Arlington County, Virginia CIP
2025 − 2034
STORMWATER MANAGEMENT: STORMWATER INFRASTRUCTURE/
CAPACITY IMPROVEMENTS PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. 33rd Street North to
Williamsburg Capacity
0 160 1,115 1,175 1,010 1,260 0 0 0 0 4,720
2. Capacity Project Feasibility
Studies
150 155 160 165 165 170 170 175 175 175 1,660
3. Columbia Pike at South
Greenbrier Street
1,000 1,190 820 8,980 5,200 0 0 0 0 0 17,190
4. Crossman Run Watershed
Capacity Improvements
0 3,420 3,140 1,600 15,425 12,990 0 0 0 0 36,575
5. Flood Resiliency Design &
Construction Guidelines
150 0 0 0 0 0 0 0 0 0 150
6. Flood Risk Reduction
Program
1,500 1,590 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 14,250
7. Langston Boulevard Culvert
at North Sycamore
440 0 0 0 0 0 0 0 0 0 440
8. Lower Long Branch Flood
Risk Reduction Project
0 0 0 0 0 645 665 700 720 740 3,470
9. Lubber Run Watershed
Capacity Improvements
1,500 3,610 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 66,960
10. Miscellaneous Expansion/
Capacity Projects
0 310 0 325 0 335 0 345 0 355 1,670
11. North Thomas Street 255 875 1,125 0 0 0 0 0 0 0 2,255
12. Spout Run Watershed
Capacity Improvements
7,900 8,130 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 69,965
13. Stohman's Run Watershed
Capacity Improvements
250 515 1,310 0 0 0 0 0 0 0 2,075
14. Torreyson Run Watershed
Capacity Improvements
1,725 4,140 4,860 5,340 1,635 0 0 0 0 0 17,700
15. Williamsburg at North
Underwood Capacity
0 155 865 960 1,125 0 0 0 0 0 3,105
Total Recommendation 14,870 24,250 27,095 30,350 39,715 30,865 15,125 23,095 19,990 16,830 242,185
F - 59
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 0 0 4,000 0 0 0 0 0 0 4,000
State Funding 0 0 0 0 0 0 0 0 0 0 0
Developer Contributions 0 0 0 0 0 0 0 0 0 0 0
New Bond Issue 0 0 23,030 26,145 39,715 30,695 15,125 22,920 19,990 16,655 194,275
PAYG 0 0 0 0 0 0 0 0 0 0 0
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 740 155 160 205 0 170 0 175 0 175 1,780
Other Funding 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 740 155 23,190 30,350 39,715 30,865 15,125 23,095 19,990 16,830 200,055
Previously Approved Funding
Authorized but Unissued
Bonds 14,130 24,095 3,905 0 0 0 0 0 0 0 42,130
Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0
Other Previously Approved
Funds 0 0 0 0 0 0 0 0 0 0 0
Subtotal Previously Approved
Funding 14,130 24,095 3,905 0 0 0 0 0 0 0 42,130
Total Funding Sources 14,870 24,250 27,095 30,350 39,715 30,865 15,125 23,095 19,990 16,830 242,185
F - 60
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
1. 33RD STREET NORTH TO WILLIAMSBURG CAPACITY
Project Highlights:
• This is a watershed -scale project in the Little Pimmit Run
watershed to increase capacity by connecting previously
constructed storm drain improvements from the cul-de-sac at
33rd Street North to Williamsburg Boulevard.
• Land acquisition is required.
• Existing stormwater pipes experience capacity issues -
expansion of capacity is currently restrained by small
easements and other nearby utilities.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Rock Spring
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 1,175 1,010 1,260 3,445
Previous Funding
Authorized but Unissued
Bonds
160 1,115 1,275
Total Funding 0 160 1,115 1,175 1,010 1,260 0 0 0 0 4,720
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Summer 2025
• Construction Summer 2026
Changes from Prior CIP:
Timing of expenditures has pushed out four years from the
previous CIP.
