Complete Streets Program(PDF, 1MB)

Arlington County · Arlington County · Budget documents

Open the original document More from Arlington County

Text

Extracted automatically from the original. Tables and formatting may not survive; the original document is authoritative.

Arlington County, Virginia CIP 2025 − 2034 TRANSPORTATION: COMPLETE ARLINGTON STREETS PROGRAM 10 YEAR CATEGORY SUMMARY (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total 1. Arlington View Trail Connector 400 156 4,845 5,038 0 0 0 0 0 0 10,439 2. Army Navy Drive Complete Street 7,100 2,000 0 0 0 0 0 0 0 0 9,100 3. BIKEArlington 1,307 1,344 4,776 4,432 4,749 4,520 4,177 4,592 8,920 8,582 47,399 4. Bridge Renovation / Replacement 5,371 12,018 5,330 440 1,020 2,914 3,063 0 0 0 30,156 5. Capital Bikeshare 1,395 1,211 1,683 1,639 1,650 1,917 2,348 2,172 2,175 2,381 18,571 6. Columbia Pike Streets 40,027 3,588 532 255 0 0 0 0 0 0 44,402 7. Crystal City, Pentagon City, Potomac Yard Streets 11,128 12,230 18,846 21,423 26,086 2,685 4,118 8,932 21,137 22,975 149,560 8. Improvements Outside Major Corridors 15,349 16,069 17,787 16,748 5,974 8,682 8,754 7,494 17,637 10,474 124,968 9. Intelligent Transportation Systems 6,387 3,290 1,913 2,456 619 1,229 657 1,304 696 1,383 19,934 10. Langston Blvd Multimodal Improvements 400 200 800 2,250 2,000 4,800 12,940 15,100 9,700 3,500 51,690 11. Neighborhood Complete Streets 3,599 1,343 1,467 1,690 1,804 1,823 1,878 1,924 1,980 2,037 19,545 12. Parking Meters 206 419 298 581 328 601 1,535 1,040 152 146 5,306 13. Parking Technology 646 1,130 888 566 586 596 616 783 651 677 7,139 14. Rosslyn-Ballston Arterial Street Improvements 7,053 10,292 17,177 28,774 14,483 8,580 7,977 3,630 10,395 14,309 122,670 15. Strategic Network Analysis and Planning 498 593 610 628 647 667 687 707 729 750 6,516 16. Street Lighting 2,506 1,896 2,023 2,133 1,530 1,633 1,807 1,669 1,783 1,974 18,954 17. Street Safety Improvements (SSI) 2,502 2,283 2,348 2,418 2,492 2,569 2,644 2,724 2,808 2,892 25,680 18. Transportation Asset Management 203 209 214 221 227 234 241 247 255 263 2,314 19. Transportation Systems & Traffic Signals 6,908 3,346 4,486 4,904 3,046 2,550 2,627 2,706 2,787 2,871 36,231 20. WALKArlington 3,421 2,016 861 1,349 750 771 810 837 864 888 12,567 Total Recommendation 116,406 75,633 86,884 97,945 67,991 46,771 56,879 55,861 82,669 76,102 763,141 E - 24 CATEGORY FUNDING SOURCES (in $1,000s) FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year Total New Funding Federal Funding 1,090 2,390 3,584 2,200 800 500 1,500 1,000 0 0 13,064 State Funding 1,228 1,716 8,633 13,977 6,636 3,277 2,993 2,000 3,000 3,000 46,460 Developer Contributions 850 867 2,280 5,695 4,393 3,845 3,577 0 0 0 21,507 New Bond Issue 1,555 1,495 2,190 2,305 2,435 2,755 2,940 1,295 1,350 1,430 19,750 PAYG 1,951 2,618 3,962 4,118 3,990 4,333 5,380 5,156 4,236 4,357 40,101 Short Term Finance 0 0 0 0 0 0 0 0 0 0 0 Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0 Other Funding 0 357 357 0 0 0 0 0 0 0 714 TCF - Commercial & Industrial Tax (C&I) 2,486 8,276 14,372 24,157 14,136 10,421 8,686 4,970 6,891 11,094 105,489 TCF - NVTA Local 7,296 12,761 11,629 13,775 9,290 10,742 12,025 9,690 10,060 10,877 108,145 Regional Funding 500 500 7,400 12,400 18,300 7,300 14,440 27,620 44,920 31,940 165,320 TCF Bonds 0 0 0 0 0 0 0 0 0 0 0 Tax Increment Financing (TIF) 247 2,566 5,440 8,379 7,988 1,182 3,708 4,130 12,181 13,385 59,206 TIF Bonds 0 0 0 0 0 0 0 0 0 0 0 TCF for Operating Costs 0 0 0 0 0 0 0 0 0 0 0 Subtotal New Funding 17,203 33,546 59,847 87,006 67,968 44,355 55,249 55,861 82,638 76,083 579,756 Previously Approved Funding Authorized but Unissued Bonds 596 42 0 0 0 0 0 0 0 0 638 Issued but Unspent Bonds 1,387 617 713 0 0 0 0 0 0 0 2,717 TCF - Commercial & Industrial Tax (C&I) 53,156 10,103 6,726 4,287 0 29 89 0 31 19 74,440 TCF - NVTA Local 11,119 3,993 1,658 0 0 0 0 0 0 0 16,770 Regional Funding 16,472 6,569 5,128 5,560 0 0 0 0 0 0 33,729 Tax Increment Financing (TIF) 3,786 3,240 5,143 862 23 2,387 1,541 0 0 0 16,982 Other Previously Approved Funds 12,687 17,522 7,670 230 0 0 0 0 0 0 38,109 Subtotal Previously Approved Funding 99,203 42,086 27,038 10,939 23 2,416 1,630 0 31 19 183,385 Total Funding Sources 116,406 75,632 86,885 97,945 67,991 46,771 56,879 55,861 82,669 76,102 763,141 E - 25 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 1. ARLINGTON VIEW TRAIL CONNECTOR Project Highlights: • The project will provide a new connection for bicycle and pedestrian access between the Arlington View neighborhood and the Army Navy Country Club driveway connection to Army Navy Drive. • Access will be restricted to bicycles and pedestrians. • The Use Permit was approved in June 2010 and the public use and access easement was recorded in March 2012. The easement may terminate automatically if construction contracts are not awarded within 20 years of that date. Associated Plan(s): Master Transportation Plan Neighborhood(s): Arlington Ridge Arlington View New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total TCF - Commercial & Industrial Tax (C&I) 109 2,423 2,519 5,051 TCF - NVTA Local 108 2,422 2,519 5,049 Previous Funding TCF - Commercial & Industrial Tax (C&I) 91 78 169 TCF - NVTA Local 92 78 170 Total Funding 400 156 4,845 5,038 0 0 0 0 0 0 10,439 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Cr itical Milestones: • Planning and Engineering Winter 2019 - Spring 2026 • Construction Fall 2026 - Summer 2028 Ch anges from Prior CIP: The County selected a hybrid stairs -runnel design approach, which resulted in increased project costs compared to the previous CIP. The project was named "Army Navy Country Club Trail Connector" in the FY 2023 - FY 2032 CIP. Pro ject Links: • Arlington View Trail Connector: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Army-Navy-Country-Club- Trail-Connector E - 26 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 2. ARMY NAVY DRIVE COMPLETE STREET Project Highlights: • The project rebuilds Army Navy Drive as a multimodal complete street featuring enhanced bicycle, transit, and pedestrian facilities and street trees. • The reconstruction will provide a physically separated two-way protected bicycle facility along the south side of Army Navy Drive, in addition to shorter and safer pedestrian crossings, and will accommodate future dedicated transit lanes. • The project will improve local connections between the Pentagon and Crystal City and Pentagon City. