CITY COUNCIL WORK SESSION
Tuesday, March 11, 2025 | 4:00 PM
2nd Floor Training Room- City Hall
900 Church Street
Lynchburg, VA 24504
AGENDA
I. Welcome Larry Taylor, Mayor
II. Work Session Agenda Overview Wynter C. Benda, City Manager
III. Work Session Agenda Items Wynter C. Benda, City Manager
III.1. Capital Improvement Program (CIP) Discussion
III.2. Televising Committee Meetings
III.3. City/Schools Joint Meeting Update
IV. Business Item Briefing(s)
IV.4. Heritage Park Improvements
IV.5. Virginia Opioid Abatement Authority Grant Award
V. Roll Call
VI. Closed Session
VI.6. Consideration of a closed meeting to discuss the award of a public contract
involving the expenditure of public funds, where discussion in an open session
would adversely affect the bargaining position or negotiating strategy of the
public body, pursuant to Section 2.2-3711(A)(29) of the Code of Virginia, 1950,
as amended, the subject of the closed meeting being specific to a future contract
between the City and CertainTeed.
VI.7. Consideration of a closed meeting to consult the City Attorney, or his designee,
regarding specific legal matters requiring the provision of legal advice, pursuant
to Section 2.2-3711(A)(8) of the Code of Virginia, 1950, as amended; the subject
of the closed meeting being specific to a legal analysis of Virginia and other
relevant laws applicable to the conduct of Councilmember Martin Misjuns and
Councilmember Chris Faraldi.
Page 1 of 47
City Council
Agenda Item III.1.
Information Only
AGENDA ITEM SUMMARY
MEETING DATE PRESENTED BY
March 11, 2025 Donna Witt, Chief Financial Officer
AGENDA ITEM # III.1
Capital Improvement Program (CIP) Discussion
RECOMMENDATION
Hear responses to questions from City Council regarding the FY 2026 - FY 2030 CIP
SUMMARY
The City Capital and Schools Capital projects proposed in the FY 2026 - FY 2030 Proposed Budget
were presented at the February 25th Work Session. This work session is to respond to City Council
questions regarding the CIP.
PRIOR ACTION(S)
February 25, 2025: City Council Work Session
FISCAL IMPACT
CONTACT(S)
Donna Witt, Chief Financial Officer
ATTACHMENT(S)
1. FY 2026-2030 Capital Improvement Program 03112025
2. Library Presentation 2025
3. CIP Presentation Miller Park Pool
REVIEWED BY
Date: March 06, 2025
Donna Witt, Chief Financial Officer
Date: March 06, 2025
Page 2 of 47
Gregory Patrick, Deputy City Manager
Date: March 06, 2025
Alicia Finney, Clerk of Council
Page 3 of 47
Page 4 of 47
2
Proposed FY 2026 – 2030 CIP
Updated Schedule of Appropriations
Project Title
Appropriations
Through
06/30/2025
Budget
FY 2026
Planned
FY 2027
Planned
FY 2028
Planned
FY 2029
Planned
FY 2030
Five-Year
Estimated Net
cost
Hollins Mill Road Bridge Replacement with Bikeway Improvements 8,268,000 0 8,116,410 0 3,466,652 0 11,583,062
Lynchburg Center for Industry - Phase II 262,007 1,048,030 0 0 0 0 1,048,030
Miller Park Pool Assessment/Replacement 50,000 300,000 10,100,000 0 0 0 10,400,000
Total 8,580,007 1,348,030 18,216,410 0 3,466,652 0 23,031,092
Project Title
Appropriations
Through
06/30/2025
Budget
FY 2026
Planned
FY 2027
Planned
FY 2028
Planned
FY 2029
Planned
FY 2030
Five-Year
Estimated Net
cost
Hollins Mill Road Bridge Replacement with Bikeway Improvements 16,384,658 0 0 0 3,466,652 0 3,466,652
