Arlington County, Virginia CIP
2025 − 2034
LOCAL PARKS AND RECREATION PROGRAMS: SYNTHETIC
TURF PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Synthetic Turf Program 0 0 2,337 3,132 2,094 1,975 1,634 3,617 4,710 1,700 21,199
2. Greenbrier Park/Yorktown
High Stadium Field
1,164 0 0 0 0 0 0 0 0 0 1,164
3. Kenmore Middle School
Athletic Field Conversion
9,842 0 0 0 0 0 0 0 0 0 9,842
4. Long Bridge Park Synthetic
Field #3
0 1,041 0 0 0 0 0 0 0 0 1,041
5. Thomas Jefferson Middle
School Lower Field
819 0 0 0 0 0 0 0 0 0 819
Total Recommendation 11,825 1,041 2,337 3,132 2,094 1,975 1,634 3,617 4,710 1,700 34,065
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 2,400 0 0 0 0 0 0 0 0 0 2,400
PAYG 1,155 0 0 0 0 0 0 0 0 0 1,155
Short Term Finance 0 1,041 1,702 1,997 2,094 1,975 1,007 2,231 3,000 1,511 16,558
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 5,270 0 635 1,135 0 0 627 1,386 1,710 189 10,952
Tax Increment Financing (TIF) 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 8,825 1,041 2,337 3,132 2,094 1,975 1,634 3,617 4,710 1,700 31,065
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Tax Increment Financing (TIF) 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 3,000 0 0 0 0 0 0 0 0 0 3,000
Subtotal Previously Approved
Funding 3,000 0 0 0 0 0 0 0 0 0 3,000
Total Funding Sources 11,825 1,041 2,337 3,132 2,094 1,975 1,634 3,617 4,710 1,700 34,065
C - 37
LOCAL PARKS AND RECREATION PROGRAMS Capital Improvement Plan
Synthetic Turf Program FY 2025-2034
1. SYNTHETIC TURF PROGRAM
Project Highlights:
• Arlington County has invested significantly in the
construction of synthetic turf fields to meet the demand for
athletic fields that serve a wide variety of athletic programs
and drop-in use.
• The County has 15 rectangular fields with synthetic turf and
two diamond fields with synthetic turf bringing the total
number of synthetic fields to 17.
• Synthetic turf typically has an eight-year useful life.
Associated Plan(s):
Long Bridge Park Master Plan (2013)
Public Spaces Master Plan (PSMP)
N
eighborhood(s):
VARIOUS
Funding Notes: Replacement and conversion of fields through the Synthetic Turf Program are typically funded with bonds, short -
term financing and other funding. Other funding includes contributions from Arlington Public Schools for their share of fields co -
located at high schools and middle schools as well as contributions from Marymount University, George Washington University, and
other partnerships.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Short Term Finance 1,702 1,997 2,094 1,975 1,007 2,231 3,000 1,511 15,517
Other Funding 635 1,135 627 1,386 1,710 189 5,682
Previous Funding
Total Funding 0 0 2,337 3,132 2,094 1,975 1,634 3,617 4,710 1,700 21,199
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Turf Replacement Construction 3-4 Months
• Turf Conversion Design and Construction 12-18 Months
C
hanges from Prior CIP:
No significant change from the previous CIP.
C - 38
LOCAL PARKS AND RECREATION PROGRAMS Capital Improvement Plan
Synthetic Turf Program FY 2025-2034
2. GREENBRIER PARK/YORKTOWN HIGH STADIUM FIELD
Project Highlights:
• Design and construction for the replacement of the synthetic
turf surfacing on the stadium athletic field.
• Synthetic turf surfacing typically has an eight -year useful
life.
• The synthetic turf surfacing at all three high school stadium
fields is laid over an underlayment pad to reduce the risk of
injuries from falls to the surface.
Associated Plan(s):
Public Spaces Master Plan (PSMP)
N
eighborhood(s):
Yorktown
Funding Notes: Cost share with APS (50% County / 50% Schools).
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 582 582
Other Funding 582 582
Previous Funding
Total Funding 1,164 0 0 0 0 0 0 0 0 0 1,164
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design of Synthetic Turf Replacement Summer 2024
• Bidding for Synthetic Turf Replacement Fall/Winter
2024
• Construction of Synthetic Turf Replacement Spring 2025
C
hanges from Prior CIP:
No change from the previous CIP.