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): Arlington Ridge Aurora Highlands Crystal City Pentagon City Funding Notes: Other Previously Approved Funds are developer contributions from 400 Army Navy Drive site plan (#2). Regional funding is from the Northern Virginia Transportation Authority (NVTA). New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Tax Increment Financing (TIF) 886 886 Previous Funding Regional Funding 7,100 527 7,627 Other Previously Approved Funds 587 587 Total Funding 7,100 2,000 0 0 0 0 0 0 0 0 9,100 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Cr itical Milestones: • Construction Fall 2022 – Fall 2025 Ch anges from Prior CIP: Project is actively in construction. Total project cost is less than the previous CIP based on awarded contract. Pro ject Links: • Army Navy Complete Streets: https://projects.arlingtonva.us/projects/army-navy-drive- complete-street/ E - 27 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 3. BIKEARLINGTON Project Highlights: • The program aims to improve conditions for bicycling by constructing new trails, renovating existing ones, and adding bike lanes on streets. • BIKEArlington also makes provisions for bicycle parking and wayfinding signage, deploys/maintains counting technology, and undertakes bike facility spot improvements. • The largest project is the Arlington Memorial Trail that will connect Memorial Avenue to Columbia Pike adjacent to Arlington National Cemetery’s perimeter wall. This project is currently in the planning stage ahead of National Environmental Policy Act (NEPA) work. • Other active projects include various Arlington Boulevard Trail enhancements and development of Custis Trail improvements. Some of these projects are not fully funded in this CIP as the projects still need to be scoped. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds are PAYG. Regional funding ( from the NVTA) is anticipated for construction of the Arlington Memorial Trail. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Federal Funding 290 230 115 200 800 500 1,500 1,000 4,635 State Funding 1,000 1,070 1,102 828 4,000 PAYG 50 183 229 204 229 206 212 230 238 244 2,025 TCF - Commercial & Industrial Tax (C&I) 72 1,133 1,168 1,727 297 334 1,491 1,488 7,710 TCF - NVTA Local 82 288 336 138 1,450 606 1,275 1,025 5,200 Regional Funding 1,000 4,000 4,000 9,000 Tax Increment Financing (TIF) 653 893 1,003 3,191 2,850 8,590 Previous Funding TCF - Commercial & Industrial Tax (C&I) 334 520 1,946 1,687 4,487 TCF - NVTA Local 528 122 1,078 1,728 Other Previously Approved Funds 23 1 24 Total Funding 1,307 1,344 4,776 4,432 4,749 4,520 4,177 4,592 8,920 8,582 47,399 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 E - 28 Critical Milestones: • Custis Trail rehabilitation scoping and preliminary design Summer 2025 - Spring 2026 • Arlington Boulevard Trail Enhancements - Fairfax Drive design Summer 2023 - Spring 2026 • Arlington Boulevard Trail south side improvements - Glebe Road to George Mason Drive design Summer 2024 - Fall 2026 Changes from Prior CIP: This CIP includes a new project on Arlington Boulevard from Jackson Street to George Mason Drive, resulting from the Arlington Boulevard Trail study. Project Links: • Arlington Memorial Trail: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Arlington-Memorial-Trail • Arlington Boulevard Trail Study: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Arlington-Boulevard-Trail- Study • Arlington Boulevard Trail - Granada Street to Edison Street: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Arlington-Boulevard-Trail- Improvements-%E2%80%93-N.-Granada-Street-to-N.- Edison-Street • Custis Trail Needs Assessment: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Custis-Trail-Needs- Assessment E - 29 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 4. BRIDGE RENOVATION / REPLACEMENT Project Highlights: • This program rehabilitates, upgrades, or replaces the 36 bridges owned by Arlington County. • Bridge reconstruction may include upgrades to sidewalks, bicycle facilities, transit stops, lighting, and facades. • Arlington Ridge Road bridge construction is expected to start in FY 2025; the City of Alexandria will pay 50 percent of the cost not covered by grant funding. • Following Arlington Ridge Road bridge replacement in FY 2027 all bridges in Arlington County will be rated Satisfactory to Good. • Shirlington Road vehicular bridge over Four Mile Run was recently upgraded with widened sidewalks on the west side of the bridge in FY 2023. Construction is currently underway for an additional separate pedestrian bridge, west of the vehicular bridge, which will add a two -way pedestrian/bicycle facility. Associated Plan(s): Master Transportation Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds include $2,845,000 from the City of Alexandria, $10,601,000 in state funding, $6,346,000 in Federal funding, and $941,000 in PAYG. