City Council & School Board Joint Committee — Agenda Packet
City of Lynchburg · Lynchburg City County · City Council & School Board Joint Committee · meeting of Mar 12, 2025 · Agenda packets
Open the original document More from City of Lynchburg
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
CITY COUNCIL & SCHOOL BOARD
JOINT COMMITTEE
Wednesday, March 12, 2025 | 5:00 PM
I.T. Conference Center
3550 Young Place
Lynchburg, VA 24501
AGENDA
I. Welcome & Introductions Councilmember Chris Faraldi, Co-Chair
School Board Member Dr. Martin Day, Co-Chair
I.1. Invocation
I.2. Opening comments from Co-chairs
I.3. Review of the notes from the February 27th meeting
II. General Business
II.4. Overview of building conditions, major maintenance needs, and priorities
II.5. Process, timeline, and data requirements for mapping student locations by
school zone
II.6. Next Steps
III. Roll Call
IV. Next Regular Meeting
IV.7. The next joint schools/council subcommittee meeting is Thursday, March 27,
2025 at 5:00 p.m.
Page 1 of 23
Elementary School Capacities,
Enrollments and Utilization
This document summarizes some information about our elementary schools and their
utilization available from the School Board’s recent facilities planning and other sources.
The following table shows the elementary school capacity estimates used by MGT in its
planning and recommendations, as well as the values which appeared in the city’s 2006 Annual
Comprehensive Financial Report, Table 27 (page 103).
We have no information about the numbers from 2006 other than what appeared in the
financial report itself, but there are many considerations and possible explanations of the
discrepancies.
•It is not clear whether the 2006 numbers refer to total occupancy, adults included, or just
students as the MGT numbers do.
•Sometimes classrooms are converted to/from other uses over the years.
•The way classrooms are utilized has certainly changed over the years. This is illustrated
vividly by comparing the photographs on pages 13 and 14 of Dominion 7’s Report of March
22, 2022! So the number of students that might have been served in a room years ago is
different from today.
•We receive supplemental funding from the state to keep our class sizes low. MGT’s numbers
take these class size limitations into account.
•Today we provide more services to students than in 2006, things like student counseling,
assistance with behavior management, and special education. These sometimes use a
space that might otherwise be a classroom.
Elementary School 2006 Table 27 MGT and Dominion 7
Bedford Hills 625 547
Dearington 235 250
Heritage 550 499
Linkhorne 725 528
P . Munroe 506 434
Perrymont 441 427
R.S. Payne 800 625
Sandusky 475 386
Shefield 475 480
T.C. Miller 440 276
W.M. Bass 315 250
Page 2 of 23
•The capacity estimates used by MGT were developed by Dominion 7 as part of their review
of our facilities and were based on current VDOE Guidelines for Public School Facilities,
dated 2021.
The Dominion 7 and MGT numbers are more realistic for planning purposes than those from
almost 20 years ago. Even so, some principals have commented that they don’t know how
they would accommodate the number of students indicated by the MGT numbers. In other
words the MGT estimates may still be higher than practical. And there is yet another
consideration in using these numbers, as will be noted below.
The following graph shows the history of our Fall K-5 enrollments, as reported by the VDOE, as
well as various projections for future enrollments (again K-5).
The History and Weldon-Cooper projections are up-to-date while the MGT and Cropper-GIS
projections are older, so of course don’t match the actual data from 2023 onward. The
horizontal dotted line marks the level of 3762 students, which is 80% of our estimated
elementary school capacity (4702). The advice of MGT was that enrollment should be between
80% and 94% of capacity. By these estimates we have been well below 80% for several
years. Currently we are at about 72%. To bring our utilization up to 80% we would need to
reduce elementary student capacity by more than 450 seats.
This all presumes the appropriateness of the capacity estimates. Another caveat should be
borne in mind. Several elementary school classrooms (10) are currently being used for pre-K
classes. So those rooms are not vacant but the students using them are not counted in the
K-5 enrollments above.
Finally, there is a set of graphical “heat map” density analyses for the students attending each
of the elementary schools (as of 2021-22) in the Cropper/GIS Demographics Report of April,
2022, starting on page 48.
