Arlington County, Virginia CIP
2025 − 2034
TRANSPORTATION: ARLINGTON TRANSIT PROGRAM
10 YEAR CATEGORY SUMMARY (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
1. Army Navy Drive Transit
Center
150 0 0 0 34 35 0 0 0 0 219
2. ART Fare Collection System 244 802 0 0 0 0 0 0 0 0 1,046
3. ART Fleet & Equipment
Replacement
10,637 10,051 6,050 0 10,429 0 11,916 0 0 18,601 67,684
4. ART Fleet Transition to
ZEB
900 930 37,920 1,103 30,542 5,474 21,274 3,764 5,221 27,048 134,176
5. ART Operations and
Maintenance Facility
27,404 0 0 0 0 0 0 0 0 0 27,404
6. Ballston-MU Metrorail
Station West Entrance
950 14,282 69,667 54,913 37,201 0 0 0 0 0 177,013
7. Bus Bay Expansion-East
Falls Church Metro Station
8,190 394 0 0 0 0 0 0 0 0 8,584
8. Bus Stop Accessibility
Improvements
926 883 921 954 985 1,020 1,056 1,099 1,133 1,182 10,159
9. Bus Stop and Shelter
Program
627 645 556 522 538 560 603 645 664 687 6,047
10. Court House Metrorail
Station New Elevators
206 64 3,730 2,933 12,265 24,425 13,848 0 0 0 57,471
11. Crystal City - Potomac Yard
Transitway Upkeep
489 0 0 0 0 0 0 0 0 0 489
12. Crystal City Metro Station
East Entrance
39,852 48,891 38,321 0 0 0 0 0 0 0 127,064
13. East Falls Church Metro
Station Second Entrance
0 0 0 0 0 0 0 0 400 400 800
14. Microtransit
Implementation Plan
70 500 0 0 0 0 0 0 0 0 570
15. Mobility Hub Pilot 565 0 0 0 0 0 0 0 0 0 565
16. Pentagon City Metro
Station Second Elevator
3,893 0 0 0 0 0 0 0 0 0 3,893
17. Premium Transit Network
(PrTN): ART Fleet Expansion
4,463 0 0 0 5,616 0 3,404 0 0 0 13,483
18. Premium Transit Network
(PrTN): Columbia Pike Transit
Stations
4,258 3,558 109 0 0 0 0 0 0 0 7,925
19. Premium Transit Network
(PrTN): Transit ITS and
Security Program
1,046 458 446 459 293 185 191 197 203 209 3,687
E - 51
20. Premium Network Transit
(PrTN): Transitway Extension
Potomac Ave - Alexandria
20 37 3,142 3,066 1,491 0 0 0 0 0 7,756
21. Premium Network Transit
(PrTN): Transitway Extension
to Pentagon City
7,431 12,106 4,271 0 0 0 0 0 0 0 23,808
22. Shirlington Bus Station
Expansion
310 0 0 0 600 5,850 5,150 0 0 0 11,910
23. Transit Strategic Plan
Updates
0 0 0 0 585 0 0 0 0 0 585
Total Recommendation 112,631 93,601 165,133 63,950 100,579 37,549 57,442 5,705 7,621 48,127 692,338
CATEGORY FUNDING SOURCES (in $1,000s)
FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 10 Year
Total
New Funding
Federal Funding 0 2,328 30,308 2,346 24,458 15,919 19,866 3,011 4,176 13,996 116,408
State Funding 13,912 9,871 39,474 2,504 11,074 4,087 12,129 1,320 1,560 14,261 110,192
Developer Contributions 0 0 0 6,865 0 0 0 0 0 0 6,865
New Bond Issue 0 0 0 0 0 0 0 0 0 0 0
PAYG 0 0 0 0 0 0 0 0 0 0 0
Short Term Finance 0 0 0 0 0 0 0 0 0 0 0
Stormwater Utility Fee Revenue 0 0 0 0 0 0 0 0 0 0 0
Other Funding 150 0 0 0 34 35 0 0 0 0 219
TCF - Commercial & Industrial
Tax (C&I) 19,567 25,596 10,986 14,359 39,650 639 297 310 320 1,185 112,909
TCF - NVTA Local 580 1,088 3,993 324 5,094 281 5,804 573 1,058 9,132 27,927
Regional Funding 2,200 0 0 12,000 18,451 15,850 18,844 0 0 9,553 76,898
TCF Bonds 0 0 0 0 0 0 0 0 0 0 0
Tax Increment Financing (TIF) 19,362 13,598 145 0 0 738 502 492 506 0 35,343
TIF Bonds 0 0 0 0 0 0 0 0 0 0 0
TCF for Operating Costs 0 0 0 0 0 0 0 0 0 0 0
Subtotal New Funding 55,771 52,481 84,906 38,398 98,761 37,549 57,442 5,706 7,620 48,127 486,761
Previously Approved Funding
Authorized but Unissued
Bonds 0 0 0 0 0 0 0 0 0 0 0
Issued but Unspent Bonds 407 0 0 0 0 0 0 0 0 0 407
TCF - Commercial & Industrial
Tax (C&I) 4,789 3,236 0 0 0 0 0 0 0 0 8,025
TCF - NVTA Local 5,081 3,543 778 147 327 0 0 0 0 0 9,876
Regional Funding 6,500 18,169 70,099 17,828 0 0 0 0 0 0 112,596
Tax Increment Financing (TIF) 421 91 0 0 0 0 0 0 0 0 512
Other Previously Approved
Funds 39,662 16,081 9,350 7,577 1,491 0 0 0 0 0 74,161
Subtotal Previously Approved
Funding 56,860 41,120 80,227 25,552 1,818 0 0 0 0 0 205,577
Total Funding Sources 112,631 93,601 165,133 63,950 100,579 37,549 57,442 5,706 7,620 48,127 692,338
E - 52
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
1. ARMY NAVY DRIVE TRANSIT CENTER
Project Highlights:
• Construction of a new multi -modal, multi -jurisdictional
facility near the Pentagon by WMATA; County's role is
limited to staff support during design and construction.
