RESCHEDULED: Physical Development Committee Meeting — Agenda Packet
City of Lynchburg · Lynchburg City County · Physical Development Committee · meeting of Feb 18, 2025 · Agenda packets
Open the original document More from City of Lynchburg
Text
Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.
PHYSICAL DEVELOPMENT COMMITTEE
City Council Committee
Tuesday, February 18, 2025 | 2:00 PM
I.T. Conference Center
3550 Young Place
Lynchburg, VA 24501
AGENDA
I. Welcome Councilmember Jacqueline Timmer,
Chair
II. Information Items
II.1. A Minute for Planning - Community Development
II.2. Large Project Updates for Public Works and Water Resources - Over $5 Million
III. General Business
III.3. Additional VDOT lane miles for FY26
IV. Roll Call
V. Next Regular Meeting
Page 1 of 25
CAPITAL PROJECTS UPDATE
February 11, 2025
Public Works
Page 2 of 25
RIVERFRONT PARK
IMPROVEMENTS
• Total cost: $8.7 million
• Funding: Fully funded
• Construction start: April 2024
• Anticipated construction finish:
Spring 2026
• Phase: Construction
• Utilities complete – water/sewer
• Power awaiting AEP
• Foundation work underway
• Restroom @ 100%
• Amphitheater @ 90%
• Restroom construction @ 80%
• Amphitheater
• Steel Roof Assemblies @ 40%
• Current progress:
• On-time: Yes
• On-budget: Yes
Page 3 of 25
POLICE DEPARTMENT
HEADQUARTERS
• Total cost: $48.5 million
• Funding: Fully funded
• Construction start: October
2022
• Anticipated construction finish:
February 2025
• Phase: Construction
• Building is nearing completion
• Drywall/finishes/fixtures being
punchlisted
• FF&E deliveries underway
• Current progress:
• On-time: Yes
• On-budget: Council approved
funding for FF&E increases, further
change orders are pending. No
additional funding needed
Page 4 of 25
BEDFORD AVENUE BRIDGE
• Total cost: $24.2 million
• Funding: Need additional funds from
CIP/VDOT Requesting additional $8.8M
from VDOT
• Anticipated Construction start: Spring
2027
• Anticipated construction finish: Winter
2029/30
• Phase: Pre-Design
• Working through procurement with VDOT
• Negotiating with Consultant
• Current progress:
• On-time: No, will reset when contract is
signed
• On-budget: Yes
Page 5 of 25
BREEZEWOOD DRIVE
IMPROVEMENTS
• Total cost: $9.8 million
• Funding: Fully funded
• Anticipated Construction start: Fall
2026
• Anticipated construction finish: Fall
2027
• Phase: Design
• Consultant under contract
• Surveying completed
• 30% plans in next 60 days
• Current progress:
• On-time: Yes
• On-budget: Yes
Page 6 of 25
FIFTH STREET
RECONSTRUCTION
• Total cost: $7.3 million
• Funding: Fully funded
• Anticipated Construction start: Spring
2025
• Anticipated construction finish: Fall
2027
• Phase: Right of way
• 90% complete
• One parcel has 11 heirs, mostly out of state
• Current progress:
• On-time: No, will reset when right of way
secured
• On-budget: Yes
Page 7 of 25
DOWNTOWN RENEWAL:
MAIN STREET EAST
• Total cost: $4.2 million – general fund
• Funding: Fully funded
• Construction start: August 2024
• Anticipated construction finish:
December 2026
• Phase: Construction
• Underway – Working on underground utilities
• Current progress:
• On-time: Yes
• On-budget: Yes
Page 8 of 25
JOHN LYNCH BRIDGE
• Total cost: $7.2 million
• Funding: Fully funded
• Construction start: Winter 2025
• Anticipated construction finish:
Summer 2026
• Phase: Construction
• Underway – Working on joint replacements
• Current progress:
• On-time: Yes
• On-budget: Yes
Page 9 of 25
501/221 INTERSECTION
• Total cost: $85.8 million
• Funding: Need additional $11.7M from
CIP/VDOT Requesting additional $5.8M from
VDOT
• Anticipated Construction start: Spring
2028
