Arlington County, Virginia
Arlington County, Virginia CIP
2025 − 2034
REGIONAL PARTNERSHIPS AND CONTINGENCIES: REGIONAL
PARTNERSHIPS PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Northern Virginia Criminal
Justice Academy
127 128 0 0 0 0 0 0 0 0 255
2. Northern Virginia Regional
Park Authority
731 738 768 776 783 791 799 807 815 823 7,831
Total Recommendation 858 866 768 776 783 791 799 807 815 823 8,086
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 0 0 0 0 0 0 0 0
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 0 0 0 0 0 0 0 0 0 0 0
PAYG 858 866 768 776 783 791 799 807 815 823 8,086
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 858 866 768 776 783 791 799 807 815 823 8,086
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 0 0 0 0 0 0 0 0 0 0 0
Subtotal Previously Approved
Funding 0 0 0 0 0 0 0 0 0 0 0
Total Funding Sources 858 866 768 776 783 791 799 807 815 823 8,086
C - 3
Arlington County, Virginia
REGIONAL PARTNERSHIPS AND CONTINGENCIES Capital Improvement Plan
Regional Partnerships FY 2025-2034
1. NORTHERN VIRGINIA CRIMINAL JUSTICE ACADEMY
Project Highlights:
• The Northern Virginia Criminal Justice Academy (NVCJA)
provides law enforcement training and is comprised of
seventeen police and sheriff agencies from Northern Virginia
and the District of Columbia.
• In 2006, the principal members agreed to fund the
construction of the Emergency Vehicle Operations Center
(EVOC).
• The bond financing contributions towards the NVCJTA
partnership continues through 2026.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 127 128 255
Previous Funding
Total Funding 127 128 0 0 0 0 0 0 0 0 255
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Changes in funding reflect the completion of bond financing
contributions in FY 2026.
.
C - 4
Arlington County, Virginia
REGIONAL PARTNERSHIPS AND CONTINGENCIES Capital Improvement Plan
Regional Partnerships FY 2025-2034
2. NORTHERN VIRGINIA REGIONAL PARK AUTHORITY
Project Highlights:
• The Northern Virginia Regional Park Authority (NVRPA) is
a multi-jurisdictional agency comprised of Arlington County,
Fairfax County, Loudoun County, and the Cities of
Alexandria, Falls Church, and Fairfax.
• Northern Virginia Regional Park Authority owns and
protects more than 10,000 acres of land in 19 parks, including
Potomac Overlook, Upton Hill and the W&OD Regional
Parks in Arlington.
• Funds are used to preserve, improve, expand, renovate and
enhance the parks and facilities.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
PAYG 731 738 768 776 783 791 799 807 815 823 7,831
Previous Funding
Total Funding 731 738 768 776 783 791 799 807 815 823 7,831
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Funding adjusted based on current and anticipated regional
cost allocations.
C - 5
Source: Arlington County website. First collected Oct 27, 2026.