• Establishes a central bus route connection and transfer hub in
the busy Pentagon and Pentagon City travel markets.
• Facilitates safe movement of people transferring between
different services.
• Expected to be fully funded and constructed by WMATA.
Associated Plan(s):
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
Pentagon City
Funding Notes: WMATA will provide funding for this project.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Other Funding 150 34 35 219
Previous Funding
Total Funding 150 0 0 0 34 35 0 0 0 0 219
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Construction begins Fall 2028
• Construction ends Spring 2030
Changes from Prior CIP:
Construction start date moved from FY 2027 to FY 2029.
E - 53
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
2. ART FARE COLLECTION SYSTEM
Project Highlights:
• ART buses are equipped with electronic fareboxes that
connect to the regional SmarTrip fare collection system,
making transfers more seamless.
• Current fareboxes are nearing the end of their useful lives and
need to be replaced with the next generation farebox being
implemented by WMATA.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
VARIOUS
Funding Notes: New funding is anticipated to include a combination of state and local funds.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 545 545
TCF - NVTA Local 95 95
Previous Funding
TCF - NVTA Local 244 162 406
Total Funding 244 802 0 0 0 0 0 0 0 0 1,046
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Upgrade light maintenance facility to be
compatible with existing and new generation
fareboxes.
Spring 2026
Changes from Prior CIP:
The project's name was changed from ART Bus Farebox Upgrade
to ART Fare Collection System to align with the scope of the
project.
E - 54
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
3. ART FLEET & EQUIPMENT REPLACEMENT
Project Highlights:
• This program funds the replacement of buses that have
reached the end of their useful life based on public transit
standards, which is 12 years.
• The program helps to maintain and improve the reliability,
accessibility, and sustainability of ART service.
• ART currently has a fleet of 78 Compressed Natural Gas
(CNG) buses, and many will need to be replaced over the ten-
year CIP period as they reach the end of their useful life.
• Discussions with DRPT and other funding partners on zero-
emission buses and related technology are ongoing.
• The costs in FY 2026 reflect the purchase of eight Zero
Emission Buses (ZEBs), specifically Battery Electric Buses
(BEBs).
• Future bus purchases are also expected to be BEBs; however,
this CIP program reflects the replacement cost of buses at the
CNG cost beyond FY 2026. The incremental costs associated
with BEB technology are captured in the ART Fleet
Transition to ZEB CIP program.
Associated Plan(s):
Community Energy Plan
Master Transportation Plan
Transit Strategic Plan
ART Zero-Emissions Bus Study
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds consist of state grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 6,835 4,114 7,092 8,103 12,648 38,792
TCF - NVTA Local 1,301 3,337 3,813 5,953 14,404
Previous Funding
TCF - NVTA Local 3,404 3,216 635 7,255
Other Previously
Approved Funds 7,233 7,233
Total Funding 10,637 10,051 6,050 0 10,429 0 11,916 0 0 18,601 67,684
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Fifteen 35-foot replacement buses Summer 2024
• Eight 40-foot replacement buses Spring 2026
• Eight 40-foot replacement buses Spring 2027
• Thirteen 40-foot replacement buses Spring 2029
• Fourteen 40-foot replacement buses Spring 2031
• Twenty 40-foot replacement buses Spring 2034
Changes from Prior CIP:
Vehicle cost in the previous CIP reflected Battery Electric Buses
(BEBs) in all fiscal years.
E - 55
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
4. ART FLEET TRANSITION TO ZEB
Project Highlights:
• This program contains funding to transition the ART fleet
to 100 percent Zero Emission Buses (ZEBs).
• Program captures the incremental cost of purchasing
Battery Electric Buses (BEBs) for planned vehicle
purchases reflected in the ART Fleet Replacement and
ART Fleet Expansion CIP programs – this includes the
estimated cost differential as well as the need to purchase
additional buses owing to range limitations of BEBs (1.3
BEBs are assumed for every 1.0 CNG bus).
• Program provides infrastructure on -route, at ART’s
Operations and Maintenance Facility (AOMF), and at
ART’s Light Maintenance Facility (LMF). Infrastructure
will include fast chargers, overhead pantograph chargers,
charging cabinets, generators, switchgear , power blocks,
utility upgrades, and other necessary items needed for
charging.
• This program will also provide for additional land and BEB
infrastructure to meet ART’s future bus parking needs as
identified in the Transit Strategic Plan.