• Anticipated construction finish: Winter
2030/31
• Phase: Design
• Working through procurement with VDOT
• Negotiating with Consultant
• Current progress:
• On-time: No, will reset when contract is signed
• On-budget: No, additional funds needed
Page 10 of 25
CAPITAL PROJECTS UPDATE
February 11, 2025
Water Resources
Page 11 of 25
LYHBEYOND: BLACKWATER CSO TUNNEL
• Total cost: $103.9 million
• Funding: Fully funded
• Construction start: July 2024
• Anticipated construction finish: July 2027
• Phase: Construction
• Construction of Downtown CSO Pump Station
shaft ongoing at 7th Street site
• Drill-and-blast operations ongoing
• Current progress:
• On-time: Yes
• Minor delays; recovery schedule in development
• On-budget: Yes
Page 12 of 25
COLLEGE LAKE DAM REMOVAL
• Total cost: $22.5 million
• Funding: Fully funded
• Construction start: January 2024
• Anticipated construction finish: July 2025
• Phase: Stream and wetland restoration
• Current progress:
• On-time: Yes
• On-budget: Yes, within the original budget,
however:
• Change orders paid to date: $358,755
• Change orders pending: Changes to stabilization
strategy of old bridge will result in savings of
approximately $10,000
& LAKEBED RESTORATION
Page 13 of 25
DOWNTOWN RENEWAL:
MAIN STREET EAST
• Total cost: $10.7 million
• Water: $4.3 million*
• Sewer: $1.4 million*
• Stormwater: $800,000*
• General: $4.2 million*
• Funding: Fully funded
• Construction start: August 2024
• Anticipated construction finish: December 2026
• Phase: Construction
• Current progress:
• On-time: Yes
• On-budget: Yes
* These amounts reflect December 2024 adjusted values
Page 14 of 25
RICHLAND HILLS SEWER
EXTENSION, PHASE 1
• Total cost: $8 million (ARPA eligible: $6.6 million)
• Funding: Fully funded
• Construction start: November 2024
• Anticipated construction finish: June 2026
• Phase: Construction
• Current progress:
• On-time: Yes
• On-budget: Yes
Page 15 of 25
COLLEGE HILL UTILITY
IMPROVEMENTS
• Total cost: $5.54 million
• Funding: Fully funded
• Construction start: December 2024
• Anticipated construction finish: March 2026
• Phase: Construction
• Currently working on Madison Street
• Project includes: 4,500 linear feet water line;
1,400 lf sewer line; 300 lf storm line
• Current progress:
• On-time: Yes
• On-budget: Yes
6th & MADISON
PROJECT
Page 16 of 25
LEAD SERVICE LINE
INVENTORY PROGRAM
• Cost for current phase: $1.48 million (initial inventory only)
• Future costs: TBD – anticipate $30+ million over 10 years
based on regulatory requirements and current known
system information
• Funding: Current inventory work fully funded; replacement
program not funded but applying for State funding
• LCRR Inventory: Submitted to VDH in October 2024;
VDH has approved; first round of notifications complete
• Anticipated finish: EPA’s Lead & Copper Rule Improvements
(LCRI) has anticipated deadline of 2037
• Phase: Self-reporting ongoing; reopening consulting
contract to establish LCRI program
• Current phase progress:
• On-time: Yes
• On-budget: Yes
Page 17 of 25
Physical Development
Committee
Agenda Item III.3.
Action
AGENDA ITEM SUMMARY
MEETING DATE PRESENTED BY
February 18, 2025 Lee Newland
AGENDA ITEM # III.3
Additional VDOT lane miles for FY26
RECOMMENDATION
Approve the attached resolution requesting Virginia Department of Transportation (VDOT) to
increase the official City Street lane mileage for reimbursement of highway maintenance funds for
FY 2026.
SUMMARY
When required, usually each year, the City submits a list of new or improved streets to VDOT for
acceptance into the street maintenance system for payments to the City from the Commonwealth.