F - 61
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
2. CAPACITY PROJECT FEASIBILITY STUDIES
Project Highlights:
• Planning and feasibility studies provide an integrated
approach to proper scoping of potential projects.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 165 170 175 510
Stormwater Utility Fee
Revenue 150 155 160 165 170 175 175 1,150
Previous Funding
Total Funding 150 155 160 165 165 170 170 175 175 175 1,660
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No change from the previous CIP.
F - 62
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
3. COLUMBIA PIKE AT SOUTH GREENBRIER STREET
Project Highlights:
• This project will help mitigate frequent and severe flooding
around Columbia Pike and South Greenbrier Street by
increasing stormwater system capacity and efficiency
(identified for Critical Vulnerability).
• Easements will likely be required to complete the necessary
improvements.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Columbia Forest
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Federal Funding 4,000 4,000
New Bond Issue 820 4,980 5,200 11,000
Previous Funding
Authorized but Unissued
Bonds 1,000 1,190 2,190
Total Funding 1,000 1,190 820 8,980 5,200 0 0 0 0 0 17,190
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Feasibility Study Fall 2022
• Design Spring 2024
• Construction Fall 2024
Changes from Prior CIP:
Timing of expenditures has pushed out two years from the
previous CIP.
Project Links:
• West Columbia Pike Stormwater Improvements – Official
Website of Arlington County Virginia Government
(arlingtonva.us):
https://www.arlingtonva.us/Government/Programs/Office-
of-Sustainability-and-Environment/Stormwater/Stormwater-
Capacity-Improvements/West-Columbia-Pike-Stormwater-
Improvements
F - 63
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
4. CROSSMAN RUN WATERSHED CAPACITY IMPROVEMENTS
Project Highlights:
• This project is a watershed scale solution for flooding and
drainage issues (identified for Critical Vulnerability).
• Solutions may include a combination of pipe upgrades, new
conveyance systems, and underground detention vaults.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Arlington-East Falls Church
Williamsburg
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 2,340 1,600 15,425 12,990 32,355
Previous Funding
Authorized but Unissued
Bonds
3,420 800 4,220
Total Funding 0 3,420 3,140 1,600 15,425 12,990 0 0 0 0 36,575
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Summer 2025
• Construction FY 2026 –
FY 2030
Changes from Prior CIP:
Timing of expenditures has pushed out three years from the
previous CIP.
Project Links:
• Crossman Run Stormwater Improvements – Official
Website of Arlington County Virginia Government
(arlingtonva.us):
https://www.arlingtonva.us/Government/Programs/Office-
of-Sustainability-and-Environment/Stormwater/Stormwater-
Capacity-Improvements/Crossman-Run-Stormwater-
Improvements
F - 64
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
5. FLOOD RESILIENCY DESIGN & CONSTRUCTION GUIDELINES
Project Highlights:
• The Flood Resiliency Design and Construction Guidelines
Manual was approved by the County's Stormwater Inter -
Departmental Working Group as a key action.
• Guidelines will be voluntary in the initial phase.
• Areas targeted for resiliency design and construction will be
identified by Risk Assessment & Management Plan (RAMP)
Study.
• Will address both residential and commercial design and
construction measures, techniques, policies, and
mechanisms.
• Project includes active engagement with the public and key
stakeholders in real estate, architecture, construction,
appraisals, and insurance.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Stormwater Utility Fee
Revenue 150 150
Previous Funding
Total Funding 150 0 0 0 0 0 0 0 0 0 150
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Development of Guidelines FY 2025
Changes from Prior CIP:
Timing of expenditures has pushed out two years from the
previous CIP.
F - 65
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
6. FLOOD RISK REDUCTION PROGRAM
Project Highlights:
• This program implements the capacity and flood risk
reduction project priorities identified in the 2014 Stormwater
Master Plan for areas which have experienced repeated
flooding.
• The projects in this program may not be watershed scale in
scope.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 11,160
Previous Funding
Authorized but Unissued
Bonds 1,500 1,590 3,090
Total Funding 1,500 1,590 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 14,250
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
No change from the previous CIP.
F - 66
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
7. LANGSTON BOULEVARD CULVERT AT NORTH SYCAMORE
Project Highlights:
• Watershed scale project to increase capacity of culverts
crossing Langston Boulevard at North Sycamore Street.
