Arlington County, Virginia CIP 2025 − 2034 STORMWATER MANAGEMENT: SM MAINTENANCE CAPITAL PROGRAM 10 YEAR CATEGORY SUMMARY (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total 1. Detention Vaults & Overland Relief Maintenance 100 105 105 110 110 110 110 115 115 120 1,100 2. Dumbarton Street Culvert- Downstream 3,000 1,545 0 0 0 0 0 0 0 0 4,545 3. Dumbarton Street Culvert- Upstream 3,000 1,545 0 0 0 0 0 0 0 0 4,545 4. Floodplain Channel & Split Stream Maintenance 100 105 105 110 110 110 110 115 115 120 1,100 5. Four Mile Run Flood Control Project Maintenance 500 50 55 55 55 55 55 60 60 60 1,005 6. Manhole & Catch Basin Rehabilitation 250 260 265 275 275 280 280 290 290 295 2,760 7. Military Road Culvert at Gulf Branch 2,090 1,030 0 0 0 0 0 0 0 0 3,120 8. Sidewalk Underdrains 50 50 55 55 55 55 55 60 60 60 555 9. Stormwater Frames and Covers 250 260 265 275 275 280 280 290 290 295 2,760 10. Stormwater Mains Rehabilitation & Replacement 1,000 1,545 2,120 2,455 2,725 3,080 3,250 3,450 3,565 3,775 26,965 11. Terra Cotta/ Corrugated Metal Pipe Upgrades 205 215 225 240 240 250 250 260 260 265 2,410 Total Recommendation 10,545 6,710 3,195 3,575 3,845 4,220 4,390 4,640 4,755 4,990 50,865 F - 46 CATEGORY FUNDING SOURCES (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total New Funding Federal Funding 3,000 0 0 0 0 0 0 0 0 0 3,000 State Funding 0 0 0 0 0 0 0 0 0 0 0 Developer Contributions 0 0 0 0 0 0 0 0 0 0 0 New Bond Issue 0 0 0 0 5 0 95 0 140 0 240 PAYG 0 0 0 0 0 0 0 0 0 0 0 Short Term Finance 0 0 0 0 0 0 0 0 0 0 0 Stormwater Utility Fee Revenue 2,455 2,590 3,195 3,575 3,840 4,220 4,295 4,640 4,615 4,990 38,415 Other Funding 0 0 0 0 0 0 0 0 0 0 0 Subtotal New Funding 5,455 2,590 3,195 3,575 3,845 4,220 4,390 4,640 4,755 4,990 41,655 Previously Approved Funding Authorized but Unissued Bonds 5,090 4,120 0 0 0 0 0 0 0 0 9,210 Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0 Other Previously Approved Funds 0 0 0 0 0 0 0 0 0 0 0 Subtotal Previously Approved Funding 5,090 4,120 0 0 0 0 0 0 0 0 9,210 Total Funding Sources 10,545 6,710 3,195 3,575 3,845 4,220 4,390 4,640 4,755 4,990 50,865 F - 47 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 1. DETENTION VAULTS & OVERLAND RELIEF MAINTENANCE Project Highlights: • Underground detention facilities and overland relief paths require continued capital maintenance efforts to ensure they remain effective. • Funding is included for capital maintenance of the Cardinal School vault and overland relief areas. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 100 105 105 110 110 110 110 115 115 120 1,100 Previous Funding Total Funding 100 105 105 110 110 110 110 115 115 120 1,100 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 48 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 2. DUMBARTON STREET CULVERT-DOWNSTREAM Project Highlights: • This project is a replacement of the existing Downstream Dumbarton Street Culvert which was damaged in the August 2017 storm. • Replacement is needed to expand capacity and replace existing headwalls, end walls, and deteriorating culvert barrels. The existing culvert overtops the road during extreme storm events. • Existing culvert is constructed of corrugated metal pipe, which is deteriorating and requires replacement. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Rock Spring New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Previous Funding Authorized but Unissued Bonds 3,000 1,545 4,545 Total Funding 3,000 1,545 0 0 0 0 0 0 0 0 4,545 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Spring 2023 • Construction Fall 2024 Changes from Prior CIP: Timing of expenditures has pushed out two years from the previous CIP. Project Links: • Dumbarton St Culvert Replacement – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Projects/Project- Types/Environment-Projects/Dumbarton-St-Culvert- Replacement F - 49 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 3. DUMBARTON STREET CULVERT-UPSTREAM Project Highlights: • This project is a replacement of the existing Upstream Dumbarton Street Culvert which was damaged in the August 2017 storm. • Replacement is needed to expand capacity and replace existing headwalls, end walls, and deteriorating culvert barrels. The existing culvert overtops the road during major storm events. • Existing culvert is constructed of corrugated metal pipe, which is deteriorating and requires replacement. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Rock Spring New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Federal Funding 3,000 3,000 Previous Funding Authorized but Unissued Bonds 1,545 1,545 Total Funding 3,000 1,545 0 0 0 0 0 0 0 0 4,545 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Spring 2023 • Construction Fall 2024 Changes from Prior CIP: Project cost has increased based on design and federal funding requirements. Timing of construction has pushed out two years from the previous CIP. Project Links: • Dumbarton St Culvert Replacement – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Projects/Project- Types/Environment-Projects/Dumbarton-St-Culvert- Replacement F - 50 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 4. FLOODPLAIN CHANNEL & SPLIT STREAM MAINTENANCE Project Highlights: • Floodplain channels must be maintained to ensure efficiency of the existing conveyance system. • Split streams are located at Gulf Branch, Little Pimmit Run, and Lucky Run, where the County undergrounded these streams into culverts and diverted a small man -made stream on top for aesthetic and environmental purposes. The diversion structures routinely clog and need maintenance. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 100 105 105 110 110 110 110 115 115 120 1,100 Previous Funding Total Funding 100 105 105 110 110 110 110 115 115 120 1,100 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 51 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 5. FOUR MILE RUN FLOOD CONTROL PROJECT MAINTENANCE Project Highlights: • Project is routine capital maintenance of the Four Mile Run Flood Control Project area. • Project is required by U.S. Army Corps of Engineers. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Arlington Ridge Long Branch Creek New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 500 50 55 55 55 55 55 60 60 60 1,005 Previous Funding Total Funding 500 50 55 55 55 55 55 60 60 60 1,005 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Tree replacement planting Spring 2024 • Tree removal along Long Branch/Troy Park Fall 2024 Changes from Prior CIP: Timing of expenditures has pushed out one year from the previous CIP. Project Links: • Four Mile Run Channel Maintenance and Dredging Project – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Projects/Project- Types/Environment-Projects/Four-Mile-Run-Channel- Maintenance-and-Dredging-Project F - 52 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 6. MANHOLE & CATCH BASIN REHABILITATION Project Highlights: • Project is for rehabilitation and replacement of manholes and catch basins that have been damaged or need maintenance. This is completed through lining and/or structural rebuilds when necessary. • The stormwater system inspection program identifies structures that need to be replaced or rehabilitated. Major storm events can damage structures which necessitate actions. • This work is necessary for the proper functioning of the stormwater drainage system. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 250 260 265 275 275 280 280 290 290 295 2,760 Previous Funding Total Funding 250 260 265 275 275 280 280 290 290 295 2,760 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 53 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 7. MILITARY ROAD CULVERT AT GULF BRANCH Project Highlights: • Project will replace Military Road Culvert at Gulf Branch to expand capacity and replace the deteriorating structure. • The culvert frequently overtops during storms, flooding the area including the nearby Gulf Run pump station building. • Project will be done in conjunction with the adjacent Gulf Branch Stream Resiliency project. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Gulf Branch Old Glebe New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Previous Funding Authorized but Unissued Bonds 2,090 1,030 3,120 Total Funding 2,090 1,030 0 0 0 0 0 0 0 0 3,120 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Spring 2023 • Construction Summer 2024 Changes from Prior CIP: Timing of expenditures has pushed out one year from the previous CIP. F - 54 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 8. SIDEWALK UNDERDRAINS Project Highlights: • Project installs underdrains on sidewalks, which are necessary in some locations to prevent unsafe conditions on sidewalks and reduces hazards to pedestrians. • Drainage from hillsides, sump pumps, and other poorly drained areas often seeps across sidewalks and can cause slippery conditions due to algae growth in warm months and icing conditions in cold months. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 50 50 55 55 55 55 55 60 60 60 555 Previous Funding Total Funding 50 50 55 55 55 55 55 60 60 60 555 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 55 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 9. STORMWATER FRAMES AND COVERS Project Highlights: • This program funds the required adjustments to stormwater structure frames and covers in conjunction with annual paving operations. • Adjustments involve raising or lowering a casting or precast top from its existing elevation to align with the adjacent grade, pavement, curb, etc. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 250 260 265 275 275 280 280 290 290 295 2,760 Previous Funding Total Funding 250 260 265 275 275 280 280 290 290 295 2,760 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No significant change from the previous CIP. F - 56 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 10. STORMWATER MAINS REHABILITATION & REPLACEMENT Project Highlights: • This program funds the rehabilitation and replacement of existing storm drainage pipes within the system. • Systematic rehabilitation and replacement of system assets will strengthen system integrity and reliability, protects public health and safety, reduces impacts on interconnected infrastructure, and increases long-term cost-effectiveness. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS Funding Notes: Funding is available for a nominal number of projects, depending on scale. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 5 95 140 240 Stormwater Utility Fee Revenue 1,000 1,545 2,120 2,455 2,720 3,080 3,155 3,450 3,425 3,775 26,725 Previous Funding Total Funding 1,000 1,545 2,120 2,455 2,725 3,080 3,250 3,450 3,565 3,775 26,965 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: Funding in the first half of the CIP is less than the previous CIP based on updated program priorities and other planned/ funded projects. F - 57 STORMWATER MANAGEMENT Capital Improvement Plan SM Maintenance Capital FY 2025-2034 11. TERRA COTTA/ CORRUGATED METAL PIPE UPGRADES Project Highlights: • This program funds replacement of existing, poor condition terra cotta (TC) and corrugated metal pipe (CMP) with reinforced concrete pipe or other modern pipe materials, which have longer life spans. Failure of existing, aged TC and CMP is a leading cause of various maintenance activities. • Replacement of TC and CMP within the stormwater conveyance system is a program goal.TC & CMP pipe are often in poor condition due to age, limitations of the pipe material, and shorter lifespan than reinforced concrete pipe. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 205 215 225 240 240 250 250 260 260 265 2,410 Previous Funding Total Funding 205 215 225 240 240 250 250 260 260 265 2,410 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 58

Source: Arlington County website. First collected Oct 27, 2026.