• Cost estimates provided are placeholder numbers as the
market for BEB infrastructure is rapidly changing.
Associated Plan(s):
ART Zero-Emissions Bus Study
Community Energy Plan
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
VARIOUS
C
ritical Milestones:
• Construct additional BEB
infrastructure at AOMF
Fall 2027 – Fall 2029
• Purchase Land Spring 2027
• Construct BEB infrastructure at LMF Fall 2031 - Fall 2034
C
hanges from Prior CIP:
Elements of this program were included in AOMF Phase II in the
previous CIP; the program has been expanded to include all funding
needs to help ART transition to 100 percent ZEBs.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Federal Funding 14,646 4,379 8,787 3,011 4,176 13,996 48,995
State Funding 540 577 25,154 601 26,872
TCF - Commercial &
Industrial Tax (C&I) 104 10,310 415 2,178 357 853 14,217
TCF - NVTA Local 360 249 2,456 87 1,483 1,695 262 538 2,646 9,776
Regional Funding 12,235 10,290 9,553 32,078
Tax Increment Financing
(TIF) 738 502 492 506 2,238
Previous Funding
Total Funding 900 930 37,920 1,103 30,542 5,474 21,274 3,765 5,220 27,048 134,176
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
E - 56
FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 FY34 CIP total
Replacement (55 buses)
Uses:
Replacement Buses 0 0 4,303 0 7,419 0 8,476 0 0 13,231 33,428
Land and Infrastructure 250 260 2,516 920 7, 403 4,562 494 3,354 4,798 1,616 26,173
Total Uses 250 260 6,819 920 14,822 4,562 8,970 3,354 4,798 14,847 59,601
Sources:
Local Funds 125 115 2,595 419 2,964 912 1,794 671 960 2,969 13,524
External Funds 125 145 4,224 501 11,857 3,649 7,176 2,683 3,839 11,878 46,077
Total 250 260 6,819 920 14,822 4, 562 8,970 3,354 4,798 14,847 59,601
Expansion (11 buses)
Uses:
Replacement B u s e s 0000 3 , 9 9 50 2 , 4 2 2000 6 , 4 1 6
Land and Infrastructure 263 271 9,990 184 1,481 912 99 410 422 323 14,355
Total Uses 263 271 9,990 184 5,475 912 2,520 410 422 323 20,771
Sources:
Local Funds 100 100 3,279 84 296 182 20 82 84 65 4,292
External Funds 163 172 6,710 100 5,179 730 2,501 328 338 259 16,480
Total 263 271 9,990 184 5, 475 912 2,520 410 422 323 20,771
Contingency for 1.3:1 ratio (20 buses)
Uses:
Replacement Buses 0 0 3,107 0 8,241 0 7,868 0 0 9,553 28,769
Land and Infrastructure 387 399 18,004 0 2,005 0 1,914 0 0 2,324 25,034
Total Uses 387 399 21,111 0 10,246 0 9,783 0 0 11,878 53,803
Sources:
Local Funds 135 139 6,891 0 401 0 383 0 0 465 8,415
External Funds 252 259 14,220 0 9,845 0 9,400 0 0 11,413 45,388
Total 387 399 21,111 0 10, 246 0 9,783 0 0 11,878 53,803
Total ‐ ART Fleet Transition to ZE
B
Uses:
Replacement Buses 0 0 7,410 0 19,654 0 18,766 0 0 22,784 68,614
Land and Infrastructure 900 930 30,510 1,104 10, 889 5,474 2,507 3,763 5,220 4,264 65,562
Total Uses 900 930 37,920 1,104 30,543 5,474 21,273 3,763 5,220 27,048 134,176
Sources:
Local Funds 360 354 12,766 503 3,662 1, 095 2,197 753 1,044 3,499 26,231
External Funds 540 577 25,154 601 26,881 4,379 19,076 3,011 4, 176 23,549 107,945
Total 900 930 37,920 1,104 30,543 5,474 21,273 3,763 5,220 27,048 134,176
Notes:
> Cost of land, build‐out plus charging infrastructure, and mid‐life battery replacement have been distributed across the 3 categories based on vehicle count and additional factors
> Local funds include TCF‐C&I, TCF‐NV
TA Local, and TIF. External Funds include Regional funding as well as State and Federal grants
> Additional BEB costs captured in other CIP programs are not included here. These sum to $8.6m, bringing the total for the BEB transition to $143m. They include:
> $4.5m for the 4 pilot BEBs (included in th e ART Fleet Expansion CIP program)
> $4.1m for the incremental cost of BEB vs. RNG for 8 replacement buses for FY26 (included in the ART Fleet Replacement CIP program)
ART Fleet Transition to ZEB Detail ($000)
E - 57
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
5. ART OPERATIONS AND MAINTENANCE FACILITY
Project Highlights:
• This project addresses the need for an administrative,
operations, and maintenance facility for Arlington Transit.
• This facility replaces two leased facilities (Administration
building on South Eads Street and a converted warehouse
facility used for maintenance 9 miles south in Alexandria,
VA).
• Cost includes charging infrastructure for 12 Battery Electric
Buses (BEBs), one fast charger, and solar panels on the roof
of the O&M facility and parking garage.
• Further expansion of BEB charging infrastructure is captured
in the ART Fleet Transition to ZEB CIP program.
