Arlington County, Virginia CIP 2025 − 2034 STORMWATER MANAGEMENT: STORMWATER INFRASTRUCTURE/ CAPACITY IMPROVEMENTS PROGRAM 10 YEAR CATEGORY SUMMARY (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total 1. 33rd Street North to Williamsburg Capacity 0 160 1,115 1,175 1,010 1,260 0 0 0 0 4,720 2. Capacity Project Feasibility Studies 150 155 160 165 165 170 170 175 175 175 1,660 3. Columbia Pike at South Greenbrier Street 1,000 1,190 820 8,980 5,200 0 0 0 0 0 17,190 4. Crossman Run Watershed Capacity Improvements 0 3,420 3,140 1,600 15,425 12,990 0 0 0 0 36,575 5. Flood Resiliency Design & Construction Guidelines 150 0 0 0 0 0 0 0 0 0 150 6. Flood Risk Reduction Program 1,500 1,590 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 14,250 7. Langston Boulevard Culvert at North Sycamore 440 0 0 0 0 0 0 0 0 0 440 8. Lower Long Branch Flood Risk Reduction Project 0 0 0 0 0 645 665 700 720 740 3,470 9. Lubber Run Watershed Capacity Improvements 1,500 3,610 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 66,960 10. Miscellaneous Expansion/ Capacity Projects 0 310 0 325 0 335 0 345 0 355 1,670 11. North Thomas Street 255 875 1,125 0 0 0 0 0 0 0 2,255 12. Spout Run Watershed Capacity Improvements 7,900 8,130 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 69,965 13. Stohman's Run Watershed Capacity Improvements 250 515 1,310 0 0 0 0 0 0 0 2,075 14. Torreyson Run Watershed Capacity Improvements 1,725 4,140 4,860 5,340 1,635 0 0 0 0 0 17,700 15. Williamsburg at North Underwood Capacity 0 155 865 960 1,125 0 0 0 0 0 3,105 Total Recommendation 14,870 24,250 27,095 30,350 39,715 30,865 15,125 23,095 19,990 16,830 242,185 F - 59 CATEGORY FUNDING SOURCES (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total New Funding Federal Funding 0 0 0 4,000 0 0 0 0 0 0 4,000 State Funding 0 0 0 0 0 0 0 0 0 0 0 Developer Contributions 0 0 0 0 0 0 0 0 0 0 0 New Bond Issue 0 0 23,030 26,145 39,715 30,695 15,125 22,920 19,990 16,655 194,275 PAYG 0 0 0 0 0 0 0 0 0 0 0 Short Term Finance 0 0 0 0 0 0 0 0 0 0 0 Stormwater Utility Fee Revenue 740 155 160 205 0 170 0 175 0 175 1,780 Other Funding 0 0 0 0 0 0 0 0 0 0 0 Subtotal New Funding 740 155 23,190 30,350 39,715 30,865 15,125 23,095 19,990 16,830 200,055 Previously Approved Funding Authorized but Unissued Bonds 14,130 24,095 3,905 0 0 0 0 0 0 0 42,130 Issued but Unspent Bonds 0 0 0 0 0 0 0 0 0 0 0 Other Previously Approved Funds 0 0 0 0 0 0 0 0 0 0 0 Subtotal Previously Approved Funding 14,130 24,095 3,905 0 0 0 0 0 0 0 42,130 Total Funding Sources 14,870 24,250 27,095 30,350 39,715 30,865 15,125 23,095 19,990 16,830 242,185 F - 60 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 1. 33RD STREET NORTH TO WILLIAMSBURG CAPACITY Project Highlights: • This is a watershed -scale project in the Little Pimmit Run watershed to increase capacity by connecting previously constructed storm drain improvements from the cul-de-sac at 33rd Street North to Williamsburg Boulevard. • Land acquisition is required. • Existing stormwater pipes experience capacity issues - expansion of capacity is currently restrained by small easements and other nearby utilities. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Rock Spring New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 1,175 1,010 1,260 3,445 Previous Funding Authorized but Unissued Bonds 160 1,115 1,275 Total Funding 0 160 1,115 1,175 1,010 1,260 0 0 0 0 4,720 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Summer 2025 • Construction Summer 2026 Changes from Prior CIP: Timing of expenditures has pushed out four years from the previous CIP. F - 61 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 2. CAPACITY PROJECT FEASIBILITY STUDIES Project Highlights: • Planning and feasibility studies provide an integrated approach to proper scoping of potential projects. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 165 170 175 510 Stormwater Utility Fee Revenue 150 155 160 165 170 175 175 1,150 Previous Funding Total Funding 150 155 160 165 165 170 170 175 175 175 1,660 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 62 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 3. COLUMBIA PIKE AT SOUTH GREENBRIER STREET Project Highlights: • This project will help mitigate frequent and severe flooding around Columbia Pike and South Greenbrier Street by increasing stormwater system capacity and efficiency (identified for Critical Vulnerability). • Easements will likely be required to complete the necessary improvements. