_01212026-516
City of Hendersonville · Sumner County · meeting of Jan 21, 2026 · Minutes
Open the original document More from City of Hendersonville
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
CAPTIAL PROJECTS COMMITTEE MEETING, January 21, 2026
MAIN MEETING ROOM, 5:00 pm
Present : Chairman Eddie Roberson , Vice -Chairman Bob Garza, Alderman Terri Goodwin
Absent : Alderman Mark Skidmore , Alderman Jeffrey Sasse
Others Present : Alderman Rachel Collins , Alderman Mark Evans, Alderman Mark Burdorf, Chief of
Operations (COO) Jessie Eckenroth , Interim Public Works Director Stephen Winzenread , Planning
Director Keith Free, Assistant Planning Director Timothy Whitten, RK&K Representative Stuart
Samberg
Call to order at 5:00 pm
Acceptance of the Aeenda
Motion : Alderman Terri Goodwin
Second : Alderman Bob Garza
Vote: Approved Unanimously
Minutes
A. Motion to Approve August 11 , 2025 , Capital Project Committee meeting minutes
Motion : Alderman Terri Goodwin
Second: Alderman Bob Garza
Vote : Approved unanimously
Citizens Comments
None
GNRC Update - Submitted Project, Status and Fundine
Interim Public Works Director Stephen Winzenread reported that all projects listed on the 2025
Transportation Cap ital Improvement Plan have been submitted to GNRC for consideration . They
are expecting a draft of the regional transportation plan to be released in March. Mr. Winzenread
also reported there has been a recent update to the estimate on the Drakes Creek/Stop 30 project.
As a result , an amendment for funding on this project will be submitted .
Action Items
1. Drakes Creek Traffic Study- Summary of study from RK&K with Q&A
Interim Public Works Director Stephen Winzenred reported that RK&K was asked to prepare
a study on the project . RK&K Representative Stuart Samberg was present to present the
study findings . Mr. Samberg went over three alternative options they considered:
• Alternative #1 - Coordinated Signals
• Alternative #2 -Anderson Road/Herman Harr ison Drive roundabout
• Alternative #3-Avant Lane/Countryside Drive/Anderson Road roundabout
RK&K recommended Alternative #3 as the preferred option . RK&K answered additional
question regarding the alternatives. Interim Public Works Director Stephen Winzenread
asked the committee guidance on moving forward with design . Alderman Roberson
proposed a Resolution of Intent to proceed be added as an action item for the next meeting
with the desire that all committee members be present for further discussion .
2. Stop 30 Project - Discussion/decision for the next steps
Interim Public Works Director Stephen Winzenread reported that recent work on Stop 30
included replacing several culverts , repaving , striping, and replacing several road signs .
Three design options for Stop 30 were presented which included:
a. Preliminary Concept- Concept has been develop and could be used as a guide for
future developments .
• No additional cost
b. Basic Road Design Services (10% Line a Grade Design)
• Estimate design and service cost $128,211
• Could be used as basis of design for future developments along corridor
c. Full Design - Bid Ready Documents
• Estimated design cost $715 ,800
• Estimated construction cost $19.9 million
Interim Public Works Director Stephen Winzenread asked for the committee 's approval to
move forward with one of the options . After further discussion Alderman Roberson moved
for a motion to proceed forward with the Basic Road Design Services option .
Motion: Alderman Bob Garza
Second: Alderman Terri Goodwin
Vote: Approved unanimously
Discussion Items
3. Transportat ion Capital Improvement Plan Status Update
Status provided on the 36 projects on the City 's Transportation Capital Improvement Plan.
4. West Main Access Management Plan
Discussion of the concept of the project, which includes installation of landscaped center
medians to reduce the number of conflict points in the road.
5. Landscaping and Signage (Planning)
Project concept discussed which includes a project to install a section of landscaped
median on Main Street between New Shackle Island Road and Imperial Boulevard . There
are also plans to install a gateway sign near the west City Limit along Main Street . Median
concept and sign concept ~were presented. A motion to proceed with both the median and
sign project was made by Alderman Bob Garza .
Motion: Bob Garza
Second : Terri Goodwin
Vote : Approved unanimously
6. LED Conversion Update
A contract is in place and the contractor is anticipated to soon begin work . Project is
expected to be complete by September 2026 .
7. Drakes Creek/Stop 30 Intersection
Construction cost estimate of $9.2 million has been revised to $10.8 million .
Communication with GNRC to address the funding difference has already begun with
expectation of an amendment.
8. Cherokee Culvert Replacement
Project will account for proposed widening that is part of Project #13 (Cherokee Road
School Zone) on the Transportation Capital Improvement Plan . Current status is in right -of
way (Property Acquisition) with an estimated completion in 2028 .
9. Saundersville (LIC) Exit 8
Project is in the right-of-way phase with design completion and bid letting date in 2030 .
10. Signal Synchronization Phase II
TDOT issued a notice to proceed to construction on 12/23/25. The consultant is currently
updating construction documents and plans while also preparing the bid documentation.
Estimated completion date is for the 3rd quarter of 2026.
11. West Main ADA
Project received notice to proceed to right of way, and is now the in Right-of-Way
Acquisition phase with an estimated completion in 2028 .
12. Imperial/Rockland Traffic Study
Traffic data collection, intersection analysis, and land survey has begun on the project .
13. Saundersville Road at Dayflower
Project is the design phase.
14. lnnsbrooke and Saundersville Rd Section Improvements
The Project is in the traffic analysis and design phases .
15. Other Business
None
Adjournment
Motion to Adjourn
Motion: Alderman Terri Goodwin
Second: Alderman Bob Garza
Vote: Approved Unanimously
Adjourned : 6·
(\
Eddie Roberson , Chairman
Source: City of Hendersonville website. First collected Oct 18, 2026.