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total State Funding 400 1,449 1,493 3,342 New Bond Issue 640 440 620 1,465 1,570 4,735 Previous Funding Issued but Unspent Bonds 574 697 1,271 TCF - Commercial & Industrial Tax (C&I) 75 75 Other Previously Approved Funds 5,296 11,444 3,993 20,733 Total Funding 5,371 12,018 5,330 440 1,020 2,914 3,063 0 0 0 30,156 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Arlington Ridge Road Bridge Design Design Summer 2022- Summer 2024 • Arlington Ridge Road Bridge Construction Winter 2024 (2Q FY25) - Spring 2026 • Shirlington Road Bridge Construction Summer 2023 - Fall 2024 Changes from Prior CIP: No significant changes from the previous CIP. Project Links: • Shirlington Road Bridge: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Shirlington-Road-Bridge- Maintenance-and-New-Pedestrian-Bicycle-Bridge • Arlington Ridge Road Bridge replacement: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Arlington-Ridge- RoadMount-Vernon-Avenue-Bridge E - 30 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 5. CAPITAL BIKESHARE Project Highlights: • This program funds the expansion of the Capital Bikeshare system in Arlington, including purchase of additional bikes, e-bikes, and stations. • The program also funds the replacement of bikes that have reached the end of their useful life or are lost to theft as well as decommissioning and replacement of 10-year-old stations to maintain a state of good repair. • As of March 2024, Arlington has 110 stations and 800 bicycles. Associated Plan(s): Master Transportation Plan Neighborhood(s): VARIOUS Funding Notes: Federal funding in FY 2027 is from Congestion Mitigation & Air Quality (CMAQ). Developer contributions include $35k in FY 2025 from the Pen Place site plan (#105) and $35k in FY 2026 from the Key Bridge Marriott site plan (#53). New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Federal Funding 469 469 Developer Contributions 35 35 70 TCF - Commercial & Industrial Tax (C&I) 76 803 874 825 850 886 900 941 956 1,000 8,111 TCF - NVTA Local 591 373 340 814 800 1,031 1,448 1,231 1,219 1,381 9,228 Previous Funding TCF - Commercial & Industrial Tax (C&I) 693 693 Total Funding 1,395 1,211 1,683 1,639 1,650 1,917 2,348 2,172 2,175 2,381 18,571 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Non-Personnel ($) 328 440 545 626 708 793 877 972 1,052 1,052 7,393 Total Impact 328 440 545 626 708 793 877 972 1,052 1,052 7,393 Changes from Prior CIP: Due to the popularity of the dockless e -bikes, the number of expansion stations has decreased from an average of four per year to one and the number of e-bikes has increased from 150 per year to 200. As the e -bikes don't need to be docked at a station, their start and end points are limitless. E - 31 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 6. COLUMBIA PIKE STREETS Project Highlights: • The Columbia Pike Multimodal Streets Project will improve transportation options for pedestrians, cyclists, motorists, and transit riders along the three plus mile Columbia Pike corridor and will be completed in 2025. • The street will be reconstructed in multiple segments with wider sidewalks, improved intersection configurations, improved lighting, additional street trees, new pedestrian crossings, decreased pedestrian crossing distances where possible, and transit platforms with near-level boarding. • This program includes funding through FY 2027 to provide parallel bike improvements to the Columbia Pike Bike Boulevards along 9th Street South and 12th Street South. • A federally funded companion project that realigns the far east end of Columbia Pike to provide more burial space for Arlington National Cemetery is currently under construction and estimated to complete in late 2025. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): Alcova Heights Arlington Heights Arlington View Barcroft Columbia Forest Columbia Heights Columbia Heights West Douglas Park Foxcroft Heights Penrose New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total TCF - Commercial & Industrial Tax (C&I) 279 159 438 Previous Funding TCF - Commercial & Industrial Tax (C&I) 40,027 3,309 373 255 43,964 Total Funding 40,027 3,588 532 255 0 0 0 0 0 0 44,402 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Construction Start (Seg. F, Oakland to Wakefield Summer 2022 • Construction Start (Seg. A, Joyce to Orme) Spring 2023 • Construction Start (Seg. D, Courthouse to Garfield) Fall 2023 • Construction Start (Seg C, Quinn to Courthouse) Spring 2024 • All Construction Complete Winter 2025 (2Q FY25) Changes from Prior CIP: New to this CIP is the Columbia Pike Bike Boulevard study which will kick off in Summer 2024 to identify near to long-term improvements to the 9th and 12th Street Bike Boulevards. The near-term improvements will be developed into a project in Fall 2025. Project Links: • Columbia Pike Multimodal Street Improvements : https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Columbia-Pike-Multimodal- Street-Improvements • S. Oakland St to S. Wakefield St (Seg. F): https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Columbia-Pike-Multimodal- Street-Improvements-S.-Wakefield-St-to-S.