creek Connector (CB Robinson) - 500,000 1,000,000 7,000,000 8,500,000
Pavement Management 10,000,000 10,000,000 6,500,000 10,000,000 10,000,000 46,500,000
Pavement Preventative Maintenance 250,000 250,000 250,000 250,000 1,000,000
Plan of Services Obligations 5,200,000 5,200,000
Retaining Wall Management & Maintenance 75,000 75,000 75,000 75,000 300,000
Roadway Rebuilding 2,000,000 2,000,000 2,000,000 2,000,000 8,000,000
Shallowford Road 2,000,000 10,000,000 10,000,000 - 22,000,000
Sidewalks 1,124,670 2,000,000 2,000,000 2,000,000 2,000,000 9,124,670
Standifer Gap Bridge Replacement 500,000 500,000
Thermoplastic Long Line Marking 250,000 250,000 250,000 250,000 1,000,000
Walnut Street Bridge 1,500,000 200,000 2,000,000 200,000 3,900,000
Wilcox Blvd Bridge 1,500,000 2,500,000 25,000,000 25,000,000 - 54,000,000
CDGB Sidewalks 200,000 200,000
North-South Multimodal Connectivity Corridor 1,000,000 1,000,000
East Line 2,000,000 1,000,000 3,000,000
Roadway Slope Failure 250,000 800,000 250,000 250,000 1,550,000
TIP Paving - 3,500,000 3,500,000
University Greenway 2,000,000 1,000,000 3,000,000
Hwy 58 Bicycle and Pedestrian Facilities Phase 2 - 2,100,000 - - 2,100,000
Early Learning 425,000 425,000
C - 28
City of Chattanooga
FY23-27 Capital Budget Summary by Project
Department Proposed FY23 Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 5 Year Total
Early Learning 425,000 425,000
Head Start Capital Repairs 425,000 425,000
Enterprise 106,835,000 115,038,600 99,930,253 96,103,268 60,846,663 478,753,784
Interceptor Sewer System 97,000,000 103,721,000 88,616,000 82,404,000 52,640,000 424,381,000
PW-ISS 97,000,000 103,721,000 88,616,000 82,404,000 52,640,000 424,381,000
Chattanooga WW Consolidation Study 500,000 - - - - 500,000
Citico Pump Station Improvements 4,000,000 - - - - 4,000,000
Contingency - Miscellaneous Plans and Studies 206,000 212,000 218,000 560,000 1,196,000
Contingency MBWWTP Improvements - General Purpose 2,000,000 2,060,000 3,180,000 3,270,000 5,600,000 16,110,000
E2I2 SSO Abatement Program 60,000,000 10,300,000 - - - 70,300,000
Focused SSES and Rehab - Phase II 8,000,000 8,240,000 8,480,000 8,720,000 11,200,000 44,640,000
ISS Capacity Improvements - 3,180,000 3,270,000 8,960,000 15,410,000
MBWWTP EQ Blower Replacement 750,000 - - - - 750,000
MBWWTP Oxygen Plant Replacement 12,000,000 10,300,000 - - - 22,300,000
MBWWTP Solids Process Optimization Implementation - Phase 4 (Dige 20,000,000 20,600,000 21,730,000 19,620,000 - 81,950,000
MBWWTP Wet Weather Treatment Upgrade 20,600,000 26,500,000 38,150,000 - 85,250,000
Program Management For Consent Decree 3,400,000 3,502,000 3,604,000 3,706,000 3,920,000 18,132,000
Pump Station Generator 3 750,000 - - - - 750,000
Sanitary Sewers for Annexed Areas 4,223,000 3,710,000 - - 7,933,000
Smart Sewer Implementation 1,030,000 1,060,000 1,090,000 1,680,000 4,860,000
Wilcox Blvd Chronic SSO 515,000 2,650,000 - - 3,165,000
Winterview Pump Station and Basin Improvements 500,000 - - - - 500,000
MBWWTP New Thickener Pumps 400,000 - - - - 400,000
E2I2 SSO Abatement Program - East Ridge (20,000,000) (20,000,000)