C - 39
LOCAL PARKS AND RECREATION PROGRAMS Capital Improvement Plan
Synthetic Turf Program FY 2025-2034
3. KENMORE MIDDLE SCHOOL ATHLETIC FIELD CONVERSION
Project Highlights:
• Design and construction for the conversion of two
diamond/rectangular combo fields on the campus of
Kenmore Middle School.
• The fields are currently natural turf and in poor condition.
The goal of the project is to convert these fields to synthetic
turf surfacing.
• Costs include design development, excavation of existing soil
to allow for the placement of new turf and installation of
storm water management facilities, batting cages, backstops,
shade structures, signage, spectator seating, athletic
equipment, site fur nishings, accessible walkways, ADA
improvements for all park amenities, sports field fencing,
donor wall and landscaping.
• The project also includes the replacement of existing athletic
lighting and the installation of new LED sports lighting.
Associated Plan(s):
Public Spaces Master Plan (PSMP)
N
eighborhood(s):
Glencarlyn
Funding Notes: "Other Funds" include outside group fundraising ($2M), APS Cost Sharing at 70% County / 30% APS ($2.442M).
"Other Previously Approved Funds" include Field Fund balances ($1M) and existing synthetic program contingency funds ($2M).
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 2,400 2,400
Other Funding 4,442 4,442
Previous Funding
Other Previously
Approved Funds 3,000 3,000
Total Funding 9,842 0 0 0 0 0 0 0 0 0 9,842
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Operations Costs (+/-) 11 11 12 12 12 13 13 84
Total Impact 0 0 0 11 11 12 12 12 13 13 84
Critical Milestones:
• Anticipated start of Design Spring 2025
• Anticipated start of Construction Fall 2026
• Anticipated completion of Construction Summer 2027
Changes from Prior CIP:
Funding distributions are updated to reflect outside sources and
existing balances.
C - 40
LOCAL PARKS AND RECREATION PROGRAMS Capital Improvement Plan
Synthetic Turf Program FY 2025-2034
4. LONG BRIDGE PARK SYNTHETIC FIELD #3
Project Highlights:
• Design and construction for the replacement of the synthetic
turf surfacing on Field #3 at Long Bridge Park.
• Synthetic turf surfacing typically has an eight -year useful
life.
• Costs include design development, replacement of the
synthetic turf and infill, repairs to the base layer and under -
drain system, replacement of field amenities and construction
administration.
Associated Plan(s):
Public Spaces Master Plan (PSMP)
N
eighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Short Term Finance 1,041 1,041
Previous Funding
Total Funding 0 1,041 0 0 0 0 0 0 0 0 1,041
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design replacement of the synthetic turf
surfacing.
Fall 2025
• Bid replacement of the synthetic turf
surfacing.
Winter 2025
• Construction of the synthetic turf surfacing
on Field #3 at Long Bridge Park.
Spring 2026
C
hanges from Prior CIP:
No significant change from the previous CIP.
C - 41
LOCAL PARKS AND RECREATION PROGRAMS Capital Improvement Plan
Synthetic Turf Program FY 2025-2034
5. THOMAS JEFFERSON MIDDLE SCHOOL LOWER FIELD
Project Highlights:
• Design and construction for the replacement of the synthetic
turf surfacing on the Lower Field at TJ.
• Synthetic turf surfacing typically has an eight -year useful
life.
• Costs include design development, replacement of the
synthetic turf and infill, repairs to the base layer and under -
drain system, replacement of field amenities and construction
administration.
Associated Plan(s):
Public Spaces Master Plan (PSMP)
N
eighborhood(s):
Arlington Heights
Funding Notes: Cost Share with APS (70% County/30% Schools).
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 573 573
Other Funding 246 246
Previous Funding
Total Funding 819 0 0 0 0 0 0 0 0 0 819
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design of the synthetic turf field. Winter
2024/2025
• Bidding of the replacement of the synthetic
turf.
Spring 2025
• Construction of the replacement of the
synthetic turf on the Lower Field at TJ
Community Center.
Summer 2025
C
hanges from Prior CIP:
No change from the previous CIP.
C - 42