M. Day, March 7, 2025
K-5
Page 3 of 23
Lynchburg City Council and Lynchburg City Schools - 5:00 (IT Center) Ad Hoc Committee (Thursday,
February 27, 2025)
Generated by Tina P Day on Monday, March 3, 2025
Members present
Dr. Day, Mrs. Lowery, Mr. Conner, Mr. Fraldi, Mr. Wilder, Mr. Misjuns
Meeting called to order at 5:00 PM
A. CALL TO ORDER
As Co-Chair, Mr. Fraldi called the first meeting of the Ad Hoc Council/School committee meeting to order.
Before agenda is approved Dr. Day from LCS Board passed out an amended agenda.
First order of business was to decide how the procedural issue of establishing a chair to open and
conduct the meetings and whether this committee would use Council Rules or Roberts Rule
Discussion was held on these two subjects and the opinion of each committee members were asked to
share their thoughts.
After much discussion it was decided that Dr. Day would be the co-chair that presides over the meetings
and would not have a vote unless it was needed to break a tie. It was further decided that the
committee would operate under Robert's Rules of Order with the addition of one special rule: members
are not allowed to abstain from votes unless they have a genuine conflict of interest or motion is
adopted by consensus.
Motion was made by Mr. Misjuns and 2nd by Mr. Conner
Votes:
Yes: Mr. Conner, Mrs. Lowery, Dr. Day, Mr. Wilder and Mr. Misjuns
No: Mr. Fradli
Motion carries 5 to 1
Motion was made by Mr. Misjuns to adopt the amended agenda Dr. Day presented and 2nd by Mr.
Conners
Votes:
Yes: Mrs. Lowery, Mr. Conner, Dr. Day, Mr. Wilder, Mr. Misjuns
No: Mr. Fraldi
Motion carries 5 to 1
B. GENERAL BUSINESS
Discussion, Information: 1. Review meeting time, schedule, and location Discussion was held on meeting
dates and times. There are some conflicts but Mrs. Day, board clerk for LCS will look at rescheduling
things around so the board members will be able to make the scheduled dates, time and location.
Page 4 of 23
The next meeting will be held on Wednesday, March 12, 2025, at 5:00 at the IT Conference Center
Dr. Day would like to open the discussion for the following topics
• Identifying short term action to be taken
• Discuss long term goals
• Direct staff research
• Establish future meeting schedule
School Board and City Council indicated they would like to look at the following items:
• Close to home zoning
• Schools opening this Fall
• Alternative Education
• Enrollment, school capacities, student location
• The need for LCS plans to be consistent with the city's CIP commitment
• The possibility of additional state funding to support school construction
Suggestions were made about looking for outside funding to support the 68,350,00 under the proposed
FY 26-30 CIP , such as SCAP for school construction.
Overview of Building needs - LCS staff will bring a summary presentation to the next meeting.
City staff offered to provide guidance on how to assess enrollment and student locations.
Committee members asked that overview of building conditions and major maintenance needs be on
the next agenda with Dr. Copeland adding that staff recommendations for the use of CIP funding be
included in the presentation as well.
C. INFORMATION
Next joint meeting will be on Wednesday, March 12, 2025 @ 5:00 pm (IT Conference Center, Young
Place)
Thursday, March 27, 2025
Thursday, April 10, 2025
Tuesday, April 29, 2025, Full Board and Council meeting (location/time TBD)
D. ADJOURNMENT
Meeting was adjourned at 6:45 pm
Page 5 of 23
Every Child, By Name and By Need, to Graduation and Beyond
SCHOOL FACILITY
DEFERRED MAINTENANCE
Immediate and Next 5 Year Needs
City Council and School Board Joint T ask Force
March 12, 2025
1
Page 6 of 23
INTRODUCTION & DISCUSSION OF
APPROACH
● In 2022, Lynchburg City School contracted with Dominion 7 to provide an assessment of the building
conditions of our traditional PreK-12 schools. Included in the deliverables was an outline of all
architectural, mechanical, electrical, plumbing, and civil repairs that are needed to the existing
infrastructure.
○ Identified a large number of needed projects due to long-term deferred maintenance
○ Did not include recommendations for significant changes to the way systems operate
○ For instance, the recommendation did not identify changes to the function of HVAC system, but
identified the components that need to be replaced, as well as the timing they are needed.
