City of Chesapeake · Chesapeake City County · meeting of Jun 22, 2026 · Minutes

Open the original document More from City of Chesapeake

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Chesapeake StormwaterCommitteeMeeting June22,2026 ChesapeakeCityHall,HumanResourcesTrainingRoom 1.CalltoOrder:Themeetingwascalledtoorderat6:02PMwithnoobjection (Waters) 2._‘RollCall:RollwascalledbyCaseyMagruder. CommitteeMembersinAttendance: BrennenWaters(Chair) MichaelBattle RichardBunton MiltonJohnston MichaelPoyner VicNicholls MarkiellaMoore AudreyDoan(Alternate) CaseyMagruder(PWEnvironmentalProgramManager) JamesLomogda(OperationsAdministrator) ReynaldoHernandez(PWStormwaterEngineerIV) AbsentCommitteeMembers: KevinWalker(Co-Chair) — Excused TheresaHarris — Excused RyanShrader(Alternate) — Excused MatthewMorse(CAO) — Unexcused OtherCityStaffinAttendance: TonyaSnow(OfficeSpecialist) - minutes CitizensinAttendance: N/A 3.MeetingMinutes Therewasaquorum,andtheApril2026meetingminuteswereapproved(Therewasno May2026meeting). Waters/Bunton/Battle 4,CitizenComments —N/A 5. Operations Update / OPS Report James Lomogda (Operations Administrator) gave the Operations Update for the month of April 2026 stating that there were three hundred and thirty-two (332) work orders received, three hundred and twenty-one (321) field completed, and one hundred and twelve (112) still open. The Field Completed Work Orders Service Goal Days Chart James showed was all green (some of the usual categories such as cave-ins were light green but still green). James then showed the CCTV List; sixteen (16) Work Orders including jobs from 829 Canal Drive to 400-408 Brnadon Way. The list also included a corrective maintenance work order for Shea Drive (Contractual Services slip-lined a pipe). James next showed before and after project pictures: 1. 1904 Foxwood (off Shillelagh) “+ James: This job was for rear ditch work/drainage easement. Inmate crews and OPS crews did a clear and clean of the ditch. Flooding was not noted but water had been slowly draining for sure. 2. 5013 John Street (Suffolk Border off Wise Street) ** James: This job was for rear ditch work. An excavator was used for the bigger blockages — culverts ultimately go under | 664. Mr. Poyner: What is the size of the culverts? James: Triples; 36x72...48x72.. Rey: At least 36x72. James: Bridges crews inspect these types ofjobs as well. Mr. Poyner: I’m used to seeing round culverts, what kind of culverts are those? James: Yes, these types are specific to going under highways, etc. 7 > “e % >,“ ~~ >,~~ °,“Ww Next, James gave the Operations Update for the month of May 2026 stating that three hundred and forty-three (343) Work Orders were received, three hundred and twenty-five (325) field completed, and one hundred forty-eight (148) still open. The Service Goal Days Chart showed all green except for Vegetation Control and Tree Trimming. The Bucket Truck being down contributed to this. James then showed the CCTV List including jobs from Checkerspot Way to Foxgrove Lane and Glenview Road. This list included twenty-two (22) Work Orders; ten (10) of which were for cave-ins. James next showed before and after project pictures: Stormwater Committee Meeting 6/22/2026 1.1211DominionLakesCourt(Cave-in) James:Thehomeownerputinacomplaint.CrewsremovedaPVCpipe(a poolpipe)thatwasinstalledunderasidewalk. Casey:Allofthatdiatomaceousearthwasprobablybackwashedrightfrom thepoolfilter. James:Wetoldthehomeownerwecutthepopeattheright-of-wayline andcappedit.Theycouldnotatthatpointdraintheirpoolintoourpipe. Jamesshowedafterpicturesofthepipecrewsrepaireddepictinga Fergusonwrapproductthathadaverystickycoatingwhichhelpedto ensureasecureseal. Mr.Bunton/MiltonJohnston:(Referringtothepipethatwasinstalledunder thesidewalk)That’salotofworkinsteadofjustlayingyourhosedoutinthe yard... Audrey:Youdidn’tfinethem? James:Thehomeownersweretherefortwo(2)years;Thiswasdoneabout eight(8)yearsago. 