E2I2 SSO Abatement Program - Lee Hwy (5,000,000) (5,000,000)
E2I2 SSO Abatement Program - Red Bank (5,000,000) (5,000,000)
Tiftonia Pump Station #3 Safety Upgrade 500,000 2,575,000 - - - 3,075,000
Tiftonia Pump Station #1 Safety Upgrade 5,150,000 - - - 5,150,000
South Chick Pump Station Improvements 1,500,000 6,180,000 8,480,000 - - 16,160,000
Riverview Park/CGCC Chronic SSO Elimination Project 500,000 - - - - 500,000
Pump Station Improvements - Hixson 2 (Bundle) 6,500,000 - - - - 6,500,000
Pump Station Improvements - Boy Scout Rd - 530,000 3,815,000 - 4,345,000
Pump Station Improvements - Big Ridge #12 and others - - - 16,800,000 16,800,000
Pump Station Improvements - Big Ridge #1 - - 545,000 3,920,000 4,465,000
19th St Pump Station 515,000 2,650,000 - - 3,165,000
MBWWTP Vehicle Purchase and Maintainer 1,350,000 - - - - 1,350,000
MBWWTP North Recycle Pump Station 1,000,000 7,210,000 - - - 8,210,000
MBWWTP Electrical Improvements (S&C Switches) 500,000 500,000
Implementation of CD Green Infra Projects in the CSS 500,000 - - - - 500,000
Hixson Pump Station #3 Safety Upgrades 515,000 2,650,000 - - 3,165,000
Highland Park Pump Station Improvements 2,000,000 - - - - 2,000,000
Friars Branch Pump Station Grinders 350,000 - - - - 350,000
Water Quality 9,835,000 11,317,600 11,314,253 13,699,268 8,206,663 54,372,784
Public Works - Water Quality 9,835,000 11,317,600 11,314,253 13,699,268 8,206,663 54,372,784
Central Avenue Ext Separation Proj. 2,060,000 2,183,600 4,120,000 1,030,000 9,393,600
2013 Briarwood Circle 1,000,000 1,030,000 1,060,900 1,092,727 1,125,509 5,309,136
3469 Brainerd Rd. 100,000 100,000 100,000
100,000 400,000
Automated Flood Warning System 350,000 360,500 371,315 382,454 393,928 1,858,197
Dartmouth/Five Points Watershed SIP 2,750,000 - 2,060,000 2,183,600 - 6,993,600
C - 29
City of Chattanooga
FY23-27 Capital Budget Summary by Project
Department Proposed FY23 Proposed FY24 Proposed FY25 Proposed FY26 Proposed FY27 5 Year Total
Drainage Projects 500,000 - 500,000 500,000 500,000 2,000,000
Elder Mountain Road 890,000 2,000,000 2,890,000
Floodplain Modeling 200,000 250,000 312,500 375,000 450,000 1,587,500
Green Infrastructure SOV Bank 100,000 125,000 162,500 227,500 615,000
Heavy Equipment 570,000 587,100 604,713 622,854 641,540 3,026,207
Natural Resource Storage - Watkins Street 75,000 - - - - 75,000
On-Call Landscape Design 250,000 325,000 422,500 549,250 1,546,750
Provence Park 3332 Provence Street 250,000 - - - - 250,000
Pumpkin Pie Lane (Pumpkin Pie @ West 57th) 50,000 - - 850,000 - 900,000
Stormwater Asset Management Plan 1,000,000 1,545,000 1,030,000 - - 3,575,000
Stream Buffer Conservation 200,000 250,000 325,000 390,000 487,500 1,652,500
TMDL & Land Management 500,000 550,000 605,000 665,500 732,050 3,052,550
TN Riverbank Stabilization Project 1,000,000 1,030,000 1,060,900 1,092,727 1,125,509 5,309,136
USACE/FEMA Floodplain Culvert Replacement Projects 250,000 262,500 275,325 289,406 303,877 1,381,108
Wisdom Street - Upper Citico Culvert 630,000 - - - 630,000
Stream Restoration/Various Sites 250,000 312,500 375,000 450,000 540,000 1,927,500