Lynchburg Center for Industry - Phase II 1,310,037 0 0 0 0 0 0
Miller Park Pool Assessment/Replacement 50,000 10,400,000 0 0 0 0 10,400,000
Total 17,744,695 10,400,000 0 0 3,466,652 0 13,866,652
Page 5 of 47
3
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
Buildings 30,600,150 7,562,250 1,719,500 4,067,750 3,980,625 47,930,275
Transportation 18,671,311 35,079,005 20,320,148 26,642,977 23,060,274 123,773,715
Public Transit 3,704,000 1,720,950 750,000 3,900,000 1,075,000 11,149,950
Economic Development 3,900,000 9,350,000 12,246,000 8,920,000 2,350,000 36,766,000
Parks and Recreation 3,564,000 12,340,000 2,213,000 1,961,000 3,205,000 23,283,000
Miscellaneous 1,750,000 700,000 275,000 3,155,000 3,075,000 8,955,000
Reserves 400,000 400,000 400,000 400,000 400,000 2,000,000
Total City Capital $62,589,461 $67,152,205 $37,923,648 $49,046,727 $37,145,899 $253,857,940
Five-Year
Estimated
Net Cost
Five Year Proposed Appropriations to be Financed By The City
FY 2026 FY 2027 FY 2028 FY 2029 FY 2030
Buildings 30,600,150 7,562,250 1,719,500 4,067,750 3,980,625 47,930,275
Transportation 17,623,281 26,962,595 20,320,148 26,642,977 23,060,274 114,609,275
Public Transit 3,704,000 1,720,950 750,000 3,900,000 1,075,000 11,149,950
Economic Development 3,900,000 9,350,000 12,246,000 8,920,000 2,350,000 36,766,000
Parks and Recreation 13,664,000 2,240,000 2,213,000 1,961,000 3,205,000 23,283,000
Miscellaneous 1,750,000 700,000 275,000 3,155,000 3,075,000 8,955,000
Reserves 400,000 400,000 400,000 400,000 400,000 2,000,000
Total City Capital $71,641,431 $48,935,795 $37,923,648 $49,046,727 $37,145,899 $244,693,500
Five-Year
Estimated
Net Cost
Five Year Proposed Appropriations to be Financed By The City
Proposed
Updated
Page 6 of 47
Page 7 of 47
PUBLIC LIBRARY RENOVATION
Tuesday, March 11, 2025
Page 8 of 47
LYNCHBURG LIBRARY HISTORY
Jones Memorial
Library
• 1908
• Service limited to
white residents
only
Friends of the
Lynchburg
Public Library
• 1964
• A library for all
citizens
Lynchburg
Public Library
• 1966
• Entrance view
from Main Street
• 8,000 sq. ft. space
Page 9 of 47
LYNCHBURG LIBRARY HISTORY
Pittman Plaza
• 1984
• Formerly a Sears
Department Store,
built in 1960
Jones Memorial
relocates
• 1987
• Second floor of Main
Library
• Local history focus
Page 10 of 47
LYNCHBURG PUBLIC LIBRARY TODAY
FY 2024
• 18,000 library card holders
• 150,000 library visitors
• 17,000 public computer sessions
• 325,000 materials circulated
• 400 library programs
• 10,000 people attended
library programs
• 1,430 lunches served during
Summer Food Service Program
Page 11 of 47
CURRENT FACILITY CHALLENGES
Page 12 of 47
LOOKING FORWARD
• Repair infrastructure
concerns
• Sewer Backups
• Roof Leaks
• HVAC failures causing
leaks
• Outdated electrical &
wiring
• Community meeting spaces
• Program spaces
• Public makerspace
• Computer lab upgrades
• Improved accessibility
• Upgraded shelving and
lighting
• Expanded services
Main
Library
Renovation
Photo courtesy of Tymoff & Moss Architects
Page 13 of 47
MILLER PARK POOL
ASSESSMENT/REPLACEMENT
March 11, 2024
Page 14 of 47
LYNCHBURG’S POOL HISTORY
• Lynchburg was home to 3 segregated, public pools –
Riverside and Miller Parks for white swimmers and
Jefferson Park for black swimmers.
• Pools were closed July 4, 1961.