For FY 2026, staff has identified 1.36 lane miles of street segments that need to be added. These
street segments are shown on the attached maps and VDOT U-1 Form.
This action is required by VDOT to add these segments to the system.
PRIOR ACTION(S)
None
FISCAL IMPACT
1.36 additional lane miles will increase highway maintenance funds in the amount of $23,232
annually.
CONTACT(S)
Lee Newland
Gaynelle Hart, Director of Public Works
ATTACHMENT(S)
1. RESOLUTION
2. U-1 FORM
3. Rosedale Map
4. Independence Map
5. Belle Terre Map
6. Grove Hill Map
Page 18 of 25
REVIEWED BY
Date: January 29, 2025
Gaynelle Hart, Director of Public Works
Date: February 06, 2025
Gregory Patrick, Deputy City Manager
Date: February 06, 2025
Alicia Finney, Clerk of Council
Page 19 of 25
RESOLUTION:
WHEREAS, the Virginia Department of Transportation (VDOT) requires action to increase the lane mileage for
street maintenance entitlement funds from the Commonwealth; and,
WHEREAS, 1.36 lane miles of local and arterial streets have been identified to be added to the system; and,
NOW, THEREFORE, BE IT RESOLVED THAT: The Lynchburg City Council requests the Commonwealth
Transportation Board to approve the addition of lane mileage as enumerated on Form U-1.
Adopted:______________________
Certified:______________________
Clerk of Council
Page 20 of 25
Page 21 of 25
Rosedale Boulevard
µ
DISCLAIMER: THIS MAP IS NEITHER A LEGALLY RECORDED MAP NOR A SURVEY AND IS NOT INTENDED TO BE USED AS
SUCH. THE INFORMATION DISPLAYED IS A COMPILATION OF RECORDS, INFORMATION, AND DATA OBTAINED FROM
VARIOUS SOURCES. THE CITY OF LYNCHBURG IS NOT RESPONSIBLE FOR ITS ACCURACY OR HOW CURRENT IT MAY BE.
0 100 200
ft
1 inch = 100 feet
PRINTED ON
January 21, 20251:1,200
Page 22 of 25
Independence Ln
µ
DISCLAIMER: THIS MAP IS NEITHER A LEGALLY RECORDED MAP NOR A SURVEY AND IS NOT INTENDED TO BE USED AS
SUCH. THE INFORMATION DISPLAYED IS A COMPILATION OF RECORDS, INFORMATION, AND DATA OBTAINED FROM
VARIOUS SOURCES. THE CITY OF LYNCHBURG IS NOT RESPONSIBLE FOR ITS ACCURACY OR HOW CURRENT IT MAY BE.
0 100 200
ft
1 inch = 100 feet
PRINTED ON
January 16, 20251:1,200
Page 23 of 25
Belle Terre and Thicket Drives
µ
DISCLAIMER: THIS MAP IS NEITHER A LEGALLY RECORDED MAP NOR A SURVEY AND IS NOT INTENDED TO BE USED AS
SUCH. THE INFORMATION DISPLAYED IS A COMPILATION OF RECORDS, INFORMATION, AND DATA OBTAINED FROM
VARIOUS SOURCES. THE CITY OF LYNCHBURG IS NOT RESPONSIBLE FOR ITS ACCURACY OR HOW CURRENT IT MAY BE.
0 100 200
ft
1 inch = 100 feet
PRINTED ON
January 17, 20251:1,200
Page 24 of 25
Grove Hill Terrace
µ
DISCLAIMER: THIS MAP IS NEITHER A LEGALLY RECORDED MAP NOR A SURVEY AND IS NOT INTENDED TO BE USED AS
SUCH. THE INFORMATION DISPLAYED IS A COMPILATION OF RECORDS, INFORMATION, AND DATA OBTAINED FROM
VARIOUS SOURCES. THE CITY OF LYNCHBURG IS NOT RESPONSIBLE FOR ITS ACCURACY OR HOW CURRENT IT MAY BE.
0 150 300
ft
1 inch = 150 feet
PRINTED ON
January 21, 20251:1,800
Page 25 of 25