Project is additional phase of previous project.
• Project will coordinate with Transportation for improvements
to the intersection.
• Project will improve hydraulic capacity of existing culverts
and piped systems, including elements such as increased pipe
diameters, detention, green overland flow, and pump
systems.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Stormwater Utility Fee
Revenue 440 440
Previous Funding
Total Funding 440 0 0 0 0 0 0 0 0 0 440
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Summer 2023
• Construction Spring 2025
Changes from Prior CIP:
Project scope and size has decreased from the previous CIP.
Project Links:
• Crossman Run Stormwater Improvements – Official Website
of Arlington County Virginia Government (arlingtonva.us):
https://www.arlingtonva.us/Government/Programs/Office-
of-Sustainability-and-Environment/Stormwater/Stormwater-
Capacity-Improvements/Crossman-Run-Stormwater-
Improvements
F - 67
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
8. LOWER LONG BRANCH FLOOD RISK REDUCTION PROJECT
Project Highlights:
• Project goal is to reduce the risk of flooding along Lower
Long Branch from South Glebe Road to 26th Street South,
including Troy Park.
• Project has potential to remove properties from FEMA
floodplains.
Associated Plan(s):
Storm Water Master Plan
Watershed Management Plan
Neighborhood(s):
Long Branch Creek
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 645 665 700 720 740 3,470
Previous Funding
Total Funding 0 0 0 0 0 645 665 700 720 740 3,470
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Develop public outreach plan Summer 2029
• Develop and refine concept plans Summer 2030
• FEMA studies Summer 2031
• Rescope project and initiate final designs Summer 2032
Changes from Prior CIP:
Timing of expenditures has pushed out two years from the
previous CIP.
F - 68
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
9. LUBBER RUN WATERSHED CAPACITY IMPROVEMENTS
Project Highlights:
• Watershed scale improvements in multiple locations. Project
areas experienced repeated and -in some cases - extreme
flooding (identified for Critical Vulnerability).
• Acquisition of rights -of-ways, easements, and land are
required.
• Solution may include a combination of pipe upgrades, new
conveyance lines, and underground detention.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Bluemont
Glebewood
John M. Langston
Tara-Leeway Heights
Waycroft-Woodlawn
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 61,850
Previous Funding
Authorized but Unissued
Bonds 1,500 3,610 5,110
Total Funding 1,500 3,610 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 66,960
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Summer 2024
• Construction Fall 2025
Changes from Prior CIP:
Timing of expenditures has pushed out two years from the
previous CIP.
Project Links:
• Lubber Run Stormwater project page:
https://environment.arlingtonva.us/stormwater-capacity-
improvements/lubber-run-stormwater-improvements/
F - 69
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
10. MISCELLANEOUS EXPANSION/ CAPACITY PROJECTS
Project Highlights:
• This program is for the design and construction of pipe
extensions needed to address localized drainage problems.
• The project goal is to increase capacity of the secondary and
tertiary storm drainage system where data, surveys, and
capacity studies identify insufficiency or under-development
of the system.
• This program is not intended to provide watershed scale
drainage improvements.
• This program is for the design and construction of new storm
drainage system assets where none currently exist.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 285 335 345 355 1,320
Stormwater Utility Fee
Revenue
40 40
Previous Funding
Authorized but Unissued
Bonds
310 310
Total Funding 0 310 0 325 0 335 0 345 0 355 1,670
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Changes from Prior CIP:
Slight changes to the timing and cost from the previous CIP.
F - 70
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
11. NORTH THOMAS STREET
Project Highlights:
• Project will increase capacity of the storm drain system along
North Thomas Street to mitigate flooding during severe
storms.
• Project includes installation of approximately 700 linear feet
of 60 -inch diameter storm sewer and upgrades to several
inlets into the system.
• Existing stormwater infrastructure has needed several repairs
due to deteriorating condition.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Donaldson Run
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Previous Funding
Authorized but Unissued
Bonds 255 875 1,125 2,255
Total Funding 255 875 1,125 0 0 0 0 0 0 0 2,255
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Summer 2024
• Construction Summer 2025
Changes from Prior CIP:
Timing of expenditures has pushed out one year from previous
CIP.