Associated Plan(s):
Community Energy Plan
Transit Strategic Plan
ART Zero-Emissions Bus Study
Neighborhood(s):
Green Valley
VARIOUS
Funding Notes: Operations costs for the facility includes a building engineer, building maintenance, utilities, security, cleaning, etc.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 12,318 12,318
TCF - Commercial &
Industrial Tax (C&I) 13,716 13,716
Previous Funding
TCF - Commercial &
Industrial Tax (C&I) 1,346 1,346
TCF - NVTA Local 24 24
Total Funding 27,404 0 0 0 0 0 0 0 0 0 27,404
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Personnel ($) 105 140 144 148 152 157 162 167 172 177 1,524
Non-Personnel ($) 553 332 342 352 363 374 385 397 409 421 3,928
Total Impact 658 472 486 500 515 531 547 564 581 598 5,452
Critical Milestones:
• Substantial completion Fall 2024
• Construction completion with BEB
infrastructure
Fall 2025
Changes from Prior CIP:
No change from the previous CIP.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/County-Facilities/ART-Operations-Maintenance-
Facility
E - 58
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
6. BALLSTON-MU METRORAIL STATION WEST ENTRANCE
Project Highlights:
• Project will add a new west entrance to the Ballston -MU
Metrorail Station to be located at the intersection of North
Fairfax Drive and North Vermont Street.
• New entrance will include elevators in compliance with the
American with Disabilities Act (ADA) and stairs.
• New entrance will improve access from the Glebe Road area
and the growing development in the western part of Ballston.
• The County published the Request for Qualifications (RFQ)
for a design- build delivery of the project in mid -May.
Following qualification of firms, the County will issue a
Request for Proposals (RFP) and anticipates reviewing
responsive proposals in early 2025.
Associated Plan(s):
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
Ballston-Virginia Square
Funding Notes: Regional funding includes $92,000,000 in NVTA and $4,500,000 in approved I -66 Commuter Choice funding and
$12,000,000 in a future request to the I-66 Commuter Choice Program. Developer contributions are associated with the Spire Fairmont
site plan (#331). Other Previously Approved Funds consist of $9,271,000 in state grants and $4,511,000 in developer contributions from
the Marymount University site plan (#64). The asset will be owned and operated by WMATA once completed.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Developer Contributions 6,865 6,865
TCF - Commercial &
Industrial Tax (C&I)
13,709 37,201 50,910
Regional Funding 12,000 12,000
Previous Funding
Regional Funding 570 8,569 66,489 17,828 93,456
Other Previously
Approved Funds 380 5,713 3,178 4,511 13,782
Total Funding 950 14,282 69,667 54,913 37,201 0 0 0 0 0 177,013
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Update previously developed
35% design documents
Summer 2024
• Design-Build services
procurement
Spring 2024 - Spring 2025
• Design Build phase Summer 2025 - Spring 2029
• Acceptance testing Spring 2029
• Project closeout Summer 2029
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Transportation-Projects/Ballston-MU-Metro-Station-
West-Entrance
Changes from Prior CIP:
The project cost has been conservatively increased from $150M to
$181M due to inflation and updated cost estimates for
design/construction services based on an independent cost
estimate and the County's experience on the Crystal City Metrorail
Station East Entrance, a comparable project.
E - 59
TRANSPORTATION
Capital Improvement Plan
Arlington Transit Program FY 2025-2034
7. BUS BAY EXPANSION-EAST FALLS CHURCH METRO STATION
Project Highlights:
• This project will expand bus bay capacity at the East Falls
Church metro station by adding three new bus bays.
• This project will result in the replacement of the existing
shelters in the off -street bus loop, improve bus operations,
bus circulation, and pedestrian accessibility and safety.
Associated Plan(s):
East Falls Church Area Plan
Transit Strategic Plan
Neighborhood(s):
Arlington-East Falls Church
Funding Notes: Other Previously Approved Funds consist of $764,000 in state grants and $1,200,000 from WMATA. Regional
Funding is I-66 Outside-the-Beltway Concessionaire funds. All new operating and maintenance costs that result from this project will
be funded by Metro. The asset will be owned and operated by WMATA once completed.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Regional Funding 2,200 2,200
Previous Funding
TCF - Commercial &
Industrial Tax (C&I) 301 394 695
TCF - NVTA Local 1,245 1,245
Regional Funding 2,480 2,480
Other Previously
Approved Funds 1,964 1,964
Total Funding 8,190 394 0 0 0 0 0 0 0 0 8,584
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Start construction Fall 2024
• Complete construction Spring 2026
Changes from Prior CIP:
The project cost increased by $3.6M from the FY 2023 Adopted
CIP driven primarily by changes in the required bus shelter design
and increased costs for Maintenance of Traffic (MOT),
construction management and inspection services, earthwork and
landscaping work, and project contingency.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Transportation-Projects/Bus-Bay-Expansion-at-East-
Falls-Church-Metro-Station
E - 60
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
8. BUS STOP ACCESSIBILITY IMPROVEMENTS
Project Highlights:
• On-going program to update the County's bus stops to
improve accessibility.
• Approximately 297 bus stops have been made ADA
compliant since the program launched in FY 2014.