-Oakland-St • Garfield to Quinn St (Seg. C&D): https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Columbia-Pike-Garfield- Street-to-Quinn-Street E - 32 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 7. CRYSTAL CITY, PENTAGON CITY, POTOMAC YARD STREETS Project Highlights: • This program supports ongoing major redevelopment activity in Pentagon City, Crystal City, and Potomac Yard by improving connectivity, accessibility, and safety for all modes of travel. The program implements County investments that complement redevelopment. • The largest project in the program is the Crystal City to Washington National Airport Multimodal Connection (CC2DCA) that will provide a pedestrian connection from Crystal City to National Airport. • Other projects currently in or scheduled to begin construction in the next year include improvements along South Clark- Bell Street/15th Street South and South Eads Street, as well as protected bike lane improvements along Army Navy Drive from Joyce Street to Memorial Drive. Associated Plan(s): Crystal City Sector Plan Master Transportation Plan Pentagon City Sector Plan Vision Zero Action Plan Neighborhood(s): Aurora Highlands Crystal City Pentagon City Potomac Yard Funding Notes: Regional funding is from the NVTA. Other Previously Approved Funds include $3,601,000 in federal grants and $900,000 state grants for CC2DCA and $90,000 in developer contributions. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Regional Funding 500 500 7,400 12,400 18,300 6,050 12,400 12,700 70,250 Tax Increment Financing (TIF) 47 1,474 5,228 8,161 7,763 298 2,577 2,882 8,737 10,275 47,442 Previous Funding TCF - Commercial & Industrial Tax (C&I) 3,175 2,860 154 6,189 Regional Funding 2,000 2,576 4,576 Tax Increment Financing (TIF) 3,316 3,240 5,143 862 23 2,387 1,541 16,512 Other Previously Approved Funds 2,090 1,580 921 4,591 Total Funding 11,128 12,230 18,846 21,423 26,086 2,685 4,118 8,932 21,137 22,975 149,560 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • 15th Street South/South Clark-Bell Street Realignment construction Fall 2024 - Winter 2027 (Q3 FY 2027) • South Eads Street from Army Navy Drive to 12th Street South construction Summer 2024 - Winter 2026 (Q3 FY 2026, with Parks project) • South Eads Street from 12th Street South to 15th Street South construction Summer 2024 - Fall 2025 Project Links: • 15th Street South/South Clark-Bell Street Realignment: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/15th-Street-Clark-Bell- Street-Realignment • Crystal City to Washington National Airport Multimodal Connection (CC2DCA): https://www.arlingtonva.us/Government/Projects/Project- E - 33 • Army Navy Drive Protected Bike Lane Missing Link construction Winter 2025 - Spring 2026 • CC2DCA Multimodal Connection 30 percent design completion Spring 2025 Changes from Prior CIP: Construction estimates for CC2DCA Multimodal Connection have changed upon identification and approval of the preferred alternative. Types/Transportation-Projects/CC2DCA-Multimodal- Connection-Study • South Eads Street Complete Street: 12th Street South to Army Navy Drive: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/South-Eads-Street- Complete-Street • South Eads Street Complete Street: 12th Street South to 15th Street South: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/South-Eads-Street- Complete-Street-12th-Street-to-15th-Street • Army Navy Drive Protected Bike Lane (PBL) Missing Link: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Army-Navy-Drive-PBL- Missing-Link • Long Bridge Drive Multimodal Connection: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Long-Bridge-Drive- Multimodal-Connection E - 34 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 8. IMPROVEMENTS OUTSIDE MAJOR CORRIDORS Project Highlights: • The program includes multimodal accessibility and safety enhancements to improve local pedestrian, bicycle, and transit connectivity along well- traveled routes outside primary business districts. • Projects within this program are located along arterial streets such as, but not limited to, Arlington Ridge Road, Glebe Road, Pershing Drive, Shirlington Road, Walter Reed Drive, and Military Road. • The program is advancing preliminary design work for safety improvements to the Washington Boulevard and Arlington Boulevard Interchange in cooperation with Virginia Department of Transportation. • This program includes funding for the update to the Master Transportation Plan, an element of the County’s Comprehensive Plan. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds are $295,000 in PAYG. FY 2025 funding increased as part of Adopted CIP for Carlin Springs planning. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Federal Funding 800 2,160 3,000 2,000 7,960 State Funding 443 900 5,354 6,713 3,708 500 1,500 1,500 20,618 PAYG 500 500 TCF - Commercial & Industrial Tax (C&I) 913 3,589 6,040 3,895 760 524 747 1,077 1,576 1,577 20,698 TCF - NVTA Local 300 5,586 3,243 4,140 1,506 3,158 3,007 1,077 2,161 2,317 26,495 Regional Funding 5,000 5,000 4,840 12,400 5,080 32,320 Previous Funding Issued but Unspent Bonds 552 552 TCF - Commercial & Industrial Tax (C&I) 6,174 203 6,377 TCF - NVTA Local 5,272 3,631 150 9,053 Tax Increment Financing (TIF) 100 100 Other Previously Approved Funds 295 295 Total Funding 15,349 16,069 17,787 16,748 5,974 8,682 8,754 7,494 17,637 10,474 124,968 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 E - 35 Critical Milestones: • Military & Nelly Custis construction start Fall 2024 • South Carlin Springs Road Interim Pedestrian Improvements 2025 Changes from Prior CIP: New projects in this CIP include: (1) Safety improvements at the intersection of Lorcom Lane and Vacation Lane West with the installation of a traffic signal, (2) Interim pedestrian improvements to S. Carlin Springs Road, and (3) Pedestrian improvements to the intersection of Wilson Boulevard and N. Livingston Street. The CIP also advances the improvements outlined in the George Mason Drive Multimodal Study. Project Links: • Pershing Drive Complete Street Improvements: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Pershing-Drive-Complete- Street-Improvements • South Walter Reed Drive Complete Streets Improvements: 5th Street S to Columbia Pike: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/South-Walter-Reed-Drive- Complete-Street • Military Road Safety Improvements: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Military-Road-Safety- Improvements E - 36 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 9. INTELLIGENT TRANSPORTATION SYSTEMS Project Highlights: • This program leverages technology to improve the efficiency of transportation systems and operations throughout the County. • Includes equipment at signals as well as stand -alone installations such as beacons and sensors. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS Funding Notes: Regional funding is from the NVTA and is for ITS improvements along major corridors. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total TCF - Commercial & Industrial Tax (C&I) 249 727 282 601 299 638 316 677 335 718 4,842 TCF - NVTA Local 365 533 269 558 320 591 341 627 361 665 4,630 Previous Funding TCF - Commercial & Industrial Tax (C&I) 181 122 303 TCF - NVTA Local 112 52 33 197 Regional Funding 5,480 1,855 1,330 1,297 9,962 Total Funding 6,387 3,289 1,914 2,456 619 1,229 657 1,304 696 1,383 19,934 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • North Glebe Road ITS Corridor improvements expected completion Summer 2025 • Langston Boulevard ITS Corridor improvements expected completion Summer 2026 • Washington Boulevard ITS Corridor Improvements Phase 1 expected completion Summer 2025 Changes from Prior CIP: The ITS corridor projects are delayed which shifts expenses from FY 2023 and FY 2024 into the FY 2025 – FY 2034 CIP. Project Links: • https://projects.arlingtonva.us/projects/intelligent- transportation-systems/ E - 37 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 10. LANGSTON BLVD MULTIMODAL IMPROVEMENTS Project Highlights: • This program will begin to implement the complete streets improvements recommended by Plan Langston Boulevard. • The program includes funding for two studies and anticipated construction funding. The first study will analyze major intersections identified for further analysis in Plan Langston Boulevard, particularly where private development is anticipated in the near-term. The second study will conduct a multimodal corridor assessment of the east end of Langston Boulevard from I -66 to Key Bridge and outlined in Plan Langston Boulevard. Associated Plan(s): East Falls Church Area Plan Lee Highway Cherrydale Revitalization Plan Master Transportation Plan Plan Langston Boulevard Neighborhood(s): Arlington-East Falls Church Cherrydale Colonial Village Donaldson Run Glebewood John M. Langston Leeway Overlee Lyon Village Maywood North Highlands North Rosslyn Old Dominion Waverly Hills Yorktown Funding Notes: State and Regional funding levels represent future requests to implement the outcomes of the two studies. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total State Funding 500 1,000 1,000 1,500 1,500 1,500 1,500 8,500 TCF - Commercial & Industrial Tax (C&I) 300 150 700 1,650 900 1,400 1,500 1,400 1,500 1,500 11,000 TCF - NVTA Local 50 50 100 100 100 100 500 100 500 500 2,100 Regional Funding 2,300 9,440 12,100 6,200 30,040 Previous Funding TCF - Commercial & Industrial Tax (C&I) 50 50 Total Funding 400 200 800 2,250 2,000 4,800 12,940 15,100 9,700 3,500 51,690 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Develop Major Intersection analysis Summer 2024 - Winter 2025 (Q2 FY26) • Develop Langston Blvd East End study Fall 2026 - Spring 2028 Changes from Prior CIP: Forecast has increased following the adoption of Plan Langston Boulevard which has helped to define expected scope of program. E - 38 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 11. NEIGHBORHOOD COMPLETE STREETS Project Highlights: • The purpose of this program is to improve walking connectivity, upgrade street crossings, and modify incomplete streets to improve safety. • Complete Streets are streets designed and operated to allow safe and comfortable use by all users. This program implements improvements on neighborhood streets to achieve this goal where feasible. The program also tests new design concepts in locations that are constrained, such as the "Shared Street Pilot". • Locations are selected by the Neighborhood Complete Streets Commission following a robust evaluation process against a set of ranking guidelines accepted by the County Board. Capital projects are developed at these locations and recommended to the County Board on an annual basis. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds are PAYG. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 420 435 450 670 670 670 670 670 670 670 5,995 PAYG 82 101 102 103 104 105 106 107 810 TCF - NVTA Local 1,087 808 916 919 1,032 1,050 1,104 1,149 1,204 1,260 10,529 Previous Funding Authorized but Unissued Bonds 399 399 TCF - NVTA Local 1,593 1,593 Other Previously Approved Funds 100 100 19 219 Total Funding 3,599 1,343 1,467 1,690 1,804 1,823 1,878 1,924 1,980 2,037 19,545 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • 3 new “Shared Streets” Pilot projects implemented Summer 2024 - Summer 2025 • South Irving Street sidewalk construction start Summer 2024 • South Irving streetlight relocation construction start Spring 2025 • 28th Street South construction start Fall 2024 • 14th Street North construction start Summer 2025 Project Links: • Neighborhood Complete Streets Projects: https://www.arlingtonva.us/Government/Projects/Programs/Neighborhood- Complete-Streets-Program/NCS-Projects • Shared Street Pilot: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/NCS-Shared-Street-Pilot Changes from Prior CIP: The program approves new projects on a yearly basis and new projects were added since the previous CIP. E - 39 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 12. PARKING METERS Project