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Columbia Forest New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Federal Funding 4,000 4,000 New Bond Issue 820 4,980 5,200 11,000 Previous Funding Authorized but Unissued Bonds 1,000 1,190 2,190 Total Funding 1,000 1,190 820 8,980 5,200 0 0 0 0 0 17,190 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Feasibility Study Fall 2022 • Design Spring 2024 • Construction Fall 2024 Changes from Prior CIP: Timing of expenditures has pushed out two years from the previous CIP. Project Links: • West Columbia Pike Stormwater Improvements – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Programs/Office- of-Sustainability-and-Environment/Stormwater/Stormwater- Capacity-Improvements/West-Columbia-Pike-Stormwater- Improvements F - 63 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 4. CROSSMAN RUN WATERSHED CAPACITY IMPROVEMENTS Project Highlights: • This project is a watershed scale solution for flooding and drainage issues (identified for Critical Vulnerability). • Solutions may include a combination of pipe upgrades, new conveyance systems, and underground detention vaults. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Arlington-East Falls Church Williamsburg New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 2,340 1,600 15,425 12,990 32,355 Previous Funding Authorized but Unissued Bonds 3,420 800 4,220 Total Funding 0 3,420 3,140 1,600 15,425 12,990 0 0 0 0 36,575 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Summer 2025 • Construction FY 2026 – FY 2030 Changes from Prior CIP: Timing of expenditures has pushed out three years from the previous CIP. Project Links: • Crossman Run Stormwater Improvements – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Programs/Office- of-Sustainability-and-Environment/Stormwater/Stormwater- Capacity-Improvements/Crossman-Run-Stormwater- Improvements F - 64 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 5. FLOOD RESILIENCY DESIGN & CONSTRUCTION GUIDELINES Project Highlights: • The Flood Resiliency Design and Construction Guidelines Manual was approved by the County's Stormwater Inter - Departmental Working Group as a key action. • Guidelines will be voluntary in the initial phase. • Areas targeted for resiliency design and construction will be identified by Risk Assessment & Management Plan (RAMP) Study. • Will address both residential and commercial design and construction measures, techniques, policies, and mechanisms. • Project includes active engagement with the public and key stakeholders in real estate, architecture, construction, appraisals, and insurance. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 150 150 Previous Funding Total Funding 150 0 0 0 0 0 0 0 0 0 150 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Development of Guidelines FY 2025 Changes from Prior CIP: Timing of expenditures has pushed out two years from the previous CIP. F - 65 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 6. FLOOD RISK REDUCTION PROGRAM Project Highlights: • This program implements the capacity and flood risk reduction project priorities identified in the 2014 Stormwater Master Plan for areas which have experienced repeated flooding. • The projects in this program may not be watershed scale in scope. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 11,160 Previous Funding Authorized but Unissued Bonds 1,500 1,590 3,090 Total Funding 1,500 1,590 1,995 2,205 1,070 1,100 1,130 1,190 1,220 1,250 14,250 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No change from the previous CIP. F - 66 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 7. LANGSTON BOULEVARD CULVERT AT NORTH SYCAMORE Project Highlights: • Watershed scale project to increase capacity of culverts crossing Langston Boulevard at North Sycamore Street. Project is additional phase of previous project. • Project will coordinate with Transportation for improvements to the intersection. • Project will improve hydraulic capacity of existing culverts and piped systems, including elements such as increased pipe diameters, detention, green overland flow, and pump systems. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Stormwater Utility Fee Revenue 440 440 Previous Funding Total Funding 440 0 0 0 0 0 0 0 0 0 440 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Summer 2023 • Construction Spring 2025 Changes from Prior CIP: Project scope and size has decreased from the previous CIP. Project Links: • Crossman Run Stormwater Improvements – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Programs/Office- of-Sustainability-and-Environment/Stormwater/Stormwater- Capacity-Improvements/Crossman-Run-Stormwater- Improvements F - 67 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 8. LOWER LONG BRANCH FLOOD RISK REDUCTION PROJECT Project Highlights: • Project goal is to reduce the risk of flooding along Lower Long Branch from South Glebe Road to 26th Street South, including Troy Park. • Project has potential to remove properties from FEMA floodplains. Associated Plan(s): Storm Water Master Plan Watershed Management Plan Neighborhood(s): Long Branch Creek New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 645 665 700 720 740 3,470 Previous Funding Total Funding 0 0 0 0 0 645 665 700 720 740 3,470 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Develop public outreach plan Summer 2029 • Develop and refine concept plans Summer 2030 • FEMA studies Summer 2031 • Rescope project and initiate final designs Summer 2032 Changes from Prior CIP: Timing of expenditures has pushed out two years from the previous CIP. F - 68 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 9. LUBBER RUN WATERSHED CAPACITY IMPROVEMENTS Project Highlights: • Watershed scale improvements in multiple locations. Project areas experienced repeated and -in some cases - extreme flooding (identified for Critical Vulnerability). • Acquisition of rights -of-ways, easements, and land are required. • Solution may include a combination of pipe upgrades, new conveyance lines, and underground detention. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Bluemont Glebewood John M. Langston Tara-Leeway Heights Waycroft-Woodlawn New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 61,850 Previous Funding Authorized but Unissued Bonds 1,500 3,610 5,110 Total Funding 1,500 3,610 3,075 1,260 6,455 6,560 6,240 14,870 13,385 10,005 66,960 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Summer 2024 • Construction Fall 2025 Changes from Prior CIP: Timing of expenditures has pushed out two years from the previous CIP. Project Links: • Lubber Run Stormwater project page: https://environment.arlingtonva.us/stormwater-capacity- improvements/lubber-run-stormwater-improvements/ F - 69 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 10. MISCELLANEOUS EXPANSION/ CAPACITY PROJECTS Project Highlights: • This program is for the design and construction of pipe extensions needed to address localized drainage problems. • The project goal is to increase capacity of the secondary and tertiary storm drainage system where data, surveys, and capacity studies identify insufficiency or under-development of the system. • This program is not intended to provide watershed scale drainage improvements. • This program is for the design and construction of new storm drainage system assets where none currently exist. Associated Plan(s): Storm Water Master Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 285 335 345 355 1,320 Stormwater Utility Fee Revenue 40 40 Previous Funding Authorized but Unissued Bonds 310 310 Total Funding 0 310 0 325 0 335 0 345 0 355 1,670 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: Slight changes to the timing and cost from the previous CIP. F - 70 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 11. NORTH THOMAS STREET Project Highlights: • Project will increase capacity of the storm drain system along North Thomas Street to mitigate flooding during severe storms. • Project includes installation of approximately 700 linear feet of 60 -inch diameter storm sewer and upgrades to several inlets into the system. • Existing stormwater infrastructure has needed several repairs due to deteriorating condition. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Donaldson Run New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Previous Funding Authorized but Unissued Bonds 255 875 1,125 2,255 Total Funding 255 875 1,125 0 0 0 0 0 0 0 2,255 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Summer 2024 • Construction Summer 2025 Changes from Prior CIP: Timing of expenditures has pushed out one year from previous CIP. F - 71 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 12. SPOUT RUN WATERSHED CAPACITY IMPROVEMENTS Project Highlights: • This is a watershed scale project to increase capacity of storm sewers and provide overland relief pathways to mitigate impacts of flooding (identified for Critical Vulnerability). • Current focus is on providing an overland relief flow path for larger storm events. • Land acquisition is required. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Cherrydale Waverly Hills New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 53,935 Previous Funding Authorized but Unissued Bonds 7,900 8,130 16,030 Total Funding 7,900 8,130 8,630 8,340 7,630 7,805 6,920 5,815 4,490 4,305 69,965 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Non-Personnel ($) 75 100 125 150 175 200 225 250 1,300 Total Impact 75 100 125 150 175 200 225 250 1,300 Critical Milestones: • Design Ongoing through Spring 2034 • Construction Ongoing through Spring2034 Changes from Prior CIP: Slight changes in funding levels from the previous CIP. Project Links: • Spout Run Stormwater Project Page: https://environment.arlingtonva.us/stormwater-capacity- improvements/spout-run-stormwater-improvements/ F - 72 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 13. STOHMAN'S RUN WATERSHED CAPACITY IMPROVEMENTS Project Highlights: • This project will increase capacity of the storm drainage system in Stohman's Run watershed along 39th Street North where there is no overland relief. • Project will reduce potential damage to public and private property due to repeated flooding. • Easement acquisitions required. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Stafford-Albermarle-Glebe New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 1,310 1,310 Previous Funding Authorized but Unissued Bonds 250 515 765 Total Funding 250 515 1,310 0 0 0 0 0 0 0 2,075 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Ongoing through Spring 2026 • Construction Spring 2027 Changes from Prior CIP: Timing of expenditures has pushed out two years from previous CIP. F - 73 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 14. TORREYSON RUN WATERSHED CAPACITY IMPROVEMENTS Project Highlights: • This is a watershed scale project to increase capacity of storm sewers and provide overland relief pathways to mitigate impacts of flooding (identified for Critical Vulnerability). • Initial project implementation focuses on reducing risk of flooding in Westover area, which experienced severe flooding in 2019. • Future improvements include upstream detention facility and pipe upgrades to complete the watershed scale flooding solutions. Downstream improvements near I -66 are also in planning stages. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Highland Park-Overlee Knoll Leeway Overlee Tara-Leeway Heights New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 4,860 5,340 1,635 11,835 Previous Funding Authorized but Unissued Bonds 1,725 4,140 5,865 Total Funding 1,725 4,140 4,860 5,340 1,635 0 0 0 0 0 17,700 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Design Ongoing through Spring 2028 • Construction Ongoing through Spring 2029 Changes from Prior CIP: Timing of expenditures has pushed out two years from the previous CIP. Project Links: • Torreyson Run Stormwater Improvements – Official Website of Arlington County Virginia Government (arlingtonva.us): https://www.arlingtonva.us/Government/Programs/Office- of-Sustainability-and-Environment/Stormwater/Stormwater- Capacity-Improvements/Torreyson-Run-Stormwater- Improvements F - 74 STORMWATER MANAGEMENT Capital Improvement Plan Stormwater Infrastructure/ Capacity Improvements FY 2025-2034 15. WILLIAMSBURG AT NORTH UNDERWOOD CAPACITY Project Highlights: • This project will reduce the hydraulic grade line in Williamsburg Boulevard and increase capacity of the storm drain system to address area flooding • Project entails approximately 500 linear feet of 60-inch diameter storm sewer. Associated Plan(s): Storm Water Master Plan Neighborhood(s): Arlington-East Falls Church New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 960 1,125 2,085 Previous Funding Authorized but Unissued Bonds 155 865 1,020 Total Funding 0 155 865 960 1,125 0 0 0 0 0 3,105 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 C ritical Milestones: • Design Summer 2026 • Construction Summer 2027 C hanges from Prior CIP: Timing of expenditures has pushed out three years from the previous CIP. F - 75

Source: Arlington County website. First collected Oct 27, 2026.