• Of the 990 bus stops in the county, about 60 percent are not
ADA-compliant but only 10 percent are not accessible.
• Non-ADA-compliant bus stops may be possible to access
with varying levels of difficulty, but do not comply with
current federal guidance; non -accessible bus stops are not
possible to access for those with different mobility abilities.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
VARIOUS
Funding Notes: Funding plan assumes 68 percent state capital reimbursement grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 630 600 626 649 670 694 718 748 771 804 6,910
TCF - Commercial &
Industrial Tax (C&I) 148 142 148 152 157 163 169 175 181 189 1,624
TCF - NVTA Local 148 141 147 153 158 163 169 176 181 189 1,625
Previous Funding
Total Funding 926 883 921 954 985 1,020 1,056 1,099 1,133 1,182 10,159
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Each fiscal year includes funding for the
design of 20 to 25 bus stop improvements.
Changes from Prior CIP:
No significant change from the previous CIP.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Uncategorised/Bus-Stop-Accessibility-Improvements
E - 61
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
9. BUS STOP AND SHELTER PROGRAM
Project Highlights:
• As of April 2024, Arlington County had 990 bus stops, 308
of which include bus shelters. Some locations have multiple
shelters, resulting in a total of 330 shelters.
• Bus shelters have a useful life of 15 years, on average, but
periodic repairs help extend life.
• This program replaces existing bus shelters that are aging,
installs new shelters where needed, and makes repairs and
improvements.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds consist of $122,000 in state grants and $57,000 in PAYG. Funding plan assumes
68 percent state capital reimbursement grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 304 439 378 355 367 382 409 438 451 467 3,990
TCF - Commercial &
Industrial Tax (C&I) 72 103 89 83 85 89 97 104 107 110 939
TCF - NVTA Local 72 103 89 84 86 89 97 103 106 110 939
Previous Funding
Other Previously
Approved Funds 179 179
Total Funding 627 645 556 522 538 560 603 645 664 687 6,047
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Non-Personnel ($) 125 129 133 137 141 145 149 153 157 161 1,430
Total Impact 125 129 133 137 141 145 149 153 157 161 1,430
Critical Milestones:
• Annual program goals: Replace 5-10
shelters and install up to 3 new shelters.
Changes from Prior CIP:
No significant change from the previous CIP.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Uncategorised/Bus-Stop-and-Shelter-Program
E - 62
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
10. COURT HOUSE METRORAIL STATION NEW ELEVATORS
Project Highlights:
• The Court House Metrorail Station has only one street
elevator to the mezzanine that is small, slow, and heavily
used.
• This project will provide for design, engineering, and
construction of two street level elevators (that will replace the
current elevator and add an additional one).
• Elevators will increase access to the station mezzanine and
accommodate emergency services as well as those traveling
with luggage, bicycles, strollers, or by wheelchair.
Associated Plan(s):
Court House Sector Plan
Transit Strategic Plan
Neighborhood(s):
Courthouse
Funding Notes: New funding plan consists of FTA and DRPT grants, and I66 Commuter Choice funding. Other Previously Approved
Funds are developer contributions from the 2311 Wilson Boulevard site plan (#263) and the 2401 Wilson Boulevard site plan (#404).
The asset will be owned and operated by WMATA once completed.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Federal Funding 825 2,346 9,812 11,540 11,079 35,602
State Funding 206 587 2,453 2,885 2,769 8,900
Regional Funding 10,000 10,000
Previous Funding
Other Previously
Approved Funds 206 64 2,699 2,969
Total Funding 206 64 3,730 2,933 12,265 24,425 13,848 0 0 0 57,471
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Complete preliminary engineering Spring 2027
• Complete final design Summer 2029
• Start early construction activities Summer 2028
• Complete construction Spring 2031
Changes from Prior CIP:
The project cost has almost doubled based on a new cost
estimate from the on-call estimation contractor.
E - 63
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
11. CRYSTAL CITY - POTOMAC YARD TRANSITWAY UPKEEP
Project Highlights:
• This project will investigate the cause of glass breakage on
the Transitway shelters and implement fixes.
• This project will also undertake various other tasks relating
to the transitway including replacing real time info
signs/flags at all stations, implementing treatments to prevent
bird nesting, investigating options to prevent cars from
entering transit lan es, and repairing/replacing loose brick
pavers.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
Crystal City
Funding Notes: Other Previously Approved Funds consist of state grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Previous Funding
Tax Increment Financing
(TIF) 421 421
Other Previously
Approved Funds 68 68
Total Funding 489 0 0 0 0 0 0 0 0 0 489
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Start design, construction, and equipment
replacement
Summer 2024
• Complete design, construction, and
equipment replacement
Winter 2025
Changes from Prior CIP:
Cost decreased from the previous CIP following a study that
scoped out the project.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Uncategorised/Crystal-City-Potomac-Yard-
Transitway
E - 64
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
12. CRYSTAL CITY METRO STATION EAST ENTRANCE
Project Highlights:
• This project will provide a new entrance at the east end of the
metro station to provide easier access from Crystal Drive,
VRE Station, and Crystal Drive at 18th Street South.
• New entrance will include elevators in compliance with the
Americans with Disabilities Act and stairs.
• This project will expand the walkshed for the station and
connect high density commercial and residential
development along Crystal Drive.