Page 15 of 47
HISTORY
• Miller Park’s current pool opened in 1986
Page 16 of 47
EXISTING CONDITIONS
Aerial View
Page 17 of 47
INVESTMENTS, REPAIRS AND
MAINTENANCE
• 2023-24 Large leaks
• 800,000+ gallons of water
• Pool light fixture replace and sealing
• Caulk expansion joints
• Past repairs
• 2008 - Re-plaster pool
• 2008 - Pump and filter replacement
• 2021 - Slide pump replacement
• 2019-2024 - Misc repairs
• Investments
• 2024 - New deck chairs, tables and umbrellas
• 2019 - Pool cover
Page 18 of 47
REPAIR NEEDS
Page 19 of 47
REPAIR NEEDS
Page 20 of 47
MILLER PARK POOL REIMAGINED
Aerial View
Page 21 of 47
MILLER PARK POOL REIMAGINED
Page 22 of 47
City Council
Agenda Item III.3.
Information Only
AGENDA ITEM SUMMARY
MEETING DATE PRESENTED BY
March 11, 2025 Gregory Patrick, Deputy City Manager
AGENDA ITEM # III.3
City/Schools Joint Meeting Update
RECOMMENDATION
N/A
SUMMARY
The first city/schools joint committee took place on February 27th. The committee adopted
guidelines and a meeting schedule. The guidelines are attached to this agenda item. This update
will provide City Council with an overview of the guidelines and the request for a joint meeting of the
full City Council and School Board on April 29th for the Committee to present it's findings and
recommendations.
PRIOR ACTION(S)
N/A
FISCAL IMPACT
N/A
CONTACT(S)
Gregory Patrick, Deputy City Manager
ATTACHMENT(S)
1. Adopted Guidelines
REVIEWED BY
Date: March 06, 2025
Alicia Finney, Clerk of Council
Page 23 of 47
Adopted Guidelines
The purpose of the Joint Committee is to explore policy matters and funding that concerns both
governing bodies. The Committee will provide collaborative review, analysis, and recommendations
regarding the use of infrastructure funds. The Committee will meet bi‐weekly, or at the discretion of the
Co‐Chairs, to work on topics including, but not limited to the following:
• Identify long-term goals and develop short term action plan
• Identify location of student population and determine system capacity
• Overview of building conditions and major maintenance needs
• Budget and capital improvement program
• Ongoing revenue and efficiency considerations
Membership consists of three members of City Council and three members of the School Board, with
Co-Chairs selected by the Mayor and School Board Chair. The first meeting shall be an organizational
meeting that takes place on Thursday, February, 27th at 5:00 pm, at which the following shall be
addressed:
• Identify short term actions to be taken
• Discuss long term goals
• Direct staff research
• Establish future meeting schedule
The body shall meet with the goal of producing a report in April, and will dissolve no later than June 30,
2025. The City Manager or his designee will coordinate the meetings and agenda on the advice of the
Co-Chairs. At every meeting committee members will have the opportunity to thoroughly discuss,
analyze, and ask questions in order to make a final recommendation.
Meeting Schedule
Wednesday, March 12th at 5:00 pm: Work Session
Thursday, March 27th at 5:00 pm: Work Session
Thursday, April 10th at 5:00 pm: Work Session
Tuesday, April 29th at 4:00 pm: Joint Meeting with City Council / School Board to present
recommendations
Monday June 30th: Committee Sunsets
Page 24 of 47
City Council
Agenda Item IV.4.
Business Item Briefings
AGENDA ITEM SUMMARY
MEETING DATE PRESENTED BY
March 11, 2025 Wyatt Woody, Director of Parks and
Recreation
AGENDA ITEM # IV.4
Heritage Park Improvements
RECOMMENDATION
This item will appear for City Council action on the March 25, 2025 General Business
agenda. Approval of the return of real estate from Lynchburg City Schools specific to Heritage High
School.
SUMMARY
Parks & Recreation is requesting acceptance of a former Heritage High School athletic facility as
part of Heritage Park. The facility would be renovated using existing capital funding to provide a
much-needed multipurpose field in an area of the City that has limited public recreation options. As
part of the renovations, field lighting would be added to extend the availability of the field's use.
The Lynchburg City School Board unanimously approved the return of real estate at their March 4,
2025 meeting.
PRIOR ACTION(S)
N/A
FISCAL IMPACT
City Council previously appropriated funding for improvements and field lighting for Heritage Park.
CONTACT(S)
Wyatt Woody, Director of Parks and Recreation
ATTACHMENT(S)
1. Heritage Park BIB
REVIEWED BY
Page 25 of 47
Date: March 06, 2025
Alicia Finney, Clerk of Council
Page 26 of 47
HERITAGE PARK
PROPERTY TRANSFER
Tuesday, March 11, 2025
Page 27 of 47
PURPOSE & ACTION
Purpose:
Council acceptance of real property transfer from LCS located behind
Heritage High School.