○ Also, did not include the alternative and regional schools
● This deliverable provided a 20-year time frame for needed improvements, which has been the basis
for the large majority of capital improvement plan submissions
Page 7 of 23
INTRODUCTION & DISCUSSION OF
APPROACH
● This presentation provides an outline of the improvements identified at each school, with
recommended timing and an estimated cost.
○ Because these figures were generated in FY 2022, costs over the term of the coming capital
plan are likely to be higher than those in the report. Additionally, design costs were not
factored into those cost. For that reason, we have escalated the identified costs by 25%
○ Additionally, if an improvement was already completed prior to this exercise, we removed
that cost from the estimate. Example: Sheffield Elementary Chiller and Boiler replacement
has already been completed and is not included in these costs
● We have also included other division priorities that were not included in this report, though many
were included as cash projects in the City Manager’s proposed CIP .
Page 8 of 23
PROJECT TYPES
Projects are identified by type. Each school’s needs are different, but many have similar types needs.
● Architecture: Covers projects related to building structures, facades, roofing, flooring, and interior
and exterior finishes to maintain or improve school facilities.
● Civil: Includes site-related improvements such as parking lots, sidewalks, and stormwater
management to enhance safety and accessibility.
● Plumbing: Encompasses upgrades and maintenance of water supply, drainage, sewer systems, and
restroom facilities to ensure compliance with health and safety standards.
● Mechanical: Focuses on HVAC systems, boilers, and ventilation improvements to maintain indoor
air quality and efficient temperature controls.
● Electrical: Addresses electrical infrastructure, including lighting, power distribution and control,
and fire alarm systems to support school operations and safety. In a number of cases, electrical
efficiency would be improved through improvements identified (such as the replacement of older
lighting fixtures)
Page 9 of 23
ELEMENTARY SCHOOLS | PAGE 1
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
Bass* 0.22 0.50 1.70 0.35 2.77
Bedford Hills 0.04 0.22 2.40 1.25 0.20 1.47 5.58
Dearington** 1.22 0.10 1.30 1.10 0.16 3.88
Heritage** 0.12 1.25 1.40 0.20 2.97
Hutcherson 0.10 0.17 1.20 0.15 1.62
Linkhorne** 0.80 0.13 2.10 1.74 0.20 0.60 5.57
*does not include the Bass upgraded 4-pipe HVAC system (included in a later slide)
**does not include gyms at these schools (included in a later slide)
Page 10 of 23
ELEMENTARY SCHOOLS | PAGE 2
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
Paul Munro** 0.85 2.20 0.22 3.27
Perrymont 0.20 0.03 2.20 1.92 0.20 0.53 5.08
RS Payne 1.50 0.10 2.60 2.30 0.37 6.87
Sandusky** 0.62 0.10 0.90 1.80 0.22 1.53 5.17
Sheffield 0.03 0.77 1.75 0.10 2.65
TC Miller 0.13 0.16 1.82 1.70 0.12 3.93
T otal Elem.
Schools 4.63 1.19 16.86 20.06 2.49 4.13 49.36
**does not include gyms at these schools (included in a later slide)
Page 11 of 23
MIDDLE SCHOOLS
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
Dunbar 0.70 3.50 4.38 0.35 0.10 9.03
Linkhorne 0.03 4.80 2.30 0.18 7.31
Sandusky 0.05 2.30 1.60 3.95
T otal Middle
Schools 0.73 0.00 8.35 8.98 0.53 1.70 20.29
Page 12 of 23
HIGH SCHOOLS
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
E. C. Glass 0.75 0.13 3.10 7.10 0.35 11.43
Heritage 5.28 5.28
T otal High Schools 0.75 0.13 3.10 12.38 0.35 0.00 16.71
Page 13 of 23
NON-TRADITIONAL SCHOOLS
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
LAUREL 0.20 0.20
Fort Hill 0.20 0.20
T otal
Non-Traditional 0.00 0.00 0.00 0.00 0.00 0.40 0.40
These buildings were not assessed during the 2022 Facilities Assessment Report, but likely do have
additional concerns.