• A Guaranteed Maximum Price proposal and Comprehensive
Agreement for Final Design and Construction was approved
by Arlington County Board in July 2023.
Associated Plan(s):
Crystal City Sector Plan
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
Crystal City
Funding Notes: Project funding includes $82.5 million allocated by the Commonwealth to meet its commitment to Amazon. That
funding is a mix of federal and state funding. Other Previously Approved Funds consist of $10,804,000 in a federal grant and
$18,233,000 in state grant. The asset will be owned and operated by WMATA once completed.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Federal Funding 2,328 29,483 31,811
State Funding 582 8,693 9,275
TCF - Commercial &
Industrial Tax (C&I)
23,836 23,836
Tax Increment Financing
(TIF) 19,362 13,598 145 33,105
Previous Funding
Other Previously
Approved Funds 20,490 8,547 29,037
Total Funding 39,852 48,891 38,321 0 0 0 0 0 0 0 127,064
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Final design Summer 2024 - Winter 2025
• Construction Fall 2024 - Spring 2027
• Project closeout Spring 2027
Changes from Prior CIP:
Project cost increased by about 50 percent compared to the
previous CIP as the prior CIP estimate was based only on
conceptual planning work.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Transportation-Projects/Crystal-City-Metro-Station-
Second-Entrance
E - 65
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
13. EAST FALLS CHURCH METRO STATION SECOND ENTRANCE
Project Highlights:
• This project will undertake the planning, design, and
construction of a full second entrance to the East Falls Church
Metrorail Station.
• The project will improve pedestrian access to the station from
points west.
• It will be coordinated with the City of Falls Church.
Associated Plan(s):
East Falls Church Area Plan
Transit Strategic Plan
Neighborhood(s):
Arlington-East Falls Church
Funding Notes: The County anticipates submitting requests to external funding sources for design and construction, which will be
reflected in the next CIP update. The asset will be owned and operated by WMATA once completed.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 200 200 400
TCF - NVTA Local 200 200 400
Previous Funding
Total Funding 0 0 0 0 0 0 0 0 400 400 800
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Planning Fall 2033 - Fall 2034
Changes from Prior CIP:
Project start has been delayed two years.
E - 66
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
14. MICROTRANSIT IMPLEMENTATION PLAN
Project Highlights:
• This project will study microtransit and implement a pilot.
• Microtransit is a form of demand -responsive service that
operates on a smaller scale than traditional public transit.
• The pilot will be implemented in fall 2025 in zones defined
by the planning process; the goal will be to determine if
microtransit provides options for shared transport in areas
where low performance ART routes are eliminated.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 35 35
TCF - NVTA Local 500 500
Previous Funding
TCF - NVTA Local 35 35
Total Funding 70 500 0 0 0 0 0 0 0 0 570
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Study complete Spring 2025
• Pilot start Fall 2025
Changes from Prior CIP:
The project is new to the FY 2025 - FY 2034 CIP.
E - 67
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
15. MOBILITY HUB PILOT
Project Highlights:
• This project is for the design and implementation of a
Mobility Hub Pilot in the Court House Plaza area.
• The pilot brings together various elements at one location
including but not limited to: bus stops, shared mobility device
corrals, bike parking, ADA compliant pedestrian facilities,
wayfinding/information hubs, and parklets.
• The goal is to provide greater access to multimodal
transportation and improve public infrastructure.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
Courthouse
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Previous Funding
TCF - Commercial &
Industrial Tax (C&I) 565 565
Total Funding 565 0 0 0 0 0 0 0 0 0 565
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design of the Mobility-Hub
pilot
Spring 2024 - Fall 2024
• Implementation of Mobility
Hub pilot
Spring 2025
Changes from Prior CIP:
Project completion has been delayed a year to FY 2025.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Plans-
Studies/Transportation-Plans-Studies/Mobility-Hub-
Guidebook
E - 68
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
16. PENTAGON CITY METRO STATION SECOND ELEVATOR
Project Highlights:
• Construction of a second street to mezzanine elevator to
provide access to the Pentagon City Metro Station from the
west side of South Hayes Street.
• Improves general access and compliance with the Americans
with Disabilities Act (ADA).
• Provides back-up ADA access when the other elevator is out
of service for repairs or maintenance.
Associated Plan(s):
Master Transportation Plan
Pentagon City Sector Plan
Transit Strategic Plan
Neighborhood(s):
Pentagon City
Funding Notes: The asset will be owned and operated by WMATA once completed.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
TCF - Commercial &
Industrial Tax (C&I) 3,893 3,893
Previous Funding
Total Funding 3,893 0 0 0 0 0 0 0 0 0 3,893
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Complete construction and open Summer 2024
• Project closeout Fall 2024
Changes from Prior CIP:
Total project cost increased from $10.5M in the previous CIP to
$17.3M due to a variety of factors including unforeseen site
conditions, supply chain issues, and production delays. Milestone
dates and costs reflect the current project schedule.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Transportation-Projects/Pentagon-City-Metro-
Station-Second-Elevator
E - 69
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
17. PREMIUM TRANSIT NETWORK (PRTN): ART FLEET
EXPANSION
Project Highlights:
• This program funds the purchase of additional buses to
support the 10-year service plan for ART.