2.409WoodardsFordRoadOff-RoadSideDitch) James:SideDitchhadabuildupofleaves,etc.Fourtosixinchesof sedimentwasremoved;dumptruckswereusedtohauldebrisaway. Mr.Poyner:(Referringtoprojectpicture):Arethoserocksontopofthe debrispile? James:No,thoseareleaves. James:Trifoldswerelefttoletpeopleknowtheycan’tblowtheirleavesinto streets/ditches. Casey:Ourcrewshavealsodonealotofeducationoutthere. 3.EdgertonRoad ?, “eoJames:Citizencalledinregardingpoordrainagealongroadway;no drainagestructuresonEdgerton. JamesshowedamapStatingthatthegreenlinesrepresentedsewer,the bluelinesrepresentedwater,andthepurpleonesrepresentedstormwater infrastructure. James:OPScrewshadsurveyedthatareatoremovegrassthatwas growingthroughthejointspaces,etc.Weedkillwasputdownandyards wereedgedwherefloodingwashappening. James:Peoplewerealsoaskedtobeawareofstreetsweepingschedules andnottoparkstreetsideonthosedays. James:We’vetalkedwithReyaboutaddingtotheunfundedlistfor drainageimprovements. Mr.Poyner:(ReferringtotheprojectphotosJamesshowed):So,wehave ourowndronefortakingpictures? James/Rey:No,GIS. Markiella:Doyougetverymanyservicerequestsforthatarea? StormwaterCommitteeMeeting 6/22/2026 James: Yes, and survey shots are important in helping us. Mr. Poyner: When you do work like that and you come across a road that needs repair, do you put in a request of ignore it? James: If someone complains, Contractual Services will take a look about resurfacing. Repaving roads are based on a set rating system. James: ISG is a service we used years ago we used years ago who would go along roads and document cracks on roads, etc. and rate from most important. Rey: Also has to do with ongoing projects. James: Yeah, for example, Bainbridge Road has an HRSD project which is about 50% done, so we wouldn't go out there while that’s going on. Brennen thanked James for his report. 6. Engineering Update Rey started by following up on Sam’s presentation from the last Stormwater Committee meeting (April 2026), showing a ranked list of unfunded projects depicting Sunlight Drive and Country Road under Newly Added Projects. “+ Rey: The list is eight pages long and is broken down into categories such as source of project (CSR, etc.), impacts of flooding, how often flooding occurs, impacts on residents, impacts on businesses, etc. Categories also included water quality benefits, population benefitted, etc. Rey showed a Stormwater Projects Description of Ranking Scale with a 0-to-5-point scale, 5 indicating living / finished space flooded/ arterial and collector streets flooded above the curb and0 indicating no flooding at all. “* Rey: The feasibility category is broken down into five subcategories: . No displacement of residences /businesses required . Access the site without acquisition ofproperty rights . Strong public support . Acquire a permit/ mitigation . Correct the problem The point system was discussed, Re: Relative Project Costs: § points for less than $200,000 3 points for $200,000 to $499,000 2 points for $500,000 to 1,000,000 1 point for over $1,000,000 Stormwater Committee Meeting 6/22/2026 >, “~~Rey:Iftwo(2)projectsaretiedinpoints,thenavailableprogramfundingcould determineoneprojectmovingforwardaheadofanotherproject. Next,Reyshowedthelistoftoptenprojects. “ ,“ >>,* ,“ ?, O >, Ye %O Oe >,~° >,~° >,“~e o,~e ¢,+e \2~~ °,~e 0,“° ¢, ¢, ~~ OO Mr.Poyner:Doyouupdatethislisteveryyear? Rey:Yes,otherprojectsgoingoninfluencethis. Mr.Poyner:Howmanypeopleupdateit? Rey:JustourStormwatergroup. Mr.Poyner:That’salotofwork. Rey:Yeah,Oliveisinvolvedwiththis.She’sveryknowledgeable. Milton:Isitthenumberofhousesorthenumberofpeople? Rey:Population. Markiella:So,youentertheproject,doyouthenaddthepointsuporisitdone asagroup? Rey:Agroup.Wediscussallprojectshappening. Markiella:Howdowatershedprojectsgetonthelistordothey? Rey:Theydo.ReyshowedthelistagainpointingoutsomethathadanMD abbreviation(MasterDrainage). Markiella:So,MDmeansitstemmedfromawatershedstudy? Rey:Basically,yes. MarkiellaaskedReyifprojectsonlistwereinpriorityorder? Rey:Forthemostpart;therehavebeenupdatesonsome. Mr.Poyner:They'llbelockedinbyAugust. BrennenthankedReyforhisreport. 