Page 14 of 23
OTHER DIVISION PRIORITIES | IN THE SCHOOL BOARD APPROVED
CIP
(those italicized are already included in the City Manager’s Proposed CIP, as stated below)
FY 26 FY 27 FY 28 FY 29 FY 30
Bass HVAC System Upgrade 4.10
Interior and Exterior Plaster Repair and Painting* 0.38 0.40 0.44 0.50
High School Athletic Improvements 1.73 0.86 0.95 0.68
Elementary Gym Additions (adding LES & SES gyms) 2.53 2.60 2.65 2.71 2.78
Middle School Athletic Field Improv. and Lighting 0.66 0.69 0.72
Elementary Playground Modernization* 0.25 0.25 0.25 0.25 0.25
Paving and Fencing* 0.22 0.22 0.23 0.24 0.25
Reserves (Maintenance and Electrical/Mechanical)* 0.50 0.50 0.50 0.50
Civic Auditorium Improvements* 0.17 0.17 0.12 0.14
Middle School CTE Improvements* 0.48 0.44 0.40 0.30
Page 15 of 23
OVERVIEW OF CURRENT NEEDS
Type Architectural Civil Mechanical Electrical Plumbing Roof T otal
Elementary 4.63 1.19 16.86 20.06 2.49 4.13 49.36
Middle 0.73 0.00 8.35 8.98 0.53 1.70 20.29
High 0.75 0.13 3.10 12.38 0.35 0.00 16.71
Non-Traditional 0.40 0.40
Other Division
Priorities 13.27 6.32 4.10 23.69
T otals 19.38 7.64 32.41 41.42 3.37 6.23 110.45
Page 16 of 23
PRIORITIES
(developed for the purposes of the joint task force meeting, but have not been reviewed by the School Board’s
Finance and Facilities Committee)
● Elementary Schools that have critical improvements and have not have major improvements (LES,
PES, PME, SES, etc.)
● Projects that will allow the division to leverage external funds (grant funds, historic tax credits,
etc.)
● Roof projects
● Student facing improvements that promote high quality experiences and safety (elementary gyms,
high school athletic improvements)
● Completion of larger projects (example, upgrades to E. C. Glass HVAC, Dunbar HVAC)
Page 17 of 23
ELEMENTARY SCHOOLS PRIORITIZED | PAGE 1
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
Bass
Bedford Hills
Dearington** 1.22 0.10 1.30 1.10 0.16 3.88
Heritage** 0.12 1.25 0.20 1.57
Hutcherson
Linkhorne** 0.80 0.13 2.10 1.74 0.20 0.60 5.57
Page 18 of 23
ELEMENTARY SCHOOLS PRIORITIZED | PAGE 2
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
Paul Munro** 0.85 2.20 0.22 3.27
Perrymont 0.20 0.03 2.20 1.92 0.20 0.53 5.08
RS Payne 1.50 0.10 2.60 2.30 0.37 6.87
Sandusky** 0.62 0.10 0.90 1.80 0.22 1.53 5.17
Sheffield
TC Miller
T otal Elem.
Schools
4.46 0.46 11.20 11.06 1.57 2.66 31.41
Page 19 of 23
MIDDLE SCHOOLS PRIORITIZED
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
Dunbar 3.50 0.35 0.10 3.95
Linkhorne 0.18 0.18
Sandusky 0.05 1.60 1.65
T otal Middle
Schools
0.00 0.00 3.55 0.00 0.53 1.70 5.78
Page 20 of 23
HIGH SCHOOLS PRIORITIZED
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
E. C. Glass 0.75 0.13 3.10 0.35 4.33
Heritage 0.00
T otal High Schools 0.75 0.13 3.10 0.00 0.35 0.00 4.33
Page 21 of 23
NON-TRADITIONAL SCHOOLS PRIORITIZED
School Architectural Civil Mechanical Electrical Plumbing Roof T otal
LAUREL 0.20 0.20
Fort Hill 0.20 0.20
T otal
Non-Traditional 0.00 0.00 0.00 0.00 0.00 0.40 0.40
Page 22 of 23
SUMMARY OF PRIORITIZED NEEDS
Type Architectural Civil Mechanical Electrical Plumbing Roof T otal
Elementary 4.46 0.46 11.20 11.06 1.57 2.66 31.41
Middle 0.00 0.00 3.55 0.00 0.53 1.70 5.78
High 0.75 0.13 3.10 0.00 0.35 0.00 4.33
Non-Traditional 0.40 0.40
Other Division
Priorities 13.27 4.22 4.10 21.59
T otals 18.48 4.81 21.95 11.06 2.45 4.76 63.51
Page 23 of 23