• The costs in FY 2025 reflect the purchase of four Battery
Electric Buses (BEBs) for a BEB pilot.
• Future bus purchases are also expected to be BEBs; however,
CNG costs are used in this CIP program as the incremental
costs associated with ZEB technology are captured in the
ART Fleet Transition to ZEB CIP program.
Associated Plan(s):
Community Energy Plan
Transit Strategic Plan
ART Zero-Emissions Bus Study
Neighborhood(s):
VARIOUS
Funding Notes: Other Previously Approved Funds consist of state grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
TCF - Commercial &
Industrial Tax (C&I) 1,428 1,428
Regional Funding 5,616 3,404 9,020
Previous Funding
Other Previously
Approved Funds 3,035 3,035
Total Funding 4,463 0 0 0 5,616 0 3,404 0 0 0 13,483
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Four Battery Electric Buses Spring 2025
• Procure 7 buses and related on-bus
equipment
Spring 2029
• Procure 4 buses and related on-bus
equipment
Spring 2031
Changes from Prior CIP:
The addition of four BEBs for a pilot. Also, the vehicle cost for
future year purchases in the previous CIP reflected BEBs.
E - 70
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
18. PREMIUM TRANSIT NETWORK (PRTN): COLUMBIA PIKE
TRANSIT STATIONS
Project Highlights:
• Design and construction of 23 Transit Stations at 12 locations
along Columbia Pike.
• The first eight shelters are operational; construction of the
remaining stations will follow the Columbia Pike Multimodal
project.
• Transit Stations include shelters with seating, real -time
information and near level boarding.
Associated Plan(s):
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
Alcova Heights
Arlington Heights
Arlington View
Barcroft
Columbia Forest
Columbia Heights
Columbia Heights West
Douglas Park
Penrose
Funding Notes: Other Previously Approved Funds consist of $1,322,000 in federal grants and $212,000 in state grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
TCF - Commercial &
Industrial Tax (C&I)
1,041 109 1,150
Previous Funding
Issued but Unspent Bonds 407 407
TCF - Commercial &
Industrial Tax (C&I) 2,317 2,517 4,834
Other Previously
Approved Funds 1,534 1,534
Total Funding 4,258 3,558 109 0 0 0 0 0 0 0 7,925
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Non-Personnel ($) 58 82 110 138 150 155 159 164 169 170 1,355
Total Impact 58 82 110 138 150 155 159 164 169 170 1,355
Critical Milestones:
• Phase 3 construction completion - Orme
E&W
Spring 2025
• Phase 4 construction completion - Thomas
E, Taylor W, George Mason E&W,
Oakland E
Spring 2026
• Phase 5 construction completion - Walter
Reed W, Barton E& W, Courthouse E&W,
Scott E&W, Glebe E
Spring 2026
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Transportation-Projects/Columbia-Pike-Transit-
Stations
Changes from Prior CIP:
The project phasing plan has been adjusted to better coordinate
with the Columbia Pike Multimodal Street reconstruction project.
TRANSPORTATION
Capital Improvement Plan
E - 71
Arlington Transit Program FY 2025-2034
19. PREMIUM TRANSIT NETWORK (PRTN): TRANSIT ITS AND
SECURITY PROGRAM
Project Highlights:
• This program funds technology to improve transit operations
and rider information systems. Disparate systems and data
sources will be consolidated. Additional initiatives under this
program are listed below.
• Transit Signal Priority (TSP) implementation for better
running times of buses in congested corridors, particularly on
Columbia Pike and Langston Boulevard.
• Text-based system for real time bus arrival information on
mobile phones.
• Preplanning for end -of-life replacements of current
technology to maintain a state of good repair as required by
FTA.
• Video recorded on buses allowing for enhanced safety of
customers and bus operators.
Associated Plan(s):
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
VARIOUS
Critical Milestones:
• Deployment of TSP on Langston Boulevard
corridor
Summer 2024
• Deployment of TSP on Columbia Pike
corridor
Summer 2025
• Issue RFP for business intelligence
automation
Summer 2025
• Issue RFP for text-based arrival system Winter 2025
• Deployment of TSP on Glebe Road corridor Spring 2026
• Deployment of TSP on Crystal
City/Pentagon City corridor
Spring 2027
Funding Notes: Other Previously Approved Funds consist of state grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 85 293 303 312 199 126 130 134 138 142 1,862
TCF - Commercial &
Industrial Tax (C&I)
29 30 31 31 32 33 186
TCF - NVTA Local 30 29 30 32 33 34 188
Previous Funding
TCF - Commercial &
Industrial Tax (C&I) 236 236
TCF - NVTA Local 129 165 143 147 35 619
Other Previously
Approved Funds 596 596
Total Funding 1,046 458 446 459 293 185 191 197 203 209 3,687
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Personnel ($) 2 2 2 2 2 2 2 2 2 2 20
Non-Personnel ($) 147 254 266 269 271 386 388 389 392 392 3,154
Total Impact 149 256 268 271 273 388 390 391 394 394 3,174
Changes from Prior CIP:
This program is ongoing from the previous CIP and includes
updated schedule and cost estimates.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Uncategorised/Transit-ITS-and-Security-Program
E - 72
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
20. PREMIUM NETWORK TRANSIT (PRTN): TRANSITWAY
EXTENSION POTOMAC AVE - ALEXANDRIA
Project Highlights:
• This project will construct the third segment (Segment C) of
the transitway serving the Crystal City / Potomac Yard
corridor connecting to the City of Alexandria.