Why:
Develops an underutilized property and helps to address and area of the
City that was identified as having limited public recreation options. As
part of the renovations, field lighting would be added to extend the
availability of the field’s use.
Page 28 of 47
HERITAGE PARK
IMPROVEMENTS
Supported by current
master plans and
Comprehensive Plan
City Council
Positive public
feedback
Page 29 of 47
NEXT STEPS:
March 25, 2025
Acceptance of property transfer from Lynchburg City Schools
Page 30 of 47
City Council
Agenda Item IV.5.
Business Item Briefings
AGENDA ITEM SUMMARY
MEETING DATE PRESENTED BY
March 11, 2025 Donna Witt, Chief Financial Officer
AGENDA ITEM # IV.5
Virginia Opioid Abatement Authority Grant Award
RECOMMENDATION
Consideration of adopting Resolution #R-25-___ to authorize the City Manager to execute a
Memorandum of Understanding (MOU) with Roads to Recovery, Inc. (R2R).
Consideration of introducing Resolution #R-25-___ amending the FY 2025 City/Federal/State Aid
Fund budget and appropriating $193,422 with resources from the Virginia Opioid Abatement
Authority's (OAA) Grant to the City of Lynchburg for FY 2025, in relation to a R2R 8-Bed Withdrawal
Management Program, for purposes of providing funds to establish and deliver withdrawal
management services for individuals with opioid and other substance use disorders in Central
Virginia’s Planning District 11 (which includes the City, and the Virginia Counties of Amherst,
Appomattox, Bedford, and Campbell).
SUMMARY
City Council will consider this item at its regular meeting on March 11, 2025. The City receives funds
from the OAA through direct distributions and grants. R2R has applied to utilize City grant funds to
establish and deliver withdrawal management services for individuals with opioid and other
substance-use disorders in the City. The OAA has awarded R2R $193,421.31 for this purpose. In
order to accept the grant funds and transfer the funds to R2R, City Council is requested to authorize
the City Manager to sign the MOU between R2R and the City and also adopt the resolution to
appropriate the funds.
PRIOR ACTION(S)
FISCAL IMPACT
None; the appropriated funds of $193,422 are resources from the OAA grant
CONTACT(S)
Donna Witt, Chief Financial Officer
ATTACHMENT(S)
1. BIB - OAA grant for R2R
2. Resolution - OAA Award Resolution (R2R)
Page 31 of 47
3. OAA MOU 3.3.2025
4. VA Opioid Abatement Authority Award Acceptance Letter
REVIEWED BY
Date: March 06, 2025
Donna Witt, Chief Financial Officer
Date: March 06, 2025
Gregory Patrick, Deputy City Manager
Date: March 06, 2025
Alicia Finney, Clerk of Council
Page 32 of 47
Page 33 of 47
Authorize the City Manager to execute a Memorandum of Understanding
(MOU) with Roads to Recovery and appropriate $193,422 from the Virginia
Opioid Abatement Authority (OAA)
Roads to Recovery in conjunction with the City has successfully applied
for funding from the OAA
2
Page 34 of 47
1. Direct distribution to participating localities, which includes the City
• Appropriated for use by the Recovery Court
2. Funds allocated to the locality but must be approved through an
application process
• Requesting appropriation for Roads to Recovery
3. Funds available through a competitive grant process
• Appropriated for Horizon Behavioral Health
3
Page 35 of 47
• Authorize the City Manager to execute the MOU with Roads to Recovery
• Appropriate OAA grant funds for use by Roads to Recovery for a
withdrawal management program
4
Page 36 of 47
Page 37 of 47
RESOLUTION: #R-25-____
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF LYNCHBURG:
1. That the City of Lynchburg, Virginia (“City”), as a fiscal agent for Roads to Recovery, Inc. (“R2R”), a nonprofit
Recovery Community Organization duly organized and existing under the laws of the Commonwealth of Virginia,
shall manage a grant from the Virginia Opioid Abatement Authority (the “OAA”), such grant being specific to R2R
establishing and maintaining an 8-Bed Withdrawal Management Program and providing services related to the
same, for individuals with opioid and other substance use disorders in Central Virginia's Planning District 11
(which includes the City, and the Virginia Counties of Amherst, Appomattox, Bedford, and Campbell), hereafter
the “Project”, in accordance with a proposed Memorandum of Understanding (“MOU”), between the City and
R2R, dated March 11, 2025, and incorporated herein by reference.