Grand Total 202,937,591 196,777,600 190,440,253 189,713,268 129,106,663 908,975,375
C - 30
RESOLUTION NO. ___________
A RESOLUTION EXPRESSING THE INT ENT OF THE CITY OF CHATTANOOGA T O
ISSUE BONDS IN THE AGGREGATE AMOUNT NOT TO EXCEED THIRTY MILLIO N
FIVE HUNDRED THOUSAND DOLLARS ($30,500,000) FOR THE PURPOSE OF PAYING
ALL OR A PORTION OF THE COSTS OF THE FOLLOWING: POLICE SERVICE
RENOVATION, MAIN STREET EXTENSION, APPARATUS REPLACEMENT PLAN,
CAPITAL MAINTENANCE AND REPAIR PROJECTS, REGIONAL TRAINING CENT ER,
STATION #15 REPLACEMENT, CITY BUILDINGS & COMMUNITY CENTERS MAJ OR
SYSTEM REPLACEMENT, CITY FACILITIES CAPITAL IMPROVEMENTS AND/OR
CAMPUS CONSOLIDATION, LAKE RESORT SLOPE REPAIR, LAW ENFORCEMENT
TRAINING CENTER, PAVEMENT MANAGEM ENT, AND STANDIFER GAP BRIDGE
REPLACEMENT
________________________________________________
WHEREAS, Sections 9-21-101 to 9-21-1017, both inclusive, Tenne ssee Code Annotated,
authorize municipalities in the State of Tennessee to issue bonds for public works projects; and
WHEREAS, Section 9-21-205 of said Code provides that before bo nds may be issued the
governing body of the municipality shall adopt a resolution kno wn as the “INITIAL
RESOLUTION” determining to issue such bonds:
NOW, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA,
TENNESSEE, That pursuant to the p rovisions of Tennessee Code An notated, referred to in the
preamble hereof, there be issued and sold Bonds in the aggregat e amount not to exceed Thirty
Million Five Hundred Thousand Dollars ($30,500,000) of the City of Chattanooga, Tennessee
for the purpose of paying all or a portion of the costs of City Facilities Capital Improvements
and/or Campus Consolidation, Police Service Renovation, Main St reet Extension, Apparatus
Replacement Plan, Capital Maintenance and Repair Projects, Regi onal Training Center, Station
#15 Replacement, City Buildings & Community Centers Major Syste m Replacement, City
Facilities Capital Improvements and/or Campus Consolidation, La ke Resort Slope Repair, Law
C - 31
DRAFT
Enforcement Training Center, Pavement Management, and Standifer Gap Bridge Replacement.
Said bonds shall bear interest at such rate or rates not to exc eed the rate or rates prescribed by
law payable semiannually and shall be payable exclusively from taxes and shall be issued at the
time or times and bear date or dates and mature at such times a s may hereafter be determined by
resolution.
BE IT FURTHER RESOLVED, That this resolution also contemplates and authorizes the
use of proceeds of any bonds hereaf ter issued by the City for t he purpose described herein to be
used to reimburse the City for any costs incurred on or after (a date sixty (60) days prior to
adoption of this resolution) and, in addition, de minimis amoun ts incurred before that date and
amounts not exceeding twenty percent percent (20%) of the adjus ted issue price of the bonds
which are expended for prelimin ary expenditures, within the mea ning of Treasury Regulation
Section 1.150-2, all of which costs are incurred or to be incur red with respect to projects referred
to in this resolution.
ADOPTED:____________________, 2022
C - 32
DRAFT