7.EnvironmentalReport CaseyMagrudergavetheEnvironmentalReportforAprilandMay2026,sayingthat Aprilhadfifteen(15)complaints;spills,pooldischargesandtherewereonehundred thirty-eight(138)BMPinspections.ForMay,therewerefifteen(15)CSRs(alotfrom oilleaksincars);alsohadtheYadkinRoadtrainincidentwithaSpiveytruckgetting obliterated. ,“~ “~ o+,% o,“~e o,“~e +,~~ O~~ Soy% Milton:Didthedriversurvive? Casey:Theyneverfollowedup,butitdidn’tlookgood. Brennen:Wasitduetoaconstructionproject? Casey:No. Audrey:Isthereagate? Casey:No,theguyprobablyjusthadnoideahowfastitwasgoing. Mr.Poyner:Whatdoyoudoaboutoilleaks? Casey:Tellpeopletofixthecar,putkittylitterdown,callforittobetowedifit isinoperable. StormwaterCommitteeMeeting 6/22/2026 Casey gave further information on the report for May 2026. Casey: There were one hundred sixty-seven (167) BMP inspections in May. Casey: We had a Facebook post about algae on ponds in May and how to get a handle on it. Casey: Dave Mergen’s group is down three people. In April, there were one hundred ninety-six (196) single family home sites open and three hundred thirty- nine (339) inspections. One hundred thirty-three (133) commercial sites open and two hundred ninety (290) inspections. 48 Hour Rain Events — four hundred thirty- two (432). Casey: They also issued five (5) Stop Work Orders in April (which is a lot). Milton: All new construction? Casey: Yes. Casey: For May, there were one hundred ninety-seven (197) single family home sites open; one hundred thirty-nine (139) commercial sites open and two hundred eighty-four (284) inspections. 48 Hour Rain Events — four hundred forty-two (442). Casey: They also issued Stop Work Order in May. Mr. Poyner: Could one hundred fifty (150) inspections really have been one hundred twenty (120) inspections with thirty (30) follow-ups? Casey: Yes. We have to log every time we go out. Milton: RE: Annual Report discussed at previous meeting/s: Is everything wrapped with the EPA now? Casey: | sent my comments. The audit was in December, the report came in April. Annual reports are due October 1% every year. Markiella: Which Facebook page had the post about algae? Casey: City of Chesapeake. ?~ ?,~o ?,~~ },~ Brennen thanked Casey for her report. 8. Unfinished / New Business RE: Unfinished Business Brennen: With Mr. Morse’sabsence tonight, there is no update for the appeals process. Markiella to James: How many bucket trucks are there? James: For tree trimming — one (1), Expressway has one (1), Bridges has one (1), Operations has three (3), so six all together. Markiella: Do other people ask to borrow ours? James: Rarely. Markiella: Are there plans to add one more bucket truck for Stormwater? James: A second truck for tree trimming could come out of either Enterprise or Operational Budget. Brennen: What is the estimate on one of those trucks? James: Similar to forty feet? $250,000 to $300,000. Stormwater Committee Meeting 6/22/2026 **Markiella:Projectsfundedbyabandonedprojects — canyouletusknowwhich projectshavebeenabandoned? “*Markiella:HowmuchistheStormwaterBudget? RE:NewBusiness Markiella(toCommitteemembers):Arey'allawarethatthereisaHazard MitigationPlan? Audrey:Yes,inNorfolk,it’sbrokendownintodivisions. Markiella:Mainpointistoleteveryoneknow.Thehighesthazardthisplan istryingtomitigateisflooding,so|thinkthatdirectlycorrelateswithus. Markiella:Repetitivefloodareas. Mr.Bunton:ClearingCooper’sDitchalongwithHillwell(ACOE) — arethere anyupdates? Casey:|thinkit’sintheprocessnow. Audrey:ItwasdesignedwhennewdevelopmentscameinoffWhitehurst Roadtwenty-fiveyearsago. ReytoMarkiella:I’mnotinvolvedwithit,butI'llseewhat|canfind — might bePhaseIl... Mr.Bunton:Where|work(atthehospital),wehaveourownHazard MitigationPlan. Markiella:What’snumberone? Mr.Bunton:Flooding. Themeetingwasadjournedat7:04PM. *PleasenotethatperArticleViloftheChesapeakeStormwaterCommittee BylawsadoptedJune26,2023,therewasNOregularmeetingscheduledin May2026. ThenextmeetingisscheduledforJuly27,2026. "Minutesapprovedbythe cme N StormwaterCommitteeMeeting 6/22/2026

Source: City of Chesapeake website. First collected Oct 26, 2026.