2. That the City Manager, or his designee, on behalf of the City, is authorized to execute the MOU with R2R in
relation to the Project and may take any further actions necessary in connection with the same.
3. That this Resolution shall be effective upon its adoption.
Adopted:
Certified:
Clerk of Council
RESOLUTION: #R-25-____
BE IT RESOLVED BY THE COUNCIL OF THE CITY OF LYNCHBURG: that the FY 2025 City/Federal/State
Aid Fund Budget is amended and $193,422 is appropriated therein for expenditure, with resources from a Virginia
Opioid Abatement Authority (“OAA”) grant to the City of Lynchburg, Virginia (“City”) for FY 2025, in relation to a
Roads to Recovery, Inc. 8-Bed Withdrawal Management Program, for purposes of providing funds to establish
and deliver withdrawal management services for individuals with opioid and other substance use disorders in
Central Virginia’s Planning District 11 (which includes the City, and the Virginia Counties of Amherst,
Appomattox, Bedford, and Campbell).
Introduced: Adopted:
Certified:
Clerk of Council
Page 38 of 47
1
MEMORANDUM OF UNDERSTANDING
BY AND BETWEEN
ROADS TO RECOVERY, INC. AND CITY OF LYNCHBURG, VIRGINIA
THIS MEMORANDUM OF UNDERSTANDING ("MOU"), made and entered into on this 11th
day of March, 2025, by and between Roads to Recovery, Inc. ("R2R"), a nonprofit Recovery Community
Organization duly organized and existing under the laws of the Commonwealth of Virginia, and the City
of Lynchburg, Virginia ("City"), a municipal corporation and political subdivision of the Commonwealth
of Virginia, collectively referred to as the "Parties."
RECITALS
WHEREAS, R2R met with the City in 2024 to discuss a partnership and application to the Virginia
Opioid Abatement Authority (“OAA”) for funds to allow R2R to establish and deliver withdrawal
management services for individuals with opioid and other substance use disorders in the City of
Lynchburg, Virginia and the Commonwealth of Virginia. Further, R2R demonstrated their organization
possesses the necessary expertise, experience, and capacity to deliver medically supervised withdrawal
management services to those individuals, and R2R worked with the City to apply for OAA funding in the
Fall of 2024. Subsequently, the OAA approved the use and allocation of OAA funding in the amount of
One Hundred Ninety-Three Thousand Four Hundred Twenty-One Dollars and Thirty-One Cents
($193,421.31) for the purpose of addressing the Opioid Epidemic through the establishment and operation
of an 8-Bed Withdrawal Management Program in Central Virginia's Planning District 11 which includes
the City, and the Counties of Amherst, Appomattox, Bedford, and Campbell; and
WHEREAS, R2R was founded in 2010 and incorporated in 2013 as a Recovery Community
Organization, and since that time has provided critical recovery support services, including recovery
housing and center-based peer recovery support ("PRS") services, to over two hundred (200) individuals
annually who are seeking recovery from substance use disorders ("SUDs"); and
WHEREAS, the City, in furtherance of its commitment to public health, the well-being of City
residents, and helping fight the Opioid Epidemic across the Commonwealth of Virginia, has agreed to
partner with R2R and act as the fiscal agent to ensure that the OAA funds are administered and utilized in
compliance with all applicable OAA, legal, and regulatory requirements; and
Page 39 of 47
2
WHEREAS, the Parties mutually desire to set forth their respective roles and responsibilities in
implementing the said 8-Bed Withdrawal Management Program in a manner that is transparent, efficient,
and beneficial to the City, R2R, and the community; and
WHEREAS, the “Project” subject to this MOU is briefly described as follows:
City will partner with R2R to provide partial funding for staff-related costs for a Withdrawal Management
Program (WMP). The WMP will provide care, support, and connection to ongoing treatment and recovery
services for up to 417 adults each year who are experiencing withdrawal from opioid and other substance
use disorders in Central Virginia's Planning District 11 which includes the City, and the Counties of
Amherst, Appomattox, Bedford, and Campbell. The eight-bed program emphasizes evidence-based peer
and social supports for the delivery of detoxification services in a safe and supportive environment,
including wraparound support for seamless transitioning to treatment and other recovery support services,
and other community services that will assist our people to achieve and sustain recovery. The program
includes a specialized, structured environment for individuals experiencing opioid and other substance
withdrawal sufficient to require 24-hour support but not require the resources of a hospital facility. R2R’s
proposal will fund programming/service costs for FY25.; and
WHEREAS, the City, by a Resolution duly adopted by the Lynchburg City Council on March 11,
2025, the City Manager was authorized to: 1) execute a grant application to the OAA for
programming/service costs for FY25 in relation to the Project in the amount of $193,421.31, 2) to accept
the grant award connected with the said application, and 3) to execute all documents in connection
therewith, in relation to the “Project”; and
WHEREAS, R2R and the City desire to enter into this MOU to memorialize their relationship
under the said OAA grant application and the “Project”.