F - 71
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
12. SPOUT RUN WATERSHED CAPACITY IMPROVEMENTS
Project Highlights:
• This is a watershed scale project to increase capacity of storm
sewers and provide overland relief pathways to mitigate
impacts of flooding (identified for Critical Vulnerability).
• Current focus is on providing an overland relief flow path for
larger storm events.
• Land acquisition is required.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Cherrydale
Waverly Hills
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 53,935
Previous Funding
Authorized but Unissued
Bonds 7,900 8,130 16,030
Total Funding 7,900 8,130 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 69,965
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Non-Personnel ($) 75 100 125 150 175 200 225 250 1,300
Total Impact 75 100 125 150 175 200 225 250 1,300
Critical Milestones:
• Design Ongoing through Spring 2034
• Construction Ongoing through Spring2034
Changes from Prior CIP:
Slight changes in funding levels from the previous CIP.
Project Links:
• Spout Run Stormwater Project Page:
https://environment.arlingtonva.us/stormwater-capacity-
improvements/spout-run-stormwater-improvements/
F - 72
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
13. STOHMAN'S RUN WATERSHED CAPACITY IMPROVEMENTS
Project Highlights:
• This project will increase capacity of the storm drainage
system in Stohman's Run watershed along 39th Street North
where there is no overland relief.
• Project will reduce potential damage to public and private
property due to repeated flooding.
• Easement acquisitions required.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Stafford-Albermarle-Glebe
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 1,310 1,310
Previous Funding
Authorized but Unissued
Bonds 250 515 765
Total Funding 250 515 1,310 0 0 0 0 0 0 0 2,075
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Ongoing through Spring 2026
• Construction Spring 2027
Changes from Prior CIP:
Timing of expenditures has pushed out two years from previous
CIP.
F - 73
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
14. TORREYSON RUN WATERSHED CAPACITY IMPROVEMENTS
Project Highlights:
• This is a watershed scale project to increase capacity of storm
sewers and provide overland relief pathways to mitigate
impacts of flooding (identified for Critical Vulnerability).
• Initial project implementation focuses on reducing risk of
flooding in Westover area, which experienced severe
flooding in 2019.
• Future improvements include upstream detention facility and
pipe upgrades to complete the watershed scale flooding
solutions. Downstream improvements near I -66 are also in
planning stages.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Highland Park-Overlee Knoll
Leeway Overlee
Tara-Leeway Heights
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 4,860 5,340 1,635 11,835
Previous Funding
Authorized but Unissued
Bonds 1,725 4,140 5,865
Total Funding 1,725 4,140 4,860 5,340 1,635 0 0 0 0 0 17,700
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Ongoing through Spring 2028
• Construction Ongoing through Spring 2029
Changes from Prior CIP:
Timing of expenditures has pushed out two years from the
previous CIP.
Project Links:
• Torreyson Run Stormwater Improvements – Official
Website of Arlington County Virginia Government
(arlingtonva.us):
https://www.arlingtonva.us/Government/Programs/Office-
of-Sustainability-and-Environment/Stormwater/Stormwater-
Capacity-Improvements/Torreyson-Run-Stormwater-
Improvements
F - 74
STORMWATER MANAGEMENT Capital Improvement Plan
Stormwater Infrastructure/ Capacity Improvements FY 2025-2034
15. WILLIAMSBURG AT NORTH UNDERWOOD CAPACITY
Project Highlights:
• This project will reduce the hydraulic grade line in
Williamsburg Boulevard and increase capacity of the storm
drain system to address area flooding
• Project entails approximately 500 linear feet of 60-inch
diameter storm sewer.
Associated Plan(s):
Storm Water Master Plan
Neighborhood(s):
Arlington-East Falls Church
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
New Bond Issue 960 1,125 2,085
Previous Funding
Authorized but Unissued
Bonds 155 865 1,020
Total Funding 0 155 865 960 1,125 0 0 0 0 0 3,105
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
C
ritical Milestones:
• Design Summer 2026
• Construction Summer 2027
C
hanges from Prior CIP:
Timing of expenditures has pushed out three years from the
previous CIP.
F - 75