Highlights: • The annual capital cost schedule provides for replacement of meters at the end of their useful life, assuming a ten-year life span. • It supports analysis of parking meter data and research into and deployment of new technology to allow the County to manage public curb space more efficiently or improve customer convenience. • Replacement strategies, such as replacing major meter components, are applied to extend the life of equipment. • Maintaining parking meters in a state of good repair ensures steady collection of revenue, consistent operating and maintenance costs, and quality customer experience. Associated Plan(s): Master Transportation Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds include $53,000 in Developer Contributions and $174,000 in PAYG. The combination of carryover into FY 2024 and lower replacement needs in the early years means prior approved funds help cover program needs and lowers required new funds in FY 2025 and FY 2026. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 181 298 581 328 601 1,535 1,040 152 146 4,862 Previous Funding Authorized but Unissued Bonds 153 42 195 Issued but Unspent Bonds 22 22 Other Previously Approved Funds 53 174 227 Total Funding 206 419 298 581 328 601 1,535 1,040 152 146 5,306 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: The FY 2025 - FY 2034 CIP reverts back to an annual capital cost schedule which best reflects staff's estimate of expenses each year based on the replacement cycle (vs. the prior CIP in which the costs had been "smoothed" out across the ten years). This shift to a more accurate depiction of costs by year has dramatically reduced the budget required for FY 2025. Furthermore, due to the fact that so many replacements were required for modem upgrades in a short period between FY 2021 and FY 2022, this acceleration "brought forward" replacement costs into this ten- year CIP period, raising the total cost of this ten-year CIP vs. that of the previous CIP (it also explains the cost jump in FY 2031 and FY 2032). To defray this cost increase, this update continues to assume meter door replacements rather than full meter replacements through FY 2027 and splitting the replacements half and half between full meter and door replacements from FY 2027 through FY 2034. E - 40 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 13. PARKING TECHNOLOGY Project Highlights: • This program undertakes upgrades to technology systems that support the County’s parking policies. • Investments in hardware and software will improve performance management of metered parking spaces and support demand-based parking meter pricing using in-pavement sensor equipment. • Technology upgrades will allow the County to maintain and improve residential permit parking (RPP) administration and enable enforcement via license plate recognition (LPR) technology. • Developer-funded studies are separately tracked and managed. Associated Plan(s): Master Transportation Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds include $1,456,000 in State funds (Innovation and Technology Transportation Fund, or ITTF grant), $30,000 in developer funds and $332,000 in PAYG. The ITTF grant is funding the demand-based parking-meter pricing pilot. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Developer Contributions 30 15 45 PAYG 801 566 586 596 616 783 651 677 5,276 Previous Funding Other Previously Approved Funds 616 1,115 87 1,818 Total Funding 646 1,130 888 566 586 596 616 783 651 677 7,139 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • Demand-based parking pricing pilot implementation 2023 to 2026 Changes from Prior CIP: Staff has updated its cost estimates and timeline for the upgrade to the RPP program's administrative software based on a contract with a vendor and internal staff discussions. Project Links: • Report for Dec. 15, 2020 Board Meeting Re: Performance Parking E - 41 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 14. ROSSLYN-BALLSTON ARTERIAL STREET IMPROVEMENTS Project Highlights: • The program provides significant street and sidewalk safety improvements along Clarendon Boulevard, Wilson Boulevard, Fairfax Drive, Fort Myer Drive, and other nearby intersections. • Improvements include road reconfigurations, new crosswalks, new signage and striping, bike lanes, underground utilities, new streetlights, updated traffic signals, street trees, and updated bus shelters. • Active projects include Wilson Boulevard from 10th Street North to North Kenmore Street, and Meade Street multimodal improvements. • The largest project in the portfolio is Fort Myer Drive. The scope includes removal of the tunnel followed by two- way conversion and addition of a cycle track. This project is dependent on a series of discrete capital projects reaching completion before the two-way conversion can be completed. There are also developer contributions funding the project, the receipt of which is dependent on redevelopment (outlined in Funding Notes below). Associated Plan(s): Ballston Sector Plan Clarendon Sector Plan Court House Sector Plan Master Transportation Plan Vision Zero Action Plan Neighborhood(s): Ashton Heights Ballston-Virginia Square Bluemont Clarendon-Courthouse Colonial Village Lyon Village North Rosslyn Radnor-Ft. Meyer Heights Funding Notes: Projects are primarily funded with TCF-C&I but also benefit from developer contributions, including contributions into the utility undergrounding fund. Funding from developer contributions includes approximately: $7,500,000 from the Rosslyn Gat eway site plan (#419), $5,000,000 from the Ames Center site plan (#1), $4,500,000 from the Holiday Inn site plan (#79), and $5,000,000 from the 1401 Wilson Boulevard site plan (#429). Other Previously Approved Funds reflect the remaining developer contribution bala nce ($206,000) from the Red Top site plan (#438) and the utility undergrounding fund ($4,638,000). Regional Funding is from the NVTA. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total State Funding 785 816 2,279 5,694 426 10,000 Developer Contributions 785 817 2,280 5,695 4,393 3,845 3,577 21,392 Other Funding 357 357 714 TCF - Commercial & Industrial Tax (C&I) 510 2,348 2,106 10,916 9,664 4,735 4,400 475 4,149 39,303 Regional Funding 3,630 9,920 10,160 23,710 Previous Funding TCF - Commercial & Industrial Tax (C&I) 2,071 2,941 4,155 1,976 11,143 Regional Funding 1,892 1,611 3,798 4,263 11,564 Other Previously Approved Funds 1,010 1,402 2,202 230 4,844 Total Funding 7,053 10,292 17,177 28,774 14,483 8,580 7,977 3,630 10,395 14,309 122,670 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: Project Links: E - 42 • Wilson Boulevard - 10th Street to North Kenmore Street construction Fall 2024 - Summer 2027 • Wilson Boulevard and North Rhodes Street Intersection Safety Project Fall 2023 - Spring 2026 Changes from Prior CIP: New projects in this CIP include Wilson Boulevard and North Rhodes Street intersection improvements and Clarendon Boulevard and North Oak Street streetscape improvements. • Wilson Boulevard Streetscape Improvements: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Wilson-Boulevard- Streetscape-Improvements-Clarendon-Area • Core of Rosslyn Transportation Study: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Core-of-Rosslyn- Transportation-Study E - 43 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 15. STRATEGIC NETWORK ANALYSIS AND PLANNING Project Highlights: • This program supports data analysis and management activities, which guide decision -making to implement the Vision Zero Action Plan and other transportation operations programs. The program also supports transportation planning, studies, community engageme nt, and performance measurement with a focus on safety. • Progress reporting is provided through the biannual Vision Zero public reporting cycle, and a month- long community engagement is hosted annually to review progress. • Funding for these activities is critical to programming transparent, equitable, and data -supported projects and services for the community. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total TCF - NVTA Local 478 593 610 628 647 667 687 707 729 750 6,496 Previous Funding TCF - NVTA Local 20 20 Total Funding 498 593 610 628 647 667 687 707 729 750 6,516 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No significant change from the previous CIP. Project Links: • https://www.arlingtonva.us/files/sharedassets/public/v/1/transportation/documents/action - plan_revised_draft_v3.pdf E - 44 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 16. STREET LIGHTING Project Highlights: • This program implements projects to achieve the goals stated in the Streetlight Management Plan (SMP) that include enhancing public safety and increasing the operational service level of streetlights throughout the County. • Major projects install lights where lighting does not exist or is insufficient and are prioritized for high activity areas or areas with safety considerations. • This program also includes the conversion of Dominion Energy (DE) owned lights to LED technology, which reduces electricity consumption and increases service reliability. Associated Plan(s): Community Energy Plan Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 770 610 640 410 85 115 185 90 125 190 3,220 PAYG 989 1,250 1,324 1,364 1,405 1,447 1,490 1,535 1,583 12,387 TCF - Commercial & Industrial Tax (C&I) 30 81 84 86 89 92 182 644 Previous Funding Issued but Unspent Bonds 30 21 51 TCF - Commercial & Industrial Tax (C&I) 270 70 98 369 29 89 31 19 975 Tax Increment Financing (TIF) 370 370 Other Previously Approved Funds 1,066 206 35 1,307 Total Funding 2,506 1,896 2,023 2,133 1,530 1,633 1,807 1,669 1,783 1,974 18,954 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Critical Milestones: • LED Retrofit of DE lights expected to be completed. Winter 2025 (Q3 FY26) Changes from Prior CIP: No significant change from the previous CIP. Project Links: • https://www.arlingtonva.us/Government/Programs/Transporta tion/Streets/Streetlights/Streetlight-Project E - 45 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 17. STREET SAFETY IMPROVEMENTS (SSI) Project Highlights: • The Street Safety Improvements (SSI) Program funds capital improvements identified through the County’s Vision Zero Program which the County Board adopted in July 2019. • SSI supports safety projects for pedestrians, bicyclists, transit riders, or motorists as determined through a comprehensive crash analysis. Examples include signage, pavement markings, minor changes to curb, and deployment of Rectangular Rapid Flashing Beacons (RRFBs). • Projects that are initiated by Vision Zero Report -A-Problem (R-A-P) and the Customer Care Communication (C3) platform may be implemented through this program. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 165 240 245 250 260 270 275 285 295 305 2,590 PAYG 1,378 1,004 1,034 1,066 1,097 1,130 1,165 1,199 1,235 1,271 11,579 TCF - Commercial & Industrial Tax (C&I) 279 328 337 348 358 369 380 391 403 415 3,608 TCF - NVTA Local 636 711 732 754 777 800 824 849 875 901 7,859 Previous Funding Authorized but Unissued Bonds 44 44 Total Funding 2,502 2,283 2,348 2,418 2,492 2,569 2,644 2,724 2,808 2,892 25,680 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: Funding for this program has increased significantly compared to the previous CIP as a result of program acceleration to meet community and Board expectations. Project Links: • https://projects.arlingtonva.us/projects/vision-zero-pilot-projects/ • https://www.arlingtonva.us/files/sharedassets/public/v/1/transportation/documents/action - plan_revised_draft_v3.pdf • https://www.arlingtonva.us/Government/Projects/Project-Types/Transportation- Projects/Quick-Build-Safety-Projects • https://www.arlingtonva.us/Government/Programs/Transportation/Vision-Zero/High- Injury-Network-Corridor-Safety-Audits • https://www.arlingtonva.us/Government/Programs/Transportation/Vision-Zero/Safety- Before-After-Studies • https://www.arlingtonva.us/Government/Programs/Transportation/Vision-Zero/Systemic- Safety-Improvements E - 46 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 18. TRANSPORTATION ASSET MANAGEMENT Project Highlights: • The program provides systems to maintain real -time transportation assets, manage transportation data, and develop a central traffic database. • Program uses Cartegraph as the asset management and inventory platform and continues to integrate additional features available from the vendor. • Includes tools to establish an inventory control system and workorder system with asset and warehouse inventory so that the assets are managed. Associated Plan(s): Master Transportation Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds are PAYG. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total PAYG 23 157 161 166 171 176 181 186 192 198 1,611 TCF - Commercial & Industrial Tax (C&I) 50 52 53 55 56 58 60 61 63 65 573 Previous Funding Other Previously Approved Funds 130 130 Total Funding 203 209 214 221 227 234 241 247 255 263 2,314 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 Changes from Prior CIP: No significant change from the previous CIP E - 47 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 19. TRANSPORTATION SYSTEMS & TRAFFIC SIGNALS Project Highlights: • This program focuses on traffic signal rebuilds, infrastructure replacement, and signal optimization. • Projects improve accessibility, safety, efficiency, and remote monitoring capabilities at signalized intersections. • Signal optimization is an ongoing program that operates on a three-year cycle to improve safety and reduce delays along major corridors. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds include $2,380,000 in State Funding, $150,000 of Developer Contributions and $510,000 of PAYG. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 315 570 885 TCF - Commercial & Industrial Tax (C&I) 1,326 2,185 3,511 TCF - NVTA Local 2,581 2,433 2,334 2,404 2,476 2,550 2,627 2,706 2,787 2,871 25,769 Previous Funding Issued but Unspent Bonds 805 16 821 TCF - NVTA Local 1,808 397 2,205 Other Previously Approved Funds 1,714 913 413 3,040 Total Funding 6,908 3,346 4,486 4,904 3,046 2,550 2,627 2,706 2,787 2,871 36,231 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Non-Personnel ($) 33 44 55 66 77 88 99 110 121 132 825 Total Impact 33 44 55 66 77 88 99 110 121 132 825 Critical Milestones: • Typical upgrade projects include 12 months design, 4 months procurement, and 12 months construction Changes from Prior CIP: No significant changes from the previous CIP. Project Links: • Traffic Signal Upgrades: https://www.arlingtonva.us/Government/Projects/Project- Types/Uncategorised/Traffic-Signal-Upgrades E - 48 TRANSPORTATION Capital Improvement Plan Complete Arlington Streets FY 2025-2034 20. WALKARLINGTON Project Highlights: • The WALKArlington program makes enhancements to Arlington's sidewalk and pedestrian infrastructure in coordination with other programs in the CIP. This includes completion of the planned walkway network, making it fully accessible for all users and improving pedestrian safety. • The program focuses on arterial street sidewalk upgrades, transit-access improvements, ancillary sidewalk projects to support Arlington Public Schools safe routes to schools, and stand-alone safety and accessibility upgrades. Associated Plan(s): Master Transportation Plan Vision Zero Action Plan Neighborhood(s): VARIOUS Funding Notes: Other Previously Approved Funds are PAYG. New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total New Bond Issue 200 210 215 220 230 235 240 250 260 265 2,325 PAYG 104 107 110 113 116 120 123 127 131 1,051 TCF - NVTA Local 1,018 1,386 327 801 182 189 212 219 224 232 4,790 Tax Increment Financing (TIF) 200 206 212 218 225 231 238 245 253 260 2,288 Previous Funding TCF - Commercial & Industrial Tax (C&I) 15 15 TCF - NVTA Local 1,694 110 1,804 Other Previously Approved Funds 294 294 Total Funding 3,421 2,016 861 1,349 750 771 810 837 864 888 12,567 Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total Total Impact 0 0 0 0 0 0 0 0 0 0 0 E - 49 Critical Milestones: • N. Ohio Street safety improvements construction Summer 2024 - Spring 2025 • Rosslyn-Ballston corridor accessibility improvements construction complete Summer 2024 • N. Park Drive and N. George Mason Drive signal improvements construction Summer 2024 - Winter 2024 C hanges from Prior CIP: New projects in this CIP include N. Park Drive and N. George Mason Drive signal improvements and John Marshall and Little Falls Drive Intersection Improvements. Project Links: • N. Ohio Street at 12th Road N. and 14th Street N. Improvements: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Ohio-Street-Safety- Improvements • N. Park Drive & N. George Mason Drive Intersection Improvements: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Lorcom-Lane-Safety- Project/N.-Park-Drive-and-N.-George-Mason-Drive- Intersection-Improvements • Lorcom Lane Safety Project: https://www.arlingtonva.us/Government/Projects/Project- Types/Transportation-Projects/Lorcom-Lane-Safety-Project E - 50

Source: Arlington County website. First collected Oct 27, 2026.