NOW, THEREFORE, WITNESSETH: that the Parties to this MOU, in consideration of the above
recitals and the mutual covenants and stipulations set out herein, agree as follows:
1. Upon receipt of the funds connected to the OAA grant for the Project, R2R shall use all of
the said funds in accordance with all applicable requirements, terms, and conditions of the OAA
grant for the Project. If R2R violates such requirements, terms, conditions, and/or any
representations made herein by R2R as to the Project, then within thirty (30) days of a written
request from the OAA, or the City acting on behalf of the OAA, R2R shall return to the OAA or
the City, as applicable, any and all funds not used in compliance with the requirements, terms,
and/or conditions of the OAA grant for the Project.
2. R2R shall provide the City, upon request and in writing, a list of all grants received for the
Project or related/connected to the Project.
3. R2R represents to the City that the Project will achieve sustainable funding without OAA
assistance by Fiscal Year 2027 (FY27).
Page 40 of 47
3
4. R2R represents that the Project’s 8-Bed Withdrawal Management Program and its
connected facilities, once completed and ready for use, will remain in operation for at least five (5)
full calendar years for its stated and anticipated purpose(s), or all of the OAA grant funding
contemplated hereby will be returned to the City (and in turn provided to the OAA) by R2R, with
the option at the OAA’s discretion, that such amounts may be prorated to account for the years that
the said 8-Bed Withdrawal Management Program and its connected facilities remained in
operation.
5. R2R further represents that the Project’s 8-Bed Withdrawal Management Program and its
connected facilities, once completed and ready for use, will be used for purposes of the Project
during the life of the said OAA grant award and any subsequent OAA grant awards for the Project.
6. R2R will provide the following services at its sole effort and expense:
A. Medically Supervised Peer Delivered Detox Support: Ensure 24/7 monitoring and medical
oversight of individuals undergoing withdrawal management.
B. Nursing Assessments: Conduct intake and comprehensive assessments to determine
appropriate care pathways.
C. Peer Recovery Support Services: Offer peer coaching and recovery planning to individuals
before, during, and after withdrawal management.
D. Referral and Case Management: Provide linkages to long-term treatment, housing, and
wraparound services.
E. Community Engagement & Outreach: Educate and inform the public about available
withdrawal management services and increase program access for underserved populations.
F. Comply with all applicable local, state, and federal requirements connected to its operations
and the OAA grant for the Project and the 8-Bed Withdrawal Management Program.
G. Ensure that all program staff, including medical and peer recovery specialists, are properly
trained and credentialed.
H. Manage the day-to-day operations of the 8-Bed Withdrawal Management Program and its
connected facilities, ensuring the highest quality of care and safety for program participants.
I. Submit required program reports, financial records, and evaluation data to the City, and
where required the OAA, in a timely manner.
J. Collaborate with community partners, law enforcement, and healthcare providers to
ensure continuity of care for individuals served.
K. R2R shall maintain accurate financial records and provide documentation of expenditures
to the City upon request.
L. Comply with R2R-required financial reporting requirements connected to the OAA grant
contemplated hereby and the Project.
Page 41 of 47
4
7. The City shall, at its sole effort and expense:
A. Serve as the fiscal agent for the OAA grant for the Project, ensuring compliance with City-
required financial reporting requirements connected to the same.