• Construction includes a dedicated transit -only southbound
lane as well as bike and pedestrian improvements along
Potomac Avenue.
Associated Plan(s):
Crystal City Sector Plan
Master Transportation Plan
Potomac Yards Design Guidelines
Transit Strategic Plan
Neighborhood(s):
Potomac Yard
Funding Notes: Other Previously Approved Funds consist of state grants.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Previous Funding
Other Previously
Approved Funds 20 37 3,142 3,066 1,491 7,756
Total Funding 20 37 3,142 3,066 1,491 0 0 0 0 0 7,756
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
Critical Milestones:
• Design Spring 2025 - Spring 2027
• Start construction Summer 2028
Changes from Prior CIP:
Project timeline has been delayed three years.
E - 73
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
21. PREMIUM NETWORK TRANSIT (PRTN): TRANSITWAY
EXTENSION TO PENTAGON CITY
Project Highlights:
• This project will extend the Crystal City Potomac Yard
Transitway from Crystal City to Pentagon City.
• It will provide dedicated transit lanes, five new transit
stations, traffic signal modifications, and sidewalk / curb
improvements.
• Construction started in FY 2022 and the project is expected
to be completed in segments by FY 2027.
Associated Plan(s):
Crystal City Sector Plan
Master Transportation Plan
Metropolitan Park Design Guidelines
Pentagon Centre Site Guiding Principles
Pentagon City Planning Task Force Report
Pentagon City Sector Plan
Transit Development Plan
Neighborhood(s):
Aurora Highlands
Crystal City
Pentagon City
Funding Notes: Other Previously Approved Funds consist of $5,675,000 in state grants and $333,000 in developer contributions
from the Pentagon Centre site plan (#297).
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
TCF - Commercial &
Industrial Tax (C&I)
370 330 700
Previous Funding
TCF - Commercial &
Industrial Tax (C&I) 24 325 349
Regional Funding 3,450 9,600 3,610 16,660
Tax Increment Financing
(TIF)
91 91
Other Previously
Approved Funds 3,957 1,720 331 6,008
Total Funding 7,431 12,106 4,271 0 0 0 0 0 0 0 23,808
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Non-Personnel ($) 70 85 100 105 110 115 120 125 130 960
Total Impact 0 70 85 100 105 110 115 120 125 130 960
Critical Milestones:
• Start construction Segment IIA Winter 2025
• Complete construction Segment IIA Spring 2026
Changes from Prior CIP:
Due to the hold in construction for Pen Place, the design for
segment IIA had to be revised at 100 percent design to incorporate
additional corridor improvements on the north curb of 12th Street
South. The anticipated impact on the project timeline due to this
delay is 18 months.
Project Links:
• https://www.arlingtonva.us/Government/Projects/Project-
Types/Uncategorised/Transitway-Extension-to-Pentagon-
City
E - 74
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
22. SHIRLINGTON BUS STATION EXPANSION
Project Highlights:
• Project focuses on adding bus bay(s) to the Shirlington
Station to meet growing demand.
Associated Plan(s):
Transit Strategic Plan
Neighborhood(s):
Shirlington
Funding Notes: Regional funding is NVTA. Minor operating costs anticipated for utilities, communications, snow removal, and
cleaning.
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
TCF - Commercial &
Industrial Tax (C&I) 310 310
Regional Funding 600 5,850 5,150 11,600
Previous Funding
Total Funding 310 0 0 0 600 5,850 5,150 0 0 0 11,910
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Non-Personnel ($) 6 6 6 6 24
Total Impact 0 0 0 0 0 0 6 6 6 6 24
Critical Milestones:
• Planning study to identify
opportunities to address project
needs
Winter 2024 - Fall 2024
• Engineering and final design Fall 2028 - Spring 2029
• Construction Fall 2029 - Spring 2031
Changes from Prior CIP:
Cost has more than doubled from previous CIP due to scope
changes. New application for design and construction submitted
to NVTA for $11.6 million.
E - 75
TRANSPORTATION Capital Improvement Plan
Arlington Transit Program FY 2025-2034
23. TRANSIT STRATEGIC PLAN UPDATES
Project Highlights:
• Major update of Arlington's Transit Strategic Plan (ATSP)
as required by the state every six years.
Associated Plan(s):
Master Transportation Plan
Transit Strategic Plan
Neighborhood(s):
VARIOUS
New Funding FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
State Funding 293 293
Previous Funding
TCF - NVTA Local 292 292
Total Funding 0 0 0 0 585 0 0 0 0 0 585
Operating Impact FY 2025 FY 2026 FY 2027 FY 2028 FY 2029 FY 2030 FY 2031 FY 2032 FY 2033 FY 2034 Total
Total Impact 0 0 0 0 0 0 0 0 0 0 0
C
ritical Milestones:
• Complete ATSP update (Comprehensive
Operational Analysis-COA)
Summer 2028
C
hanges from Prior CIP:
This is a carryover from previous CIP and includes the addition
of a comprehensive operational analysis of ART services.
E - 76