B. Assist in the oversight and administration of the OAA grant funds for the Project where
required by state and federal regulations.
C. Facilitate connections between R2R and relevant municipal agencies, including public
health and social services.
D. Provide oversight in the collection of program data and evaluation metrics to assess
program effectiveness.
E. Assist in promoting public awareness of the program and its benefits to the community.
E. The City, as the fiscal agent, will ensure that funds are disbursed in accordance with the
terms of the OAA grant agreement.
8. The 8-Bed Withdrawal Management Program of the Project, for FY25,will be funded in
the amount of $193,421.31 through the OAA. Such funds shall be used exclusively for program-
related costs, including staff salaries, supplies, operational expenses, and administrative costs.
9. This MOU shall take effect upon execution by the Parties and shall remain in effect for the
duration of the funding period unless modified by mutual written agreement or terminated by either
Party hereto with thirty (30) days' written notice.
10. Both Parties shall comply with all federal, state, and local laws and regulations, which
apply to them under the Project and the 8-Bed Withdrawal Management Program, including where
applicable HIPAA and the confidentiality provisions under 42 CFR Part 2.
11. If any part, provision, or portion of this MOU is deemed unenforceable by a court of
competent jurisdiction, then the Parties agree all remaining parts, provisions, and portions of this
MOU shall remain in full force and effect.
12. This MOU embodies the entire understanding of the Parties, and it supersedes all previous
agreements that may have existed between the Parties with respect to the subjects described herein.
13. Modifications, additions, amendments, and/or alternations to any of the provisions of this
MOU shall be in writing and signed by duly authorized representatives of the Parties.
14. This MOU shall be governed in its entirety by the laws of the Commonwealth of Virginia.
Any litigation arising between the Parties hereto, in relation to this MOU, shall be filed in the courts
of the City of Lynchburg, Virginia.
Page 42 of 47
5
15. R2R shall maintain all necessary licenses, permits, approvals, and the like connected to its
operations, this MOU, or both.
16. All notices or other writings required to be given under this MOU shall be given by date-
and-time stamped facsimile, hand delivery with signed receipt, overnight or other courier with
signed receipt, or by return receipt certified or registered mail, addressed to the proper Party to the
following addresses, or at such other address as may be subsequently given pursuant to this Section,
and shall be deemed given within seven (7) days of being sent or provided:
If to City:
City of Lynchburg, Virginia
Attn: Chief Financial Officer
900 Church Street
Lynchburg, VA 24504
If to R2R:
Roads to Recovery, Inc.
Attn: Sandy Kanehl, CEO
3000 Langhorne Road
Lynchburg, VA 24501
17. The Parties shall be deemed and construed as independent contractors with respect to
one another for all purposes, and nothing contained in this MOU shall be determined to
create a partnership or joint venture between R2R and the City with respect to the Parties'
activities under this MOU. R2R and the City are each responsible for their own respective
liabilities under this MOU.
18. The waiver by either R2R or the City of any default or breach by the other Party of any
of the provisions of this MOU shall not be deemed a continuing waiver or waiver of any
other breach by the other Party of the same or another provision hereof.
19. This MOU shall be binding upon and shall inure to the benefit of the Parties and their
respective successors and assigns. Further, this MOU, nor any part thereof, may be assigned
without the written consent of the non-assigning Party.
20. No third-party beneficiaries are intended by this MOU.
21. The Parties agree this MOU may be executed by electronic signature. Without
limitation, “electronic signature” shall include faxed versions of an original signature or
electronically scanned and transmitted versions (e.g., via pdf) of an original signature. This
MOU may be executed in counterparts. Each of which when so executed shall be deemed to
be an original and all of which taken together shall constitute one document.
Page 43 of 47
6
IN WITNESS WHEREOF, the Parties, or authorized agents on their behalf, do hereby execute this
MOU as of the date first above written.
Roads to Recovery, Inc.:
_____________________________
Sandy Kanehl, CEO
Date: _________________________
City of Lynchburg, Virginia:
_____________________________
Wynter C. Benda, City Manager
Date: _________________________
Page 44 of 47
Page 45 of 47
Page 46 of 47
Page 47 of 47
Source: City of Lynchburg website. First collected Oct 26, 2026.